CN114108678B - Anchor rod static pressure pile construction method for reinforcing transformer substation foundation - Google Patents

Anchor rod static pressure pile construction method for reinforcing transformer substation foundation Download PDF

Info

Publication number
CN114108678B
CN114108678B CN202111398108.7A CN202111398108A CN114108678B CN 114108678 B CN114108678 B CN 114108678B CN 202111398108 A CN202111398108 A CN 202111398108A CN 114108678 B CN114108678 B CN 114108678B
Authority
CN
China
Prior art keywords
pile
foundation
water tank
transformer substation
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111398108.7A
Other languages
Chinese (zh)
Other versions
CN114108678A (en
Inventor
方俊齐
徐文哲
孙正竹
史佳炳
吕书栋
王聪燚
李雯婷
吕蕾
陈诚
倪宇翔
张航
徐淳信
高旭呈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Zhejiang Electric Power Transmission and Transforming Engineering Co
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Zhejiang Electric Power Transmission and Transforming Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Zhejiang Electric Power Transmission and Transforming Engineering Co filed Critical State Grid Corp of China SGCC
Priority to CN202111398108.7A priority Critical patent/CN114108678B/en
Publication of CN114108678A publication Critical patent/CN114108678A/en
Application granted granted Critical
Publication of CN114108678B publication Critical patent/CN114108678B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method of an anchor rod static pressure pile for reinforcing a transformer substation foundation, and relates to the field of transformer substation foundation reinforcing methods. The number of the electric wires and the electrified equipment in the transformer substation is large, the large economic loss can be brought to the foundation reinforcement construction of the transformer substation when the power is cut off, and potential safety hazards are brought to the power grid. The invention reserves pile holes and pre-buried anchor rods when the transformer substation equipment foundation pile cap is constructed, a counterweight water tank is arranged on the foundation pile cap, a pressure sensor is arranged at the bottom of the water tank, a static pile press is installed after counterweight is injected, a pile is pressed in place by the static pile press, and finally, the pile holes are poured by C30 micro-expansion concrete, so that the pile and the foundation are firmly combined together, the pile can bear upper load, and the foundation reinforcement effect is achieved. According to the method, the water injection counterweight water tank is arranged on the foundation pile cap, so that the foundation pile cap is not arched in the pile pressing process, the normal operation of substation equipment in the static pile construction process can be effectively ensured, and the counterweight increase and decrease can be conveniently realized.

Description

一种变电站地基加固的锚杆静压桩施工方法Construction method of anchor static pressure pile for substation foundation reinforcement

技术领域technical field

本发明涉及变电站地基加固施工方法领域,尤其涉及一种变电站地基加固的锚杆静压桩施工方法。The invention relates to the field of substation foundation reinforcement construction methods, in particular to a construction method of anchor static pressure piles for substation foundation reinforcement.

背景技术Background technique

变电站扩建施工中,周边带电导线及带电设备较多,针对变电站地基加固的施工情况变得复杂,如果停电施工,不仅被批准的时长较短,而且会带来较大的经济损失,给电网安全稳定带来隐患,另外,变电站内部空间有限,大型施工设备无法进入,为施工带来不便。During the substation expansion construction, there are many live wires and live equipment around, and the construction situation for substation foundation reinforcement becomes complicated. If the construction is interrupted, not only will the approval period be shorter, but it will also bring greater economic losses. Stability brings hidden dangers. In addition, the internal space of the substation is limited, and large construction equipment cannot enter, which brings inconvenience to construction.

锚杆静压桩施工技术可方便地应用于相对较小的空间地基加固,已经广泛应用于老厂或用于普通建筑物改造工程中的地基加固,但由于变电站内带电设备众多,涉及到变电站所在地的整个社会区域的电力供应,如果出现因施工而发生电网故障,将会造成极大的损失,而施工时,相对较小的变电站地基的上拱变形都有可能会导致断电和设备出现故障而停止工作。The anchor static pressure pile construction technology can be easily applied to relatively small space foundation reinforcement. It has been widely used in old factories or for foundation reinforcement in ordinary building renovation projects. However, due to the large number of live equipment in the substation, it involves substation If there is a power grid failure due to construction in the power supply of the entire social area where it is located, it will cause great losses. During construction, the upward arch deformation of the foundation of a relatively small substation may cause power outages and equipment failures. malfunction and stop working.

发明内容Contents of the invention

本发明要解决的技术问题和提出的技术任务是对现有技术方案进行完善与改进,提供一种变电站地基加固的锚杆静压桩施工方法,以保障施工时变电站设备的正常运行为目的。为此,本发明采取以下技术方案。The technical problem to be solved and the technical task proposed by the present invention are to perfect and improve the existing technical solutions, and to provide a construction method of anchor static pressure piles for substation foundation reinforcement, with the purpose of ensuring the normal operation of substation equipment during construction. For this reason, the present invention takes the following technical solutions.

一种变电站地基加固的锚杆静压桩施工方法,包括以下步骤:A construction method of anchor static pressure piles for substation foundation reinforcement, comprising the following steps:

1)变电站设备基础承台施工,每个设计桩孔位置预留桩孔和预埋锚杆;1) For substation equipment foundation cap construction, pile holes and pre-embedded anchors are reserved for each designed pile hole position;

2)在基础承台上面布置多个水箱,水箱与每个预留桩孔保持有施工所需的间距;2) Multiple water tanks are arranged on the foundation cap, and the distance between the water tank and each reserved pile hole is maintained for construction;

3)在每个水箱的底部四角及中心布置压力传感器,并把压力传感器连接到终端配重显示装置;3) Arrange pressure sensors at the four corners and the center of the bottom of each water tank, and connect the pressure sensors to the terminal counterweight display device;

4)在水箱中注水作为配重以提供静压桩所需的抗拔力,保证压桩过程中基础承台不会拱起;4) Inject water into the water tank as a counterweight to provide the pullout force required by the static pressure pile, so as to ensure that the foundation cap will not be arched during the pile pressing process;

5)根据带电设备及导线的安全带电距离,确定桩段长度;5) Determine the length of the pile section according to the safe charging distance of live equipment and conductors;

6)通过预埋锚杆安装压桩反力架,完成静压桩机的安装;6) Install the pile pressure reaction force frame through the pre-embedded anchor rod to complete the installation of the static pile machine;

7)把桩段吊装到位后静压到位,进行深度及压力值记录;7) After the pile section is hoisted in place, the static pressure is in place, and the depth and pressure value are recorded;

8)根据最终设计要求增加若干桩段,把后桩段吊装到位后需与前桩段焊接,并根据需要增加水箱配重;8) Add some pile sections according to the final design requirements, after the rear pile section is hoisted in place, it needs to be welded with the front pile section, and the water tank counterweight should be added as needed;

9)当压桩力到达1.5倍压桩的设计荷载时,拆除静压桩机,在压桩顶部焊接锚筋;9) When the pile pressure reaches 1.5 times the design load of the pile, remove the static pile machine and weld the anchor bars on the top of the pile;

10)用C30微膨胀混凝土浇筑桩孔,使桩与基础牢固地结合在一起,桩便能承受上部荷载,起到地基加固的效果。10) Pour the pile hole with C30 micro-expansion concrete, so that the pile and the foundation are firmly combined, and the pile can bear the upper load and achieve the effect of foundation reinforcement.

本方法根据变电站内带电设备及导线的安全带电距离,确定桩段长度,确保搬运吊装过程中不会触碰设备,提升安全性;通过在基础承台上面布置多个注水配重水箱可方便地增加对基础承台的压力,保证压桩过程中基础承台不拱起,保证静压桩施工时避免对带电设备的影响,能有效保障静压桩施工时变电站设备的正常运行,在水箱底部布置压力传感器,可方便地根据施工的进度对应地实现配重增减的量化检测,以方便配重增减;采用水作配重,增加及卸载方便快捷、施工便捷、荷载增加可控、并且可以重复利用。This method determines the length of the pile section according to the safe charging distance of the live equipment and wires in the substation, so as to ensure that the equipment will not be touched during the handling and hoisting process, and the safety is improved; by arranging multiple water injection counterweight water tanks on the foundation cap, it can be conveniently Increase the pressure on the foundation cap, ensure that the foundation cap does not arch during the pile pressing process, and ensure that the impact on the live equipment is avoided during the construction of the static pressure pile, which can effectively ensure the normal operation of the substation equipment during the construction of the static pressure pile. The arrangement of pressure sensors can conveniently realize the quantitative detection of the increase or decrease of the counterweight according to the progress of the construction, so as to facilitate the increase or decrease of the counterweight; the use of water as the counterweight is convenient and fast for adding and unloading, convenient for construction, and the increase of load is controllable. Can be reused.

作为优选技术手段:所述的水箱采用橡胶材质。易携带、可重复利用,成本低。As an optimal technical means: the water tank is made of rubber. Easy to carry, reusable, and low cost.

作为优选技术手段:所述的基础承台的四角布置有所述的水箱,水箱与预留孔距离不小于1米。该位置和距离可方便静压桩施工操作。As an optimal technical means: the four corners of the foundation cap are arranged with the water tank, and the distance between the water tank and the reserved hole is not less than 1 meter. This position and distance can facilitate the static pressure pile construction operation.

作为优选技术手段:步骤4)中,水箱中注水时采用水泵连接透明网纹管注水,水源首先采用因基坑开挖产生的地下水。实现现场水资源的有效利用,降低成本。As an optimal technical means: in step 4), when injecting water into the water tank, use a water pump connected to a transparent reticulated pipe to inject water, and the water source first uses groundwater generated by excavation of the foundation pit. Realize the effective use of on-site water resources and reduce costs.

作为优选技术手段:用C30微膨胀混凝土浇筑桩孔完成后,水箱中的水作为混凝土养护用水。实现水的综合利用。As an optimal technical means: after the pile hole is poured with C30 micro-expansion concrete, the water in the water tank is used as concrete maintenance water. Realize the comprehensive utilization of water.

有益效果:本方法根据变电站内带电设备及导线的安全带电距离,确定桩段长度,确保搬运吊装过程中不会触碰设备,提升安全性;通过在基础承台上面布置多个注水配重水箱可方便地增加对基础承台的压力,保证压桩过程中基础承台不拱起,保证静压桩施工时避免对带电设备的影响,能有效保障静压桩施工时变电站设备的正常运行,在水箱底部布置压力传感器,可方便地根据施工的进度对应地实现配重增减的量化检测,以方便配重增减;采用水作配重,增加及卸载方便快捷、施工便捷、荷载增加可控、并且可以重复利用。Beneficial effects: This method determines the length of the pile section according to the safe charging distance of live equipment and wires in the substation, so as to ensure that the equipment will not be touched during the handling and hoisting process, and the safety is improved; by arranging multiple water injection counterweight water tanks on the foundation cap It can easily increase the pressure on the foundation cap, ensure that the foundation cap does not arch during the pile pressing process, and ensure that the impact on the live equipment is avoided during the static pressure pile construction, and can effectively ensure the normal operation of the substation equipment during the static pressure pile construction. The pressure sensor is arranged at the bottom of the water tank, which can conveniently realize the quantitative detection of the increase or decrease of the counterweight according to the progress of the construction, so as to facilitate the increase or decrease of the counterweight; using water as the counterweight, the addition and unloading are convenient and quick, the construction is convenient, and the load can be increased. control and can be reused.

附图说明Description of drawings

图1是本发明流程示意图。Fig. 1 is a schematic flow chart of the present invention.

图2是本发明实例中桩孔及水箱分布示意图。Fig. 2 is a schematic diagram of the distribution of pile holes and water tanks in the example of the present invention.

图3是本发明中静压桩机工作示意图。Fig. 3 is a working diagram of the static pile machine in the present invention.

图中:1、基础承台;2、水箱;3、桩孔;4、静压桩机;5、锚杆;6、桩段。In the figure: 1. Foundation cap; 2. Water tank; 3. Pile hole; 4. Static pile driver; 5. Anchor rod; 6. Pile section.

具体实施方式Detailed ways

以下结合说明书附图对本发明的技术方案做进一步的详细说明。The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings.

如图1-3所示,一种变电站地基加固的锚杆静压桩施工方法,其过程包括以下步骤:As shown in Figure 1-3, a construction method of anchor static pressure piles for substation foundation reinforcement, the process includes the following steps:

S1:变电站设备基础承台1施工,每个设计桩孔3位置预留桩孔3和预埋锚杆5;S1: Construction of substation equipment foundation cap 1, reserve pile holes 3 and pre-embedded anchor rods 5 at each designed pile hole 3 position;

S2:在基础承台1上面布置水箱2,水箱2与每个预留桩孔3保持有施工所需的间距;S2: Arrange the water tank 2 on the foundation cap 1, and keep the distance required for construction between the water tank 2 and each reserved pile hole 3;

S3:在每个水箱2的底部四角及中心布置压力传感器,并把压力传感器连接到终端配重显示装置;S3: arrange pressure sensors at the four corners and the center of the bottom of each water tank 2, and connect the pressure sensors to the terminal counterweight display device;

S4:在水箱2中注水作为配重以提供静压桩所需的抗拔力,保证压桩过程中基础承台1不会拱起;S4: inject water into the water tank 2 as a counterweight to provide the pullout force required by the static pressure pile, and ensure that the foundation cap 1 will not be arched during the pile pressing process;

S5:根据带电设备及导线的安全带电距离,确定桩段6长度;S5: Determine the length of pile section 6 according to the safe charging distance of live equipment and conductors;

S6:通过预埋的锚杆5安装压桩反力架,完成静压桩机4的安装;S6: install the pile pressure reaction force frame through the pre-embedded anchor rod 5, and complete the installation of the static pile machine 4;

S7:把桩段6吊装到位后静压到位,进行深度及压力值记录;S7: After the pile section 6 is hoisted in place, the static pressure is in place, and the depth and pressure value are recorded;

S8:根据最终设计要求增加压桩,把后桩段6吊装到位后需与前桩段6焊接,并根据需要增减水箱2配重;S8: Add pressure piles according to the final design requirements. After hoisting the rear pile section 6 into place, it needs to be welded with the front pile section 6, and increase or decrease the counterweight of the water tank 2 as required;

S9:当压桩力到达1.5倍压桩的设计荷载时,拆除静压桩机4,在压桩顶部焊接锚筋;S9: When the pile pressure reaches 1.5 times the design load of the pile, remove the static pile machine 4, and weld the anchor bars on the top of the pile;

S10:用C30微膨胀混凝土浇筑桩孔3,使桩与基础牢固地结合在一起,桩便能承受上部荷载,起到地基加固的效果。S10: Pour the pile hole 3 with C30 micro-expansion concrete, so that the pile and the foundation are firmly combined, and the pile can bear the upper load and achieve the effect of foundation reinforcement.

对每个桩孔3均按以上步骤S6到S10的过程操作。For each stake hole 3, operate according to the process of the above steps S6 to S10.

如图2所示为本实例的基础承台1施工范围,包括左部桩孔区域和右部桩孔区域,右部桩孔按纵横均4排列,桩间距为1.5米,4个水箱2布置于右部桩孔区域的4个角部,水箱2与桩孔3距离为1米,右部桩孔区域的中间设有1个水箱2,水箱2与桩孔3距离为1米。左部桩孔区域按横2纵3排2列桩孔3,其中左列每2个桩孔3之间布置一个水箱2,右列布置2个水箱2,且2个水箱2间隔2个桩孔3,水箱2与桩孔3之间的距离均为1米。As shown in Figure 2, the construction scope of the foundation cap 1 of this example includes the left pile hole area and the right pile hole area. The right pile holes are arranged in 4 vertically and horizontally, the pile spacing is 1.5 meters, and 4 water tanks are arranged. At the four corners of the right pile hole area, the distance between the water tank 2 and the pile hole 3 is 1 meter, and a water tank 2 is arranged in the middle of the right pile hole area, and the distance between the water tank 2 and the pile hole 3 is 1 meter. The pile hole area on the left is divided into 2 rows and 3 rows and 2 columns of pile holes 3, in which a water tank 2 is arranged between every 2 pile holes 3 in the left row, and 2 water tanks 2 are arranged in the right row, and the 2 water tanks 2 are separated by 2 piles The hole 3, the distance between the water tank 2 and the pile hole 3 are all 1 meter.

本实例中,水箱2采用橡胶材质。易携带、不容易撞击损坏,可重复利用,成本低。In this example, the water tank 2 is made of rubber. Easy to carry, not easy to be damaged by impact, reusable, and low cost.

步骤S4中,水箱2中注水时采用水泵连接透明网纹管注水,水源首先采用因基坑开挖产生的地下水,。实现现场水资源的有效利用,降低成本。In step S4, when filling water into the water tank 2, a water pump is used to connect the transparent reticulated pipe for water injection, and the water source is firstly groundwater generated by the excavation of the foundation pit. Realize the effective use of on-site water resources and reduce costs.

用C30微膨胀混凝土浇筑桩孔3完成后,水箱2中的水作为混凝土养护用水。实现水的综合利用。After the pile hole 3 is poured with C30 micro-expansion concrete, the water in the water tank 2 is used as concrete maintenance water. Realize the comprehensive utilization of water.

本方法根据变电站内带电设备及导线的安全带电距离,确定桩段6长度,确保搬运吊装过程中不会触碰设备,提升安全性;通过在基础承台1上面布置多个注水配重水箱2可方便地增加对基础承台1的压力,保证压桩过程中基础承台1不拱起,保证静压桩施工时避免对带电设备的影响,能有效保障静压桩施工时变电站设备的正常运行,在水箱2底部布置压力传感器,可方便地根据施工的进度对应地实现配重增减的量化检测,以方便配重增减;采用水作配重,增加及卸载方便快捷、施工便捷、荷载增加可控、并且可以重复利用。This method determines the length of the pile section 6 according to the safe charging distance of the live equipment and wires in the substation, so as to ensure that the equipment will not be touched during the handling and hoisting process, and the safety is improved; by arranging multiple water injection counterweight water tanks 2 on the foundation cap 1 It can easily increase the pressure on the foundation cap 1, ensure that the foundation cap 1 does not arch during the pile pressing process, ensure that the impact on the live equipment is avoided during the static pressure pile construction, and can effectively ensure the normal operation of the substation equipment during the static pressure pile construction. Operation, the pressure sensor is arranged at the bottom of the water tank 2, which can conveniently realize the quantitative detection of the increase or decrease of the counterweight according to the progress of the construction, so as to facilitate the increase or decrease of the counterweight; using water as the counterweight, the addition and unloading are convenient and quick, and the construction is convenient and convenient. The load increase is controllable and reusable.

以上图1-3所示的一种变电站地基加固的锚杆静压桩施工方法是本发明的具体实施例,已经体现出本发明突出的实质性特点和显著进步,可根据实际的使用需要,在本发明的启示下,对其进行形状、结构等方面的等同修改,均在本方案的保护范围之列。The anchor static pressure pile construction method shown in the above Figures 1-3 is a specific embodiment of the present invention, which has demonstrated the outstanding substantive features and significant progress of the present invention, and can be used according to actual needs. Under the enlightenment of the present invention, equivalent modifications to it in terms of shape, structure, etc., all fall within the scope of protection of this proposal.

Claims (5)

1. A construction method of an anchor rod static pressure pile for reinforcing a transformer substation foundation is characterized by comprising the following steps:
1) Constructing a transformer substation equipment foundation pile cap (1), and reserving pile holes (3) and pre-buried anchor rods (5) at the positions of each designed pile hole (3);
2) A plurality of water tanks (2) are arranged on the foundation pile cap (1), and the water tanks (2) and each reserved pile hole (3) are kept with a space required by construction;
3) Pressure sensors are arranged at four corners and the center of the bottom of each water tank (2) and are connected to a terminal counterweight display device;
4) The water is injected into the water tank (2) to be used as a counterweight to provide the pulling resistance required by the static pile, so that the foundation pile cap (1) is prevented from arching in the pile pressing process;
5) Determining the length of the pile section (6) according to the safe charging distance of the charging equipment and the lead;
6) Installing a pile pressing reaction frame through an embedded anchor rod (5) to finish the installation of a static pile pressing machine (4);
7) Hoisting the pile section (6) in place, then carrying out static pressure in place, and recording depth and pressure values;
8) Adding a plurality of pile segments (6) according to the final design requirement, hoisting the rear pile segment (6) in place, welding with the front pile segment (6), and adding the counterweight of the water tank (2) according to the requirement;
9) When the pile pressing force reaches 1.5 times of the design load of the pile pressing, removing the static pile pressing machine (4), and welding anchor bars at the top of the pile pressing;
10 And (3) pouring pile holes (3) by using C30 micro-expansion concrete, so that the piles and the foundation are firmly combined together, the piles can bear upper load, and the foundation reinforcement effect is achieved.
2. The construction method of the anchor rod static pressure pile for reinforcing the foundation of the transformer substation according to claim 1, wherein the construction method comprises the following steps: the water tank (2) is made of rubber.
3. The construction method of the anchor rod static pressure pile for reinforcing the foundation of the transformer substation according to claim 1, wherein the construction method comprises the following steps: the four corners of the basic bearing platform (1) are provided with the water tank (2), and the distance between the water tank (2) and the reserved hole is not less than 1 meter.
4. The construction method of the anchor rod static pressure pile for reinforcing the foundation of the transformer substation according to claim 1, wherein the construction method comprises the following steps: in the step 4), a water pump is used for connecting a transparent reticulate pattern pipe for water injection when water is injected into the water tank (2), and the water source firstly adopts groundwater generated by excavation of a foundation pit.
5. The construction method of the anchor rod static pressure pile for reinforcing the foundation of the transformer substation according to claim 1, wherein the construction method comprises the following steps: and after the C30 micro-expansion concrete pouring pile hole (3) is finished, water in the water tank (2) is used as water for concrete curing.
CN202111398108.7A 2021-11-19 2021-11-19 Anchor rod static pressure pile construction method for reinforcing transformer substation foundation Active CN114108678B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111398108.7A CN114108678B (en) 2021-11-19 2021-11-19 Anchor rod static pressure pile construction method for reinforcing transformer substation foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111398108.7A CN114108678B (en) 2021-11-19 2021-11-19 Anchor rod static pressure pile construction method for reinforcing transformer substation foundation

Publications (2)

Publication Number Publication Date
CN114108678A CN114108678A (en) 2022-03-01
CN114108678B true CN114108678B (en) 2023-08-22

Family

ID=80440250

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111398108.7A Active CN114108678B (en) 2021-11-19 2021-11-19 Anchor rod static pressure pile construction method for reinforcing transformer substation foundation

Country Status (1)

Country Link
CN (1) CN114108678B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0580098A1 (en) * 1992-07-21 1994-01-26 Bernfried Dr.-Ing. Sudbrack Method and device for pile foundation
CN101644063A (en) * 2009-09-15 2010-02-10 河海大学 Loading and unloading method for water bag load of PCC pile
WO2012149670A1 (en) * 2011-04-30 2012-11-08 安徽省高速公路控股集团有限公司 Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
WO2015154132A1 (en) * 2014-04-07 2015-10-15 Nxt Enterprise Ltd Building system
CN105780823A (en) * 2016-03-14 2016-07-20 彭宝安 Foldable ballast water tank for pile foundation static load test
CN107090860A (en) * 2017-05-09 2017-08-25 广东省建筑科学研究院集团股份有限公司 A kind of shallow foundation rectifying of leaned building ruggedized construction and its construction method
CN111576921A (en) * 2020-05-21 2020-08-25 苏州第一建筑集团有限公司 Dismantling and rebuilding construction method for existing foundation building in rail transit protection area
JP2020148042A (en) * 2019-03-14 2020-09-17 株式会社技研製作所 Pile press-in system and pile press-in method
KR102162941B1 (en) * 2019-12-19 2020-10-07 지에스건설 주식회사 Pile pressing method and controlling method for pile pressing apparatus

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0580098A1 (en) * 1992-07-21 1994-01-26 Bernfried Dr.-Ing. Sudbrack Method and device for pile foundation
CN101644063A (en) * 2009-09-15 2010-02-10 河海大学 Loading and unloading method for water bag load of PCC pile
WO2012149670A1 (en) * 2011-04-30 2012-11-08 安徽省高速公路控股集团有限公司 Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
WO2015154132A1 (en) * 2014-04-07 2015-10-15 Nxt Enterprise Ltd Building system
CN105780823A (en) * 2016-03-14 2016-07-20 彭宝安 Foldable ballast water tank for pile foundation static load test
CN107090860A (en) * 2017-05-09 2017-08-25 广东省建筑科学研究院集团股份有限公司 A kind of shallow foundation rectifying of leaned building ruggedized construction and its construction method
JP2020148042A (en) * 2019-03-14 2020-09-17 株式会社技研製作所 Pile press-in system and pile press-in method
KR102162941B1 (en) * 2019-12-19 2020-10-07 지에스건설 주식회사 Pile pressing method and controlling method for pile pressing apparatus
CN111576921A (en) * 2020-05-21 2020-08-25 苏州第一建筑集团有限公司 Dismantling and rebuilding construction method for existing foundation building in rail transit protection area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
锚杆静力压桩的设计与施工;潘天森;《建筑技术》;19921231(第01期);全文 *

Also Published As

Publication number Publication date
CN114108678A (en) 2022-03-01

Similar Documents

Publication Publication Date Title
CN201250407Y (en) Embedded steel wale
CN102127974B (en) Design and construction method of additional cellar under existing building
CN101824800B (en) Method for construction of bridge cast-in-situ pre-stressed concrete continuous beam
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN103195085B (en) Downward story-adding basement and construction method thereof
CN106149768B (en) A kind of float Structure and its construction method of the underground structure of fender post combination Guan Liang
CN105951869B (en) A kind of construction method of the not reserved construction joint Tower Crane Foundation by Steel Lattice Column of underground garage
CN102864788A (en) Method for underpinning reinforced bridge pile foundation by bear-type static pressure cluster pile
CN207700185U (en) A kind of retaining wall device for manual hole digging pile
CN104912569A (en) Draw shaft treatment method
CN104652288A (en) Construction system of cast-in-situ large-tonnage box girder for soft soil foundation and construction method
CN102535525B (en) Structure and method utilizing anti-floating anchor rods to support underground raft plates
CN103882883B (en) Tower crane and garage frame post share a foundation construction method
CN109854266B (en) Non-excavation type pipe jacking prestressed beam construction method
CN114108678B (en) Anchor rod static pressure pile construction method for reinforcing transformer substation foundation
CN207685879U (en) A kind of lift stake reinforcing bearing platform construction platform
CN209779640U (en) foundation pit supporting pile top crown beam construction structure
CN204475195U (en) The construction system of the cast-in-place large-tonnage box beam of soft foundation
CN209339172U (en) Novel pile plate composite foundation
CN206562613U (en) A kind of mini pile suspension roof support structure
CN109555130B (en) Middle plate of subway main body structure and temporary supporting structure and construction method
CN210104759U (en) Anti type underground structure that floats
CN209260748U (en) A stepped tower crane foundation
CN103147446A (en) Visible-beam and hidden-rib lattice anchor cable foundation pit supporting structure
CN210459229U (en) Support assembled in deep basal pit and trade and prop construction frock

Legal Events

Date Code Title Description