CN115450246A - Tower crane foundation and basement raft combined structure and construction method thereof - Google Patents
Tower crane foundation and basement raft combined structure and construction method thereof Download PDFInfo
- Publication number
- CN115450246A CN115450246A CN202211012902.8A CN202211012902A CN115450246A CN 115450246 A CN115450246 A CN 115450246A CN 202211012902 A CN202211012902 A CN 202211012902A CN 115450246 A CN115450246 A CN 115450246A
- Authority
- CN
- China
- Prior art keywords
- tower crane
- basement
- crane foundation
- raft
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明公开了一种塔吊基础与地下室筏板结合结构及其施工方法,结构包括地下室垫层及防水层、地下室筏板钢筋、塔吊基础钢筋、插筋、塔吊预埋螺栓;其中,地下室垫层及防水层上方设置整体浇筑的塔吊基础和地下室筏板混凝土,混凝土内部设置地下室筏板钢筋和塔吊基础钢筋,在地下室筏板的位置具有横向插筋;塔吊基础钢筋的中间均匀设置塔吊所需的预埋螺栓,塔吊预埋螺栓的上端置于混凝土的外部。该方案中塔吊基础和筏板结合的施工工序较为简单,节约模板及混凝土材料。有效解决了塔吊使用过程中塔吊基础积水问题,避免再次清理、浇筑塔吊基础处地下室筏板。
The invention discloses a combination structure of a tower crane foundation and a basement raft slab and a construction method thereof. The structure includes a basement cushion and a waterproof layer, a basement raft slab steel bar, a tower crane foundation steel bar, inserting bars, and tower crane pre-embedded bolts; wherein, the basement cushion The tower crane foundation and basement raft slab concrete poured as a whole are set above the waterproof layer, and the basement raft slab reinforcement and tower crane foundation reinforcement are arranged inside the concrete, and there are horizontal insertion bars at the position of the basement raft slab; the middle of the tower crane foundation reinforcement is uniformly arranged for the tower crane. Embedded bolts, the upper ends of the tower crane embedded bolts are placed outside the concrete. In this scheme, the construction process of combining tower crane foundation and raft slab is relatively simple, saving formwork and concrete materials. It effectively solves the problem of water accumulation in the foundation of the tower crane during the use of the tower crane, and avoids cleaning and pouring the basement raft at the foundation of the tower crane again.
Description
技术领域technical field
本发明属于混凝土结构施工领域,具体涉及一种塔吊基础与地下室筏板结合结构及其施工方法。The invention belongs to the field of concrete structure construction, and in particular relates to a combination structure of a tower crane foundation and a basement raft and a construction method thereof.
背景技术Background technique
塔吊作为施工现场常用的垂直运输工具,在塔吊基础施工过程中经常遇到塔吊基础和地下室基础筏板在同一位置。在塔吊使用过程中,塔吊基础经常积水,存在安全隐患;地下室筏板基础钢筋一直暴露在外,容易造成锈蚀,存在质量隐患;而且塔吊拆除后,地下室筏板需要重新清理、浇筑,造成施工不便。Tower crane is a commonly used vertical transportation tool on the construction site. During the construction of tower crane foundation, it is often encountered that the tower crane foundation and the basement foundation raft are in the same position. During the use of the tower crane, the foundation of the tower crane often accumulates water, which poses a safety hazard; the steel bars of the basement raft foundation are always exposed, which is easy to cause corrosion and poses a quality risk; and after the tower crane is dismantled, the basement raft needs to be cleaned and poured again, causing construction inconvenience .
现有技术的施工工序较为复杂,需设置基础模板,需砌筑砖胎膜或者安装模板,不能有效解决塔吊使用过程中易积水等问题。The construction process of the prior art is relatively complicated, and the foundation formwork needs to be set, and the brick membrane or the formwork needs to be installed, which cannot effectively solve the problems of easy water accumulation during the use of the tower crane.
发明内容Contents of the invention
本发明所要解决的技术问题是:提供一种塔吊基础与地下室筏板结合结构及其施工方法,解决了现有技术中塔吊基础积水的问题。The technical problem to be solved by the present invention is to provide a combination structure of tower crane foundation and basement raft slab and its construction method, which solves the problem of tower crane foundation water accumulation in the prior art.
本发明为解决上述技术问题采用以下技术方案:The present invention adopts the following technical solutions for solving the problems of the technologies described above:
一种塔吊基础与地下室筏板结合结构,包括地下室垫层及防水层、地下室筏板钢筋、塔吊基础钢筋、插筋、塔吊预埋螺栓;其中,地下室垫层及防水层上方设置整体浇筑的塔吊基础和地下室筏板混凝土,混凝土内部设置地下室筏板钢筋和塔吊基础钢筋,在地下室筏板的位置具有横向插筋;塔吊基础钢筋的中间均匀设置塔吊所需的预埋螺栓,塔吊预埋螺栓的上端置于混凝土的外部。A combination structure of tower crane foundation and basement raft, including basement cushion and waterproof layer, basement raft reinforcement, tower crane foundation reinforcement, insertion bars, and tower crane pre-embedded bolts; wherein, an integrally poured tower crane is arranged above the basement cushion and waterproof layer Foundation and basement raft concrete, inside the concrete are set basement raft steel bars and tower crane foundation steel bars, and horizontal bars are inserted at the position of the basement raft slab; in the middle of the tower crane foundation steel bars, the pre-embedded bolts required by the tower crane are evenly arranged, and the pre-embedded bolts of the tower crane The upper end rests on the exterior of the concrete.
插筋的两端设置套筒,用于相邻单元结构的连接。Sleeves are provided at both ends of the ribs for the connection of adjacent unit structures.
在施工缝的位置设置止水钢板。Install waterproof steel plate at the position of construction joint.
当塔吊基础和筏板结合处有柱墩时,塔吊基础钢筋和柱墩钢筋为整体绑扎在一起。When there is a column pier at the junction of the tower crane foundation and the raft, the tower crane foundation reinforcement and the column pier reinforcement are bound together as a whole.
塔吊基础上层钢筋的位置位于地下室筏板上层钢筋的下侧。The location of the upper reinforcement of the tower crane foundation is located on the lower side of the upper reinforcement of the basement raft.
塔吊基础与地下室筏板结合施工方法,包括如下步骤:The combined construction method of the tower crane foundation and the basement raft includes the following steps:
步骤1、开挖至塔吊基础和地下室筏板设计标高;Step 1. Excavate to the design elevation of tower crane foundation and basement raft;
步骤2、根据地下室原设计图纸施工地下室垫层及防水层;Step 2. Construct the basement cushion and waterproof layer according to the original design drawings of the basement;
步骤3、绑扎地下室筏板钢筋及塔吊基础钢筋;
步骤4、安装止水钢板及塔吊基础预埋螺栓;
步骤5、浇筑塔吊基础和地下室筏板混凝土。
步骤1中塔吊基础设计顶标高与地下室筏板基础顶标高相同,开挖至设计标高,高低差位置时采用砌筑砖胎膜结构。In step 1, the designed top elevation of the tower crane foundation is the same as the top elevation of the basement raft foundation, and excavation is carried out to the design elevation, and the masonry brick membrane structure is used at the position of the height difference.
步骤3中绑扎钢筋的具体过程如下:The specific process of binding steel bars in
根据设计图纸分别绑扎地下室筏板钢筋及塔吊基础钢筋,绑扎时将塔吊基础上层钢筋放置在地下室筏板上层钢筋下侧;Bind the basement raft reinforcement and the tower crane foundation reinforcement respectively according to the design drawings, and place the upper reinforcement of the tower crane foundation on the lower side of the basement raft reinforcement when binding;
当塔吊基础与筏板结合处有柱墩时,至少将塔吊基础和柱墩范围内的钢筋绑扎完成;当塔吊基础与筏板结合处无柱墩时,至少将塔吊基础范围内的钢筋绑扎完成;When there is a column pier at the joint between the tower crane foundation and the raft slab, at least the steel bars within the scope of the tower crane foundation and the column pier should be bound; when there is no column pier at the joint between the tower crane foundation and the raft slab, at least the steel bars within the range of the tower crane foundation should be bound ;
预留出地下室筏板插筋,并且在插筋两端安装连接件。Reserve the raft ribs in the basement, and install connectors at both ends of the ribs.
所述连接件为套筒。The connecting piece is a sleeve.
步骤4的具体过程如下:The specific process of
在施工缝的位置安装一圈止水钢板,在塔吊基础的中间相应位置安装竖向的塔吊预埋螺栓。Install a ring of water-stop steel plates at the position of the construction joint, and install vertical tower crane embedded bolts at the corresponding position in the middle of the tower crane foundation.
与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
1、该方案中塔吊基础和筏板结合的施工工序较为简单,节约模板及混凝土材料。1. In this scheme, the construction process of combining tower crane foundation and raft slab is relatively simple, saving formwork and concrete materials.
2、与传统的施工方法相比,减少了混凝土及模板用量,并有效解决了塔吊使用过程中塔吊基础积水问题,避免再次清理、浇筑塔吊基础处地下室筏板。2. Compared with the traditional construction method, it reduces the amount of concrete and formwork, and effectively solves the problem of water accumulation in the foundation of the tower crane during the use of the tower crane, avoiding cleaning and pouring the basement raft at the foundation of the tower crane again.
3、避免现有施工方法施工缝长期不能封闭,钢筋、止水钢板的锈蚀问题,提高混凝土施工质量及塔吊使用过程中的安全性。3. Avoid the long-term failure of the existing construction method to close the construction joints, the corrosion of steel bars and water-stop steel plates, and improve the quality of concrete construction and the safety of tower cranes during use.
附图说明Description of drawings
图1为本发明筏板与塔吊基础结合处有柱墩结构示意图。Fig. 1 is a schematic diagram of the pier structure at the junction of the raft and the tower crane foundation of the present invention.
图2为本发明筏板与塔吊基础结合处无柱墩结构示意图。Fig. 2 is a schematic diagram of the column-free pier structure at the junction of the raft and the tower crane foundation of the present invention.
其中,图中的标识为:1-地下室垫层及防水层;2-地下室筏板钢筋;3-塔吊基础钢筋;4-插筋;5-套筒;6-止水钢板;7-塔吊预埋螺栓;8-筏板;9-塔吊基础;10-柱墩。Among them, the marks in the figure are: 1-basement cushion and waterproof layer; 2-basement raft reinforcement; 3-tower crane foundation reinforcement; 4-insertion bars; Buried bolts; 8-raft; 9-tower crane foundation; 10-column pier.
具体实施方式detailed description
为了使本技术领域的人员更好地理解本申请方案,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分的实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都应当属于本申请保护的范围。In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiment of the application will be clearly and completely described below in conjunction with the accompanying drawings in the embodiment of the application. Obviously, the described embodiment is only It is an embodiment of a part of the application, but not all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by persons of ordinary skill in the art without creative efforts shall fall within the scope of protection of this application.
一种塔吊基础与地下室筏板结合结构,包括地下室垫层及防水层、地下室筏板钢筋、塔吊基础钢筋、插筋、塔吊预埋螺栓;其中,地下室垫层及防水层上方设置整体浇筑的塔吊基础和地下室筏板混凝土,混凝土内部设置地下室筏板钢筋和塔吊基础钢筋,在地下室筏板的位置具有横向插筋;塔吊基础钢筋的中间均匀设置塔吊所需的预埋螺栓,塔吊预埋螺栓的上端置于混凝土的外部。A combination structure of tower crane foundation and basement raft, including basement cushion and waterproof layer, basement raft reinforcement, tower crane foundation reinforcement, insertion bars, and tower crane pre-embedded bolts; wherein, an integrally poured tower crane is arranged above the basement cushion and waterproof layer Foundation and basement raft concrete, inside the concrete are set basement raft steel bars and tower crane foundation steel bars, and horizontal bars are inserted at the position of the basement raft slab; in the middle of the tower crane foundation steel bars, the pre-embedded bolts required by the tower crane are evenly arranged, and the pre-embedded bolts of the tower crane The upper end rests on the exterior of the concrete.
具体实施例一,如图1、图2所示,Specific embodiment one, as shown in Fig. 1, Fig. 2,
一种塔吊基础与地下室筏板结合结构,包括地下室垫层及防水层1、地下室筏板钢筋2、塔吊基础钢筋3、插筋4、塔吊预埋螺栓7;其中,地下室垫层及防水层1的上方设置整体浇筑的塔吊基础9和地下室筏板8混凝土,混凝土内部设置地下室筏板钢筋2和塔吊基础钢筋3,在地下室筏板8的位置具有横向插筋4;塔吊基础钢筋3的中间均匀设置塔吊所需的预埋螺栓7,塔吊预埋螺栓7的上端置于混凝土的外部。A combination structure of a tower crane foundation and a basement raft, comprising a basement cushion and a waterproof layer 1, a basement raft steel bar 2, a tower crane
插筋的两端设置套筒5,用于相邻单元结构的连接。
在施工缝的位置设置止水钢板6。Set the
当塔吊基础9和筏板8结合处有柱墩10时,塔吊基础钢筋和柱墩钢筋为整体绑扎在一起。When there is a
塔吊基础上层钢筋的位置位于地下室筏板上层钢筋的下侧。The location of the upper reinforcement of the tower crane foundation is located on the lower side of the upper reinforcement of the basement raft.
该方案中塔吊基础与地下室筏板结合结构的施工方法,包括如下步骤:The construction method of the combined structure of tower crane foundation and basement raft slab in this scheme includes the following steps:
步骤1、开挖至塔吊基础和地下室筏板设计标高;Step 1. Excavate to the design elevation of tower crane foundation and basement raft;
步骤2、根据地下室原设计图纸施工地下室垫层及防水层;Step 2. Construct the basement cushion and waterproof layer according to the original design drawings of the basement;
步骤3、绑扎地下室筏板钢筋及塔吊基础钢筋;
步骤4、安装止水钢板及塔吊基础预埋螺栓;
步骤5、浇筑塔吊基础和地下室筏板混凝土。
具体实施例二,Specific embodiment two,
塔吊基础与地下室筏板结合结构的施工方法,包括如下步骤:The construction method of the combination structure of the tower crane foundation and the basement raft slab includes the following steps:
步骤1、开挖至塔吊基础和地下室筏板设计标高,高低差位置时采用砌筑砖胎膜结构或其他措施;所述塔吊基础顶标高与地下室筏板顶标高相同。Step 1. Excavate to the design elevation of the tower crane foundation and basement raft, and adopt masonry brick membrane structure or other measures at the height difference position; the elevation of the tower crane foundation top is the same as that of the basement raft top.
步骤2、根据地下室原设计图纸要求,施工地下室垫层及防水层。Step 2. According to the requirements of the original design drawings of the basement, construct the basement cushion and waterproof layer.
步骤3、绑扎地下室筏板钢筋及塔吊基础钢筋;分别独立绑扎地下室筏板钢筋及塔吊基础钢筋,绑扎时将塔吊基础上层钢筋网放置在地下室筏板上层钢筋下侧;根据需绑扎的地下室筏板范围,预留出插筋;具体过程如下:
3.1、根据设计图纸分别绑扎地下室筏板钢筋及塔吊基础钢筋,绑扎时将塔吊基础上层钢筋放置在地下室筏板上层钢筋下侧;3.1. Bind the basement raft steel bars and the tower crane foundation steel bars respectively according to the design drawings. When binding, place the upper layer steel bars of the tower crane foundation on the lower side of the basement raft board upper layer steel bars;
3.2、当塔吊基础与筏板结合处有柱墩时,至少将塔吊基础和柱墩范围内的钢筋绑扎完成;当塔吊基础与筏板结合处无柱墩时,至少将塔吊基础范围内的钢筋绑扎完成;3.2. When there is a column pier at the junction of the tower crane foundation and the raft slab, at least the steel bars within the scope of the tower crane foundation and the column pier shall be bound; when there is no column pier at the junction of the tower crane foundation and the raft slab, at least the Lashing completed;
3.3、根据规范要求,预留出地下室筏板插筋,单元结构之间的连接方式最好采用套筒连接,也可采用其他连接方式。3.3. According to the requirements of the specification, the basement raft inserts are reserved, and the connection between the unit structures is best to use a sleeve connection, and other connection methods can also be used.
步骤4、安装止水钢板及塔吊基础预埋螺栓;在施工缝的位置安装一圈止水钢板,起到止水作用;在塔吊基础的中间相应位置安装竖向的塔吊预埋螺栓或根据塔吊安装方案安装其他预埋件。
步骤5、浇筑先施工的塔吊基础和地下室筏板混凝土,安装好模板后浇筑塔吊基础和地下室筏板基础混凝土;
根据施工进度,施工其他部分的地下室筏板。According to the construction progress, construct the basement rafts of other parts.
本申请公开了一种地下室筏板与塔吊基础结合结构及其施工方法,其特征是采用本施工方法,将筏板与塔吊基础结合,在保证施工质量的同时,能减少混凝土及模板用量,有效解决塔吊使用过程中塔吊基础积水问题,避免再次清理、浇筑塔吊基础处地下室筏板,解决施工缝处钢筋、止水钢板的锈蚀问题,可在全国范围进行推广应用,具有较好的经济、安全及社会效益。The application discloses a combination structure of basement raft and tower crane foundation and its construction method, which is characterized in that the raft and tower crane foundation are combined by using the construction method, which can reduce the amount of concrete and formwork while ensuring the construction quality, effectively Solve the problem of water accumulation in the foundation of the tower crane during the use of the tower crane, avoid cleaning and pouring the basement raft at the foundation of the tower crane again, solve the corrosion problem of the steel bars and water-stop steel plates at the construction joints, and can be popularized and applied nationwide, with good economic, safety and social benefits.
本方法将地下室筏板与塔吊基础结合施工,与传统的施工方法相比,减少了混凝土及模板用量,并有效解决了塔吊使用过程中塔吊基础积水问题,避免再次清理、浇筑塔吊基础处地下室筏板,避免现有施工方法施工缝长期不能封闭,钢筋、止水钢板的锈蚀问题,提高混凝土施工质量及塔吊使用过程中的安全性。This method combines the basement raft with the tower crane foundation. Compared with the traditional construction method, it reduces the amount of concrete and formwork, and effectively solves the problem of water accumulation in the tower crane foundation during the use of the tower crane, avoiding cleaning and pouring the basement at the tower crane foundation again. The raft board can avoid the long-term unsealable construction joints of existing construction methods, and the corrosion of steel bars and water-stop steel plates, and improve the quality of concrete construction and the safety of tower cranes during use.
需要说明的是,本申请的说明书和权利要求书及上述附图中的术语“包括”和“具有”以及他们的任何变形,意图在于覆盖不排他的包含,例如,包含了一系列步骤或单元的过程、方法、系统、产品或设备不必限于清楚地列出的那些步骤或单元,而是可包括没有清楚地列出的或对于这些过程、方法、产品或设备固有的其它步骤或单元。It should be noted that the terms "comprising" and "having" in the specification and claims of the present application and the above-mentioned drawings, as well as any variations thereof, are intended to cover non-exclusive inclusion, for example, including a series of steps or units A process, method, system, product or device is not necessarily limited to those steps or elements explicitly listed, but may include other steps or elements not explicitly listed or inherent to the process, method, product or device.
在本申请中,术语“上”、“下”、“左”、“右”、“前”、“后”、“顶”、“底”、“内”、“外”、“中”、“竖直”、“水平”、“横向”、“纵向”等指示的方位或位置关系为基于附图所示的方位或位置关系。这些术语主要是为了更好地描述本申请及其实施例,并非用于限定所指示的装置、元件或组成部分必须具有特定方位,或以特定方位进行构造和操作。In this application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", The orientations or positional relationships indicated by "vertical", "horizontal", "horizontal", and "longitudinal" are based on the orientations or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit that the indicated device, element or component must have a specific orientation, or be constructed and operated in a specific orientation.
并且,上述部分术语除了可以用于表示方位或位置关系以外,还可能用于表示其他含义,例如术语“上”在某些情况下也可能用于表示某种依附关系或连接关系。对于本领域普通技术人员而言,可以根据具体情况理解这些术语在本申请中的具体含义。Moreover, some of the above terms may be used to indicate other meanings besides orientation or positional relationship, for example, the term "upper" may also be used to indicate a certain attachment relationship or connection relationship in some cases. Those skilled in the art can understand the specific meanings of these terms in this application according to specific situations.
此外,术语“安装”、“设置”、“设有”、“连接”、“相连”、“套接”应做广义理解。例如,可以是固定连接,可拆卸连接,或整体式构造;可以是机械连接,或电连接;可以是直接相连,或者是通过中间媒介间接相连,又或者是两个装置、元件或组成部分之间内部的连通。对于本领域普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。Furthermore, the terms "installed", "disposed", "provided", "connected", "connected", "socketed" are to be interpreted broadly. For example, it may be a fixed connection, a detachable connection, or an integral structure; it may be a mechanical connection or an electrical connection; it may be a direct connection or an indirect connection through an intermediary; internal connectivity. Those of ordinary skill in the art can understand the specific meanings of the above terms in this application according to specific situations.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211012902.8A CN115450246A (en) | 2022-08-23 | 2022-08-23 | Tower crane foundation and basement raft combined structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211012902.8A CN115450246A (en) | 2022-08-23 | 2022-08-23 | Tower crane foundation and basement raft combined structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115450246A true CN115450246A (en) | 2022-12-09 |
Family
ID=84298206
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211012902.8A Pending CN115450246A (en) | 2022-08-23 | 2022-08-23 | Tower crane foundation and basement raft combined structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115450246A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115726394A (en) * | 2022-12-19 | 2023-03-03 | 中铁建设集团有限公司 | Tower crane foundation structure and construction method |
-
2022
- 2022-08-23 CN CN202211012902.8A patent/CN115450246A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115726394A (en) * | 2022-12-19 | 2023-03-03 | 中铁建设集团有限公司 | Tower crane foundation structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110761322B (en) | Cast-in-place pipe gallery side wall horizontal construction joint reinforcing structure and construction method thereof | |
CN103015719B (en) | Integral casting process for reinforced concrete wastewater tank of pre-drilling engineering | |
CN108797638A (en) | Integrated assembled piping lane based on composite bottom board and its construction method | |
CN211007021U (en) | Prefabricated balcony of prefabricated building | |
CN206298900U (en) | A kind of diaphram wall built-in type steel encloses purlin plug system | |
CN208441138U (en) | Integrated assembled piping lane based on composite bottom board | |
CN115450246A (en) | Tower crane foundation and basement raft combined structure and construction method thereof | |
CN201473974U (en) | Novel steel plate water stopper | |
CN212670968U (en) | Composite floor and building | |
CN212507370U (en) | Pouring body and pouring hanging die for joint of assembled building laminated slab | |
CN113062236A (en) | Wall protection integrated pipe culvert and construction method thereof | |
CN209163167U (en) | A prefabricated floor connecting node structure | |
CN218346804U (en) | A consolidate pull rod that is used for horizontal seam leak protection of superimposed sheet to starch | |
CN216713983U (en) | Prefabricated side plate for assembled concrete pool | |
CN216865648U (en) | Board connection structure falls in prefabricated superimposed sheet | |
CN206220132U (en) | A kind of base plate and exterior wall junction construction typified form support | |
CN109853806A (en) | It overlaps concrete steel ladder mouth and splices two-way floor | |
CN213979911U (en) | Basement outer wall post-cast strip template structure | |
CN208792081U (en) | An expansion joint device | |
CN213174518U (en) | Connecting structure for connecting parts on prefabricated stairs | |
CN211200755U (en) | Basement roof movement joint waterproof construction structure | |
CN208685813U (en) | A kind of plug-in parapet connecting node construction of clear-water concrete | |
CN207194035U (en) | The constructing structure of the construction joint of basement bottom board and Side fascia | |
CN221919502U (en) | Precast bridge caps and piers | |
CN220827952U (en) | Wallboard for civil engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |