CN114658250A - A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure - Google Patents

A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure Download PDF

Info

Publication number
CN114658250A
CN114658250A CN202210299719.4A CN202210299719A CN114658250A CN 114658250 A CN114658250 A CN 114658250A CN 202210299719 A CN202210299719 A CN 202210299719A CN 114658250 A CN114658250 A CN 114658250A
Authority
CN
China
Prior art keywords
embedded box
concrete
reserved
floor slab
suspended
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210299719.4A
Other languages
Chinese (zh)
Inventor
王勇
罗亚军
郑思
张亮
皮俊超
王胜猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202210299719.4A priority Critical patent/CN114658250A/en
Publication of CN114658250A publication Critical patent/CN114658250A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/64Insulation or other protection; Elements or use of specified material therefor for making damp-proof; Protection against corrosion
    • E04B1/644Damp-proof courses
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,解决了下部悬空结构楼板预留洞口封堵及装饰困难的技术问题。本发明包括以下步骤:①施工准备、②预制构件、③安装预制构件、④浇筑悬空楼板、⑤悬空楼板底部装饰、⑥临时封堵、⑦浇筑封堵。本发明可广泛运用于高层、超高层建筑避难层及空中连廊施工中,通过提前安装预埋盒的方法,即保证了后续施工的顺利展开,又解决了洞口封堵及装饰装修收尾困难问题,该方法操作简便、实用,可以被广泛的运用。本发明可直接在预留洞口浇筑混凝土,且提前在预埋盒外侧底部及堵塞突出预埋盒的底面涂刷与悬空楼板的底部装饰同色的防锈漆,可以达到洞口封堵及装饰一体化施工的目的。The invention discloses a decoration integrated sealing method for the reserved opening of the floor slab of the lower suspended structure, which solves the technical problems of difficulty in sealing and decoration of the reserved opening of the floor slab of the lower suspended structure. The present invention comprises the following steps: 1. construction preparation, 2. prefabricated components, 3. installation of prefabricated components, 4. pouring suspended floor slabs, 5. bottom decoration of suspended floor slabs, 6. temporary sealing, 7. pouring and sealing. The invention can be widely used in the construction of high-rise and super-high-rise building refuge floors and aerial corridors. By installing the pre-embedded box in advance, it not only ensures the smooth development of subsequent construction, but also solves the difficult problems of hole blocking and decoration and finishing. , the method is simple, practical, and can be widely used. The present invention can directly pour concrete at the reserved hole, and paint the same color anti-rust paint on the outer bottom of the pre-embedded box and the bottom surface of the blocked protruding pre-embedded box in advance, which can achieve the integration of hole sealing and decoration. purpose of construction.

Description

一种下部悬空结构楼板预留洞口的装饰一体化封堵方法A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure

技术领域technical field

本发明涉及预留洞口封堵技术领域,特别是指一种下部悬空结构楼板预留洞口的装饰一体化封堵方法。The invention relates to the technical field of reserved hole sealing, in particular to a decoration integrated sealing method for reserved holes in a floor slab of a lower suspended structure.

背景技术Background technique

随着我国城镇化进程的加快以及人民生活水平的提高,高层、超高层住宅项目建设数量、建设规模正在稳步增长。为满足建筑消防疏散需求,下部悬空避难层结构楼板在高层、超高层建筑中大量应用。在此类结构施工中需配合预留一些临时施工洞口,但是临时施工洞口封堵及该部位装饰、装修等收尾施工成为困扰大量建筑施工人员的一大难题。传统的施工方法是,临时施工洞口需要浇筑封闭时,采用打凿方式将钢筋凿出,将折弯起的钢筋弯平后进行再进行支模浇筑。这种施工方法不仅使标化价格增高,并且后期修补也会增加人工以及材料的修补成本。With the acceleration of my country's urbanization process and the improvement of people's living standards, the number and scale of high-rise and super-high-rise residential projects are steadily increasing. In order to meet the needs of building fire evacuation, the lower suspended refuge floor structure floor is widely used in high-rise and super high-rise buildings. In the construction of such structures, some temporary construction openings need to be reserved, but the blocking of temporary construction openings and the finishing construction such as decoration and decoration of this part have become a major problem that plagues a large number of construction workers. The traditional construction method is that when the temporary construction opening needs to be poured and closed, the steel bar is chiseled out by chiseling, and the bent steel bar is bent and flattened, and then the formwork is poured. This construction method not only increases the standard price, but also increases the labor and material repair costs for later repairs.

发明内容SUMMARY OF THE INVENTION

针对上述背景技术中的不足,本发明提出一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,解决了下部悬空结构楼板预留洞口封堵及装饰困难的技术问题。In view of the above-mentioned deficiencies in the background technology, the present invention proposes a method for integrating decoration and blocking of reserved openings in the floor slab of the lower suspended structure, which solves the technical problems of difficulty in sealing and decoration of the reserved openings in the floor slab of the lower suspended structure.

本申请的技术方案是这样实现的:一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,包括以下步骤:The technical solution of the present application is achieved in this way: a method for integrating decoration and sealing of reserved openings in a floor slab of a lower suspended structure, comprising the following steps:

①施工准备,在悬空楼板混凝土浇筑前设计预留洞口的尺寸、位置和数量;①Construction preparation, design the size, location and quantity of reserved openings before concrete pouring of suspended floor slabs;

②预制构件,根据步骤①中确定的预留洞口数量和尺寸,在工厂预制止水环、预埋盒、预埋盒的顶盖及预埋盒的堵塞,预埋盒的底部设置有工作孔;②Prefabricated components, according to the number and size of the reserved openings determined in step ①, the water stop ring, the embedded box, the top cover of the embedded box and the blockage of the embedded box are pre-prepared in the factory, and the bottom of the embedded box is provided with a working hole ;

③安装预制构件,在悬空楼板混凝土浇筑前,将步骤②中的止水环预埋在步骤①中预留洞口设计位置的外周,并与楼板底筋进行定位焊接,完成止水环1预埋工作后,将步骤②中预制的预埋盒嵌入到止水环内周;③Install the prefabricated components. Before the suspended floor concrete is poured, the water stop ring in step ② is pre-buried on the outer periphery of the design position of the opening reserved in step ①, and the positioning welding is performed with the floor bottom rib to complete the pre-embedding of the water stop ring 1. After working, insert the prefabricated embedded box in step ② into the inner circumference of the water stop ring;

④浇筑悬空楼板,将步骤③中的止水环和预埋盒与悬空楼板同步浇筑混凝土;④Pour the suspended floor, and pour the water stop ring and the embedded box in step ③ simultaneously with the suspended floor to pour concrete;

⑤悬空楼板底部装饰,步骤④中的悬空楼板浇筑后且达到设计强度后,拆除底模板,对预埋盒露出的底部进行除锈和喷漆;⑤ The bottom of the suspended floor is decorated. After the suspended floor in step ④ is poured and reaches the design strength, the bottom formwork is removed, and the exposed bottom of the embedded box is derusted and painted;

⑥临时封堵,当预留洞口暂时不使用时,采用步骤②中的顶盖封堵在预埋盒的工作孔中;⑥ Temporary blocking, when the reserved hole is temporarily not used, use the top cover in step ② to block the working hole of the embedded box;

⑦浇筑封堵,当预留洞口不再使用时,取出步骤⑥中的顶盖,采用步骤②中的堵塞与工作孔插装配合,然后进行混凝土浇筑。⑦Pouring and sealing. When the reserved hole is no longer used, take out the top cover in step ⑥, use the plugging in step ② to insert and fit the working hole, and then carry out concrete pouring.

进一步地,所述步骤③中,在悬空楼板混凝土浇筑前,将顶盖盖在预埋盒上部,在顶盖与预埋盒之间的拼缝处粘贴透明胶布进行密封处理,防止步骤④浇筑混凝土时泥浆顺着拼缝缝隙流入到预埋盒底部。Further, in the step 3., before the concrete of the suspended floor slab is poured, the top cover is covered on the upper part of the embedded box, and the transparent tape is pasted at the joint between the top cover and the embedded box to carry out sealing treatment to prevent step ④ from pouring. During concrete, the mud flows into the bottom of the embedded box along the joint gap.

进一步地,当进行步骤③时,在悬空楼板设计预留洞口的位置设置预留钢筋,当进行进行步骤⑦时,将预留钢筋与预埋盒搭接并焊接后浇筑混凝土。Further, when step 3 is performed, reserved steel bars are set at the positions of the reserved openings in the design of the suspended floor slab, and when step 7 is performed, the reserved steel bars are lapped and welded with the embedded box and then poured into concrete.

进一步地,所述步骤②中的止水环、预埋盒、及堵塞采用精密车床设备进行加工,确保尺寸允许偏差在0.3mm内。Further, the water stop ring, the pre-embedded box, and the plug in the step ② are processed with precision lathe equipment to ensure that the allowable deviation of the size is within 0.3mm.

进一步地,在所述步骤⑤中,除锈工作完成后,涂刷与悬空楼板的底部装饰面同色的防锈漆,防锈漆涂刷时应做到一底二面。Further, in the step ⑤, after the rust removal work is completed, the anti-rust paint of the same color as the bottom decorative surface of the suspended floor slab is painted, and the anti-rust paint should be painted on one bottom and two sides.

进一步地,进行所述一底二面时,涂刷底漆时应确保基层平整、干躁,中间漆涂刷工作应待底漆完全干躁后才能进行,面漆应采用喷涂方式进行,施工前应做好悬空楼板底部装饰面的成品保护工作,避免对悬空楼板的底部装饰面造成污染。Further, when carrying out the above-mentioned one bottom and two sides, the base layer should be smooth and dry when applying the primer, the intermediate paint should be painted after the primer is completely dry, and the top paint should be sprayed. The finished product protection of the bottom decorative surface of the suspended floor should be done well before, so as to avoid pollution to the bottom decorative surface of the suspended floor.

进一步地,进行所述步骤⑦时,取出顶盖后,对预埋盒的内部进行清理,然后采用步骤②中的堵塞与工作孔插装配合,堵塞伸出工作孔的端面涂刷与悬空楼板的底部装饰面同色的防锈漆。Further, when carrying out the step 7, after taking out the top cover, the interior of the embedded box is cleaned up, and then the blockage in step 2 is used to insert and cooperate with the working hole, and the end face brushing and the suspended floor slab extending out of the working hole are blocked. Anti-rust paint of the same color as the bottom decorative surface.

进一步地,所述步骤⑦中浇筑的混凝土强度比悬空楼板的浇筑混凝土强度高一个等级。Further, the strength of the concrete poured in the step (7) is one grade higher than the strength of the poured concrete of the suspended floor slab.

进一步地,所述步骤⑦中浇筑的混凝土为微膨胀细石混凝土。Further, the concrete poured in the step (7) is micro-expanded fine stone concrete.

与现有技术相比,本发明的有益效果包括:Compared with the prior art, the beneficial effects of the present invention include:

1. 本发明可广泛运用于高层、超高层建筑避难层及空中连廊施工中,通过提前安装预埋盒的方法,即保证了后续施工的顺利展开,又解决了洞口封堵及装饰装修收尾困难问题,该方法操作简便、实用,可以被广泛的运用。1. The present invention can be widely used in the construction of high-rise, super-high-rise building refuge floors and aerial corridors. By installing the pre-embedded box in advance, the smooth development of the subsequent construction is ensured, and the hole blocking and decoration finishing are solved. Difficult problems, the method is easy to operate, practical, and can be widely used.

2. 本发明将预埋盒提前预埋在悬空楼板内,后期进行洞口封堵时不用支设模板,可直接浇筑混凝土,且提前在预埋盒外侧底部及堵塞突出预埋盒的底面涂刷与悬空楼板的底部装饰同色的防锈漆,可以达到洞口封堵及装饰一体化施工的目的。2. In the present invention, the pre-embedded box is pre-buried in the suspended floor slab in advance. When the opening is blocked in the later stage, there is no need to set up a template, and the concrete can be directly poured, and the bottom surface of the outer side of the pre-embedded box and the bottom surface of the block protruding pre-embedded box are painted in advance. The anti-rust paint of the same color as the bottom decoration of the suspended floor can achieve the purpose of integrated construction of hole sealing and decoration.

3. 在浇筑悬空楼板前根据后续施工需求将预埋盒安装在对应位置,为防止杂物及水泥浆流入预埋盒内,按要求将顶盖缓缓嵌入预埋盒内,待后续施工完成后,预留洞口达到封堵条件时,在预埋盒外侧底部及堵塞的下端面涂刷与悬空楼板的底部装饰同色的防锈漆,最后完成预留洞口封堵工作。本发明易于施工,实用简单,节约成本和加快施工进度。3. Before pouring the suspended floor slab, install the embedded box in the corresponding position according to the subsequent construction requirements. In order to prevent sundries and cement slurry from flowing into the embedded box, slowly insert the top cover into the embedded box as required, and wait for the subsequent construction to be completed. Then, when the reserved hole reaches the blocking condition, the bottom of the outside of the embedded box and the blocked lower end surface are painted with the same color of anti-rust paint as the bottom decoration of the suspended floor, and finally the reserved hole is blocked. The invention is easy to construct, practical and simple, saves cost and accelerates construction progress.

具体实施方式Detailed ways

下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be described clearly and completely below. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

一种下部悬空结构楼板预留洞口的装饰一体化封堵方法,①施工准备,在悬空楼板混凝土浇筑前设计预留洞口的尺寸、位置和数量;A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure. (1) Construction preparation, design the size, position and quantity of the reserved openings before concrete pouring of the suspended floor slab;

②预制构件,根据步骤①中确定的预留洞口数量和尺寸,在工厂预制止水环、预埋盒、预埋盒的顶盖及预埋盒的堵塞,预埋盒的底部设置有工作孔;止水环、预埋盒、及堵塞采用精密车床设备进行加工,确保尺寸允许偏差在0.3mm内。②Prefabricated components, according to the number and size of the reserved openings determined in step ①, the water stop ring, the embedded box, the top cover of the embedded box and the blockage of the embedded box are pre-prepared in the factory, and the bottom of the embedded box is provided with a working hole ; Water stop ring, pre-embedded box, and plug are processed with precision lathe equipment to ensure that the allowable deviation of the size is within 0.3mm.

③安装预制构件,在悬空楼板混凝土浇筑前,将步骤②中的止水环预埋在步骤①中预留洞口设计位置的外周,并与楼板底筋进行定位焊接,完成止水环1预埋工作后,将步骤②中预制的预埋盒嵌入到止水环内周。在悬空楼板混凝土浇筑前,将顶盖盖在预埋盒上部,在顶盖与预埋盒之间的拼缝处粘贴透明胶布进行密封处理,防止步骤④浇筑混凝土时泥浆顺着拼缝缝隙流入到预埋盒底部。③Install the prefabricated components. Before the suspended floor concrete is poured, the water stop ring in step ② is pre-buried on the outer periphery of the design position of the opening reserved in step ①, and the positioning welding is performed with the floor bottom rib to complete the pre-embedding of the water stop ring 1. After the work, insert the prefabricated embedded box in step ② into the inner circumference of the water stop ring. Before the concrete of the suspended floor is poured, cover the top cover on the upper part of the embedded box, and paste the transparent tape on the joint between the top cover and the embedded box for sealing treatment, so as to prevent the mud from flowing into the joint gap when the concrete is poured in step ④. to the bottom of the embedded box.

④浇筑悬空楼板,将步骤③中的止水环和预埋盒与悬空楼板同步浇筑混凝土;④Pour the suspended floor, and pour the water stop ring and the embedded box in step ③ simultaneously with the suspended floor to pour concrete;

⑤悬空楼板底部装饰,步骤④中的悬空楼板浇筑后且达到设计强度后,拆除底模板,对预埋盒露出的底部进行除锈和喷漆。除锈工作完成后,涂刷与悬空楼板的底部装饰面同色的防锈漆,防锈漆涂刷时应做到一底二面。⑤ Decorate the bottom of the suspended floor. After the suspended floor in step ④ is poured and reaches the design strength, the bottom formwork is removed, and the exposed bottom of the embedded box is derusted and painted. After the rust removal work is completed, paint the anti-rust paint of the same color as the decorative surface of the bottom of the suspended floor.

进一步地,进行所述一底二面时,涂刷底漆时应确保基层平整、干躁,中间漆涂刷工作应待底漆完全干躁后才能进行,面漆应采用喷涂方式进行,施工前应做好悬空楼板底部装饰面的成品保护工作,避免对悬空楼板的底部装饰面造成污染。Further, when carrying out the above-mentioned one bottom and two sides, the base layer should be smooth and dry when applying the primer, the intermediate paint should be painted after the primer is completely dry, and the top paint should be sprayed. The finished product protection of the bottom decorative surface of the suspended floor should be done well before, so as to avoid pollution to the bottom decorative surface of the suspended floor.

⑥临时封堵,当预留洞口暂时不使用时,采用步骤②中的顶盖封堵在预埋盒的工作孔中;⑥ Temporary blocking, when the reserved hole is temporarily not used, the top cover in step ② is used to block the working hole of the embedded box;

⑦浇筑封堵,当预留洞口不再使用时,取出步骤⑥中的顶盖,采用步骤②中的堵塞与工作孔插装配合,然后进行混凝土浇筑。具体地,取出顶盖后,对预埋盒的内部进行清理,然后采用步骤②中的堵塞与工作孔插装配合,堵塞伸出工作孔的端面涂刷与悬空楼板的底部装饰面同色的防锈漆。⑦Pouring and sealing. When the reserved hole is no longer used, take out the top cover in step ⑥, use the plugging in step ② to insert and fit the working hole, and then carry out concrete pouring. Specifically, after taking out the top cover, clean the interior of the embedded box, and then use the plugging in step ② to insert and cooperate with the working hole, and the end face of the blocked working hole is painted with the same color as the bottom decorative surface of the suspended floor slab. Rust paint.

进一步地,当进行步骤③时,在悬空楼板设计预留洞口的位置设置预留钢筋,当进行进行步骤⑦时,将预留钢筋与预埋盒搭接并焊接后浇筑混凝土。预留洞口封堵浇筑的混凝土强度比悬空楼板的浇筑混凝土强度高一个等级,优选浇筑微膨胀细石混凝土。Further, when step 3 is performed, reserved steel bars are set at the positions of the reserved openings in the design of the suspended floor slab, and when step 7 is performed, the reserved steel bars are lapped and welded with the embedded box and then poured into concrete. The strength of the concrete poured by the reserved opening is one grade higher than that of the suspended floor slab, and the micro-expanded fine stone concrete is preferably poured.

本发明未详尽之处均为本领域技术人员所公知的常规技术手段。The non-exhaustive parts of the present invention are conventional technical means known to those skilled in the art.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (9)

1. A decoration integrated plugging method for reserved holes of a lower suspended structure floor slab is characterized by comprising the following steps:
firstly, construction preparation, wherein the size, the position and the number of reserved holes are designed before concrete pouring of the suspended floor;
prefabricating a member, prefabricating water stop rings, an embedded box, a top cover of the embedded box and blockage of the embedded box in a factory according to the number and the size of the reserved holes determined in the step I, wherein a working hole is formed in the bottom of the embedded box;
installing a prefabricated part, embedding the water stop ring in the step II in the periphery of the designed position of the reserved hole in the step I before concrete pouring of the suspended floor slab, welding the water stop ring with the bottom rib of the floor slab in a positioning manner, and embedding the embedded box prefabricated in the step II in the inner periphery of the water stop ring after the embedding work of the water stop ring 1 is completed;
fourthly, a suspended floor is poured, and concrete is poured synchronously with the water stop ring, the embedded box and the suspended floor in the third step;
fifthly, decorating the bottom of the suspended floor, removing the bottom template after the suspended floor in the step IV is poured and reaches the design strength, and removing rust and spraying paint on the exposed bottom of the embedded box;
temporarily plugging, and when the reserved hole is not used temporarily, plugging the top cover in the working hole of the embedded box by adopting the step II;
and seventhly, pouring and blocking, when the reserved hole is not used any more, taking out the top cover in the step (sixthly), inserting and matching the blocking and the working hole in the step (sixthly), and then pouring concrete.
2. The method of claim 1, wherein the method comprises the steps of: and step three, before the concrete of the suspended floor is poured, covering the top cover on the upper part of the embedded box, and pasting a transparent adhesive tape at the seam between the top cover and the embedded box for sealing treatment, so as to prevent the slurry from flowing into the bottom of the embedded box along the seam when the concrete is poured in the step four.
3. The method of claim 2, wherein the method comprises the steps of: and (c) when the step (c) is carried out, arranging a reserved steel bar at the position of the reserved hole on the suspended floor slab, and when the step (c) is carried out, overlapping the reserved steel bar with the embedded box, welding and then pouring concrete.
4. The method of any one of claims 1 to 3 for the decorative integrated plugging of a reserved opening in a lower suspended structure floor, wherein: and processing the water stop ring, the embedded box and the plug in the second step by using a precision lathe device to ensure that the allowable deviation of the size is within 0.3 mm.
5. The method of claim 4, wherein the method comprises the steps of: in the fifth step, after the rust removing work is finished, the rust-proof paint with the same color as the bottom decorative surface of the suspended floor slab is coated, and one bottom surface and two surfaces are formed when the rust-proof paint is coated.
6. The method of claim 5, wherein the method comprises the steps of: when the first surface and the second surface are carried out, the base layer is ensured to be flat and dry when the primer is coated, the intermediate paint coating work can be carried out after the primer is completely dry, the finish paint is sprayed, the finished product protection work of the bottom decorative surface of the suspended floor slab is carried out before construction, and the bottom decorative surface of the suspended floor slab is prevented from being polluted.
7. The method of integrally plugging the reserved hole in the lower suspended structure floor slab as claimed in any one of claims 1 to 3 and 5 to 6, wherein: and (c) when the top cover is taken out, cleaning the inside of the embedded box, and then adopting the plug-in fit with the working hole in the step (c) to brush the end face of the plug extending out of the working hole with the anti-rust paint with the same color as the bottom decorative surface of the suspended floor slab.
8. The method of claim 7 for integrally sealing a preformed opening in a lower suspended structure floor, wherein the method comprises: and step (c), the strength of the concrete poured in the step (c) is higher than that of the concrete poured in the suspended floor slab by one grade.
9. The method of claim 8, wherein the method comprises the steps of: and step (c), pouring concrete into the mold, wherein the concrete is micro-expanded fine stone concrete.
CN202210299719.4A 2022-03-25 2022-03-25 A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure Pending CN114658250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210299719.4A CN114658250A (en) 2022-03-25 2022-03-25 A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210299719.4A CN114658250A (en) 2022-03-25 2022-03-25 A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure

Publications (1)

Publication Number Publication Date
CN114658250A true CN114658250A (en) 2022-06-24

Family

ID=82032039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210299719.4A Pending CN114658250A (en) 2022-03-25 2022-03-25 A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure

Country Status (1)

Country Link
CN (1) CN114658250A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202969967U (en) * 2012-11-07 2013-06-05 中建三局第二建设工程有限责任公司 Temporary protecting device for once formed floor reserved hole
US9228689B1 (en) * 2013-09-13 2016-01-05 Roger Cline System and method for in-place vent pipe restoration
CN108166531A (en) * 2017-12-26 2018-06-15 中国建筑第七工程局有限公司 Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip
CN210177985U (en) * 2019-06-14 2020-03-24 淮安市宏茂金属制品有限公司 Material conveying port free of bar planting
CN111305566A (en) * 2020-03-27 2020-06-19 中建二局第二建筑工程有限公司 High-rise residential full-professional alternate construction floor water interception method
CN213745289U (en) * 2020-11-08 2021-07-20 广东电白建设集团有限公司 Through-floor pump pipe fixing system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202969967U (en) * 2012-11-07 2013-06-05 中建三局第二建设工程有限责任公司 Temporary protecting device for once formed floor reserved hole
US9228689B1 (en) * 2013-09-13 2016-01-05 Roger Cline System and method for in-place vent pipe restoration
CN108166531A (en) * 2017-12-26 2018-06-15 中国建筑第七工程局有限公司 Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip
CN210177985U (en) * 2019-06-14 2020-03-24 淮安市宏茂金属制品有限公司 Material conveying port free of bar planting
CN111305566A (en) * 2020-03-27 2020-06-19 中建二局第二建筑工程有限公司 High-rise residential full-professional alternate construction floor water interception method
CN213745289U (en) * 2020-11-08 2021-07-20 广东电白建设集团有限公司 Through-floor pump pipe fixing system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周凌峰;: "铝模施工质量及施工效率的提升策略", 智能城市, no. 17 *

Similar Documents

Publication Publication Date Title
CN103470067B (en) Transformation and construction method used for facing bare concrete of existing building outer wall
US5502941A (en) Method and apparatus for producing an ornamental concrete surface
CN101585205B (en) Method for producing and mounting moulded concrete anaglyph unit plate
CN111305566B (en) High-rise residential full-professional alternate construction floor water interception method
CN103046709A (en) Building construction method of inner wall surface
CN104018598A (en) A kind of exterior wall structure and construction installation method
CN106760535A (en) One kind exempts from plastering construction method using aluminum alloy mould plate casting concrete interior wall
CN105908889A (en) Construction method for prefabrication and reverse installation of cornice concrete decoration members of archaistic building
CN107190889A (en) Steel frame lightweight sandwich board integrated wall and its construction method
CN114658250A (en) A decoration integrated sealing method for reserved openings in a floor slab of a lower suspended structure
CN207176990U (en) A steel frame lightweight sandwich panel integrated wall
CN102900233B (en) Dual face raw slurry clean water concrete construction
CN113802845A (en) Synchronous reverse construction method for high-rise building outer wall decoration engineering and main body structure
CN109339355A (en) The construction method of the aluminium sheet roofing waterproofing node of structural slab is done using ALC plate
CN109763573B (en) Water stop ridge and construction method thereof
CN112815153A (en) Waterproof treatment method for root of through-wall or floor pipeline
CN201908415U (en) Wall decorative board layer structure
CN217924247U (en) Unit type clear water-imitating concrete skeleton partition wall structure
CN216921377U (en) Decoration integration plugging device of entrance to a cave is reserved to unsettled structure floor in lower part
CN113323396A (en) Integrated construction method for external wall of fabricated building
CN212405863U (en) Building facade decoration structure
CN106894542A (en) One kind exempts from plastering construction method using aluminum alloy mould plate casting concrete inner side of outer wall
CN212926756U (en) Waterproof joint structure of flue root
CN210086744U (en) Assembled piping shaft for high-rise building
CN1047425C (en) Attaching process for colour facing concrete board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220624