[go: up one dir, main page]

CN115125838A - A kind of connectable cable and construction method - Google Patents

A kind of connectable cable and construction method Download PDF

Info

Publication number
CN115125838A
CN115125838A CN202210721998.9A CN202210721998A CN115125838A CN 115125838 A CN115125838 A CN 115125838A CN 202210721998 A CN202210721998 A CN 202210721998A CN 115125838 A CN115125838 A CN 115125838A
Authority
CN
China
Prior art keywords
cable
fixed
anchor
cable body
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210721998.9A
Other languages
Chinese (zh)
Inventor
唐军华
赵祥林
黄强盛
潘剑飞
叶明坤
谭国全
韦谋超
宋威
唐小丽
邓彩萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liuzhou Qiaoxia Engineering Co ltd
Liuzhou Qiaoxia Cable Product Co ltd
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Original Assignee
Liuzhou Qiaoxia Engineering Co ltd
Liuzhou Qiaoxia Cable Product Co ltd
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liuzhou Qiaoxia Engineering Co ltd, Liuzhou Qiaoxia Cable Product Co ltd, CRCC Harbour and Channel Engineering Bureau Group Co Ltd filed Critical Liuzhou Qiaoxia Engineering Co ltd
Priority to CN202210721998.9A priority Critical patent/CN115125838A/en
Publication of CN115125838A publication Critical patent/CN115125838A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种可接长缆索及施工方法,包括固定端锚具(1)和张拉端锚具(2),其特征在于:所述固定端锚具(1)与固定端索体(3)的固定端相固定,张拉端锚具(2)与张拉端索体(5)的固定端相固定,固定端索体(3)的连接端与张拉端索体(5)的连接端之间通过一段或多段可接长的中间索体(4)相连接固定,相邻中间索体(4)的端部之间以及中间索体(4)的端部与拉端索体(5)的连接端之间通过中间接头(6)进行连接固定,本发明结构合理,采用了可接长结构,能够根据实际需要灵活调整长度,在施工现场就能方便的进行接长固定,连接可靠,整体强度高,并且有利于安装挂篮,提高了施工效率,缩短了施工周期,方便维护,并能有效减少维护成本。

Figure 202210721998

A connectable cable and a construction method, comprising a fixed-end anchor (1) and a tension-end anchor (2), characterized in that: the fixed-end anchor (1) and the fixed-end cable body (3) are connected The fixed end is fixed, the tension end anchor (2) is fixed with the fixed end of the tension end cable body (5), the connection end of the fixed end cable body (3) and the connection end of the tension end cable body (5) They are connected and fixed by one or more lengthable intermediate cable bodies (4), between the ends of adjacent intermediate cable bodies (4) and between the ends of the intermediate cable bodies (4) and the pulling end cable body (5). ) connection ends are connected and fixed through the intermediate joint (6), the present invention has a reasonable structure, adopts a lengthable structure, can flexibly adjust the length according to actual needs, can be easily connected and fixed at the construction site, and the connection is reliable. , The overall strength is high, and it is conducive to the installation of hanging baskets, which improves the construction efficiency, shortens the construction period, facilitates maintenance, and can effectively reduce maintenance costs.

Figure 202210721998

Description

一种可接长缆索及施工方法A kind of connectable cable and construction method

技术领域technical field

本发明涉及一种缆索及施工方法,尤其涉及一种可接长缆索及施工方法,属于桥梁工程技术领域。The invention relates to a cable and a construction method, in particular to a connectable long cable and a construction method, belonging to the technical field of bridge engineering.

背景技术Background technique

一直以来,斜拉桥在进行桥梁架设施工时需要在桥塔的塔顶设铰接结构,并从桥塔处开始施工,分段浇筑或安装梁体节段,一段一段的向外延伸。在对各梁体节段的施工过程中需要搭建施工平台或施工挂篮装置,便于搭建模板和进行其它施工作业,需要安装临时拉索来承载施工平台或施工挂篮,施工时在施工平台或施工挂篮上搭建模板,再浇筑混凝土,在等待梁体节段的混凝土达到固化强度的同时安装永久索,当梁体节段的混凝土固化达到设计强度时,对永久索进行张拉,由永久索承担梁体节段的重量,实现了受力的体系转换。完成该梁体节段的施工后,将挂篮松开,向前移动到相邻的下一个梁体节段的施工位置,重复前面的梁体节段施工,依次类推完成梁体的建设。For a long time, the cable-stayed bridge needs to set up a hinged structure on the top of the pylon during the construction of the bridge truss, and start the construction from the pylon, pour or install the beam sections in sections, and extend out section by section. During the construction of each beam section, it is necessary to build a construction platform or a construction hanging basket device to facilitate the construction of formwork and other construction operations. It is necessary to install temporary cables to carry the construction platform or construction hanging basket. During construction, the construction platform or construction hanging Build the formwork on the basket, pour concrete, install the permanent cable while waiting for the concrete of the beam section to reach the curing strength. , to realize the system transformation of the force. After completing the construction of the beam body segment, loosen the hanging basket, move forward to the construction position of the next adjacent beam body segment, repeat the previous beam body segment construction, and so on to complete the beam body construction.

现有的拉索在工厂是按照定长生产的,出厂后按定长使用,锚具调整量较短,当需要较长或较短的拉索时,只能再生产,不仅费用高,生产周期较长,影响施工进度。而在实际使用过程中,对于不同跨度、不同高度的斜拉桥以及相同斜拉桥的不同部位对拉索的长度要求都不相同,而现有的拉索不能根据实际需要灵活调整长度,使用不太方便,该技术问题一直没能得到有效的解决。The existing cables are produced according to the fixed length in the factory. After leaving the factory, they are used according to the fixed length. The adjustment amount of the anchorage is short. When a longer or shorter cable is required, it can only be reproduced. longer, affecting the construction progress. In the actual use process, the length requirements of the cables are different for cable-stayed bridges with different spans and heights and different parts of the same cable-stayed bridge, and the existing cables cannot flexibly adjust the length according to actual needs. Inconvenient, this technical problem has not been effectively solved.

发明内容SUMMARY OF THE INVENTION

本发明的第一个目的是针对现有的斜拉桥使用的缆索为定长结构,不能根据实际需要灵活调整长度,使用不太方便,同时不利于安装挂篮,影响施工周期的缺陷和不足,本发明专利提供一种结构合理,采用了可接长结构,能够根据实际需要灵活调整长度,在施工现场就能方便的进行接长固定,连接可靠,整体强度高,并且有利于安装挂篮,提高了施工效率,缩短了施工周期的一种可接长缆索。The first purpose of the present invention is that the cables used in the existing cable-stayed bridges are fixed-length structures, the length cannot be flexibly adjusted according to actual needs, the use is inconvenient, it is not conducive to the installation of hanging baskets, and the defects and deficiencies that affect the construction period , The patent of the present invention provides a reasonable structure, adopts a lengthable structure, can flexibly adjust the length according to actual needs, can be easily connected and fixed at the construction site, has reliable connection, high overall strength, and is conducive to the installation of hanging baskets , which can improve the construction efficiency and shorten the construction period.

本发明的第二个目的是针对现有斜拉桥前支点挂篮施工方式需要不断调整缆索的长度,缆索不能根据实际需要灵活调整长度,施工周期长的缺陷和不足,提供一种安装方便,在施工现场就能方便的对缆索进行接长固定,整体强度高,稳定性好,能缩短施工周期的一种斜拉桥可接长缆索前支点挂篮施工方法。The second object of the present invention is to provide a convenient installation method for the defects and shortcomings of the existing cable-stayed bridge front fulcrum hanging basket construction method that needs to continuously adjust the length of the cables, the cables cannot be flexibly adjusted according to actual needs, and the construction period is long. The cable-stayed bridge can be easily connected and fixed at the construction site by lengthening and fixing, the overall strength is high, the stability is good, and the construction period of the cable-stayed bridge can be shortened.

本发明的第三个目的是针对现有体外预应力索体较长,在施工时穿索不方便,施工周期长,同时缆索不能根据实际需要灵活调整长度,维修更换时只能整体进行更换的缺陷和不足,提供一种安装方便,在施工现场就能方便进行分段穿索,并能对缆索进行接长固定,能缩短施工周期,并且在维修更换时,只需进行部分更换,不用进行整根全部更换,减小了维修成本的一种体外预应力可接长缆索施工方法。The third object of the present invention is that the existing external prestressed cable body is long, it is inconvenient to wear the cable during construction, and the construction period is long. At the same time, the length of the cable cannot be flexibly adjusted according to actual needs, and can only be replaced as a whole during maintenance and replacement. Defects and deficiencies, provide a convenient installation, can easily carry out segmented cable threading at the construction site, and can lengthen and fix the cables, which can shorten the construction period, and only need to replace part of the replacement when repairing and replacing. It is a construction method of external prestressed and connectable cables that can replace the whole cable and reduce the maintenance cost.

为实现上述第一个发明目的,本发明的技术解决方案是:一种可接长缆索,包括固定端锚具和张拉端锚具,其特征在于:所述固定端锚具与固定端索体的固定端相固定,张拉端锚具与张拉端索体的固定端相固定,固定端索体的连接端与张拉端索体的连接端之间通过一段或多段可接长的中间索体相连接固定,固定端索体的连接端与中间索体的端部之间、中间索体的端部之间以及中间索体的端部与拉端索体的连接端之间通过中间接头进行连接固定。In order to achieve the above-mentioned first purpose of the invention, the technical solution of the present invention is: a connectable cable, including a fixed end anchor and a tension end anchor, characterized in that: the fixed end anchor and the fixed end cable The fixed end of the cable body is fixed, the anchorage of the tension end is fixed with the fixed end of the cable body of the tension end, and the connecting end of the cable body of the fixed end and the connecting end of the cable body of the tension end are connected by one or more lengths. The intermediate cable bodies are connected and fixed, and the connection between the connecting end of the fixed end cable body and the end of the intermediate cable body, between the ends of the intermediate cable body, and between the end of the intermediate cable body and the connecting end of the pulling end cable body pass through. The intermediate joint is connected and fixed.

进一步的,所述固定端锚具包括锚杯、垫板、螺母以及锚具密封装置,固定端索体的固定端固定在锚杯内,锚杯上分别安装有垫板和螺母,锚杯外端的固定端索体上设置有锚具密封装置。Further, the fixed end anchor includes an anchor cup, a backing plate, a nut and an anchor sealing device, the fixed end of the fixed end cable body is fixed in the anchor cup, the backing plate and the nut are respectively installed on the anchor cup, and the outside of the anchor cup is An anchor sealing device is arranged on the fixed end cable body of the end.

进一步的,所述张拉端锚具包括锚杯、垫板、螺母以及锚具密封装置,固定端索体的固定端固定在锚杯内,锚杯上分别安装有垫板和螺母,锚杯外端的固定端索体上设置有锚具密封装置,锚杯内与固定端索体的连接部位设置有环氧或铝合金锚固体。Further, the tension end anchor includes an anchor cup, a backing plate, a nut and an anchor sealing device, the fixed end of the fixed end cable body is fixed in the anchor cup, and the backing plate and the nut are respectively installed on the anchor cup. An anchor sealing device is arranged on the fixed end cable body at the outer end, and epoxy or aluminum alloy anchors are arranged in the connection part of the anchor cup and the fixed end cable body.

进一步的,所述固定端索体、中间索体或者张拉端索体采用平行钢丝缆索、钢绞线索、挤压缆索、钢拉杆、钢丝绳索或碳纤维索中的一种或任意两种以上的组合。Further, the fixed end cable body, the intermediate cable body or the tension end cable body adopts one or any two or more of parallel wire cables, steel strand cables, extruded cables, steel tie rods, steel wire ropes or carbon fiber cables. combination.

进一步的,所述中间接头包括接头套、接头拉杆、接头筒以及接头塞,中间索体的一端固定有接头套,与之连接的相邻的一根中间索体的一端固定有接头塞,接头套与接头拉杆的一端相连接,接头拉杆的另一端通过接头筒与接头塞相连接。Further, the intermediate joint includes a joint sleeve, a joint tie rod, a joint cylinder and a joint plug, one end of the intermediate cable body is fixed with a joint sleeve, and one end of an adjacent intermediate cable body connected to it is fixed with a joint plug, and the joint is fixed. The sleeve is connected with one end of the joint pull rod, and the other end of the joint pull rod is connected with the joint plug through the joint barrel.

进一步的,所述中间接头包括锚具、耳板以及销轴,固定端索体、中间索体或者张拉端索体的一端与锚具相固定,锚具通过销轴与耳板相连接。Further, the intermediate joint includes an anchor, an ear plate and a pin, one end of the fixed end cable body, the intermediate cable body or the tension end cable body is fixed with the anchor, and the anchor is connected with the ear plate through the pin.

进一步的,所述中间接头包括锚具、耳板、叉耳以及叉耳销轴,固定端索体、中间索体或者张拉端索体的一端与锚具相固定,锚具与叉耳连接固定,叉耳通过叉耳销轴与耳板相连接。Further, the intermediate joint includes an anchor, an ear plate, a fork lug and a fork lug pin, one end of the fixed end cable body, the intermediate cable body or the tension end cable body is fixed with the anchor, and the anchor is connected with the fork lug. The fork lug is connected with the lug plate through the fork lug pin shaft.

进一步的,所述固定端索体、中间索体或者张拉端索体由钢绞线为索股而制成,钢绞线采用光面钢绞线、镀锌钢绞线、镀锌铝钢绞线或无粘结钢绞线,并且索股的外表面设置有钢绞线护套或缠绕包带,索体的外表面设置有双层外护套或缠绕包带。Further, the fixed end cable body, the intermediate cable body or the tension end cable body are made of steel strands as cable strands, and the steel strands are made of smooth steel strands, galvanized steel strands, galvanized aluminum steel Stranded wire or unbonded steel strand, and the outer surface of the cable strand is provided with a steel strand sheath or wrapping tape, and the outer surface of the cable body is provided with a double-layer outer sheath or wrapping tape.

为实现上述第二个发明目的,本发明的技术解决方案是:一种可接长缆索施工方法,其特征在于包括以下步骤:In order to achieve the above-mentioned second purpose of the invention, the technical solution of the present invention is: a construction method for connecting a long cable, which is characterized by comprising the following steps:

a、首先在桥塔安装固定端锚具和固定端索体;a. First, install the fixed end anchorage and the fixed end cable body on the bridge tower;

b、随后通过中间接头依次以接长的方式一根或多根中间索体;b. One or more intermediate cable bodies are then connected in sequence through intermediate joints in a manner of lengthening;

c、接着将位于最下方的中间索体通过中间接头与张拉端索体的一端连接固定,并将张拉端索体的另一端通过张拉端锚具与梁体节段进行连接固定;c. Next, connect and fix the lowermost intermediate cable body with one end of the tension end cable body through the intermediate joint, and connect and fix the other end of the tension end cable body with the beam body segment through the tension end anchor;

d、从桥塔处开始依次安装多根可接长缆索,并安装挂篮,建立施工阶段的临时受力体系,在挂篮上搭建模板,浇筑梁体节段的混凝土;d. From the bridge tower, install multiple cables that can be connected in sequence, and install hanging baskets to establish a temporary stress system during the construction stage, build templates on the hanging baskets, and pour concrete for the beam sections;

e、每完成一段浇筑梁体节段的施工就依次前移挂篮,依次类推完成全部梁体的施工;e. Each time the construction of a pouring beam body segment is completed, the hanging basket is moved forward in turn, and the construction of all beam bodies is completed by analogy;

f、在等待梁体节段上的混凝土凝固的同时,进行永久索的安装施工,对永久索进行张拉,使得永久索承担梁体节段的重量,实现了受力体系的转换,完成施工。f. While waiting for the concrete on the beam body segment to solidify, the installation and construction of the permanent cable are carried out, and the permanent cable is tensioned so that the permanent cable bears the weight of the beam body segment, realizes the conversion of the force system, and completes the construction.

为实现上述第三个发明目的,本发明的技术解决方案是:一种体外预应力可接长缆索施工方法,其特征在于包括以下步骤:In order to achieve the above-mentioned third purpose of the invention, the technical solution of the present invention is: a construction method for externally prestressed extendable cables, which is characterized by comprising the following steps:

a、首先预留或预埋安装锚箱,并安装一个或多个转向器;a. First reserve or pre-embed the anchor box, and install one or more diverters;

b、再向转向器内分段穿入中间索体,并依次将各个中间索体之间通过中间接头进行连接固定,形成长缆索;b. The intermediate cable bodies are penetrated in sections into the steering gear, and the intermediate cable bodies are connected and fixed through the intermediate joints in turn to form a long cable;

c、然后安装锚具,将长缆索固定在锚具上;c. Then install the anchor, and fix the long cable on the anchor;

d、最后对长缆索进行张拉,完成预应力张拉。d. Finally, the long cable is tensioned to complete the prestress tension.

一种采用可接长缆索的桥梁拉索施工方法,其特征在于包括以下步骤:A bridge cable construction method using connectable cables, which is characterized by comprising the following steps:

a、首先在实际长度不够的桥梁拉索上通过中间接头依次连接固定一段或多段中间索体,或者整段桥梁拉索都采用可接长缆索连接固定而成;a. First, connect and fix one or more sections of intermediate cables on the bridge cables with insufficient actual length through intermediate joints in turn, or the entire bridge cables are connected and fixed by connectable cables;

b、然后安装锚具,将桥梁拉索固定在锚具上;b. Then install the anchor, and fix the bridge cable on the anchor;

c、最后对桥梁拉索进行张拉,完成可接长缆索的安装。c. Finally, tension the bridge cable to complete the installation of the connectable cable.

本发明的有益效果是:The beneficial effects of the present invention are:

1.本发明的索体有位于端部的固定端索体和张拉端索体以及位于中部的多段式中间索体构成,中间索体之间通过中间接头连接固定,连接固定后形成了与传统单根定长式缆索性能相同的索体结构。1. The cable body of the present invention is composed of a fixed end cable body and a tension end cable body located at the end and a multi-section intermediate cable body located in the middle. The intermediate cable bodies are connected and fixed by intermediate joints. The cable body structure with the same performance as the fixed-length cable.

2.本发明采用了中间接头实现了固定端索体的连接端与中间索体的端部之间、中间索体的端部之间以及中间索体的端部与拉端索体的连接端之间的有效连接固定,保证了各索体之间连接固定的牢固性。2. The invention adopts the intermediate joint to realize the connection between the connecting end of the fixed end cable body and the end of the intermediate cable body, between the ends of the intermediate cable body, and between the end of the intermediate cable body and the connecting end of the pulling end cable body The effective connection and fixation ensures the firmness of the connection and fixation between the cable bodies.

3.本发明改进了传统前支点挂篮的施工方法,借助于可接长缆索极大地方便了施工,不需要频发更换缆索,在现场就能够进行接长固定,有利于浇筑梁体节段的施工和受力体系的转换。另外,对于体外预应力索体在施工现场就能方便进行分段穿索,并能对缆索进行接长固定,能缩短施工周期,并且在维修更换时,只需进行部分更换,不用进行整根全部更换,减小了维修成本。3. The invention improves the traditional construction method of the front fulcrum hanging basket, greatly facilitates construction by means of the connectable length cables, does not need to replace the cables frequently, can be connected and fixed on site, and is beneficial to the construction and acceptance of the pouring beam body segments. transformation of the force system. In addition, the external prestressed cable body can be easily threaded in sections at the construction site, and the cable can be lengthened and fixed, which can shorten the construction period, and when repairing and replacing, only a part of the cable needs to be replaced instead of the entire cable. All replacement, reducing maintenance costs.

4.本发明结构合理,采用了可接长结构,能够根据实际需要灵活调整长度,在施工现场就能方便的进行接长固定,连接可靠,整体强度高,并且有利于安装挂篮,提高了施工效率,缩短了施工周期。4. The invention has a reasonable structure, adopts an extendable structure, can flexibly adjust the length according to actual needs, can be easily extended and fixed on the construction site, has reliable connection, high overall strength, and is conducive to the installation of hanging baskets and improves construction efficiency. , shorten the construction period.

附图说明Description of drawings

图1是本发明的结构示意图。Figure 1 is a schematic structural diagram of the present invention.

图2是本发明的结构简图。Figure 2 is a schematic diagram of the structure of the present invention.

图3是本发明固定端锚具的结构示意图。FIG. 3 is a schematic structural diagram of a fixed end anchor of the present invention.

图4是本发明张拉端锚具的结构示意图。FIG. 4 is a schematic structural diagram of the tension end anchor of the present invention.

图5是本发明中间接头第一种实施方式的结构示意图。FIG. 5 is a schematic structural diagram of the first embodiment of the intermediate joint of the present invention.

图6是本发明中间接头第二种实施方式的结构示意图。FIG. 6 is a schematic structural diagram of the second embodiment of the intermediate joint of the present invention.

图7是本发明中间接头第三种实施方式的结构示意图。Fig. 7 is a schematic structural diagram of the third embodiment of the intermediate joint of the present invention.

图8是本发明索体第一种实施方式的结构示意图。FIG. 8 is a schematic structural diagram of the first embodiment of the cable body of the present invention.

图9是本发明索体第二种实施方式的结构示意图。FIG. 9 is a schematic structural diagram of the second embodiment of the cable body of the present invention.

图10是本发明索体第三种实施方式的结构示意图。FIG. 10 is a schematic structural diagram of the third embodiment of the cable body of the present invention.

图11是本发明前支点挂篮施工状态图。Figure 11 is a construction state diagram of the front fulcrum hanging basket of the present invention.

图12是本发明体外预应力缆索的施工状态图。Fig. 12 is a construction state diagram of the external prestressed cable of the present invention.

图13是本发明可接长缆索的施工状态图。Fig. 13 is a construction state view of the connectable cable of the present invention.

图中:固定端锚具1,张拉端锚具2,固定端索体3,中间索体4,张拉端索体5,中间接头6,接头套7,接头拉杆8,接头筒9,接头塞10,锚具11,耳板12,销轴13,叉耳14,叉耳销轴15,钢绞线16,钢绞线护套17,外护套18,高强聚酯带19,缠绕包带20,锚杯21,垫板22,螺母23,锚具密封装置24,桥塔25,永久索26,梁体节段27,挂篮28,转向器29。In the figure: fixed end anchorage 1, tensioned end anchorage 2, fixed end cable body 3, intermediate cable body 4, tensioned end cable body 5, intermediate joint 6, joint sleeve 7, joint tie rod 8, joint barrel 9, Joint plug 10, anchor 11, lug plate 12, pin 13, fork lug 14, fork lug pin 15, steel strand 16, steel strand sheath 17, outer sheath 18, high-strength polyester tape 19, winding Tape 20, anchor cup 21, backing plate 22, nut 23, anchor seal 24, bridge tower 25, permanent cable 26, beam body segment 27, hanging basket 28, diverter 29.

具体实施方式Detailed ways

以下结合附图说明和具体实施方式对本发明作进一步的详细描述。The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

参见图1至图13,本发明的一种可接长缆索,包括固定端锚具1和张拉端锚具2,其特征在于:所述固定端锚具1与固定端索体3的固定端相固定,张拉端锚具2与张拉端索体5的固定端相固定,固定端索体3的连接端与张拉端索体5的连接端之间通过一段或多段可接长的中间索体4相连接固定,固定端索体3的连接端与中间索体4的端部之间、中间索体4的端部之间以及中间索体4的端部与拉端索体5的连接端之间通过中间接头6进行连接固定。1 to 13 , a connectable cable of the present invention includes a fixed end anchor 1 and a tensioned end anchor 2, and is characterized in that: the fixed end anchor 1 and the fixed end cable body 3 are fixed The ends are fixed, the tension end anchor 2 is fixed with the fixed end of the tension end cable body 5, and the connection end of the fixed end cable body 3 and the connection end of the tension end cable body 5 can be connected by one or more sections. The intermediate cable bodies 4 are connected and fixed, between the connecting end of the fixed end cable body 3 and the end of the intermediate cable body 4, between the ends of the intermediate cable body 4, and between the end of the intermediate cable body 4 and the pulling end cable body The connection ends of 5 are connected and fixed through the intermediate joint 6 .

所述固定端锚具1包括锚杯21、垫板22、螺母23以及锚具密封装置24,固定端索体3的固定端固定在锚杯21内,锚杯21上分别安装有垫板22和螺母23,锚杯21外端的固定端索体3上设置有锚具密封装置24。The fixed end anchor 1 includes an anchor cup 21, a backing plate 22, a nut 23 and an anchor sealing device 24. The fixed end of the fixed end cable body 3 is fixed in the anchor cup 21, and backing plates 22 are respectively installed on the anchor cups 21. And the nut 23, the fixed end cable body 3 at the outer end of the anchor cup 21 is provided with an anchor seal device 24.

所述张拉端锚具2包括锚杯21、垫板22、螺母23以及锚具密封装置24,固定端索体3的固定端固定在锚杯21内,锚杯21上分别安装有垫板22和螺母23,锚杯21外端的固定端索体3上设置有锚具密封装置24,锚杯21内与固定端索体3的连接部位设置有环氧或铝合金锚固体。The tension end anchor 2 includes an anchor cup 21, a backing plate 22, a nut 23 and an anchor sealing device 24, the fixed end of the fixed end cable body 3 is fixed in the anchor cup 21, and the backing plate is respectively installed on the anchor cup 21 22 and nut 23, the fixed end cable body 3 at the outer end of the anchor cup 21 is provided with an anchor sealing device 24, and the connection part in the anchor cup 21 with the fixed end cable body 3 is provided with an epoxy or aluminum alloy anchor.

所述固定端索体3、中间索体4或者张拉端索体5采用平行钢丝缆索、钢绞线索、挤压缆索、钢拉杆、钢丝绳索或碳纤维索中的一种或任意两种以上的组合。The fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 adopts one or any two or more of parallel wire cables, steel strand cables, extruded cables, steel tie rods, steel wire ropes or carbon fiber cables. combination.

所述中间接头6包括接头套7、接头拉杆8、接头筒9以及接头塞10,中间索体4的一端固定有接头套7,与之连接的相邻的一根中间索体4的一端固定有接头塞10,接头套7与接头拉杆8的一端相连接,接头拉杆8的另一端通过接头筒9与接头塞10相连接。The intermediate joint 6 includes a joint sleeve 7, a joint pull rod 8, a joint cylinder 9 and a joint plug 10. One end of the intermediate cable body 4 is fixed with a joint sleeve 7, and one end of an adjacent intermediate cable body 4 connected to it is fixed. There is a joint plug 10 , the joint sleeve 7 is connected with one end of the joint pull rod 8 , and the other end of the joint pull rod 8 is connected with the joint plug 10 through the joint cylinder 9 .

所述中间接头6包括锚具11、耳板12以及销轴13,固定端索体3、中间索体4或者张拉端索体5的一端与锚具11相固定,锚具11通过销轴13与耳板12相连接。The intermediate joint 6 includes an anchor 11 , an ear plate 12 and a pin shaft 13 . One end of the fixed end cable body 3 , the intermediate cable body 4 or the tension end cable body 5 is fixed with the anchor device 11 , and the anchor device 11 passes through the pin shaft. 13 is connected to the ear plate 12 .

所述中间接头6包括锚具11、耳板12、叉耳14以及叉耳销轴15,固定端索体3、中间索体4或者张拉端索体5的一端与锚具11相固定,锚具11与叉耳14连接固定,叉耳14通过叉耳销轴15与耳板12相连接。The intermediate joint 6 includes an anchor 11, an ear plate 12, a fork lug 14 and a fork lug pin 15, and one end of the fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 is fixed with the anchor device 11, The anchor 11 is connected and fixed with the fork lug 14 , and the fork lug 14 is connected with the lug plate 12 through the fork lug pin shaft 15 .

所述固定端索体3、中间索体4或者张拉端索体5由钢绞线16为索股而制成,钢绞线16采用光面钢绞线、镀锌钢绞线、镀锌铝钢绞线或无粘结钢绞线,并且索股的外表面设置有钢绞线护套17或缠绕包带,索体的外表面设置有双层外护套18或缠绕包带20。The fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 are made of steel strands 16 as cable strands, and the steel strands 16 are made of smooth steel strands, galvanized steel strands, galvanized steel strands, etc. Aluminum steel strand or unbonded steel strand, and the outer surface of the strand is provided with a steel strand sheath 17 or wrapping tape, and the outer surface of the cable body is provided with a double outer sheath 18 or wrapping tape 20 .

一种可接长缆索施工方法,其特征在于包括以下步骤:A construction method for a connectable cable, characterized by comprising the following steps:

a、首先在桥塔25安装固定端锚具1和固定端索体3;a. First, install the fixed end anchorage 1 and the fixed end cable body 3 on the bridge tower 25;

b、随后通过中间接头6依次以接长的方式一根或多根中间索体4;b. One or more intermediate cable bodies 4 are subsequently extended in sequence through the intermediate joint 6;

c、接着将位于最下方的中间索体4通过中间接头6与张拉端索体5的一端连接固定,并将张拉端索体5的另一端通过张拉端锚具2与梁体节段27进行连接固定;c. Next, connect and fix the lowermost intermediate cable body 4 with one end of the tension end cable body 5 through the intermediate joint 6, and connect the other end of the tension end cable body 5 to the beam body segment 27 through the tension end anchor 2 connect and fix;

d、从桥塔25处开始依次安装多根可接长缆索,并安装挂篮28,建立施工阶段的临时受力体系,在挂篮28上搭建模板,浇筑梁体节段27的混凝土;d, from the bridge tower 25, install a plurality of cables that can be connected in sequence, and install the hanging basket 28 to establish a temporary stress system in the construction stage, build a template on the hanging basket 28, and pour the concrete of the beam body segment 27;

e、每完成一段浇筑梁体节段27的施工就依次前移挂篮28,依次类推完成全部梁体的施工;e. Move the hanging basket 28 forward in turn every time the construction of a casted beam body segment 27 is completed, and so on to complete the construction of all the beam bodies;

f、在等待梁体节段27上的混凝土凝固的同时,进行永久索26的安装施工,对永久索26进行张拉,使得永久索26承担梁体节段27的重量,实现了受力体系的转换,完成施工。f. While waiting for the concrete on the beam body section 27 to solidify, the installation and construction of the permanent cable 26 is carried out, and the permanent cable 26 is tensioned, so that the permanent cable 26 bears the weight of the beam body section 27, and the conversion of the force-bearing system is realized. construction.

一种体外预应力可接长缆索施工方法,其特征在于包括以下步骤:A construction method for externally prestressed connectable cables, characterized by comprising the following steps:

a、首先预留或预埋安装锚箱,并安装一个或多个转向器29;a. First reserve or pre-embed the anchor box, and install one or more diverters 29;

b、再向转向器29内分段穿入中间索体4,并依次将各个中间索体4之间通过中间接头6进行连接固定,形成长缆索;b. Insert the intermediate cable bodies 4 into the diverter 29 in sections, and connect and fix the intermediate cable bodies 4 through the intermediate joints 6 in turn to form a long cable;

c、然后安装锚具,将长缆索固定在锚具上;c. Then install the anchor, and fix the long cable on the anchor;

d、最后对长缆索进行张拉,完成预应力张拉。d. Finally, the long cable is tensioned to complete the prestress tension.

一种采用可接长缆索的桥梁拉索施工方法,其特征在于包括以下步骤:A bridge cable construction method using connectable cables, which is characterized by comprising the following steps:

a、首先在实际长度不够的桥梁拉索上通过中间接头6依次连接固定一段或多段中间索体4,或者整段桥梁拉索都采用可接长缆索连接固定而成;a. First, connect and fix one or more sections of intermediate cable bodies 4 on the bridge cables with insufficient actual length through the intermediate joints 6 in turn, or the entire bridge cables are connected and fixed by connectable cables;

b、然后安装锚具,将桥梁拉索固定在锚具上;b. Then install the anchor, and fix the bridge cable on the anchor;

c、最后对桥梁拉索进行张拉,完成可接长缆索的安装。c. Finally, tension the bridge cable to complete the installation of the connectable cable.

参见说明书附图,本发明与传统整根式缆索不同,采用的是可以根据实际需要进行连接加长的可接长缆索,在施工现场按照需要接长到所需要的长度。本发明的索体部分主要包括位于一端的单根固定端索体3、位于中间的一根或多根中间索体4以及位于另一端的单根张拉端索体5,能根据需要进行接长的部分主要体现在中间索体4上,中间索体4采用多段式结构,每段中间索体4的长度不大于1000米。Referring to the accompanying drawings in the description, the present invention is different from the traditional integral cable in that it adopts an extendable cable that can be connected and lengthened according to actual needs, and can be lengthened to the required length on the construction site as required. The cable body part of the present invention mainly includes a single fixed end cable body 3 at one end, one or more intermediate cable bodies 4 at the middle, and a single tension end cable body 5 at the other end, which can be connected as required. The long part is mainly reflected in the intermediate cable body 4, which adopts a multi-section structure, and the length of each intermediate cable body 4 is not more than 1000 meters.

固定端索体3、中间索体4或者张拉端索体5可采用平行钢丝缆索、钢绞线索、挤压缆索、钢拉杆、钢丝绳索或碳纤维索等索结构中的一种或两种以上的组合,索体的外表面采用了防护或防护措施,具体防护或防腐结构可以是塑料管、热挤包塑料管或者金属管,塑料管不仅限于HDPE、PE、PP、PE。索股采用光面钢绞线、镀锌钢绞线、镀锌铝钢绞线、无粘结钢绞线或其它类型的绞线,钢丝或钢绞线采用防腐方式或无防腐方式,采用防腐时,具体可以采用环氧树脂、镀锌或镀锌铝、镀高钒、防腐油脂或防腐蜡中的一种或其中任意两种以上的组合。另外,在索股的外表面设置有钢绞线护套17或缠绕包带,索体的外表面设置有单层外护套、双层外护套18或缠绕包带20,还可以缠绕设置高强聚酯带19。The fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 can adopt one or more of the cable structures such as parallel wire cables, steel strand cables, extruded cables, steel tie rods, steel wire ropes or carbon fiber cables. The outer surface of the cable body adopts protective or protective measures. The specific protective or anti-corrosion structure can be a plastic pipe, a hot-extruded plastic pipe or a metal pipe. The plastic pipe is not limited to HDPE, PE, PP, PE. The cable strands are made of smooth steel strands, galvanized steel strands, galvanized aluminum steel strands, unbonded steel strands or other types of strands. Specifically, one or a combination of any two or more of epoxy resin, galvanized or galvanized aluminum, high vanadium plating, anti-corrosion grease or anti-corrosion wax can be used. In addition, the outer surface of the cable strand is provided with a steel strand sheath 17 or a wrapping tape, and the outer surface of the cable body is provided with a single-layer outer sheath, a double-layer outer sheath 18 or a wrapping tape 20, which can also be wrapped around High-strength polyester tape 19.

固定端索体3的固定端与固定端锚具1相固定,固定端锚具1可以采用多种结构形式,典型的固定端锚具1包括锚杯21、垫板22、螺母23以及锚具密封装置24,固定端索体3的固定端固定在锚杯21内,锚杯21上分别安装有垫板22和螺母23,锚杯21外端的固定端索体3上设置有锚具密封装置24。固定端索体3与固定端索体3之间可以采用夹片式锚固、环氧砂浆式、挤压式、灌注合金式固定方式中的一种或多种组合。The fixed end of the fixed end cable body 3 is fixed with the fixed end anchor 1. The fixed end anchor 1 can adopt various structural forms. A typical fixed end anchor 1 includes an anchor cup 21, a backing plate 22, a nut 23 and an anchor. The sealing device 24, the fixed end of the fixed end cable body 3 is fixed in the anchor cup 21, the backing plate 22 and the nut 23 are respectively installed on the anchor cup 21, and the fixed end cable body 3 at the outer end of the anchor cup 21 is provided with an anchor sealing device twenty four. One or more combinations of clip-type anchoring, epoxy mortar type, extrusion type, and pouring alloy fixing methods may be adopted between the fixed end cable body 3 and the fixed end cable body 3 .

张拉端索体5的固定端与张拉端锚具2相固定,张拉端锚具2可以采用多种结构形式,典型的张拉端锚具2包括锚杯21、垫板22、螺母23以及锚具密封装置24,固定端索体3的固定端固定在锚杯21内,锚杯21上分别安装有垫板22和螺母23,锚杯21外端的固定端索体3上设置有锚具密封装置24,锚杯21内与固定端索体3的连接部位设置有环氧或铝合金锚固体。The fixed end of the tension end cable body 5 is fixed with the tension end anchor 2. The tension end anchor 2 can adopt various structural forms. A typical tension end anchor 2 includes an anchor cup 21, a backing plate 22, and a nut. 23 and the anchoring device sealing device 24, the fixed end of the fixed end cable body 3 is fixed in the anchor cup 21, the anchor cup 21 is respectively installed with a backing plate 22 and a nut 23, and the fixed end cable body 3 at the outer end of the anchor cup 21 is provided with a The anchoring device sealing device 24 and the connection part of the anchor cup 21 and the fixed end cable body 3 are provided with epoxy or aluminum alloy anchors.

固定端索体3的连接端与张拉端索体5的连接端之间通过一段或多段可接长的中间索体4相连接固定。固定端索体3的连接端与中间索体4的端部之间、中间索体4的端部之间以及中间索体4的端部与拉端索体5的连接端之间都通过中间接头6进行连接固定,中间接头6保证了各索体之间连接固定的牢固性。中间接头6可以采用多种结构形式,主要包括以下几种实施方式:The connection end of the cable body 3 at the fixed end and the connection end of the cable body 5 at the tension end are connected and fixed by one or more lengths of intermediate cable bodies 4 . Between the connecting end of the fixed end cable body 3 and the end of the intermediate cable body 4, between the ends of the intermediate cable body 4 and between the end of the intermediate cable body 4 and the connecting end of the pulling end cable body 5 all pass through the middle. The joint 6 is connected and fixed, and the intermediate joint 6 ensures the firmness of the connection and fixation between the cable bodies. The intermediate joint 6 can adopt various structural forms, mainly including the following embodiments:

实施例1:中间接头6包括接头套7、接头拉杆8、接头筒9以及接头塞10,中间索体4的一端固定有接头套7,与之连接的相邻的一根中间索体4的一端固定有接头塞10,接头套7与接头拉杆8的一端相连接,接头拉杆8的另一端通过接头筒9与接头塞10相连接。Example 1: The intermediate joint 6 includes a joint sleeve 7, a joint pull rod 8, a joint cylinder 9 and a joint plug 10. One end of the intermediate cable body 4 is fixed with the joint sleeve 7, and the adjacent intermediate cable body 4 connected to it has a joint sleeve 7. One end is fixed with a joint plug 10 , the joint sleeve 7 is connected with one end of the joint pull rod 8 , and the other end of the joint pull rod 8 is connected with the joint plug 10 through the joint cylinder 9 .

实施例2:中间接头6包括锚具11、耳板12以及销轴13,固定端索体3、中间索体4或者张拉端索体5的一端与锚具11相固定,端索体5的一端在锚具11中形成分叉以提高锚固强度,锚具11通过销轴13与耳板12相连接。Example 2: The intermediate joint 6 includes an anchor 11, an ear plate 12 and a pin shaft 13, one end of the fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 is fixed with the anchor tool 11, and the end cable body 5 One end of the anchoring device 11 forms a bifurcation to improve the anchoring strength, and the anchoring device 11 is connected with the ear plate 12 through the pin shaft 13 .

实施例3:中间接头6包括锚具11、耳板12、叉耳14以及叉耳销轴15,固定端索体3、中间索体4或者张拉端索体5的一端与锚具11相固定,端索体5的一端在锚具11中形成分叉以提高锚固强度,锚具11与叉耳14连接固定,叉耳14通过叉耳销轴15与耳板12相连接。Embodiment 3: The intermediate joint 6 includes the anchor 11, the lug plate 12, the fork lug 14 and the fork lug pin 15, and one end of the fixed end cable body 3, the intermediate cable body 4 or the tension end cable body 5 is connected to the anchor device 11. For fixing, one end of the end cable body 5 forms a bifurcation in the anchor 11 to improve the anchoring strength. The anchor 11 is connected and fixed with the fork lug 14, and the fork lug 14 is connected with the lug plate 12 through the fork lug pin 15.

本发明斜拉桥可接长缆索前支点挂篮施工的施工步骤和方法如下:首先在桥塔25安装固定端锚具1和固定端索体3,随后通过中间接头6依次以接长的方式一根或多根中间索体4。从桥塔25处开始依次安装多根可接长缆索,并安装挂篮28,建立施工阶段的临时受力体系,在挂篮28上搭建模板,浇筑梁体节段27的混凝土,每完成一段浇筑梁体节段27的施工就依次前移挂篮28,依次类推完成全部梁体的施工。在等待梁体节段27上的混凝土凝固的同时,进行永久索26的安装施工,对永久索26进行张拉,使得永久索26承担梁体节段27的重量,实现了受力体系的转换,完成施工。The construction steps and method of the hanging basket construction at the front fulcrum of the cable-stayed bridge of the present invention that can be connected with long cables are as follows: firstly, the fixed end anchorage 1 and the fixed end cable body 3 are installed on the bridge tower 25, and then the intermediate joints 6 are successively connected in a way of lengthening. One or more intermediate cable bodies 4 . From the bridge tower 25, install a plurality of cables that can be connected in sequence, and install the hanging basket 28 to establish a temporary stress system during the construction stage, build a formwork on the hanging basket 28, and pour the concrete of the beam body section 27. For the construction of section 27, the hanging basket 28 is moved forward in turn, and so on to complete the construction of all beam bodies. While waiting for the concrete on the beam body segment 27 to solidify, the installation and construction of the permanent cable 26 is carried out, and the permanent cable 26 is tensioned so that the permanent cable 26 bears the weight of the beam body segment 27, realizing the conversion of the force system and completing the construction.

本发明可接长缆索施工方法的施工步骤和方法如下:首先预留或预埋安装锚箱,并安装一个或多个转向器29,再向转向器29内分段穿入中间索体4,并依次将各个中间索体4之间通过中间接头6进行连接固定,形成长缆索,还可以在长缆索的一端固定连接固定端锚具1,在长缆索的另一端安装固定张拉端锚具2,然后安装锚具,将长缆索固定在锚具上。最后对长缆索进行张拉,完成预应力张拉。The construction steps and methods of the construction method for connecting a long cable of the present invention are as follows: first, reserve or pre-embed the installation anchor box, and install one or more diverters 29, and then penetrate the intermediate cable body 4 into the diverter 29 in sections, And successively connect and fix each intermediate cable body 4 through the intermediate joint 6 to form a long cable. It is also possible to fix and connect the fixed end anchorage 1 at one end of the long cable, and install and fix the tension end anchorage at the other end of the long cable. 2, then install the anchor and fix the long cable on the anchor. Finally, the long cable is tensioned to complete the prestress tension.

采用本发明可接长缆索的桥梁拉索施工方法如下:首先在实际长度不够的桥梁拉索上通过中间接头6依次连接固定一段或多段中间索体4,或者整段桥梁拉索都采用可接长缆索连接固定而成。然后安装锚具,将桥梁拉索固定在锚具上。最后对桥梁拉索进行张拉,完成可接长缆索的安装。本方法同样适用于拱桥拉索、悬索桥吊索等桥梁工程中。The construction method of the bridge cable that adopts the present invention to connect the long cable is as follows: first, connect and fix one or more sections of intermediate cable bodies 4 on the bridge cable whose actual length is not enough through the intermediate joint 6, or the entire bridge cable adopts the connectable cable. Long cables are connected and fixed. Then install the anchor and fix the bridge cable on the anchor. Finally, the bridge cables are tensioned to complete the installation of the connectable cables. This method is also applicable to bridge engineering such as arch bridge cables and suspension bridge suspension cables.

以上内容是结合具体实施方式对本发明所做的进一步详细说明,不能认为本发明的具体实施只局限于这些说明,对于本发明所属技术领域的普通技术人员来说,在不脱离本发明构思的前提下,所做出的简单修改和替换,都应当视为属于本发明的保护范围。The above content is a further detailed description of the present invention in conjunction with the specific embodiments, and it should not be considered that the specific implementation of the present invention is limited to these descriptions. Hereinafter, any simple modifications and substitutions made should be regarded as belonging to the protection scope of the present invention.

Claims (10)

1.一种可接长缆索,包括固定端锚具(1)和张拉端锚具(2),其特征在于:所述固定端锚具(1)与固定端索体(3)的固定端相固定,张拉端锚具(2)与张拉端索体(5)的固定端相固定,固定端索体(3)的连接端与张拉端索体(5)的连接端之间通过一段或多段可接长的中间索体(4)相连接固定,固定端索体(3)的连接端与中间索体(4)的端部之间、中间索体(4)的端部之间以及中间索体(4)的端部与拉端索体(5)的连接端之间通过中间接头(6)进行连接固定。1. An extendable cable, comprising a fixed end anchor (1) and a tension end anchor (2), characterized in that: the fixed end anchor (1) and the fixed end cable body (3) are fixed The ends are fixed, the tension end anchor (2) is fixed with the fixed end of the tension end cable body (5), and the connection end of the fixed end cable body (3) is connected with the connection end of the tension end cable body (5). The cables are connected and fixed by one or more lengthable intermediate cable bodies (4). Between the parts and between the end of the intermediate cable body (4) and the connection end of the pulling end cable body (5), the intermediate joint (6) is used for connection and fixation. 2.根据权利要求1所述的一种可接长缆索,其特征在于:所述固定端锚具(1)包括锚杯(21)、垫板(22)、螺母(23)以及锚具密封装置(24),固定端索体(3)的固定端固定在锚杯(21)内,锚杯(21)上分别安装有垫板(22)和螺母(23),锚杯(21)外端的固定端索体(3)上设置有锚具密封装置(24)。2 . The extendable cable according to claim 1 , wherein the fixed end anchor ( 1 ) comprises an anchor cup ( 21 ), a backing plate ( 22 ), a nut ( 23 ) and an anchor seal. 3 . The device (24), the fixed end of the fixed end cable body (3) is fixed in the anchor cup (21), the anchor cup (21) is respectively installed with a backing plate (22) and a nut (23), outside the anchor cup (21) An anchor sealing device (24) is arranged on the fixed end cable body (3) of the end. 3.根据权利要求1所述的一种可接长缆索,其特征在于:所述张拉端锚具(2)包括锚杯(21)、垫板(22)、螺母(23)以及锚具密封装置(24),固定端索体(3)的固定端固定在锚杯(21)内,锚杯(21)上分别安装有垫板(22)和螺母(23),锚杯(21)外端的固定端索体(3)上设置有锚具密封装置(24),锚杯(21)内与固定端索体(3)的连接部位设置有环氧或铝合金锚固体。3. The extendable cable according to claim 1, characterized in that: the tension end anchor (2) comprises an anchor cup (21), a backing plate (22), a nut (23) and an anchor The sealing device (24), the fixed end of the fixed end cable body (3) is fixed in the anchor cup (21), and the anchor cup (21) is respectively provided with a backing plate (22) and a nut (23), and the anchor cup (21) An anchoring device sealing device (24) is arranged on the fixed end cable body (3) at the outer end, and epoxy or aluminum alloy anchors are arranged in the connection part of the anchor cup (21) with the fixed end cable body (3). 4.根据权利要求2所述的一种可接长缆索,其特征在于:所述固定端索体(3)、中间索体(4)或者张拉端索体(5)采用平行钢丝缆索、钢绞线索、挤压缆索、钢拉杆、钢丝绳索或碳纤维索中的一种或任意两种以上的组合。4. A connectable cable according to claim 2, characterized in that: the fixed end cable body (3), the intermediate cable body (4) or the tension end cable body (5) are made of parallel wire cables, One or a combination of any two or more of steel strand cables, extruded cables, steel tie rods, steel wire ropes or carbon fiber cables. 5.根据权利要求1所述的一种可接长缆索,其特征在于:所述中间接头(6)包括接头套(7)、接头拉杆(8)、接头筒(9)以及接头塞(10),中间索体(4)的一端固定有接头套(7),与之连接的相邻的一根中间索体(4)的一端固定有接头塞(10),接头套(7)与接头拉杆(8)的一端相连接,接头拉杆(8)的另一端通过接头筒(9)与接头塞(10)相连接。5. The extendable cable according to claim 1, wherein the intermediate joint (6) comprises a joint sleeve (7), a joint pull rod (8), a joint barrel (9) and a joint plug (10) ), one end of the intermediate cable body (4) is fixed with a joint sleeve (7), and one end of an adjacent intermediate cable body (4) connected to it is fixed with a joint plug (10), the joint sleeve (7) and the joint One end of the pull rod (8) is connected, and the other end of the joint pull rod (8) is connected with the joint plug (10) through the joint cylinder (9). 6.根据权利要求1所述的一种可接长缆索,其特征在于:所述中间接头(6)包括锚具(11)、耳板(12)以及销轴(13),固定端索体(3)、中间索体(4)或者张拉端索体(5)的一端与锚具(11)相固定,锚具(11)通过销轴(13)与耳板(12)相连接。6 . The extendable cable according to claim 1 , wherein the intermediate joint ( 6 ) comprises an anchor ( 11 ), an ear plate ( 12 ) and a pin shaft ( 13 ), and the fixed end cable body (3) One end of the intermediate cable body (4) or the tension end cable body (5) is fixed with the anchor (11), and the anchor (11) is connected with the ear plate (12) through the pin (13). 7.根据权利要求1所述的一种可接长缆索,其特征在于:所述固定端索体(3)、中间索体(4)或者张拉端索体(5)由钢绞线(16)为索股而制成,钢绞线(16)采用光面钢绞线、镀锌钢绞线、镀锌铝钢绞线或无粘结钢绞线,并且索股的外表面设置有钢绞线护套(17)或缠绕包带,索体的外表面设置有双层外护套(18)或缠绕包带(20)。7 . The extendable cable according to claim 1 , wherein the fixed end cable body ( 3 ), the intermediate cable body ( 4 ) or the tension end cable body ( 5 ) are made of steel strands ( 7 . 16) Made for cable strands, the steel strands (16) are made of smooth steel strands, galvanized steel strands, galvanized aluminum steel strands or unbonded steel strands, and the outer surfaces of the strands are provided with The steel strand sheath (17) or the wrapping tape is provided, and the outer surface of the cable body is provided with a double outer sheath (18) or the wrapping tape (20). 8.一种可接长缆索施工方法,其特征在于包括以下步骤:8. A construction method for a connectable cable, characterized in that it comprises the following steps: a、首先在桥塔(25)安装固定端锚具(1)和固定端索体(3);a. First, install the fixed end anchorage (1) and the fixed end cable body (3) on the bridge tower (25); b、随后通过中间接头(6)依次以接长的方式一根或多根中间索体(4);b. One or more intermediate cable bodies (4) are then connected in turn through the intermediate joint (6) in a manner of lengthening; c、接着将位于最下方的中间索体(4)通过中间接头(6)与张拉端索体(5)的一端连接固定,并将张拉端索体(5)的另一端通过张拉端锚具(2)与梁体节段(27)进行连接固定;c. Next, connect and fix the lowermost intermediate cable body (4) with one end of the tension end cable body (5) through the intermediate joint (6), and connect the other end of the tension end cable body (5) through tensioning The end anchor (2) is connected and fixed with the beam body segment (27); d、从桥塔(25)处开始依次安装多根可接长缆索,并安装挂篮(28),建立施工阶段的临时受力体系,在挂篮(28)上搭建模板,浇筑梁体节段(27)的混凝土;d. From the bridge tower (25), install a plurality of cables that can be connected in sequence, and install the hanging basket (28) to establish a temporary stress system during the construction stage, build a template on the hanging basket (28), and pour the beam body segment (28). 27) concrete; e、每完成一段浇筑梁体节段(27)的施工就依次前移挂篮(28),依次类推完成全部梁体的施工;e. Move the hanging basket (28) forward in turn every time the construction of a casted beam body segment (27) is completed, and so on to complete the construction of all the beam bodies; f、在等待梁体节段(27)上的混凝土凝固的同时,进行永久索(26)的安装施工,对永久索(26)进行张拉,使得永久索(26)承担梁体节段(27)的重量,实现了受力体系的转换,完成施工。f. While waiting for the concrete on the beam body segment (27) to solidify, carry out the installation and construction of the permanent cable (26), and tension the permanent cable (26) so that the permanent cable (26) bears the weight of the beam body segment (27). , to realize the conversion of the force system and complete the construction. 9.一种体外预应力可接长缆索施工方法,其特征在于包括以下步骤:9. A construction method for externally prestressed connectable cables, characterized by comprising the following steps: a、首先预留或预埋安装锚箱,并安装一个或多个转向器(29);a. First reserve or pre-embed the anchor box, and install one or more diverters (29); b、再向转向器(29)内分段穿入中间索体(4),并依次将各个中间索体(4)之间通过中间接头(6)进行连接固定,形成长缆索;b. The intermediate cable bodies (4) are penetrated into the diverter (29) in sections, and the intermediate cable bodies (4) are connected and fixed through the intermediate joints (6) in turn to form a long cable; c、然后安装锚具,将长缆索固定在锚具上;c. Then install the anchor, and fix the long cable on the anchor; d、最后对长缆索进行张拉,完成预应力张拉。d. Finally, the long cable is tensioned to complete the prestress tension. 10.一种采用可接长缆索的桥梁拉索施工方法,其特征在于包括以下步骤:10. A method for constructing a bridge cable that can be connected with a long cable, characterized in that it comprises the following steps: a、首先在实际长度不够的桥梁拉索上通过中间接头(6)依次连接固定一段或多段中间索体(4),或者整段桥梁拉索都采用可接长缆索连接固定而成;a. First, connect and fix one or more sections of intermediate cable bodies (4) on the bridge cables with insufficient actual length through the intermediate joints (6) in turn, or the entire bridge cables are connected and fixed by using extendable cables; b、然后安装锚具,将桥梁拉索固定在锚具上;b. Then install the anchor, and fix the bridge cable on the anchor; c、最后对桥梁拉索进行张拉,完成可接长缆索的安装。c. Finally, tension the bridge cable to complete the installation of the connectable cable.
CN202210721998.9A 2022-06-24 2022-06-24 A kind of connectable cable and construction method Pending CN115125838A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210721998.9A CN115125838A (en) 2022-06-24 2022-06-24 A kind of connectable cable and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210721998.9A CN115125838A (en) 2022-06-24 2022-06-24 A kind of connectable cable and construction method

Publications (1)

Publication Number Publication Date
CN115125838A true CN115125838A (en) 2022-09-30

Family

ID=83379732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210721998.9A Pending CN115125838A (en) 2022-06-24 2022-06-24 A kind of connectable cable and construction method

Country Status (1)

Country Link
CN (1) CN115125838A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101054795A (en) * 2007-05-28 2007-10-17 重庆交通大学 Segmentation mounting method for cable of cable stayed bridge and connector for implementing cable segmented connection
CN102587572A (en) * 2012-04-01 2012-07-18 北京市建筑工程研究院有限责任公司 Steel strand stay rope and manufacturing method thereof
CN105735146A (en) * 2016-03-11 2016-07-06 广东省长大公路工程有限公司 Different-cable construction method for led cable hanging basket of concrete cable-stayed bridge
CN107905123A (en) * 2017-10-26 2018-04-13 中铁第四勘察设计院集团有限公司 A kind of multi-joint continuous rigid frame end bay temporary T structure cantilever construction transforming methods of structural system
CN207793883U (en) * 2017-12-26 2018-08-31 浙锚科技股份有限公司 Carbon fiber cable-cabin structure
KR20190088304A (en) * 2018-01-18 2019-07-26 다올이앤씨 주식회사 Tension introduction method for thunderbolt protection cable of cable bridge
CN112663507A (en) * 2020-12-23 2021-04-16 浙江省大成建设集团有限公司 Tower beam synchronous construction method for short-tower cable-stayed bridge
FR3106839A1 (en) * 2020-01-30 2021-08-06 Soletanche Freyssinet Maintenance process for a system of carrying cables and associated structural cable
CN215482319U (en) * 2021-07-30 2022-01-11 南京工大桥隧与轨道交通研究院有限公司 Sectional type stay cable system
CN113931084A (en) * 2021-10-08 2022-01-14 新疆交通建设集团股份有限公司 Construction method for external prestress of steel-concrete composite beam
CN215671271U (en) * 2021-03-19 2022-01-28 安徽金星预应力工程技术有限公司 Connector for 2400 MPa-grade steel strand testing
CN218027194U (en) * 2022-06-24 2022-12-13 柳州市桥厦缆索制品有限公司 Cable structure capable of being lengthened

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101054795A (en) * 2007-05-28 2007-10-17 重庆交通大学 Segmentation mounting method for cable of cable stayed bridge and connector for implementing cable segmented connection
CN102587572A (en) * 2012-04-01 2012-07-18 北京市建筑工程研究院有限责任公司 Steel strand stay rope and manufacturing method thereof
CN105735146A (en) * 2016-03-11 2016-07-06 广东省长大公路工程有限公司 Different-cable construction method for led cable hanging basket of concrete cable-stayed bridge
CN107905123A (en) * 2017-10-26 2018-04-13 中铁第四勘察设计院集团有限公司 A kind of multi-joint continuous rigid frame end bay temporary T structure cantilever construction transforming methods of structural system
CN207793883U (en) * 2017-12-26 2018-08-31 浙锚科技股份有限公司 Carbon fiber cable-cabin structure
KR20190088304A (en) * 2018-01-18 2019-07-26 다올이앤씨 주식회사 Tension introduction method for thunderbolt protection cable of cable bridge
FR3106839A1 (en) * 2020-01-30 2021-08-06 Soletanche Freyssinet Maintenance process for a system of carrying cables and associated structural cable
CN112663507A (en) * 2020-12-23 2021-04-16 浙江省大成建设集团有限公司 Tower beam synchronous construction method for short-tower cable-stayed bridge
CN215671271U (en) * 2021-03-19 2022-01-28 安徽金星预应力工程技术有限公司 Connector for 2400 MPa-grade steel strand testing
CN215482319U (en) * 2021-07-30 2022-01-11 南京工大桥隧与轨道交通研究院有限公司 Sectional type stay cable system
CN113931084A (en) * 2021-10-08 2022-01-14 新疆交通建设集团股份有限公司 Construction method for external prestress of steel-concrete composite beam
CN218027194U (en) * 2022-06-24 2022-12-13 柳州市桥厦缆索制品有限公司 Cable structure capable of being lengthened

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘士林等: "《斜拉桥》", 31 August 2002, 人民交通出版社, pages: 329 - 330 *
黄明鑫: "《大型张弦梁结构的设计与施工》", 31 March 2005, 山东科学技术出版社, pages: 285 - 292 *

Similar Documents

Publication Publication Date Title
KR100969005B1 (en) Constructing method of suspension bridge and temporary cable therefor
CN101215824B (en) External transverse tension prestressing device for late-stage deflection control of long-span continuous steel bridges
CN102864742B (en) Anchor device of first sliding and then fixing type combined steel anchor boxes of cable stayed bridge and construction method thereof
CN101054791A (en) Joist type cable arch bridge structure and its construction method
CN107849831A (en) Method for carrying out pushing tow/construction bridge using prefabricated panel and steel-pipe concrete truss
CN104947589B (en) Multistrand finished cable type anchorage prestress anchor device and construction method thereof
CN201169752Y (en) External prestressed steel structure anchorage steering system for old bridge reinforcement
CN106498837A (en) A kind of novel bridge and its construction method
CN103898834B (en) A kind of steel tube concrete combination beam and truss-like Sarasota cable-stayed bridge and construction method thereof
CN218027194U (en) Cable structure capable of being lengthened
CN107034785A (en) Rope construction method is changed in a kind of interchangeable anchorage prestress anchoraging device and its installation
CN115125838A (en) A kind of connectable cable and construction method
CN102286929A (en) Hinged arch springing of arch center
CN100396868C (en) High-strength steel wire pre-tensioned prestressed anchorage system and its construction method
CN106436587A (en) Chain link type automatic synchronous tensioning system and method for prestressed wire ropes
CN116516836A (en) A method for continuous jacking of large-span steel girders without guide girders in approach bridges
CN206693055U (en) Super-long prestressed steel tendon staggered anchor arrangement structure
CN217601208U (en) Vertical prestressing force system of railway bridge roof beam
CN216884551U (en) High-strength built-in post-tensioned reinforced concrete pole
CN211472142U (en) Bridge pier of swivel cable-stayed bridge and reinforcing device thereof
CN217203592U (en) An in-body prestressed beam tensile structure at the junction of tower-girder-pier of a cable-stayed bridge
CN114837059A (en) A kind of rock anchor cable-stayed flexible arch cooperative system bridge in mountainous area and its construction method
CN211006391U (en) Bridge reinforcing apparatus
CN207210932U (en) Prefabricated bridge space concrete filled steel tube truss combination beamss attachment means
CN205688330U (en) Ultra-long vertical unbonded prestressed structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination