CN115325037A - Flexible production line for bearing assembly - Google Patents

Flexible production line for bearing assembly Download PDF

Info

Publication number
CN115325037A
CN115325037A CN202210861253.2A CN202210861253A CN115325037A CN 115325037 A CN115325037 A CN 115325037A CN 202210861253 A CN202210861253 A CN 202210861253A CN 115325037 A CN115325037 A CN 115325037A
Authority
CN
China
Prior art keywords
bearing
bearing assembly
assembly
production line
raw material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210861253.2A
Other languages
Chinese (zh)
Inventor
杨志凯
许德章
汪步云
李公文
邓启超
杨鸥
陈龙
曹浩然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Polytechnic University
Wuhu Anpu Robot Industry Technology Research Institute Co Ltd
Original Assignee
Anhui Polytechnic University
Wuhu Anpu Robot Industry Technology Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Polytechnic University, Wuhu Anpu Robot Industry Technology Research Institute Co Ltd filed Critical Anhui Polytechnic University
Priority to CN202210861253.2A priority Critical patent/CN115325037A/en
Publication of CN115325037A publication Critical patent/CN115325037A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C43/00Assembling bearings
    • F16C43/04Assembling rolling-contact bearings
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/74Feeding, transfer, or discharging devices of particular kinds or types
    • B65G47/90Devices for picking-up and depositing articles or materials
    • B65G47/92Devices for picking-up and depositing articles or materials incorporating electrostatic or magnetic grippers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F9/00Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes
    • B66F9/06Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes movable, with their loads, on wheels or the like, e.g. fork-lift trucks
    • B66F9/063Automatically guided
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C43/00Assembling bearings
    • F16C43/04Assembling rolling-contact bearings
    • F16C43/06Placing rolling bodies in cages or bearings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Transportation (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mounting Of Bearings Or Others (AREA)
  • Warehouses Or Storage Devices (AREA)

Abstract

The invention relates to the technical field of automatic assembly of robots, in particular to a flexible production line for bearing assembly, wherein a ball filling device, a setting device and a ball separating device are integrated on each bearing assembly platform, a steel ball blanking mechanism is arranged at the top end of the ball filling device and is used for automatically and sequentially blanking steel balls with different types and sizes, a plurality of transportation components are used for sending out a bearing assembly instruction, calling an idle transportation component to a raw material three-dimensional warehouse, transporting a raw material tray taken out of the raw material three-dimensional warehouse to an idle bearing assembly platform by using a stacker, assembling an inner ring and an outer ring by using the setting device, filling the corresponding type of steel balls into a bearing by the ball filling device according to an order, sending the bearing to the ball separating device for ball separation and placing and installing a retainer after the operation is finished, transporting the assembled bearing to a riveting press by using the transportation component for riveting, finally placing the bearing on a finished product three-dimensional warehouse, finishing the flexible assembly of the bearing, and simultaneously producing bearing products with different types.

Description

一种轴承装配柔性生产线A flexible production line for bearing assembly

技术领域technical field

本发明涉及机器人自动化装配技术领域,尤其涉及一种轴承装配柔性生产线。The invention relates to the technical field of robot automatic assembly, in particular to a flexible bearing assembly production line.

背景技术Background technique

轴承是当代机械设备中一种重要零部件,一般由外圈、内圈、钢珠和保持架组成,现有技术中,例如中国专利文献CN201410547121.8公开的一种关节轴承装配自动生产线包括集储料、内外圈测量、开缝、合套、游隙检测、激光打标、清洗、涂油和包装为一体,各设备前后顺次设置,解决现有关节轴承装配时自动化程度低、装配效率低的问题,中国专利文献CN202110359101.8公开的一种轴承自动化装配装置包括回转单元以及围绕回转单元布置的第一上料单元、第二上料单元、第三上料单元、第四上料单元、第五上料单元、出料单元,完成自动化装配,中国专利文献CN202011307013.5公开的一种轴承自动化装配教学生产线包括灌珠模块、合套模块、行走轴模块、分珠模块、铆压模块,通过工业机器人装配过程中应用自动化生产线,可实现深沟球轴承的自动化装配、轴承铆压、视觉检测、自动上下料,但是,以上现有轴承装配生产线均采用专机,一专机只能进行一种固定型号轴承生产,不能满足小批量多型号的同时生产需求,新增一种型号的轴承装配需要大量的设备和资金投入,且轴承装配只能根据预先设定进行,当一种原材料出现短缺或者生产计划出现改变,设备只能停止运行,由此,还不足以满足更高的实用性需求。Bearings are an important part of contemporary mechanical equipment, and are generally composed of outer rings, inner rings, steel balls and cages. In the prior art, for example, a joint bearing assembly automatic production line disclosed in Chinese patent document CN201410547121.8 includes storage Material, inner and outer ring measurement, slotting, fitting, clearance detection, laser marking, cleaning, oiling and packaging are integrated, and each equipment is set up in sequence to solve the problem of low automation and low assembly efficiency in the assembly of existing joint bearings problem, the Chinese patent document CN202110359101.8 discloses a bearing automatic assembly device including a rotary unit and a first feeding unit, a second feeding unit, a third feeding unit, a fourth feeding unit arranged around the rotating unit, The fifth feeding unit and the discharging unit complete automatic assembly. A teaching production line for automatic assembly of bearings disclosed in Chinese patent document CN202011307013.5 includes a bead filling module, a set module, a walking shaft module, a bead separating module, and a riveting module. Through the application of automated production lines in the assembly process of industrial robots, automatic assembly of deep groove ball bearings, bearing riveting, visual inspection, and automatic loading and unloading can be realized. The production of fixed-type bearings cannot meet the simultaneous production needs of small batches and multiple models. The assembly of a new type of bearing requires a large amount of equipment and capital investment, and the bearing assembly can only be carried out according to preset settings. When a raw material is in short supply or The production plan has changed, and the equipment can only stop running, so it is not enough to meet the higher practical needs.

发明内容Contents of the invention

有鉴于此,本发明的目的在于提出一种轴承装配柔性生产线,以解决专机只能进行一种固定型号轴承生产,不能满足小批量多型号的同时生产需求的问题。In view of this, the purpose of the present invention is to propose a flexible bearing assembly production line to solve the problem that a special machine can only produce a fixed type of bearing and cannot meet the simultaneous production needs of small batches of multiple types.

基于上述目的,本发明提供了一种轴承装配柔性生产线,包括用于储存原料的原材料立体库、用于存放轴承成品的成品立体库、用于在原材料立体库取出原材料托盘的堆垛机、用于钢珠灌输的灌珠器、用于轴承内圈、外圈与钢珠合套装配的定型器、用于合套后轴承内钢珠等分与上保持架的安装的分珠器、用于分珠后轴承与下保持架铆压的铆压机,其特征在于,还包括:Based on the above purpose, the present invention provides a flexible production line for bearing assembly, including a raw material three-dimensional warehouse for storing raw materials, a finished product three-dimensional warehouse for storing finished bearing products, a stacker for taking out raw material trays from the raw material three-dimensional warehouse, Bead filling device for steel ball infusion, sizing device for bearing inner ring, outer ring and steel ball assembly, bead separator for bearing inner steel ball equalization and installation of upper cage after assembly, bead separator for bead separation The riveting machine for riveting the rear bearing and the lower cage is characterized in that it also includes:

轴承装配台,轴承装配台排列布设有若干个,各轴承装配台上均集成设置有灌珠器、定型器、分珠器,灌珠器顶端设有钢珠下料机构,用于不同型号大小的钢珠自动逐次下料;There are several bearing assembly tables arranged in a row. Each bearing assembly table is integrated with a bead filling device, a shaper, and a bead separator. The top of the bead filling device is equipped with a steel ball unloading mechanism, which is used for different models and sizes. Steel balls are automatically fed one by one;

运输组件,运输组件设有若干个,用于将原材料立体库取出的原材料托盘运输至闲置的轴承装配台上装配。There are several transportation components, which are used to transport the raw material pallets taken out of the raw material three-dimensional warehouse to the idle bearing assembly table for assembly.

优选地,轴承装配台前侧设有料盘传送带。Preferably, a tray conveyor belt is provided on the front side of the bearing assembly platform.

优选地,原材料立体库前侧设有原料输送带。Preferably, a raw material conveyor belt is provided on the front side of the raw material three-dimensional warehouse.

优选地,运输组件包括多个传送带复合AGV,传送带复合AGV顶端设有用于传送原材料托盘的传送带。Preferably, the transport assembly includes a plurality of conveyor belt compound AGVs, and a conveyor belt for transporting raw material pallets is provided at the top of the conveyor belt compound AGVs.

优选地,运输组件还包括机械臂复合AGV,机械臂复合AGV顶端设有多自由度的协作机械臂,协作机械臂末端装设有电磁吸盘,得电产生电磁吸附,用于抓取包装好的轴承。Preferably, the transportation component also includes a composite AGV with manipulators. A multi-degree-of-freedom collaborative robot arm is provided at the top of the composite AGV. An electromagnetic chuck is installed at the end of the collaborative robot arm, which is electrically powered to generate electromagnetic adsorption for grabbing the packaged bearings.

优选地,轴承装配台上设有转运机械手和操作机械手,转运机械手和操作机械手末端装设有电磁夹爪,用于多型号轴承的抓取定位装配。Preferably, the bearing assembly platform is provided with a transfer manipulator and an operation manipulator, and the ends of the transfer manipulator and the operation manipulator are equipped with electromagnetic grippers for grasping, positioning and assembling of multi-type bearings.

优选地,钢珠下料机构包括设于灌珠器顶端的料斗,料斗底部连接有料筒,料筒内立设有挡柱,挡柱外侧与料筒内侧之间形成环形的间隙,间隙内螺旋绕设有多条旋转滑道,旋转滑道底端开设有漏孔,由上至下的漏孔孔径依次减小,以供不同型号大小的钢珠自动逐次下料。Preferably, the steel ball unloading mechanism includes a hopper arranged at the top of the bead filling device, a material cylinder is connected to the bottom of the hopper, and a retaining column is erected inside the material cylinder, and an annular gap is formed between the outside of the retaining column and the inside of the material cylinder, and the gap is spirally wound There are multiple rotating slideways, and there is a leakage hole at the bottom of the rotating slideway, and the diameter of the leakage hole decreases successively from top to bottom, so that steel balls of different types and sizes can be automatically discharged one by one.

优选地,各旋转滑道顶端为位于料斗与料筒的连接处环形开口,各环形开口之间设有隔板,各环形开口的宽度与各旋转滑道的漏孔孔径对应一致。Preferably, the top of each rotating slideway is an annular opening at the connection between the hopper and the barrel, and a partition is provided between each annular opening, and the width of each annular opening corresponds to the diameter of the leakage hole of each rotating slideway.

优选地,旋转滑道尾端设有电磁阀门,用于控制相应数量的钢珠下料。Preferably, an electromagnetic valve is provided at the end of the rotary slideway to control the feeding of a corresponding number of steel balls.

优选地,灌珠器上设有用于带动料筒振动下料的振动器。Preferably, the bead filler is provided with a vibrator for driving the barrel to vibrate and discharge.

本发明的有益效果:通过各轴承装配台上均集成设置有灌珠器、定型器、分珠器,同时灌珠器顶端设有钢珠下料机构,用于不同型号大小的钢珠自动逐次下料,若干个运输组件,待发出轴承装配指令,呼叫空闲的运输组件至原材料立体库前,利用堆垛机将原材料立体库取出的原材料托盘运输至闲置的轴承装配台上,经由定型器组装内圈外圈,灌珠器根据订单对轴承进行相应型号钢珠灌装,完成此项操作后送至分珠器进行分珠并放置安装保持架,装配完成的轴承由运输组件搬运至铆压机内铆压处理,并最终放置于成品立体库上,完成轴承的柔性装配,同时进行不同型号的轴承产品的同时生产工作。Beneficial effects of the present invention: each bearing assembly platform is integrated with a bead filling device, a shaping device, and a bead separator, and the top of the bead filling device is equipped with a steel ball unloading mechanism, which is used for automatic successive unloading of steel balls of different sizes , a number of transport components, wait for the bearing assembly command to be issued, call the idle transport components to the raw material three-dimensional warehouse, use the stacker to transport the raw material pallets taken out of the raw material three-dimensional warehouse to the idle bearing assembly table, and assemble the inner ring through the shaper The outer ring and the bead filling device fill the bearing with the corresponding type of steel balls according to the order. After this operation is completed, it is sent to the bead separator for separation and installation of the cage. The assembled bearing is transported by the transportation component to the riveting machine for internal riveting Pressing treatment, and finally placed on the three-dimensional warehouse of finished products, complete the flexible assembly of bearings, and carry out simultaneous production of different types of bearing products at the same time.

附图说明Description of drawings

为了更清楚地说明本发明或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the present invention or the technical solutions in the prior art, the accompanying drawings that need to be used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the accompanying drawings in the following description are only the present invention. Invention, for those of ordinary skill in the art, other drawings can also be obtained based on these drawings without creative work.

图1为本发明的整体俯视结构示意图;Fig. 1 is the overall top view structure schematic diagram of the present invention;

图2为本发明的轴承装配台的俯视结构示意图;Fig. 2 is a top view structural schematic diagram of the bearing assembly platform of the present invention;

图3为本发明的原材料立体库和传送带复合AGV的立体结构示意图;Fig. 3 is the schematic diagram of the three-dimensional structure of the raw material three-dimensional warehouse and the conveyor belt composite AGV of the present invention;

图4为本发明的轴承装配台的立体结构示意图;Fig. 4 is a three-dimensional structural schematic diagram of the bearing assembly platform of the present invention;

图5为本发明的铆压机的立体结构示意图;Fig. 5 is the schematic diagram of the three-dimensional structure of the riveting press of the present invention;

图6为本发明的机械臂复合AGV和成品立体库的立体结构示意图;Fig. 6 is the schematic diagram of the three-dimensional structure of the manipulator composite AGV and the finished product three-dimensional warehouse of the present invention;

图7为本发明的钢珠下料机构的结构示意图;Fig. 7 is a schematic structural view of the steel ball blanking mechanism of the present invention;

图8为本发明的钢珠下料机构的俯视图。Fig. 8 is a top view of the steel ball unloading mechanism of the present invention.

图中标记为:Labeled in the figure:

1、传送带复合AGV;2、料盘传送带;3、轴承装配台;301、示教器;302、显示屏;303、分珠器;304、转运机械手;305、定型器;306、灌珠器;307、操作机械手;308、控制板;4、铆压传送带;5、铆压机;6、七轴机械手;7、废品库;8、打包机;9、机械臂复合AGV;10、成品立体库;11、堆垛机;12、原材料立体库;13、原料输送带;14、钢珠下料机构;141、料斗;142、料筒;143、挡柱;144、旋转滑道;145、漏孔;146、环形开口;147、隔板;148、振动器。1. Conveyor belt composite AGV; 2. Tray conveyor belt; 3. Bearing assembly platform; 301. Teaching device; 302. Display screen; 303. Bead separator; 304. Transfer manipulator; ;307. Operation manipulator; 308. Control panel; 4. Riveting conveyor belt; 5. Riveting machine; 6. Seven-axis manipulator; warehouse; 11. stacker; 12. three-dimensional raw material warehouse; 13. raw material conveyor belt; 14. steel ball unloading mechanism; 141. hopper; 142. barrel; Hole; 146, annular opening; 147, partition; 148, vibrator.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚明白,以下结合具体实施例,对本发明进一步详细说明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with specific examples.

需要说明的是,除非另外定义,本发明使用的技术术语或者科学术语应当为本发明所属领域内具有一般技能的人士所理解的通常意义。本发明中使用的“第一”、“第二”以及类似的词语并不表示任何顺序、数量或者重要性,而只是用来区分不同的组成部分。“包括”或者“包含”等类似的词语意指出现该词前面的元件或者物件涵盖出现在该词后面列举的元件或者物件及其等同,而不排除其他元件或者物件。“连接”或者“相连”等类似的词语并非限定于物理的或者机械的连接,而是可以包括电性的连接,不管是直接的还是间接的。“上”、“下”、“左”、“右”等仅用于表示相对位置关系,当被描述对象的绝对位置改变后,则该相对位置关系也可能相应地改变。It should be noted that, unless otherwise defined, the technical terms or scientific terms used in the present invention shall have the usual meanings understood by those skilled in the art to which the present invention belongs. "First", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. "Comprising" or "comprising" and similar words mean that the elements or items appearing before the word include the elements or items listed after the word and their equivalents, without excluding other elements or items. Words such as "connected" or "connected" are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "Down", "Left", "Right" and so on are only used to indicate the relative positional relationship. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

如图1至图8所示,一种轴承装配柔性生产线,包括用于储存原料的原材料立体库12、用于存放轴承成品的成品立体库10、用于在原材料立体库12取出原材料托盘的堆垛机11、用于钢珠灌输的灌珠器306、用于轴承内圈、外圈与钢珠合套装配的定型器305、用于合套后轴承内钢珠等分与上保持架的安装的分珠器303、用于分珠后轴承与下保持架铆压的铆压机5,还包括轴承装配台3,轴承装配台3排列布设有若干个,各轴承装配台3上均集成设置有灌珠器306、定型器305、分珠器303,灌珠器306顶端设有钢珠下料机构14,用于不同型号大小的钢珠自动逐次下料,运输组件,运输组件设有若干个,用于将原材料立体库12取出的原材料托盘运输至闲置的轴承装配台3上装配。As shown in Figures 1 to 8, a flexible bearing assembly production line includes a raw material three-dimensional warehouse 12 for storing raw materials, a finished product three-dimensional warehouse 10 for storing finished bearing products, and a stack for taking out raw material trays from the raw material three-dimensional warehouse 12. Stacker 11, bead filling device 306 for steel ball infusion, sizing device 305 for bearing inner ring, outer ring and steel ball assembly, assembly for the assembly of bearing inner steel balls and the installation of the upper cage The bead device 303, the riveting machine 5 used for riveting the bearing and the lower cage after separating the beads, also includes a bearing assembly table 3, and several bearing assembly tables 3 are arranged in a row, and each bearing assembly table 3 is integrated with a filling machine. The bead device 306, the shaper 305, the bead separator 303, the top of the bead filling device 306 is provided with a steel ball unloading mechanism 14, which is used for automatic successive unloading of steel balls of different sizes, and the transport assembly is provided with several transport assemblies for The raw material pallets taken out of the raw material three-dimensional warehouse 12 are transported to the idle bearing assembly platform 3 for assembly.

本发明基于现有的轴承自动化装配教学生产线,包括用于储存原料的原材料立体库12、用于存放轴承成品的成品立体库10、用于在原材料立体库12取出原材料托盘的堆垛机11、用于钢珠灌输的灌珠器306、用于轴承内圈、外圈与钢珠合套装配的定型器305、用于合套后轴承内钢珠等分与上保持架的安装的分珠器303、用于分珠后轴承与下保持架铆压的铆压机5,特别的,还包括轴承装配台3,轴承装配台3排列布设有若干个,并在各轴承装配台3上均集成设置有灌珠器306、定型器305、分珠器303,同时灌珠器306顶端设有钢珠下料机构14,用于不同型号大小的钢珠自动逐次下料,若干个运输组件,待发出轴承装配指令,呼叫空闲的运输组件至原材料立体库12前,利用堆垛机11将原材料立体库12取出的原材料托盘运输至闲置的轴承装配台3上,经由定型器305组装内圈外圈,灌珠器306根据订单对轴承进行相应型号钢珠灌装,完成此项操作后送至分珠器303进行分珠并放置安装保持架,装配完成的轴承由运输组件搬运至铆压机5内铆压处理,并最终放置于成品立体库10上,完成轴承的柔性装配,同时进行不同型号的轴承产品的同时生产工作。The present invention is based on the existing bearing automatic assembly teaching production line, including a raw material three-dimensional warehouse 12 for storing raw materials, a finished product three-dimensional warehouse 10 for storing finished bearing products, a stacker 11 for taking out raw material pallets from the raw material three-dimensional warehouse 12, Bead injector 306 for infusion of steel balls, shaper 305 for assembly of bearing inner ring, outer ring and steel balls, bead separator 303 for equal division of steel balls in the bearing and installation of upper cage after assembly, The riveting machine 5 used for riveting the bearing and the lower cage after separating the balls, in particular, also includes a bearing assembly table 3, and several bearing assembly tables 3 are arranged in a row, and each bearing assembly table 3 is integrated with a The bead filling device 306, the setting device 305, the bead separating device 303, and the top of the bead filling device 306 is equipped with a steel ball unloading mechanism 14, which is used for automatic unloading of steel balls of different sizes one by one, several transport components, pending the issue of bearing assembly instructions , before calling the idle transport components to the raw material three-dimensional warehouse 12, use the stacker 11 to transport the raw material pallets taken out of the raw material three-dimensional warehouse 12 to the idle bearing assembly table 3, assemble the inner and outer rings through the shaper 305, and the bead filling device 306 fills the bearing with steel balls of the corresponding type according to the order. After this operation is completed, it is sent to the bead separator 303 to separate the beads and install the cage. The assembled bearing is transported by the transportation component to the riveting machine 5 for internal riveting. And finally placed on the finished product three-dimensional warehouse 10, the flexible assembly of the bearing is completed, and the simultaneous production of different types of bearing products is carried out at the same time.

在本发明的实施例中,轴承装配台3前侧设有料盘传送带2。In the embodiment of the present invention, a tray conveyor belt 2 is provided on the front side of the bearing assembly platform 3 .

在本发明的实施例中,原材料立体库12前侧设有原料输送带13。In the embodiment of the present invention, a raw material conveyor belt 13 is provided on the front side of the raw material three-dimensional warehouse 12 .

在本发明的实施例中,运输组件包括多个传送带复合AGV1,传送带复合AGV1顶端设有用于传送原材料托盘的传送带,从而依靠堆垛机11将原材料立体库12取出的原材料托盘运输至原料输送带13上,由原料输送带13运输至传送带复合AGV1上,再运送至闲置的料盘传送带2上,以进行相应的装配作业,优选的,铆压机5前侧还设有铆压传送带4、七轴机械手6,装配好的轴承由传送带复合AGV1运送至铆压传送带4上料,再由七轴机械手6抓取进入铆压机5内铆压。In the embodiment of the present invention, the transport assembly includes a plurality of conveyor belt complex AGV1, and the top of the conveyor belt complex AGV1 is provided with a conveyor belt for conveying raw material pallets, thereby relying on the stacker 11 to transport the raw material pallets taken out of the raw material three-dimensional warehouse 12 to the raw material conveyor belt 13, transported by the raw material conveyor belt 13 to the conveyor belt composite AGV1, and then transported to the idle tray conveyor belt 2 for corresponding assembly operations. Preferably, the front side of the riveting press 5 is also provided with a riveting conveyor belt 4, The seven-axis manipulator 6, the assembled bearing is transported by the conveyor belt compound AGV1 to the riveting conveyor belt 4 for loading, and then the seven-axis manipulator 6 grabs it and enters the riveting press 5 for riveting.

在本发明的实施例中,运输组件还包括机械臂复合AGV9,机械臂复合AGV9顶端设有多自由度的协作机械臂,协作机械臂末端装设有电磁吸盘,得电产生电磁吸附,用于抓取包装好的轴承,从而搬运打包好的轴承至成品立体库10上放置。In an embodiment of the present invention, the transport assembly also includes a composite manipulator AGV9, a multi-degree-of-freedom cooperative robot arm is provided at the top of the composite robot AGV9, and an electromagnetic chuck is installed at the end of the cooperative robot arm, which is powered to generate electromagnetic adsorption for Catch the packed bearings, thereby transporting the packed bearings to the finished product three-dimensional warehouse 10 for placement.

在本发明的实施例中,轴承装配台3上设有转运机械手304和操作机械手307,转运机械手304和操作机械手307末端装设有电磁夹爪,用于多型号轴承的抓取定位装配,通过传送带复合AGV1将原料经料盘传送带2送至转运机械手304取料处,转运机械手304将零件搬运至定型器305组装内圈外圈后,操作机械手307将部件取至灌珠器306,灌珠器306根据订单对轴承进行相应型号钢珠灌装,完成此项操作后送至分珠器303进行分珠,再由转运机械手304将保持架放置完成,转运机械手304将装配完成的轴承搬运至料盘传送带2,再由料盘传送带2将轴承输送给传送带复合AGV1上。In the embodiment of the present invention, a transfer manipulator 304 and an operation manipulator 307 are provided on the bearing assembly platform 3, and electromagnetic grippers are installed at the ends of the transfer manipulator 304 and the operation manipulator 307, which are used for grabbing and positioning assembly of multiple types of bearings. The conveyor belt compound AGV1 sends the raw materials to the transfer manipulator 304 pick-up place through the tray conveyor belt 2, and the transfer manipulator 304 transports the parts to the shaper 305 and assembles the inner and outer rings, and then operates the manipulator 307 to take the parts to the bead filling device 306, and fills the beads The machine 306 fills the bearing with steel balls of the corresponding type according to the order. After this operation is completed, it is sent to the bead separator 303 for bead separation, and then the transfer manipulator 304 completes the placement of the cage, and the transfer manipulator 304 transports the assembled bearing to the material. The disc conveyor belt 2, and then the bearing is transported to the conveyor belt composite AGV1 by the material tray conveyor belt 2.

在本发明的实施例中,钢珠下料机构14包括设于灌珠器顶端的料斗141,用于混装不同型号大小的钢珠,料斗141底部连接有料筒142,料筒142内轴心位置立设有挡柱143,挡柱143外侧与料筒142内侧之间形成环形的间隙,间隙内螺旋绕设有多条旋转滑道144,每条旋转滑道144底端开设有漏孔145,且由上至下的漏孔145孔径依次减小,以供不同型号大小的钢珠自动逐次下料。In the embodiment of the present invention, the steel ball unloading mechanism 14 includes a hopper 141 located at the top of the bead filling device for mixing steel balls of different sizes. A stop post 143 is provided, and an annular gap is formed between the outside of the stop post 143 and the inside of the barrel 142, and a plurality of rotating slides 144 are spirally wound in the gap, and a leak hole 145 is provided at the bottom of each rotating slide 144, and The hole diameters of the leakage holes 145 decrease successively from top to bottom, so that steel balls of different sizes are automatically fed successively.

在本发明的实施例中,各旋转滑道144顶端为位于料斗141与料筒142的连接处环形开口146,各环形开口146之间设有隔板147,各环形开口146的宽度与各旋转滑道144的漏孔孔径对应一致,从而料斗141内混装的钢珠沿各环形开口146对应向下漏料,即使尺寸小于环形开口146的钢珠落入该旋转滑道144,也会在螺旋向下滑落时,由漏孔145逐次再向下漏料,直至落至对应大小尺寸的旋转滑道144内,实现对应大小尺寸的钢珠由相应旋转滑道144落出装配。In the embodiment of the present invention, the top of each rotating slideway 144 is an annular opening 146 at the junction of the hopper 141 and the material barrel 142, and a partition 147 is arranged between each annular opening 146, and the width of each annular opening 146 is related to each rotation The hole diameters of the leak holes of the slideway 144 are correspondingly consistent, so that the mixed steel balls in the hopper 141 leak downward along the corresponding annular openings 146, even if the steel balls with a size smaller than the annular openings 146 fall into the rotating slideway 144, they will also flow in the spiral direction. When the bottom falls, the leakage hole 145 leaks material down successively until it falls into the rotating slideway 144 of corresponding size and size, so that the steel balls of corresponding size and size are dropped out of the corresponding rotating slideway 144 for assembly.

在本发明的实施例中,旋转滑道144尾端设有电磁阀门,装配时,对应旋转滑道144尾端处的电磁阀门打开,用于控制相应数量的钢珠下料,再自动合闭。In the embodiment of the present invention, an electromagnetic valve is provided at the tail end of the rotating slideway 144. During assembly, the electromagnetic valve at the tail end of the corresponding rotating slideway 144 is opened to control the feeding of a corresponding number of steel balls, and then automatically closed.

在本发明的实施例中,灌珠器306上设有用于带动料筒142振动下料的振动器148,以进一步利于钢珠的振动下料。In the embodiment of the present invention, the bead filling device 306 is provided with a vibrator 148 for driving the barrel 142 to vibrate and discharge the material, so as to further facilitate the vibration and discharge of the steel balls.

具体的,轴承装配台3上还设有示教器301、显示屏302,用于生产显示或教学演示,轴承装配台3上还设有控制板308,用于控制作业参数,铆压机5旁侧还设有用于存放不合格品的废品库7,以及用于打包作业的打包机8。Specifically, the bearing assembly platform 3 is also provided with a teaching pendant 301 and a display screen 302 for production display or teaching demonstration. The bearing assembly platform 3 is also provided with a control panel 308 for controlling operation parameters. The riveting press 5 The side is also provided with a waste warehouse 7 for depositing unqualified products, and a baler 8 for baling operations.

在本发明公开的一种轴承装配柔性生产线中,使用时,通过各轴承装配台3上均集成设置有灌珠器306、定型器305、分珠器303,同时灌珠器306顶端设有钢珠下料机构14,用于不同型号大小的钢珠自动逐次下料,若干个运输组件,待发出轴承装配指令,呼叫空闲的运输组件至原材料立体库12前,利用堆垛机11将原材料立体库12取出的原材料托盘运输至闲置的轴承装配台3上,经由定型器305组装内圈外圈,灌珠器306根据订单对轴承进行相应型号钢珠灌装,完成此项操作后送至分珠器303进行分珠并放置安装保持架,装配完成的轴承由运输组件搬运至铆压机5内铆压处理,并最终放置于成品立体库10上,完成轴承的柔性装配,同时进行不同型号的轴承产品的同时生产工作。In a flexible production line for bearing assembly disclosed by the present invention, when in use, each bearing assembly platform 3 is integrated with a bead filling device 306, a shaper 305, and a bead separator 303, and at the same time, steel balls are installed on the top of the bead filling device 306. The unloading mechanism 14 is used for automatic unloading of steel balls of different sizes one by one. Several transport components are waiting to issue a bearing assembly instruction, and call the idle transport components to the raw material three-dimensional warehouse 12, and use the stacker 11 to place the raw material three-dimensional warehouse 12 The raw material trays taken out are transported to the idle bearing assembly station 3, and the inner and outer rings are assembled through the shaper 305, and the bead filling device 306 fills the bearing with steel balls of the corresponding type according to the order, and sends it to the bead separator 303 after this operation is completed Beads are separated and the cage is placed and installed. The assembled bearing is transported by the transport component to the riveting machine 5 for internal riveting treatment, and finally placed on the finished product three-dimensional warehouse 10 to complete the flexible assembly of the bearing and carry out different types of bearing products at the same time simultaneous production work.

所属领域的普通技术人员应当理解:以上任何实施例的讨论仅为示例性的,并非旨在暗示本发明的范围(包括权利要求)被限于这些例子;在本发明的思路下,以上实施例或者不同实施例中的技术特征之间也可以进行组合,步骤可以以任意顺序实现,并存在如上所述的本发明的不同方面的许多其它变化,为了简明它们没有在细节中提供。Those of ordinary skill in the art should understand that: the discussion of any of the above embodiments is exemplary only, and is not intended to imply that the scope of the present invention (including claims) is limited to these examples; under the idea of the present invention, the above embodiments or Combinations between technical features in different embodiments are also possible, steps may be carried out in any order, and there are many other variations of the different aspects of the invention as described above, which are not presented in detail for the sake of brevity.

本发明旨在涵盖落入所附权利要求的宽泛范围之内的所有这样的替换、修改和变型。因此,凡在本发明的精神和原则之内,所做的任何省略、修改、等同替换、改进等,均应包含在本发明的保护范围之内。The present invention is intended to embrace all such alternatives, modifications and variations that fall within the broad scope of the appended claims. Therefore, any omissions, modifications, equivalent replacements, improvements, etc. within the spirit and principles of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1. The utility model provides a flexible production line of bearing assembly, includes the three-dimensional storehouse of raw and other materials that is used for storing the raw and other materials, is used for depositing the three-dimensional storehouse of finished product of bearing finished product, a stacker that is used for taking out raw and other materials tray in the three-dimensional storehouse of raw and other materials, a irritate pearl ware that is used for the steel ball to infuse, a calibrator that is used for bearing inner race, outer lane and steel ball fit assembly, a branch pearl ware that is used for the installation of the interior steel ball of bearing etc. and last holder after the cover, a riveting press that is used for dividing behind the pearl bearing and lower holder riveting, a serial communication port, still include:
the device comprises a plurality of bearing assembly tables, a ball filling device, a shaping device and a ball distributing device, wherein the bearing assembly tables are distributed in an arrayed manner, the ball filling device, the shaping device and the ball distributing device are integrated on each bearing assembly table, and a steel ball blanking mechanism is arranged at the top end of each ball filling device and is used for automatically and successively blanking steel balls of different types and sizes;
the transportation assembly is provided with a plurality of trays for transporting the raw material trays taken out of the raw material three-dimensional warehouse to an idle bearing assembly table for assembly.
2. The bearing assembling flexible production line of claim 1, wherein a tray conveyor is arranged on the front side of the bearing assembling table.
3. The bearing assembly flexible production line of claim 1, wherein a raw material conveying belt is arranged on the front side of the raw material three-dimensional warehouse.
4. The bearing assembly flexible production line of claim 1, wherein said transport assembly comprises a plurality of conveyor composite AGVs having a conveyor belt on top for conveying a raw material pallet.
5. The bearing assembling flexible production line of claim 1, wherein the transportation assembly further comprises a mechanical arm composite AGV, the top end of the mechanical arm composite AGV is provided with a multi-degree-of-freedom cooperative mechanical arm, and an electromagnetic chuck is arranged at the tail end of the cooperative mechanical arm, so that electricity is generated to generate electromagnetic adsorption for grabbing the packaged bearing.
6. The bearing assembling flexible production line of claim 1, wherein a transferring manipulator and an operating manipulator are arranged on the bearing assembling table, and electromagnetic clamping jaws are arranged at the tail ends of the transferring manipulator and the operating manipulator and used for grabbing, positioning and assembling of bearings of multiple models.
7. The bearing assembling flexible production line as claimed in claim 1, wherein the steel ball blanking mechanism comprises a hopper arranged at the top end of the steel ball filling device, a material cylinder is connected to the bottom of the hopper, a retaining column is vertically arranged in the material cylinder, an annular gap is formed between the outer side of the retaining column and the inner side of the material cylinder, a plurality of rotating slideways are spirally wound in the gap, a leakage hole is formed at the bottom end of each rotating slideway, and the diameters of the leakage holes from top to bottom are sequentially reduced so as to automatically and gradually blank steel balls of different types and sizes.
8. The flexible production line for bearing assembly according to claim 7, wherein the top end of each rotary slideway is an annular opening at the joint of the hopper and the charging barrel, a partition plate is arranged between the annular openings, and the width of each annular opening is correspondingly consistent with the aperture of a leak hole of each rotary slideway.
9. The flexible production line for bearing assembly according to claim 7, wherein an electromagnetic valve is arranged at the tail end of the rotating slideway and used for controlling the blanking of a corresponding number of steel balls.
10. The flexible production line for bearing assembly according to claim 7, wherein a vibrator for driving the charging barrel to vibrate and discharge is arranged on the bead filling device.
CN202210861253.2A 2022-07-20 2022-07-20 Flexible production line for bearing assembly Pending CN115325037A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210861253.2A CN115325037A (en) 2022-07-20 2022-07-20 Flexible production line for bearing assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210861253.2A CN115325037A (en) 2022-07-20 2022-07-20 Flexible production line for bearing assembly

Publications (1)

Publication Number Publication Date
CN115325037A true CN115325037A (en) 2022-11-11

Family

ID=83919843

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210861253.2A Pending CN115325037A (en) 2022-07-20 2022-07-20 Flexible production line for bearing assembly

Country Status (1)

Country Link
CN (1) CN115325037A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117515050A (en) * 2023-12-02 2024-02-06 江苏保捷精锻有限公司 Automatic bearing assembly production line and control method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4410871A1 (en) * 1994-03-29 1996-01-11 Tepcon Eng Gmbh Ball=sorting equipment according to size
CN205833631U (en) * 2016-07-19 2016-12-28 刘春涛 A kind of novel production steel ball industrial steel ball screening installation
CN206184776U (en) * 2016-11-09 2017-05-24 芜湖市永帆精密模具科技有限公司 A sorting device for mechanical parts
CN109372896A (en) * 2018-11-08 2019-02-22 昆山艾博机器人股份有限公司 A kind of bearing automatic assembling device
CN208786857U (en) * 2018-06-01 2019-04-26 合肥力和机械有限公司 A kind of sorting mechanism of bearing ball
CN210304583U (en) * 2019-08-19 2020-04-14 龙口市新达精密滚动体有限公司 Automatic screening device for wind power bearing steel balls
CN210585905U (en) * 2019-06-28 2020-05-22 宁波奉化精瑞钢球有限公司 Bearing steel ball screening device
CN112509450A (en) * 2020-11-19 2021-03-16 芜湖安普机器人产业技术研究院有限公司 Bearing automatic assembly teaching production line

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4410871A1 (en) * 1994-03-29 1996-01-11 Tepcon Eng Gmbh Ball=sorting equipment according to size
CN205833631U (en) * 2016-07-19 2016-12-28 刘春涛 A kind of novel production steel ball industrial steel ball screening installation
CN206184776U (en) * 2016-11-09 2017-05-24 芜湖市永帆精密模具科技有限公司 A sorting device for mechanical parts
CN208786857U (en) * 2018-06-01 2019-04-26 合肥力和机械有限公司 A kind of sorting mechanism of bearing ball
CN109372896A (en) * 2018-11-08 2019-02-22 昆山艾博机器人股份有限公司 A kind of bearing automatic assembling device
CN210585905U (en) * 2019-06-28 2020-05-22 宁波奉化精瑞钢球有限公司 Bearing steel ball screening device
CN210304583U (en) * 2019-08-19 2020-04-14 龙口市新达精密滚动体有限公司 Automatic screening device for wind power bearing steel balls
CN112509450A (en) * 2020-11-19 2021-03-16 芜湖安普机器人产业技术研究院有限公司 Bearing automatic assembly teaching production line

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
B.B.科希洛夫: "《装配工艺学原理与自动装配设备》", vol. 1, 31 December 1983, 中国农业机械出版社, pages: 137 - 141 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117515050A (en) * 2023-12-02 2024-02-06 江苏保捷精锻有限公司 Automatic bearing assembly production line and control method
CN117515050B (en) * 2023-12-02 2024-05-31 江苏保捷精锻有限公司 Automatic bearing assembly production line and control method

Similar Documents

Publication Publication Date Title
CN207971567U (en) Surface treatment machine equipped with assembly line, with rejecting function, automatic loading and unloading
CN202728597U (en) Boxing device for batteries-in-rows
CN114221013B (en) Explosion-proof plate assembly welding equipment for power battery cover
CN203490337U (en) Device for detecting electrical performance of diode/triode and rejecting defective products
CN108878952A (en) A kind of lithium battery automatic assembly line
JPH11165852A (en) Production system
CN102873752B (en) Automatic moulding and demoulding equipment for tubular products
US11834281B2 (en) Method for automated repalletizing of packaged goods
CN115325037A (en) Flexible production line for bearing assembly
CN115122065A (en) Control system and control method for bearing assembly flexible production line
KR20090126067A (en) Automated device for inputting raw materials and extracting molded lens, and method for inputting raw materials and extracting molded lens
CN215035135U (en) Planet carrier intelligence pressure round pin equipment
CN215390864U (en) A high-precision mobile phone sorting and assembling device
CN207683868U (en) A kind of metalwork automatic detecting packing equipment
CN205969720U (en) Automation equipment is carried to mold insert
CN212049464U (en) Full-automatic flexible glue dispensing production line
CN209430624U (en) A kind of bearing assembles flowing water processing line automatically
CN213064379U (en) Automatic assembly robot workstation of no holder bearing
CN217411557U (en) Full-automatic film detection boxing equipment
CN207155219U (en) A kind of automated exchanged cutter equipment
CN216036916U (en) Blade production line
CN114435938B (en) Automatic feeding system for valve body of regulating valve
CN215988904U (en) Flexible production system for power battery pack
US12208477B2 (en) Manufacturing machine to manufacture a product
CN113809406A (en) Flexible production system for power battery pack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination