CN114329953A - Method for judging whether screw pile enters bearing stratum or not - Google Patents
Method for judging whether screw pile enters bearing stratum or not Download PDFInfo
- Publication number
- CN114329953A CN114329953A CN202111612072.8A CN202111612072A CN114329953A CN 114329953 A CN114329953 A CN 114329953A CN 202111612072 A CN202111612072 A CN 202111612072A CN 114329953 A CN114329953 A CN 114329953A
- Authority
- CN
- China
- Prior art keywords
- pile
- screw
- torque
- bearing stratum
- judging whether
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
技术领域technical field
本发明属于土木交通地基处理领域,尤其涉及一种判断地基处理时螺钉桩是否到达持力层的方法。The invention belongs to the field of civil and transportation foundation treatment, and in particular relates to a method for judging whether a screw pile reaches a bearing layer during foundation treatment.
背景技术Background technique
道路工程施工中,采用螺钉桩与原土形成复合地基,从而达到地基加固目的时,由于施工路线长,施工面积大,对于桩的数量要求比较多。同时由于地层地质结构的复杂性和不均匀分布,导致按照单桩承载力设计方法计算出每一根桩的具体长度是十分困难的,且需要投入很大的人力和时间。但是,在螺钉桩施工过程中,桩端若按要求达到良好的持力层并进入一定嵌固深度,不但可以增加单桩极限承载力,有效控制沉降,还能够保证路基整体稳定性。反之,若由于桩的长度过短,桩端未到达设计所选定的持力层,则会极大的降低路基实际承载力,让路基产生非正常沉降,甚至开裂。若由于桩的长度过长,进入持力层深度过大又无形中增加了桩身材料用量,增加工程成本。所以,准确地判断螺钉桩施工时桩端是否已经到达设计所选定的持力层是十分有必要的。In road engineering construction, screw piles and original soil are used to form a composite foundation to achieve the purpose of foundation reinforcement. Due to the long construction route and large construction area, there are more requirements for the number of piles. At the same time, due to the complexity and uneven distribution of the stratum geological structure, it is very difficult to calculate the specific length of each pile according to the single-pile bearing capacity design method, and it requires a lot of manpower and time. However, in the process of screw pile construction, if the pile end reaches a good bearing layer and enters a certain embedding depth as required, it can not only increase the ultimate bearing capacity of the single pile, effectively control the settlement, but also ensure the overall stability of the roadbed. On the other hand, if the length of the pile is too short and the end of the pile does not reach the bearing layer selected in the design, the actual bearing capacity of the subgrade will be greatly reduced, resulting in abnormal settlement or even cracking of the subgrade. If the length of the pile is too long and the depth into the bearing layer is too large, the material consumption of the pile body will be increased invisibly and the engineering cost will be increased. Therefore, it is very necessary to accurately judge whether the pile end has reached the bearing layer selected by the design during the construction of the screw pile.
目前在施工过程中判断螺钉桩桩端是否到达持力层的方法大多停留在经验层面,主要的判定方法有:At present, most of the methods for judging whether the pile end of the screw pile reaches the bearing layer during the construction process remain at the level of experience. The main judgment methods are:
1)利用地勘报告的地层情况估算出持力层位置;1) Estimate the position of the bearing layer by using the strata reported in the geological prospecting report;
2)对钻出岩屑或岩渣进行经验判定,是否达到持力岩层;2) Make an empirical judgment on whether the drilled cuttings or slag have reached the bearing rock formation;
3)以相邻钻孔的持力层深度作为判定依据,确定本桩持力层深度;3) The depth of the bearing layer of the pile is determined based on the depth of the bearing layer of the adjacent boreholes;
4)根据钻机振动剧烈程度(钻进难易程度)判定是否达到持力层;4) Determine whether the bearing layer is reached according to the degree of vibration of the drilling rig (difficulty of drilling);
5)看电流表,电流表窜动很利害,就说明钻不下去了,到达了持力层。5) Looking at the ammeter, it is very important for the ammeter to move, which means that the drilling can not go on, and it has reached the holding layer.
但是,这些判定方法均存在一定程度的缺陷:However, these judgment methods all have certain defects:
1)地质勘测不能做到一桩一勘测孔,岩层的高低起伏,复杂的风化情况,地勘报告不能准确的描绘;1) Geological survey cannot be done one by one. The undulating rock formations and complex weathering conditions cannot be accurately described in the geological survey report;
2)岩层中经常会有孤石存在,钻出的孤石岩块存在与持力层岩石相似的情况,容易产生误判而发生事故;2) There are often boulders in the rock formation, and the drilled boulder blocks are similar to the rock of the bearing layer, which is prone to misjudgment and accidents;
3)地层的走向一般存在倾角,加之倾角的多变性,导致相邻桩孔持力层深度不同;3) The strike of the stratum generally has a dip angle, and the variability of the dip angle leads to different depths of the bearing layers of adjacent pile holes;
4)钻机的振动剧烈程度和电流表数值窜动程度均是钻机操作者根据经验判断,具有较大的主观性。4) The severity of vibration of the drilling rig and the degree of movement of the ammeter value are judged by the operator of the drilling rig based on experience, which is highly subjective.
所以,目前工程实践中判别桩端是否到达持力层的方法均是不准确的。Therefore, the methods of judging whether the pile end has reached the bearing layer in current engineering practice are all inaccurate.
发明专利CN201510878558提供一种机械成孔混凝土灌注桩桩底持力层检测方法,包括下述步骤:①在大直径桩孔底部沿圆周方向均匀放置数个双检检波器;②使用电火花震源在桩孔底部中心部位人工激发弹性波;③利用浅层地震仪记录桩孔底双检检波器接收到的反射波;④分析研究这些波形记录进而判断桩孔底一定范围内是否存在溶洞、溶槽或破碎带等不良地质条件。该发明的方法不必在桩孔底部再施工进行地质勘察钻孔,使持力层检测成本大幅降低、检测速度快。Invention patent CN201510878558 provides a method for detecting the bearing layer at the bottom of a mechanically perforated concrete cast-in-situ pile, which includes the following steps: ① uniformly placing several dual detectors along the circumferential direction at the bottom of the large-diameter pile hole; ② using an electric spark source to The elastic wave is artificially excited at the center of the bottom of the pile hole; ③ The reflected waves received by the double detectors at the bottom of the pile hole are recorded by the shallow seismometer; ④ The waveform records are analyzed and studied to determine whether there are karst caves and troughs within a certain range at the bottom of the pile hole Or bad geological conditions such as broken zone. The method of the invention does not need to carry out geological survey drilling at the bottom of the pile hole, so that the detection cost of the bearing layer is greatly reduced and the detection speed is fast.
发明专利CN201711353299提供一种高压喷水摄像确定灌注桩持力层的方法,包括以下步骤:(1)在桩孔的正上方架设卷扬机,并将摄像组通过钢丝绳吊设在卷扬机上;(2)将高压水管延伸至并固定在摄像组上;(3)通过卷扬机将摄像组慢慢放入桩孔底部,并通过高压水管将高压水喷入桩孔底部,在桩孔底部形成清水段,通过摄像组观测桩孔底部的岩层情况,并记录下孔壁的情况;(4)通过卷扬机将摄像组取出。这样通过摄像组观测并记录到的桩孔底部的岩层更加直观,能够清楚的判断灌注桩是否全断面进入持力层。该本发明提供的高压喷水摄像确定灌注桩持力层的方法,用于检测灌注桩的桩孔的底部是否全断面达到了持力层,并且结构简单,判断更加直观。Invention patent CN201711353299 provides a method for determining the bearing layer of cast-in-place piles by high-pressure water spray camera, comprising the following steps: (1) erecting a hoist just above the pile hole, and hoisting the camera group on the hoist through a wire rope; (2) Extend the high-pressure water pipe to and fix it on the camera group; (3) slowly put the camera group into the bottom of the pile hole through the hoist, and spray the high-pressure water into the bottom of the pile hole through the high-pressure water pipe to form a clear water section at the bottom of the pile hole, and pass The camera group observes the rock formation at the bottom of the pile hole and records the hole wall condition; (4) The camera group is taken out through the hoist. In this way, the rock formation at the bottom of the pile hole observed and recorded by the camera group is more intuitive, and it can be clearly judged whether the cast-in-place pile enters the bearing layer in its full section. The method for determining the bearing layer of a cast-in-place pile provided by the high-pressure water spray camera provided by the present invention is used to detect whether the bottom of the pile hole of the cast-in-situ pile reaches the bearing layer in its full section, and has a simple structure and more intuitive judgment.
发明专利CN201810509888提供一种三维分析桩基持力层的方法,包括步骤s1:收集地勘资料及设计施工图;步骤s2:将地勘资料及设计施工图整合成一份CAD图;步骤s3:通过BIM软件结合地勘资料及设计施工图进行三维建模;步骤s4:在CAD图中截取任意桩,将该桩以及与其处于同一直线上的另外若干桩一起导入三维模型中的对应位置。步骤s5:在三维模型中对该桩以及与其处于同一直线上的另外若干桩进行剖面切割,得出其切割断面图,并计算出这一排桩进入持力层的实际深度。步骤s6:优化桩长。与现有技术相比,该发明操作简单,能够直观、快速的对设计的每一个桩桩长及持力层进深进行准确的分析并进行校正,从而节约了桩材。Invention patent CN201810509888 provides a three-dimensional analysis method for the bearing layer of pile foundation, including step s1: collecting geological survey data and design and construction drawings; step s2: integrating the geological survey data and design and construction drawings into a CAD drawing; step s3: passing the The BIM software performs 3D modeling in combination with geological survey data and design and construction drawings; step s4: intercept any pile in the CAD drawing, and import the pile and several other piles on the same line into the corresponding position in the 3D model. Step s5: Cut the pile and several other piles on the same line in the three-dimensional model to obtain the cut section diagram, and calculate the actual depth of the row of piles entering the bearing layer. Step s6: Optimize the pile length. Compared with the prior art, the invention has simple operation, and can intuitively and quickly perform accurate analysis and correction on each designed pile length and bearing layer depth, thereby saving pile materials.
这些方法为持力层的检测提供了一些思路,但这些方法依然不能及时准确地判断螺钉桩是否已经进入持力层。因此,本领域需要一种新的螺钉桩是否进入持力层的判定方法。These methods provide some ideas for the detection of the bearing layer, but these methods still cannot accurately judge whether the screw pile has entered the bearing layer in time. Therefore, there is a need in the art for a new method for judging whether the screw pile enters the bearing layer.
发明内容SUMMARY OF THE INVENTION
扭矩传感器,又称力矩传感器、扭力传感器、转矩传感器、扭矩仪,分为动态和静态两大类,其中动态扭矩传感器又可叫做转矩传感器、转矩转速传感器、非接触扭矩传感器、旋转扭矩传感器等。扭矩传感器是对各种旋转或非旋转机械部件上对扭转力矩感知的检测。扭矩传感器将扭力的物理变化转换成精确的电信号。Torque sensors, also known as torque sensors, torque sensors, torque sensors, and torque meters, are divided into two categories: dynamic and static. Dynamic torque sensors can also be called torque sensors, torque speed sensors, non-contact torque sensors, and rotational torque. sensors, etc. Torque sensors are the detection of torsional torque sensing on various rotating or non-rotating mechanical components. Torque sensors convert physical changes in torque into precise electrical signals.
本发明提供一种螺钉桩是否进入持力层的判定方法,所述方法包括在螺旋钻机动力头和螺杆交接处安装扭矩传感器,实时监测螺杆钻入过程中受到的扭矩,得到扭矩与深度的关系曲线,根据关系曲线的变化特征判断螺钉桩钻入过程中桩端是否到达持力层。The invention provides a method for judging whether a screw pile has entered a bearing layer. The method includes installing a torque sensor at the junction of an auger power head and a screw, monitoring the torque received during the drilling process of the screw in real time, and obtaining the relationship between the torque and the depth. According to the change characteristics of the relationship curve, it is judged whether the pile end reaches the bearing layer during the drilling process of the screw pile.
在一种具体的实施方式中,在得到所述关系曲线后,根据其变化特征并结合地质勘察资料来判断螺钉桩钻入过程中桩端是否到达持力层。In a specific embodiment, after the relationship curve is obtained, it is judged whether the pile end reaches the bearing layer during the drilling process of the screw pile according to its change characteristics and combined with geological survey data.
在一种具体的实施方式中,所述方法包括如下步骤:In a specific embodiment, the method includes the following steps:
步骤一、在螺旋钻机动力头和螺杆的连接处安装扭矩传感器;Step 1. Install a torque sensor at the connection between the auger power head and the screw;
步骤二、螺旋钻机就位,开始钻孔,获得扭矩T随深度h变化的实时数据;
步骤三、通过电子记录仪表得到T-h曲线;
步骤四、根据T-h曲线变化特征按区段划分土层,得到钻头实时所在土层;Step 4: Divide the soil layer by section according to the change characteristics of the T-h curve to obtain the soil layer where the drill bit is located in real time;
步骤五、根据钻头实时所在土层,结合工程地质勘察资料持力层的位置,判断是否到达持力层。Step 5: According to the real-time soil layer where the drill bit is located, combined with the position of the force-bearing layer in the engineering geological survey data, determine whether the force-bearing layer is reached.
本发明至少具备如下有益效果:本发明能够及时准确和直观地判断螺钉桩施工过程中,桩端是否到达持力层,保证地基加固处理质量,加快施工进度,在保证螺钉桩承载力的同时,有效控制桩的长度,降低成本。The invention at least has the following beneficial effects: the invention can timely, accurately and intuitively judge whether the pile end reaches the bearing layer during the construction of the screw pile, ensure the quality of the foundation reinforcement treatment, speed up the construction progress, and at the same time ensure the bearing capacity of the screw pile, Effectively control the length of the pile and reduce the cost.
附图说明Description of drawings
图1为本发明所述螺钉桩是否进入持力层的判定方法流程图。FIG. 1 is a flow chart of the method for determining whether the screw pile enters the bearing layer according to the present invention.
图2为一种具体实施方式中的T-h曲线图。FIG. 2 is a T-h curve diagram in a specific embodiment.
具体实施方式Detailed ways
针对当前螺钉桩施工中,桩端是否进入持力层的判断方法存在检测速度慢,受钻机操作者经验影响较大,精确度不高等缺陷。本发明提出了一种通过在螺旋钻机动力头和螺杆交接处安装扭矩传感器,实时监测螺杆钻入过程中受到的扭矩,得到扭矩—深度曲线,根据其变化特征并结合地质勘察资料,来判断螺钉桩钻入过程中桩端是否到达持力层的方法,使螺钉桩桩端是否到达持力层的判断更加科学、精确、及时和直观。In view of the current screw pile construction, the method of judging whether the pile end enters the bearing layer has the defects of slow detection speed, great influence by the experience of the drilling rig operator, and low accuracy. The invention proposes a method of installing a torque sensor at the junction of the auger power head and the screw, monitoring the torque received during the drilling process of the screw in real time, obtaining a torque-depth curve, and judging the screw according to its variation characteristics and combined with geological survey data. The method of whether the pile end reaches the bearing layer during the drilling process of the pile makes the judgment of whether the pile end of the screw pile reaches the bearing layer is more scientific, accurate, timely and intuitive.
工作原理:螺钉桩在钻入过程中,依靠螺旋钻机发动机产生的给进力和扭矩传递给特制螺杆,使螺杆对土体进行冲击和切削,进而达到钻进成孔的效果。钻进时,在一定的给进力下,同一土层内扭矩随着深度的增加而变化,变化趋势整体上呈线性关系;针对不同土层,由于物理特性及力学特性差异,扭矩必然会随着土层的改变而发生明显的变化,且不同土层内呈不同的线性关系。因此,可以通过分析扭矩随深度的变化趋势和土层的映射关系来实现地层特征辨识。Working principle: During the drilling process of the screw pile, the feed force and torque generated by the auger engine are transmitted to the special screw, so that the screw can impact and cut the soil, thereby achieving the effect of drilling into a hole. During drilling, under a certain feed force, the torque in the same soil layer changes with the increase of depth, and the change trend is linear as a whole; for different soil layers, due to the differences in physical and mechanical properties, the torque will inevitably change with the There are obvious changes with the change of the soil layer, and there are different linear relationships in different soil layers. Therefore, stratum feature identification can be realized by analyzing the variation trend of torque with depth and the mapping relationship of soil layers.
通过安装在螺旋钻机动力头和螺杆交接处的扭矩传感器,对钻进过程中螺杆受到扭矩实时监测,并通过电子量测记录仪表把它显示和记录下来,得到T-h曲线。在同一土层内,给进力一定时,扭矩随着钻进深度的变化特征是一致的,对于不同的土层,由于土体的物理特性和力学特性的不同,这种随着深度改变的变化特征会存在明显的不同。T-h曲线反映为:在同一土层深度范围内,扭矩T随着深度的变化趋势呈线性关系。不同土层深度的区段内,扭矩T随着深度的变化趋势存在明显的差异。因而可以通过读取T-h曲线的变化特征,划分不同土层区段,判断出钻进时钻头实时到达地表之下第几层土层,结合地质勘察资料持力层的大概位置,即可实时准确地判断螺钉桩钻入过程中,桩端是否到达了持力层。Through the torque sensor installed at the junction of the auger power head and the screw, the torque of the screw during the drilling process is monitored in real time, and it is displayed and recorded by the electronic measuring and recording instrument to obtain the T-h curve. In the same soil layer, when the feeding force is constant, the torque changes with the drilling depth are consistent. For different soil layers, due to the different physical and mechanical properties of the soil, this change with depth Variation characteristics can be significantly different. The T-h curve is reflected as follows: in the same soil depth range, the variation trend of torque T with depth is linear. In the sections with different soil depths, there are obvious differences in the variation trend of torque T with depth. Therefore, by reading the changing characteristics of the T-h curve, it can be divided into different soil layer sections, and it can be judged that the drill bit reaches the soil layer under the surface in real time when drilling, and combined with the approximate position of the bearing layer of the geological survey data, it can be accurately real-time. It can be judged whether the pile end has reached the bearing layer during the drilling process of the screw pile.
钻进过程中,给进力保持相对稳定,在这种条件下考察扭矩T随着深度的变化趋势,即考察T-h曲线可基本判别出持力层的位置,再结合工程的地质勘察资料持力层的大概位置,即可准确判断出该位置的持力层深度。例如图2所示位置的实施例中,给出了扭矩T随着深度h的变化趋势,图2中的多个黑点代表不同深度测得的实时扭矩值,由图2可见,在钻进深度为0~3.65米时,扭矩值上下浮动不大,拟合出的直线为一条向右略向上倾斜的直线,且相应为砂质黄土。而钻进深度为3.65米以上时,扭矩值急速增大,拟合出的直线为一条向右上方剧烈倾斜的直线,且相应为粗圆砾土。即可初步判断出该位置为持力层。再结合地质勘察资料,可进一步判断和确定螺钉桩钻入过程中桩端已经到达持力层。During the drilling process, the feeding force remains relatively stable. Under this condition, the variation trend of the torque T with the depth is examined, that is, the position of the bearing layer can be basically determined by examining the T-h curve, and the bearing force can be basically determined by combining the geological survey data of the project. The approximate position of the layer can accurately determine the depth of the bearing layer at this position. For example, in the embodiment shown in Fig. 2, the variation trend of the torque T with the depth h is given. The multiple black dots in Fig. 2 represent the real-time torque values measured at different depths. It can be seen from Fig. 2 that during drilling When the depth is 0 to 3.65 meters, the torque value does not fluctuate much up and down, and the fitted line is a straight line that slopes slightly upward to the right, and is corresponding to sandy loess. When the drilling depth is above 3.65 meters, the torque value increases rapidly, and the fitted straight line is a straight line that slopes sharply to the upper right, and the corresponding coarse round gravel soil. It can be preliminarily determined that the position is the holding layer. Combined with the geological survey data, it can be further judged and confirmed that the pile end has reached the bearing layer during the drilling process of the screw pile.
上述实施例仅为清楚地说明本发明技术方案所作的举例,而并非是对本发明的实施方式的限定。在不改变本发明基本构思和实质的情况下,任何其它等同技术特征的变换或修改,都应属于本发明权利要求的保护范围。The above embodiments are only examples for clearly illustrating the technical solutions of the present invention, and are not intended to limit the embodiments of the present invention. Under the condition that the basic idea and essence of the present invention are not changed, any transformation or modification of other equivalent technical features shall fall within the protection scope of the claims of the present invention.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111612072.8A CN114329953B (en) | 2021-12-27 | 2021-12-27 | Method for judging whether screw pile enters bearing layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111612072.8A CN114329953B (en) | 2021-12-27 | 2021-12-27 | Method for judging whether screw pile enters bearing layer |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114329953A true CN114329953A (en) | 2022-04-12 |
CN114329953B CN114329953B (en) | 2024-07-30 |
Family
ID=81013716
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111612072.8A Active CN114329953B (en) | 2021-12-27 | 2021-12-27 | Method for judging whether screw pile enters bearing layer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114329953B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855748A (en) * | 2022-05-24 | 2022-08-05 | 中交第四航务工程局有限公司 | Output torque-based cement mixing pile soil layer identification method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2001033027A2 (en) * | 1999-11-03 | 2001-05-10 | Halliburton Energy Services, Inc. | Method for optimizing the bit design for a well bore |
CN1955380A (en) * | 2006-06-12 | 2007-05-02 | 铁道第三勘察设计院 | Testing method of rock-soil engineering in-situ rotation touch investigating and its special equipment |
CN103255785A (en) * | 2012-02-15 | 2013-08-21 | 陈彦平 | Technology for performing foundation pile quality detection and geology survey by adopting single tube longitudinal wave method |
CN105653811A (en) * | 2016-01-11 | 2016-06-08 | 重庆市送变电工程有限公司 | Rocked depth determining method for high voltage transformer substation deep back filled region rotary excavation drilling |
JP2018112010A (en) * | 2017-01-12 | 2018-07-19 | 株式会社大林組 | Support layer arrival determination method and determination assist system |
CN109371974A (en) * | 2018-10-25 | 2019-02-22 | 广西建工集团基础建设有限公司 | A kind of PHC tubular pole implantation construction method suitable for hard geology |
CN111241621A (en) * | 2020-01-13 | 2020-06-05 | 西南交通大学 | A method for evaluating the stability of high-strength pile composite foundation under embankment |
-
2021
- 2021-12-27 CN CN202111612072.8A patent/CN114329953B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2001033027A2 (en) * | 1999-11-03 | 2001-05-10 | Halliburton Energy Services, Inc. | Method for optimizing the bit design for a well bore |
CN1955380A (en) * | 2006-06-12 | 2007-05-02 | 铁道第三勘察设计院 | Testing method of rock-soil engineering in-situ rotation touch investigating and its special equipment |
CN103255785A (en) * | 2012-02-15 | 2013-08-21 | 陈彦平 | Technology for performing foundation pile quality detection and geology survey by adopting single tube longitudinal wave method |
CN105653811A (en) * | 2016-01-11 | 2016-06-08 | 重庆市送变电工程有限公司 | Rocked depth determining method for high voltage transformer substation deep back filled region rotary excavation drilling |
JP2018112010A (en) * | 2017-01-12 | 2018-07-19 | 株式会社大林組 | Support layer arrival determination method and determination assist system |
CN109371974A (en) * | 2018-10-25 | 2019-02-22 | 广西建工集团基础建设有限公司 | A kind of PHC tubular pole implantation construction method suitable for hard geology |
CN111241621A (en) * | 2020-01-13 | 2020-06-05 | 西南交通大学 | A method for evaluating the stability of high-strength pile composite foundation under embankment |
Non-Patent Citations (5)
Title |
---|
刘先珊;张同乐;牛万保;: "不同地层比功阈值优化的统计方法及其应用", 土木建筑与环境工程, no. 02, pages 58 - 64 * |
周双勇等: "利用旋挖机实时钻进参数判定持力层的方法", 《重庆大学学报》, vol. 40, no. 11, pages 56 - 63 * |
董辉等: "兰新客运专线戈壁路基CFG桩加固试验研究", 《土木工程》, vol. 28, no. 02, pages 50 - 53 * |
许明;刘先珊;周泽宏;张林;牛万保;张同乐;: "旋挖钻机钻进入岩判定与地层识别方法", 中南大学学报(自然科学版), no. 12, 26 December 2017 (2017-12-26), pages 3344 - 3349 * |
许明;刘先珊;周泽宏;张林;牛万保;张同乐;: "旋挖钻机钻进入岩判定与地层识别方法", 中南大学学报(自然科学版), no. 12, pages 3344 - 3349 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855748A (en) * | 2022-05-24 | 2022-08-05 | 中交第四航务工程局有限公司 | Output torque-based cement mixing pile soil layer identification method |
Also Published As
Publication number | Publication date |
---|---|
CN114329953B (en) | 2024-07-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107589471B (en) | A kind of Railway Tunnel Synthetic Geological Prediction Ahead of Construction method | |
Wang et al. | In-situ digital profiling of soil to rock strength from drilling process monitoring of 200 m deep drillhole in loess ground | |
CN107503361B (en) | Bedding rock slope weak layer stress monitoring and surrounding rock reinforcing method | |
RU2688714C1 (en) | Device and method of determining, during drilling, coefficient of fortress according to protodyakov of the tunnel roof rock based on the sound level meter | |
CN110221341A (en) | A kind of constructing tunnel unfavorable geology advanced prediction method | |
WO2020057363A1 (en) | Observation device and observation method for absolute convergence amount of surface of roadway | |
CN101581234A (en) | Comprehensive underground test method for deformation and damage of terranes of mining top plate and mining bottom plate of coal bed | |
CN111077583B (en) | Construction activation dual parameter monitoring system and monitoring method | |
CN114329953A (en) | Method for judging whether screw pile enters bearing stratum or not | |
Li et al. | Identifying the geological interface of the stratum of tunnel granite and classifying rock mass according to drilling energy theory | |
CN215919159U (en) | Digital drilling device | |
CN117552483B (en) | Test method for foundation reinforcement influence range of dynamic compaction treatment | |
CN110579194B (en) | Field test method and application of fracture position of lateral basic top rock beam in gob-side roadway | |
CN117233861A (en) | Tunnel three-dimensional geological visualization comprehensive forecasting method | |
CN110067268A (en) | The improper discontinuous varying depth measuring equipment in stratum in a kind of prefabricated pile penetration process based on sound emission | |
CN116988786A (en) | Three-dimensional ground stress measuring method for underground mine | |
CN115707858A (en) | Geological exploration drilling quality detection method | |
CN110630320B (en) | Overburden rock isolation grouting filling position determination method based on drilling injection flow measurement | |
CN114814977B (en) | Accurate exploration method for rock mass structural surface and weak local area in soil-rock dual foundation pit slope | |
CN113477978A (en) | Digital drilling device and disease detection and repair method | |
Song et al. | A method for determining the overburden failure height of coal mining based on the change of drilling speed and the leakage of sectional water injection in underground upward bolehole | |
CN105203563A (en) | Detection method of canal lining quality in south-to-north water diversion project | |
CN117449903B (en) | Stope bottom plate damage depth monitoring method | |
CN118835981B (en) | A sensor-based intelligent monitoring method for reinforced concrete pile pouring | |
CN112761712B (en) | A method for detecting small structures in coal mining face based on drilling through bed drainage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |