CN114753713A - Building construction rail guard - Google Patents
Building construction rail guard Download PDFInfo
- Publication number
- CN114753713A CN114753713A CN202210607314.2A CN202210607314A CN114753713A CN 114753713 A CN114753713 A CN 114753713A CN 202210607314 A CN202210607314 A CN 202210607314A CN 114753713 A CN114753713 A CN 114753713A
- Authority
- CN
- China
- Prior art keywords
- clamping
- block
- mounting base
- lifting
- protective guard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009435 building construction Methods 0.000 title claims abstract description 30
- 238000009434 installation Methods 0.000 claims abstract description 120
- 238000010276 construction Methods 0.000 claims abstract description 78
- 239000011796 hollow space material Substances 0.000 claims abstract description 45
- 230000001681 protective effect Effects 0.000 claims description 30
- 230000033001 locomotion Effects 0.000 claims description 17
- 230000005540 biological transmission Effects 0.000 claims description 4
- 230000000149 penetrating effect Effects 0.000 claims 2
- 239000000178 monomer Substances 0.000 abstract description 20
- 230000001066 destructive effect Effects 0.000 abstract description 3
- 238000000034 method Methods 0.000 description 20
- 238000005192 partition Methods 0.000 description 11
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 8
- 238000010586 diagram Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 229910052742 iron Inorganic materials 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000005553 drilling Methods 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 230000003028 elevating effect Effects 0.000 description 2
- 230000002708 enhancing effect Effects 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000004064 recycling Methods 0.000 description 2
- 230000001629 suppression Effects 0.000 description 2
- 229910001335 Galvanized steel Inorganic materials 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 239000008397 galvanized steel Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 239000010935 stainless steel Substances 0.000 description 1
- 229910001220 stainless steel Inorganic materials 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/16—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts using prefabricated panel-like elements, e.g. wired frames
- E04H17/18—Corrals, i.e. easily transportable or demountable enclosures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/20—Posts therefor
- E04H17/22—Anchoring means therefor, e.g. specially-shaped parts entering the ground; Struts or the like
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
本发明提供了一种房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体;述防滑安装块包括底面具有防滑结构的防滑板,防滑板的上表面固定设置有连接块,所述连接块的两个相对侧面上设有夹持孔;所述施工防护栏单体包括安装基座以及设置于安装基座上的栏杆部;所述安装基座为底部开口的中空结构,安装基座的底部开口尺寸足够使得防滑安装块的连接块伸入至安装基座的中空空间,且安装基座的中空空间内安装有能够与防滑安装块的连接块上的两个夹持孔相夹持或松脱的活动夹持连接机构。本发明中防滑安装块和施工防护栏单体能够单独更换,且拆卸安装施工简便无破坏,能够进行二次回收使用。
The invention provides a building construction protection fence, which includes a non-slip installation block for installation on the ground, and a construction protection fence unit that can be detachably clamped and installed on the non-slip installation block; the non-slip installation block includes The bottom surface has an anti-skid plate with an anti-skid structure, the upper surface of the anti-skid plate is fixedly provided with a connecting block, and two opposite sides of the connecting block are provided with clamping holes; The railing part on the base; the mounting base is a hollow structure with an opening at the bottom, and the size of the bottom opening of the mounting base is enough to make the connecting block of the anti-skid mounting block protrude into the hollow space of the mounting base, and the hollow space of the mounting base is A movable clamping connection mechanism capable of clamping or releasing with the two clamping holes on the connection block of the anti-skid installation block is installed in the space. In the present invention, the non-slip installation block and the construction guardrail monomer can be replaced independently, and the disassembly, installation and construction are simple and non-destructive, and can be recycled and used twice.
Description
技术领域technical field
本发明涉及房建施工设备领域,具体涉及一种房建施工防护栏。The invention relates to the field of housing construction equipment, in particular to a housing construction protection fence.
背景技术Background technique
房屋建筑工程是指各类房屋建筑及其附属设施和与其配套的线路、管道、设备安装工程及室内外装修工程,“房屋建筑”指有顶盖、梁柱、墙壁、基础以及能够形成内部空间,满足人们生产、居住、学习、公共活动等需要的工程。Housing construction engineering refers to all kinds of housing construction and its ancillary facilities and their supporting lines, pipelines, equipment installation works and indoor and outdoor decoration works. , to meet the needs of people's production, living, learning, public activities and other projects.
在房屋建筑工程进行勘察、规划、设计、施工、安装和维护等各项技术工作时,常常需要防护栏,现有的防护栏底部要么没有设置防滑措施,要么在底部设置简单且固定的防滑块或防滑垫。When conducting various technical work such as survey, planning, design, construction, installation and maintenance of housing construction projects, guardrails are often required. The bottom of the existing guardrails either does not have anti-skid measures, or is provided with simple and fixed anti-skid blocks at the bottom. or non-slip mats.
没有设置防滑措施的防护栏防滑系数较低,无法起到防滑的作用,对于基坑边坡处的护栏或者是高层的护栏而言,没有防滑措施会有较大的安全隐患。The anti-skid coefficient of the guardrail without anti-skid measures is low and cannot play the role of anti-skid. For the guardrail on the slope of the foundation pit or the guardrail on the high-rise, there will be a greater safety hazard without anti-skid measures.
护栏底部设置简单且固定的防滑块或防滑垫的护栏虽能够起到一定的防滑作用,但是在使用完毕后,在拆除防护栏时往往会将防滑块损毁或将上部防护栏损毁,进而导致整个防护栏的废弃,无法进行二次回收使用,浪费了大量的资源。The guardrail with simple and fixed anti-skid blocks or anti-skid pads at the bottom of the guardrail can play a certain anti-slip effect, but after use, the anti-skid blocks or the upper guardrail are often damaged when the guardrail is removed, which will lead to the whole. The abandonment of the guardrail cannot be used for secondary recycling, which wastes a lot of resources.
另外,现有常用的建筑围挡式的护栏常常为铁质的护栏板,安装方式为手动安装,具体为在硬化的地面或已经铺好的人行道地面打孔并安装膨胀螺丝,然后将护栏底部与膨胀螺丝螺纹连接,护栏单体之间也采用螺丝进行连接,在此过程中需要破坏地面原始结构,在施工完成护栏拆除后,地面上留下大量的螺丝孔,行人在行走时容易绊倒,降低行人在人行道行走时的安全系数;护栏安装时还需要大量的人力进行螺丝的紧固操作,这一操作费时费力;而且铁质的护栏板高度过高,不适合勘察时对现场的查看。而且铁质的护栏板防风效果较差,容易被大风吹倒或发生变形,有较大的安全隐患。In addition, the existing commonly used building enclosure-type guardrails are often iron guardrail boards, and the installation method is manual installation, specifically, drilling holes on the hardened ground or paved sidewalk ground and installing expansion screws, and then installing the bottom of the guardrail. It is threadedly connected with expansion screws, and the guardrails are also connected by screws. During this process, the original structure of the ground needs to be destroyed. After the guardrail is removed, a large number of screw holes are left on the ground, and pedestrians are prone to tripping when walking. , reducing the safety factor of pedestrians walking on the sidewalk; the installation of the guardrail also requires a lot of manpower to fasten the screws, which is time-consuming and laborious; and the height of the iron guardrail is too high, which is not suitable for site inspection during surveys. . Moreover, the iron guardrail has poor windproof effect and is easily blown down or deformed by strong winds, posing a greater safety hazard.
发明内容SUMMARY OF THE INVENTION
本发明目的在于提供一种房建施工防护栏,以解决现有施工防护栏损坏后拆卸及更换安装不便、更换成本较高等技术问题。The purpose of the present invention is to provide a building construction guardrail, so as to solve the technical problems of inconvenient disassembly, replacement and installation, and high replacement cost after the existing construction guardrail is damaged.
为了解决上述技术问题,本发明采用了如下的技术方案:In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions:
一种房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体;A housing construction construction guardrail, comprising a non-slip installation block for installation on the ground, and a construction guardrail monomer capable of being detachably clamped and installed on the non-slip installation block;
所述防滑安装块包括底面具有防滑结构的防滑板6,防滑板6的上表面固定设置有连接块7,所述连接块7的两个相对侧面上设有夹持孔;The anti-skid installation block includes a skid plate 6 with an anti-skid structure on the bottom surface, a connecting block 7 is fixedly arranged on the upper surface of the anti-skid plate 6, and two opposite sides of the connecting block 7 are provided with clamping holes;
所述施工防护栏单体包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The construction guardrail unit includes an installation base 1 and a railing portion arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the bottom opening of the installation base 1 is sufficient to make the anti-skid installation block. The connecting block 7 extends into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is provided with a movable movable that can be clamped or released with the two clamping holes on the connecting block 7 of the anti-skid mounting block. Clamp connection mechanism.
这样,当房建施工防护栏上的防滑安装块或者施工防护栏单体受损时,可以将防滑安装块或者施工防护栏单体进行独立更换,增加房建施工防护栏的利用率,延长使用年限;而且防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,拆卸及更换安装都更加方便。In this way, when the non-slip mounting block or the single construction guardrail on the housing construction guardrail is damaged, the non-slip mounting block or the single construction guardrail can be replaced independently, which increases the utilization rate of the housing construction guardrail and prolongs the use of the guardrail. Moreover, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, which is more convenient for disassembly and replacement and installation.
上述的房建施工防护栏中,优选的,所述活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构。In the above-mentioned housing construction protection bar, preferably, the movable clamping connection mechanism includes two
这样,活动夹持连接采用了夹持块横向移动并与连接块插接的方式实现防滑安装块的快速拆装,方便防滑安装块或者施工防护栏单体的更换。In this way, the movable clamping connection adopts the method of lateral movement of the clamping block and plug connection with the connecting block to realize the rapid disassembly and assembly of the anti-skid installation block, which is convenient for the replacement of the anti-skid installation block or the single construction guardrail.
上述的房建施工防护栏中,优选的,所述夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动。In the above-mentioned housing construction protection bar, preferably, the clamping block driving mechanism includes a rotating
采用上述夹持块驱动机构采用了传动的方式,使夹持块能够进行线性横向运动,使夹持块伸入或伸出夹持孔的过程更加精准和平稳。The above-mentioned clamping block driving mechanism adopts a transmission mode, so that the clamping block can perform linear lateral movement, so that the process of the clamping block extending into or out of the clamping hole is more precise and stable.
上述的房建施工防护栏中,优选的,所述横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内。In the above-mentioned housing construction protection bar, preferably, the lateral sliding limit mechanism includes a
采用上述横向限位机构能够使夹持块横向运动的方向更精准,不容易发生偏离。The use of the above-mentioned lateral limiting mechanism can make the direction of lateral movement of the clamping block more precise and less likely to deviate.
上述的房建施工防护栏中,优选的,所述施工防护栏单体还包括与安装基座1可拆卸连接的配重块2;所述配重块2上设有挂钩,所述安装基座1的外侧面上设有挂孔,所述配重块2通过挂钩可拆卸的安装连接在安装基座1外侧面的挂孔上。In the above-mentioned building construction guardrail, preferably, the construction guardrail unit further includes a counterweight 2 that is detachably connected to the installation base 1; the counterweight 2 is provided with a hook, and the installation base Hanging holes are provided on the outer side of the base 1 , and the counterweight 2 is detachably installed and connected to the hanging holes on the outer side of the mounting base 1 through hooks.
配重块更够增加房建施工防护栏的整体稳定性,使其不容易受到大风或相当外力的影响,而且可以增加底部防滑安装块与地面之间的摩擦力,从而增强房建施工防护栏的防滑作用。The counterweight is enough to increase the overall stability of the building construction guardrail, making it less susceptible to strong winds or considerable external forces, and can increase the friction between the bottom anti-skid installation block and the ground, thereby enhancing the building construction guardrail anti-slip effect.
上述的房建施工防护栏中,优选的,还包括用于连接相邻两个施工防护栏单体的防护栏连接杆,所述防护栏连接杆的两个端头位置处均具有尺寸径向扩展延伸的连接卡块;The above-mentioned building construction guardrail, preferably, further includes a guardrail connecting rod for connecting two adjacent construction guardrail monomers, and the two end positions of the guardrail connecting rod have radial dimensions. Extended extension connection card block;
所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处。The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a
采用上述连接杆以及防护栏连接部的结构能够降低施工防护栏单体之间的安装难度,提高安装效率,同时,通过卡接限位部的结构能够提高施工防护栏单体之间的连接强度,使房建施工防护栏更加的稳固。Using the structure of the connecting rod and the connecting part of the guardrail can reduce the difficulty of installation between the construction guardrail monomers, improve the installation efficiency, and at the same time, the connection strength between the construction guardrail monomers can be improved by the structure of the clamping limit part. , so that the building construction guardrail is more stable.
上述的房建施工防护栏中,优选的,所述升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。In the above-mentioned housing construction protection fence, preferably, the lifting block driving mechanism includes a vertical screw thread connected with the
这样,能够实现升降块的自动升降,减轻安装人员的安装负担,提高安装效率。In this way, the automatic lifting and lowering of the lifting block can be realized, the installation burden of the installer is reduced, and the installation efficiency is improved.
上述的房建施工防护栏中,优选的,所述防护栏连接杆包括第一连接组件和第二连接组件;所述第一连接组件包括第一连接柱21和固定设置在第一连接柱21一端的第一连接卡块,第一连接柱21的另一端设有外螺纹;所述第一连接组件包括第二连接柱24和固定设置在第二连接柱24一端的第二连接卡块,第二连接柱24的另一端设有外螺纹;所述第一连接柱21和第二连接柱24的外螺纹端通过内螺纹连接套22进行连接。In the above-mentioned building construction guardrail, preferably, the guardrail connecting rod includes a first connecting assembly and a second connecting assembly; the first connecting assembly includes a first connecting
通过内螺纹连接套实现第一连接柱和第二连接柱之间的连接,方便快捷且连接牢固,有利于提高安装效率,降低安装难度,同时也使房建施工防护栏更加的稳固。The connection between the first connection column and the second connection column is realized through the inner threaded connection sleeve, which is convenient, quick and firm in connection, which is beneficial to improve the installation efficiency, reduce the installation difficulty, and at the same time make the building construction guardrail more stable.
本发明还提供一种施工防护栏单体,包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The present invention also provides a construction guardrail unit, comprising an installation base 1 and a railing portion arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the opening at the bottom of the installation base 1 is Enough to make the connecting block 7 of the anti-skid mounting block extend into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is installed with two clamping holes on the connecting block 7 of the anti-skid mounting block. Or loose movable clamp connection mechanism.
上述的施工防护栏单体中,优选的,所述活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构;In the above-mentioned construction guardrail unit, preferably, the movable clamping connection mechanism includes two laterally arranged and oppositely arranged
所述夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动;The clamping block driving mechanism includes a rotating
所述横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内;The lateral sliding limit mechanism includes a
所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处;The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a
所述升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。The lifting block driving mechanism includes a vertical screw thread connected with the lifting
本发明具有以下有益效果:The present invention has the following beneficial effects:
1、本发明的房建施工防护栏中,其防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,使得防滑安装块和施工防护栏单体局部损坏后都分别能够单独更换,有助于降低了更换成本,拆卸及更换安装也更加方便,且拆卸安装施工简便无破坏,能够进行二次回收使用;1. In the housing construction guardrail of the present invention, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, so that the anti-skid installation block and the construction guardrail monomer can be separately damaged after partial damage. The replacement helps to reduce the replacement cost, and the disassembly, replacement and installation are also more convenient, and the disassembly and installation construction is simple and non-destructive, and can be recycled and used for the second time;
2、本发明的防护栏采用防护栏连接杆有动力装配方式,以及防护栏连接杆之间的螺纹及内螺纹连接套进行连接,此装配方式和连接方式使防护栏单体之间的连接更加稳固,同时,人工只需辅助防护栏单体之间的连接,使防护栏单体之间的连接更加便捷;2. The guardrail of the present invention adopts the power assembly method of the guardrail connecting rod, and the thread and the inner thread connecting sleeve between the guardrail connecting rods are connected. This assembly method and connection method make the connection between the guardrail monomers more convenient. It is stable, and at the same time, it is only necessary to assist the connection between the guardrail units manually, which makes the connection between the guardrail units more convenient;
3、本发明的防护栏无需对周边安装环境进行机械打孔,无需人工紧固大量的螺丝,对周边环境友好无破坏,拆除后无安全隐患;3. The guardrail of the present invention does not require mechanical drilling of the surrounding installation environment, does not need to manually tighten a large number of screws, is friendly to the surrounding environment and does not damage the surrounding environment, and has no potential safety hazards after dismantling;
4、本发明的防护栏底部还可以配备配重,使防护栏能够保持自身稳定,不易受到恶劣天气的影响;4. The bottom of the guardrail of the present invention can also be equipped with a counterweight, so that the guardrail can maintain its own stability and is not easily affected by bad weather;
5、本发明的防护栏自带驱动电路及供电电源,能够给防护栏的附加设施,如降尘喷雾器等提供附加接口,便于防护栏及其附加设施的集成化,适用于多场景。5. The guardrail of the present invention has its own drive circuit and power supply, which can provide additional interfaces for the additional facilities of the guardrail, such as dust suppression sprayers, etc., which facilitates the integration of the guardrail and its additional facilities, and is suitable for multiple scenarios.
附图说明Description of drawings
为了使发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明作进一步的详细描述,其中:In order to make the purpose, technical solutions and advantages of the invention clearer, the present invention will be described in further detail below in conjunction with the accompanying drawings, wherein:
图1为本发明一种房建施工防护栏的结构示意图;Fig. 1 is the structural representation of a kind of building construction guardrail of the present invention;
图2为本发明一种房建施工防护栏配重块与安装基座的连接结构示意图;Figure 2 is a schematic diagram of the connection structure of a building construction guardrail counterweight and an installation base of the present invention;
图3为本发明一种房建施工防护栏连接块与防滑板的连接结构示意图;FIG. 3 is a schematic diagram of the connection structure of a connecting block of a building construction guardrail and an anti-skid plate according to the present invention;
图4为本发明一种房建施工防护栏安装基座的内部结构示意图;4 is a schematic diagram of the internal structure of a housing construction construction guardrail installation base according to the present invention;
图5为本发明一种房建施工防护栏升降块与螺纹杆的连接结构示意图;Figure 5 is a schematic diagram of the connection structure of the lifting block and the threaded rod of a housing construction construction guardrail according to the present invention;
图6为本发明一种房建施工防护栏导向柱与第一连接柱的连接结构示意图;6 is a schematic diagram of the connection structure of a guide post of a housing construction construction guardrail and a first connection post of the present invention;
图7为本发明一种房建施工防护栏连接杆与转动盘的连接结构示意图。FIG. 7 is a schematic diagram of the connection structure of a connecting rod of a building construction guardrail and a rotating disk according to the present invention.
附图标记说明:1、安装基座;2、配重块;3、连接部壳体;4、护栏柱;5、顶板;6、防滑板;7、连接块;8、驱动电路及供电电源;9、升降驱动电机;10、夹持驱动电机;11、第一转动齿轮;12、第二转动齿轮;13、升降驱动横杆;14、第一锥齿轮;15、第二锥齿轮;16、转动轴;17、螺纹杆;18、升降块;19、卡接限位部;20、第一连接卡块;21、第一连接柱;22、内螺纹连接套;23、第二连接卡块;24、第二连接柱;25、导向柱;30、转动盘;31、连接杆;32、夹持块;33、定位滑柱;34、定位滑套;35、第一隔板;36、第一放置腔;37、第二放置腔;38、第二隔板。Description of reference numerals: 1. Installation base; 2. Counterweight; 3. Connection part housing; 4. Guardrail post; 5. Top plate; 6. Anti-skid plate; 7. Connection block; 8. Drive circuit and power supply 9. Lifting drive motor; 10. Clamping drive motor; 11. First rotating gear; 12. Second rotating gear; 13. Lifting and driving cross bar; 14. First bevel gear; , rotating shaft; 17, threaded rod; 18, lifting block; 19, clamping limit part; 20, first connecting block; 21, first connecting column; 22, internal thread connecting sleeve; 23, second connecting card block; 24, the second connecting column; 25, the guide column; 30, the rotating plate; 31, the connecting rod; 32, the clamping block; 33, the positioning slide column; 34, the positioning slide sleeve; 35, the first partition plate; 36 , the first placement cavity; 37, the second placement cavity; 38, the second partition.
具体实施方式Detailed ways
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be described clearly and completely below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are some, but not all, embodiments of the present invention. The components of the embodiments of the invention generally described and illustrated in the drawings herein may be arranged and designed in a variety of different configurations. Thus, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”等仅用于区分描述,而不能理解为指示或暗示相对重要性。此外,术语“水平”、“竖直”等术语并不表示要求部件绝对水平或悬垂,而是可以稍微倾斜。如“水平”仅仅是指其方向相对“竖直”而言更加水平,并不是表示该结构一定要完全水平,而是可以稍微倾斜。在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。It should be noted that like numerals and letters refer to like items in the following figures, so once an item is defined in one figure, it does not require further definition and explanation in subsequent figures. In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship that the product of the invention is usually placed in use, only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying The device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as limiting the invention. Furthermore, the terms "first", "second", "third", etc. are only used to differentiate the description and should not be construed as indicating or implying relative importance. Furthermore, the terms "horizontal", "vertical" and the like do not imply that a component is required to be absolutely horizontal or overhang, but rather may be slightly inclined. For example, "horizontal" only means that its direction is more horizontal than "vertical", it does not mean that the structure must be completely horizontal, but can be slightly inclined. In the description of the present invention, it should also be noted that, unless otherwise expressly specified and limited, the terms "arranged", "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection, It can also be a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or the internal communication between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood in specific situations.
本发明能够解决多个技术问题:The present invention can solve multiple technical problems:
1、现有防护栏底部防滑措施与上部结构不可拆分,导致各部分结构损坏之后不易更换,不利于进行二次回收利用,更换成本较高;1. The anti-skid measures at the bottom of the existing guardrail cannot be separated from the upper structure, which makes it difficult to replace each part of the structure after damage, which is not conducive to secondary recycling and high replacement costs;
2、现有防护栏的装配方式需要大量人工操作,装配过程复杂;2. The assembly method of the existing guardrail requires a lot of manual operations, and the assembly process is complicated;
3、现有防护栏的装配方式对周边环境有损坏,且拆除后地面留有残留物,有安全隐患;3. The assembly method of the existing guardrail will damage the surrounding environment, and there are residues on the ground after removal, which is a potential safety hazard;
4、现有防护栏只有铁质的薄板,容易收到恶劣天气的影响,具有安全隐患。4. The existing guardrails are only iron sheets, which are easily affected by bad weather and have potential safety hazards.
采用本发明所公开的一种房建施工防护栏具有如下技术效果:Adopting a kind of building construction guardrail disclosed by the present invention has the following technical effects:
1、本发明的房建施工防护栏中,其防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,使得防滑安装块和施工防护栏单体局部损坏后都分别能够单独更换,有助于降低了更换成本,拆卸及更换安装也更加方便,且拆卸安装施工简便无破坏,能够进行二次回收使用;1. In the housing construction guardrail of the present invention, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer by clamping and installation, so that the anti-skid installation block and the construction guardrail monomer can be separately damaged after partial damage. The replacement helps to reduce the replacement cost, and the disassembly, replacement and installation are also more convenient, and the disassembly and installation construction is simple and non-destructive, and can be recycled and used for the second time;
2、本发明的防护栏采用防护栏连接杆有动力装配方式,以及防护栏连接杆之间的螺纹及内螺纹连接套进行连接,此装配方式和连接方式使防护栏单体之间的连接更加稳固,同时,人工只需辅助防护栏单体之间的连接,使防护栏单体之间的连接更加便捷;2. The guardrail of the present invention adopts the power assembly method of the guardrail connecting rod, and the thread and the inner thread connecting sleeve between the guardrail connecting rods are connected. This assembly method and connection method make the connection between the guardrail monomers more convenient. It is stable, and at the same time, it is only necessary to assist the connection between the guardrail units manually, which makes the connection between the guardrail units more convenient;
3、本发明的防护栏无需对周边安装环境进行机械打孔,无需人工紧固大量的螺丝,对周边环境友好无破坏,拆除后无安全隐患;3. The guardrail of the present invention does not require mechanical drilling of the surrounding installation environment, does not need to manually tighten a large number of screws, is friendly to the surrounding environment and does not damage the surrounding environment, and has no potential safety hazards after dismantling;
4、本发明的防护栏底部还可以配备配重,使防护栏能够保持自身稳定,不易受到恶劣天气的影响;4. The bottom of the guardrail of the present invention can also be equipped with a counterweight, so that the guardrail can maintain its own stability and is not easily affected by bad weather;
5、本发明的防护栏自带驱动电路及供电电源,能够给防护栏的附加设施,如降尘喷雾器等提供附加接口,便于防护栏及其附加设施的集成化,适用于多场景。5. The guardrail of the present invention has its own drive circuit and power supply, which can provide additional interfaces for the additional facilities of the guardrail, such as dust suppression sprayers, etc., which facilitates the integration of the guardrail and its additional facilities, and is suitable for multiple scenarios.
基于以上要解决的技术问题,如图1-7所示,本发明的房建施工防护栏,包括用于安装在地面的防滑安装块,以及能够可拆卸的夹持安装在所述防滑安装块上的施工防护栏单体。Based on the above technical problems to be solved, as shown in FIGS. 1-7 , the housing construction protection fence of the present invention includes a non-slip mounting block for installing on the ground, and a detachable clamping installation on the anti-slip mounting block. On the construction guardrail monomer.
防滑安装块包括底面具有防滑结构的防滑板6,防滑板6的上表面固定设置有连接块7,所述连接块7的两个相对侧面上设有夹持孔。The anti-skid installation block includes a skid plate 6 with an anti-skid structure on the bottom surface, a connecting block 7 is fixedly arranged on the upper surface of the anti-skid plate 6, and two opposite sides of the connecting block 7 are provided with clamping holes.
施工防护栏单体包括安装基座1以及设置于安装基座1上的栏杆部;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。The single construction guardrail includes an installation base 1 and a railing part arranged on the installation base 1; the installation base 1 is a hollow structure with an opening at the bottom, and the size of the bottom opening of the installation base 1 is sufficient to allow the connection of the anti-skid installation blocks. The block 7 extends into the hollow space of the installation base 1, and the hollow space of the installation base 1 is installed with a movable clamp that can be clamped or released with the two clamping holes on the connection block 7 of the anti-skid installation block connection mechanism.
当房建施工防护栏上的防滑安装块或者施工防护栏单体受损时,可以将防滑安装块或者施工防护栏单体进行独立更换,增加房建施工防护栏的利用率,延长使用年限;而且防滑安装块与施工防护栏单体之间通过夹持安装形成可拆卸连接,拆卸及更换安装都更加方便。When the non-slip mounting block or the single construction guardrail on the housing construction guardrail is damaged, the non-slip mounting block or the single construction guardrail can be independently replaced to increase the utilization rate of the housing construction guardrail and prolong the service life; In addition, a detachable connection is formed between the anti-skid installation block and the construction guardrail monomer through clamping and installation, and the disassembly and replacement installation are more convenient.
其中,作为优选,活动夹持连接机构包括两个横向排布且相对设置的夹持块32,且两个夹持块32正对于防滑安装块的连接块7伸入至安装基座1的中空空间时两个夹持孔所在位置处,且夹持块32上具有能够伸入夹持孔内的夹持凸起部;还包括用于限制两个夹持块32横向的相互靠近或相互远离移动的横向滑动限位机构,以及用于驱动两个夹持块32移动的夹持块驱动机构。活动夹持连接采用了夹持块横向移动并与连接块插接的方式实现防滑安装块的快速拆装,方便防滑安装块或者施工防护栏单体的更换。Wherein, preferably, the movable clamping connection mechanism includes two laterally arranged and oppositely arranged clamping blocks 32, and the two clamping blocks 32 are facing the connection block 7 of the anti-skid installation block and extend into the hollow of the installation base 1 In space, where the two clamping holes are located, and the clamping
作为优选,夹持块驱动机构包括横向布置于两个夹持块32之间的转动盘30,转动盘30边缘的两个相对位置处可转动的连接在两个连接杆31的一端,两个连接杆31的另一端分别可转动的连接在两个夹持块32上;所述转动盘30通过固定安装在安装基座1的中空空间内的夹持驱动电机10驱动转动。采用上述夹持块驱动机构采用了传动的方式,使夹持块能够进行线性横向运动,使夹持块伸入或伸出夹持孔的过程更加精准和平稳。Preferably, the clamping block driving mechanism includes a
作为优选,横向滑动限位机构包括与夹持块32固定连接且横向布置的定位滑柱33,所述定位滑柱33远离夹持块32的一端可滑动的插入在横向布置的筒状的定位滑套34内,进而通过定位滑柱33在定位滑套34内的横向滑动限制两个夹持块32横向的相互靠近或相互远离移动;所述定位滑套34固定安装在安装基座1的中空空间内。采用上述横向限位机构能够使夹持块横向运动的方向更精准,不容易发生偏离。Preferably, the lateral sliding limit mechanism includes a
作为具体的实施方式而言,本发明的房建施工防护栏可以设计包括多个施工防护栏单体,各个施工防护栏单体之间并排的可拆卸连接,所述施工防护栏单体包括安装基座1、与安装基座1顶面固定连接的栏杆部、与栏杆部侧壁活动连接的防护栏连接杆以及与安装基座1底部活动连接的防滑安装块;所述安装基座1为底部开口的中空结构,安装基座1的底部开口尺寸足够使得防滑安装块的连接块7伸入至安装基座1的中空空间,且安装基座1的中空空间内安装有能够与防滑安装块的连接块7上的两个夹持孔相夹持或松脱的活动夹持连接机构。防滑安装块通过活动夹持连接机构进行安装和拆卸,防滑安装块与活动夹持连接机构连接处开设有夹持孔;所述活动夹持连接机构包括能够横向的相互靠近或相互远离移动的一对夹持块32,夹持块32通过横向滑动限位机构固定连接于安装基座1内壁上;夹持块32能够在横向滑动限位机构的带动下从防滑安装块的夹持孔内外横向移动,实现防滑安装块的安装或拆卸。As a specific embodiment, the building construction guardrail of the present invention can be designed to include a plurality of construction guardrail units, and each construction guardrail unit is detachably connected side by side, and the construction guardrail unit includes installation The base 1, the railing part fixedly connected with the top surface of the installation base 1, the guard rail connecting rod movably connected with the side wall of the railing part, and the anti-skid mounting block movably connected with the bottom of the installation base 1; the installation base 1 is: The hollow structure with the bottom opening, the size of the bottom opening of the mounting base 1 is enough to make the connecting block 7 of the anti-skid mounting block extend into the hollow space of the mounting base 1, and the hollow space of the mounting base 1 is installed with the anti-skid mounting block. A movable clamping connection mechanism in which the two clamping holes on the connecting block 7 are clamped or released. The non-slip mounting block is installed and disassembled through a movable clamping connection mechanism, and a clamping hole is opened at the connection between the non-slip installation block and the movable clamping connection mechanism; For the clamping
作为优选,所述活动夹持连接机构还包括与夹持块32转动连接的连接杆31和能够驱动连接杆31发生横向位移的动力系统;所述动力系统包括驱动电路及供电电源8、夹持驱动电机10和转动盘30,其中驱动电路及供电电源8固定连接于安装基座1内壁上,夹持驱动电机10通过导线与驱动电路及供电电源8电性连接;夹持驱动电机10的输出端与转动盘30固定连接,连接杆31与转动盘30顶面位于圆周同一直径线的两端转动连接,连接杆31与夹持块32的顶端转动连接;夹持驱动电机10固定于支撑架上,支撑架固定安装于安装基座1的内壁上。Preferably, the movable clamping connection mechanism further includes a connecting
作为优选,所述横向滑动限位机构包括定位滑柱33和与定位滑柱33外表面滑动连接的定位滑套34,定位滑套34与安装基座1内壁固定连接,横向滑动限位机构能够对夹持块32的横向移动进行限位支撑,使连接块7与安装基座1的安装或拆卸过程更加平稳。Preferably, the lateral sliding limit mechanism includes a
作为优选,所述防滑安装块包括防滑板6和连接块7,连接块7对应于夹持块32的侧壁上开设有夹持孔,夹持块32能够在连接块7的夹持孔内部横向移动;连接块7的底面固定有防滑板6,且防滑板6的底部均布设置有多个防滑块,能够增加防护栏的防滑功能;所述夹持块32的夹持凸起部可设置于底部,使得夹持块32整体形状为“L”形,其中夹持块32“L”形的竖边垂直于地面,“L”形的横边能够在连接块7的夹持孔内伸入或缩出。防滑安装块的可更换能够避免在防护栏发生损伤时对防护栏进行整体的更换,进而降低使用成本,有利于节约资源。Preferably, the anti-slip mounting block includes an anti-skid plate 6 and a connecting block 7 . The connecting block 7 is provided with a clamping hole on the side wall corresponding to the
作为优选,夹持驱动电机10和连接块7之间设置一固定于安装基座1内壁的第二隔板38,夹持驱动电机10固定连接于第二隔板38表面,即采用第二隔板38作为夹持驱动电机10的支撑架,使夹持驱动电机10运行时更加的平稳。Preferably, a
另外,第二隔板38板面上,对应于夹持块32的滑动范围开设有缺口,夹持块32的“L”形的竖边穿过第二隔板38板面上的缺口,并能够沿第二隔板38长边延伸方向进行横向滑动。随着夹持块32的横向滑动能够实现对连接块7进行夹持或者脱离。In addition, on the surface of the
所述栏杆部包括与安装基座1顶面固定连接的两个连接部壳体3以及与连接部壳体3顶面固定连接的顶板5,连接部壳体3对顶板5起支撑作用。The railing part includes two connecting part shells 3 fixedly connected with the top surface of the installation base 1 and a top plate 5 fixedly connected with the top surface of the connecting part shell 3 , and the connecting part shell 3 supports the top plate 5 .
两个连接部壳体3之间且位于安装基座1的顶面固定有护栏板或均布的护栏柱,护栏板或护栏柱4的顶端与顶板5底面固定连接;连接部壳体3以及护栏板或护栏柱的高度不低于1.1米;所述连接部壳体3为中空柱状结构,且连接部壳体3内部空间与安装基座1的内部空间相连通,两个连接部壳体3沿安装基座1的顶面长边延伸方向的两端轴对称固定连接,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔。Between the two connection part shells 3 and located on the top surface of the installation base 1, a guardrail board or uniformly distributed guardrail post is fixed, and the top of the guardrail board or guardrail post 4 is fixedly connected with the bottom surface of the top board 5; the connection part housing 3 and The height of the guardrail board or guardrail column is not less than 1.1 meters; the connecting part shell 3 is a hollow cylindrical structure, and the inner space of the connecting part shell 3 is connected with the inner space of the installation base 1, and the two connecting part shells are connected with each other. 3. The two ends along the extension direction of the long side of the top surface of the installation base 1 are axially symmetrically connected, and the side of the connecting part housing 3 facing away from the railing part is provided with a connecting block for the connecting rod of the protective railing to extend into. Connect vias.
作为优选,两个连接部壳体3之间固定的为护栏柱4,护栏柱4为圆柱结构,每个护栏柱4之间的间隙小于10cm。Preferably, guardrail posts 4 are fixed between the two connection part shells 3, the guardrail posts 4 are cylindrical structures, and the gap between each guardrail post 4 is less than 10 cm.
作为一种具体实施方式,如图1-3所示,可以设计安装基座1底部外侧面装配有配重块2;配重块2朝向安装基座1外侧面的一侧固定有挂钩,安装基座1底部外侧面上配合挂钩开设有挂孔,通过将挂钩插入挂孔中完成配重与安装基座1的连接。配重块更够增加房建施工防护栏的整体稳定性,使其不容易受到大风或相当外力的影响,而且可以增加底部防滑安装块与地面之间的摩擦力,从而增强房建施工防护栏的防滑作用。As a specific implementation, as shown in Figures 1-3, it can be designed that the bottom outer side of the mounting base 1 is equipped with a counterweight 2; A hanging hole is formed on the outer surface of the bottom of the base 1 with the hook, and the connection between the counterweight and the installation base 1 is completed by inserting the hook into the hanging hole. The counterweight is enough to increase the overall stability of the building construction guardrail, making it less susceptible to strong winds or considerable external forces, and can increase the friction between the bottom anti-skid installation block and the ground, thereby enhancing the building construction guardrail anti-slip effect.
作为本发明方案的进一步的优化设计,为了更好的使得多个施工防护栏单体之间能够相互连接形成房建施工防护栏结构,还可以增加施工防护栏单体之间的连接安装结构。As a further optimized design of the solution of the present invention, in order to better enable multiple construction guardrail units to be connected to each other to form a building construction guardrail structure, the connection and installation structure between the construction guardrail units can also be increased.
具体而言,如图1至图7所示,包括用于连接相邻两个施工防护栏单体的防护栏连接杆,所述防护栏连接杆的两个端头位置处均具有尺寸径向扩展延伸的连接卡块。所述施工防护栏单体的安装基座1上位于栏杆部的两侧位置处还设有防护栏连接部;所述防护栏连接部包括中空的连接部壳体3,所述连接部壳体3背向栏杆部的一侧开设有能够供防护栏连接杆的连接卡块伸入的连接通孔,连接部壳体3的中空空间内安装有能够竖向升降滑动的升降块18,升降块18的顶部具有能够与防护栏连接杆的连接卡块相卡接配合的卡接限位部19;所述卡接限位部19上开设有开口背向栏杆部一侧的方向、且竖向向上贯通至卡接限位部19顶端的卡接槽,所述卡接槽的槽腔空间能够供防护栏连接杆的连接卡块伸入,所述卡接槽的槽口横向宽度能够供防护栏连接杆的杆部通过且小于连接卡块的横向宽度,使得卡接槽的横截面形成“T”型槽;所述槽腔空间是指卡接限位部19顶端的卡接槽内部空间;所述升降块18能够在升降块驱动机构的带动下执行升降运动,且升降块18在位于升降的最低位置处和最高位置处时,卡接限位部19的顶端分别处于低于连接通孔位置处和高于连接通孔位置处。采用上述连接杆以及防护栏连接部的结构能够降低施工防护栏单体之间的安装难度,提高安装效率,同时,通过卡接限位部的结构能够提高施工防护栏单体之间的连接强度,使房建施工防护栏更加的稳固。Specifically, as shown in FIG. 1 to FIG. 7 , it includes a guardrail connecting rod for connecting two adjacent construction guardrail monomers, and the two end positions of the guardrail connecting rod have radial dimensions. Extension extension connection card block. The installation base 1 of the construction guardrail unit is also provided with guardrail connecting parts located on both sides of the railing part; the guardrail connecting part includes a hollow connecting part shell 3, and the connecting part shell 3. The side facing away from the railing portion is provided with a connecting through hole through which the connecting block of the connecting rod of the guardrail can be inserted, and a
作为优选,升降块驱动机构把包括与升降块18螺纹连接的竖向螺杆,以及横向可转动安装在安装基座1的中空空间内的升降驱动横杆13;所述竖向螺杆竖向可转动的安装在防护栏连接部,且向下延伸伸入至安装基座1的中空空间内,且与所述升降驱动横杆13通过锥形齿轮副传动连接;所述升降驱动横杆13通过固定安装在安装基座1的中空空间内的升降驱动电机9驱动转动。这样,能够实现升降块的自动升降,减轻安装人员的安装负担,提高安装效率。Preferably, the lifting block driving mechanism comprises a vertical screw thread connected with the lifting
作为优选,防护栏连接杆包括第一连接组件和第二连接组件;所述第一连接组件包括第一连接柱21和固定设置在第一连接柱21一端的第一连接卡块,第一连接柱21的另一端设有外螺纹;所述第一连接组件包括第二连接柱24和固定设置在第二连接柱24一端的第二连接卡块,第二连接柱24的另一端设有外螺纹;所述第一连接柱21和第二连接柱24的外螺纹端通过内螺纹连接套22进行连接。通过内螺纹连接套实现第一连接柱和第二连接柱之间的连接,方便快捷且连接牢固,有利于提高安装效率,降低安装难度,同时也使房建施工防护栏更加的稳固。Preferably, the guardrail connecting rod includes a first connecting assembly and a second connecting assembly; the first connecting assembly includes a first connecting
作为具体的实施方式而言,一个施工防护栏单体上安装的第一连接组件与另一个施工防护栏单体上安装的第二连接组件通过内螺纹连接套22螺纹连接后,能够将两个施工防护栏单体连接起来。As a specific embodiment, after the first connection component installed on one construction guardrail unit and the second connection component installed on the other construction guardrail unit are threadedly connected by the internal
优选的,如图7所示,还可以在第一连接柱21和第二连接柱24的其中一个连接柱的外螺纹端增设导向柱25,另一个连接柱上设置插接孔;设置导向柱25的目的是在与另一个施工防护栏上的第一连接柱21滑动连接时导向柱插接入插接快内,能够便于防护栏连接杆的定位,增强安装定位准确度。Preferably, as shown in FIG. 7 , a
作为一种具体实施方式,所述升降块驱动机构能够通过电力系统自动升降,所述电力系统包括升降驱动电机9、升降驱动横杆13以及转动轴16;所述电力系统位于安装基座1内部;所述升降驱动电机9固定于安装基座1内壁上,升降驱动电机9与驱动电路及供电电源8通过导线电性连接,升降驱动电机9的输出端固定连接有第一转动齿轮11;所述升降驱动横杆13的中段固定连接有第二转动齿轮12,升降驱动横杆13的两端分别固定连接有第一锥齿轮14,其中,第二转动齿轮12和第一转动齿轮11啮合连接;升降驱动横杆13上转动连接有至少两个支撑板,支撑板与安装基座1的内壁固定连接,能够让升降驱动横杆13转动的更加的稳定;所述升降驱动横杆13两端分别啮合连接有转动轴16,所述转动轴16转动连接有支撑板,支撑板固定于安装基座1内壁上,能够让转动轴16转动稳定;所述转动轴16的一端固定连接有第二锥齿轮15,另一端固定连接有及螺纹杆17;转动轴16通过第二锥齿轮15与升降驱动横杆13两端的第一锥齿轮14啮合连接;螺纹杆17顶端与升降块18螺纹连接。As a specific embodiment, the lifting block driving mechanism can be automatically lifted and lowered by an electric power system, and the electric power system includes a lifting driving motor 9 , a lifting driving
作为优选,在安装基座1内设置第一隔板35,使安装基座1内形成两个独立的腔体,即第一放置腔36和第二放置腔37,升降块驱动机构设置于第一放置腔36内,活动夹持连接机构设置于第二放置腔37内,使各部件之间工作时更加的独立,不会相互影响;其中,第一放置腔36与连接部壳体3的内部相连通,所述升降块驱动机构中升降驱动横杆13上设置的支撑板与第一隔板35的表面固定连接,转动轴16与第一隔板35的表面转动连接。Preferably, a
作为优选,驱动电路及供电电源8固定于第一放置腔36的安装基座1内壁上,用于给予防护栏中的电器提供动力。Preferably, the drive circuit and the power supply 8 are fixed on the inner wall of the installation base 1 of the
本发明所述施工防护栏主体材质为镀锌钢或不锈钢。The main material of the construction guardrail of the present invention is galvanized steel or stainless steel.
本发明所公开的一种房建施工防护栏在搭建时,首先将多个施工防护栏单体吊装至目标位置,并排列整齐,然后安装各个单体的防护栏连接杆。When constructing a building construction guardrail disclosed in the present invention, firstly, a plurality of construction guardrail monomers are hoisted to a target position, and arranged in an orderly manner, and then the guardrail connecting rods of each monomer are installed.
首先将第一连接组件插入连接部壳体3上的连接通孔内,通过升降块驱动机构内的升降驱动电机9带动卡接限位部19的上升,使第一连接组件上的第一连接卡块20位于卡接限位部19上的夹持孔中,具体卡接限位部19的上升过程如下所述:升降驱动电机9带动第一转动齿轮11进行转动,第一转动齿轮11转动带动啮合连接的第二转动齿轮12进行转动,第二转动齿轮12转动带动升降驱动横杆13进行转动,升降驱动横杆13转动的同时带动第一锥齿轮14转动,第一锥齿轮14转动带动啮合连接的第二锥齿轮15转动,第二锥齿轮15转动通过转动轴16带动螺纹杆17转动,螺纹杆17转动带动螺纹连接的升降块18升降,升降块18升降带动卡接限位部19上升。First, insert the first connecting assembly into the connecting through hole on the connecting part housing 3, and drive the latching limit part 19 to rise by the elevating drive motor 9 in the elevating block drive mechanism, so that the first connection on the first connecting assembly is made. The clamping
经过以上过程后,完成第一连接组件的连接,然后进行第二连接组件的连接,其连接过程同第一连接组件的连接,再此不再赘述,在第二连接组件连接完成后,将连接组件上的导向柱25与另一个防护栏上的连接组件上的插接孔对齐并插接,然后转动并拧紧内螺纹连接套22,使第二连接柱24和第一连接柱21连接牢固,进而使防护栏单体之间连接更加稳固。After the above process, the connection of the first connection component is completed, and then the connection of the second connection component is performed, and the connection process is connected with the first connection component, and will not be repeated here. The guide post 25 on the assembly is aligned with the insertion hole on the connection assembly on the other guardrail and inserted, and then the inner
当需要对防滑安装块进行更换时,通过夹持驱动电机10带动转动盘30进行转动,转动盘30转动带动转动连接的连接杆31进行转动,进而带动夹持块32分别横向的相互远离移动,从而使夹持块32脱离连接块7,完成连接块7的拆卸。再将安装基座1抬起,换入新的防滑安装块,并执行防滑安装块的安装操作步骤,即夹持块32伸入连接块7的夹持孔中,从而完成对防滑板6进行更换。When the anti-skid mounting block needs to be replaced, the
可以理解,本发明是通过一些实施例进行描述的,本领域技术人员知悉的,在不脱离本发明的精神和范围的情况下,可以对这些特征和实施例进行各种改变或等效替换。另外,在本发明的教导下,可以对这些特征和实施例进行修改以适应具体的情况及材料而不会脱离本发明的精神和范围。因此,本发明不受此处所公开的具体实施例的限制,所有落入本申请的权利要求范围内的实施例都属于本发明所保护的范围内。It can be understood that the present invention is described by some embodiments, and those skilled in the art know that various changes or equivalent substitutions can be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, in the teachings of this invention, these features and embodiments may be modified to adapt a particular situation and material without departing from the spirit and scope of the invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application fall within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210607314.2A CN114753713B (en) | 2022-05-31 | 2022-05-31 | Construction rail guard is built in room |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210607314.2A CN114753713B (en) | 2022-05-31 | 2022-05-31 | Construction rail guard is built in room |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114753713A true CN114753713A (en) | 2022-07-15 |
CN114753713B CN114753713B (en) | 2023-07-18 |
Family
ID=82337236
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210607314.2A Active CN114753713B (en) | 2022-05-31 | 2022-05-31 | Construction rail guard is built in room |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114753713B (en) |
Citations (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002357023A (en) * | 2001-05-30 | 2002-12-13 | Toyo Exterior Co Ltd | Device for erecting and fixing post of installation on ground |
US6648304B1 (en) * | 2002-03-01 | 2003-11-18 | Xcel Distribution, Inc. | Modular fence |
KR101576938B1 (en) * | 2014-07-01 | 2015-12-15 | 권상우 | The pivotable balustrade |
US20170037653A1 (en) * | 2014-04-13 | 2017-02-09 | Manfred Schopf | Clamps for panel-type fences |
JP2017040147A (en) * | 2015-08-21 | 2017-02-23 | 株式会社Lixil | Fence fitting structure |
US20190112817A1 (en) * | 2015-10-09 | 2019-04-18 | Aluminco A.E. | Glass windbreaker |
CN209011701U (en) * | 2018-10-26 | 2019-06-21 | 沈阳工学院 | A kind of water conservancy construction safety guard |
CN209976161U (en) * | 2019-03-20 | 2020-01-21 | 河北建设集团股份有限公司 | Rail guard for construction |
CN211923774U (en) * | 2020-03-17 | 2020-11-13 | 王波 | Municipal construction fast-assembling protector |
CN211974612U (en) * | 2020-03-18 | 2020-11-20 | 重庆胤通建设开发有限公司 | Safety protective guard is used in electric power engineering construction |
CN212176804U (en) * | 2020-04-10 | 2020-12-18 | 江苏诤友交通科技有限公司 | Rail guard convenient to installation and dismantlement |
CN212958036U (en) * | 2020-06-23 | 2021-04-13 | 浙江国建建设有限公司 | Security protection device for construction |
CN113047199A (en) * | 2021-02-04 | 2021-06-29 | 天长市锦瑞防护设施有限公司 | Rail guard for building with flexible function |
CN213806695U (en) * | 2020-10-26 | 2021-07-27 | 钟家颖 | Town road foundation ditch safety protection subassembly |
CN213898441U (en) * | 2020-11-05 | 2021-08-06 | 山东美汉林建设集团有限公司 | Liftable bounding wall for building engineering |
CN214740404U (en) * | 2021-03-18 | 2021-11-16 | 重庆第二师范学院 | Rail guard is used in kindergarten |
CN215056069U (en) * | 2021-03-29 | 2021-12-07 | 江苏省华建建设股份有限公司 | High building protector for construction that stability is good |
CN215485138U (en) * | 2021-06-03 | 2022-01-11 | 佛山市富贵龙门业有限公司 | Assembled railing |
CN216380523U (en) * | 2021-06-03 | 2022-04-26 | 马东旭 | Movable building construction platform convenient to fix |
CN216617122U (en) * | 2021-12-08 | 2022-05-27 | 广州市川拓瑞工程设备有限公司 | Rail guard is used in civil engineering construction |
-
2022
- 2022-05-31 CN CN202210607314.2A patent/CN114753713B/en active Active
Patent Citations (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002357023A (en) * | 2001-05-30 | 2002-12-13 | Toyo Exterior Co Ltd | Device for erecting and fixing post of installation on ground |
US6648304B1 (en) * | 2002-03-01 | 2003-11-18 | Xcel Distribution, Inc. | Modular fence |
US20170037653A1 (en) * | 2014-04-13 | 2017-02-09 | Manfred Schopf | Clamps for panel-type fences |
KR101576938B1 (en) * | 2014-07-01 | 2015-12-15 | 권상우 | The pivotable balustrade |
JP2017040147A (en) * | 2015-08-21 | 2017-02-23 | 株式会社Lixil | Fence fitting structure |
US20190112817A1 (en) * | 2015-10-09 | 2019-04-18 | Aluminco A.E. | Glass windbreaker |
CN209011701U (en) * | 2018-10-26 | 2019-06-21 | 沈阳工学院 | A kind of water conservancy construction safety guard |
CN209976161U (en) * | 2019-03-20 | 2020-01-21 | 河北建设集团股份有限公司 | Rail guard for construction |
CN211923774U (en) * | 2020-03-17 | 2020-11-13 | 王波 | Municipal construction fast-assembling protector |
CN211974612U (en) * | 2020-03-18 | 2020-11-20 | 重庆胤通建设开发有限公司 | Safety protective guard is used in electric power engineering construction |
CN212176804U (en) * | 2020-04-10 | 2020-12-18 | 江苏诤友交通科技有限公司 | Rail guard convenient to installation and dismantlement |
CN212958036U (en) * | 2020-06-23 | 2021-04-13 | 浙江国建建设有限公司 | Security protection device for construction |
CN213806695U (en) * | 2020-10-26 | 2021-07-27 | 钟家颖 | Town road foundation ditch safety protection subassembly |
CN213898441U (en) * | 2020-11-05 | 2021-08-06 | 山东美汉林建设集团有限公司 | Liftable bounding wall for building engineering |
CN113047199A (en) * | 2021-02-04 | 2021-06-29 | 天长市锦瑞防护设施有限公司 | Rail guard for building with flexible function |
CN214740404U (en) * | 2021-03-18 | 2021-11-16 | 重庆第二师范学院 | Rail guard is used in kindergarten |
CN215056069U (en) * | 2021-03-29 | 2021-12-07 | 江苏省华建建设股份有限公司 | High building protector for construction that stability is good |
CN215485138U (en) * | 2021-06-03 | 2022-01-11 | 佛山市富贵龙门业有限公司 | Assembled railing |
CN216380523U (en) * | 2021-06-03 | 2022-04-26 | 马东旭 | Movable building construction platform convenient to fix |
CN216617122U (en) * | 2021-12-08 | 2022-05-27 | 广州市川拓瑞工程设备有限公司 | Rail guard is used in civil engineering construction |
Non-Patent Citations (2)
Title |
---|
王波;: "超高落地外架的设计与施工", 安徽建筑, no. 03, pages 65 - 66 * |
王羽;张昶;舒宗瑛;: "桩周岩土稳定性评价中无损探测技术的应用", 中外公路, no. 02, pages 25 - 28 * |
Also Published As
Publication number | Publication date |
---|---|
CN114753713B (en) | 2023-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105565221A (en) | Lifting device for maintaining wiring terminals on power distribution station outdoor wall | |
KR100945561B1 (en) | Method and apparatus for constructing pole of tower-type facilities | |
CN114753713A (en) | Building construction rail guard | |
CN204139631U (en) | Quick-release protective railings for construction sites | |
CN110905206A (en) | Overhanging discharging platform with drawing type channel and construction method | |
CN210867008U (en) | Adjustable traction pulley for incoming cable of residential meter box | |
CN211447919U (en) | Power box protection shed convenient to mount and dismount | |
CN217420434U (en) | Assembled suspension platform for electric hanging basket | |
CN210483251U (en) | Municipal works are with construction warning baffle | |
CN221741579U (en) | Fixing device for building steel structure support column | |
CN203345999U (en) | Special multifunctional lifting frame for busbar bridge | |
CN114229740A (en) | Machine of lifting is used in installation of building interior decoration furred ceiling board | |
CN216476706U (en) | Building rail is used in municipal administration convenient to dismantle | |
CN113668871B (en) | Prefabricated reinforced concrete structural beam for assembled house building | |
CN114575655B (en) | Power supply line support frame | |
CN220979087U (en) | Building construction management encloses fender fixing device | |
CN112523491A (en) | Assembled steel construction building joins externally template | |
CN216588056U (en) | Highway engineering is with making an uproar protection rail that falls | |
CN112279174A (en) | Firm underground pipeline is well lid opening device for measurement | |
CN110697596A (en) | Material lifting device for building engineering | |
CN221399908U (en) | Positioning die for construction of embedded anchor bolts | |
CN217439682U (en) | Simple guardrail upright post fixing device capable of being repeatedly used in turnover mode | |
CN219622434U (en) | Construction security protection device | |
CN215562776U (en) | An easy-to-build tower crane base structure with anti-fall | |
CN215484755U (en) | Liftable support for construction engineering construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20220715 Assignee: Chongqing Lingshi Engineering Technology Co.,Ltd. Assignor: CHONGQING University OF EDUCATION Contract record no.: X2024980035462 Denomination of invention: A building construction protective fence Granted publication date: 20230718 License type: Common License Record date: 20241210 |
|
EE01 | Entry into force of recordation of patent licensing contract |