CN115075224A - Steel-flexible combined multifunctional baffle plate for precast tubular pile and implementation method - Google Patents
Steel-flexible combined multifunctional baffle plate for precast tubular pile and implementation method Download PDFInfo
- Publication number
- CN115075224A CN115075224A CN202210811991.6A CN202210811991A CN115075224A CN 115075224 A CN115075224 A CN 115075224A CN 202210811991 A CN202210811991 A CN 202210811991A CN 115075224 A CN115075224 A CN 115075224A
- Authority
- CN
- China
- Prior art keywords
- plate
- metal plate
- rigid metal
- stainless steel
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The invention relates to the technical field of pipe pile construction, in particular to a steel-flexible combined multifunctional baffle plate for a precast pipe pile and an implementation method, wherein the steel-flexible combined multifunctional baffle plate comprises the following steps: the side surface of the rigid metal plate is provided with a flexible rubber ring, the surface of the rigid metal plate is provided with an accommodating groove, a metal handle is arranged in the accommodating groove, and the side surface of the accommodating groove is provided with a sliding groove; the stainless steel sheet metal is arranged at the bottom of the rigid metal plate; the sliding plate is arranged inside the sliding chute, and a connecting plate is arranged between the sliding plate and the metal handle; the beneficial effects are that: the rigid metal plate is inserted into the end part of the pile core of the tubular pile, and is supported on the surface of the side wall of the pile core through the stainless steel metal sheet to prevent the rigid metal plate from sliding towards the inside of the pile core, so that the problem that soil enters the pile core in the construction process is effectively avoided.
Description
Technical Field
The invention relates to the technical field of pipe pile construction, in particular to a steel-flexible combined multifunctional baffle plate for a precast pipe pile and an implementation method.
Background
The precast tubular pile is a foundation component in the building engineering, and has the advantages of high single-pile bearing capacity, high construction speed, short construction period, low cost and the like;
when the existing prefabricated tubular pile is constructed, the tubular pile is lifted by a pile driver, the pile position is aligned, the verticality of a pile frame is adjusted, and then the tubular pile is hammered into the pile position by the pile driver;
but at the in-process of tubular pile construction, have inside earth gets into the stake core, need the manual work to dig out the inside earth of stake core, waste time and energy, influence work efficiency.
Disclosure of Invention
The invention aims to provide a steel-flexible combined prefabricated pipe pile multifunctional baffle and an implementation method thereof, and aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a multi-functional baffle of precast tubular pile of gentle combination of steel, the multi-functional baffle of precast tubular pile of gentle combination of steel includes:
the side surface of the rigid metal plate is provided with a flexible rubber ring, the surface of the rigid metal plate is provided with an accommodating groove, a metal handle is arranged inside the accommodating groove, and the side surface of the accommodating groove is provided with a sliding groove;
the stainless steel metal sheet is arranged at the bottom of the rigid metal plate;
the slide, the slide sets up in the inside of spout, is provided with the connecting plate between slide and the metal handle.
Preferably, the flexible rubber ring is fixedly bonded with the edge of the rigid metal plate, the sealing performance of the rigid metal plate is improved through the flexible rubber ring, and the functions of retaining soil and retaining concrete are achieved.
Preferably, the constant head tank has been seted up to one side of accomodating the groove, and the inside of constant head tank is fixed and is provided with the guide bar No. one, and the inside slip of constant head tank is provided with the fixture block, and No. two spigot surfaces have been seted up on the surface of fixture block, and a guiding hole has been seted up to the side of fixture block, and a guiding hole runs through the both sides of fixture block, and the fixture block locates the surface of a guide bar through a guiding hole slip cap, is provided with reset spring between the inner wall of fixture block and constant head tank, and reset spring overlaps the surface of locating a guide bar.
Preferably, the metal handle is square plate-shaped structure, and logical groove has been seted up to one side that the metal handle is close to the fixture block, and logical groove is close to the lateral wall of the one end of fixture block and has been seted up a spigot surface, and a spigot surface slides with No. two spigot surfaces and sets up, and the both ends symmetry of metal handle is provided with the hinge head No. one, and a hinge head and metal handle are overall structure.
Preferably, four sets of sliding chutes are formed in the sliding chutes, the four sets of sliding chutes are symmetrically formed in the side walls at two ends of the accommodating groove, a second guide rod is fixedly mounted inside the sliding chute, and telescopic grooves are symmetrically formed in two ends of the accommodating groove.
Preferably, stainless steel sheetmetal fixed welding is in a side surface that the metal handle was kept away from to the rigid metal plate, and the stainless steel sheetmetal is provided with three groups, and three groups of stainless steel sheetmetals are circumference array distribution, and the stainless steel sheetmetal has elasticity, and the stainless steel sheetmetal is bent plate structure, and the one end of keeping away from the rigid metal plate under the stainless steel sheetmetal initial state is one hundred degrees left and right sides contained angle with the radial of rigid metal plate, and the diameter of the circle that the one end outer fringe of rigid metal plate formed is kept away from to three groups of stainless steel sheetmetals is greater than the diameter of rigid metal plate.
Preferably, the both ends of slide and the lateral wall of spout slide the setting, and the slide is provided with two sets ofly, and the fixed surface of slide is connected with the shrouding, and the shrouding slides and pegs graft in the inside of flexible groove, and No. two guiding holes have been seted up on the surface of slide, and the slide is located the surface of No. two guide bars through No. two guiding hole sliding sleeve.
Preferably, a jacking spring is arranged between one side of the sliding plate, which is far away from the metal handle, and the inner wall of the sliding groove, the jacking spring is sleeved on the surface of the second guide rod, and one side of the sliding plate, which is close to the metal handle, is fixedly connected with a second hinge joint.
Preferably, the two ends of the connecting plate are symmetrically provided with hinge grooves, and the connecting plate is rotatably connected with the first hinge joint and the second hinge joint through the hinge grooves at the two ends respectively through rotating shafts.
The utility model provides a realization method of multi-functional baffle of precast tubular pile of soft combination of steel, according to multi-functional baffle of precast tubular pile of soft combination of steel realize, and this multi-functional baffle of precast tubular pile of soft combination of steel's concrete realization method includes:
and (3) transportation: after the rigid metal plate is processed, the metal handle is pressed into the accommodating groove, the metal handle extrudes the second guide surface through the first guide surface, the clamping block moves towards the through groove, after the clamping block penetrates through the rigid metal plate, the resilience force of the reset spring drives the clamping block to be clamped on the surface of the metal handle, and the metal handle is fixed in the accommodating groove, so that the rigid metal plate is convenient to stack during transportation;
when the soil baffle is used: the control block moves to the position of the through groove, the resilience force of the jacking spring drives the sliding plate to move towards the direction of the metal handle, the connecting plate is turned over towards the outer side of the accommodating groove, the metal handle is pushed out of the accommodating groove, then the stainless steel metal sheet faces towards the direction of the tubular pile head, the end part of the stainless steel metal sheet is controlled to be elastically bent towards the inner side of the rigid metal plate, the stainless steel metal sheet is bent into ninety degrees, the rigid metal plate is inserted into the pile core, the rigid metal plate is flush with the end part of the tubular pile head, the three groups of stainless steel metal sheets are supported on the surface of the inner wall of the pile core, the rigid metal plate is prevented from sliding towards the inside of the pile core, and the rigid metal plate is attached to the side wall of the pile core through the flexible rubber ring to prevent soil from entering the inside of the pile core;
when the concrete baffle is used as a concrete baffle: the rigid metal plate is pulled out from the pile core through the metal handle, one side of the rigid metal plate, which is provided with the stainless steel metal sheet, is welded with the prefabricated reinforcement cage in a point-to-point mode, then one end of the rigid metal plate, which is provided with the metal handle, is inserted into the pile core towards the pipe pile head, the stainless steel metal sheet is bent into ninety degrees under the extrusion of the side wall of the pile core, the rigid metal plate is inserted into the preset position and then fixed with the position of the prefabricated reinforcement cage through the positioning steel bar, at the moment, the rigid metal plate is attached to the inner wall of the pile core through the flexible rubber ring, the concrete leakage of the pile core is prevented, and the concrete compactness of the pile core is ensured.
Compared with the prior art, the invention has the beneficial effects that:
according to the steel-flexible combined multifunctional baffle plate for the precast tubular pile, the rigid metal plate is inserted into the end part of the pile core of the tubular pile, and the rigid metal plate is prevented from sliding towards the interior of the pile core by abutting the stainless steel metal sheet on the surface of the side wall of the pile core, so that the problem that soil enters the pile core in the construction process is effectively avoided;
when concrete is poured into the pile core of the tubular pile, the rigid metal plate is welded at the bottom of the prefabricated reinforcement cage, so that the concrete leakage of the pile core is prevented, and the concrete compactness of the pile core is ensured;
when the rigid metal plate is transported, the metal handle is fixed inside the accommodating groove through the clamping block, so that the rigid metal plate can be conveniently stacked, and the rigid metal plate can be conveniently transported.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of the structure at A in FIG. 1 according to the present invention;
FIG. 3 is a schematic view of the slider structure of the present invention;
FIG. 4 is a schematic diagram of a rigid metal plate structure according to the present invention;
FIG. 5 is an enlarged view of the structure at B in FIG. 4 according to the present invention;
FIG. 6 is an enlarged view of the structure of FIG. 4 at C according to the present invention;
FIG. 7 is a schematic cross-sectional view of the present invention;
FIG. 8 is a diagram illustrating a fixture block structure of the present invention;
FIG. 9 is a schematic view of a metal handle according to the present invention;
FIG. 10 is a schematic view of the connection plate structure of the present invention;
FIG. 11 is a schematic cross-sectional view of the present invention as a concrete baffle;
fig. 12 is a schematic sectional view of the present invention as a soil guard.
In the figure: rigid metal plate 1, accomodate groove 11, constant head tank 12, guide bar 13, spout 14, No. two guide bars 15, telescopic slot 16, stainless steel sheetmetal 2, flexible rubber circle 3, metal handle 4, logical groove 41, a spigot surface 42, a hinge 43, connecting plate 5, hinge slot 51, slide 6, shrouding 61, No. two guiding holes 62, No. two hinge 63, top hold spring 64, fixture block 7, No. two spigot surface 71, a guiding hole 72, reset spring 73.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clear and fully described, embodiments of the present invention are further described in detail below with reference to the accompanying drawings. It is to be understood that the specific embodiments described herein are merely illustrative of some embodiments of the invention and are not limiting of the invention, and that all other embodiments obtained by those of ordinary skill in the art without the exercise of inventive faculty are within the scope of the invention.
In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "a," "an," "first," "second," "third," "fourth," "fifth," and "sixth" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
For the purposes of simplicity and explanation, the principles of the embodiments are described by referring mainly to examples. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the embodiments. It will be apparent, however, to one skilled in the art that the embodiments may be practiced without these specific details. In some instances, well-known methods and structures have not been described in detail so as not to unnecessarily obscure the embodiments. In addition, all embodiments may be used in combination with each other.
Referring to fig. 1 to 12, the present invention provides a technical solution:
the first embodiment is as follows:
the utility model provides a multi-functional baffle of precast tubular pile of gentle combination of steel, the multi-functional baffle of precast tubular pile of gentle combination of steel includes: the side surface of the rigid metal plate 1 is provided with a flexible rubber ring 3, the surface of the rigid metal plate 1 is provided with a containing groove 11, a metal handle 4 is arranged inside the containing groove 11, and the side surface of the containing groove 11 is provided with a sliding groove 14; the stainless steel sheet metal 2 is arranged at the bottom of the rigid metal plate 1; the sliding plate 6 is arranged inside the sliding groove 14, and the connecting plate 5 is arranged between the sliding plate 6 and the metal handle 4; the flexible rubber ring 3 is fixedly bonded with the edge of the rigid metal plate 1, the sealing performance of the rigid metal plate 1 is improved through the flexible rubber ring 3, and the functions of soil retaining and concrete retaining are achieved; make stainless steel sheetmetal 2 towards the inside of stake core, insert the top of stake core with rigidity metal sheet 1, make the surface of rigidity metal sheet 1 flush with the surface of tubular pile head, stainless steel sheetmetal 2 props the lateral wall surface at the stake core, prevents that rigidity metal sheet 1 from sliding to the inside of stake core, realizes blockking earth entering stake core.
The second embodiment:
on the basis of the first embodiment, in order to fix the position of the metal handle 4, a positioning groove 12 is formed in one side of the accommodating groove 11, a first guide rod 13 is fixedly arranged inside the positioning groove 12, a fixture block 7 is slidably arranged inside the positioning groove 12, a second guide surface 71 is formed on the surface of the fixture block 7, a first guide hole 72 is formed in the side surface of the fixture block 7, the first guide hole 72 penetrates through two sides of the fixture block 7, the fixture block 7 is slidably sleeved on the surface of the first guide rod 13 through the first guide hole 72, a return spring 73 is arranged between the fixture block 7 and the inner wall of the positioning groove 12, and the return spring 73 is sleeved on the surface of the first guide rod 13; the metal handle 4 is of a square plate-shaped structure, a through groove 41 is formed in one side, close to the fixture block 7, of the metal handle 4, a first guide surface 42 is formed in the side wall, close to one end of the fixture block 7, of the through groove 41, the first guide surface 42 and a second guide surface 71 are arranged in a sliding mode, first hinges 43 are symmetrically arranged at two ends of the metal handle 4, and the first hinges 43 and the metal handle 4 are of an integral structure; in the process of pressing the metal handle 4 into the accommodating groove 11, the metal handle 4 presses the fixture block 7 toward the through groove 41 through the first guide surface 42 and the second guide surface 71, so that the fixture block 7 passes through the through groove 41, and then under the elastic force action of the return spring 73, the fixture block 7 is clamped on the surface of the metal handle 4, so that the metal handle 4 is specified in the accommodating groove 11.
Example three:
on the basis of the second embodiment, in order to realize the movement and fixation of the rigid metal plate 1 in the pile core, the stainless steel metal sheets 2 are fixedly welded on the surface of one side of the rigid metal plate 1, which is far away from the metal handle 4, three groups of stainless steel metal sheets 2 are arranged, the three groups of stainless steel metal sheets 2 are distributed in a circumferential array mode, the stainless steel metal sheets 2 have elasticity, the stainless steel metal sheets 2 are in a bent plate structure, an included angle between one end, which is far away from the rigid metal plate 1, of each stainless steel metal sheet 2 in an initial state and the radial direction of the rigid metal plate 1 is about one hundred degrees, and the diameter of a circle formed by the outer edge of one end, which is far away from the rigid metal plate 1, of the three groups of stainless steel metal sheets 2 is larger than the diameter of the rigid metal plate 1; when the rigid metal plate 1 is used as a soil baffle, the stainless steel metal sheet 2 faces the inside of the pile core when the rigid metal plate 1 is inserted into the pile core, because one end of the stainless steel metal sheet 2, which is far away from the rigid metal plate 1, bounces to the outer side of the rigid metal plate 1, when the rigid metal plate 1 is subjected to extrusion force towards the inside of the pile core, the end part of the stainless steel metal sheet 2 is propped against the inner wall of the pile core to prevent the rigid metal plate 1 from moving, when the rigid metal plate 1 is used as a concrete baffle, the stainless steel metal sheet 2 faces the outside of the pile core when the rigid metal plate 1 is inserted into the pile core, and the end part of the stainless steel metal sheet 2 is opposite to the moving direction of the rigid metal plate 1 and cannot prevent the rigid metal plate 1 from moving.
Example four:
on the basis of the third embodiment, in order to realize the ejection of the metal handle 4 from the inside of the accommodating groove 11, four sets of sliding grooves 14 are formed in the sliding grooves 14, the four sets of sliding grooves 14 are symmetrically formed in the side walls of the two ends of the accommodating groove 11, a second guide rod 15 is fixedly installed in the sliding grooves 14, and telescopic grooves 16 are symmetrically formed in the two ends of the accommodating groove 11; two ends of the sliding plate 6 are arranged with the side wall of the sliding groove 14 in a sliding manner, two groups of sliding plates 6 are arranged, the surface of the sliding plate 6 is fixedly connected with a sealing plate 61, the sealing plate 61 is inserted in the telescopic groove 16 in a sliding manner, a second guide hole 62 is formed in the surface of the sliding plate 6, and the sliding plate 6 is slidably sleeved on the surface of the second guide rod 15 through the second guide hole 62; a jacking spring 64 is arranged between one side of the sliding plate 6, which is far away from the metal handle 4, and the inner wall of the sliding chute 14, the jacking spring 64 is sleeved on the surface of the second guide rod 15, and one side of the sliding plate 6, which is close to the metal handle 4, is fixedly connected with a second hinge joint 63; two ends of the connecting plate 5 are symmetrically provided with hinge grooves 51, and the connecting plate 5 is respectively rotatably connected with the first hinge joint 43 and the second hinge joint 63 through the hinge grooves 51 at the two ends through rotating shafts; the fixture block 7 is controlled to move to the position of the through groove 41, at the moment, the metal handle 4 loses the resistance of the fixture block 7, the jacking spring 64 extrudes the connecting plate 5 through the sliding plate 6, and the connecting plate 5 drives the metal handle 4 to bounce towards the outside of the accommodating groove 11.
Example five:
the utility model provides a realization method of multi-functional baffle of precast tubular pile of gentle combination of steel, according to the multi-functional baffle of precast tubular pile of gentle combination of steel realize, and this multi-functional baffle of precast tubular pile of gentle combination of steel concrete realization method includes:
and (3) transportation: after the rigid metal plate 1 is processed, the metal handle 4 is pressed into the accommodating groove 11, the metal handle 4 extrudes the second guide surface 71 through the first guide surface 42, so that the fixture block 7 moves towards the direction of the through groove 41, after the fixture block 7 passes through the rigid metal plate 1, the resilience force of the reset spring 73 drives the fixture block 7 to be clamped on the surface of the metal handle 4, the metal handle 4 is fixed in the accommodating groove 11, and the rigid metal plate 1 is convenient to stack during transportation;
when the soil baffle is used: the control fixture block 7 moves to the position of the through groove 41, the resilience force of the jacking spring 64 drives the sliding plate 6 to move towards the direction of the metal handle 4, the connecting plate 5 is turned towards the outer side of the accommodating groove 11, so that the metal handle 4 is pushed out of the accommodating groove 11, then the stainless steel metal sheet 2 faces the direction of the tubular pile head, the end part of the stainless steel metal sheet 2 is controlled to be elastically bent towards the inner side of the rigid metal plate 1, the stainless steel metal sheet 2 is bent into ninety degrees, the rigid metal plate 1 is inserted into the pile core, the rigid metal plate 1 is flush with the end part of the tubular pile head, the three groups of stainless steel metal sheets 2 are supported on the surface of the inner wall of the pile core, the rigid metal plate 1 is prevented from sliding towards the interior of the pile core, the rigid metal plate 1 is attached to the side wall of the pile core through the flexible rubber ring 3, and soil is prevented from entering the interior of the pile core;
when the concrete baffle is used: pull out rigid metal plate 1 from the stake core through metal handle 4, with rigid metal plate 1 be provided with one side and prefabricated steel reinforcement cage point-to-point welding of stainless steel sheetmetal 2, then with rigid metal plate 1 be provided with the inside that metal handle 4 inserted the stake core towards the tubular pile head, stainless steel sheetmetal 2 buckles into the ninety degrees under the extrusion of stake core lateral wall, after rigid metal plate 1 male setting position, through the position of the fixed prefabricated steel reinforcement cage of positioning bar, at this moment, rigid metal plate 1 passes through the laminating of flexible rubber circle 3 with the inner wall of stake core, prevent that stake core concrete from leaking thick liquid, guarantee stake core concrete compactness.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (10)
1. The utility model provides a multi-functional baffle of precast tubular pile of gentle combination which characterized in that: the multi-functional baffle of gentle precast tubular pile who combines of steel includes:
the flexible rubber ring is arranged on the side surface of the rigid metal plate (1), a containing groove (11) is formed in the surface of the rigid metal plate (1), a metal handle (4) is arranged inside the containing groove (11), and a sliding groove (14) is formed in the side surface of the containing groove (11);
the stainless steel metal sheet (2), the stainless steel metal sheet (2) is arranged at the bottom of the rigid metal plate (1);
the sliding plate (6), the sliding plate (6) is arranged in the sliding groove (14), and a connecting plate (5) is arranged between the sliding plate (6) and the metal handle (4).
2. The multifunctional baffle plate for the precast tubular pile combined with the steel and the flexible steel as claimed in claim 1, is characterized in that: the flexible rubber ring (3) is fixedly bonded with the edge of the rigid metal plate (1), the sealing performance of the rigid metal plate (1) is improved through the flexible rubber ring (3), and the functions of retaining soil and concrete are achieved.
3. The multifunctional baffle plate for the precast tubular pile combined with the steel and the flexible steel as claimed in claim 2, is characterized in that: positioning groove (12) have been seted up to one side of accomodating groove (11), the inside fixed guide bar (13) that is provided with of positioning groove (12), the inside slip of positioning groove (12) is provided with fixture block (7), No. two spigot surface (71) have been seted up on the surface of fixture block (7), guide hole (72) have been seted up to the side of fixture block (7), the both sides of fixture block (7) are run through in guide hole (72), the surface of guide bar (13) is located through guide hole (72) sliding sleeve in fixture block (7), be provided with reset spring (73) between the inner wall of fixture block (7) and positioning groove (12), reset spring (73) cover is located the surface of a guide bar (13).
4. The multifunctional baffle plate for the precast tubular pile combined with the steel and the flexible steel as claimed in claim 3, is characterized in that: metal handle (4) are square plate structure, and logical groove (41) have been seted up to one side that metal handle (4) are close to fixture block (7), and leading surface (42) have been seted up to the lateral wall that leads to groove (41) and be close to the one end of fixture block (7), and leading surface (42) and No. two leading surfaces (71) slide to be set up, and the both ends symmetry of metal handle (4) is provided with a hinge (43), and a hinge (43) and metal handle (4) are overall structure.
5. The multifunctional baffle plate for the steel-flexible precast tubular pile of claim 4, is characterized in that: four sets of chutes (14) are arranged, the four sets of chutes (14) are symmetrically arranged on the side walls at two ends of the accommodating groove (11), two guide rods (15) are fixedly arranged inside the chutes (14), and the two ends of the accommodating groove (11) are symmetrically provided with telescopic grooves (16).
6. The multifunctional baffle plate for the steel-flexible precast tubular pile of claim 5, is characterized in that: stainless steel sheetmetal (2) fixed welding is in a side surface of keeping away from metal handle (4) in rigid metal plate (1), stainless steel sheetmetal (2) are provided with three groups, three stainless steel sheetmetal (2) of group are circumference array distribution, stainless steel sheetmetal (2) have elasticity, stainless steel sheetmetal (2) are the bent plate structure, and the one end of keeping away from rigid metal plate (1) under stainless steel sheetmetal (2) initial state is one hundred degrees left and right sides contained angle with the radial of rigid metal plate (1), the diameter of the circle that rigid metal plate (1) was kept away from to three stainless steel sheetmetal (2) one end outer fringe formed is greater than the diameter of rigid metal plate (1).
7. The multifunctional baffle plate for the steel-flexible precast tubular pile of claim 6, is characterized in that: the both ends of slide (6) and the lateral wall of spout (14) slide and set up, slide (6) are provided with two sets ofly, and the fixed surface of slide (6) is connected with shrouding (61), and shrouding (61) slide and peg graft in the inside of telescopic slot (16), and No. two guiding holes (62) have been seted up on the surface of slide (6), and slide (6) are located the surface of No. two guide bars (15) through No. two guiding holes (62) sliding sleeve.
8. The multifunctional baffle plate for precast tubular piles in flexible combination according to claim 7, is characterized in that: a jacking spring (64) is arranged between one side, far away from the metal handle (4), of the sliding plate (6) and the inner wall of the sliding groove (14), the jacking spring (64) is sleeved on the surface of the second guide rod (15), and a second hinge joint (63) is fixedly connected to one side, close to the metal handle (4), of the sliding plate (6).
9. The multifunctional baffle plate for precast tubular piles in flexible combination according to claim 8, is characterized in that: hinge grooves (51) are symmetrically formed in two ends of the connecting plate (5), and the connecting plate (5) is rotatably connected with the first hinge head (43) and the second hinge head (63) through the hinge grooves (51) in the two ends respectively.
10. The implementation method of the steel-flexible combined multifunctional baffle of the precast tubular pile is characterized in that: the multifunctional baffle plate for the precast tubular pile of any one of claims 1 to 9, wherein the concrete implementation method of the multifunctional baffle plate for the precast tubular pile comprises the following steps:
and (3) transportation: after the rigid metal plate (1) is machined, the metal handle (4) is pressed into the accommodating groove (11), the metal handle (4) extrudes the second guide surface (71) through the first guide surface (42), the fixture block (7) moves towards the direction of the through groove (41), after the fixture block (7) penetrates through the rigid metal plate (1), the resilience force of the reset spring (73) drives the fixture block (7) to be clamped on the surface of the metal handle (4), the metal handle (4) is fixed inside the accommodating groove (11), and stacking of the rigid metal plate (1) during transportation is facilitated;
when the soil baffle is used: the control fixture block (7) moves to the position of the through groove (41), the resilience force of the jacking spring (64) drives the sliding plate (6) to move towards the metal handle (4), the connecting plate (5) is turned over towards the outer side of the accommodating groove (11), so that the metal handle (4) is pushed out of the accommodating groove (11), then the stainless steel metal sheet (2) faces towards the direction of the tubular pile head, the end part of the stainless steel metal sheet (2) is controlled to be elastically bent towards the inner side of the rigid metal plate (1), the stainless steel metal sheet (2) is bent into ninety degrees, the rigid metal plate (1) is inserted into the pile core, the rigid metal plate (1) is aligned with the end part of the tubular pile head, the three groups of stainless steel metal sheets (2) are supported on the surface of the inner wall of the pile core, the rigid metal plate (1) is prevented from sliding towards the inner part of the pile core, the rigid metal plate (1) is attached to the side wall of the pile core through the flexible rubber ring (3), preventing soil from entering the interior of the pile core;
when the concrete baffle is used: the method comprises the steps of pulling out a rigid metal plate (1) from a pile core through a metal handle (4), welding one side, provided with a stainless steel metal sheet (2), of the rigid metal plate (1) with a prefabricated reinforcement cage in a point-to-point mode, inserting one end, provided with the metal handle (4), of the rigid metal plate (1) into the pile core towards a pipe pile head, bending the stainless steel metal sheet (2) into ninety degrees under the extrusion of the side wall of the pile core, fixing the position of the prefabricated reinforcement cage through a positioning reinforcement after the rigid metal plate (1) is inserted into the preset position, and attaching the rigid metal plate (1) to the inner wall of the pile core through a flexible rubber ring (3) at the moment, so that pile core concrete leakage is prevented, and the concrete compactness of the pile core is guaranteed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210811991.6A CN115075224B (en) | 2022-07-12 | 2022-07-12 | Steel-flexible combined multifunctional baffle for prefabricated pipe piles and implementation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210811991.6A CN115075224B (en) | 2022-07-12 | 2022-07-12 | Steel-flexible combined multifunctional baffle for prefabricated pipe piles and implementation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115075224A true CN115075224A (en) | 2022-09-20 |
CN115075224B CN115075224B (en) | 2023-07-07 |
Family
ID=83259852
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210811991.6A Active CN115075224B (en) | 2022-07-12 | 2022-07-12 | Steel-flexible combined multifunctional baffle for prefabricated pipe piles and implementation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115075224B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN118361126A (en) * | 2024-06-18 | 2024-07-19 | 中国建筑第四工程局有限公司 | Movable steel column top covering device and method thereof |
Citations (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05209415A (en) * | 1992-01-29 | 1993-08-20 | Nippon Chikou Kk | Panzer mast foundation pile and driving method therefor |
JPH07247545A (en) * | 1994-03-04 | 1995-09-26 | Teruo Koi | Method of treating soil cement in pile hole and device thereof |
US5961253A (en) * | 1994-12-05 | 1999-10-05 | Okawa; Shogen | Pile head dresser, pile head dressing method, and, placement of cast-in-place concrete piles |
CN2767503Y (en) * | 2004-10-21 | 2006-03-29 | 董立春 | Tri-proof well cover |
KR20110000245U (en) * | 2009-07-02 | 2011-01-10 | 주식회사 그린에스엔티 | File safety cover |
CN103061335A (en) * | 2013-01-21 | 2013-04-24 | 中国十七冶集团有限公司 | Pile hole dirt preventing cast iron metal cover plate for prestressed concrete tubular pile and mounting method of pile hole dirt preventing cast iron metal cover plate |
CN203066066U (en) * | 2013-01-22 | 2013-07-17 | 中国十七冶集团有限公司 | Soil-proof cover plate for pile hole of prestressed concrete tubular pile |
CN205276273U (en) * | 2016-01-06 | 2016-06-01 | 代朝阳 | Civil engineering construction uses hollow pile body |
CN206554132U (en) * | 2017-03-06 | 2017-10-13 | 云南云岭高速公路建设集团有限公司 | A kind of sound detecting pipe top anti-block apparatus |
CN207469248U (en) * | 2017-11-01 | 2018-06-08 | 福建宏盛建设集团有限公司 | A kind of piling sludge baffle arrangement |
CN109162289A (en) * | 2018-10-30 | 2019-01-08 | 江西博慧工程技术服务有限公司 | The prefabricated carrying pier structure of one kind and its construction method |
CN109322307A (en) * | 2018-11-19 | 2019-02-12 | 中国冶集团有限公司 | A kind of hollow pile crown plugging device and its construction method used |
CN110130637A (en) * | 2019-05-16 | 2019-08-16 | 戚康麟 | An easy-to-assemble building formwork |
CN110374084A (en) * | 2019-06-28 | 2019-10-25 | 中国一冶集团有限公司 | Prefabricated tubular pile stomidium plugging device and method |
CN212335990U (en) * | 2020-03-17 | 2021-01-12 | 中国华冶科工集团有限公司 | End section tubular pile top cover plate |
CN213952200U (en) * | 2020-09-30 | 2021-08-13 | 中国电建集团山东电力建设第一工程有限公司 | Device for preventing pile head of PHC precast tubular pile from entering soil |
CN214530661U (en) * | 2020-10-29 | 2021-10-29 | 中冶天工集团有限公司 | Protection device for prevent earth from flowing backward pile core in tubular pile construction |
CN113684824A (en) * | 2021-09-16 | 2021-11-23 | 中国建筑第八工程局有限公司 | PHC prestressed pipe pile soil-retaining cover plate and construction method thereof |
CN113699978A (en) * | 2021-08-26 | 2021-11-26 | 北京市市政一建设工程有限责任公司 | Anti-settling grouting process |
CN215715286U (en) * | 2021-08-31 | 2022-02-01 | 中交一航局生态工程有限公司 | Soil-proof device for pile hole of tubular pile |
CN216007022U (en) * | 2021-10-27 | 2022-03-11 | 中铁上海工程局集团有限公司 | Covering device |
-
2022
- 2022-07-12 CN CN202210811991.6A patent/CN115075224B/en active Active
Patent Citations (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05209415A (en) * | 1992-01-29 | 1993-08-20 | Nippon Chikou Kk | Panzer mast foundation pile and driving method therefor |
JPH07247545A (en) * | 1994-03-04 | 1995-09-26 | Teruo Koi | Method of treating soil cement in pile hole and device thereof |
US5961253A (en) * | 1994-12-05 | 1999-10-05 | Okawa; Shogen | Pile head dresser, pile head dressing method, and, placement of cast-in-place concrete piles |
CN2767503Y (en) * | 2004-10-21 | 2006-03-29 | 董立春 | Tri-proof well cover |
KR20110000245U (en) * | 2009-07-02 | 2011-01-10 | 주식회사 그린에스엔티 | File safety cover |
CN103061335A (en) * | 2013-01-21 | 2013-04-24 | 中国十七冶集团有限公司 | Pile hole dirt preventing cast iron metal cover plate for prestressed concrete tubular pile and mounting method of pile hole dirt preventing cast iron metal cover plate |
CN203066066U (en) * | 2013-01-22 | 2013-07-17 | 中国十七冶集团有限公司 | Soil-proof cover plate for pile hole of prestressed concrete tubular pile |
CN205276273U (en) * | 2016-01-06 | 2016-06-01 | 代朝阳 | Civil engineering construction uses hollow pile body |
CN206554132U (en) * | 2017-03-06 | 2017-10-13 | 云南云岭高速公路建设集团有限公司 | A kind of sound detecting pipe top anti-block apparatus |
CN207469248U (en) * | 2017-11-01 | 2018-06-08 | 福建宏盛建设集团有限公司 | A kind of piling sludge baffle arrangement |
CN109162289A (en) * | 2018-10-30 | 2019-01-08 | 江西博慧工程技术服务有限公司 | The prefabricated carrying pier structure of one kind and its construction method |
CN109322307A (en) * | 2018-11-19 | 2019-02-12 | 中国冶集团有限公司 | A kind of hollow pile crown plugging device and its construction method used |
CN110130637A (en) * | 2019-05-16 | 2019-08-16 | 戚康麟 | An easy-to-assemble building formwork |
CN110374084A (en) * | 2019-06-28 | 2019-10-25 | 中国一冶集团有限公司 | Prefabricated tubular pile stomidium plugging device and method |
CN212335990U (en) * | 2020-03-17 | 2021-01-12 | 中国华冶科工集团有限公司 | End section tubular pile top cover plate |
CN213952200U (en) * | 2020-09-30 | 2021-08-13 | 中国电建集团山东电力建设第一工程有限公司 | Device for preventing pile head of PHC precast tubular pile from entering soil |
CN214530661U (en) * | 2020-10-29 | 2021-10-29 | 中冶天工集团有限公司 | Protection device for prevent earth from flowing backward pile core in tubular pile construction |
CN113699978A (en) * | 2021-08-26 | 2021-11-26 | 北京市市政一建设工程有限责任公司 | Anti-settling grouting process |
CN215715286U (en) * | 2021-08-31 | 2022-02-01 | 中交一航局生态工程有限公司 | Soil-proof device for pile hole of tubular pile |
CN113684824A (en) * | 2021-09-16 | 2021-11-23 | 中国建筑第八工程局有限公司 | PHC prestressed pipe pile soil-retaining cover plate and construction method thereof |
CN216007022U (en) * | 2021-10-27 | 2022-03-11 | 中铁上海工程局集团有限公司 | Covering device |
Non-Patent Citations (1)
Title |
---|
于书翰;: "在深水中修筑钻孔桩基础的探讨", 公路 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN118361126A (en) * | 2024-06-18 | 2024-07-19 | 中国建筑第四工程局有限公司 | Movable steel column top covering device and method thereof |
CN118361126B (en) * | 2024-06-18 | 2024-08-20 | 中国建筑第四工程局有限公司 | Movable steel column top covering device and method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN115075224B (en) | 2023-07-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN115075224A (en) | Steel-flexible combined multifunctional baffle plate for precast tubular pile and implementation method | |
CN118128040B (en) | Foundation reinforcement construction equipment based on frozen land section and construction method thereof | |
CN214940058U (en) | Variable-diameter prestressed high-strength concrete pipe pile structure | |
CN214993893U (en) | Foundation pit slope-setting supporting structure | |
CN217733999U (en) | Quick butt joint structure of prestressed concrete pipe pile | |
CN210917393U (en) | Foundation pit supporting structure | |
CN211200406U (en) | Pipeline slot supporting device | |
CN219768639U (en) | Mixed type prestressed reinforced concrete pipe pile | |
CN209323829U (en) | A steel tube concrete column base node | |
CN215241723U (en) | Prefabricated wallboard preformed hole frock | |
WO2023080774A1 (en) | A system for guiding tremie pipe placement and a method for using thereof | |
CN215105255U (en) | Core filling concrete pouring device at pile splicing part of prestressed concrete pipe pile | |
CN110952531B (en) | Extensible nested steel pipe pile and installation method thereof | |
CN220468821U (en) | Seepage-proof plastic steel sheet pile for soft soil foundation | |
CN113513026A (en) | Soft soil foundation deep foundation pit pile end rear anchoring combined steel sheet pile and construction method thereof | |
CN220318509U (en) | Tubular pile connecting device | |
CN213114893U (en) | Drainage pile for construction drainage | |
CN214460427U (en) | High-efficient pipe that punches a hole of forked drilling bored concrete pile | |
CN220486416U (en) | A composite pile structure that can improve the bearing capacity of pile foundations | |
CN212926027U (en) | Assembled foundation treatment device | |
CN217500343U (en) | Construction structures that floats is prevented to bored concrete pile steel reinforcement cage | |
CN219951913U (en) | Stiff composite pile | |
JPS603144Y2 (en) | Earth retention shoring device for excavated trenches | |
CN222252256U (en) | Building engineering foundation reinforcing apparatus | |
CN215948905U (en) | Can have enough to meet need reverse beam template and consolidate and thick controlling means of board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |