[go: up one dir, main page]

CN115450128A - Cover plate pouring platform, equipment and construction method - Google Patents

Cover plate pouring platform, equipment and construction method Download PDF

Info

Publication number
CN115450128A
CN115450128A CN202211235891.XA CN202211235891A CN115450128A CN 115450128 A CN115450128 A CN 115450128A CN 202211235891 A CN202211235891 A CN 202211235891A CN 115450128 A CN115450128 A CN 115450128A
Authority
CN
China
Prior art keywords
platform
construction
pouring
cover
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211235891.XA
Other languages
Chinese (zh)
Inventor
高明祥
王军良
王建新
黄勇
何卫平
刘喜龙
刘文忠
南娜
伍江
屈润栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Beixin Road and Bridge Group Co Ltd
Original Assignee
Xinjiang Beixin Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Beixin Road and Bridge Group Co Ltd filed Critical Xinjiang Beixin Road and Bridge Group Co Ltd
Priority to CN202211235891.XA priority Critical patent/CN115450128A/en
Publication of CN115450128A publication Critical patent/CN115450128A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本申请公开了一种盖板浇筑平台、设备及施工方法,涉及道路工程的技术领域,以解决现有术中通过搭建支架方式现浇盖板、过程复杂、费时费力的技术问题。本申请的盖板浇筑平台包括:至少两个轨道、施工装置以及升降装置。其中,轨道分别安装在两个台身的侧壁上;施工装置可移动地设于轨道上,且位于两个台身之间;升降装置设于轨道上;施工装置由升降装置顶升至台身的顶部,以浇筑用于连接两个台身的盖板。故本申请具有施工安全、操作简单、通用性强、周转方便快捷的优点。

Figure 202211235891

The application discloses a cover slab pouring platform, equipment and a construction method, which relate to the technical field of road engineering and solve the technical problem that the existing cover slab is cast in place by building a bracket, the process is complicated, time-consuming and labor-intensive. The cover pouring platform of the present application includes: at least two rails, a construction device and a lifting device. Among them, the rails are respectively installed on the side walls of the two platforms; the construction device is movably arranged on the rails and located between the two platforms; the lifting device is arranged on the rails; the construction device is lifted to the platform by the lifting device. The top of the stand to pour the cover plate used to connect the two stands. Therefore, the present application has the advantages of safe construction, simple operation, strong versatility, and convenient and fast turnover.

Figure 202211235891

Description

一种盖板浇筑平台、设备及施工方法A cover pouring platform, equipment and construction method

技术领域technical field

本申请涉及道路工程的技术领域,具体而言,涉及一种盖板浇筑平台、设备及施工方法。The present application relates to the technical field of road engineering, in particular to a cover pouring platform, equipment and construction method.

背景技术Background technique

现有技术中,在涵洞、小桥等道路设施的修建过程中,其施工工艺多采用支架法,施工人员通常在涵身或桥台建造完成后搭设满堂脚手架,并对其连接顶板或连接盖板同样进行支架现浇。这种浇筑方式的施工方法存在诸多不足,例如:对台身较高或跨度较大的道路设施进行施工时,为加快施工进度,施工人员通常采用全涵、全桥方式搭设支架时,该搭设方式所需要的支架数量很大,且搭设过程耗时费工;在道路设施的修建位置地质条件差或涉及过水桥涵搭建时,常出现的因地基承载力不足而造成的处理费用高的问题,以及因水流量较大或环境恶劣、施工人员难以搭设支架而造成的工期耽误问题。In the prior art, during the construction of road facilities such as culverts and small bridges, the construction technology mostly adopts the scaffolding method. The construction workers usually set up a full house of scaffolding after the construction of the culvert body or abutment, and connect the roof or the connecting cover to it. The slabs are also cast-in-place for the brackets. There are many deficiencies in the construction method of this pouring method. For example, when constructing road facilities with a high platform body or a large span, in order to speed up the construction progress, when the construction personnel usually use the full culvert and full bridge method to erect the support, the erection The number of supports required by the method is large, and the erection process is time-consuming and labor-intensive; when the construction location of road facilities has poor geological conditions or involves the construction of bridges and culverts, the problem of high processing costs often occurs due to insufficient foundation bearing capacity , as well as delays in the construction period due to large water flow or harsh environment, and difficulty in erecting supports for construction personnel.

发明内容Contents of the invention

本申请的目的在于提供一种盖板浇筑平台、设备及施工方法,其能够通过可移动式浇筑平台,克服支架搭设浇筑平台造成的费时费力等缺陷,且本申请具有提高浇筑质量、节约成本、通用性强、安全性高、操作简单等优点。The purpose of this application is to provide a cover pouring platform, equipment and construction method, which can overcome the time-consuming and labor-intensive defects caused by erecting the pouring platform through the movable pouring platform, and the application has the advantages of improving the pouring quality, saving costs, It has the advantages of strong versatility, high safety and simple operation.

本申请的实施例是这样实现的:The embodiment of the application is realized like this:

本申请第一方面提供了一种盖板浇筑平台,包括:至少两个轨道、施工装置以及升降装置。其中,轨道分别安装在两个台身的侧壁上;施工装置可移动地设于轨道上,且位于两个台身之间;升降装置设于轨道上;施工装置由升降装置顶升至台身的顶部,以浇筑用于连接两个台身的盖板。The first aspect of the present application provides a cover pouring platform, including: at least two rails, a construction device and a lifting device. Among them, the rails are respectively installed on the side walls of the two platforms; the construction device is movably arranged on the rails and is located between the two platforms; the lifting device is arranged on the rails; the construction device is lifted to the platform by the lifting device The top of the body to pour the cover plate used to connect the two bodies.

于一实施例中,台身的侧壁上设有多个预留孔,一个预留孔内设有一个钢棒,一个轨道与多个钢棒连接。In one embodiment, a plurality of reserved holes are provided on the side wall of the table body, a steel rod is arranged in a reserved hole, and a rail is connected with the plurality of steel rods.

于一实施例中,各个预留孔与台身的顶面之间的距离相等。In one embodiment, the distances between the reserved holes and the top surface of the platform are equal.

于一实施例中,升降装置包括多个升降机构,一个升降机构设于一个钢棒的顶部。In one embodiment, the lifting device includes a plurality of lifting mechanisms, and one lifting mechanism is arranged on the top of a steel bar.

于一实施例中,盖板浇筑平台还包括多个轨夹器,轨夹器设于轨道上,当施工装置落于轨道时,轨夹器抵靠于施工装置的底部阶面上。In one embodiment, the cover pouring platform further includes a plurality of rail grippers, the rail grippers are arranged on the track, and when the construction device falls on the track, the rail grippers abut against the bottom step of the construction device.

于一实施例中,施工装置包括两个主纵梁,一个主纵梁设于一个台身旁的轨道上,主纵梁的两端设有行走轮箱。In one embodiment, the construction device includes two main longitudinal beams, one main longitudinal beam is arranged on the track next to a platform, and the two ends of the main longitudinal beams are provided with traveling wheel boxes.

于一实施例中,施工装置还包括多个丝杆,丝杆的两端分别与两个主纵梁连接。In one embodiment, the construction device further includes a plurality of screw rods, and the two ends of the screw rods are respectively connected to the two main longitudinal beams.

于一实施例中,施工装置还包括剪刀撑,剪刀撑具有四个支撑端,两个支撑端与一个主纵梁连接。In one embodiment, the construction device further includes a scissor brace, the scissor brace has four support ends, and two support ends are connected to a main longitudinal beam.

于一实施例中,施工装置还包括多个分配梁以及浇筑模板。其中,每个分配梁的两端分别搭设于两个主纵梁的顶面上;浇筑模板覆盖于多个分配梁的顶面上。In one embodiment, the construction device further includes a plurality of distribution beams and a pouring formwork. Wherein, the two ends of each distribution beam are erected on the top surfaces of two main longitudinal beams respectively; the pouring formwork is covered on the top surfaces of multiple distribution beams.

于一实施例中,盖板浇筑平台包括至少一个工作护栏,工作护栏设于施工装置的顶面,且横跨于两个台身之间。In one embodiment, the cover pouring platform includes at least one working guardrail, and the working guardrail is arranged on the top surface of the construction device and spans between two platform bodies.

本申请第二方面提供了一种盖板浇筑设备,盖板浇筑设备包括至少一个本申请第一方面任一实施例的盖板浇筑平台。The second aspect of the present application provides a cover slab casting equipment, which includes at least one cover slab casting platform according to any embodiment of the first aspect of the present application.

本申请第三方面提供了一种盖板浇筑设备的施工方法,包括:在搭设完成如本申请第二方面任一实施例的盖板浇筑设备后,调节升降装置的伸缩长度,以将施工装置顶升至台身的顶部;在施工装置的顶面上浇筑用于连接两个台身的盖板;在施工装置下落至轨道后,控制施工装置移动至下一浇筑位置的下方。The third aspect of the present application provides a construction method of the cover pouring equipment, including: after erecting the cover pouring equipment according to any embodiment of the second aspect of the present application, adjusting the telescopic length of the lifting device so that the construction device Jacking up to the top of the platform; pouring a cover plate for connecting the two platforms on the top surface of the construction device; after the construction device falls to the track, control the construction device to move to the bottom of the next pouring position.

本申请与现有技术相比的有益效果是:本申请通过安装在台身上的盖板浇筑平台,以可移动、升降的施工装置实现了在复杂地质条件下、无需搭设大量支架即可在涵洞、桥梁纵深处的任意位置浇筑连接两侧台身的盖板,有效地提高了盖板的浇筑质量、浇筑效率与施工安全性,且适用于多种作业环境与作业空间、装卸方便,故本申请还具有通用性强、节约成本等多方面优势。The beneficial effect of this application compared with the prior art is: this application uses the cover plate pouring platform installed on the platform, and realizes the construction of the culvert under complex geological conditions without the need to build a large number of supports with a movable and lifting construction device. , The cover slab connecting the two sides of the platform can be poured at any position in the depth of the bridge, which effectively improves the pouring quality, pouring efficiency and construction safety of the cover slab, and is suitable for various working environments and working spaces, and is easy to load and unload. The application also has many advantages such as strong versatility and cost saving.

附图说明Description of drawings

为了更清楚地说明本申请实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本申请的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following will briefly introduce the accompanying drawings used in the embodiments. It should be understood that the following drawings only show some embodiments of the present application, so It should be regarded as a limitation on the scope, and those skilled in the art can also obtain other related drawings based on these drawings without creative work.

图1为本申请一实施例示出的盖板浇筑设备的结构示意图;Fig. 1 is a schematic structural view of a cover pouring equipment shown in an embodiment of the present application;

图2(a)为本申请一实施例示出的盖板浇筑平台应用于涵洞时的横断面结构示意图;Fig. 2 (a) is the schematic diagram of the cross-sectional structure when the cover pouring platform shown in an embodiment of the application is applied to a culvert;

图2(b)为本申请一实施例示出的盖板浇筑平台应用于涵洞时的纵断面结构示意图;Fig. 2 (b) is a schematic diagram of the vertical section structure when the cover plate pouring platform shown in an embodiment of the present application is applied to a culvert;

图2(c)为本申请一实施例示出的盖板浇筑平台的局部结构示意图;Fig. 2 (c) is the partial structure schematic diagram of the cover plate pouring platform shown in one embodiment of the present application;

图3(a)为本申请一实施例示出的卡轨器的结构示意图;Fig. 3 (a) is the schematic structural diagram of the rail clamp shown in one embodiment of the present application;

图3(b)为本申请一实施例示出的轨夹器的结构示意图;Fig. 3 (b) is a schematic structural view of the rail clamp shown in an embodiment of the present application;

图3(c)为本申请一实施例示出的主纵梁的结构示意图;Fig. 3 (c) is the structural representation of the main longitudinal beam shown in an embodiment of the present application;

图4为本申请一实施例示出的台身加工预留孔并放置钢棒步骤的涵洞横断面示意图;Fig. 4 is a schematic diagram of a cross-sectional view of a culvert in the step of processing reserved holes in the platform body and placing steel rods according to an embodiment of the present application;

图5(a)为本申请一实施例示出的轨道安装步骤的涵洞横断面示意图;Fig. 5 (a) is the cross-sectional schematic view of the culvert of the track installation step shown in an embodiment of the present application;

图5(b)为本申请一实施例示出的轨道安装步骤的涵洞纵断面示意图;Fig. 5 (b) is the schematic diagram of the longitudinal section of the culvert of the track installation step shown in an embodiment of the present application;

图6(a)为本申请一实施例示出的施工装置拼装步骤的涵洞横断面示意图;Fig. 6 (a) is the schematic diagram of the culvert cross-section of the construction device assembling step shown in an embodiment of the present application;

图6(b)为本申请一实施例示出的施工装置拼装步骤的涵洞纵断面示意图;Fig. 6 (b) is the schematic diagram of the longitudinal section of the culvert of the construction device assembling step shown in an embodiment of the present application;

图7(a)为本申请一实施例示出的预压测试时的涵洞横断面示意图;Fig. 7 (a) is the schematic diagram of the cross-section of the culvert during the preload test shown in an embodiment of the present application;

图7(b)为本申请一实施例示出的预压测试时的涵洞纵断面示意图;Fig. 7 (b) is the schematic diagram of the longitudinal section of the culvert during the preload test shown in an embodiment of the present application;

图8(a)为本申请一实施例示出的盖板分块初步浇筑时的涵洞纵断面示意图;Fig. 8 (a) is the schematic diagram of the longitudinal section of the culvert during the initial pouring of the cover plate shown in one embodiment of the application;

图8(b)为本申请一实施例示出的盖板分块再次浇筑时的涵洞纵断面示意图;Fig. 8 (b) is a schematic diagram of the longitudinal section of the culvert when the cover plate is poured again in blocks according to an embodiment of the present application;

图9为本申请一实施例示出的盖板脱模步骤的涵洞纵断面示意图;Fig. 9 is a schematic diagram of a longitudinal section of a culvert showing the demoulding step of a cover plate according to an embodiment of the present application;

图10为本申请一实施例示出的施工装置移动至下一浇筑位置时的涵洞纵断面示意图。Fig. 10 is a schematic diagram of a longitudinal section of a culvert when the construction device moves to the next pouring position according to an embodiment of the present application.

图标:1-盖板浇筑设备;2-盖板浇筑平台;21-轨道;211-钢棒;212-卡轨器;2121-限位片;2122-容置空位;2123-支撑板;213-轨夹器;2131-挡片;2130-安装空位;2312-锁紧螺栓;22-施工装置;221-主纵梁;2210-梁身;2211-行走轮箱;2212-阶面;2213-电机;2214-移动轮毂;2215-安装座;222-丝杆;223-剪刀撑;2231-支撑端;224-分配梁;225-浇筑模板;23-升降装置;231-升降机构;24-工作护栏;30-地基;31-台身;310-沉降缝;311-预留孔;32-台帽;33-盖板;330-浇筑位置;34-预压块。Icons: 1-cover pouring equipment; 2-cover pouring platform; 21-track; 211-steel rod; 212-rail clamp; 2121-limiting piece; Rail clamp; 2131-block; 2130-installation space; 2312-locking bolt; 22-construction device; 221-main longitudinal beam; 2210-beam body; 2211-traveling wheel box; ;2214-mobile hub;2215-installation seat;222-screw rod;223-scissors support;2231-support end;224-distribution beam;225-casting formwork;23-lifting device;231-lifting mechanism;24-working guardrail 30-foundation; 31-body; 310-settlement joint; 311-reserved hole; 32-cap; 33-cover; 330-pouring position;

具体实施方式detailed description

术语“第一”、“第二”、“第三”等仅用于区分描述,并不表示排列序号,也不能理解为指示或暗示相对重要性。The terms "first", "second", "third" and so on are only used for distinguishing descriptions, and do not represent sequence numbers, nor can they be understood as indicating or implying relative importance.

此外,术语“水平”、“竖直”、“悬垂”等术语并不表示要求部件绝对水平或悬垂,而是可以稍微倾斜。如“水平”仅仅是指其方向相对“竖直”而言更加水平,并不是表示该结构一定要完全水平,而是可以稍微倾斜。In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are absolutely horizontal or overhanging, but may be slightly inclined. For example, "horizontal" only means that its direction is more horizontal than "vertical", and it does not mean that the structure must be completely horizontal, but can be slightly inclined.

在本申请的描述中,需要说明的是,术语“内”、“外”、“左”、“右”、“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该申请产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。In the description of the present application, it should be noted that the orientation or positional relationship indicated by the terms "inner", "outer", "left", "right", "upper", "lower" etc. are based on the Orientation or positional relationship, or the orientation or positional relationship that the application product is usually placed in use, is only for the convenience of describing the application and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, in order to Specific orientation configurations and operations, therefore, are not to be construed as limitations on the application.

在本申请的描述中,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。In the description of this application, unless otherwise clearly stipulated and limited, the terms "installation", "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrally connected; it may be mechanically connected or electrically connected; it may be directly connected or indirectly connected through an intermediary, and it may be the internal communication of two components.

下面将结合附图对本申请的技术方案进行清楚、完整地描述。The technical solutions of the present application will be clearly and completely described below in conjunction with the accompanying drawings.

请参照图1,图1为本申请一实施例示出的盖板浇筑设备1的结构示意图。如图1所示,本申请提供了一种盖板浇筑设备1,该设备结合以往桥梁、涵洞施工经验、并在此基础上不断完善,设计形成了现浇涵洞盖板或小桥梁板所需的自行式一体化施工设备,该设备使盖板浇筑过程的施工效率得以提高,施工的质量、安全性以及环保性得到可靠控制,且适配性强。Please refer to FIG. 1 . FIG. 1 is a schematic structural diagram of a cover pouring equipment 1 shown in an embodiment of the present application. As shown in Figure 1, the application provides a cover pouring equipment 1, the equipment combined with previous bridge, culvert construction experience, and based on this continuous improvement, designed to form the cast-in-place culvert cover slab or small bridge slab required Self-propelled integrated construction equipment, which improves the construction efficiency of the cover slab pouring process, and reliably controls the quality, safety and environmental protection of the construction, and has strong adaptability.

其中,盖板浇筑设备1包括至少一个盖板浇筑平台2。当涵洞或桥梁纵深过长时,可以采用两个以上盖板浇筑平台2连接在一起的方式加快施工进度。于本申请下述实施例中,仅以一个盖板浇筑平台2为例。Wherein, the cover casting equipment 1 includes at least one cover casting platform 2 . When the depth of the culvert or the bridge is too long, the construction progress can be accelerated by connecting more than two cover pouring platforms 2 together. In the following embodiments of the present application, only one cover pouring platform 2 is taken as an example.

请参照图2(a)、图2(b),图2(a)为本申请一实施例示出的盖板浇筑平台2应用于涵洞时的横断面结构示意图;图2(b)为本申请一实施例示出的盖板浇筑平台2应用于涵洞时的纵断面结构示意图。如图2(a)、图2(b)所示,盖板浇筑平台2包括:至少两个轨道21、施工装置22以及升降装置23。其中,轨道21分别安装在两个台身31的侧壁上;施工装置22可移动地设于轨道21上,且位于两个台身31之间;升降装置23设于轨道21上;施工装置22由升降装置23顶升至台身31的顶部,以浇筑用于连接两个台身31的盖板33。Please refer to Fig. 2 (a), Fig. 2 (b), Fig. 2 (a) is the cross-sectional structure schematic diagram when the cover pouring platform 2 shown in one embodiment of the application is applied to the culvert; Fig. 2 (b) is the application A schematic diagram of the longitudinal section structure of the cover slab pouring platform 2 shown in one embodiment when it is applied to a culvert. As shown in FIG. 2( a ) and FIG. 2( b ), the cover plate pouring platform 2 includes: at least two rails 21 , a construction device 22 and a lifting device 23 . Wherein, track 21 is respectively installed on the side wall of two platform bodies 31; Construction device 22 is arranged on track 21 movably, and is positioned between two platform bodies 31; Lifting device 23 is arranged on track 21; Construction device 22 is lifted to the top of the platform body 31 by the lifting device 23 to pour a cover plate 33 for connecting the two platform bodies 31 .

在盖板33浇筑之前,涵洞或桥梁等道路设施纵向延伸、且两侧(道路设施自身的两端)均由数段间隔一定距离的台身31构成,同一侧纵向延伸方向上的台身31之间设有沉降缝310,沉降缝310是指为防止建筑物各部分由于地基30不均匀沉降引起建筑物破坏所设置的垂直缝。为此,应在适当位置如复杂的平面或体形转折处、高度变化处、荷载、地基30的压缩性和地基30处理的方法明显不同处设置沉降缝310,已进一步保证道路设施长期使用的稳定性。Before the cover plate 33 is poured, road facilities such as culverts or bridges extend longitudinally, and both sides (both ends of the road facility itself) are composed of several sections of abutment 31 at a certain distance, and the abutment 31 in the longitudinal extension direction of the same side Settlement joints 310 are arranged between them, and settlement joints 310 refer to vertical joints set to prevent building damage caused by uneven settlement of the foundation 30 in various parts of the building. For this reason, settlement joints 310 should be set at appropriate positions such as complex plane or body shape turning points, height changes, loads, foundation 30 compressibility, and foundation 30 treatment methods that are obviously different, so as to further ensure the long-term stability of road facilities. sex.

每段台身31的顶部设有台帽32,台身31设于地基30上,本申请实施例即在道路设施两侧的台身31及台身31之间的空位上搭设盖板浇筑平台2,以使施工人员无需搭设支架即可随施工装置22上升至两侧台帽32之间的空位处进行盖板33浇筑工作。The top of each platform body 31 is provided with a platform cap 32, and the platform body 31 is arranged on the foundation 30. In the embodiment of the present application, a cover plate pouring platform is set up on the platform body 31 on both sides of the road facility and the space between the platform body 31. 2, so that the construction personnel can rise with the construction device 22 to the space between the platform caps 32 on both sides to perform the pouring work of the cover plate 33 without erecting a support.

为了在两侧台身31上初步搭设轨道21,台身31的侧壁上预设有多个预留孔311,一个预留孔311内设有一个钢棒211,一个轨道21与多个钢棒211通过卡轨器212连接,一个轨道21的某一端通过两个卡轨器212搭设在一个钢棒211上,以进一步安装在台身31的侧壁上,一个轨道21至少需要两个钢棒211保持稳定。在台上侧壁上,相邻钢棒211之间的间隔距离、与每个台身31上预留孔311或钢棒211的数量根据施工需要设置,若存在轨道21较长或搭设于轨道21上的施工装置22重量较重等特殊情况,可以通过增加钢棒211数量、缩短间隔距离的方式增加轨道21的稳定性。In order to preliminarily set up the track 21 on the platform body 31 on both sides, a plurality of reserved holes 311 are preset on the side wall of the platform body 31, and a steel rod 211 is arranged in a reserved hole 311, and a rail 21 is connected with a plurality of steel rods. The rod 211 is connected by a rail clamp 212, and a certain end of a track 21 is erected on a steel rod 211 by two rail clamps 212 to be further installed on the side wall of the table body 31. A rail 21 requires at least two steel rods. Rod 211 remains stable. On the side wall of the platform, the spacing distance between adjacent steel bars 211, and the number of reserved holes 311 or steel bars 211 on each platform body 31 are set according to construction needs. In special cases such as the heavy weight of the construction device 22 on the 21, the stability of the track 21 can be increased by increasing the number of steel rods 211 and shortening the spacing distance.

于一实施例中,为保证搭设于钢棒211上的轨道21与台身31的顶面平行,即轨道21各处与台帽32之间的距离相等,在预设各个预留孔311时需保证预留孔311与台身31的顶面之间的距离相等。In one embodiment, in order to ensure that the track 21 erected on the steel rod 211 is parallel to the top surface of the table body 31, that is, the distance between the track 21 and the table cap 32 is equal, each reserved hole 311 is preset It is necessary to ensure that the distance between the reserved hole 311 and the top surface of the platform body 31 is equal.

施工装置22包括两个主纵梁221,一个主纵梁221设于一个台身31旁的轨道21上,主纵梁221的两端各设有一个行走轮箱2211,设于主纵梁221一端的行走轮箱2211上设有电机2213,设于主纵梁221两端的移动轮箱内均设有移动轮毂2214,梁身2210与两端的移动轮箱构成“π”字形的主纵梁221。Construction device 22 comprises two main longitudinal beams 221, and a main longitudinal beam 221 is located on the track 21 beside a platform body 31, and the two ends of main longitudinal beam 221 are respectively provided with a walking wheel box 2211, is located at main longitudinal beam 221 The traveling wheel box 2211 at one end is equipped with a motor 2213, and the moving wheel boxes at both ends of the main longitudinal beam 221 are equipped with moving hubs 2214, and the beam body 2210 and the moving wheel boxes at both ends form a "π"-shaped main longitudinal beam 221 .

请参见图2(c),图2(c)为本申请一实施例示出的盖板浇筑平台2的局部结构示意图。请结合图2(a)至图2(c)所示,主纵梁221的梁身2210上还设有四个安装座2215,安装座2215用于连接丝杆222以及加固支撑所用的剪刀撑223。丝杆222的两端分别通过安装座2215与两侧台身31旁的主纵梁221连接。剪刀撑223具有四个支撑端2231,每两个支撑端2231通过安装座2215与一个主纵梁221连接。每个主纵梁221上设有四个安装座2215,每个安装座2215上均连接有一个丝杆222且两侧台身31旁的主纵梁221规格相同、安装座2215位置对应。每个主纵梁221的中间两个安装座2215上还连接有一个剪刀撑223的两个支撑端2231。于一实施例中,丝杆222为长度可调节的调节丝杆。Please refer to FIG. 2( c ). FIG. 2( c ) is a partial structural schematic view of the cover plate pouring platform 2 shown in an embodiment of the present application. Please refer to Fig. 2(a) to Fig. 2(c), there are also four installation seats 2215 on the beam body 2210 of the main longitudinal beam 221, and the installation seats 2215 are used to connect the screw rod 222 and the scissor brace used for reinforcement support 223. Both ends of the threaded rod 222 are respectively connected to the main longitudinal beams 221 next to the platform body 31 on both sides through the mounting base 2215 . The scissor brace 223 has four supporting ends 2231 , and every two supporting ends 2231 are connected to one main longitudinal beam 221 through the mounting base 2215 . Each main longitudinal beam 221 is provided with four installation seats 2215, and each installation seat 2215 is connected with a threaded mandrel 222 and the specifications of the main longitudinal beams 221 next to the platform body 31 on both sides are the same, and the positions of the installation seats 2215 are corresponding. Two supporting ends 2231 of a scissor brace 223 are also connected to the middle two installation seats 2215 of each main longitudinal beam 221 . In one embodiment, the screw rod 222 is an adjustable screw rod with adjustable length.

施工装置22还包括多个分配梁224以及浇筑模板225。其中,每个分配梁224的两端分别搭设于两个主纵梁221的顶面上,分配梁224为“工”字型;浇筑模板225覆盖于多个分配梁224的顶面上,浇筑模板225由多个相同规格的浇筑单元板构成。The construction device 22 also includes a plurality of distribution beams 224 and a casting formwork 225 . Wherein, the two ends of each distribution beam 224 are erected on the top surfaces of two main longitudinal beams 221 respectively, and the distribution beams 224 are in the shape of "I"; The formwork 225 is composed of a plurality of pouring unit plates of the same specification.

于一实施例中,盖板浇筑平台2还包括至少一个工作护栏24,工作护栏24设于施工装置22的顶面,设于主纵梁221、分配梁224以及浇筑模板225的边缘位置且横跨于两个台身31之间。工作护栏24用于保证施工人员在浇筑连接两个台帽32的盖板33时的安全性,防止施工人员因疏忽意外踩空从高处跌落。In one embodiment, the cover plate pouring platform 2 also includes at least one working guardrail 24, the working guardrail 24 is arranged on the top surface of the construction device 22, and is arranged on the edge positions of the main longitudinal beam 221, the distribution beam 224 and the pouring formwork 225 and horizontally It straddles between the two platform bodies 31 . The working guardrail 24 is used to ensure the safety of the construction personnel when pouring the cover plate 33 connecting the two platform caps 32, and prevents the construction personnel from accidentally stepping on the air and falling from a height due to negligence.

升降装置23包括多个升降机构231,升降机构231设于轨道21上且位于钢棒211的顶部。于一实施例中,升降机构231可以为千斤顶。升降机构231位于主纵梁221与轨道21之间,在施工人员调节升降机构231的伸缩长度时,主纵梁221可以随升降机构231上升至盖板33的水平浇筑位置330或随升降机构231下落于轨道21上。于本申请下述实施例中,每个主纵梁221可由两个升降机构231顶升,一个盖板浇筑平台2由四个升降机构231顶升,升降机构231的顶升面设于每个主纵梁221的梁身2210底部。于本申请其他实施例中,升降机构231可以设为其他数量。The lifting device 23 includes a plurality of lifting mechanisms 231 , and the lifting mechanisms 231 are arranged on the track 21 and located on top of the steel bar 211 . In one embodiment, the lifting mechanism 231 can be a jack. The lifting mechanism 231 is located between the main longitudinal beam 221 and the track 21. When construction personnel adjust the telescopic length of the lifting mechanism 231, the main longitudinal beam 221 can rise to the horizontal pouring position 330 of the cover plate 33 with the lifting mechanism 231 or with the lifting mechanism 231. Fall on track 21. In the following embodiments of the present application, each main longitudinal girder 221 can be lifted by two lifting mechanisms 231, and one cover pouring platform 2 can be lifted by four lifting mechanisms 231, and the lifting surface of the lifting mechanism 231 is set on each The bottom of the beam body 2210 of the main longitudinal beam 221 . In other embodiments of the present application, other numbers of lifting mechanisms 231 can be set.

于一实施例中,盖板浇筑平台2还包括多个轨夹器213,轨夹器213设于轨道21上,当主纵梁221落于轨道21时,轨夹器213抵靠于主纵梁221的底部阶面2212上,防止施工装置22在轨道21上因受力出现突然地不确定滑动、造成危险施工或浇注位置偏离。In one embodiment, the cover pouring platform 2 further includes a plurality of rail clamps 213, and the rail clamps 213 are arranged on the track 21. When the main longitudinal beam 221 falls on the track 21, the rail clamps 213 lean against the main longitudinal beam 221 on the bottom step surface 2212, to prevent the construction device 22 from suddenly slipping uncertainly due to force on the track 21, causing dangerous construction or pouring position deviation.

请参见图3(a),图3(a)为本申请一实施例示出的卡轨器212的结构示意图。如图3(a)所示,卡轨器212包括支撑板2123、限位片2121,限位片2121为弯折的L形结构且与支撑板2123之间构成容置空位2122。安装轨道21时,两个卡轨器212的支撑板2123设于钢棒211的两侧且轨道21的底部设于容置空位2122内,由限位片2121限制避免从钢棒211上方滑脱。Please refer to FIG. 3( a ). FIG. 3( a ) is a schematic structural diagram of a rail clip 212 shown in an embodiment of the present application. As shown in FIG. 3( a ), the rail clamp 212 includes a support plate 2123 and a limiting piece 2121 . The limiting piece 2121 is a bent L-shaped structure and forms an accommodating space 2122 with the supporting plate 2123 . When the track 21 is installed, the support plates 2123 of the two rail clamps 212 are arranged on both sides of the steel bar 211 and the bottom of the track 21 is set in the accommodating space 2122, which is restricted by the stopper 2121 to avoid slipping from the steel bar 211 top.

请参见图3(b),图3(b)为本申请一实施例示出的轨夹器213的结构示意图。如图3(b)所示,轨夹器213包括挡片2131、锁紧螺栓2312与安装空位2130。在限制轨道21上的主纵梁221移动时,轨夹器213的挡片2131抵靠于主纵梁221的底部阶面2212上,其底部的安装空位2130容置有轨道21的顶端,施工人员可以拧动锁紧螺栓2312以使轨道21与轨夹器213的相对位置固定、且保证轨夹器213不发生滑动,进而保证与轨夹器213接触的主纵梁221也不在轨道21上发生移动。Please refer to FIG. 3( b ), which is a schematic structural diagram of the rail clamp 213 shown in an embodiment of the present application. As shown in FIG. 3( b ), the rail clamp 213 includes a blocking piece 2131 , a locking bolt 2312 and an installation space 2130 . When restricting the movement of the main longitudinal beam 221 on the track 21, the stop piece 2131 of the rail clamp 213 is against the bottom step surface 2212 of the main longitudinal beam 221, and the installation space 2130 at the bottom accommodates the top of the track 21, and the construction Personnel can twist the locking bolt 2312 to fix the relative position of the rail 21 and the rail clamp 213, and ensure that the rail clamp 213 does not slide, and then ensure that the main longitudinal beam 221 in contact with the rail clamp 213 is not on the rail 21 Movement occurs.

请参见图3(c),图3(c)为本申请一实施例示出的主纵梁221的结构示意图。请结合图1至图3(c)所示,主纵梁221包括梁身2210与两端的行走轮箱2211,两端的行走轮箱2211内均设有可在轨道21上滚动的行走轮毂,一端的行走轮箱2211上设有驱动移动轮毂2214移动的电机2213。两端的行走轮箱2211与梁身2210构成“π”形结构。Please refer to FIG. 3( c ), which is a schematic structural view of the main longitudinal beam 221 shown in an embodiment of the present application. 1 to 3 (c), the main longitudinal beam 221 includes the beam body 2210 and the wheel boxes 2211 at both ends, and the wheel boxes 2211 at both ends are provided with wheel hubs that can roll on the track 21. The traveling wheel box 2211 is provided with a motor 2213 that drives the mobile hub 2214 to move. The traveling wheel boxes 2211 at both ends and the beam body 2210 form a "π"-shaped structure.

盖板浇筑设备1的安装施工流程、以及相应的盖板浇筑过程主要包括如下步骤:The installation and construction process of the cover pouring equipment 1 and the corresponding cover pouring process mainly include the following steps:

S01:施工人员准备施工过程所需要的图纸、相应的材料与相应的施工工具等,以做好盖板浇筑设备1安装前的准备工作。S01: The construction personnel prepare the drawings, corresponding materials and corresponding construction tools required for the construction process, so as to make preparations for the installation of the cover pouring equipment 1 .

S02:在准备好后开始测量放线、挖掘基坑。S02: Start measuring and setting out the line and excavating the foundation pit after preparation.

S03:在挖好基坑并获得基坑两侧的台身31或墙身后,施工人员在台身31上施工并设置预留孔311,以在后续准备安装轨道21之前向预留孔311中放置需要的钢棒211来支撑轨道21。S03: After the foundation pit is dug and the platform body 31 or walls on both sides of the foundation pit are obtained, the construction personnel construct on the platform body 31 and set the reserved holes 311, so as to fill the reserved holes 311 before preparing to install the track 21 The required steel rods 211 are placed to support the track 21 .

S04:安装轨道21。S04: Install the track 21.

S05:在施工人员安装好轨道21后,对轨道21进行行走试验并调整轨道21以保证两侧台身31上的轨道21平行且轨距一致;S05: After the construction personnel installed the track 21, conduct a running test on the track 21 and adjust the track 21 to ensure that the tracks 21 on the platform bodies 31 on both sides are parallel and have the same gauge;

S06:在轨道21调整好后,施工人员进行支模的标高调整,主纵梁221、分配梁224以及浇筑模板225的安装。S06: After the track 21 is adjusted, the construction workers adjust the elevation of the formwork, and install the main longitudinal beam 221, the distribution beam 224 and the pouring formwork 225.

S07:在安装好盖板浇筑设备1后,施工人员通过升降装置23将浇筑模板225顶升至台帽32之间,在浇筑模板225上安装钢筋、分块支模并浇筑盖板33。S07: After the cover pouring equipment 1 is installed, the construction workers lift the pouring formwork 225 to between the platform caps 32 through the lifting device 23, install steel bars on the pouring formwork 225, support the formwork in blocks, and pour the cover slab 33.

S08:对浇筑好的盖板33进行养护。S08: Carry out maintenance on the poured cover plate 33 .

S09:施工人员调整升降装置23,使升降装置23回缩并拆除浇筑模板225。S09: The construction workers adjust the lifting device 23 to retract the lifting device 23 and remove the pouring formwork 225 .

S10:进行台身31下一节段的盖板33浇筑施工流程(根据现场施工情况可选择重新执行S03至S05中的任一步骤,以继续对涵洞或桥梁纵深方向的下一节段台身31进行盖板33浇筑)。S10: Carry out the pouring construction process of the cover plate 33 of the next section of the abutment 31 (according to the construction situation on site, any step in S03 to S05 can be selected to be re-executed to continue the next section of the abutment in the depth direction of the culvert or bridge 31 carry out cover plate 33 pouring).

上述步骤中的具体细节请参见下述内容及相应附图。For specific details in the above steps, please refer to the following content and corresponding drawings.

请参见图4,图4为本申请一实施例示出的台身31加工预留孔311并放置钢棒211步骤的涵洞横断面示意图。如图4所示,在墙身或台身31基础施工完成后,施工人员根据设计图纸放出墙身或台身31控制线。施工时,施工人员在距离台身31顶面116cm,距离台身31两侧边沿50cm的位置(请结合图5(b),也可以设置为其他位置尺寸值)设置预留孔311,预留孔311采用Φ630mmpvc或其他尺寸,且预埋深度为30cm。Please refer to FIG. 4 . FIG. 4 is a schematic diagram of a cross-sectional view of a culvert in the steps of machining a reserved hole 311 and placing a steel rod 211 in the platform body 31 shown in an embodiment of the present application. As shown in Fig. 4, after the foundation construction of the wall body or the platform body 31 is completed, the construction personnel release the control line of the wall body or the platform body 31 according to the design drawings. During construction, the construction personnel set up a reserved hole 311 at a position 116cm away from the top surface of the platform body 31 and 50cm away from the sides of the platform body 31 (please refer to Figure 5(b), or it can be set to other position size values). The hole 311 adopts Φ630mmpvc or other dimensions, and the embedded depth is 30cm.

在已加工好预留孔311后,施工人员在安装轨道21之前人工安装穿心棒(即为钢棒211),穿心棒采用直径50mm、长度60cm的钢材质,单根重量7.7Kg。于一实施例中,每节台身31每一侧安装2根钢棒211,两侧对称安装,共安装4根钢棒211。若每节台身31或墙身的纵深长度超过8m,则可以在墙身或台身31上安装2套以上盖板浇筑平台2、并由多套盖板浇筑平台2组成盖板浇筑设备1,以加快盖板33浇筑的进度。After the reserved hole 311 has been processed, the construction personnel manually install the piercing rod (that is, the steel rod 211) before installing the track 21. The piercing rod is made of steel with a diameter of 50mm and a length of 60cm, and a single weight is 7.7Kg. In one embodiment, two steel rods 211 are installed on each side of each platform body 31 , and the two sides are symmetrically installed, and a total of four steel rods 211 are installed. If the depth of each platform body 31 or wall body exceeds 8m, more than two sets of cover casting platforms 2 can be installed on the wall or platform body 31, and cover casting equipment 1 can be composed of multiple sets of cover casting platforms 2 , to speed up the progress of the cover plate 33 pouring.

请参见图5(a)、图5(b),图5(a)为本申请一实施例示出的轨道21安装步骤的涵洞横断面示意图;图5(b)为本申请一实施例示出的轨道21安装步骤的涵洞纵断面示意图。如图5(a)、图5(b)所示,于一实施例中,轨道21采用工字型轨道21,轨道21的截面尺寸可以为上宽70mm、下宽150mm、高度200mm、采用厚20mm钢板焊接。单根轨道21长度为8m,每根轨道21重量约为478Kg,在安装轨道21时采用人工配合吊车安装。每套盖板浇筑平台2配4节轨道21。轨道21根据施工进度可以选择分段安装、也可以选择两段同时安装,轨道21安装铺设在台身31侧壁的钢棒211上。为防止轨道21意外移动或脱落,轨道21与钢棒211之间采用卡轨器212定位,每根钢棒211的两侧安装2个卡轨器212。在轨道21安装完成后,施工人员需要检查轨道21的轨距是否一致,以进一步保证轨道21的正常功能。Please refer to Fig. 5 (a), Fig. 5 (b), Fig. 5 (a) is a schematic diagram of the culvert cross section of the track 21 installation step shown in one embodiment of the application; Schematic diagram of the longitudinal section of the culvert for the installation steps of the track 21. As shown in Figure 5(a) and Figure 5(b), in one embodiment, the track 21 adopts an I-shaped track 21, and the cross-sectional size of the track 21 can be 70mm in width at the top, 150mm in width at the bottom, and 200mm in height. 20mm steel plate welding. The length of a single track 21 is 8m, and the weight of each track 21 is about 478Kg. When the track 21 is installed, it is manually installed with a crane. Every cover plate pouring platform 2 is equipped with 4 sections of tracks 21. The track 21 can be installed in sections according to the construction progress, or two sections can be selected to be installed at the same time. The track 21 is installed and laid on the steel rod 211 of the side wall of the platform body 31 . In order to prevent the track 21 from accidentally moving or falling off, a rail clamp 212 is used for positioning between the track 21 and the steel rod 211, and two rail clamps 212 are installed on both sides of each steel rod 211. After the installation of the track 21 is completed, construction personnel need to check whether the gauge of the track 21 is consistent, so as to further ensure the normal function of the track 21 .

请参见图6(a)、图6(b),图6(a)为本申请一实施例示出的施工装置22拼装步骤的涵洞横断面示意图;图6(b)为本申请一实施例示出的施工装置22拼装步骤的涵洞纵断面示意图。请结合图1至图6(b)所示,于一实施例中,在轨道21安装完成后,施工人员进行主纵梁221安装,主纵梁221两端为行走轮箱2211,两端行走轮箱2211内均设有移动轮毂2214,且一端为主动轮,一端为从动轮。主纵梁221采用遥控控制电机2213启停的方式进一步控制主动轮与从动轮的停止和行走,电机2213采用慢速电机2213,行走速度为3米每分钟,每节主纵梁221长度8m,形状近似为“Π”型。主纵梁221采用厚度20mm钢板焊接而成并采用人工配合吊车安装。Please refer to Fig. 6 (a), Fig. 6 (b), Fig. 6 (a) is a schematic cross-sectional view of the culvert of the construction device 22 assembling steps shown in one embodiment of the application; Fig. 6 (b) shows an embodiment of the application The schematic diagram of the longitudinal section of the culvert of the construction device 22 assembly steps. Please refer to Fig. 1 to Fig. 6(b), in one embodiment, after the track 21 is installed, the construction personnel install the main longitudinal beam 221, and the two ends of the main longitudinal beam 221 are walking wheel boxes 2211, and the two ends are walking The wheel box 2211 is equipped with a moving wheel hub 2214, and one end is a driving wheel and the other end is a driven wheel. The main longitudinal beam 221 adopts the mode of remote control motor 2213 to start and stop to further control the stopping and walking of the driving wheel and the driven wheel. The motor 2213 adopts a slow motor 2213, and the walking speed is 3 meters per minute. The length of each main longitudinal beam 221 is 8m. The shape is approximately "Π" type. The main longitudinal beam 221 is welded by steel plates with a thickness of 20 mm and installed manually with a crane.

两侧台身31旁的主纵梁221安装完成后,主纵梁221通过4根横向的丝杆222连接加固并定位,在横向丝杆222调整完成后再安装剪刀撑223以增加主纵梁221的横向稳定性与主纵梁221的刚性。After the installation of the main longitudinal beams 221 next to the platform body 31 on both sides is completed, the main longitudinal beams 221 are connected, reinforced and positioned by four horizontal screw rods 222. After the adjustment of the horizontal screw rods 222 is completed, the scissor braces 223 are installed to increase the main longitudinal beams. The lateral stability of 221 and the rigidity of main longitudinal beam 221.

于本申请一实施例中,每个盖板浇筑平台2设有一个剪刀撑223。安装完成后,施工人员控制主纵梁221进行纵向试验行走并根据行走情况调整两侧轨道21,确保施工装置22在盖板浇筑平台2后续使用过程中行走平顺。In an embodiment of the present application, each cover pouring platform 2 is provided with a scissor brace 223 . After the installation is completed, the construction personnel control the main longitudinal beam 221 to conduct a longitudinal test and adjust the rails 21 on both sides according to the running conditions to ensure that the construction device 22 runs smoothly during the subsequent use of the cover pouring platform 2 .

请参见图7(a)、图7(b),图7(a)为本申请一实施例示出的预压测试时的涵洞横断面示意图;图7(b)为本申请一实施例示出的预压测试时的涵洞纵断面示意图。Please refer to Fig. 7(a), Fig. 7(b), Fig. 7(a) is a schematic diagram of the cross-section of the culvert during the preload test shown in one embodiment of the application; Schematic diagram of the culvert profile during the preload test.

请结合图1至图7(b)所示,在丝杆222及剪刀撑223安装完成后,施工人员于主纵梁221顶面铺设工字钢型的分配梁224,分配梁224的间距根据跨度不同采用不同间距,间距为45cm~70cm,具体间距以实际荷载计算为准,然后在分配梁224顶面铺设浇筑模板225。施工人员还于主纵梁221的梁身2210下方的轨道21上安装升降机构231(例如千斤顶),升降机构231设于钢棒211上方。安装完成后,施工装置22的高程通过升降机构231调整,并通过轨道21及行走轮箱2211在整个盖板33浇筑范围的下方水平移动,实现无需支架的逐段式移动施工。Please refer to Fig. 1 to Fig. 7(b), after the screw rod 222 and the scissor brace 223 are installed, the construction personnel lay the I-shaped steel distribution beam 224 on the top surface of the main longitudinal beam 221, and the distance between the distribution beam 224 is according to Different spacings are used for different spans, and the spacing is 45cm to 70cm. The specific spacing is subject to actual load calculation, and then the pouring formwork 225 is laid on the top surface of the distribution beam 224 . Construction workers also install a lifting mechanism 231 (such as a jack) on the track 21 below the beam body 2210 of the main longitudinal beam 221 , and the lifting mechanism 231 is arranged above the steel bar 211 . After the installation is completed, the elevation of the construction device 22 is adjusted by the lifting mechanism 231, and moves horizontally below the entire cover plate 33 pouring range through the track 21 and the traveling wheel box 2211, so as to realize the segment-by-stage mobile construction without support.

于一实施例中,在轨道21对应钢棒211位置放置升降机构231,升降机构231可以采用16吨机械千斤顶,行程200mm,每套盖板浇筑平台2配置4个千斤顶,千斤顶对施工装置22的顶升高度约180mm左右。千斤顶伸长,盖板浇筑平台2的施工装置22也就由千斤顶顶升,当浇筑模板225被顶升至铺模控制线时,施工人员控制千斤顶停止伸长,并搬动手柄锁紧千斤顶。In one embodiment, a lifting mechanism 231 is placed at the position corresponding to the steel bar 211 on the track 21. The lifting mechanism 231 can use a 16-ton mechanical jack with a stroke of 200mm. Each set of cover plate pouring platform 2 is equipped with 4 jacks. The jacking height is about 180mm. The jack is extended, and the construction device 22 of the cover plate pouring platform 2 is also lifted by the jack. When the pouring formwork 225 is lifted to the formwork control line, the construction personnel control the jack to stop extending, and move the handle to lock the jack.

在初次安装盖板浇筑平台2并且浇筑模板225铺设完成后,施工人员需要对盖板浇筑平台2进行预压测试,以检验盖板浇筑平台2的强度、刚度、稳定性。预压测试前施工人员需要在浇筑模板225上面铺设彩条布以防止浇筑模板225受损。After the cover pouring platform 2 is installed for the first time and the pouring formwork 225 is laid, the construction personnel need to perform a preload test on the cover pouring platform 2 to check the strength, rigidity and stability of the cover pouring platform 2 . Before the pre-compression test, construction workers need to lay color strips on the pouring formwork 225 to prevent the pouring formwork 225 from being damaged.

预压测试采用多个预压块34模拟预压负载,总负载设计为浇筑模板225设计荷载的120%。预压分三级进行,分别为预压荷载总量的60%,100%,120%,施工人员预先布设9个观测点进行沉降观测,预压测试合格的结果以两次观测结果差值不大于2mm、且第三级加载2天后观测结果差值不大于3mm为准,满足上述条件才可以认定沉降处于稳定状态。预压块34的卸载同样采用分级卸载,并记录每分级卸载后的浇筑模板225回弹量,该回弹量作为后期施工线型控制的原始数据,且浇筑模板225根据预压数据也可以预留一定的预拱度。The preload test uses multiple preload blocks 34 to simulate the preload, and the total load is designed to be 120% of the design load of the pouring formwork 225 . The preloading is carried out in three stages, which are respectively 60%, 100%, and 120% of the total preloading load. The construction personnel pre-arranged 9 observation points for settlement observation. If the difference is greater than 2mm and the difference between the observation results after 2 days of loading at the third stage is not greater than 3mm, the settlement can be considered to be in a stable state only if the above conditions are met. The unloading of the pre-compression block 34 also adopts graded unloading, and records the rebound amount of the pouring formwork 225 after each graded unloading. Leave a certain amount of pre-camber.

在搭设完成盖板浇筑设备1、且盖板浇筑设备1已通过预压测试后,施工人员调节升降装置23的伸缩长度,以将施工装置22顶升至台身31的顶部、并开始在施工装置22的顶面上浇筑用于连接两个台身31的盖板33。After the cover pouring equipment 1 has been erected and the cover pouring equipment 1 has passed the preload test, the construction personnel adjust the telescopic length of the lifting device 23 to lift the construction device 22 to the top of the platform body 31 and start construction. A cover plate 33 for connecting the two platform bodies 31 is poured on the top surface of the device 22 .

请参见图8(a)、图8(b),图8(a)为本申请一实施例示出的盖板分块初步浇筑时的涵洞纵断面示意图;图8(b)为本申请一实施例示出的盖板分块再次浇筑时的涵洞纵断面示意图。Please refer to Fig. 8(a), Fig. 8(b), Fig. 8(a) is a schematic diagram of the longitudinal section of the culvert during the initial pouring of the cover plate shown in an embodiment of the application; Fig. 8(b) is an implementation of the application The schematic diagram of the longitudinal section of the culvert when the cover slab is poured in blocks is shown as an example.

如图1至图8(b)所示,施工人员首先在浇筑模板225上将钢筋分块绑扎以完成侧模安装,然后针对各个侧模逐个进行盖板33或梁板的浇筑。以图8(a)、图8(b)中,盖板33分六块浇筑为例,施工人员先对间隔的前三块进行侧模安装与混凝土浇筑;当盖板33的前三块砼强度达到要求时,拆除前三段侧模,开始间隔的后三段侧模的钢筋安装,并进行混凝土浇筑。请结合图6(a)所示,盖板横跨两侧台身31之间,且对应长度为L。As shown in Fig. 1 to Fig. 8(b), the construction workers first bind the steel bars in blocks on the pouring formwork 225 to complete the installation of the side forms, and then pour the cover plates 33 or beam slabs one by one for each side form. Taking Fig. 8(a) and Fig. 8(b) as an example, the cover plate 33 is poured in six pieces, and the construction personnel first install the side formwork and concrete pouring for the first three pieces of the interval; when the first three pieces of the cover plate 33 When the strength meets the requirements, the first three sections of side forms are removed, and the steel bars of the last three sections of side forms are installed at intervals, and concrete is poured. Please refer to FIG. 6( a ), the cover board spans between the two sides of the platform body 31 , and the corresponding length is L.

在盖板33每一段混凝土浇筑完并达到终凝时间时,施工人员就要对其覆盖土工布进行浇水保湿养护,养护时间一般为7天左右,视天气和气温酌情调整,盖板33在砼强度达到设计或规范要求后方可拆除。When the concrete of each section of the cover plate 33 is poured and reaches the final setting time, the construction personnel will carry out watering and moisturizing maintenance on the covered geotextile. The concrete strength can only be demolished after reaching the design or specification requirements.

请参见图9,图9为本申请一实施例示出的盖板33脱模步骤的涵洞纵断面示意图。如图9所示,施工人员在盖板33浇筑完成、拆除浇筑模板225时,要操作升降机构231下降,施工装置22在重力作用下跟随升降机构231一同下降,下降的时候要缓慢稳定。施工装置22下降后分配梁224及浇筑模板225会自然脱落,其中,未脱落的分配梁224和浇筑模板225采用人工拆除。Please refer to FIG. 9 . FIG. 9 is a schematic diagram of a longitudinal section of a culvert during the demoulding step of the cover plate 33 shown in an embodiment of the present application. As shown in Figure 9, when the construction personnel complete the pouring of the cover plate 33 and remove the pouring formwork 225, they must operate the lifting mechanism 231 to descend, and the construction device 22 will descend together with the lifting mechanism 231 under the action of gravity, and it should be slow and stable when descending. After the construction device 22 is lowered, the distribution beam 224 and the pouring formwork 225 will fall off naturally, and the distribution beam 224 and the pouring formwork 225 that have not fallen off are manually removed.

升降装置23回缩一定距离后,主纵梁221的行走轮箱2211会落到轨道21上。此时施工人员取出升降机构231,用卡轨器212限位以防止主纵梁221移动,施工人员拆除的浇筑模板225暂时搁置在分配梁224上。After the lifting device 23 retracts a certain distance, the traveling wheel box 2211 of the main longitudinal beam 221 will fall on the track 21 . At this time, the construction workers take out the lifting mechanism 231 and limit the position with the rail clamp 212 to prevent the main longitudinal beam 221 from moving.

请参见图10,图10为本申请一实施例示出的施工装置22移动至下一浇筑位置330时的涵洞纵断面示意图。如图10所示,当前盖板33浇筑完成施工装置22需要移动至下一节段的台身31再次准备盖板33浇筑施时,施工装置22先下落至轨道21,施工人员在下一节段的墙身、台式上制备预留孔311、安装钢棒211及轨道21。随后施工人员调整和固定轨道21,经检查符合要求后,松开轨夹器213,操作控制器使主纵梁221在轨道21上行走,控制施工装置22移动至下一浇筑位置330的下方。施工装置22行走至下一浇筑位置330的下方后,施工人员再次通过轨夹器213锁紧主纵梁221,并对平台检查和调整。然后再次控制升降机构231伸长以将浇筑模板225顶升至支模标高、进行模板安装与钢筋安装、开展下一节盖板33的现浇施工。施工人员依次循环完成每个节段台身31的顶部的盖板浇筑直至整个涵洞或桥梁的盖板33浇筑完成。Please refer to FIG. 10 , which is a schematic cross-sectional view of the culvert when the construction device 22 moves to the next pouring position 330 according to an embodiment of the present application. As shown in Figure 10, when the front cover plate 33 is poured and the construction device 22 needs to move to the platform body 31 of the next section to prepare the cover plate 33 pouring again, the construction device 22 first falls to the track 21, and the construction personnel will move to the next section. Prepare reserved holes 311, install steel rods 211 and tracks 21 on the body of the wall and the table top. Then the construction workers adjust and fix the track 21, and after checking that it meets the requirements, release the rail clamp 213, operate the controller to make the main longitudinal beam 221 walk on the track 21, and control the construction device 22 to move to the bottom of the next pouring position 330. After the construction device 22 moves to the bottom of the next pouring position 330, the construction personnel lock the main longitudinal beam 221 again through the rail clamp 213, and check and adjust the platform. Then control the elongation of the lifting mechanism 231 again to lift the pouring formwork 225 to the formwork support level, carry out formwork installation and steel bar installation, and carry out the cast-in-place construction of the next section cover plate 33. The construction personnel complete the pouring of the cover plate on the top of the platform body 31 of each segment sequentially in a cycle until the pouring of the cover plate 33 of the entire culvert or bridge is completed.

本申请提供的盖板浇筑设备1与施工方法在应用于涵洞、小桥现浇修建过程中不需要搭设支架、只需要借助安装在台身31上的盖板浇筑平台2即可进行现浇施工。其次,对地质条件差、作业空间不足或正在过水的桥涵,不会出现因地基承载力不足而造成的处理费用高、或水流量较大、作业空间太小而无法搭设支架等施工问题,其实用性较强、通用型较高。另外,本申请提供的盖板浇筑设备1在应用时施工质量可靠,分节段施工安全性高,操作简单,且周转方便快捷,对于各种跨径的涵洞、小桥的盖板现浇施工只需要更换丝杆222即可,降低施工成本且具有较好的技术经济效益。The cover pouring equipment 1 and the construction method provided by the present application do not need to set up supports when they are applied to the cast-in-place construction of culverts and small bridges, and only need to use the cover pouring platform 2 installed on the platform body 31 to carry out cast-in-place construction . Secondly, for bridges and culverts with poor geological conditions, insufficient working space or passing water, there will be no construction problems such as high treatment costs due to insufficient foundation bearing capacity, or large water flow, too small working space to erect supports, etc. It has strong practicability and high universality. In addition, the cover pouring equipment 1 provided by this application has reliable construction quality during application, high safety in segmented construction, simple operation, and convenient and fast turnover. Only the screw rod 222 needs to be replaced, which reduces the construction cost and has better technical and economic benefits.

本申请通过安装在台身31上的盖板浇筑平台2,以可移动、升降的施工装置22实现了在复杂地质条件下、无需搭设大量支架即可在涵洞、桥梁纵深处的任意位置浇筑连接两侧台身31的盖板33。本申请有效地提高了盖板33的浇筑质量、浇筑效率与施工安全性,且适用于多种作业环境与作业空间、装卸方便,还具有通用性强、节约成本等多方面优势。In this application, through the cover pouring platform 2 installed on the platform body 31, the movable and lifting construction device 22 realizes the pouring and connection at any position in the depth of the culvert and bridge under complex geological conditions without erecting a large number of supports. The cover plate 33 of the platform body 31 on both sides. This application effectively improves the pouring quality, pouring efficiency and construction safety of the cover plate 33, is applicable to various working environments and working spaces, is convenient to load and unload, and has many advantages such as strong versatility and cost saving.

以上所述仅为本申请的优选实施例而已,并不用于限制本申请,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above descriptions are only preferred embodiments of the present application, and are not intended to limit the present application. For those skilled in the art, there may be various modifications and changes in the present application. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of this application shall be included within the protection scope of this application.

Claims (12)

1. The utility model provides a apron pouring platform which characterized in that includes:
the at least two rails are respectively arranged on the side walls of the two platform bodies;
the construction device is movably arranged on the track and is positioned between the two platform bodies;
the lifting device is arranged on the track; the construction device is jacked to the top of the platform body by the lifting device so as to pour the cover plate for connecting the two platform bodies.
2. The cover plate pouring platform according to claim 1, wherein a plurality of preformed holes are formed in the side wall of the platform body, one steel bar is arranged in each preformed hole, and one rail is connected with the plurality of steel bars.
3. The deck casting platform as claimed in claim 2, wherein each of said preformed holes is equidistant from a top surface of said deck.
4. The decking pouring platform defined in claim 2 wherein the lifting means includes a plurality of lifting mechanisms, one on top of each of the steel bars.
5. The cover deck pouring platform as recited in claim 1, further comprising:
and the rail clamps are arranged on the rail, and when the construction device falls on the rail, the rail clamps are abutted against the bottom step surface of the construction device.
6. The deck casting platform as claimed in claim 1, wherein said construction means comprises:
the two main longitudinal beams are arranged on the track beside the platform body, and the two ends of each main longitudinal beam are provided with a traveling wheel box.
7. The deck casting platform as claimed in claim 6, wherein said construction means further comprises:
and two ends of the screw rod are respectively connected with the two main longitudinal beams.
8. The deck casting platform as claimed in claim 6, wherein said construction means further comprises:
the cross brace is provided with four support ends, and the two support ends are connected with the main longitudinal beam.
9. The deck casting platform as claimed in claim 6, wherein said construction means further comprises:
the two ends of each distribution beam are respectively erected on the top surfaces of the two main longitudinal beams;
and the pouring templates cover the top surfaces of the distribution beams.
10. The deck casting platform as claimed in claim 1, wherein said deck casting platform comprises:
and the working guardrail is arranged on the top surface of the construction device and stretches across the two platform bodies.
11. Cover casting installation, characterized in that it comprises at least one cover casting platform according to any of claims 1 to 10.
12. The construction method of the cover plate pouring equipment is characterized by comprising the following steps:
after the cover plate pouring equipment according to claim 11 is erected, adjusting the telescopic length of the lifting device to lift the construction device to the top of the platform body;
pouring a cover plate for connecting the two platform bodies on the top surface of the construction device;
and after the construction device falls to the track, controlling the construction device to move to the position below the next pouring position.
CN202211235891.XA 2022-10-10 2022-10-10 Cover plate pouring platform, equipment and construction method Pending CN115450128A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211235891.XA CN115450128A (en) 2022-10-10 2022-10-10 Cover plate pouring platform, equipment and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211235891.XA CN115450128A (en) 2022-10-10 2022-10-10 Cover plate pouring platform, equipment and construction method

Publications (1)

Publication Number Publication Date
CN115450128A true CN115450128A (en) 2022-12-09

Family

ID=84308457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211235891.XA Pending CN115450128A (en) 2022-10-10 2022-10-10 Cover plate pouring platform, equipment and construction method

Country Status (1)

Country Link
CN (1) CN115450128A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202595630U (en) * 2012-05-03 2012-12-12 中铁七局集团有限公司 Template construction trolley for steel-frame bridge crossing business line
CN103615264A (en) * 2013-11-26 2014-03-05 华北水利水电大学 Desert conduit two-casting type steel form trolley and casting method
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
CN108035741A (en) * 2018-02-05 2018-05-15 三门峡市水利勘测设计有限责任公司 A kind of backform trolley
CN108979664A (en) * 2018-06-20 2018-12-11 中铁六局集团有限公司 Existing subway tunnel based on mobile casting platform protects steel structure pouring construction method
CN109779684A (en) * 2019-03-14 2019-05-21 甘肃路桥建设集团有限公司 Rapid and standardized construction device and construction method for integrated highway tunnel cable trough
CN209686260U (en) * 2018-11-22 2019-11-26 中铁八局集团昆明铁路建设有限公司 A kind of crown formwork jumbo for the construction of diplopore arch culvert
CN215595601U (en) * 2021-07-12 2022-01-21 中国建筑第八工程局有限公司 A template platform truck for cast-in-place apron of tunnel center escape canal
CN216999345U (en) * 2022-03-11 2022-07-19 中铁二十四局集团有限公司 Walking wheel stopper for bridge girder erection machine

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202595630U (en) * 2012-05-03 2012-12-12 中铁七局集团有限公司 Template construction trolley for steel-frame bridge crossing business line
CN103615264A (en) * 2013-11-26 2014-03-05 华北水利水电大学 Desert conduit two-casting type steel form trolley and casting method
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
CN108035741A (en) * 2018-02-05 2018-05-15 三门峡市水利勘测设计有限责任公司 A kind of backform trolley
CN108979664A (en) * 2018-06-20 2018-12-11 中铁六局集团有限公司 Existing subway tunnel based on mobile casting platform protects steel structure pouring construction method
CN209686260U (en) * 2018-11-22 2019-11-26 中铁八局集团昆明铁路建设有限公司 A kind of crown formwork jumbo for the construction of diplopore arch culvert
CN109779684A (en) * 2019-03-14 2019-05-21 甘肃路桥建设集团有限公司 Rapid and standardized construction device and construction method for integrated highway tunnel cable trough
CN215595601U (en) * 2021-07-12 2022-01-21 中国建筑第八工程局有限公司 A template platform truck for cast-in-place apron of tunnel center escape canal
CN216999345U (en) * 2022-03-11 2022-07-19 中铁二十四局集团有限公司 Walking wheel stopper for bridge girder erection machine

Similar Documents

Publication Publication Date Title
CN100441779C (en) Bridge construction method with prefabricated translation in place in the air
CN104695337B (en) Self-lifting sliding and turnover construction system and construction method
CN113235472B (en) Concrete placement platform truck is contained to apron
CN112320611B (en) Overweight assembled prefabricated stair hoisting device and construction method
CN115075143B (en) Bridge tower column construction method
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN115306136B (en) Inclined wall eversion climbing type steel platform construction device and method
CN116065500A (en) Cable-stayed bridge tower girder synchronous system and construction method
CN110878532A (en) Subway box girder translation construction device and method
CN214993219U (en) Concrete placement platform truck is contained to apron
CN203200664U (en) Slip-form construction device for variable cross-section hollow high pier
CN118958134A (en) An integral moving device for a load-bearing disc buckle scaffold
CN111395176B (en) Mobile formwork lowering and dismantling construction method based on convenience
CN210766417U (en) Pier-spanning lifting beam support device at side position of bridge
CN115450128A (en) Cover plate pouring platform, equipment and construction method
CN111364741A (en) Construction process for integrally moving disc buckle type full-hall support
CN207727440U (en) Whole self-crawling type integrated platform for bridge tower construction
CN216765625U (en) Integral hydraulic creeping formwork structure for double-column pier construction
CN214116258U (en) A high-speed railway prefabricated box girder anti-drop beam stop installation device
CN213869897U (en) Tunnel lining reinforcing steel bar trolley
CN212426772U (en) Suspended bracket system for cast-in-place bridge deck of steel plate composite beam
CN213233105U (en) Small-span concrete cast-in-place box girder support system
CN217679020U (en) A kind of downward guide adjustment device for steel cage of underground continuous wall
CN113802468A (en) Asymmetric cable-stayed bridge special-shaped concrete tower column construction process
CN114875955B (en) Ultra-long concrete straight retaining wall template mounting device and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221209