CN114658250A - A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure - Google Patents
A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure Download PDFInfo
- Publication number
- CN114658250A CN114658250A CN202210299719.4A CN202210299719A CN114658250A CN 114658250 A CN114658250 A CN 114658250A CN 202210299719 A CN202210299719 A CN 202210299719A CN 114658250 A CN114658250 A CN 114658250A
- Authority
- CN
- China
- Prior art keywords
- embedded box
- concrete
- reserved
- floor slab
- suspended
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0203—Arrangements for filling cracks or cavities in building constructions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/64—Insulation or other protection; Elements or use of specified material therefor for making damp-proof; Protection against corrosion
- E04B1/644—Damp-proof courses
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
- E04F21/02—Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
- E04F21/06—Implements for applying plaster, insulating material, or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G15/00—Forms or shutterings for making openings, cavities, slits, or channels
- E04G15/06—Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,解决了下部悬空结构楼板预留洞口封堵及装饰困难的技术问题。本发明包括以下步骤:①施工准备、②预制构件、③安装预制构件、④浇筑悬空楼板、⑤悬空楼板底部装饰、⑥临时封堵、⑦浇筑封堵。本发明可广泛运用于高层、超高层建筑避难层及空中连廊施工中,通过提前安装预埋盒的方法,即保证了后续施工的顺利展开,又解决了洞口封堵及装饰装修收尾困难问题,该方法操作简便、实用,可以被广泛的运用。本发明可直接在预留洞口浇筑混凝土,且提前在预埋盒外侧底部及堵塞突出预埋盒的底面涂刷与悬空楼板的底部装饰同色的防锈漆,可以达到洞口封堵及装饰一体化施工的目的。The invention discloses a decoration integrated sealing method for the reserved opening of the floor slab of the lower suspended structure, which solves the technical problems of difficulty in sealing and decoration of the reserved opening of the floor slab of the lower suspended structure. The present invention comprises the following steps: 1. construction preparation, 2. prefabricated components, 3. installation of prefabricated components, 4. pouring suspended floor slabs, 5. bottom decoration of suspended floor slabs, 6. temporary sealing, 7. pouring and sealing. The invention can be widely used in the construction of high-rise and super-high-rise building refuge floors and aerial corridors. By installing the pre-embedded box in advance, it not only ensures the smooth development of subsequent construction, but also solves the difficult problems of hole blocking and decoration and finishing. , the method is simple, practical, and can be widely used. The present invention can directly pour concrete at the reserved hole, and paint the same color anti-rust paint on the outer bottom of the pre-embedded box and the bottom surface of the blocked protruding pre-embedded box in advance, which can achieve the integration of hole sealing and decoration. purpose of construction.
Description
技术领域technical field
本发明涉及预留洞口封堵技术领域,特别是指一种下部悬空结构楼板预留洞口的装饰一体化封堵方法。The invention relates to the technical field of reserved hole sealing, in particular to a decoration integrated sealing method for reserved holes in a floor slab of a lower suspended structure.
背景技术Background technique
随着我国城镇化进程的加快以及人民生活水平的提高,高层、超高层住宅项目建设数量、建设规模正在稳步增长。为满足建筑消防疏散需求,下部悬空避难层结构楼板在高层、超高层建筑中大量应用。在此类结构施工中需配合预留一些临时施工洞口,但是临时施工洞口封堵及该部位装饰、装修等收尾施工成为困扰大量建筑施工人员的一大难题。传统的施工方法是,临时施工洞口需要浇筑封闭时,采用打凿方式将钢筋凿出,将折弯起的钢筋弯平后进行再进行支模浇筑。这种施工方法不仅使标化价格增高,并且后期修补也会增加人工以及材料的修补成本。With the acceleration of my country's urbanization process and the improvement of people's living standards, the number and scale of high-rise and super-high-rise residential projects are steadily increasing. In order to meet the needs of building fire evacuation, the lower suspended refuge floor structure floor is widely used in high-rise and super high-rise buildings. In the construction of such structures, some temporary construction openings need to be reserved, but the blocking of temporary construction openings and the finishing construction such as decoration and decoration of this part have become a major problem that plagues a large number of construction workers. The traditional construction method is that when the temporary construction opening needs to be poured and closed, the steel bar is chiseled out by chiseling, and the bent steel bar is bent and flattened, and then the formwork is poured. This construction method not only increases the standard price, but also increases the labor and material repair costs for later repairs.
发明内容SUMMARY OF THE INVENTION
针对上述背景技术中的不足,本发明提出一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,解决了下部悬空结构楼板预留洞口封堵及装饰困难的技术问题。In view of the above-mentioned deficiencies in the background technology, the present invention proposes a method for integrating decoration and blocking of reserved openings in the floor slab of the lower suspended structure, which solves the technical problems of difficulty in sealing and decoration of the reserved openings in the floor slab of the lower suspended structure.
本申请的技术方案是这样实现的:一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,包括以下步骤:The technical solution of the present application is achieved in this way: a method for integrating decoration and sealing of reserved openings in a floor slab of a lower suspended structure, comprising the following steps:
①施工准备,在悬空楼板混凝土浇筑前设计预留洞口的尺寸、位置和数量;①Construction preparation, design the size, location and quantity of reserved openings before concrete pouring of suspended floor slabs;
②预制构件,根据步骤①中确定的预留洞口数量和尺寸,在工厂预制止水环、预埋盒、预埋盒的顶盖及预埋盒的堵塞,预埋盒的底部设置有工作孔;②Prefabricated components, according to the number and size of the reserved openings determined in step ①, the water stop ring, the embedded box, the top cover of the embedded box and the blockage of the embedded box are pre-prepared in the factory, and the bottom of the embedded box is provided with a working hole ;
③安装预制构件,在悬空楼板混凝土浇筑前,将步骤②中的止水环预埋在步骤①中预留洞口设计位置的外周,并与楼板底筋进行定位焊接,完成止水环1预埋工作后,将步骤②中预制的预埋盒嵌入到止水环内周;③Install the prefabricated components. Before the suspended floor concrete is poured, the water stop ring in step ② is pre-buried on the outer periphery of the design position of the opening reserved in step ①, and the positioning welding is performed with the floor bottom rib to complete the pre-embedding of the water stop ring 1. After working, insert the prefabricated embedded box in step ② into the inner circumference of the water stop ring;
④浇筑悬空楼板,将步骤③中的止水环和预埋盒与悬空楼板同步浇筑混凝土;④Pour the suspended floor, and pour the water stop ring and the embedded box in step ③ simultaneously with the suspended floor to pour concrete;
⑤悬空楼板底部装饰,步骤④中的悬空楼板浇筑后且达到设计强度后,拆除底模板,对预埋盒露出的底部进行除锈和喷漆;⑤ The bottom of the suspended floor is decorated. After the suspended floor in step ④ is poured and reaches the design strength, the bottom formwork is removed, and the exposed bottom of the embedded box is derusted and painted;
⑥临时封堵,当预留洞口暂时不使用时,采用步骤②中的顶盖封堵在预埋盒的工作孔中;⑥ Temporary blocking, when the reserved hole is temporarily not used, use the top cover in step ② to block the working hole of the embedded box;
⑦浇筑封堵,当预留洞口不再使用时,取出步骤⑥中的顶盖,采用步骤②中的堵塞与工作孔插装配合,然后进行混凝土浇筑。⑦Pouring and sealing. When the reserved hole is no longer used, take out the top cover in step ⑥, use the plugging in step ② to insert and fit the working hole, and then carry out concrete pouring.
进一步地,所述步骤③中,在悬空楼板混凝土浇筑前,将顶盖盖在预埋盒上部,在顶盖与预埋盒之间的拼缝处粘贴透明胶布进行密封处理,防止步骤④浇筑混凝土时泥浆顺着拼缝缝隙流入到预埋盒底部。Further, in the step 3., before the concrete of the suspended floor slab is poured, the top cover is covered on the upper part of the embedded box, and the transparent tape is pasted at the joint between the top cover and the embedded box to carry out sealing treatment to prevent step ④ from pouring. During concrete, the mud flows into the bottom of the embedded box along the joint gap.
进一步地,当进行步骤③时,在悬空楼板设计预留洞口的位置设置预留钢筋,当进行进行步骤⑦时,将预留钢筋与预埋盒搭接并焊接后浇筑混凝土。Further, when step 3 is performed, reserved steel bars are set at the positions of the reserved openings in the design of the suspended floor slab, and when step 7 is performed, the reserved steel bars are lapped and welded with the embedded box and then poured into concrete.
进一步地,所述步骤②中的止水环、预埋盒、及堵塞采用精密车床设备进行加工,确保尺寸允许偏差在0.3mm内。Further, the water stop ring, the pre-embedded box, and the plug in the step ② are processed with precision lathe equipment to ensure that the allowable deviation of the size is within 0.3mm.
进一步地,在所述步骤⑤中,除锈工作完成后,涂刷与悬空楼板的底部装饰面同色的防锈漆,防锈漆涂刷时应做到一底二面。Further, in the step ⑤, after the rust removal work is completed, the anti-rust paint of the same color as the bottom decorative surface of the suspended floor slab is painted, and the anti-rust paint should be painted on one bottom and two sides.
进一步地,进行所述一底二面时,涂刷底漆时应确保基层平整、干躁,中间漆涂刷工作应待底漆完全干躁后才能进行,面漆应采用喷涂方式进行,施工前应做好悬空楼板底部装饰面的成品保护工作,避免对悬空楼板的底部装饰面造成污染。Further, when carrying out the above-mentioned one bottom and two sides, the base layer should be smooth and dry when applying the primer, the intermediate paint should be painted after the primer is completely dry, and the top paint should be sprayed. The finished product protection of the bottom decorative surface of the suspended floor should be done well before, so as to avoid pollution to the bottom decorative surface of the suspended floor.
进一步地,进行所述步骤⑦时,取出顶盖后,对预埋盒的内部进行清理,然后采用步骤②中的堵塞与工作孔插装配合,堵塞伸出工作孔的端面涂刷与悬空楼板的底部装饰面同色的防锈漆。Further, when carrying out the step 7, after taking out the top cover, the interior of the embedded box is cleaned up, and then the blockage in step 2 is used to insert and cooperate with the working hole, and the end face brushing and the suspended floor slab extending out of the working hole are blocked. Anti-rust paint of the same color as the bottom decorative surface.
进一步地,所述步骤⑦中浇筑的混凝土强度比悬空楼板的浇筑混凝土强度高一个等级。Further, the strength of the concrete poured in the step (7) is one grade higher than the strength of the poured concrete of the suspended floor slab.
进一步地,所述步骤⑦中浇筑的混凝土为微膨胀细石混凝土。Further, the concrete poured in the step (7) is micro-expanded fine stone concrete.
与现有技术相比,本发明的有益效果包括:Compared with the prior art, the beneficial effects of the present invention include:
1. 本发明可广泛运用于高层、超高层建筑避难层及空中连廊施工中,通过提前安装预埋盒的方法,即保证了后续施工的顺利展开,又解决了洞口封堵及装饰装修收尾困难问题,该方法操作简便、实用,可以被广泛的运用。1. The present invention can be widely used in the construction of high-rise, super-high-rise building refuge floors and aerial corridors. By installing the pre-embedded box in advance, the smooth development of the subsequent construction is ensured, and the hole blocking and decoration finishing are solved. Difficult problems, the method is easy to operate, practical, and can be widely used.
2. 本发明将预埋盒提前预埋在悬空楼板内,后期进行洞口封堵时不用支设模板,可直接浇筑混凝土,且提前在预埋盒外侧底部及堵塞突出预埋盒的底面涂刷与悬空楼板的底部装饰同色的防锈漆,可以达到洞口封堵及装饰一体化施工的目的。2. In the present invention, the pre-embedded box is pre-buried in the suspended floor slab in advance. When the opening is blocked in the later stage, there is no need to set up a template, and the concrete can be directly poured, and the bottom surface of the outer side of the pre-embedded box and the bottom surface of the block protruding pre-embedded box are painted in advance. The anti-rust paint of the same color as the bottom decoration of the suspended floor can achieve the purpose of integrated construction of hole sealing and decoration.
3. 在浇筑悬空楼板前根据后续施工需求将预埋盒安装在对应位置,为防止杂物及水泥浆流入预埋盒内,按要求将顶盖缓缓嵌入预埋盒内,待后续施工完成后,预留洞口达到封堵条件时,在预埋盒外侧底部及堵塞的下端面涂刷与悬空楼板的底部装饰同色的防锈漆,最后完成预留洞口封堵工作。本发明易于施工,实用简单,节约成本和加快施工进度。3. Before pouring the suspended floor slab, install the embedded box in the corresponding position according to the subsequent construction requirements. In order to prevent sundries and cement slurry from flowing into the embedded box, slowly insert the top cover into the embedded box as required, and wait for the subsequent construction to be completed. Then, when the reserved hole reaches the blocking condition, the bottom of the outside of the embedded box and the blocked lower end surface are painted with the same color of anti-rust paint as the bottom decoration of the suspended floor, and finally the reserved hole is blocked. The invention is easy to construct, practical and simple, saves cost and accelerates construction progress.
具体实施方式Detailed ways
下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be described clearly and completely below. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,①施工准备,在悬空楼板混凝土浇筑前设计预留洞口的尺寸、位置和数量;A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure. (1) Construction preparation, design the size, position and quantity of the reserved openings before concrete pouring of the suspended floor slab;
②预制构件,根据步骤①中确定的预留洞口数量和尺寸,在工厂预制止水环、预埋盒、预埋盒的顶盖及预埋盒的堵塞,预埋盒的底部设置有工作孔;止水环、预埋盒、及堵塞采用精密车床设备进行加工,确保尺寸允许偏差在0.3mm内。②Prefabricated components, according to the number and size of the reserved openings determined in step ①, the water stop ring, the embedded box, the top cover of the embedded box and the blockage of the embedded box are pre-prepared in the factory, and the bottom of the embedded box is provided with a working hole ; Water stop ring, pre-embedded box, and plug are processed with precision lathe equipment to ensure that the allowable deviation of the size is within 0.3mm.
③安装预制构件,在悬空楼板混凝土浇筑前,将步骤②中的止水环预埋在步骤①中预留洞口设计位置的外周,并与楼板底筋进行定位焊接,完成止水环1预埋工作后,将步骤②中预制的预埋盒嵌入到止水环内周。在悬空楼板混凝土浇筑前,将顶盖盖在预埋盒上部,在顶盖与预埋盒之间的拼缝处粘贴透明胶布进行密封处理,防止步骤④浇筑混凝土时泥浆顺着拼缝缝隙流入到预埋盒底部。③Install the prefabricated components. Before the suspended floor concrete is poured, the water stop ring in step ② is pre-buried on the outer periphery of the design position of the opening reserved in step ①, and the positioning welding is performed with the floor bottom rib to complete the pre-embedding of the water stop ring 1. After the work, insert the prefabricated embedded box in step ② into the inner circumference of the water stop ring. Before the concrete of the suspended floor is poured, cover the top cover on the upper part of the embedded box, and paste the transparent tape on the joint between the top cover and the embedded box for sealing treatment, so as to prevent the mud from flowing into the joint gap when the concrete is poured in step ④. to the bottom of the embedded box.
④浇筑悬空楼板,将步骤③中的止水环和预埋盒与悬空楼板同步浇筑混凝土;④Pour the suspended floor, and pour the water stop ring and the embedded box in step ③ simultaneously with the suspended floor to pour concrete;
⑤悬空楼板底部装饰,步骤④中的悬空楼板浇筑后且达到设计强度后,拆除底模板,对预埋盒露出的底部进行除锈和喷漆。除锈工作完成后,涂刷与悬空楼板的底部装饰面同色的防锈漆,防锈漆涂刷时应做到一底二面。⑤ Decorate the bottom of the suspended floor. After the suspended floor in step ④ is poured and reaches the design strength, the bottom formwork is removed, and the exposed bottom of the embedded box is derusted and painted. After the rust removal work is completed, paint the anti-rust paint of the same color as the decorative surface of the bottom of the suspended floor.
进一步地,进行所述一底二面时,涂刷底漆时应确保基层平整、干躁,中间漆涂刷工作应待底漆完全干躁后才能进行,面漆应采用喷涂方式进行,施工前应做好悬空楼板底部装饰面的成品保护工作,避免对悬空楼板的底部装饰面造成污染。Further, when carrying out the above-mentioned one bottom and two sides, the base layer should be smooth and dry when applying the primer, the intermediate paint should be painted after the primer is completely dry, and the top paint should be sprayed. The finished product protection of the bottom decorative surface of the suspended floor should be done well before, so as to avoid pollution to the bottom decorative surface of the suspended floor.
⑥临时封堵,当预留洞口暂时不使用时,采用步骤②中的顶盖封堵在预埋盒的工作孔中;⑥ Temporary blocking, when the reserved hole is temporarily not used, the top cover in step ② is used to block the working hole of the embedded box;
⑦浇筑封堵,当预留洞口不再使用时,取出步骤⑥中的顶盖,采用步骤②中的堵塞与工作孔插装配合,然后进行混凝土浇筑。具体地,取出顶盖后,对预埋盒的内部进行清理,然后采用步骤②中的堵塞与工作孔插装配合,堵塞伸出工作孔的端面涂刷与悬空楼板的底部装饰面同色的防锈漆。⑦Pouring and sealing. When the reserved hole is no longer used, take out the top cover in step ⑥, use the plugging in step ② to insert and fit the working hole, and then carry out concrete pouring. Specifically, after taking out the top cover, clean the interior of the embedded box, and then use the plugging in step ② to insert and cooperate with the working hole, and the end face of the blocked working hole is painted with the same color as the bottom decorative surface of the suspended floor slab. Rust paint.
进一步地,当进行步骤③时,在悬空楼板设计预留洞口的位置设置预留钢筋,当进行进行步骤⑦时,将预留钢筋与预埋盒搭接并焊接后浇筑混凝土。预留洞口封堵浇筑的混凝土强度比悬空楼板的浇筑混凝土强度高一个等级,优选浇筑微膨胀细石混凝土。Further, when step 3 is performed, reserved steel bars are set at the positions of the reserved openings in the design of the suspended floor slab, and when step 7 is performed, the reserved steel bars are lapped and welded with the embedded box and then poured into concrete. The strength of the concrete poured by the reserved opening is one grade higher than that of the suspended floor slab, and the micro-expanded fine stone concrete is preferably poured.
本发明未详尽之处均为本领域技术人员所公知的常规技术手段。The non-exhaustive parts of the present invention are conventional technical means known to those skilled in the art.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of the present invention. within the scope of protection.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210299719.4A CN114658250A (en) | 2022-03-25 | 2022-03-25 | A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210299719.4A CN114658250A (en) | 2022-03-25 | 2022-03-25 | A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114658250A true CN114658250A (en) | 2022-06-24 |
Family
ID=82032039
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210299719.4A Pending CN114658250A (en) | 2022-03-25 | 2022-03-25 | A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114658250A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202969967U (en) * | 2012-11-07 | 2013-06-05 | 中建三局第二建设工程有限责任公司 | Temporary protecting device for once formed floor reserved hole |
US9228689B1 (en) * | 2013-09-13 | 2016-01-05 | Roger Cline | System and method for in-place vent pipe restoration |
CN108166531A (en) * | 2017-12-26 | 2018-06-15 | 中国建筑第七工程局有限公司 | Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip |
CN210177985U (en) * | 2019-06-14 | 2020-03-24 | 淮安市宏茂金属制品有限公司 | Material conveying port free of bar planting |
CN111305566A (en) * | 2020-03-27 | 2020-06-19 | 中建二局第二建筑工程有限公司 | High-rise residential full-professional alternate construction floor water interception method |
CN213745289U (en) * | 2020-11-08 | 2021-07-20 | 广东电白建设集团有限公司 | Through-floor pump pipe fixing system |
-
2022
- 2022-03-25 CN CN202210299719.4A patent/CN114658250A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202969967U (en) * | 2012-11-07 | 2013-06-05 | 中建三局第二建设工程有限责任公司 | Temporary protecting device for once formed floor reserved hole |
US9228689B1 (en) * | 2013-09-13 | 2016-01-05 | Roger Cline | System and method for in-place vent pipe restoration |
CN108166531A (en) * | 2017-12-26 | 2018-06-15 | 中国建筑第七工程局有限公司 | Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip |
CN210177985U (en) * | 2019-06-14 | 2020-03-24 | 淮安市宏茂金属制品有限公司 | Material conveying port free of bar planting |
CN111305566A (en) * | 2020-03-27 | 2020-06-19 | 中建二局第二建筑工程有限公司 | High-rise residential full-professional alternate construction floor water interception method |
CN213745289U (en) * | 2020-11-08 | 2021-07-20 | 广东电白建设集团有限公司 | Through-floor pump pipe fixing system |
Non-Patent Citations (1)
Title |
---|
周凌峰;: "铝模施工质量及施工效率的提升策略", 智能城市, no. 17 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103470067B (en) | Transformation and construction method used for facing bare concrete of existing building outer wall | |
US5502941A (en) | Method and apparatus for producing an ornamental concrete surface | |
CN101585205B (en) | Method for producing and mounting moulded concrete anaglyph unit plate | |
CN111305566B (en) | High-rise residential full-professional alternate construction floor water interception method | |
CN103046709A (en) | Building construction method of inner wall surface | |
CN104018598A (en) | A kind of exterior wall structure and construction installation method | |
CN106760535A (en) | One kind exempts from plastering construction method using aluminum alloy mould plate casting concrete interior wall | |
CN105908889A (en) | Construction method for prefabrication and reverse installation of cornice concrete decoration members of archaistic building | |
CN107190889A (en) | Steel frame lightweight sandwich board integrated wall and its construction method | |
CN114658250A (en) | A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure | |
CN207176990U (en) | A steel frame lightweight sandwich panel integrated wall | |
CN102900233B (en) | Dual face raw slurry clean water concrete construction | |
CN113802845A (en) | Synchronous reverse construction method for high-rise building outer wall decoration engineering and main body structure | |
CN109339355A (en) | The construction method of the aluminium sheet roofing waterproofing node of structural slab is done using ALC plate | |
CN109763573B (en) | Water stop ridge and construction method thereof | |
CN112815153A (en) | Waterproof treatment method for root of through-wall or floor pipeline | |
CN201908415U (en) | Wall decorative board layer structure | |
CN217924247U (en) | Unit type clear water-imitating concrete skeleton partition wall structure | |
CN216921377U (en) | Decoration integration plugging device of entrance to a cave is reserved to unsettled structure floor in lower part | |
CN113323396A (en) | Integrated construction method for external wall of fabricated building | |
CN212405863U (en) | Building facade decoration structure | |
CN106894542A (en) | One kind exempts from plastering construction method using aluminum alloy mould plate casting concrete inner side of outer wall | |
CN212926756U (en) | Waterproof joint structure of flue root | |
CN210086744U (en) | Assembled piping shaft for high-rise building | |
CN1047425C (en) | Attaching process for colour facing concrete board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220624 |