[go: up one dir, main page]

CN114753713A - Building construction rail guard - Google Patents

Building construction rail guard Download PDF

Info

Publication number
CN114753713A
CN114753713A CN202210607314.2A CN202210607314A CN114753713A CN 114753713 A CN114753713 A CN 114753713A CN 202210607314 A CN202210607314 A CN 202210607314A CN 114753713 A CN114753713 A CN 114753713A
Authority
CN
China
Prior art keywords
clamping
block
mounting base
lifting
protective guard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210607314.2A
Other languages
Chinese (zh)
Other versions
CN114753713B (en
Inventor
叶丹
王波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University of Education
Original Assignee
Chongqing University of Education
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University of Education filed Critical Chongqing University of Education
Priority to CN202210607314.2A priority Critical patent/CN114753713B/en
Publication of CN114753713A publication Critical patent/CN114753713A/en
Application granted granted Critical
Publication of CN114753713B publication Critical patent/CN114753713B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/16Fences constructed of rigid elements, e.g. with additional wire fillings or with posts using prefabricated panel-like elements, e.g. wired frames
    • E04H17/18Corrals, i.e. easily transportable or demountable enclosures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/20Posts therefor
    • E04H17/22Anchoring means therefor, e.g. specially-shaped parts entering the ground; Struts or the like
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本发明提供了一种房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体;述防滑安装块包括底面具有防滑结构的防滑板,防滑板的上表面固定设置有连接块,所述连接块的两个相对侧面上设有夹持孔;所述施工防护栏单体包括安装基座以及设置于安装基座上的栏杆部;所述安装基座为底部开口的中空结构,安装基座的底部开口尺寸足够使得防滑安装块的连接块伸入至安装基座的中空空间,且安装基座的中空空间内安装有能够与防滑安装块的连接块上的两个夹持孔相夹持或松脱的活动夹持连接机构。本发明中防滑安装块和施工防护栏单体能够单独更换,且拆卸安装施工简便无破坏,能够进行二次回收使用。

Figure 202210607314

The invention provides a building construction protection fence, which includes a non-slip installation block for installation on the ground, and a construction protection fence unit that can be detachably clamped and installed on the non-slip installation block; the non-slip installation block includes The bottom surface has an anti-skid plate with an anti-skid structure, the upper surface of the anti-skid plate is fixedly provided with a connecting block, and two opposite sides of the connecting block are provided with clamping holes; The railing part on the base; the mounting base is a hollow structure with an opening at the bottom, and the size of the bottom opening of the mounting base is enough to make the connecting block of the anti-skid mounting block protrude into the hollow space of the mounting base, and the hollow space of the mounting base is A movable clamping connection mechanism capable of clamping or releasing with the two clamping holes on the connection block of the anti-skid installation block is installed in the space. In the present invention, the non-slip installation block and the construction guardrail monomer can be replaced independently, and the disassembly, installation and construction are simple and non-destructive, and can be recycled and used twice.

Figure 202210607314

Description

一种房建施工防护栏A kind of housing construction protection fence

技术领域technical field

本发明涉及房建施工设备领域,具体涉及一种房建施工防护栏。The invention relates to the field of housing construction equipment, in particular to a housing construction protection fence.

背景技术Background technique

房屋建筑工程是指各类房屋建筑及其附属设施和与其配套的线路、管道、设备安装工程及室内外装修工程,“房屋建筑”指有顶盖、梁柱、墙壁、基础以及能够形成内部空间,满足人们生产、居住、学习、公共活动等需要的工程。Housing construction engineering refers to all kinds of housing construction and its ancillary facilities and their supporting lines, pipelines, equipment installation works and indoor and outdoor decoration works. , to meet the needs of people's production, living, learning, public activities and other projects.

在房屋建筑工程进行勘察、规划、设计、施工、安装和维护等各项技术工作时,常常需要防护栏,现有的防护栏底部要么没有设置防滑措施,要么在底部设置简单且固定的防滑块或防滑垫。When conducting various technical work such as survey, planning, design, construction, installation and maintenance of housing construction projects, guardrails are often required. The bottom of the existing guardrails either does not have anti-skid measures, or is provided with simple and fixed anti-skid blocks at the bottom. or non-slip mats.

没有设置防滑措施的防护栏防滑系数较低,无法起到防滑的作用,对于基坑边坡处的护栏或者是高层的护栏而言,没有防滑措施会有较大的安全隐患。The anti-skid coefficient of the guardrail without anti-skid measures is low and cannot play the role of anti-skid. For the guardrail on the slope of the foundation pit or the guardrail on the high-rise, there will be a greater safety hazard without anti-skid measures.

护栏底部设置简单且固定的防滑块或防滑垫的护栏虽能够起到一定的防滑作用,但是在使用完毕后,在拆除防护栏时往往会将防滑块损毁或将上部防护栏损毁,进而导致整个防护栏的废弃,无法进行二次回收使用,浪费了大量的资源。The guardrail with simple and fixed anti-skid blocks or anti-skid pads at the bottom of the guardrail can play a certain anti-slip effect, but after use, the anti-skid blocks or the upper guardrail are often damaged when the guardrail is removed, which will lead to the whole. The abandonment of the guardrail cannot be used for secondary recycling, which wastes a lot of resources.

另外,现有常用的建筑围挡式的护栏常常为铁质的护栏板,安装方式为手动安装,具体为在硬化的地面或已经铺好的人行道地面打孔并安装膨胀螺丝,然后将护栏底部与膨胀螺丝螺纹连接,护栏单体之间也采用螺丝进行连接,在此过程中需要破坏地面原始结构,在施工完成护栏拆除后,地面上留下大量的螺丝孔,行人在行走时容易绊倒,降低行人在人行道行走时的安全系数;护栏安装时还需要大量的人力进行螺丝的紧固操作,这一操作费时费力;而且铁质的护栏板高度过高,不适合勘察时对现场的查看。而且铁质的护栏板防风效果较差,容易被大风吹倒或发生变形,有较大的安全隐患。In addition, the existing commonly used building enclosure-type guardrails are often iron guardrail boards, and the installation method is manual installation, specifically, drilling holes on the hardened ground or paved sidewalk ground and installing expansion screws, and then installing the bottom of the guardrail. It is threadedly connected with expansion screws, and the guardrails are also connected by screws. During this process, the original structure of the ground needs to be destroyed. After the guardrail is removed, a large number of screw holes are left on the ground, and pedestrians are prone to tripping when walking. , reducing the safety factor of pedestrians walking on the sidewalk; the installation of the guardrail also requires a lot of manpower to fasten the screws, which is time-consuming and laborious; and the height of the iron guardrail is too high, which is not suitable for site inspection during surveys. . Moreover, the iron guardrail has poor windproof effect and is easily blown down or deformed by strong winds, posing a greater safety hazard.

发明内容SUMMARY OF THE INVENTION

本发明目的在于提供一种房建施工防护栏,以解决现有施工防护栏损坏后拆卸及更换安装不便、更换成本较高等技术问题。The purpose of the present invention is to provide a building construction guardrail, so as to solve the technical problems of inconvenient disassembly, replacement and installation, and high replacement cost after the existing construction guardrail is damaged.

为了解决上述技术问题,本发明采用了如下的技术方案:In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions:

一种房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体;A housing construction construction guardrail, comprising a non-slip installation block for installation on the ground, and a construction guardrail monomer capable of being detachably clamped and installed on the non-slip installation block;

所述防滑安装块包括底面具有防滑结构的防滑板6,防滑板6的上表面固定设置有连接块7,所述连接块7的两个相对侧面上设有夹持孔;The anti-skid installation block includes a skid plate 6 with an anti-skid structure on the bottom surface, a connecting block 7 is fixedly arranged on the upper surface of the anti-skid plate 6, and two opposite sides of the connecting block 7 are provided with clamping holes;

所述施工防护栏单体包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The construction guardrail unit includes an installation base 1 and a railing portion arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the bottom opening of the installation base 1 is sufficient to make the anti-skid installation block. The connecting block 7 extends into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is provided with a movable movable that can be clamped or released with the two clamping holes on the connecting block 7 of the anti-skid mounting block. Clamp connection mechanism.

这样,当房建施工防护栏上的防滑安装块或者施工防护栏单体受损时,可以将防滑安装块或者施工防护栏单体进行独立更换,增加房建施工防护栏的利用率,延长使用年限;而且防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,拆卸及更换安装都更加方便。In this way, when the non-slip mounting block or the single construction guardrail on the housing construction guardrail is damaged, the non-slip mounting block or the single construction guardrail can be replaced independently, which increases the utilization rate of the housing construction guardrail and prolongs the use of the guardrail. Moreover, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, which is more convenient for disassembly and replacement and installation.

上述的房建施工防护栏中,优选的,所述活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构。In the above-mentioned housing construction protection bar, preferably, the movable clamping connection mechanism includes two clamping blocks 32 arranged laterally and oppositely arranged, and the two clamping blocks 32 are facing the connection block 7 of the anti-skid installation block. When extending into the hollow space of the mounting base 1, the two clamping holes are located, and the clamping block 32 has clamping protrusions that can extend into the clamping holes; it also includes a clamping protrusion for restricting the two clamping holes. A lateral sliding limit mechanism for moving the blocks 32 laterally toward each other or away from each other, and a clamping block driving mechanism for driving the two clamping blocks 32 to move.

这样,活动夹持连接采用了夹持块横向移动并与连接块插接的方式实现防滑安装块的快速拆装,方便防滑安装块或者施工防护栏单体的更换。In this way, the movable clamping connection adopts the method of lateral movement of the clamping block and plug connection with the connecting block to realize the rapid disassembly and assembly of the anti-skid installation block, which is convenient for the replacement of the anti-skid installation block or the single construction guardrail.

上述的房建施工防护栏中,优选的,所述夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动。In the above-mentioned housing construction protection bar, preferably, the clamping block driving mechanism includes a rotating disk 30 arranged laterally between the two clamping blocks 32, and the rotating disk 30 is rotatably connected at two relative positions on the edge At one end of the two connecting rods 31 , the other ends of the two connecting rods 31 are respectively rotatably connected to the two clamping blocks 32 ; Holding the drive motor 10 to drive and rotate.

采用上述夹持块驱动机构采用了传动的方式,使夹持块能够进行线性横向运动,使夹持块伸入或伸出夹持孔的过程更加精准和平稳。The above-mentioned clamping block driving mechanism adopts a transmission mode, so that the clamping block can perform linear lateral movement, so that the process of the clamping block extending into or out of the clamping hole is more precise and stable.

上述的房建施工防护栏中,优选的,所述横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内。In the above-mentioned housing construction protection bar, preferably, the lateral sliding limit mechanism includes a positioning slide column 33 that is fixedly connected to the clamping block 32 and arranged laterally. The two clamping blocks 32 are slidably inserted into the laterally arranged cylindrical positioning sliding sleeve 34, and then the lateral sliding of the positioning sliding column 33 in the positioning sliding sleeve 34 restricts the lateral movement of the two clamping blocks 32 toward or away from each other; the positioning The sliding sleeve 34 is fixedly installed in the hollow space of the mounting base 1 .

采用上述横向限位机构能够使夹持块横向运动的方向更精准,不容易发生偏离。The use of the above-mentioned lateral limiting mechanism can make the direction of lateral movement of the clamping block more precise and less likely to deviate.

上述的房建施工防护栏中,优选的,所述施工防护栏单体还包括与安装基座1可拆卸连接的配重块2;所述配重块2上设有挂钩,所述安装基座1的外侧面上设有挂孔,所述配重块2通过挂钩可拆卸的安装连接在安装基座1外侧面的挂孔上。In the above-mentioned building construction guardrail, preferably, the construction guardrail unit further includes a counterweight 2 that is detachably connected to the installation base 1; the counterweight 2 is provided with a hook, and the installation base Hanging holes are provided on the outer side of the base 1 , and the counterweight 2 is detachably installed and connected to the hanging holes on the outer side of the mounting base 1 through hooks.

配重块更够增加房建施工防护栏的整体稳定性,使其不容易受到大风或相当外力的影响,而且可以增加底部防滑安装块与地面之间的摩擦力,从而增强房建施工防护栏的防滑作用。The counterweight is enough to increase the overall stability of the building construction guardrail, making it less susceptible to strong winds or considerable external forces, and can increase the friction between the bottom anti-skid installation block and the ground, thereby enhancing the building construction guardrail anti-slip effect.

上述的房建施工防护栏中,优选的,还包括用于连接相邻两个施工防护栏单体的防护栏连接杆,所述防护栏连接杆的两个端头位置处均具有尺寸径向扩展延伸的连接卡块;The above-mentioned building construction guardrail, preferably, further includes a guardrail connecting rod for connecting two adjacent construction guardrail monomers, and the two end positions of the guardrail connecting rod have radial dimensions. Extended extension connection card block;

所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处。The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a lifting block 18 that can be vertically lifted and slid is installed in the hollow space of the connecting portion shell 3. The lifting block The top of the 18 has a snap-on limit portion 19 that can be snap-fitted with the connection block of the connecting rod of the guardrail; the snap-on limit portion 19 is provided with an opening facing away from the side of the rail portion, and is vertical. The clipping slot extends upward to the top of the clipping limit portion 19, the cavity space of the clipping slot can be inserted into the connecting block of the connecting rod of the guardrail, and the lateral width of the slot of the clipping slot can be used for protection The rod portion of the railing connecting rod passes through and is smaller than the lateral width of the connecting block; the lifting block 18 can perform the lifting motion under the driving of the lifting block driving mechanism, and the lifting block 18 is located at the lowest position and the highest position of the lifting. , the top ends of the snap-on limiting portions 19 are located at a position lower than and higher than the connecting through hole, respectively.

采用上述连接杆以及防护栏连接部的结构能够降低施工防护栏单体之间的安装难度,提高安装效率,同时,通过卡接限位部的结构能够提高施工防护栏单体之间的连接强度,使房建施工防护栏更加的稳固。Using the structure of the connecting rod and the connecting part of the guardrail can reduce the difficulty of installation between the construction guardrail monomers, improve the installation efficiency, and at the same time, the connection strength between the construction guardrail monomers can be improved by the structure of the clamping limit part. , so that the building construction guardrail is more stable.

上述的房建施工防护栏中,优选的,所述升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。In the above-mentioned housing construction protection fence, preferably, the lifting block driving mechanism includes a vertical screw thread connected with the lifting block 18, and a lifting driving cross bar that is rotatably installed in the hollow space of the installation base 1. 13; The vertical screw rod is vertically rotatable installed on the connecting part of the guardrail, and extends downward into the hollow space of the installation base 1, and is transmitted with the lifting driving crossbar 13 through a bevel gear pair Connection; the lift drive cross bar 13 is driven and rotated by the lift drive motor 9 fixedly installed in the hollow space of the mounting base 1 .

这样,能够实现升降块的自动升降,减轻安装人员的安装负担,提高安装效率。In this way, the automatic lifting and lowering of the lifting block can be realized, the installation burden of the installer is reduced, and the installation efficiency is improved.

上述的房建施工防护栏中,优选的,所述防护栏连接杆包括第一连接组件和第二连接组件;所述第一连接组件包括第一连接柱21和固定设置在第一连接柱21一端的第一连接卡块,第一连接柱21的另一端设有外螺纹;所述第一连接组件包括第二连接柱24和固定设置在第二连接柱24一端的第二连接卡块,第二连接柱24的另一端设有外螺纹;所述第一连接柱21和第二连接柱24的外螺纹端通过内螺纹连接套22进行连接。In the above-mentioned building construction guardrail, preferably, the guardrail connecting rod includes a first connecting assembly and a second connecting assembly; the first connecting assembly includes a first connecting column 21 and is fixedly arranged on the first connecting column 21 The first connection block at one end, and the other end of the first connection post 21 is provided with an external thread; the first connection assembly includes a second connection post 24 and a second connection block fixed at one end of the second connection post 24, The other end of the second connection post 24 is provided with an external thread; the external thread ends of the first connection post 21 and the second connection post 24 are connected by an internal thread connection sleeve 22 .

通过内螺纹连接套实现第一连接柱和第二连接柱之间的连接,方便快捷且连接牢固,有利于提高安装效率,降低安装难度,同时也使房建施工防护栏更加的稳固。The connection between the first connection column and the second connection column is realized through the inner threaded connection sleeve, which is convenient, quick and firm in connection, which is beneficial to improve the installation efficiency, reduce the installation difficulty, and at the same time make the building construction guardrail more stable.

本发明还提供一种施工防护栏单体,包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The present invention also provides a construction guardrail unit, comprising an installation base 1 and a railing portion arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the opening at the bottom of the installation base 1 is Enough to make the connecting block 7 of the anti-skid mounting block extend into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is installed with two clamping holes on the connecting block 7 of the anti-skid mounting block. Or loose movable clamp connection mechanism.

上述的施工防护栏单体中,优选的,所述活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构;In the above-mentioned construction guardrail unit, preferably, the movable clamping connection mechanism includes two laterally arranged and oppositely arranged clamping blocks 32, and the two clamping blocks 32 are opposite to the connection block 7 of the anti-skid installation block. When extending into the hollow space of the mounting base 1, the two clamping holes are located, and the clamping block 32 has clamping protrusions that can extend into the clamping holes; it also includes a clamping protrusion for restricting the two clamping holes. a lateral sliding limit mechanism for moving the blocks 32 laterally close to each other or away from each other, and a clamping block driving mechanism for driving the two clamping blocks 32 to move;

所述夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动;The clamping block driving mechanism includes a rotating disk 30 arranged laterally between the two clamping blocks 32. Two opposite positions of the edge of the rotating disk 30 are rotatably connected to one end of the two connecting rods 31. The other ends of the rods 31 are respectively rotatably connected to the two clamping blocks 32; the rotating disk 30 is driven and rotated by the clamping driving motor 10 fixedly installed in the hollow space of the mounting base 1;

所述横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内;The lateral sliding limit mechanism includes a positioning slide 33 that is fixedly connected with the clamping block 32 and is arranged laterally. inside the sleeve 34, and then the lateral sliding of the positioning sliding column 33 in the positioning sliding sleeve 34 restricts the lateral movement of the two clamping blocks 32 toward or away from each other; the positioning sliding sleeve 34 is fixedly installed in the hollow of the installation base 1. in space;

所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处;The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a lifting block 18 that can be vertically lifted and slid is installed in the hollow space of the connecting portion shell 3. The lifting block The top of the 18 has a snap-on limit portion 19 that can be snap-fitted with the connection block of the connecting rod of the guardrail; the snap-on limit portion 19 is provided with an opening facing away from the side of the rail portion, and is vertical. The clipping slot extends upward to the top of the clipping limit portion 19, the cavity space of the clipping slot can be inserted into the connecting block of the connecting rod of the guardrail, and the lateral width of the slot of the clipping slot can be used for protection The rod portion of the railing connecting rod passes through and is smaller than the lateral width of the connecting block; the lifting block 18 can perform the lifting motion under the driving of the lifting block driving mechanism, and the lifting block 18 is located at the lowest position and the highest position of the lifting. , the top end of the snap-on limit portion 19 is located at a position lower than the connecting through hole and higher than the connecting through hole;

所述升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。The lifting block driving mechanism includes a vertical screw thread connected with the lifting block 18, and a lifting driving cross bar 13 installed in the hollow space of the installation base 1 rotatably; It is installed at the connecting part of the guardrail, extends downward into the hollow space of the installation base 1, and is connected with the lift drive crossbar 13 through a conical gear pair; the lift drive crossbar 13 is fixedly installed The lift drive motor 9 in the hollow space of the mounting base 1 is driven to rotate.

本发明具有以下有益效果:The present invention has the following beneficial effects:

1、本发明的房建施工防护栏中,其防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,使得防滑安装块和施工防护栏单体局部损坏后都分别能够单独更换,有助于降低了更换成本,拆卸及更换安装也更加方便,且拆卸安装施工简便无破坏,能够进行二次回收使用;1. In the housing construction guardrail of the present invention, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, so that the anti-skid installation block and the construction guardrail monomer can be separately damaged after partial damage. The replacement helps to reduce the replacement cost, and the disassembly, replacement and installation are also more convenient, and the disassembly and installation construction is simple and non-destructive, and can be recycled and used for the second time;

2、本发明的防护栏采用防护栏连接杆有动力装配方式,以及防护栏连接杆之间的螺纹及内螺纹连接套进行连接,此装配方式和连接方式使防护栏单体之间的连接更加稳固,同时,人工只需辅助防护栏单体之间的连接,使防护栏单体之间的连接更加便捷;2. The guardrail of the present invention adopts the power assembly method of the guardrail connecting rod, and the thread and the inner thread connecting sleeve between the guardrail connecting rods are connected. This assembly method and connection method make the connection between the guardrail monomers more convenient. It is stable, and at the same time, it is only necessary to assist the connection between the guardrail units manually, which makes the connection between the guardrail units more convenient;

3、本发明的防护栏无需对周边安装环境进行机械打孔,无需人工紧固大量的螺丝,对周边环境友好无破坏,拆除后无安全隐患;3. The guardrail of the present invention does not require mechanical drilling of the surrounding installation environment, does not need to manually tighten a large number of screws, is friendly to the surrounding environment and does not damage the surrounding environment, and has no potential safety hazards after dismantling;

4、本发明的防护栏底部还可以配备配重,使防护栏能够保持自身稳定,不易受到恶劣天气的影响;4. The bottom of the guardrail of the present invention can also be equipped with a counterweight, so that the guardrail can maintain its own stability and is not easily affected by bad weather;

5、本发明的防护栏自带驱动电路及供电电源,能够给防护栏的附加设施,如降尘喷雾器等提供附加接口,便于防护栏及其附加设施的集成化,适用于多场景。5. The guardrail of the present invention has its own drive circuit and power supply, which can provide additional interfaces for the additional facilities of the guardrail, such as dust suppression sprayers, etc., which facilitates the integration of the guardrail and its additional facilities, and is suitable for multiple scenarios.

附图说明Description of drawings

为了使发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明作进一步的详细描述,其中:In order to make the purpose, technical solutions and advantages of the invention clearer, the present invention will be described in further detail below in conjunction with the accompanying drawings, wherein:

图1为本发明一种房建施工防护栏的结构示意图;Fig. 1 is the structural representation of a kind of building construction guardrail of the present invention;

图2为本发明一种房建施工防护栏配重块与安装基座的连接结构示意图;Figure 2 is a schematic diagram of the connection structure of a building construction guardrail counterweight and an installation base of the present invention;

图3为本发明一种房建施工防护栏连接块与防滑板的连接结构示意图;FIG. 3 is a schematic diagram of the connection structure of a connecting block of a building construction guardrail and an anti-skid plate according to the present invention;

图4为本发明一种房建施工防护栏安装基座的内部结构示意图;4 is a schematic diagram of the internal structure of a housing construction construction guardrail installation base according to the present invention;

图5为本发明一种房建施工防护栏升降块与螺纹杆的连接结构示意图;Figure 5 is a schematic diagram of the connection structure of the lifting block and the threaded rod of a housing construction construction guardrail according to the present invention;

图6为本发明一种房建施工防护栏导向柱与第一连接柱的连接结构示意图;6 is a schematic diagram of the connection structure of a guide post of a housing construction construction guardrail and a first connection post of the present invention;

图7为本发明一种房建施工防护栏连接杆与转动盘的连接结构示意图。FIG. 7 is a schematic diagram of the connection structure of a connecting rod of a building construction guardrail and a rotating disk according to the present invention.

附图标记说明:1、安装基座;2、配重块;3、连接部壳体;4、护栏柱;5、顶板;6、防滑板;7、连接块;8、驱动电路及供电电源;9、升降驱动电机;10、夹持驱动电机;11、第一转动齿轮;12、第二转动齿轮;13、升降驱动横杆;14、第一锥齿轮;15、第二锥齿轮;16、转动轴;17、螺纹杆;18、升降块;19、卡接限位部;20、第一连接卡块;21、第一连接柱;22、内螺纹连接套;23、第二连接卡块;24、第二连接柱;25、导向柱;30、转动盘;31、连接杆;32、夹持块;33、定位滑柱;34、定位滑套;35、第一隔板;36、第一放置腔;37、第二放置腔;38、第二隔板。Description of reference numerals: 1. Installation base; 2. Counterweight; 3. Connection part housing; 4. Guardrail post; 5. Top plate; 6. Anti-skid plate; 7. Connection block; 8. Drive circuit and power supply 9. Lifting drive motor; 10. Clamping drive motor; 11. First rotating gear; 12. Second rotating gear; 13. Lifting and driving cross bar; 14. First bevel gear; , rotating shaft; 17, threaded rod; 18, lifting block; 19, clamping limit part; 20, first connecting block; 21, first connecting column; 22, internal thread connecting sleeve; 23, second connecting card block; 24, the second connecting column; 25, the guide column; 30, the rotating plate; 31, the connecting rod; 32, the clamping block; 33, the positioning slide column; 34, the positioning slide sleeve; 35, the first partition plate; 36 , the first placement cavity; 37, the second placement cavity; 38, the second partition.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be described clearly and completely below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are some, but not all, embodiments of the present invention. The components of the embodiments of the invention generally described and illustrated in the drawings herein may be arranged and designed in a variety of different configurations. Thus, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”等仅用于区分描述,而不能理解为指示或暗示相对重要性。此外,术语“水平”、“竖直”等术语并不表示要求部件绝对水平或悬垂,而是可以稍微倾斜。如“水平”仅仅是指其方向相对“竖直”而言更加水平,并不是表示该结构一定要完全水平,而是可以稍微倾斜。在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。It should be noted that like numerals and letters refer to like items in the following figures, so once an item is defined in one figure, it does not require further definition and explanation in subsequent figures. In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship that the product of the invention is usually placed in use, only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying The device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as limiting the invention. Furthermore, the terms "first", "second", "third", etc. are only used to differentiate the description and should not be construed as indicating or implying relative importance. Furthermore, the terms "horizontal", "vertical" and the like do not imply that a component is required to be absolutely horizontal or overhang, but rather may be slightly inclined. For example, "horizontal" only means that its direction is more horizontal than "vertical", it does not mean that the structure must be completely horizontal, but can be slightly inclined. In the description of the present invention, it should also be noted that, unless otherwise expressly specified and limited, the terms "arranged", "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection, It can also be a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or the internal communication between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.

本发明能够解决多个技术问题:The present invention can solve multiple technical problems:

1、现有防护栏底部防滑措施与上部结构不可拆分,导致各部分结构损坏之后不易更换,不利于进行二次回收利用,更换成本较高;1. The anti-skid measures at the bottom of the existing guardrail cannot be separated from the upper structure, which makes it difficult to replace each part of the structure after damage, which is not conducive to secondary recycling and high replacement costs;

2、现有防护栏的装配方式需要大量人工操作,装配过程复杂;2. The assembly method of the existing guardrail requires a lot of manual operations, and the assembly process is complicated;

3、现有防护栏的装配方式对周边环境有损坏,且拆除后地面留有残留物,有安全隐患;3. The assembly method of the existing guardrail will damage the surrounding environment, and there are residues on the ground after removal, which is a potential safety hazard;

4、现有防护栏只有铁质的薄板,容易收到恶劣天气的影响,具有安全隐患。4. The existing guardrails are only iron sheets, which are easily affected by bad weather and have potential safety hazards.

采用本发明所公开的一种房建施工防护栏具有如下技术效果:Adopting a kind of building construction guardrail disclosed by the present invention has the following technical effects:

1、本发明的房建施工防护栏中,其防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,使得防滑安装块和施工防护栏单体局部损坏后都分别能够单独更换,有助于降低了更换成本,拆卸及更换安装也更加方便,且拆卸安装施工简便无破坏,能够进行二次回收使用;1. In the housing construction guardrail of the present invention, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, so that the anti-skid installation block and the construction guardrail monomer can be separately damaged after partial damage. The replacement helps to reduce the replacement cost, and the disassembly, replacement and installation are also more convenient, and the disassembly and installation construction is simple and non-destructive, and can be recycled and used for the second time;

2、本发明的防护栏采用防护栏连接杆有动力装配方式,以及防护栏连接杆之间的螺纹及内螺纹连接套进行连接,此装配方式和连接方式使防护栏单体之间的连接更加稳固,同时,人工只需辅助防护栏单体之间的连接,使防护栏单体之间的连接更加便捷;2. The guardrail of the present invention adopts the power assembly method of the guardrail connecting rod, and the thread and the inner thread connecting sleeve between the guardrail connecting rods are connected. This assembly method and connection method make the connection between the guardrail monomers more convenient. It is stable, and at the same time, it is only necessary to assist the connection between the guardrail units manually, which makes the connection between the guardrail units more convenient;

3、本发明的防护栏无需对周边安装环境进行机械打孔,无需人工紧固大量的螺丝,对周边环境友好无破坏,拆除后无安全隐患;3. The guardrail of the present invention does not require mechanical drilling of the surrounding installation environment, does not need to manually tighten a large number of screws, is friendly to the surrounding environment and does not damage the surrounding environment, and has no potential safety hazards after dismantling;

4、本发明的防护栏底部还可以配备配重,使防护栏能够保持自身稳定,不易受到恶劣天气的影响;4. The bottom of the guardrail of the present invention can also be equipped with a counterweight, so that the guardrail can maintain its own stability and is not easily affected by bad weather;

5、本发明的防护栏自带驱动电路及供电电源,能够给防护栏的附加设施,如降尘喷雾器等提供附加接口,便于防护栏及其附加设施的集成化,适用于多场景。5. The guardrail of the present invention has its own drive circuit and power supply, which can provide additional interfaces for the additional facilities of the guardrail, such as dust suppression sprayers, etc., which facilitates the integration of the guardrail and its additional facilities, and is suitable for multiple scenarios.

基于以上要解决的技术问题,如图1-7所示,本发明的房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体。Based on the above technical problems to be solved, as shown in FIGS. 1-7 , the housing construction protection fence of the present invention includes a non-slip mounting block for installing on the ground, and a detachable clamping installation on the anti-slip mounting block. On the construction guardrail monomer.

防滑安装块包括底面具有防滑结构的防滑板6,防滑板6的上表面固定设置有连接块7,所述连接块7的两个相对侧面上设有夹持孔。The anti-skid installation block includes a skid plate 6 with an anti-skid structure on the bottom surface, a connecting block 7 is fixedly arranged on the upper surface of the anti-skid plate 6, and two opposite sides of the connecting block 7 are provided with clamping holes.

施工防护栏单体包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The single construction guardrail includes an installation base 1 and a railing part arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the bottom opening of the installation base 1 is sufficient to allow the connection of the anti-skid installation blocks. The block 7 extends into the hollow space of the installation base 1, and the hollow space of the installation base 1 is installed with a movable clamp that can be clamped or released with the two clamping holes on the connection block 7 of the anti-skid installation block connection mechanism.

当房建施工防护栏上的防滑安装块或者施工防护栏单体受损时,可以将防滑安装块或者施工防护栏单体进行独立更换,增加房建施工防护栏的利用率,延长使用年限;而且防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,拆卸及更换安装都更加方便。When the non-slip mounting block or the single construction guardrail on the housing construction guardrail is damaged, the non-slip mounting block or the single construction guardrail can be independently replaced to increase the utilization rate of the housing construction guardrail and prolong the service life; In addition, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer through clamping and installation, and the disassembly and replacement installation are more convenient.

其中,作为优选,活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构。活动夹持连接采用了夹持块横向移动并与连接块插接的方式实现防滑安装块的快速拆装,方便防滑安装块或者施工防护栏单体的更换。Wherein, preferably, the movable clamping connection mechanism includes two laterally arranged and oppositely arranged clamping blocks 32, and the two clamping blocks 32 are facing the connection block 7 of the anti-skid installation block and extend into the hollow of the installation base 1 In space, where the two clamping holes are located, and the clamping block 32 has clamping protrusions that can extend into the clamping holes; it also includes a function for restricting the two clamping blocks 32 from approaching or moving away from each other laterally. The moving lateral sliding limit mechanism, and the clamping block driving mechanism for driving the two clamping blocks 32 to move. The movable clamping connection adopts the method of lateral movement of the clamping block and plug-in connection with the connecting block to realize the rapid disassembly and assembly of the anti-skid installation block, which is convenient for the replacement of the anti-skid installation block or the single construction guardrail.

作为优选,夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动。采用上述夹持块驱动机构采用了传动的方式,使夹持块能够进行线性横向运动,使夹持块伸入或伸出夹持孔的过程更加精准和平稳。Preferably, the clamping block driving mechanism includes a rotating disk 30 arranged laterally between the two clamping blocks 32, two opposite positions of the edge of the rotating disk 30 are rotatably connected to one end of the two connecting rods 31, and the two The other ends of the connecting rods 31 are respectively rotatably connected to the two clamping blocks 32; The above-mentioned clamping block driving mechanism adopts a transmission mode, so that the clamping block can perform linear lateral movement, so that the process of the clamping block extending into or out of the clamping hole is more precise and stable.

作为优选,横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内。采用上述横向限位机构能够使夹持块横向运动的方向更精准,不容易发生偏离。Preferably, the lateral sliding limit mechanism includes a positioning slide 33 that is fixedly connected to the clamping block 32 and arranged laterally. In the sliding sleeve 34, the lateral sliding of the positioning sliding column 33 in the positioning sliding sleeve 34 restricts the lateral movement of the two clamping blocks 32 toward or away from each other; the positioning sliding sleeve 34 is fixedly installed on the mounting base 1. in the hollow space. The use of the above-mentioned lateral limiting mechanism can make the direction of lateral movement of the clamping block more precise and less likely to deviate.

作为具体的实施方式而言,本发明的房建施工防护栏可以设计包括多个施工防护栏单体,各个施工防护栏单体之间并排的可拆卸连接,所述施工防护栏单体包括安装基座1、与安装基座1顶面固定连接的栏杆部、与栏杆部侧壁活动连接的防护栏连接杆以及与安装基座1底部活动连接的防滑安装块;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。防滑安装块通过活动夹持连接机构进行安装和拆卸,防滑安装块与活动夹持连接机构连接处开设有夹持孔;所述活动夹持连接机构包括能够横向的相互靠近或相互远离移动的一对夹持块32,夹持块32通过横向滑动限位机构固定连接于安装基座1内壁上;夹持块32能够在横向滑动限位机构的带动下从防滑安装块的夹持孔内外横向移动,实现防滑安装块的安装或拆卸。As a specific embodiment, the building construction guardrail of the present invention can be designed to include a plurality of construction guardrail units, and each construction guardrail unit is detachably connected side by side, and the construction guardrail unit includes installation The base 1, the railing part fixedly connected with the top surface of the installation base 1, the guard rail connecting rod movably connected with the side wall of the railing part, and the anti-skid mounting block movably connected with the bottom of the installation base 1; the installation base 1 is: The hollow structure with the bottom opening, the size of the bottom opening of the mounting base 1 is enough to make the connecting block 7 of the anti-skid mounting block extend into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is installed with the anti-skid mounting block. A movable clamping connection mechanism in which the two clamping holes on the connecting block 7 are clamped or released. The non-slip mounting block is installed and disassembled through a movable clamping connection mechanism, and a clamping hole is opened at the connection between the non-slip installation block and the movable clamping connection mechanism; For the clamping block 32, the clamping block 32 is fixedly connected to the inner wall of the mounting base 1 through the lateral sliding limit mechanism; Move to install or remove the anti-skid mounting block.

作为优选,所述活动夹持连接机构还包括与夹持块32转动连接的连接杆31和能够驱动连接杆31发生横向位移的动力系统;所述动力系统包括驱动电路及供电电源8、夹持驱动电机10和转动盘30,其中驱动电路及供电电源8固定连接于安装基座1内壁上,夹持驱动电机10通过导线与驱动电路及供电电源8电性连接;夹持驱动电机10的输出端与转动盘30固定连接,连接杆31与转动盘30顶面位于圆周同一直径线的两端转动连接,连接杆31与夹持块32的顶端转动连接;夹持驱动电机10固定于支撑架上,支撑架固定安装于安装基座1的内壁上。Preferably, the movable clamping connection mechanism further includes a connecting rod 31 rotatably connected to the clamping block 32 and a power system capable of driving the connecting rod 31 to laterally displace; the power system includes a drive circuit and a power supply 8, a clamping The driving motor 10 and the rotating disk 30, wherein the driving circuit and the power supply 8 are fixedly connected to the inner wall of the mounting base 1, and the clamping driving motor 10 is electrically connected with the driving circuit and the power supply 8 through wires; the output of the clamping driving motor 10 is The end is fixedly connected with the rotating disk 30, the connecting rod 31 is rotatably connected with the top surface of the rotating disk 30 at the two ends of the same diameter line of the circumference, and the connecting rod 31 is rotatably connected with the top end of the clamping block 32; the clamping drive motor 10 is fixed on the support frame , the support frame is fixedly installed on the inner wall of the installation base 1 .

作为优选,所述横向滑动限位机构包括定位滑柱33和与定位滑柱33外表面滑动连接的定位滑套34,定位滑套34与安装基座1内壁固定连接,横向滑动限位机构能够对夹持块32的横向移动进行限位支撑,使连接块7与安装基座1的安装或拆卸过程更加平稳。Preferably, the lateral sliding limit mechanism includes a positioning sliding column 33 and a positioning sliding sleeve 34 slidably connected to the outer surface of the positioning sliding column 33. The positioning sliding sleeve 34 is fixedly connected to the inner wall of the installation base 1, and the lateral sliding limiting mechanism can The lateral movement of the clamping block 32 is limited and supported, so that the installation or disassembly process of the connection block 7 and the installation base 1 is more stable.

作为优选,所述防滑安装块包括防滑板6和连接块7,连接块7对应于夹持块32的侧壁上开设有夹持孔,夹持块32能够在连接块7的夹持孔内部横向移动;连接块7的底面固定有防滑板6,且防滑板6的底部均布设置有多个防滑块,能够增加防护栏的防滑功能;所述夹持块32的夹持凸起部可设置于底部,使得夹持块32整体形状为“L”形,其中夹持块32“L”形的竖边垂直于地面,“L”形的横边能够在连接块7的夹持孔内伸入或缩出。防滑安装块的可更换能够避免在防护栏发生损伤时对防护栏进行整体的更换,进而降低使用成本,有利于节约资源。Preferably, the anti-slip mounting block includes an anti-skid plate 6 and a connecting block 7 . The connecting block 7 is provided with a clamping hole on the side wall corresponding to the clamping block 32 , and the clamping block 32 can be located inside the clamping hole of the connecting block 7 . Lateral movement; the bottom surface of the connecting block 7 is fixed with an anti-skid plate 6, and the bottom of the anti-skid plate 6 is evenly provided with a plurality of anti-skid blocks, which can increase the anti-skid function of the guardrail; the clamping protrusion of the clamping block 32 can be It is arranged at the bottom, so that the overall shape of the clamping block 32 is an "L" shape, wherein the vertical side of the "L" shape of the clamping block 32 is perpendicular to the ground, and the horizontal side of the "L" shape can be in the clamping hole of the connecting block 7 Extend or retract. The replaceable anti-skid mounting block can avoid the overall replacement of the guardrail when the guardrail is damaged, thereby reducing the use cost and saving resources.

作为优选,夹持驱动电机10和连接块7之间设置一固定于安装基座1内壁的第二隔板38,夹持驱动电机10固定连接于第二隔板38表面,即采用第二隔板38作为夹持驱动电机10的支撑架,使夹持驱动电机10运行时更加的平稳。Preferably, a second partition plate 38 fixed on the inner wall of the mounting base 1 is provided between the clamping drive motor 10 and the connecting block 7, and the clamping and driving motor 10 is fixedly connected to the surface of the second partition plate 38, that is, the second partition plate 38 is used. The plate 38 is used as a support frame for clamping the driving motor 10 , so that the clamping and driving motor 10 operates more smoothly.

另外,第二隔板38板面上,对应于夹持块32的滑动范围开设有缺口,夹持块32的“L”形的竖边穿过第二隔板38板面上的缺口,并能够沿第二隔板38长边延伸方向进行横向滑动。随着夹持块32的横向滑动能够实现对连接块7进行夹持或者脱离。In addition, on the surface of the second partition plate 38, a gap is formed corresponding to the sliding range of the clamping block 32, and the vertical edge of the “L” shape of the clamping block 32 passes through the gap on the surface of the second partition plate 38, and It can slide laterally along the extending direction of the long side of the second partition plate 38 . The connecting block 7 can be clamped or disengaged with the lateral sliding of the clamping block 32 .

所述栏杆部包括与安装基座1顶面固定连接的两个连接部壳体3以及与连接部壳体3顶面固定连接的顶板5,连接部壳体3对顶板5起支撑作用。The railing part includes two connecting part shells 3 fixedly connected with the top surface of the installation base 1 and a top plate 5 fixedly connected with the top surface of the connecting part shell 3 , and the connecting part shell 3 supports the top plate 5 .

两个连接部壳体3之间且位于安装基座1的顶面固定有护栏板或均布的护栏柱,护栏板或护栏柱4的顶端与顶板5底面固定连接;连接部壳体3以及护栏板或护栏柱的高度不低于1.1米;所述连接部壳体3为中空柱状结构,且连接部壳体3内部空间与安装基座1的内部空间相连通,两个连接部壳体3沿安装基座1的顶面长边延伸方向的两端轴对称固定连接,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔。Between the two connection part shells 3 and located on the top surface of the installation base 1, a guardrail board or uniformly distributed guardrail post is fixed, and the top of the guardrail board or guardrail post 4 is fixedly connected with the bottom surface of the top board 5; the connection part housing 3 and The height of the guardrail board or guardrail column is not less than 1.1 meters; the connecting part shell 3 is a hollow cylindrical structure, and the inner space of the connecting part shell 3 is connected with the inner space of the installation base 1, and the two connecting part shells are connected with each other. 3. The two ends along the extension direction of the long side of the top surface of the installation base 1 are axially symmetrically connected, and the side of the connecting part housing 3 facing away from the railing part is provided with a connecting block for the connecting rod of the protective railing to extend into. Connect vias.

作为优选,两个连接部壳体3之间固定的为护栏柱4,护栏柱4为圆柱结构,每个护栏柱4之间的间隙小于10cm。Preferably, guardrail posts 4 are fixed between the two connection part shells 3, the guardrail posts 4 are cylindrical structures, and the gap between each guardrail post 4 is less than 10 cm.

作为一种具体实施方式,如图1-3所示,可以设计安装基座1底部外侧面装配有配重块2;配重块2朝向安装基座1外侧面的一侧固定有挂钩,安装基座1底部外侧面上配合挂钩开设有挂孔,通过将挂钩插入挂孔中完成配重与安装基座1的连接。配重块更够增加房建施工防护栏的整体稳定性,使其不容易受到大风或相当外力的影响,而且可以增加底部防滑安装块与地面之间的摩擦力,从而增强房建施工防护栏的防滑作用。As a specific implementation, as shown in Figures 1-3, it can be designed that the bottom outer side of the mounting base 1 is equipped with a counterweight 2; A hanging hole is formed on the outer surface of the bottom of the base 1 with the hook, and the connection between the counterweight and the installation base 1 is completed by inserting the hook into the hanging hole. The counterweight is enough to increase the overall stability of the building construction guardrail, making it less susceptible to strong winds or considerable external forces, and can increase the friction between the bottom anti-skid installation block and the ground, thereby enhancing the building construction guardrail anti-slip effect.

作为本发明方案的进一步的优化设计,为了更好的使得多个施工防护栏单体之间能够相互连接形成房建施工防护栏结构,还可以增加施工防护栏单体之间的连接安装结构。As a further optimized design of the solution of the present invention, in order to better enable multiple construction guardrail units to be connected to each other to form a building construction guardrail structure, the connection and installation structure between the construction guardrail units can also be increased.

具体而言,如图1至图7所示,包括用于连接相邻两个施工防护栏单体的防护栏连接杆,所述防护栏连接杆的两个端头位置处均具有尺寸径向扩展延伸的连接卡块。所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度,使得卡接槽的横截面形成“T”型槽;所述槽腔空间是指卡接限位部19顶端的卡接槽内部空间;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处。采用上述连接杆以及防护栏连接部的结构能够降低施工防护栏单体之间的安装难度,提高安装效率,同时,通过卡接限位部的结构能够提高施工防护栏单体之间的连接强度,使房建施工防护栏更加的稳固。Specifically, as shown in FIG. 1 to FIG. 7 , it includes a guardrail connecting rod for connecting two adjacent construction guardrail monomers, and the two end positions of the guardrail connecting rod have radial dimensions. Extension extension connection card block. The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a lifting block 18 that can be vertically lifted and slid is installed in the hollow space of the connecting portion shell 3. The lifting block The top of the 18 has a snap-on limit portion 19 that can be snap-fitted with the connection block of the connecting rod of the guardrail; the snap-on limit portion 19 is provided with an opening facing away from the side of the rail portion, and is vertical. The clipping slot extends upward to the top of the clipping limit portion 19, the cavity space of the clipping slot can be inserted into the connecting block of the connecting rod of the guardrail, and the lateral width of the slot of the clipping slot can be used for protection The rod portion of the rail connecting rod passes through and is smaller than the lateral width of the connecting block, so that the cross section of the snap groove forms a "T"-shaped groove; ; The lifting block 18 can be driven by the lifting block drive mechanism to perform lifting movement, and when the lifting block 18 is located at the lowest position and the highest position of the lifting, the top of the clamping limit portion 19 is respectively below the connecting at the position of the hole and above the position of the connecting through hole. Using the structure of the connecting rod and the connecting part of the guardrail can reduce the difficulty of installation between the construction guardrail monomers, improve the installation efficiency, and at the same time, the connection strength between the construction guardrail monomers can be improved by the structure of the clamping limit part. , so that the building construction guardrail is more stable.

作为优选,升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。这样,能够实现升降块的自动升降,减轻安装人员的安装负担,提高安装效率。Preferably, the lifting block driving mechanism comprises a vertical screw thread connected with the lifting block 18, and a lifting driving cross bar 13 installed in the hollow space of the mounting base 1 rotatably in the lateral direction; the vertical screw rod is rotatable vertically. It is installed in the connecting part of the guardrail, and extends downward into the hollow space of the installation base 1, and is connected with the lift drive cross bar 13 through a bevel gear pair; the lift drive cross bar 13 is fixed by The lift drive motor 9 installed in the hollow space of the mounting base 1 is driven to rotate. In this way, the automatic lifting and lowering of the lifting block can be realized, the installation burden of the installer is reduced, and the installation efficiency is improved.

作为优选,防护栏连接杆包括第一连接组件和第二连接组件;所述第一连接组件包括第一连接柱21和固定设置在第一连接柱21一端的第一连接卡块,第一连接柱21的另一端设有外螺纹;所述第一连接组件包括第二连接柱24和固定设置在第二连接柱24一端的第二连接卡块,第二连接柱24的另一端设有外螺纹;所述第一连接柱21和第二连接柱24的外螺纹端通过内螺纹连接套22进行连接。通过内螺纹连接套实现第一连接柱和第二连接柱之间的连接,方便快捷且连接牢固,有利于提高安装效率,降低安装难度,同时也使房建施工防护栏更加的稳固。Preferably, the guardrail connecting rod includes a first connecting assembly and a second connecting assembly; the first connecting assembly includes a first connecting column 21 and a first connecting block fixed at one end of the first connecting column 21, the first connecting The other end of the column 21 is provided with an external thread; the first connection assembly includes a second connection column 24 and a second connection block fixed at one end of the second connection column 24, and the other end of the second connection column 24 is provided with an external thread. Thread; the external thread ends of the first connection post 21 and the second connection post 24 are connected by an internal thread connection sleeve 22 . The connection between the first connection column and the second connection column is realized through the inner threaded connection sleeve, which is convenient, quick and firm in connection, which is beneficial to improve the installation efficiency, reduce the installation difficulty, and at the same time make the building construction guardrail more stable.

作为具体的实施方式而言,一个施工防护栏单体上安装的第一连接组件与另一个施工防护栏单体上安装的第二连接组件通过内螺纹连接套22螺纹连接后,能够将两个施工防护栏单体连接起来。As a specific embodiment, after the first connection component installed on one construction guardrail unit and the second connection component installed on the other construction guardrail unit are threadedly connected by the internal thread connection sleeve 22, the two The construction guardrail is connected in a single unit.

优选的,如图7所示,还可以在第一连接柱21和第二连接柱24的其中一个连接柱的外螺纹端增设导向柱25,另一个连接柱上设置插接孔;设置导向柱25的目的是在与另一个施工防护栏上的第一连接柱21滑动连接时导向柱插接入插接快内,能够便于防护栏连接杆的定位,增强安装定位准确度。Preferably, as shown in FIG. 7 , a guide post 25 can also be added to the external thread end of one of the first connection post 21 and the second connection post 24, and the other connection post is provided with an insertion hole; The purpose of 25 is to insert the guide column into the plug-in quick when slidingly connecting with the first connecting column 21 on another construction guardrail, which can facilitate the positioning of the guardrail connecting rod and enhance the installation and positioning accuracy.

作为一种具体实施方式,所述升降块驱动机构能够通过电力系统自动升降,所述电力系统包括升降驱动电机9、升降驱动横杆13以及转动轴16;所述电力系统位于安装基座1内部;所述升降驱动电机9固定于安装基座1内壁上,升降驱动电机9与驱动电路及供电电源8通过导线电性连接,升降驱动电机9的输出端固定连接有第一转动齿轮11;所述升降驱动横杆13的中段固定连接有第二转动齿轮12,升降驱动横杆13的两端分别固定连接有第一锥齿轮14,其中,第二转动齿轮12和第一转动齿轮11啮合连接;升降驱动横杆13上转动连接有至少两个支撑板,支撑板与安装基座1的内壁固定连接,能够让升降驱动横杆13转动的更加的稳定;所述升降驱动横杆13两端分别啮合连接有转动轴16,所述转动轴16转动连接有支撑板,支撑板固定于安装基座1内壁上,能够让转动轴16转动稳定;所述转动轴16的一端固定连接有第二锥齿轮15,另一端固定连接有及螺纹杆17;转动轴16通过第二锥齿轮15与升降驱动横杆13两端的第一锥齿轮14啮合连接;螺纹杆17顶端与升降块18螺纹连接。As a specific embodiment, the lifting block driving mechanism can be automatically lifted and lowered by an electric power system, and the electric power system includes a lifting driving motor 9 , a lifting driving cross bar 13 and a rotating shaft 16 ; the power system is located inside the installation base 1 . The lift drive motor 9 is fixed on the inner wall of the installation base 1, the lift drive motor 9 is electrically connected with the drive circuit and the power supply 8 through wires, and the output end of the lift drive motor 9 is fixedly connected with the first rotating gear 11; The middle section of the lifting and driving cross bar 13 is fixedly connected with a second rotating gear 12, and both ends of the lifting driving cross-bar 13 are fixedly connected with a first bevel gear 14, wherein the second rotating gear 12 and the first rotating gear 11 are meshed and connected. At least two support plates are rotatably connected to the lift drive cross bar 13, and the support plates are fixedly connected to the inner wall of the mounting base 1, which can make the lift drive cross bar 13 rotate more stably; both ends of the lift drive cross bar 13 A rotating shaft 16 is meshed and connected respectively, and a supporting plate is rotatably connected to the rotating shaft 16, and the supporting plate is fixed on the inner wall of the installation base 1, which can make the rotating shaft 16 rotate stably; one end of the rotating shaft 16 is fixedly connected with a second The other end of the bevel gear 15 is fixedly connected with a threaded rod 17; the rotating shaft 16 is meshed with the first bevel gear 14 at both ends of the lifting driving crossbar 13 through the second bevel gear 15;

作为优选,在安装基座1内设置第一隔板35,使安装基座1内形成两个独立的腔体,即第一放置腔36和第二放置腔37,升降块驱动机构设置于第一放置腔36内,活动夹持连接机构设置于第二放置腔37内,使各部件之间工作时更加的独立,不会相互影响;其中,第一放置腔36与连接部壳体3的内部相连通,所述升降块驱动机构中升降驱动横杆13上设置的支撑板与第一隔板35的表面固定连接,转动轴16与第一隔板35的表面转动连接。Preferably, a first partition 35 is arranged in the installation base 1, so that two independent cavities are formed in the installation base 1, namely the first placement cavity 36 and the second placement cavity 37, and the lifting block driving mechanism is arranged in the first place. In the first placing cavity 36, the movable clamping connecting mechanism is arranged in the second placing cavity 37, so that the components work more independently and will not influence each other; Internally connected, the support plate provided on the lift drive cross bar 13 in the lift block drive mechanism is fixedly connected to the surface of the first partition plate 35 , and the rotating shaft 16 is rotatably connected to the surface of the first partition plate 35 .

作为优选,驱动电路及供电电源8固定于第一放置腔36的安装基座1内壁上,用于给予防护栏中的电器提供动力。Preferably, the drive circuit and the power supply 8 are fixed on the inner wall of the installation base 1 of the first placement cavity 36 to provide power to the electrical appliances in the guardrail.

本发明所述施工防护栏主体材质为镀锌钢或不锈钢。The main material of the construction guardrail of the present invention is galvanized steel or stainless steel.

本发明所公开的一种房建施工防护栏在搭建时,首先将多个施工防护栏单体吊装至目标位置,并排列整齐,然后安装各个单体的防护栏连接杆。When constructing a building construction guardrail disclosed in the present invention, firstly, a plurality of construction guardrail monomers are hoisted to a target position, and arranged in an orderly manner, and then the guardrail connecting rods of each monomer are installed.

首先将第一连接组件插入连接部壳体3上的连接通孔内,通过升降块驱动机构内的升降驱动电机9带动卡接限位部19的上升,使第一连接组件上的第一连接卡块20位于卡接限位部19上的夹持孔中,具体卡接限位部19的上升过程如下所述:升降驱动电机9带动第一转动齿轮11进行转动,第一转动齿轮11转动带动啮合连接的第二转动齿轮12进行转动,第二转动齿轮12转动带动升降驱动横杆13进行转动,升降驱动横杆13转动的同时带动第一锥齿轮14转动,第一锥齿轮14转动带动啮合连接的第二锥齿轮15转动,第二锥齿轮15转动通过转动轴16带动螺纹杆17转动,螺纹杆17转动带动螺纹连接的升降块18升降,升降块18升降带动卡接限位部19上升。First, insert the first connecting assembly into the connecting through hole on the connecting part housing 3, and drive the latching limit part 19 to rise by the elevating drive motor 9 in the elevating block drive mechanism, so that the first connection on the first connecting assembly is made. The clamping block 20 is located in the clamping hole on the clamping stopper 19. The specific lifting process of the clamping stopper 19 is as follows: the lift drive motor 9 drives the first rotating gear 11 to rotate, and the first rotating gear 11 rotates It drives the meshed second rotating gear 12 to rotate, and the second rotating gear 12 rotates to drive the lift drive cross bar 13 to rotate. The lift drive cross bar 13 rotates while driving the first bevel gear 14 to rotate, and the first bevel gear 14 rotates to drive The meshing connection of the second bevel gear 15 rotates, the rotation of the second bevel gear 15 drives the threaded rod 17 to rotate through the rotating shaft 16, the threaded rod 17 rotates to drive the threaded lifting block 18 to rise and fall, and the lifting block 18 lifts and drives the clamping stopper 19. rise.

经过以上过程后,完成第一连接组件的连接,然后进行第二连接组件的连接,其连接过程同第一连接组件的连接,再此不再赘述,在第二连接组件连接完成后,将连接组件上的导向柱25与另一个防护栏上的连接组件上的插接孔对齐并插接,然后转动并拧紧内螺纹连接套22,使第二连接柱24和第一连接柱21连接牢固,进而使防护栏单体之间连接更加稳固。After the above process, the connection of the first connection component is completed, and then the connection of the second connection component is performed, and the connection process is connected with the first connection component, and will not be repeated here. The guide post 25 on the assembly is aligned with the insertion hole on the connection assembly on the other guardrail and inserted, and then the inner thread connecting sleeve 22 is rotated and tightened, so that the second connection post 24 and the first connection post 21 are firmly connected, Thus, the connection between the guardrail monomers is more stable.

当需要对防滑安装块进行更换时,通过夹持驱动电机10带动转动盘30进行转动,转动盘30转动带动转动连接的连接杆31进行转动,进而带动夹持块32分别横向的相互远离移动,从而使夹持块32脱离连接块7,完成连接块7的拆卸。再将安装基座1抬起,换入新的防滑安装块,并执行防滑安装块的安装操作步骤,即夹持块32伸入连接块7的夹持孔中,从而完成对防滑板6进行更换。When the anti-skid mounting block needs to be replaced, the rotating disk 30 is driven to rotate by the clamping driving motor 10, and the rotating disk 30 rotates to drive the rotating connecting rod 31 to rotate, thereby driving the clamping blocks 32 to move away from each other laterally, respectively. Thus, the clamping block 32 is separated from the connecting block 7 , and the disassembly of the connecting block 7 is completed. Then lift the installation base 1, replace it with a new anti-skid installation block, and perform the installation operation steps of the anti-skid installation block, that is, the clamping block 32 extends into the clamping hole of the connecting block 7, so as to complete the installation of the anti-skid plate 6. replace.

可以理解,本发明是通过一些实施例进行描述的,本领域技术人员知悉的,在不脱离本发明的精神和范围的情况下,可以对这些特征和实施例进行各种改变或等效替换。另外,在本发明的教导下,可以对这些特征和实施例进行修改以适应具体的情况及材料而不会脱离本发明的精神和范围。因此,本发明不受此处所公开的具体实施例的限制,所有落入本申请的权利要求范围内的实施例都属于本发明所保护的范围内。It can be understood that the present invention is described by some embodiments, and those skilled in the art know that various changes or equivalent substitutions can be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, in the teachings of this invention, these features and embodiments may be modified to adapt a particular situation and material without departing from the spirit and scope of the invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application fall within the protection scope of the present invention.

Claims (10)

1. The building construction protective guard is characterized by comprising an anti-skid mounting block and a construction protective guard single body, wherein the anti-skid mounting block is used for being mounted on the ground;
the anti-skid mounting block comprises an anti-skid plate (6) with an anti-skid structure on the bottom surface, a connecting block (7) is fixedly arranged on the upper surface of the anti-skid plate (6), and clamping holes are formed in two opposite side surfaces of the connecting block (7);
the construction protective guard single body comprises a mounting base (1) and a guard bar part arranged on the mounting base (1); the mounting base (1) is of a hollow structure with an opening at the bottom, the size of the opening at the bottom of the mounting base (1) is enough to enable the connecting block (7) of the anti-skid mounting block to extend into the hollow space of the mounting base (1), and a movable clamping connecting mechanism capable of clamping or loosening with two clamping holes in the connecting block (7) of the anti-skid mounting block is mounted in the hollow space of the mounting base (1).
2. The building construction protective guard according to claim 1, wherein the movable clamping and connecting mechanism comprises two clamping blocks (32) which are transversely arranged and oppositely arranged, the two clamping blocks (32) are opposite to the positions of the two clamping holes when the connecting block (7) of the anti-skid mounting block extends into the hollow space of the mounting base (1), and clamping protrusions which can extend into the clamping holes are arranged on the clamping blocks (32); the clamping device also comprises a transverse sliding limiting mechanism used for limiting the two clamping blocks (32) to move transversely close to or away from each other, and a clamping block driving mechanism used for driving the two clamping blocks (32) to move.
3. The building construction protective guard according to claim 2, wherein the clamping block driving mechanism comprises a rotating disc (30) transversely arranged between two clamping blocks (32), two opposite positions of the edge of the rotating disc (30) are rotatably connected with one ends of two connecting rods (31), and the other ends of the two connecting rods (31) are respectively rotatably connected with the two clamping blocks (32); the rotating disc (30) is driven to rotate by a clamping driving motor (10) fixedly installed in the hollow space of the installation base (1).
4. The building construction protective guard according to claim 2, wherein the transverse sliding limiting mechanism comprises a positioning sliding column (33) fixedly connected with the clamping blocks (32) and arranged transversely, one end of the positioning sliding column (33) far away from the clamping blocks (32) is slidably inserted into a transversely arranged cylindrical positioning sliding sleeve (34), and the transverse sliding of the positioning sliding column (33) in the positioning sliding sleeve (34) limits the two clamping blocks (32) to move transversely close to or away from each other; the positioning sliding sleeve (34) is fixedly arranged in the hollow space of the mounting base (1).
5. The building construction protective guard of claim 1, wherein the construction protective guard single body further comprises a balancing weight (2) detachably connected with the mounting base (1); be equipped with the couple on balancing weight (2), be equipped with the hanging hole on the lateral surface of mounting base (1), balancing weight (2) are through couple detachable erection joint on the hanging hole of mounting base (1) lateral surface.
6. The building construction protective guard according to claim 1, further comprising a protective guard connecting rod for connecting two adjacent construction protective guard units, wherein connecting blocks extending radially and expanding in size are arranged at two end positions of the protective guard connecting rod;
guard rail connecting parts are further arranged at the positions, located on the two sides of the guard rail part, on the mounting base (1) of the construction guard rail single body; the protective guard connecting part comprises a hollow connecting part shell (3), one side of the connecting part shell (3), which is back to the guard rod part, is provided with a connecting through hole into which a connecting fixture block of the protective guard connecting rod can extend, a lifting block (18) which can vertically lift and slide is installed in the hollow space of the connecting part shell (3), and the top of the lifting block (18) is provided with a clamping limiting part (19) which can be in clamping fit with the connecting fixture block of the protective guard connecting rod; the clamping limiting part (19) is provided with a clamping groove with an opening facing back to the direction of one side of the railing part and vertically penetrating upwards to the top end of the clamping limiting part (19), a groove cavity space of the clamping groove can be used for a connecting clamping block of a connecting rod of the protective guard to stretch into, and the transverse width of a notch of the clamping groove can be used for the rod part of the connecting rod of the protective guard to pass through and is smaller than that of the connecting clamping block; the lifting block (18) can be driven by the lifting block driving mechanism to perform lifting movement, and when the lifting block (18) is located at the lowest position and the highest position of lifting, the top end of the clamping limiting portion (19) is located at the position lower than the connecting through hole and the position higher than the connecting through hole respectively.
7. The building construction protective guard of claim 6, wherein the lifting block driving mechanism comprises a vertical screw rod in threaded connection with the lifting block (18) and a lifting driving cross rod (13) which is transversely and rotatably installed in the hollow space of the mounting base (1); the vertical screw rod is vertically and rotatably arranged on the connecting part of the protective guard, extends downwards into the hollow space of the mounting base (1), and is in transmission connection with the lifting driving cross rod (13) through a bevel gear pair; the lifting driving cross rod (13) is driven to rotate by a lifting driving motor (9) fixedly installed in the hollow space of the installation base (1).
8. The building construction protective guard of claim 6, wherein the protective guard connecting rod comprises a first connecting assembly and a second connecting assembly; the first connecting assembly comprises a first connecting column (21) and a first connecting clamping block fixedly arranged at one end of the first connecting column (21), and the other end of the first connecting column (21) is provided with an external thread; the first connecting assembly comprises a second connecting column (24) and a second connecting clamping block fixedly arranged at one end of the second connecting column (24), and the other end of the second connecting column (24) is provided with an external thread; the external thread ends of the first connecting column (21) and the second connecting column (24) are connected through an internal thread connecting sleeve (22).
9. A construction protective guard single body is characterized by comprising a mounting base (1) and a guard bar part arranged on the mounting base (1); the mounting base (1) is of a hollow structure with an opening at the bottom, the size of the opening at the bottom of the mounting base (1) is enough to enable the connecting block (7) of the anti-skid mounting block to extend into the hollow space of the mounting base (1), and a movable clamping connecting mechanism capable of clamping or loosening with two clamping holes in the connecting block (7) of the anti-skid mounting block is mounted in the hollow space of the mounting base (1).
10. The construction protective guard unit as claimed in claim 9, wherein the movable clamping and connecting mechanism comprises two clamping blocks (32) which are transversely arranged and oppositely arranged, and the two clamping blocks (32) are opposite to the positions of the two clamping holes when the connecting block (7) of the anti-skid mounting block extends into the hollow space of the mounting base (1), and the clamping blocks (32) are provided with clamping protrusions which can extend into the clamping holes; the clamping device also comprises a transverse sliding limiting mechanism for limiting the transverse movement of the two clamping blocks (32) to be close to or away from each other, and a clamping block driving mechanism for driving the two clamping blocks (32) to move;
the clamping block driving mechanism comprises a rotating disc (30) transversely arranged between two clamping blocks (32), two opposite positions of the edge of the rotating disc (30) are rotatably connected to one ends of two connecting rods (31), and the other ends of the two connecting rods (31) are respectively rotatably connected to the two clamping blocks (32); the rotating disc (30) is driven to rotate by a clamping driving motor (10) fixedly arranged in the hollow space of the mounting base (1);
the transverse sliding limiting mechanism comprises a positioning sliding column (33) which is fixedly connected with the clamping blocks (32) and transversely arranged, one end, far away from the clamping blocks (32), of the positioning sliding column (33) is slidably inserted into a transversely arranged cylindrical positioning sliding sleeve (34), and then the transverse sliding of the positioning sliding column (33) in the positioning sliding sleeve (34) limits the two clamping blocks (32) to transversely move close to or away from each other; the positioning sliding sleeve (34) is fixedly arranged in the hollow space of the mounting base (1);
guard rail connecting parts are further arranged at the positions, located on the two sides of the guard rail part, on the mounting base (1) of the construction guard rail single body; the protective guard connecting part comprises a hollow connecting part shell (3), one side of the connecting part shell (3), which is back to the guard rod part, is provided with a connecting through hole into which a connecting fixture block of the protective guard connecting rod can extend, a lifting block (18) which can vertically lift and slide is installed in the hollow space of the connecting part shell (3), and the top of the lifting block (18) is provided with a clamping limiting part (19) which can be in clamping fit with the connecting fixture block of the protective guard connecting rod; the clamping limiting part (19) is provided with a clamping groove with an opening back to the direction of one side of the rail part and vertically and upwardly penetrating to the top end of the clamping limiting part (19), a groove cavity space of the clamping groove can be used for a connecting clamping block of a connecting rod of the protective guard to stretch into, and the transverse width of a notch of the clamping groove can be used for the rod part of the connecting rod of the protective guard to pass through and is smaller than the transverse width of the connecting clamping block; the lifting block (18) can perform lifting motion under the driving of the lifting block driving mechanism, and when the lifting block (18) is positioned at the lowest position and the highest position of lifting, the top end of the clamping limiting part (19) is respectively positioned at the position lower than the connecting through hole and the position higher than the connecting through hole;
the lifting block driving mechanism comprises a vertical screw rod in threaded connection with a lifting block (18) and a lifting driving cross rod (13) which is transversely and rotatably arranged in a hollow space of the mounting base (1); the vertical screw rod is vertically and rotatably arranged on the connecting part of the protective guard, extends downwards into the hollow space of the mounting base (1), and is in transmission connection with the lifting driving cross rod (13) through a bevel gear pair; the lifting driving cross rod (13) is driven to rotate by a lifting driving motor (9) fixedly installed in the hollow space of the installation base (1).
CN202210607314.2A 2022-05-31 2022-05-31 Construction rail guard is built in room Active CN114753713B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210607314.2A CN114753713B (en) 2022-05-31 2022-05-31 Construction rail guard is built in room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210607314.2A CN114753713B (en) 2022-05-31 2022-05-31 Construction rail guard is built in room

Publications (2)

Publication Number Publication Date
CN114753713A true CN114753713A (en) 2022-07-15
CN114753713B CN114753713B (en) 2023-07-18

Family

ID=82337236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210607314.2A Active CN114753713B (en) 2022-05-31 2022-05-31 Construction rail guard is built in room

Country Status (1)

Country Link
CN (1) CN114753713B (en)

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002357023A (en) * 2001-05-30 2002-12-13 Toyo Exterior Co Ltd Device for erecting and fixing post of installation on ground
US6648304B1 (en) * 2002-03-01 2003-11-18 Xcel Distribution, Inc. Modular fence
KR101576938B1 (en) * 2014-07-01 2015-12-15 권상우 The pivotable balustrade
US20170037653A1 (en) * 2014-04-13 2017-02-09 Manfred Schopf Clamps for panel-type fences
JP2017040147A (en) * 2015-08-21 2017-02-23 株式会社Lixil Fence fitting structure
US20190112817A1 (en) * 2015-10-09 2019-04-18 Aluminco A.E. Glass windbreaker
CN209011701U (en) * 2018-10-26 2019-06-21 沈阳工学院 A kind of water conservancy construction safety guard
CN209976161U (en) * 2019-03-20 2020-01-21 河北建设集团股份有限公司 Rail guard for construction
CN211923774U (en) * 2020-03-17 2020-11-13 王波 Municipal construction fast-assembling protector
CN211974612U (en) * 2020-03-18 2020-11-20 重庆胤通建设开发有限公司 Safety protective guard is used in electric power engineering construction
CN212176804U (en) * 2020-04-10 2020-12-18 江苏诤友交通科技有限公司 Rail guard convenient to installation and dismantlement
CN212958036U (en) * 2020-06-23 2021-04-13 浙江国建建设有限公司 Security protection device for construction
CN113047199A (en) * 2021-02-04 2021-06-29 天长市锦瑞防护设施有限公司 Rail guard for building with flexible function
CN213806695U (en) * 2020-10-26 2021-07-27 钟家颖 Town road foundation ditch safety protection subassembly
CN213898441U (en) * 2020-11-05 2021-08-06 山东美汉林建设集团有限公司 Liftable bounding wall for building engineering
CN214740404U (en) * 2021-03-18 2021-11-16 重庆第二师范学院 Rail guard is used in kindergarten
CN215056069U (en) * 2021-03-29 2021-12-07 江苏省华建建设股份有限公司 High building protector for construction that stability is good
CN215485138U (en) * 2021-06-03 2022-01-11 佛山市富贵龙门业有限公司 Assembled railing
CN216380523U (en) * 2021-06-03 2022-04-26 马东旭 Movable building construction platform convenient to fix
CN216617122U (en) * 2021-12-08 2022-05-27 广州市川拓瑞工程设备有限公司 Rail guard is used in civil engineering construction

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002357023A (en) * 2001-05-30 2002-12-13 Toyo Exterior Co Ltd Device for erecting and fixing post of installation on ground
US6648304B1 (en) * 2002-03-01 2003-11-18 Xcel Distribution, Inc. Modular fence
US20170037653A1 (en) * 2014-04-13 2017-02-09 Manfred Schopf Clamps for panel-type fences
KR101576938B1 (en) * 2014-07-01 2015-12-15 권상우 The pivotable balustrade
JP2017040147A (en) * 2015-08-21 2017-02-23 株式会社Lixil Fence fitting structure
US20190112817A1 (en) * 2015-10-09 2019-04-18 Aluminco A.E. Glass windbreaker
CN209011701U (en) * 2018-10-26 2019-06-21 沈阳工学院 A kind of water conservancy construction safety guard
CN209976161U (en) * 2019-03-20 2020-01-21 河北建设集团股份有限公司 Rail guard for construction
CN211923774U (en) * 2020-03-17 2020-11-13 王波 Municipal construction fast-assembling protector
CN211974612U (en) * 2020-03-18 2020-11-20 重庆胤通建设开发有限公司 Safety protective guard is used in electric power engineering construction
CN212176804U (en) * 2020-04-10 2020-12-18 江苏诤友交通科技有限公司 Rail guard convenient to installation and dismantlement
CN212958036U (en) * 2020-06-23 2021-04-13 浙江国建建设有限公司 Security protection device for construction
CN213806695U (en) * 2020-10-26 2021-07-27 钟家颖 Town road foundation ditch safety protection subassembly
CN213898441U (en) * 2020-11-05 2021-08-06 山东美汉林建设集团有限公司 Liftable bounding wall for building engineering
CN113047199A (en) * 2021-02-04 2021-06-29 天长市锦瑞防护设施有限公司 Rail guard for building with flexible function
CN214740404U (en) * 2021-03-18 2021-11-16 重庆第二师范学院 Rail guard is used in kindergarten
CN215056069U (en) * 2021-03-29 2021-12-07 江苏省华建建设股份有限公司 High building protector for construction that stability is good
CN215485138U (en) * 2021-06-03 2022-01-11 佛山市富贵龙门业有限公司 Assembled railing
CN216380523U (en) * 2021-06-03 2022-04-26 马东旭 Movable building construction platform convenient to fix
CN216617122U (en) * 2021-12-08 2022-05-27 广州市川拓瑞工程设备有限公司 Rail guard is used in civil engineering construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王波;: "超高落地外架的设计与施工", 安徽建筑, no. 03, pages 65 - 66 *
王羽;张昶;舒宗瑛;: "桩周岩土稳定性评价中无损探测技术的应用", 中外公路, no. 02, pages 25 - 28 *

Also Published As

Publication number Publication date
CN114753713B (en) 2023-07-18

Similar Documents

Publication Publication Date Title
CN105565221A (en) Lifting device for maintaining wiring terminals on power distribution station outdoor wall
KR100945561B1 (en) Method and apparatus for constructing pole of tower-type facilities
CN114753713A (en) Building construction rail guard
CN204139631U (en) Quick-release protective railings for construction sites
CN110905206A (en) Overhanging discharging platform with drawing type channel and construction method
CN210867008U (en) Adjustable traction pulley for incoming cable of residential meter box
CN211447919U (en) Power box protection shed convenient to mount and dismount
CN217420434U (en) Assembled suspension platform for electric hanging basket
CN210483251U (en) Municipal works are with construction warning baffle
CN221741579U (en) Fixing device for building steel structure support column
CN203345999U (en) Special multifunctional lifting frame for busbar bridge
CN114229740A (en) Machine of lifting is used in installation of building interior decoration furred ceiling board
CN216476706U (en) Building rail is used in municipal administration convenient to dismantle
CN113668871B (en) Prefabricated reinforced concrete structural beam for assembled house building
CN114575655B (en) Power supply line support frame
CN220979087U (en) Building construction management encloses fender fixing device
CN112523491A (en) Assembled steel construction building joins externally template
CN216588056U (en) Highway engineering is with making an uproar protection rail that falls
CN112279174A (en) Firm underground pipeline is well lid opening device for measurement
CN110697596A (en) Material lifting device for building engineering
CN221399908U (en) Positioning die for construction of embedded anchor bolts
CN217439682U (en) Simple guardrail upright post fixing device capable of being repeatedly used in turnover mode
CN219622434U (en) Construction security protection device
CN215562776U (en) An easy-to-build tower crane base structure with anti-fall
CN215484755U (en) Liftable support for construction engineering construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20220715

Assignee: Chongqing Lingshi Engineering Technology Co.,Ltd.

Assignor: CHONGQING University OF EDUCATION

Contract record no.: X2024980035462

Denomination of invention: A building construction protective fence

Granted publication date: 20230718

License type: Common License

Record date: 20241210

EE01 Entry into force of recordation of patent licensing contract