CN114673502A - A multi-mode disaster chain management method based on floor rock roadway - Google Patents
A multi-mode disaster chain management method based on floor rock roadway Download PDFInfo
- Publication number
- CN114673502A CN114673502A CN202210496959.3A CN202210496959A CN114673502A CN 114673502 A CN114673502 A CN 114673502A CN 202210496959 A CN202210496959 A CN 202210496959A CN 114673502 A CN114673502 A CN 114673502A
- Authority
- CN
- China
- Prior art keywords
- coal
- roadway
- coal seam
- layer
- grouting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011435 rock Substances 0.000 title claims abstract description 74
- 238000007726 management method Methods 0.000 title claims description 11
- 239000003245 coal Substances 0.000 claims abstract description 215
- 238000005553 drilling Methods 0.000 claims abstract description 62
- 238000009412 basement excavation Methods 0.000 claims abstract description 46
- 238000000034 method Methods 0.000 claims abstract description 29
- 238000005065 mining Methods 0.000 claims description 30
- 238000004080 punching Methods 0.000 claims description 17
- 238000005728 strengthening Methods 0.000 claims description 16
- 238000010276 construction Methods 0.000 claims description 14
- 239000000463 material Substances 0.000 claims description 13
- 230000015572 biosynthetic process Effects 0.000 claims description 9
- 238000013461 design Methods 0.000 claims description 6
- 238000007789 sealing Methods 0.000 claims description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 5
- 239000004568 cement Substances 0.000 claims description 3
- 239000011083 cement mortar Substances 0.000 claims description 3
- 239000000701 coagulant Substances 0.000 claims description 3
- 230000002301 combined effect Effects 0.000 claims description 3
- 238000000605 extraction Methods 0.000 abstract description 17
- 230000002787 reinforcement Effects 0.000 abstract description 7
- 238000012423 maintenance Methods 0.000 abstract description 2
- 230000035699 permeability Effects 0.000 abstract description 2
- 230000005641 tunneling Effects 0.000 abstract 2
- 230000002159 abnormal effect Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 37
- 238000010586 diagram Methods 0.000 description 4
- 239000011241 protective layer Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000002485 combustion reaction Methods 0.000 description 2
- 230000009977 dual effect Effects 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 230000002269 spontaneous effect Effects 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 230000001550 time effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C37/00—Other methods or devices for dislodging with or without loading
- E21C37/06—Other methods or devices for dislodging with or without loading by making use of hydraulic or pneumatic pressure in a borehole
- E21C37/12—Other methods or devices for dislodging with or without loading by making use of hydraulic or pneumatic pressure in a borehole by injecting into the borehole a liquid, either initially at high pressure or subsequently subjected to high pressure, e.g. by pulses, by explosive cartridges acting on the liquid
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
- E21D20/021—Grouting with inorganic components, e.g. cement
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F7/00—Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Chemical & Material Sciences (AREA)
- Inorganic Chemistry (AREA)
- Structural Engineering (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种基于底板岩巷的多模灾害链式治理方法,主要适用于高瓦斯低渗透煤层瓦斯全时空抽采及煤矸石高效处置等实际工程。The invention relates to a multi-mode disaster chain management method based on floor rock roadway, which is mainly suitable for practical projects such as high-gas and low-permeability coal seam gas full-time drainage and coal gangue efficient disposal.
背景技术Background technique
高集约化机械开采模式使得煤矿开采逐步向深部延伸,较高的地应力使得煤层孔隙率和渗透率大幅降低,瓦斯含量和瓦斯压力剧增。为保障煤层安全顺利开采,通常采用系列煤层卸压技术、瓦斯抽采方法对预开采煤层进行强化卸压抽采,比如水力压裂、水力冲孔、保护层开采、顺层瓦斯抽采、穿层瓦斯抽采等。存在保护层开采条件的煤层可优先采用保护层开采方法,而无保护层开采条件的多借助底板岩巷和穿层钻孔来治理瓦斯灾害。同时,不同工作面采掘过程中生产的大量煤矸石通常会将其从矿井中提升至地面进行堆放,从而确保地下空间的可操作性。The highly intensive mechanical mining mode makes the coal mining gradually extend to the deep. In order to ensure the safe and smooth mining of coal seams, a series of coal seam pressure relief technologies and gas drainage methods are usually used to strengthen pressure relief and drainage of pre-mined coal seams, such as hydraulic fracturing, hydraulic punching, protective layer mining, bedding gas drainage, and piercing. Layer gas extraction, etc. Coal seams with protective layer mining conditions can preferentially use protective layer mining methods, while those without protective layer mining conditions mostly rely on floor rock roadways and through-layer drilling to control gas disasters. At the same time, a large amount of coal gangue produced in the mining process of different working faces is usually lifted from the mine to the ground for stacking, so as to ensure the operability of the underground space.
现有底板岩巷通常是作为煤层采掘前瓦斯灾害防治的主要场所,主要涉及穿层钻孔瓦斯抽采和水力化卸压增透措施的实施。穿层钻孔的实施能够在一定程度上实现煤层卸压和瓦斯抽采的目的,但在实际生产过程中常存在一些应用限制:1.现有底板岩巷的利用效率较低,大多数底板岩巷的设置多针对于瓦斯灾害方式和瓦斯高效抽采;2.水力冲孔卸压手段能够对煤层结构进行有效卸压,但在后期煤巷掘进过程中的煤巷结构稳定性多产生不利影响;3.对于一些内含复杂地质结构的煤层而言,单一的穿层钻孔瓦斯采前预抽不能够很好地实现煤层瓦斯抽采达标,极大地影响工作面回采的接续效率;4.上覆煤层开采完毕后,目前都是将其底板岩巷封闭,封闭后较大的巷道空间易引起地层结构破坏和地表沉陷。同时,地面堆放的煤矸石一方面会污染地面环境,同时夹杂的易自燃煤块会引发燃烧事故的发生,严重威胁矿井地面生产安全。因此,亟需提出一种新的方法,通过考虑底板岩巷的不同时效性,根据底板岩巷所处的不同阶段分别采用特定手段,从而在保证底板岩巷支护稳定性的前提下,实现提高瓦斯抽采和煤矸石有效处置的双重效果,是本行业的研究方向之一。The existing floor rock roadway is usually used as the main place for gas disaster prevention and control before coal seam mining, mainly involving the implementation of through-bed drilling gas drainage and hydraulic pressure relief and permeability enhancement measures. The implementation of through-layer drilling can achieve the purpose of coal seam pressure relief and gas drainage to a certain extent, but there are often some application limitations in the actual production process: 1. The utilization efficiency of the existing floor rock roadway is low, and most floor rocks The setting of the roadway is mostly aimed at the gas disaster mode and the efficient gas drainage; 2. The hydraulic punching pressure relief method can effectively relieve the pressure of the coal seam structure, but the stability of the coal roadway structure in the later coal roadway excavation process is often adversely affected. 3. For some coal seams with complex geological structures, the gas pre-drainage of a single drilling hole before gas mining cannot well achieve the coal seam gas drainage standard, which greatly affects the continuous efficiency of mining face mining; 4. After the mining of the overlying coal seam is completed, the floor rock roadway is currently closed, and the large roadway space after sealing is easy to cause damage to the stratum structure and surface subsidence. At the same time, the coal gangue stacked on the ground will pollute the ground environment on the one hand, and at the same time, the inclusion of spontaneous combustion coal blocks will cause combustion accidents, which seriously threatens the safety of mine ground production. Therefore, it is urgent to propose a new method. By considering the different timeliness of the floor rock roadway, specific methods are adopted according to the different stages of the floor rock roadway, so as to ensure the support stability of the floor rock roadway. Improving the dual effect of gas extraction and effective disposal of coal gangue is one of the research directions of this industry.
发明内容SUMMARY OF THE INVENTION
针对上述现有技术存在的问题,本发明提供一种基于底板岩巷的多模灾害链式治理方法,通过考虑底板岩巷的不同时效性,根据底板岩巷所处的不同阶段分别采用特定手段,从而在保证底板岩巷支护稳定性的前提下,实现提高瓦斯抽采和煤矸石有效处置的双重效果。In view of the problems existing in the above-mentioned prior art, the present invention provides a multi-mode disaster chain management method based on the floor rock roadway. Therefore, on the premise of ensuring the support stability of the floor rock roadway, the dual effects of improving gas drainage and effective disposal of coal gangue can be achieved.
为了实现上述目的,本发明采用的技术方案是:一种基于底板岩巷的多模灾害链式治理方法,具体步骤为:In order to achieve the above purpose, the technical solution adopted in the present invention is: a multi-mode disaster chain management method based on floor rock roadway, the specific steps are:
A、先根据煤层情况确定预掘进煤巷在煤层内的起始位置及掘进设计路径,完成后在煤巷掘进之前在煤层下方的底板岩层内施工底板岩巷,接着从底板岩巷的顶板向同一煤层断面钻取多个穿层钻孔,且多个穿层钻孔在同一煤层断面内的部分均匀分布在预掘进煤巷起始位置的两侧,各个穿层钻孔均穿过目标煤层进入顶板岩层内;A. First determine the starting position of the pre-excavated coal roadway in the coal seam and the design path of the excavation according to the coal seam conditions. After the completion of the coal roadway excavation, the floor rock roadway is constructed in the floor rock layer under the coal seam, and then from the top plate of the floor rock roadway to the floor rock roadway. Multiple through-layer holes are drilled from the same coal seam section, and the parts of the multiple through-layer holes in the same coal seam section are evenly distributed on both sides of the starting position of the pre-drilling coal roadway, and each through-layer hole passes through the target coal seam into the roof rock formation;
B、在底板岩巷内布置水力冲孔设备,通过水力冲孔设备依次向各个穿层钻孔内注入高压水,冲孔压力为10~15MPa,由于高压水冲蚀作用将穿层钻孔周围的煤体冲出,每个穿层钻孔的冲孔完成标准,以各个穿层钻孔的出煤量确定,待各个穿层钻孔的水力冲孔完毕后,在预掘进煤巷两侧的煤层内各形成一个卸压区域,接着对各个穿层钻孔进行封孔,并将各个穿层钻孔通过管路连接至瓦斯抽采管路中进行瓦斯抽采,便于后续煤巷在煤层内的掘进;B. Arrange hydraulic punching equipment in the floor rock roadway, and inject high-pressure water into each through-layer drilling hole in turn through the hydraulic punching equipment, and the punching pressure is 10-15MPa. The coal body is punched out. The punching completion standard of each through-layer drilling hole is determined by the coal output of each through-layer drilling hole. A pressure relief area is formed in each of the coal seams, and then each through-layer borehole is sealed, and each through-layer borehole is connected to the gas drainage pipeline through pipelines for gas drainage, which is convenient for subsequent coal roadways in the coal seam. excavation inside;
C、按照步骤A确定的煤巷位置及掘进设计路径,开始进行煤巷掘进,在煤巷掘进过程中,根据底板岩巷走向,每隔设定距离从底板岩巷的顶板向当前所处煤层断面钻取多个穿层钻孔,并重复步骤B的处理过程,完成掘进中煤巷两侧的卸压区域布设;同时在每次钻设多个穿层钻孔后,从底板岩巷向当前所处煤层断面施工多个注浆钻孔,各个注浆钻孔处于掘进中煤巷的周围,采用注浆设备将注浆材料注入各个注浆钻孔内,待注浆材料凝固后,在当前所处煤层断面的煤巷周围形成强化区域,强化区域相对于卸压区域距离煤巷更近;接着从煤巷内向周围煤层打设多个锚杆进行支护,从而通过每隔设定距离形成强化区域及锚杆支护联合作用,从而保证煤巷掘进期间的整体稳固性,直至完成整个煤巷掘进工作;C. According to the position of the coal roadway and the design path of the roadway determined in step A, start the coal roadway excavation. During the coal roadway excavation process, according to the direction of the floor rock roadway, every set distance is from the roof of the floor rock roadway to the current coal seam Drill a plurality of through-layer boreholes at the cross-section, and repeat the process of step B to complete the layout of the pressure relief areas on both sides of the coal roadway in the excavation; Several grouting holes are constructed in the current coal seam section, and each grouting hole is located around the coal roadway in the process of excavation. The grouting equipment is used to inject the grouting material into each grouting hole. After the grouting material is solidified, the A strengthening area is formed around the coal roadway of the current coal seam section, and the strengthening area is closer to the coal roadway than the pressure relief area; then multiple bolts are set from the coal roadway to the surrounding coal seam for support, so as to pass the set distance The combined effect of strengthening area and bolt support is formed, so as to ensure the overall stability of the coal roadway during the excavation period, until the entire coal roadway excavation work is completed;
D、完成煤巷掘进工作后,开始进行煤层工作面回采,在回采期间从底板岩巷向煤层工作面前方30m的煤体施工多个定向钻孔,各个定向钻孔均穿过煤层进入顶板岩层,然后将各个定向钻孔采用步骤B的方式处理后进行二次瓦斯强化抽采,从而保证煤层工作面回采过程中的安全稳定;D. After the excavation work of the coal roadway is completed, the mining of the coal seam working face starts. During the mining period, multiple directional drilling holes are constructed from the floor rock roadway to the coal body 30m in front of the coal seam working face, and each directional drilling hole passes through the coal seam and enters the roof rock layer. , and then each directional borehole is processed by the method of step B and then the secondary gas enhanced drainage is carried out, so as to ensure the safety and stability of the coal seam working face mining process;
E、当前煤层工作面回采完毕后,重复步骤A至D在同一煤层与当前煤巷间隔一定距离后,再确定新的煤巷及底板岩巷,并将新的煤巷及底板岩巷掘进时产生的煤矸石运输至当前底板岩巷内进行湿式密封充填,同时新的煤巷掘进时能利用当前形成的卸压区域,从而在保证煤巷掘进及后续使用安全稳定前提下,提高煤巷掘进效率。E. After the mining of the current coal seam working face is completed, repeat steps A to D after the same coal seam and the current coal roadway are separated by a certain distance, and then determine the new coal roadway and floor rock roadway, and excavate the new coal roadway and floor rock roadway. The generated coal gangue is transported to the current floor rock roadway for wet sealing filling. At the same time, the currently formed pressure relief area can be used when the new coal roadway is excavated, so as to ensure the safety and stability of the coal roadway excavation and subsequent use, and improve the coal roadway excavation. efficiency.
进一步,所述步骤B中的出煤量以穿层钻孔处于煤层内的长度乘以每米出煤量获得,其中每米出煤量为1.5t/m~3t/m。通过这个判断标准能使不同穿层钻孔具有各自的冲孔结束标准,从而在实现卸压作用的前提下,有效提高施工效率。Further, the coal output in the step B is obtained by multiplying the length of the drilled hole in the coal seam by the coal output per meter, wherein the coal output per meter is 1.5t/m~3t/m. Through this judgment standard, different perforation holes can have their own punching end standards, so as to effectively improve the construction efficiency under the premise of realizing the pressure relief effect.
进一步,所述强化区域的形成范围为距离煤巷15~20m;卸压区域的形成范围为距离煤巷120~150m。采用这个设定范围,能在保证煤巷掘进及后期工作面回采过程中,强化区域及卸压区域各自所起的作用前提下,有效减少各种钻孔的施工数量提高施工效率。Further, the formation range of the strengthening area is 15-20m from the coal roadway; the formation range of the pressure relief area is 120-150m from the coal roadway. Using this setting range can effectively reduce the construction quantity of various drilling holes and improve the construction efficiency under the premise of ensuring the respective roles of the strengthening area and the pressure relief area in the process of coal roadway excavation and later working face mining.
进一步,所述穿层钻孔、注浆钻孔和定向钻孔的终孔位置均进入顶板岩层至少1m。这样能保证各个钻孔的钻设后的稳定性。Further, the final hole positions of the through-layer drilling, grouting drilling and directional drilling all enter the roof rock layer by at least 1 m. In this way, the stability after drilling of each borehole can be ensured.
进一步,在同一煤层断面上各个穿层钻孔沿煤层倾向呈扇形分布,处于煤巷每一侧的各个穿层钻孔相邻之间的夹角为30°;各个穿层钻孔的直径为80~100mm;所述注浆钻孔的直径为50~80mm,定向钻孔的直径为50~80mm。Further, on the cross section of the same coal seam, each through-layer borehole is distributed in a fan shape along the coal seam inclination, and the included angle between the adjacent through-layer boreholes on each side of the coal roadway is 30°; the diameter of each through-layer borehole is 80~ 100mm; the diameter of the grouting hole is 50-80mm, and the diameter of the directional drilling is 50-80mm.
进一步,所述定向钻孔的施工形式采用高位钻孔和顺层钻孔联合施工。这种方式能更好的提高瓦斯抽采效果。Further, the construction form of the directional drilling adopts the combined construction of high-level drilling and layer-wise drilling. This method can better improve the gas extraction effect.
进一步,所述注浆材料采用掺有快速凝结剂的水泥砂浆,水灰比为1:3,且注浆设备采用气动式注浆泵进行注浆,注浆时间控制在30~40min。采用该种注浆材料使得强化区域的加固强度更好。Further, the grouting material adopts cement mortar mixed with a rapid coagulant, the water-cement ratio is 1:3, and the grouting equipment adopts a pneumatic grouting pump for grouting, and the grouting time is controlled within 30-40 minutes. The use of this grouting material makes the reinforcement strength of the reinforced area better.
与现有技术相比,本发明考虑底板岩巷不同时间效应下的瓦斯综合治理、煤巷快速掘进与稳固、以及煤矸石就地充填三个工程集成化,在时间尺度上综合考虑煤巷采掘与瓦斯抽采的连续性,在空间尺度上提升煤层开采、瓦斯治理和矸石充填三位一体的实施效率,在提高底板岩巷利用效率基础之上,最大程度地提高预开采煤层的瓦斯灾害防治、其他接续工作面煤矸石的原位处置效率。首先,在煤巷掘进之前及掘进过程中,利用穿层钻孔和注浆钻孔对目标煤层依次进行卸压增透和注浆加固,从而在煤巷周围形成强化区域和卸压区域相结合的方式,其中强化区域更靠近煤巷,卸压区域处于强化区域的两侧,这样形成的“强化—松弛”结构一方面可提高瓦斯抽采效率,另一方面可保证煤巷安全采掘进度和后期稳定性维护;其次,在工作面回采时利用定向钻孔可实现目标煤层内异常赋存瓦斯的二次抽采,联合煤层常规瓦斯抽采方法,实现煤层瓦斯的全覆盖抽采;最后,在完成当前煤巷的工作面回采后,能将其他接续工作面进行新的煤巷及底板岩巷掘进时生产的煤矸石充填至当前废弃的底板岩巷中,可同时实现节约矸石提升成本、保护地表生态环境和预防地表塌陷等多重目的;并且新的煤巷掘进时能部分利用当前形成的卸压区域,从而在保证煤巷掘进及后续使用安全稳定前提下,减少施工流程,提高煤巷掘进效率。Compared with the prior art, the present invention considers the three engineering integration of gas comprehensive control, rapid excavation and stabilization of coal roadway, and on-site filling of coal gangue under different time effects of floor rock roadway, and comprehensively considers coal roadway excavation on the time scale. Continuity with gas extraction, improve the implementation efficiency of coal seam mining, gas control and gangue filling on the spatial scale, and maximize the gas disaster prevention and other In-situ disposal efficiency of coal gangue in the continuous working face. First of all, before and during the excavation of the coal roadway, the target coal seam is subjected to pressure relief and penetration enhancement and grouting reinforcement in turn by using through-bed drilling and grouting drilling, so as to form a combination of strengthening area and pressure relief area around the coal roadway. In this way, the strengthening area is closer to the coal roadway, and the pressure relief area is on both sides of the strengthening area. The "strengthening-relaxation" structure formed in this way can improve the gas extraction efficiency on the one hand, and ensure the safe mining progress and safety of the coal roadway on the other hand. Stability maintenance in the later stage; secondly, directional drilling can be used to realize the secondary extraction of abnormally occurring gas in the target coal seam during the mining of the working face, and combined with the conventional gas extraction method of the coal seam, the full coverage of coal seam gas extraction can be realized; finally, After completing the mining of the working face of the current coal roadway, the coal gangue produced during the excavation of the new coal roadway and the floor rock roadway in other continuous working faces can be filled into the currently abandoned floor rock roadway, which can simultaneously save the cost of gangue and increase the cost of gangue. It has multiple purposes such as protecting the surface ecological environment and preventing surface subsidence; and the newly formed pressure relief area can be partially used during the excavation of the new coal roadway, so as to reduce the construction process and improve the coal roadway under the premise of ensuring the safety and stability of the coal roadway excavation and subsequent use. excavation efficiency.
附图说明Description of drawings
图1是本发明中一个煤巷及底板岩巷的治理施工示意图;Fig. 1 is the governance construction schematic diagram of a coal roadway and floor rock roadway in the present invention;
图2是图1中煤巷掘进过程中锚杆加固断面示意图;Fig. 2 is a schematic diagram of a cross-sectional view of bolt reinforcement in the coal roadway excavation process in Fig. 1;
图3是图1中定向钻孔空间布置剖面示意图;Fig. 3 is the sectional schematic diagram of the spatial arrangement of directional drilling in Fig. 1;
图4是本发明多个煤巷及底板岩巷的治理施工示意图。FIG. 4 is a schematic diagram of the governance construction of a plurality of coal roadways and floor rock roadways of the present invention.
图中:1-煤层;2-底板岩巷;3-顶板岩层;4-注浆钻孔;5-穿层钻孔;6-煤巷;7-锚杆;8-定向钻孔;I-强化区域;II-卸压区域;III-原位区域。In the figure: 1-coal seam; 2-floor rock road; 3-roof rock layer; 4-grouting drilling; 5-through drilling; 6-coal roadway; 7-anchor; 8-directional drilling; Reinforced area; II - pressure relief area; III - in situ area.
具体实施方式Detailed ways
下面将对本发明作进一步说明。The present invention will be further described below.
如图1所示,本发明的具体步骤为:As shown in Figure 1, the concrete steps of the present invention are:
A、先根据煤层1情况确定预掘进煤巷6在煤层1内的起始位置及掘进设计路径,完成后在煤巷6掘进之前在煤层1下方的底板岩层内施工底板岩巷2,接着从底板岩巷2的顶板向同一煤层断面钻取多个穿层钻孔5,且多个穿层钻孔5在同一煤层断面内的部分均匀分布在预掘进煤巷6起始位置的两侧,各个穿层钻孔5均穿过目标煤层1进入顶板岩层3内;在同一煤层断面上各个穿层钻孔5沿煤层倾向呈扇形分布,处于煤巷6每一侧的各个穿层钻孔5相邻之间的夹角为30°;各个穿层钻孔5的直径为80~100mm;A. First determine the starting position and the design path of the
B、在底板岩巷2内布置水力冲孔设备,通过水力冲孔设备依次向各个穿层钻孔5内注入高压水,冲孔压力为10~15MPa,由于高压水冲蚀作用将穿层钻孔5周围的煤体冲出,每个穿层钻孔5的冲孔完成标准,以各个穿层钻孔5的出煤量确定,其中出煤量以穿层钻孔5处于煤层1内的长度乘以每米出煤量获得,其中每米出煤量为1.5t/m~3t/m。通过这个判断标准能使不同穿层钻孔5具有各自的冲孔结束标准,从而在实现卸压作用的前提下,有效提高施工效率;待各个穿层钻孔5的水力冲孔完毕后,在预掘进煤巷6两侧的煤层1内各形成一个卸压区域II,接着对各个穿层钻孔5进行封孔,并将各个穿层钻孔5通过管路连接至瓦斯抽采管路中进行瓦斯抽采,便于后续煤巷6在煤层1内的掘进;B. Arrange hydraulic punching equipment in the
C、按照步骤A确定的煤巷6位置及掘进设计路径,开始进行煤巷6掘进,在煤巷6掘进过程中,根据底板岩巷2走向,每隔设定距离从底板岩巷2的顶板向当前所处煤层断面钻取多个穿层钻孔5,并重复步骤B的处理过程,完成掘进中煤巷6两侧的卸压区域II布设;同时在每次钻设多个穿层钻孔5后,从底板岩巷2向当前所处煤层断面施工多个注浆钻孔4,所述注浆钻孔4的直径为50~80mm,各个注浆钻孔4处于掘进中煤巷6的周围,采用注浆设备将注浆材料注入各个注浆钻孔4内,待注浆材料凝固后,在当前所处煤层断面的煤巷6周围形成强化区域I,强化区域I相对于卸压区域II距离煤巷6更近;如图2所示,接着从煤巷6内向周围煤层1打设多个锚杆7进行支护,从而通过每隔设定距离形成强化区域I及锚杆7支护联合作用,从而保证煤巷6掘进期间的整体稳固性,直至完成整个煤巷6掘进工作;其中强化区域I的形成范围为距离煤巷15~20m;卸压区域II的形成范围为距离煤巷120~150m。采用这个设定范围,能在保证煤巷6掘进及后期工作面回采过程中,强化区域I及卸压区域II各自所起的作用前提下,有效减少各种钻孔的施工数量提高施工效率;C, according to the
D、完成煤巷6掘进工作后,开始进行煤层工作面回采,如图3所示,在回采期间从底板岩巷2向煤层工作面前方30m的煤体施工多个定向钻孔8,定向钻孔8的直径为50~80mm,所述定向钻孔8的施工形式采用高位钻孔和顺层钻孔联合施工。这种方式能更好的提高瓦斯抽采效果;各个定向钻孔8均穿过煤层1进入顶板岩层3,然后将各个定向钻孔8采用步骤B的方式处理后进行二次瓦斯强化抽采,从而保证煤层工作面回采过程中的安全稳定;所述穿层钻孔5、注浆钻孔4和定向钻孔8的终孔位置均进入顶板岩层至少1m。这样能保证各个钻孔的钻设后的稳定性。D. After completing the excavation work of the
E、当前煤层工作面回采完毕后,重复步骤A至D在同一煤层与当前煤巷间隔一定距离后,如图4所示,再确定新的煤巷6及底板岩巷2,并将新的煤巷6及底板岩巷2掘进时产生的煤矸石运输至当前底板岩巷2内进行湿式密封充填,同时新的煤巷6掘进时能利用当前形成的卸压区域II,从而在保证煤巷6掘进及后续使用安全稳定前提下,提高煤巷6掘进效率。其中湿式密封充填的过程为:利用高水材料混合煤矸石充填至底板岩巷2内,并设置埋管对充填区的空气进行负压抽采;其中高水材料的注入压力为3~5MPa,注入体积为底板岩巷2体积减去煤矸石充填体积,空气负压抽采压力为700~900kPa。E. After the mining of the current coal seam working face is completed, repeat steps A to D after a certain distance between the same coal seam and the current coal roadway, as shown in Figure 4, and then determine the
作为本发明的一种改进,所述注浆材料采用掺有快速凝结剂的水泥砂浆,水灰比为1:3,且注浆设备采用气动式注浆泵进行注浆,注浆时间控制在30~40min。采用该种注浆材料使得强化区域I的加固强度更好。As an improvement of the present invention, the grouting material adopts cement mortar mixed with a rapid coagulant, the water-cement ratio is 1:3, and the grouting equipment adopts a pneumatic grouting pump for grouting, and the grouting time is controlled at 30 to 40 minutes. The use of this grouting material makes the reinforcement strength of the reinforcement region I better.
以上所述仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above is only the preferred embodiment of the present invention, it should be pointed out that: for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can also be made, and these improvements and modifications are also It should be regarded as the protection scope of the present invention.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210496959.3A CN114673502B (en) | 2022-05-09 | 2022-05-09 | Multi-mode disaster chain type treatment method based on bottom plate rock roadway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210496959.3A CN114673502B (en) | 2022-05-09 | 2022-05-09 | Multi-mode disaster chain type treatment method based on bottom plate rock roadway |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114673502A true CN114673502A (en) | 2022-06-28 |
CN114673502B CN114673502B (en) | 2022-12-02 |
Family
ID=82080663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210496959.3A Active CN114673502B (en) | 2022-05-09 | 2022-05-09 | Multi-mode disaster chain type treatment method based on bottom plate rock roadway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114673502B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115199269A (en) * | 2022-07-08 | 2022-10-18 | 中国矿业大学 | Multi-disaster integrated prevention and control method for island outburst coal seam strong and weak coupling structure |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102409997A (en) * | 2011-12-09 | 2012-04-11 | 中国矿业大学 | Curtain grouting anti-burst method for cutting through coal and gas bursting seam in shaft |
CN102900460A (en) * | 2012-11-06 | 2013-01-30 | 中国矿业大学 | Method for performing through-going seam cutting, pressure relief, permeability enhancement and quick tunneling on soft and high-outburst coal seam |
CN103362538A (en) * | 2013-07-15 | 2013-10-23 | 中国矿业大学 | Coal seam cutting, fracturing, pressure pumping and alternating gas extraction method |
CN104314610A (en) * | 2014-10-11 | 2015-01-28 | 中煤科工集团重庆研究院有限公司 | Outburst eliminating method for coal roadway stripe region |
CN104863629A (en) * | 2015-06-11 | 2015-08-26 | 中国矿业大学 | Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole |
CN108590739A (en) * | 2018-04-11 | 2018-09-28 | 中国平煤神马能源化工集团有限责任公司 | A kind of prominent tunnel regionality energy divides source to control anti-burst method |
CN109113784A (en) * | 2018-09-20 | 2019-01-01 | 中国矿业大学 | A kind of coal bed gas extraction-water filling coupling device and method |
CN112145225A (en) * | 2020-09-22 | 2020-12-29 | 中煤能源研究院有限责任公司 | Underground in-situ pulping and backfilling system and method for coal mine tunneling gangue |
CN112664259A (en) * | 2020-12-23 | 2021-04-16 | 中国矿业大学 | Trinity comprehensive outburst prevention method for high outburst coal seam |
-
2022
- 2022-05-09 CN CN202210496959.3A patent/CN114673502B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102409997A (en) * | 2011-12-09 | 2012-04-11 | 中国矿业大学 | Curtain grouting anti-burst method for cutting through coal and gas bursting seam in shaft |
CN102900460A (en) * | 2012-11-06 | 2013-01-30 | 中国矿业大学 | Method for performing through-going seam cutting, pressure relief, permeability enhancement and quick tunneling on soft and high-outburst coal seam |
CN103362538A (en) * | 2013-07-15 | 2013-10-23 | 中国矿业大学 | Coal seam cutting, fracturing, pressure pumping and alternating gas extraction method |
CN104314610A (en) * | 2014-10-11 | 2015-01-28 | 中煤科工集团重庆研究院有限公司 | Outburst eliminating method for coal roadway stripe region |
CN104863629A (en) * | 2015-06-11 | 2015-08-26 | 中国矿业大学 | Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole |
CN108590739A (en) * | 2018-04-11 | 2018-09-28 | 中国平煤神马能源化工集团有限责任公司 | A kind of prominent tunnel regionality energy divides source to control anti-burst method |
CN109113784A (en) * | 2018-09-20 | 2019-01-01 | 中国矿业大学 | A kind of coal bed gas extraction-water filling coupling device and method |
CN112145225A (en) * | 2020-09-22 | 2020-12-29 | 中煤能源研究院有限责任公司 | Underground in-situ pulping and backfilling system and method for coal mine tunneling gangue |
CN112664259A (en) * | 2020-12-23 | 2021-04-16 | 中国矿业大学 | Trinity comprehensive outburst prevention method for high outburst coal seam |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115199269A (en) * | 2022-07-08 | 2022-10-18 | 中国矿业大学 | Multi-disaster integrated prevention and control method for island outburst coal seam strong and weak coupling structure |
Also Published As
Publication number | Publication date |
---|---|
CN114673502B (en) | 2022-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018201706A1 (en) | Method for efficient gas drainage in coal roadway strips and regional outburst elimination through staged fracturing with long borehole floor beddings | |
CN109736827B (en) | Excavation method of high-pressure gas expansion-induced cracking in the connection channel of urban subway hard rock strata | |
CN105317459A (en) | Subarea filling method used for controlling large-area falling disaster of hard roof | |
CN108590739B (en) | A kind of prominent tunnel regionality energy divides source to control anti-burst method | |
Bell | Methods of treatment of unstable ground | |
CN111101540B (en) | Construction method for passing existing electric power tunnel on open cut tunnel | |
CN104373128A (en) | Advance precipitation construction method of oversized-section double-side lower pilot tunnels of water-rich tunnel | |
CN114109394A (en) | Method for determining pile length of tunnel shallow-buried weak surrounding rock high-pressure jet grouting pile method ground surface reinforcement | |
CN108266189A (en) | A kind of lane top Tunnelling Along Goaf goaf isolation method | |
CN107035376A (en) | One kind common law in huge thick bedrock aquifer digs shaft construction method | |
CN115199269A (en) | Multi-disaster integrated prevention and control method for island outburst coal seam strong and weak coupling structure | |
CN107152309B (en) | A kind of coal seam is the high water level and high-speed drainage water damage control method of Main aquifer | |
CN111677531A (en) | A pre-mining disposal method for the caving area of the old mining residual coal re-mining working face in thick coal seam | |
CN115749776A (en) | Coal pillar recovery method based on fault grouting transformation | |
CN114673502B (en) | Multi-mode disaster chain type treatment method based on bottom plate rock roadway | |
CN114183139B (en) | Control methods and control devices for working surfaces affected by mining | |
CN113107579B (en) | A three-dimensional gas drainage method for directional long drilling combined with floor penetration drilling | |
CN115573725A (en) | Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield | |
CN110552731A (en) | top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof | |
CN114856691B (en) | A safe mining method for rock burst island working face | |
CN103291307B (en) | A kind of rich water rockhole Dewatering by leading level method | |
CN206681736U (en) | Goaf casing pipe protection system | |
CN112879010B (en) | Foundation construction method for municipal engineering | |
CN208220720U (en) | A kind of coal mining water and gas control system altogether | |
CN208294522U (en) | Waterproof of man in a kind of pilot tunnel of rich water sand-pebble layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |