[go: up one dir, main page]

CN114775664B - A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam - Google Patents

A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam Download PDF

Info

Publication number
CN114775664B
CN114775664B CN202210574920.9A CN202210574920A CN114775664B CN 114775664 B CN114775664 B CN 114775664B CN 202210574920 A CN202210574920 A CN 202210574920A CN 114775664 B CN114775664 B CN 114775664B
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
steel
foundation pit
guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210574920.9A
Other languages
Chinese (zh)
Other versions
CN114775664A (en
Inventor
冯四超
卓雷
秦定松
韩旭
邵海明
师忠盼
宣鑫鹏
武文家
陶倩倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
China Railway First Engineering Group Bridge Engineering Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
China Railway First Engineering Group Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, China Railway First Engineering Group Bridge Engineering Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN202210574920.9A priority Critical patent/CN114775664B/en
Publication of CN114775664A publication Critical patent/CN114775664A/en
Application granted granted Critical
Publication of CN114775664B publication Critical patent/CN114775664B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/08Locking forms; Edge joints; Pile crossings; Branch pieces
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The application relates to a steel sheet pile cofferdam construction method for a deep foundation pit and a steel sheet pile cofferdam, and relates to the technical field of cofferdam construction. The steel sheet pile cofferdam construction method comprises the steps of firstly obtaining geological information of a construction site, determining a construction area, setting a guide structure in the construction area, then sequentially inserting and driving steel sheet piles under the guide of the guide structure, selecting water cutters or air cutters to alternately guide holes according to the obtained geological information in the inserting and driving process so as to assist the steel sheet piles to be inserted and driven to a preset depth, excavating a foundation pit after closure of the steel sheet piles is completed, setting a plurality of inner supporting structures from top to bottom in the excavating process, and finally injecting back cover concrete towards the bottom of the foundation pit along the outer side wall of the steel sheet piles to finish back cover of the foundation pit. The construction method of the steel sheet pile cofferdam provided by the application realizes that the steel sheet pile can be inserted and driven to a deeper depth under the combined assistance of the water knife and the air knife, has good water-proof effect, and reduces the difficulty of construction hoisting.

Description

一种用于深基坑的钢板桩围堰施工方法及钢板桩围堰A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam

技术领域Technical Field

本申请涉及围堰施工技术领域,特别涉及一种用于深基坑的钢板桩围堰施工方法及钢板桩围堰。The present application relates to the technical field of cofferdam construction, and in particular to a steel sheet pile cofferdam construction method and a steel sheet pile cofferdam for a deep foundation pit.

背景技术Background Art

围堰是指在桥梁、港口及水利工程建设中,为建造永久性设施,在基坑周围修建的临时性挡水结构,其作用主要是防止水和土进入建筑物修建位置,以便在围堰内进行排水、排土的施工,使基坑开挖、建筑物修建在干涸的条件下进行。A cofferdam refers to a temporary water retaining structure built around a foundation pit for the purpose of constructing permanent facilities during the construction of bridges, ports and water conservancy projects. Its main function is to prevent water and soil from entering the construction site of the building so that drainage and soil discharge construction can be carried out within the cofferdam, allowing foundation pit excavation and building construction to be carried out under dry conditions.

围堰的种类有很多种,目前常用的围堰包括土石围堰、木质围堰、钢板桩围堰、钢管桩围堰以及钢板桩和钢管桩的组合型围堰,在大型的施工中,常用的围堰为钢板桩围堰、钢管桩围堰以及钢板桩和钢管桩的组合型围堰,其根据施工的规模、施工的地质环境等选择对应的围堰。一般钢板桩具有高强、轻质、隔水性好、使用寿命长、安全性高、对空间要求低、环保效果显著等众多的优点,再加上施工简单、工期短、可重复使用、建设费用低,其施工工艺比钢管桩及组合型围堰均简单很多,因此钢板桩的用途相当广泛。但是钢板桩受插打深度的限制,在目前,钢板桩最深的插打深度不超过10米,否则会出现变形的问题,继而影响围堰的隔离效果。There are many types of cofferdams. Commonly used cofferdams include earth and rock cofferdams, wooden cofferdams, steel sheet pile cofferdams, steel pipe pile cofferdams, and combined cofferdams of steel sheet piles and steel pipe piles. In large-scale construction, commonly used cofferdams are steel sheet pile cofferdams, steel pipe pile cofferdams, and combined cofferdams of steel sheet piles and steel pipe piles. The corresponding cofferdams are selected according to the scale of construction and the geological environment of construction. Generally, steel sheet piles have many advantages such as high strength, light weight, good water-proofing, long service life, high safety, low space requirements, and significant environmental protection effects. In addition, the construction is simple, the construction period is short, it can be reused, and the construction cost is low. Its construction process is much simpler than that of steel pipe piles and combined cofferdams. Therefore, the use of steel sheet piles is quite extensive. However, steel sheet piles are limited by the insertion depth. At present, the deepest insertion depth of steel sheet piles does not exceed 10 meters, otherwise deformation problems will occur, which will affect the isolation effect of the cofferdam.

因此在相关技术中,规模比较大且深度比较深的围堰往往采用钢管桩围堰,其的插打深度比钢板桩大,且不易变形,能适用硬质土层。但是,钢管桩围堰整体的施工难度很大,在插打过程中的挤土效应大,整体施工工期长,施工成本高。Therefore, in the related technology, steel pipe pile cofferdams are often used for cofferdams with larger scale and deeper depth, because the steel pipe pile cofferdams have a greater insertion depth than steel sheet piles, are not easily deformed, and can be applied to hard soil layers. However, the overall construction of steel pipe pile cofferdams is very difficult, the soil squeezing effect is large during the insertion process, the overall construction period is long, and the construction cost is high.

发明内容Summary of the invention

本申请实施例提供一种用于深基坑的钢板桩围堰施工方法及钢板桩围堰,以解决相关技术中钢板桩不能适应深基坑的围堰施工,在插打过程中容易变形而影响围堰性能的问题。The embodiments of the present application provide a steel sheet pile cofferdam construction method and a steel sheet pile cofferdam for a deep foundation pit, so as to solve the problem in the related art that the steel sheet piles cannot adapt to the cofferdam construction of a deep foundation pit and are easily deformed during the insertion process, thereby affecting the cofferdam performance.

第一方面,提供了一种用于深基坑的钢板桩围堰施工方法,其步骤包括:In a first aspect, a steel sheet pile cofferdam construction method for a deep foundation pit is provided, the steps comprising:

获取施工场地的地质信息,并确定施工区域;Obtain geological information of the construction site and determine the construction area;

在所述施工区域内设置导向结构;Providing a guide structure within the construction area;

在所述导向结构的导向下依次插打钢板桩,并在插打的过程中根据获取的所述地质信息选择水刀或气刀交替引孔,以辅助所述钢板桩插打至预设深度;The steel sheet piles are inserted and driven in sequence under the guidance of the guide structure, and during the insertion and driving process, a water jet or an air jet is selected to alternately guide holes according to the acquired geological information to assist the steel sheet piles to be inserted and driven to a preset depth;

完成所述钢板桩的合龙,对基坑进行挖掘,并在挖掘的过程从上至下设置多个内支撑结构;The steel sheet piles are connected together, the foundation pit is excavated, and a plurality of internal support structures are arranged from top to bottom during the excavation process;

沿所述钢板桩的外侧壁朝基坑底部注入封底混凝土,完成所述基坑的封底。The bottom sealing concrete is injected along the outer side wall of the steel sheet pile toward the bottom of the foundation pit to complete the bottom sealing of the foundation pit.

一些实施例中,所述在所述施工区域的预设位置设置导向结构,其步骤包括:In some embodiments, the step of setting a guide structure at a preset position in the construction area includes:

在所述施工区域内依次确定钢板桩的插打点位;Determine the driving points of the steel sheet piles in sequence within the construction area;

分别在确定的一圈所述插打点位的内侧和外侧沿所述插打点位的排列轨迹依次插打多根钢管桩,插打完毕后在位于内侧和外侧的所述钢管桩的顶部分别设置导向工字钢;Sequentially driving a plurality of steel pipe piles on the inner side and the outer side of a circle of driving points along the arrangement track of the driving points, and after driving is completed, respectively setting guide I-beams on the tops of the steel pipe piles located on the inner side and the outer side;

在位于内侧和外侧的所述导向工字钢上滑设多个间隔设置的限位钢筋条。A plurality of spacing reinforcement bars are slidably arranged on the guide I-beams located at the inner and outer sides.

一些实施例中,所述在所述导向结构的导向下依次插打钢板桩,其步骤还包括:In some embodiments, the step of inserting the steel sheet piles in sequence under the guidance of the guide structure further includes:

调节其中一所述限位钢筋条至对应的所述插打点位的一侧;Adjust one of the limiting steel bars to one side of the corresponding insertion point;

插打所述钢板桩,在插打的过程中分别利用位于内侧和外侧的所述导向工字钢共同辅助校正所述钢板桩沿内侧至外侧这一方向上的位置,还利用所述限位钢筋条辅助校正所述钢板桩沿左右方向的位置。The steel sheet piles are driven in, and during the driving process, the guide I-beams located on the inner and outer sides are respectively used to assist in correcting the position of the steel sheet piles in the direction from the inner side to the outer side, and the limiting steel bars are also used to assist in correcting the position of the steel sheet piles in the left-right direction.

一些实施例中,所述在插打的过程中根据获取的所述地质信息选择水刀或气刀交替引孔,以辅助所述钢板桩插打至预设深度,其步骤包括:In some embodiments, during the driving process, water jet or air knife is selected to alternately guide holes according to the acquired geological information to assist the driving of the steel sheet pile to a preset depth, and the steps include:

确定当前插打深度的地质信息,若当前插打深度的地质信息为硬塑黏土或砂砾土,则采用水刀进行引孔,若当前插打深度的地质信息为泥质粉砂岩或强风化岩,则采用气刀进行引孔;Determine the geological information of the current drilling depth. If the geological information of the current drilling depth is hard plastic clay or gravel soil, use a water knife to guide the hole. If the geological information of the current drilling depth is muddy siltstone or strongly weathered rock, use an air knife to guide the hole.

在插打的过程中根据所述地质信息选择水刀或气刀交替引孔,直至所述钢板桩插打至所述预设深度。During the driving process, water jet or air knife is selected to alternately drill holes according to the geological information until the steel sheet pile is driven to the preset depth.

一些实施例中,在插打所述钢板桩前还包括:In some embodiments, before inserting the steel sheet pile, the method further includes:

在所述钢板桩的腹板内壁沿其长度方向设置竖直设置的引孔管,并在所述引孔管的底端设置至少两个朝下方设置的引孔喷嘴;A vertically arranged hole-introducing pipe is arranged on the inner wall of the web of the steel sheet pile along its length direction, and at least two downwardly arranged hole-introducing nozzles are arranged at the bottom end of the hole-introducing pipe;

在所述钢板桩的腹板外壁沿其长度方向设置竖直设置的注浆管。A vertically arranged grouting pipe is arranged on the outer wall of the web of the steel sheet pile along its length direction.

一些实施例中,在插打所述钢板桩前还包括:In some embodiments, before inserting the steel sheet pile, the method further includes:

在所述钢板桩的扣锁上涂抹防水剂;Applying a waterproofing agent on the buckle of the steel sheet pile;

所述防水剂包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为52:38:5:75:3:10:5:5:10,所述石英砂包括100目的石英砂和200目的石英砂,且100目的石英砂和200目的石英砂的质量比为15:4。The waterproofing agent includes silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane single-component single-component two-component type I, polyurethane single-component two-component type II, cement-based permeable crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is 52:38:5:75:3:10:5:5:10. The quartz sand includes 100-mesh quartz sand and 200-mesh quartz sand, and the mass ratio of 100-mesh quartz sand to 200-mesh quartz sand is 15:4.

一些实施例中,所述在挖掘的过程从上至下设置多个内支撑结构,其步骤包括:In some embodiments, the steps of setting up multiple internal support structures from top to bottom during the excavation process include:

沿钢板桩围堰的内壁设置钢围檩;Steel purlins are set along the inner wall of the steel sheet pile cofferdam;

在所述钢围檩上设置内支撑结构;An internal supporting structure is provided on the steel purlin;

继续朝下方挖掘,并依次设置所述钢围檩和内支撑结构,且挖掘深度越大,相邻两个所述钢围檩或内支撑结构之间的间距越小。Continue to dig downwards, and sequentially set the steel perimeter purlins and the inner support structure. The greater the digging depth, the smaller the distance between two adjacent steel perimeter purlins or inner support structures.

第二方面,提供了一种用于深基坑的钢板桩围堰,其包括:In a second aspect, a steel sheet pile cofferdam for a deep foundation pit is provided, comprising:

围堰主体,其包括多根首尾相连的钢板桩,每一所述钢板桩上均设有引孔组件和注液组件,所述引孔组件用于根据施工场地的地质信息选择水刀或气刀交替引孔,以辅助所述钢板桩插打至预设深度,所述注液组件用于沿所述钢板桩的外侧壁朝基坑底部注入封底混凝土,以完成所述基坑的封底;The cofferdam body comprises a plurality of steel sheet piles connected end to end, each of the steel sheet piles is provided with a hole-guiding assembly and a liquid injection assembly, the hole-guiding assembly is used to select a water knife or an air knife to alternately guide holes according to the geological information of the construction site to assist the steel sheet piles to be driven to a preset depth, and the liquid injection assembly is used to inject bottom sealing concrete along the outer side wall of the steel sheet pile toward the bottom of the foundation pit to complete the bottom sealing of the foundation pit;

导向结构,其沿所述围堰主体的周向设置,所述导向结构用于为所述钢板桩在插打时导向。A guide structure is arranged along the circumference of the cofferdam body, and the guide structure is used to guide the steel sheet piles when they are inserted.

一些实施例中,所述导向结构包括多根钢管桩,一部分所述钢管桩沿所述钢板桩的排列轨迹在所述钢管桩的内侧间隔设置,剩余部分所述钢管桩沿所述钢板桩的排列轨迹在所述钢管桩的外侧间隔设置,位于内侧和外侧的所述钢管桩的顶部均设有多根导向工字钢,位于内侧和外侧的所述导向工字钢上滑设多个间隔设置的限位钢筋条;In some embodiments, the guide structure includes a plurality of steel pipe piles, a portion of the steel pipe piles are arranged at intervals on the inner side of the steel pipe piles along the arrangement track of the steel sheet piles, and the remaining portion of the steel pipe piles are arranged at intervals on the outer side of the steel pipe piles along the arrangement track of the steel sheet piles, and a plurality of guide I-beams are provided on the tops of the steel pipe piles located on the inner and outer sides, and a plurality of spaced limiting steel bars are slidably provided on the guide I-beams located on the inner and outer sides;

所述导向工字钢用于限制所述钢板桩插打时沿朝内侧或外侧的方向偏移,所述限位钢筋条用于限制所述钢板桩插打时沿左右侧偏移。The guide I-beam is used to limit the deviation of the steel sheet piles in the inner or outer direction when they are driven in, and the limit steel bar is used to limit the deviation of the steel sheet piles in the left or right direction when they are driven in.

一些实施例中,每一所述钢板桩的扣锁上均涂覆有防水剂,所述防水剂包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为52:38:5:75:3:10:5:5:10,所述石英砂包括100目的石英砂和200目的石英砂,且100目的石英砂和200目的石英砂的质量比为15:4。In some embodiments, each buckle of the steel sheet pile is coated with a waterproofing agent, which includes silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane one-component single-two-component type I, polyurethane one-component two-component type II, cement-based permeable crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is 52:38:5:75:3:10:5:5:10, and the quartz sand includes 100 mesh quartz sand and 200 mesh quartz sand, and the mass ratio of 100 mesh quartz sand and 200 mesh quartz sand is 15:4.

本申请提供的技术方案带来的有益效果包括:The beneficial effects of the technical solution provided by this application include:

本申请实施例提供了一种用于深基坑的钢板桩围堰施工方法,由于先在施工区域内设置导向结构,再根据获取的施工场地的地质信息在导向结构的导向下依次插打钢板桩,在插打的过程中根据获取的地质信息选择水刀或气刀交替引孔,以辅助钢板桩插打至预设深度,在对基坑挖掘的过程从上至下设置多个内支撑结构,最后沿钢板桩的外侧壁朝基坑底部注入封底混凝土,完成基坑的封底,因此,本钢板桩围堰施工方法在水刀和气刀的联合辅助下,实现了钢板桩可以插打更深的深度,且在插打过程中不会变形,以保证围堰的基础性能;另外,在整个施工过程中大大减少了取土量和混凝土的使用,隔水效果好,由于钢板桩相对质量较轻,也减小了施工吊装的难度;最后利用钢板桩自身做为母桩以供引孔及注浆,避免了单独插打母桩在后期拔出的过程中造成土层松散,影响钢板桩的插打以及围堰基础性能的问题。The embodiment of the present application provides a steel sheet pile cofferdam construction method for a deep foundation pit, in which a guide structure is first arranged in the construction area, and then the steel sheet piles are inserted and driven in sequence under the guidance of the guide structure according to the geological information of the construction site obtained, and in the process of inserting and driving, a water knife or an air knife is selected to alternately guide holes according to the geological information obtained to assist the steel sheet piles to be inserted and driven to a preset depth, and a plurality of internal support structures are arranged from top to bottom in the process of excavating the foundation pit, and finally, bottom sealing concrete is injected toward the bottom of the foundation pit along the outer wall of the steel sheet pile to complete the bottom sealing of the foundation pit. With the joint assistance of water jet and air knife, the weir construction method can achieve that the steel sheet piles can be driven deeper and will not be deformed during the driving process, so as to ensure the basic performance of the cofferdam; in addition, the amount of soil taken and the use of concrete are greatly reduced in the entire construction process, and the water-proof effect is good. Since the steel sheet piles are relatively light in weight, the difficulty of construction and hoisting is also reduced; finally, the steel sheet piles themselves are used as mother piles for drilling and grouting, avoiding the problem of loose soil layer caused by the subsequent withdrawal of the mother piles, which affects the driving of the steel sheet piles and the basic performance of the cofferdam.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

为了更清楚地说明本申请实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

图1为本申请实施例提供的用于深基坑的钢板桩围堰施工方法的流程图;FIG1 is a flow chart of a steel sheet pile cofferdam construction method for a deep foundation pit provided in an embodiment of the present application;

图2为本申请实施例提供的用于深基坑的钢板桩围堰的俯视图。FIG2 is a top view of a steel sheet pile cofferdam for a deep foundation pit provided in an embodiment of the present application.

图中:1-围堰主体,2-钢板桩,3-导向结构,30-导向工字钢,31-限位钢筋条。In the figure: 1-cofferdam body, 2-steel sheet piles, 3-guide structure, 30-guide I-beam, 31-limiting steel bar.

具体实施方式DETAILED DESCRIPTION

为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本申请的一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本申请保护的范围。In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

本申请实施例提供了一种用于深基坑的钢板桩围堰施工方法,其能解决相关技术中钢板桩不能适应深基坑的围堰施工,在插打过程中容易变形而影响围堰性能的问题。The embodiment of the present application provides a steel sheet pile cofferdam construction method for deep foundation pits, which can solve the problem in the related art that steel sheet piles cannot adapt to the cofferdam construction of deep foundation pits and are easily deformed during the insertion process, thereby affecting the cofferdam performance.

参见图1所示,本钢板桩围堰施工方法的步骤包括:首先获取施工场地的地质信息,并确定施工区域,随后在施工区域内设置导向结构3,在导向结构3的导向下依次插打钢板桩2,并在插打的过程中根据获取的地质信息选择水刀或气刀交替引孔,以辅助钢板桩2插打至预设深度,然后完成钢板桩2的合龙,对基坑进行挖掘,并在挖掘的过程从上至下设置多个内支撑结构,最后沿钢板桩2的外侧壁朝基坑底部注入封底混凝土,完成基坑的封底。As shown in Figure 1, the steps of the steel sheet pile cofferdam construction method include: first, obtaining the geological information of the construction site and determining the construction area, then setting a guide structure 3 in the construction area, and inserting the steel sheet piles 2 in sequence under the guidance of the guide structure 3, and selecting a water knife or an air knife to alternately guide holes according to the acquired geological information during the insertion process to assist the steel sheet piles 2 to be inserted to a preset depth, and then completing the closure of the steel sheet piles 2, excavating the foundation pit, and setting a plurality of internal support structures from top to bottom during the excavation process, and finally injecting bottom sealing concrete along the outer wall of the steel sheet pile 2 toward the bottom of the foundation pit to complete the bottom sealing of the foundation pit.

本钢板桩围堰施工方法通过水刀和气刀的联合采用,根据施工场地具体的地质情况,在水刀和气刀的联合辅助下,使得钢板桩2可以实现插打更深的深度,克服了在插打过程中随着深度越深可能出现变形的问题,使得在插打过程中不会变形,保证了围堰的基础性能;另外,相比采用其他的围堰形式,本钢板桩围堰施工方法在整个施工过程中大大减少了取土量和混凝土的使用,且隔水效果比钢管桩突出,由于钢板桩2相对质量较轻,也减小了施工吊装的难度,降低了施工难度;最后利用钢板桩2自身做为母桩以供引孔及注浆,避免了单独插打母桩在后期拔出的过程中可能造成土层松散,影响钢板桩2的插打以及围堰基础性能的问题。The present steel sheet pile cofferdam construction method adopts the combined use of water jets and air knives. According to the specific geological conditions of the construction site, with the joint assistance of water jets and air knives, the steel sheet piles 2 can be driven to a deeper depth, thus overcoming the problem of deformation that may occur with increasing depth during the driving process, so that the steel sheet piles will not be deformed during the driving process, thereby ensuring the basic performance of the cofferdam. In addition, compared with other cofferdam forms, the present steel sheet pile cofferdam construction method greatly reduces the amount of soil taken and the use of concrete during the entire construction process, and the water-isolating effect is more prominent than that of steel pipe piles. Since the steel sheet piles 2 are relatively light in weight, the difficulty of construction hoisting is also reduced, thereby reducing the construction difficulty. Finally, the steel sheet piles 2 themselves are used as mother piles for guide holes and grouting, thereby avoiding the problem that the soil layer may become loose during the later extraction of the mother piles driven alone, thereby affecting the driving of the steel sheet piles 2 and the basic performance of the cofferdam.

进一步的,在施工区域的预设位置设置导向结构3,其步骤主要包括:Furthermore, a guide structure 3 is set at a preset position in the construction area, and the steps mainly include:

在施工区域内依次确定钢板桩2的插打点位;Determine the insertion points of the steel sheet piles 2 in sequence within the construction area;

分别在确定的一圈插打点位的内侧和外侧沿插打点位的排列轨迹依次插打多根钢管桩,插打完毕后在位于内侧和外侧的钢管桩的顶部分别设置导向工字钢30;A plurality of steel pipe piles are sequentially driven inwardly and outwardly of a circle of determined driving points along the arrangement track of the driving points, and after driving is completed, guide I-beams 30 are respectively arranged on the tops of the steel pipe piles located inwardly and outwardly;

在位于内侧和外侧的导向工字钢30上滑设多个间隔设置的限位钢筋条31。A plurality of spacing reinforcement bars 31 are slidably mounted on the guide I-beams 30 located at the inner and outer sides.

进一步的,在导向结构3的导向下依次插打钢板桩2,其步骤还包括:Furthermore, the steel sheet piles 2 are inserted in sequence under the guidance of the guide structure 3, and the steps also include:

调节其中一限位钢筋条31至对应的插打点位的一侧;Adjust one of the limiting steel bars 31 to one side of the corresponding insertion point;

插打钢板桩2,在插打的过程中分别利用位于内侧和外侧的导向工字钢30共同辅助校正钢板桩2沿内侧至外侧这一方向上的位置,还利用限位钢筋条31辅助校正钢板桩2沿左右方向的位置。When inserting the steel sheet pile 2, the guide I-beams 30 located on the inside and outside are used to assist in correcting the position of the steel sheet pile 2 from the inside to the outside during the inserting process, and the limiting steel bar 31 is used to assist in correcting the position of the steel sheet pile 2 along the left and right direction.

具体的,在施工区域内确定各个插打点位,将各个插打点位标明后并经过复核无误后加以有效保护,随后分别在确定的一圈插打点位的内侧和外侧沿插打点位的排列轨迹依次插打多根钢管桩,利用插打的钢管桩进行初步的定位,位于内侧和外侧的钢管桩的走向均与围堰的形状对应,即均构成方形结构,在位于内侧和外侧的每一边的钢管桩上均设置导向工字钢30,导向工字钢30设置完毕后,在内外侧的同侧的导向工字钢30上架设可以沿导向工字钢长度方向滑动的限位钢筋条31,在开始插打钢板桩2时,利用位于内侧和外侧的导向工字钢30的想面侧面的侧壁共同辅助校正钢板桩2沿内侧至外侧这一方向上的位置,即作为一个基准,避免钢板桩2在插打的过程中向外侧或内侧的方向偏移,同理的,限位钢筋条31用于辅助校正钢板桩2沿左右方向的位置,避免钢板桩2在插打的过程中朝左右方向偏移。导向工字钢30和限位钢筋条31在打桩时作为导向位置及高程控制标志,可以保证打出的同侧的钢板桩2在一条直线上。Specifically, each driving point is determined in the construction area, and each driving point is marked and effectively protected after verification. Subsequently, a plurality of steel pipe piles are driven in sequence along the arrangement trajectory of the driving points on the inner and outer sides of a circle of determined driving points, and preliminary positioning is performed using the driven steel pipe piles. The directions of the steel pipe piles on the inner and outer sides correspond to the shape of the cofferdam, that is, they both form a square structure. A guide I-beam 30 is set on the steel pipe piles on each side of the inner and outer sides. After the guide I-beam 30 is set, A limit steel bar 31 that can slide along the length direction of the guide I-beam 30 is set on the side. When the steel sheet pile 2 starts to be driven, the side walls of the inner and outer guide I-beams 30 are used to assist in correcting the position of the steel sheet pile 2 from the inside to the outside, that is, as a reference to prevent the steel sheet pile 2 from deviating to the outside or inside during the driving process. Similarly, the limit steel bar 31 is used to assist in correcting the position of the steel sheet pile 2 along the left and right directions to prevent the steel sheet pile 2 from deviating to the left and right directions during the driving process. The guide I-beam 30 and the limit steel bar 31 serve as guide position and elevation control marks during pile driving, which can ensure that the driven steel sheet piles 2 on the same side are in a straight line.

进一步的,在插打的过程中根据获取的地质信息选择水刀或气刀交替引孔,以辅助钢板桩2插打至预设深度,其步骤包括:Furthermore, in the process of driving and inserting, water jet or air knife is selected to alternately guide holes according to the acquired geological information to assist the steel sheet pile 2 in driving and inserting to a preset depth, and the steps include:

确定当前插打深度的地质信息,若当前插打深度的地质信息为硬塑黏土或砂砾土,则采用水刀进行引孔,若当前插打深度的地质信息为泥质粉砂岩或强风化岩,则采用气刀进行引孔;Determine the geological information of the current drilling depth. If the geological information of the current drilling depth is hard plastic clay or gravel soil, use a water knife to guide the hole. If the geological information of the current drilling depth is muddy siltstone or strongly weathered rock, use an air knife to guide the hole.

在插打的过程中根据地质信息选择水刀或气刀交替引孔,直至钢板桩2插打至预设深度。During the driving process, water jet or air knife is selected to alternately drill holes according to geological information until the steel sheet pile 2 is driven to a preset depth.

进一步的,在插打钢板桩2前还包括:Furthermore, before inserting the steel sheet pile 2, the method further includes:

在钢板桩2的腹板内壁沿其长度方向设置竖直设置的引孔管,并在引孔管的底端设置至少两个朝下方设置的引孔喷嘴;A vertically arranged hole-introducing pipe is arranged on the inner wall of the web of the steel sheet pile 2 along its length direction, and at least two hole-introducing nozzles arranged downward are arranged at the bottom end of the hole-introducing pipe;

在钢板桩2的腹板外壁沿其长度方向设置竖直设置的注浆管。A vertical grouting pipe is arranged on the outer wall of the web of the steel sheet pile 2 along its length direction.

由于有些施工场地地质比较复杂,因此根据不同深度时对应的具体的地质信息,选择性的选择利用气刀或水刀进行引孔,具体的,若因底层硬塑黏土、砂砾土环境,导致插打不到位时,则采用高压射水辅助的方式配合钢板桩2插打,通过喷射高压水流,对钢板桩2空腔内的土层进行冲击,使周围土质受到扰动后液化,减少钢板桩2打入土层时受到的阻力,进而减少插打过程中钢板桩2扭曲、受损的可能,降低施工成本,加快施工进度,保证了施工质量;若底层地质环境变为泥质粉砂岩、强风化岩等强度更高的土质,此时再利用水刀也难以进行引孔,因此将水刀换成气刀,采用高压气冲辅助的方式配合钢板桩2的插打,高压气体在钢板桩2的桩头处会形成一个无水状态的空气区,隔离水后高压气体直接对岩层造成破坏,并在水浮力的影响下将气体上浮,整个引孔过程中对其地质再次进行液化,此高压气体水中引孔工艺对地质破坏更直接,扰动土体更高效,能显著增大钢板桩2入土的深度,保证钢板桩2插打更深的深度。Since the geology of some construction sites is relatively complex, air knives or water knives are selectively used to guide holes according to the specific geological information corresponding to different depths. Specifically, if the insertion and driving cannot be in place due to the underlying hard plastic clay or gravel soil environment, high-pressure water jetting is used to assist in the insertion and driving of steel sheet piles 2. By spraying high-pressure water flow, the soil layer in the cavity of the steel sheet pile 2 is impacted, so that the surrounding soil is liquefied after being disturbed, reducing the resistance encountered by the steel sheet pile 2 when it is driven into the soil layer, thereby reducing the possibility of distortion and damage of the steel sheet pile 2 during the insertion and driving process, reducing construction costs, speeding up construction progress, and ensuring construction quality. If the underlying soil is too deep, the steel sheet pile 2 will be easily damaged. The geological environment changes to higher strength soil such as muddy siltstone and strongly weathered rock. At this time, it is difficult to use a water knife to drill a hole. Therefore, the water knife is replaced with an air knife, and a high-pressure gas blow is used to assist the insertion of the steel sheet pile 2. The high-pressure gas will form an air zone in a water-free state at the pile head of the steel sheet pile 2. After isolating the water, the high-pressure gas directly damages the rock formation and floats under the influence of water buoyancy. During the entire drilling process, the geology is liquefied again. This high-pressure gas underwater drilling process has a more direct impact on the geology and more efficient soil disturbance. It can significantly increase the depth of the steel sheet pile 2 into the soil and ensure that the steel sheet pile 2 is driven deeper.

具体的,相比相关技术中采用单独的母桩作为引孔钢板,本钢板桩围堰施工方法中直接将需要插打的钢板桩2作为引孔母桩,因此需要插打的钢板桩2既是围堰的结构组成部分,也是用于设置引孔管和注浆管的母桩,作为围堰的结构组成部分,在完成引孔后,不需要再从土层中拔出,缩减施工工艺的同时,也避免了在拔出的过程破坏土层结构,影响后续钢板桩2的插打。Specifically, compared with the related art that uses a separate mother pile as a guide hole steel plate, the steel sheet pile 2 that needs to be driven in the present steel sheet pile cofferdam construction method is directly used as the guide hole mother pile. Therefore, the steel sheet pile 2 that needs to be driven in is not only a structural component of the cofferdam, but also a mother pile for setting the guide hole pipe and the grouting pipe. As a structural component of the cofferdam, it does not need to be pulled out from the soil layer after the guide hole is completed. While reducing the construction process, it also avoids damaging the soil layer structure during the pulling out process, affecting the subsequent driving of the steel sheet pile 2.

具体的,沿着钢板桩2的腹板内壁沿其长度方向设置竖直设置的引孔管,该引孔管在采用水刀和气刀时通用,利用固定卡扣将引孔管沿钢板桩2的长度方向固定,在距离钢板桩2的底部约20cm处,在引孔管的底端焊接两个喷嘴,喷口呈尖形,且嘴口直径大小约为1cm,将引孔管的顶端与高压水泵或高压气泵连通。在采用水刀时,先用振动锤把钢板桩2打入土层1~2m,然后再打开高压水泵,高压水泵压力控制在5~10Mpa,喷嘴终端压力保持在300~500Mpa,具体可根据现场实际情况进行测试或调整,进行施工射水辅助钢板桩2下沉,直到打至设计标高,并在设计高程停放5~10s。在采用气刀时,连通高压气泵,打开高压气泵后,气泵压力控制在3~15Mpa,喷嘴终端压力保持在300~500Mpa,具体可根据现场实际情况进行测试或调整,待高压气泵压力基本稳定后,继续沉桩,直到设计高程,最后同理将钢板桩2在设计高程处停放5-10s。Specifically, a vertically arranged lead-in hole pipe is arranged along the inner wall of the web of the steel sheet pile 2 along its length direction. The lead-in hole pipe is common when using a water knife and an air knife. The lead-in hole pipe is fixed along the length direction of the steel sheet pile 2 by a fixing buckle. Two nozzles are welded at the bottom of the lead-in hole pipe at a distance of about 20 cm from the bottom of the steel sheet pile 2. The nozzle is pointed and the nozzle diameter is about 1 cm. The top of the lead-in hole pipe is connected to a high-pressure water pump or a high-pressure air pump. When using a water knife, first use a vibrating hammer to drive the steel sheet pile 2 into the soil layer 1~2m, and then turn on the high-pressure water pump. The pressure of the high-pressure water pump is controlled at 5~10Mpa, and the nozzle terminal pressure is maintained at 300~500Mpa. It can be tested or adjusted according to the actual situation on site, and water jetting is used to assist the steel sheet pile 2 to sink until it reaches the designed elevation and parked at the designed elevation for 5~10s. When using an air knife, connect the high-pressure air pump. After turning on the high-pressure air pump, the air pump pressure is controlled at 3~15Mpa, and the nozzle terminal pressure is maintained at 300~500Mpa. The specific test or adjustment can be carried out according to the actual situation on site. After the pressure of the high-pressure air pump is basically stable, continue to sink the pile until the designed elevation is reached. Finally, park the steel sheet pile 2 at the designed elevation for 5-10s.

进一步的,在插打钢板桩2前还包括:Furthermore, before inserting the steel sheet pile 2, the method further includes:

在钢板桩2的扣锁上涂抹防水剂;Apply waterproofing agent on the buckle of steel sheet pile 2;

防水剂包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为52:38:5:75:3:10:5:5:10,石英砂包括100目的石英砂和200目的石英砂,且100目的石英砂和200目的石英砂的质量比为15:4。The waterproofing agent includes silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane one-component one-two component type I, polyurethane one-component two-component type II, cement-based penetrating crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is 52:38:5:75:3:10:5:5:10. The quartz sand includes 100 mesh quartz sand and 200 mesh quartz sand, and the mass ratio of 100 mesh quartz sand to 200 mesh quartz sand is 15:4.

具体的,由于对于钢板桩2而言,主要依靠相邻两个钢板桩2相互扣合的扣锁进行封闭,扣锁之间再结合紧密也是刚性接触,存在较大的泄漏风险。因此,为了保障钢板桩2扣锁与扣锁之间的连接得紧密性,减少水下漏水的可能性,在钢板桩2插打前,分别在每一钢板桩2的扣锁上分别涂抹防水剂,该防水剂为针对该种类型的围堰自配的一种防水剂,其成分主要包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为52:38:5:75:3:10:5:5:10,其中,石英砂包含两种不同目数的石英砂,分别为100目的石英砂和200目的石英砂。其中,硅酸盐水泥的质量为480~540g,石英砂的质量为360~400g,抗渗料粉煤灰的质量为40~60g,有机硅憎水粉的质量为720~760g,HPMC纤维素的质量为20~40g,聚氨酯单组分单双组份I型的质量为80~120g,聚氨酯单组分双组份II型的质量为40~60g,水泥基渗透结晶的质量为40~60g,聚合物水泥防水涂料JS的质量为80~120g。Specifically, for the steel sheet pile 2, the closure is mainly carried out by the buckle locks of two adjacent steel sheet piles 2, and the buckle locks are tightly connected and are also rigidly contacted, which has a greater risk of leakage. Therefore, in order to ensure the tightness of the connection between the buckle locks of the steel sheet pile 2 and reduce the possibility of underwater leakage, before the steel sheet pile 2 is inserted, a waterproofing agent is applied to the buckle locks of each steel sheet pile 2. The waterproofing agent is a waterproofing agent prepared for this type of cofferdam, and its components mainly include silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane single component single and double component type I, polyurethane single component double component type II, cement-based permeable crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is 52:38:5:75:3:10:5:5:10, wherein the quartz sand includes two different mesh sizes of quartz sand, 100 mesh quartz sand and 200 mesh quartz sand. Among them, the mass of silicate cement is 480~540g, the mass of quartz sand is 360~400g, the mass of anti-seepage material fly ash is 40~60g, the mass of silicone hydrophobic powder is 720~760g, the mass of HPMC cellulose is 20~40g, the mass of polyurethane one-component single-component and two-component type I is 80~120g, the mass of polyurethane one-component and two-component type II is 40~60g, the mass of cement-based permeable crystallization is 40~60g, and the mass of polymer cement waterproof coating JS is 80~120g.

进一步的,在挖掘的过程从上至下设置多个内支撑结构,其步骤包括:Furthermore, multiple internal support structures are arranged from top to bottom during the excavation process, and the steps include:

沿钢板桩2围堰的内壁设置钢围檩;Steel purlins are arranged along the inner wall of the steel sheet pile 2 cofferdam;

在钢围檩上设置内支撑结构;An internal support structure is provided on the steel perimeter purlin;

继续朝下方挖掘,并依次设置钢围檩和内支撑结构,且挖掘深度越大,相邻两个钢围檩或内支撑结构之间的间距越小。Continue to dig downwards and set steel purlins and internal support structures in sequence. The greater the digging depth, the smaller the distance between two adjacent steel purlins or internal support structures.

具体的,钢板桩2插打完毕后,开挖至第一道内支撑结构底标高下0.5m处,安装第一道内支撑结构,第一道内支撑结构安装完毕后,继续向下开挖至第二道内支撑结构底部下方0.5m处,安装第二道内支撑结构,第二道内支撑结构安装完毕,继续向下开挖至第三道内支撑底下0.5m处,安装第三道内支撑结构,依次循环,一般根据目前大部分深基坑的规模,大概设置四道内支撑结构就足够了,不过内支撑结构的具体数量可以根据实际的施工深度及规模大小来定。其中,由于深基坑的规模一般较大,为了保证结构的稳定性,一般在安装每一层内支撑结构前,会先设置钢围檩结构,再在钢围檩上安装对应的内支撑结构,以保证结构具有足够的强度和稳固性。Specifically, after the steel sheet pile 2 is driven, excavate to 0.5m below the bottom elevation of the first internal support structure, and install the first internal support structure. After the first internal support structure is installed, continue to excavate downward to 0.5m below the bottom of the second internal support structure, and install the second internal support structure. After the second internal support structure is installed, continue to excavate downward to 0.5m below the bottom of the third internal support, and install the third internal support structure. Repeat this process in sequence. Generally, according to the scale of most deep foundation pits at present, it is sufficient to set up about four internal support structures, but the specific number of internal support structures can be determined according to the actual construction depth and scale. Among them, since the scale of deep foundation pits is generally large, in order to ensure the stability of the structure, generally before installing each layer of internal support structure, a steel perimeter purlin structure will be set up first, and then the corresponding internal support structure will be installed on the steel perimeter purlin to ensure that the structure has sufficient strength and stability.

进一步的,在基坑开挖至约15m时,在对应的围檁上增加精轧螺纹钢拉杆对拉。因为开挖深度越深,两侧土压力越大,在土压力的作用下,钢板桩2下部有向基坑内倾斜的趋势,而钢板桩2上部则有向基坑四周倾斜的趋势,但内支撑结构只能提供抵抗周围土体向内的压力,不能抵抗顶部的这种向外倾斜趋势,因此需要采用钢筋对拉来提供拉力,以抵抗钢板桩2上部向基坑外四周倾斜,精轧螺纹钢的对拉杆可以提供足够的抗拉强度,使不良地层中基坑受力更为合理,并大大提高了基坑的安全。具体的,在对应的围檩安装完毕后,将带有法兰盘的钢管支撑通过预留螺栓孔连接,此时带有法兰盘的钢管支撑与围檩、钢板桩2通过精轧螺纹钢连接在一起,在不影响钢管支撑拆除的情况使钢管支撑成为拉压杆。Furthermore, when the foundation pit is excavated to about 15m, a fine-rolled threaded steel tie rod is added to the corresponding surrounding purlin. Because the deeper the excavation depth, the greater the soil pressure on both sides. Under the action of soil pressure, the lower part of the steel sheet pile 2 tends to tilt toward the foundation pit, while the upper part of the steel sheet pile 2 tends to tilt toward the surrounding of the foundation pit. However, the internal support structure can only provide resistance to the inward pressure of the surrounding soil, and cannot resist the outward tilting trend of the top. Therefore, it is necessary to use steel bars to provide tension to resist the upper part of the steel sheet pile 2 from tilting toward the surrounding of the foundation pit. The fine-rolled threaded steel tie rod can provide sufficient tensile strength, so that the force of the foundation pit in the poor stratum is more reasonable, and the safety of the foundation pit is greatly improved. Specifically, after the corresponding surrounding purlin is installed, the steel pipe support with a flange is connected through the reserved bolt hole. At this time, the steel pipe support with a flange is connected to the surrounding purlin and the steel sheet pile 2 through the fine-rolled threaded steel, so that the steel pipe support becomes a tension and compression rod without affecting the removal of the steel pipe support.

本申请还提供了一种用于深基坑的钢板桩围堰,参见图2所示,本钢板桩围堰主要包括围堰主体1和导向结构3,其中,围堰主体1包括多根首尾相连的钢板桩2,每一钢板桩2上均设有引孔组件和注液组件,引孔组件用于根据施工场地的地质信息选择水刀或气刀交替引孔,以辅助钢板桩2插打至预设深度,注液组件用于沿钢板桩2的外侧壁朝基坑底部注入封底混凝土,以完成基坑的封底;导向结构3沿围堰主体1的周向设置,导向结构3用于为钢板桩2在插打时导向。The present application also provides a steel sheet pile cofferdam for deep foundation pits, as shown in Figure 2, the steel sheet pile cofferdam mainly includes a cofferdam body 1 and a guide structure 3, wherein the cofferdam body 1 includes a plurality of steel sheet piles 2 connected end to end, and each steel sheet pile 2 is provided with a hole-guiding assembly and a liquid injection assembly, the hole-guiding assembly is used to select a water knife or an air knife to alternately guide holes according to the geological information of the construction site to assist the steel sheet piles 2 to be driven to a preset depth, and the liquid injection assembly is used to inject bottom sealing concrete along the outer wall of the steel sheet pile 2 toward the bottom of the foundation pit to complete the bottom sealing of the foundation pit; the guide structure 3 is arranged along the circumference of the cofferdam body 1, and the guide structure 3 is used to guide the steel sheet piles 2 when they are driven.

进一步的,导向结构3包括多根钢管桩,一部分钢管桩沿钢板桩2的排列轨迹在钢管桩的内侧间隔设置,剩余部分钢管桩沿钢板桩2的排列轨迹在钢管桩的外侧间隔设置,位于内侧和外侧的钢管桩的顶部均设有多根导向工字钢30,位于内侧和外侧的导向工字钢30上滑设多个间隔设置的限位钢筋条31;其中,导向工字钢30用于限制钢板桩2插打时沿朝内侧或外侧的方向偏移,限位钢筋条31用于限制钢板桩2插打时沿左右侧偏移。Furthermore, the guide structure 3 includes a plurality of steel pipe piles, a part of which is arranged at intervals on the inner side of the steel pipe piles along the arrangement trajectory of the steel sheet piles 2, and the remaining part of the steel pipe piles is arranged at intervals on the outer side of the steel pipe piles along the arrangement trajectory of the steel sheet piles 2, and a plurality of guide I-beams 30 are provided on the tops of the steel pipe piles located on the inner and outer sides, and a plurality of spaced limiting steel bars 31 are slidably arranged on the guide I-beams 30 located on the inner and outer sides; wherein, the guide I-beams 30 are used to limit the deviation of the steel sheet piles 2 in the inner or outer direction when being driven, and the limiting steel bars 31 are used to limit the deviation of the steel sheet piles 2 in the left and right directions when being driven.

进一步的,由于对于钢板桩2而言,主要依靠相邻两个钢板桩相互扣合的扣锁进行封闭,扣锁之间再结合紧密也是刚性接触,存在较大的泄漏风险。因此,为了保障钢板桩2扣锁与扣锁之间的连接得紧密性,减少水下漏水的可能性,在钢板桩2插打前,分别在每一钢板桩2的扣锁上分别涂抹防水剂,防水剂包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为A:B:C:D:E:F:G:H:I,石英砂包括100目的石英砂和200目的石英砂,且100目的石英砂和200目的石英砂的质量比为15:4。Furthermore, for the steel sheet pile 2, the closure is mainly carried out by the buckle of two adjacent steel sheet piles, and the buckle is tightly connected and is also rigid contact, which has a greater risk of leakage. Therefore, in order to ensure the tightness of the connection between the buckle of the steel sheet pile 2 and reduce the possibility of underwater leakage, before the steel sheet pile 2 is inserted, a waterproofing agent is applied to the buckle of each steel sheet pile 2. The waterproofing agent includes silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane single component single and double component type I, polyurethane single component double component type II, cement-based permeable crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is A: B: C: D: E: F: G: H: I, and the quartz sand includes 100 mesh quartz sand and 200 mesh quartz sand, and the mass ratio of 100 mesh quartz sand and 200 mesh quartz sand is 15:4.

其中,上述钢板桩围堰中的各个结构的功能实现与上述钢板桩围堰施工方法中的各步骤相对应,其剩余功能和实现过程在此处不再一一赘述。Among them, the functional implementation of each structure in the above-mentioned steel sheet pile cofferdam corresponds to the various steps in the above-mentioned steel sheet pile cofferdam construction method, and its remaining functions and implementation processes will not be repeated here one by one.

在本申请的描述中,需要说明的是,术语“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

需要说明的是,在本申请中,诸如“第一”和“第二”等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

以上所述仅是本申请的具体实施方式,使本领域技术人员能够理解或实现本申请。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本申请的精神或范围的情况下,在其它实施例中实现。因此,本申请将不会被限制于本文所示的这些实施例,而是要符合与本文所申请的原理和新颖特点相一致的最宽的范围。The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims (3)

1.一种用于深基坑的钢板桩围堰施工方法,其特征在于,其步骤包括:1. A steel sheet pile cofferdam construction method for a deep foundation pit, characterized in that the steps include: 获取施工场地的地质信息,并确定施工区域;Obtain geological information of the construction site and determine the construction area; 在所述施工区域内设置导向结构(3);Providing a guide structure (3) in the construction area; 在所述导向结构(3)的导向下依次插打钢板桩(2),并在插打的过程中根据获取的所述地质信息选择水刀或气刀交替引孔,以辅助所述钢板桩(2)插打至预设深度;The steel sheet piles (2) are inserted in sequence under the guidance of the guide structure (3), and during the insertion and driving process, a water jet or an air knife is selected to alternately guide holes according to the acquired geological information, so as to assist the steel sheet piles (2) to be inserted and driven to a preset depth; 完成所述钢板桩(2)的合龙,对基坑进行挖掘,并在挖掘的过程从上至下设置多个内支撑结构;The steel sheet piles (2) are connected together, the foundation pit is excavated, and a plurality of internal support structures are arranged from top to bottom during the excavation process; 沿所述钢板桩(2)的外侧壁朝基坑底部注入封底混凝土,完成所述基坑的封底;Injecting bottom sealing concrete along the outer side wall of the steel sheet pile (2) toward the bottom of the foundation pit to complete the bottom sealing of the foundation pit; 在插打所述钢板桩(2)前还包括:Before inserting the steel sheet pile (2), the method further comprises: 在所述钢板桩(2)的腹板内壁沿其长度方向设置竖直设置的引孔管,并在所述引孔管的底端设置至少两个朝下方设置的引孔喷嘴;A vertically arranged hole-introducing pipe is arranged on the inner wall of the web of the steel sheet pile (2) along its length direction, and at least two hole-introducing nozzles arranged downward are arranged at the bottom end of the hole-introducing pipe; 在所述钢板桩(2)的腹板外壁沿其长度方向设置竖直设置的注浆管;A grouting pipe is vertically arranged on the outer wall of the web of the steel sheet pile (2) along its length direction; 在插打所述钢板桩(2)前还包括:Before inserting the steel sheet pile (2), the method further comprises: 在所述钢板桩(2)的扣锁上涂抹防水剂;Applying a waterproofing agent on the buckle of the steel sheet pile (2); 所述防水剂包括硅酸盐水泥、石英砂、抗渗料粉煤灰、有机硅憎水粉、HPMC纤维素、聚氨酯单组分单双组份I型、聚氨酯单组分双组份II型、水泥基渗透结晶、聚合物水泥防水涂料JS,各组分的质量比为52:38:5:75:3:10:5:5:10,所述石英砂包括100目的石英砂和200目的石英砂,且100目的石英砂和200目的石英砂的质量比为15:4;The waterproofing agent includes silicate cement, quartz sand, anti-seepage material fly ash, silicone hydrophobic powder, HPMC cellulose, polyurethane single-component single-component type I, polyurethane single-component type II, cement-based permeable crystallization, polymer cement waterproof coating JS, and the mass ratio of each component is 52:38:5:75:3:10:5:5:10. The quartz sand includes 100-mesh quartz sand and 200-mesh quartz sand, and the mass ratio of 100-mesh quartz sand to 200-mesh quartz sand is 15:4. 所述在挖掘的过程从上至下设置多个内支撑结构,其步骤包括:The steps of setting up multiple inner support structures from top to bottom during the excavation process include: 沿钢板桩(2)围堰的内壁设置钢围檩;Steel purlins are arranged along the inner wall of the steel sheet pile (2) cofferdam; 在所述钢围檩上设置内支撑结构;An internal supporting structure is provided on the steel purlin; 继续朝下方挖掘,并依次设置所述钢围檩和内支撑结构,且挖掘深度越大,相邻两个所述钢围檩或内支撑结构之间的间距越小;Continue digging downwards, and sequentially set the steel perimeter purlins and the inner support structure, and the greater the digging depth, the smaller the distance between two adjacent steel perimeter purlins or inner support structures; 在基坑开挖至15m时,在对应的钢围檩上安装精轧螺纹钢拉杆,以连接该钢围檩和钢板桩;When the foundation pit is excavated to 15m, install the precision-rolled threaded steel tie rod on the corresponding steel purlin to connect the steel purlin and the steel sheet pile; 所述在插打的过程中根据获取的所述地质信息选择水刀或气刀交替引孔,以辅助所述钢板桩(2)插打至预设深度,其步骤包括:During the driving process, a water jet or an air jet is selected to alternately guide holes according to the acquired geological information to assist in driving the steel sheet pile (2) to a preset depth, the steps comprising: 确定当前插打深度的地质信息,若当前插打深度的地质信息为硬塑黏土或砂砾土,则采用水刀进行引孔,若当前插打深度的地质信息为泥质粉砂岩或强风化岩,则采用气刀进行引孔;Determine the geological information of the current drilling depth. If the geological information of the current drilling depth is hard plastic clay or gravel soil, use a water knife to guide the hole. If the geological information of the current drilling depth is muddy siltstone or strongly weathered rock, use an air knife to guide the hole. 在插打的过程中根据所述地质信息选择水刀或气刀交替引孔,直至所述钢板桩(2)插打至所述预设深度;During the driving process, a water knife or an air knife is selected to alternately drill holes according to the geological information until the steel sheet pile (2) is driven to the preset depth; 所述引孔喷嘴的喷口呈尖形,且嘴口直径为1cm;The nozzle of the orifice-introducing nozzle is pointed, and the diameter of the nozzle is 1 cm; 在采用水刀时,将引孔管的顶端与高压水泵连通,且高压水泵压力为5~10Mpa,引孔喷嘴终端压力保持在300~500Mpa;When using a water jet, connect the top of the orifice tube to a high-pressure water pump with a pressure of 5-10 MPa, and keep the terminal pressure of the orifice nozzle at 300-500 MPa. 在采用气刀时,将引孔管的顶端与高压气泵连通,且气泵压力为3~15Mpa,喷嘴终端压力保持在300~500Mpa。When using an air knife, connect the top of the orifice tube to a high-pressure air pump with an air pump pressure of 3-15 MPa, and maintain the nozzle terminal pressure at 300-500 MPa. 2.如权利要求1所述的一种用于深基坑的钢板桩围堰施工方法,其特征在于,所述在所述施工区域的预设位置设置导向结构(3),其步骤包括:2. A steel sheet pile cofferdam construction method for a deep foundation pit according to claim 1, characterized in that the guide structure (3) is provided at a preset position in the construction area, and the steps include: 在所述施工区域内依次确定钢板桩(2)的插打点位;Determining the driving points of the steel sheet piles (2) in sequence within the construction area; 分别在确定的一圈所述插打点位的内侧和外侧沿所述插打点位的排列轨迹依次插打多根钢管桩,插打完毕后在位于内侧和外侧的所述钢管桩的顶部分别设置导向工字钢(30);Sequentially driving a plurality of steel pipe piles on the inner side and the outer side of a circle of driving points along the arrangement track of the driving points, and after driving is completed, respectively setting guide I-beams (30) on the tops of the steel pipe piles located on the inner side and the outer side; 在位于内侧和外侧的所述导向工字钢(30)上滑设多个间隔设置的限位钢筋条(31)。A plurality of spaced-apart limiting steel bars (31) are slidably mounted on the guide I-beams (30) located on the inner and outer sides. 3.如权利要求2所述的一种用于深基坑的钢板桩围堰施工方法,其特征在于,所述在所述导向结构(3)的导向下依次插打钢板桩(2),其步骤还包括:3. A steel sheet pile cofferdam construction method for a deep foundation pit according to claim 2, characterized in that the steel sheet piles (2) are inserted and driven in sequence under the guidance of the guide structure (3), and the steps further include: 调节其中一所述限位钢筋条(31)至对应的所述插打点位的一侧;Adjusting one of the limiting steel bars (31) to one side of the corresponding insertion point; 插打所述钢板桩(2),在插打的过程中分别利用位于内侧和外侧的所述导向工字钢(30)共同辅助校正所述钢板桩(2)沿内侧至外侧这一方向上的位置,还利用所述限位钢筋条(31)辅助校正所述钢板桩(2)沿左右方向的位置。The steel sheet pile (2) is driven in, and during the driving process, the guide I-beams (30) located on the inner side and the outer side are respectively used to assist in correcting the position of the steel sheet pile (2) in the direction from the inner side to the outer side, and the limiting steel bar (31) is also used to assist in correcting the position of the steel sheet pile (2) in the left-right direction.
CN202210574920.9A 2022-05-24 2022-05-24 A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam Active CN114775664B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210574920.9A CN114775664B (en) 2022-05-24 2022-05-24 A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210574920.9A CN114775664B (en) 2022-05-24 2022-05-24 A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam

Publications (2)

Publication Number Publication Date
CN114775664A CN114775664A (en) 2022-07-22
CN114775664B true CN114775664B (en) 2024-11-05

Family

ID=82408932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210574920.9A Active CN114775664B (en) 2022-05-24 2022-05-24 A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam

Country Status (1)

Country Link
CN (1) CN114775664B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202247893U (en) * 2011-08-16 2012-05-30 中建三局建设工程股份有限公司 Novel steel sheet pile
CN106320351A (en) * 2016-08-25 2017-01-11 中铁四局集团有限公司 Small-spacing long and large underwater steel sheet pile cofferdam construction method
CN113026782A (en) * 2021-03-24 2021-06-25 中铁十六局集团有限公司 Steel sheet pile cofferdam construction process

Family Cites Families (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08333761A (en) * 1995-06-10 1996-12-17 Naoki Kumagai Retaining wall drainage draining structure
JP3450725B2 (en) * 1998-06-25 2003-09-29 美好 忠平 Ground improvement method
JP4404505B2 (en) * 2001-09-14 2010-01-27 新日本製鐵株式会社 Revetment walls such as rivers
JP3757415B2 (en) * 2001-10-03 2006-03-22 忠平 直哉 Ground improvement method and ground improvement equipment
JP2007032254A (en) * 2005-06-21 2007-02-08 Mori Juki Kogyo:Kk Pile having tip reinforcing member and pile driving construction method using the same
JP5271301B2 (en) * 2010-03-24 2013-08-21 川上産業株式会社 Bubble sheet
EP2571607A4 (en) * 2010-05-21 2016-12-21 Adrian Brozell Self-assembled surfactant structures
CN102409688B (en) * 2011-08-16 2015-12-02 中建三局建设工程股份有限公司 A kind of construction method of steel sheet-pile cofferdam
JP5942845B2 (en) * 2012-12-26 2016-06-29 新日鐵住金株式会社 Sheet pile wall, sheet pile wall construction method and sheet pile with formwork
CN203080528U (en) * 2013-01-30 2013-07-24 安徽水利开发股份有限公司 Drilling and spraying integrated foundation treating special drilling tool assembly
CN103669351B (en) * 2013-12-30 2015-04-22 恒天九五重工有限公司 Full-stroke hole-leading hydraulic static pile driver
CN104196034B (en) * 2014-09-18 2016-09-21 中建交通建设集团有限公司 A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN104929133B (en) * 2015-06-09 2016-11-09 沈阳市政集团有限公司 The construction method of sloping timbering at the bottom of a kind of deep basal pit Larsen steel sheet pile stake
CN205776215U (en) * 2016-05-17 2016-12-07 中交一公局第五工程有限公司 Steel sheet pile inserted to play is with drawing hole instrument
KR20180006791A (en) * 2016-07-11 2018-01-19 원병천 Construction method of enlarged bulb type prefabricated pile
CN106759377A (en) * 2016-12-23 2017-05-31 安徽理工大学 The construction method of recyclable building enclosure
CN106912283B (en) * 2017-02-27 2020-01-17 柳州市农业技术推广中心 Rice matrix semi-water seedling raising method
CN108532590A (en) * 2018-03-02 2018-09-14 毕建宏 The construction method and apparatus of caisson
CN110886295B (en) * 2019-11-06 2025-02-18 张辉 A construction method of a static pressure pile sinking device using a middle-through method
CN113026779A (en) * 2021-01-20 2021-06-25 安徽省公路桥梁工程有限公司 Combined steel sheet pile cofferdam and construction method
CN214783919U (en) * 2021-04-24 2021-11-19 浙江江河建设有限公司 Sheet pile hole pre-punching device
CN113048778A (en) * 2021-04-25 2021-06-29 刘曼曼 Aluminum alloy water blowing air knife system
CN113356246A (en) * 2021-05-15 2021-09-07 中铁九局集团第六工程有限公司 Construction method of combined cofferdam under hard riverbed

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202247893U (en) * 2011-08-16 2012-05-30 中建三局建设工程股份有限公司 Novel steel sheet pile
CN106320351A (en) * 2016-08-25 2017-01-11 中铁四局集团有限公司 Small-spacing long and large underwater steel sheet pile cofferdam construction method
CN113026782A (en) * 2021-03-24 2021-06-25 中铁十六局集团有限公司 Steel sheet pile cofferdam construction process

Also Published As

Publication number Publication date
CN114775664A (en) 2022-07-22

Similar Documents

Publication Publication Date Title
WO2020173100A1 (en) Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
KR101067707B1 (en) Construction method of ordered earth wall using concrete pile and grouting column
CN112253162A (en) A kind of reinforcement structure and construction method of large-diameter pipe jacking group inlet and outlet holes in water-rich sand layer
CN113186903A (en) Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN113266392A (en) Pipe jacking construction method for penetrating through existing anchor cable group
JP4451553B2 (en) Buoyancy prevention structure and construction method thereof
CN112483126A (en) Construction method of underground excavation air duct of composite stratum with upper soft part and lower hard part
CN114575355B (en) Soil protection construction method
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN114775664B (en) A steel sheet pile cofferdam construction method for deep foundation pit and steel sheet pile cofferdam
CN112227382A (en) Double-row pile structure with water stopping function and construction method thereof
CN115467339B (en) Construction method of river abutment foundation under condition of soft soil close to shallow tunnel coverage layer
CN111456021A (en) Construction method for reversely making enclosure structure by utilizing RJP piles
CN115652952B (en) Uplift pile and support pile combined inclined straight pile internal-support-free foundation pit supporting method
CN217870557U (en) Cofferdam structure located on bias water-approaching slope
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN209798763U (en) steel anchor supporting structure for foundation pit supporting
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
CN216948333U (en) Foundation ditch stagnant water supporting system under limited condition in space
CN115478549B (en) Construction method of strong water-permeable stratum lock catch steel pipe pile and steel sheet pile combined cofferdam
CN115094946B (en) Back wall construction method for pipe jacking construction
CN218204422U (en) Foundation pit supporting structure of PRC tubular pile and prestressed anchorage cable combination

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant