[go: up one dir, main page]

CN113957758B - Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic - Google Patents

Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic Download PDF

Info

Publication number
CN113957758B
CN113957758B CN202111209208.0A CN202111209208A CN113957758B CN 113957758 B CN113957758 B CN 113957758B CN 202111209208 A CN202111209208 A CN 202111209208A CN 113957758 B CN113957758 B CN 113957758B
Authority
CN
China
Prior art keywords
filler
pipeline
pipe
jacking
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111209208.0A
Other languages
Chinese (zh)
Other versions
CN113957758A (en
Inventor
和海芳
张劲泉
周雨龙
刘红义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Research Institute of Highway Ministry of Transport
Original Assignee
Research Institute of Highway Ministry of Transport
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Research Institute of Highway Ministry of Transport filed Critical Research Institute of Highway Ministry of Transport
Priority to CN202111209208.0A priority Critical patent/CN113957758B/en
Publication of CN113957758A publication Critical patent/CN113957758A/en
Application granted granted Critical
Publication of CN113957758B publication Critical patent/CN113957758B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/006Foundations for pavings made of prefabricated single units
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种不中断交通条件下既有桥梁桥路过渡段加固方法,具体步骤如下S1:测量放样;S2:工作井施工;S3:接收井施工;S4:顶进准备;S5:顶进施工,将替代填料的管道贯通路基;S6:加固处理。本发明所述的不中断交通条件下既有桥梁桥路过渡段加固方法,利用替代填料的管道所具有的良好的承载性能和变形能力,可以有效减小路基内填料的沉降,同时桥梁桥路过渡段通过替代填料的管道替代了部分路基内的填料,因此可以有效减少填料的自重从而降低地基上的载荷进而减少地基的沉降,并且通过上述方法不需要将路面全部挖开进行替代填料的管道的填埋工作,能够在不中断交通的条件下进行,并且还可以避免由于路基被挖开而引起的其他问题。

Figure 202111209208

The invention discloses a method for strengthening the transition section of an existing bridge and road without interrupting traffic. The specific steps are as follows: S1: measuring and setting out; S2: working well construction; S3: receiving well construction; S4: jacking preparation; S5: jacking In the construction, the pipeline that replaces the filler will pass through the subgrade; S6: Reinforcement treatment. The method for strengthening the transition section of an existing bridge, bridge, and road without interruption of traffic according to the present invention can effectively reduce the settlement of the filler in the subgrade by utilizing the good bearing performance and deformation capacity of the pipe replacing the filler, and at the same time, the bridge, bridge and road can be effectively reduced. In the transition section, the filling in part of the roadbed is replaced by the pipeline that replaces the filling, so the self-weight of the filling can be effectively reduced, the load on the foundation and the settlement of the foundation can be reduced, and the above method does not need to excavate all the road surface to replace the filling pipeline. The landfill work can be carried out without interrupting traffic and other problems caused by the excavation of the roadbed can also be avoided.

Figure 202111209208

Description

一种不中断交通条件下既有桥梁桥路过渡段加固方法A Reinforcing Method for Transition Section of Existing Bridges and Roads Without Interrupting Traffic

技术领域technical field

本发明涉及桥梁技术领域,更具体地说,本发明涉及一种不中断交通条件下既有桥梁桥路过渡段加固方法。The present invention relates to the technical field of bridges, and more particularly, the present invention relates to a method for strengthening the transition sections of existing bridges and roads without interrupting traffic conditions.

背景技术Background technique

桥路过渡段是道路与桥梁(涵洞)相连接的过渡部分,其在强度、刚度、材料方面有别于路基,是公路工程中的薄弱部位,不均匀沉降是该部位的主要病害,极易导致桥头跳车,严重影响行车安全和舒适性,控制填料沉降和减小地基沉降是解决桥路过渡段不均匀沉降的主要方法,但是控制填料用量只适用于在建的新桥,对于已经建成的桥梁则无法再进行填料用量的调整,在对既有桥梁进行填料控制的时候则需要封路对桥梁桥路过渡段进行全面改造。因此,有必要提出一种不中断交通条件下既有桥梁桥路过渡段加固方法,以至少部分地解决现有技术中存在的问题。The bridge-road transition section is the transitional part connecting the road and the bridge (culvert). It is different from the roadbed in terms of strength, stiffness and material. It is a weak part in highway engineering. It causes the bridge head to jump, which seriously affects the driving safety and comfort. Controlling the settlement of the filling and reducing the settlement of the foundation are the main methods to solve the uneven settlement of the bridge-road transition section, but the control of the amount of the filling is only applicable to the new bridge under construction. The amount of fillers can no longer be adjusted for the bridges of the existing bridges. When the filler control is performed on the existing bridges, it is necessary to close the road and conduct a comprehensive transformation of the bridge-road transition section. Therefore, it is necessary to propose a method for strengthening the transition sections of existing bridges and roads without interrupting traffic, so as to at least partially solve the problems existing in the prior art.

发明内容SUMMARY OF THE INVENTION

在发明内容部分中引入了一系列简化形式的概念,这将在具体实施方式部分中进一步详细说明。本发明的发明内容部分并不意味着要试图限定出所要求保护的技术方案的关键特征和必要技术特征,更不意味着试图确定所要求保护的技术方案的保护范围。A series of concepts in simplified form have been introduced in the Summary section, which are described in further detail in the Detailed Description section. The Summary of the Invention section of the present invention is not intended to attempt to limit the key features and essential technical features of the claimed technical solution, nor is it intended to attempt to determine the protection scope of the claimed technical solution.

为至少部分地解决上述问题,本发明提供了一种不中断交通条件下既有桥梁桥路过渡段加固方法,具体步骤如下:In order to at least partially solve the above problems, the present invention provides a method for strengthening the transition section of existing bridges and roads without interrupting traffic, and the specific steps are as follows:

S1:测量放样;S1: measurement stakeout;

S2:工作井施工;S2: Work well construction;

S3:接收井施工;S3: receiving well construction;

S4:顶进准备;S4: jacking preparation;

S5:顶进施工,将替代填料的管道贯通路基;S5: jacking construction, the pipeline that replaces the filler will pass through the subgrade;

S6:加固处理。S6: Reinforcement processing.

优选的是,步骤S1中还包括如下步骤:Preferably, step S1 also includes the following steps:

S101:根据既有桥梁桥路过渡段现场的平面布置和空间位置,测放出工作井、接收井位置及替代填料的管道的位置和走向;S101: According to the plane layout and spatial position of the existing bridge and bridge-road transition section site, measure and release the position and direction of the working well, the receiving well and the pipeline that replaces the filler;

S102:设置临时水准点,测设出工作井、接收井的开挖范围及深度。S102: Set a temporary leveling point, and measure the excavation range and depth of the working well and the receiving well.

优选的是,步骤S2中还包括如下步骤:Preferably, step S2 also includes the following steps:

S201:根据地质情况及现场条件,在确定的工作井位置和范围内进行开挖,并采用支护钢板进行即时支护;S201: According to the geological conditions and site conditions, excavate within the determined position and scope of the working well, and use supporting steel plates for immediate support;

S202:待开挖至设计标高时,用混凝土浇筑底板和壁板,同时确定混凝土和钢板垫块的厚度以满足顶进要求。S202: When the excavation reaches the design elevation, use concrete to pour the bottom plate and wall plate, and at the same time determine the thickness of the concrete and steel plate pads to meet the jacking requirements.

优选的是,步骤S3中还包括如下步骤:Preferably, step S3 also includes the following steps:

S301:根据地质情况及现场条件,在确定的接收井位置和范围内进行开挖,并采用支护钢板进行即时支护;S301: According to the geological conditions and site conditions, excavate within the determined location and range of the receiving well, and use supporting steel plates for immediate support;

S302:待开挖至设计标高时,用混凝土浇筑底板和壁板,满足强度和稳定性要求即可。S302: When the excavation reaches the design elevation, the bottom plate and wall plate shall be poured with concrete to meet the requirements of strength and stability.

优选的是,步骤S4中还包括如下步骤:Preferably, step S4 also includes the following steps:

S401:在工作井内设置顶管机导轨和液压千斤顶;S401: Set up pipe jacking machine guide rails and hydraulic jacks in the working well;

S402:在替代填料的管道的最前端安装掘进机,根据填土性质、覆盖层厚度等进行掘进速度和顶进速度的选择和设置。S402: Install a roadheader at the front end of the pipeline that replaces the filling, and select and set the driving speed and the jacking speed according to the properties of the filling and the thickness of the covering layer.

优选的是,步骤S5中还包括如下步骤:Preferably, step S5 also includes the following steps:

S501:待准备工作完成后,开始掘进、顶管,替代填料的管道顶进时应根据地面监测数据及时调整顶进参数;S501: After the preparatory work is completed, start excavation and pipe jacking. When the pipe replacing the filler is jacked, the jacking parameters should be adjusted in time according to the ground monitoring data;

S502:在掘进过程中,将所掘填料输出到地面;S502: During the excavation process, output the excavated filler to the ground;

S503:在第一节替代填料的管道顶进后,与下一节替代填料的管道拼装从而延长替代填料的管道的长度,继而进行下一节顶进,周而复始,直至掘进机从工作井内穿过路基到达接收井内,将掘进机吊起回收;S503: After the first section of the pipe with the substitute filler is jacked in, it is assembled with the pipe of the next section of the substitute filler to extend the length of the pipe with the substitute filler, and then the next section is jacked, and the cycle is repeated until the roadheader passes through the working well When the roadbed reaches the receiving well, the roadheader is lifted and recovered;

S504:与此同时,紧随掘进机后的替代填料的管道埋设在工作井与接收井之间,且需把第一节替代填料的管道的端部从路基内推出到接收井内一定长度,整个顶进施工结束,替代填料的管道全线贯通。S504: At the same time, the pipeline of the replacement filler following the roadheader is buried between the working well and the receiving well, and the end of the first section of the pipeline of the replacement filler needs to be pushed out from the roadbed to the receiving well for a certain length. The jacking construction is over, and the pipelines replacing the fillers are all run through.

优选的是,步骤S6中还包括如下步骤:Preferably, step S6 also includes the following steps:

S601:待贯通完成后,在替代填料的管道和路基的填料之间进行灌浆处理,以加强替代填料的管道与填料的耦合;S601: After the penetration is completed, grouting is performed between the pipe of the substitute filler and the filler of the roadbed to strengthen the coupling between the pipe of the substitute filler and the filler;

S602:最后封堵替代填料的管道的端口,将路面恢复。S602: Finally, the port of the pipeline for replacing the filler is blocked to restore the road surface.

优选的是,步骤S501中还包括:初始顶进速度宜控制在10~20mm/min;正常顶进期间,顶进速度宜控制在20~30mm/min。Preferably, step S501 further includes: the initial jacking speed should be controlled at 10-20 mm/min; during normal jacking, the jacking speed should be controlled at 20-30 mm/min.

优选的是,所述替代填料的管道为钢波纹管;Preferably, the pipeline for replacing the filler is a steel corrugated pipe;

由于钢波纹管的厚度较薄,需进行处理来进行顶进,在钢波纹管内部沿轴向对称布置若干根加强钢管以提高钢波纹管的轴线刚度,加强钢管与钢波纹管可拆卸连接;Due to the thin thickness of the steel corrugated pipe, it needs to be processed for jacking. Several reinforcing steel pipes are arranged symmetrically in the axial direction inside the steel corrugated pipe to improve the axial rigidity of the steel corrugated pipe, and the reinforcing steel pipe and the steel corrugated pipe can be detachably connected;

每节钢波纹管长度根据具体情况设定,一般可设置为2~3m。The length of each section of steel corrugated pipe is set according to the specific situation, generally can be set to 2 ~ 3m.

优选的是,所述钢波纹管之间通过连接件进行连接,Preferably, the steel corrugated pipes are connected by connecting pieces,

所述钢波纹管的端部设置有若干个爪扣,所述爪扣沿所述钢波纹管的径向向外凸起,若干个所述爪扣在所述钢波纹管的端部形成与所述钢波纹管的波峰相适应的环扣,相邻的两个所述钢波纹管通过所述环扣与所述连接件连接;The end of the steel bellows is provided with a number of claw buckles, the claw buckles protrude outward along the radial direction of the steel bellows, and a plurality of the claw buckles are formed at the end of the steel bellows to form a a ring buckle adapted to the wave crest of the steel corrugated pipe, and two adjacent steel corrugated pipes are connected to the connecting piece through the ring buckle;

所述连接件包括管体,所述管体内设有阻尼管,所述阻尼管的外壁通过簧片与所述管体的内壁连接;所述簧片包括具有初始和拉伸两种状态的弹片,所述管体的外壁上设置有插接卡头和顶进卡头,所述插接卡头与所述管体的一端形成插入端,所述顶进卡头设置在所述管体的另一端,所述插接卡头和所述顶进卡头之间形成压合腔,所述相互插接的两个钢波纹管的所述环扣均卡接在所述压合腔内并压缩变形,所述插入端插入在先顶进的所述钢波纹管的末端,并且所述管体的端部与所述加强钢管抵接,在后顶进的所述钢波纹管内的所述加强钢管与所述顶进卡头抵接。The connecting piece includes a tube body, a damping tube is arranged in the tube body, and the outer wall of the damping tube is connected with the inner wall of the tube body through a reed; the reed includes an elastic leaf with two states of initial and tension , the outer wall of the pipe body is provided with a plug-in chuck and a push-in clamp, the plug-in clamp and one end of the pipe body form an insertion end, and the push-in clamp is arranged at the end of the pipe body At the other end, a press-fit cavity is formed between the plug-in clip and the push-in clip, and the loops of the two steel bellows that are plugged into each other are clamped in the press-fit cavity and Compression deformation, the insertion end is inserted into the end of the steel corrugated pipe that is pushed forward first, and the end of the pipe body is in contact with the reinforced steel pipe, and the end of the steel corrugated pipe that is pushed backward The reinforcing steel pipe is in contact with the jacking chuck.

相比现有技术,本发明至少包括以下有益效果:Compared with the prior art, the present invention at least includes the following beneficial effects:

1、本发明所述的不中断交通条件下既有桥梁桥路过渡段加固方法,利用替代填料的管道所具有的良好的承载性能和变形能力,可以有效减小路基内填料的沉降,同时桥梁桥路过渡段通过替代填料的管道替代了部分路基内的填料,因此可以有效减少填料的自重从而降低地基上的载荷进而减少地基的沉降,并且通过上述方法不需要将路面全部挖开进行替代填料的管道的填埋工作,能够在不中断交通的条件下进行,并且还可以避免由于路基被挖开而引起的其他问题。1. The method for strengthening the transition section of existing bridges and roads under the condition of uninterrupted traffic according to the present invention can effectively reduce the settlement of the fillers in the roadbed by using the good bearing performance and deformation capacity of the pipelines that replace the fillers, and at the same time the bridges In the bridge-road transition section, the filling in part of the roadbed is replaced by the pipe that replaces the filling, so the self-weight of the filling can be effectively reduced, the load on the foundation and the settlement of the foundation can be reduced, and the above method does not need to excavate all the road surface to replace the filling. The landfill work of the pipeline can be carried out without interrupting the traffic, and other problems caused by the excavation of the roadbed can also be avoided.

本发明所述的不中断交通条件下既有桥梁桥路过渡段加固方法,本发明的其它优点、目标和特征将部分通过下面的说明体现,部分还将通过对本发明的研究和实践而为本领域的技术人员所理解。For the method for strengthening the transition section of existing bridges and roads without interruption of traffic according to the present invention, other advantages, objectives and features of the present invention will be partly reflected in the following description, and partly will also be based on the research and practice of the present invention. understood by those skilled in the art.

附图说明Description of drawings

附图用来提供对本发明的进一步理解,并且构成说明书的一部分,与本发明的实施例一起用于解释本发明,并不构成对本发明的限制。在附图中:The accompanying drawings are used to provide a further understanding of the present invention, and constitute a part of the specification, and are used to explain the present invention together with the embodiments of the present invention, and do not constitute a limitation to the present invention. In the attached image:

图1为本发明所述的加固方法的工艺流程图。FIG. 1 is a process flow diagram of the reinforcement method according to the present invention.

图2为本发明所述的加固方法施工后的桥梁桥路过渡段的剖视图。FIG. 2 is a cross-sectional view of a bridge-bridge-road transition section after the reinforcement method according to the present invention is constructed.

图3为本发明所述的加固方法施工中的剖视图。3 is a cross-sectional view of the reinforcement method according to the present invention during construction.

图4为本发明所述的加固方法中钢波纹管的结构示意图。FIG. 4 is a schematic structural diagram of a steel corrugated pipe in the reinforcement method according to the present invention.

图5为本发明所述的加固方法中加强钢管的结构示意图。FIG. 5 is a schematic structural diagram of a reinforced steel pipe in the reinforcement method according to the present invention.

图6为本发明所述的加固方法中连接件的局部剖视图。FIG. 6 is a partial cross-sectional view of the connecting piece in the reinforcing method according to the present invention.

图7为本发明所述的加固方法中连接件的插入端与钢波纹管插接的结构示意图。FIG. 7 is a schematic structural diagram of the insertion end of the connector and the steel corrugated pipe in the reinforcing method according to the present invention.

图8为本发明所述的加固方法中两个钢波纹管连接时的剖视图。FIG. 8 is a cross-sectional view of two steel corrugated pipes being connected in the reinforcement method according to the present invention.

图中:1替代填料的管道、2主梁、3支座、4桥台、5路基、6路面、7边坡、8支护钢板、9土体、10钢波纹管波峰、11钢波纹管波谷、12加强钢管、13连接件、14爪扣、15管体、16阻尼管、17簧片、18插接卡头、19顶进卡头、20插入端、21压合腔。In the picture: 1 pipeline for filling replacement, 2 main beam, 3 support, 4 bridge abutment, 5 subgrade, 6 road surface, 7 side slope, 8 supporting steel plate, 9 soil mass, 10 steel corrugated pipe crest, 11 steel corrugated pipe Valley, 12 reinforced steel pipe, 13 connector, 14 claw buckle, 15 tube body, 16 damping tube, 17 reed, 18 plug-in chuck, 19 push-in chuck, 20 insertion end, 21 press-fit cavity.

具体实施方式Detailed ways

下面结合附图以及实施例对本发明做进一步的详细说明,以令本领域技术人员参照说明书文字能够据以实施。The present invention will be further described in detail below with reference to the accompanying drawings and embodiments, so that those skilled in the art can implement the invention with reference to the description.

应当理解,本文所使用的诸如“具有”、“包含”以及“包括”术语并不排除一个或多个其它元件或其组合的存在或添加。It should be understood that terms such as "having", "comprising" and "including" as used herein do not exclude the presence or addition of one or more other elements or combinations thereof.

如图1-图8所示,本发明提供了一种不中断交通条件下既有桥梁桥路过渡段加固方法,具体步骤如下:As shown in FIG. 1-FIG. 8, the present invention provides a method for strengthening the transition section of an existing bridge and road without interrupting traffic. The specific steps are as follows:

S1:测量放样;S1: measurement stakeout;

S2:工作井施工;S2: Work well construction;

S3:接收井施工;S3: receiving well construction;

S4:顶进准备;S4: jacking preparation;

S5:顶进施工,将替代填料的管道1贯通路基;S5: jacking construction, the pipeline 1 that replaces the filler will pass through the road foundation;

S6:加固处理。S6: Reinforcement processing.

上述技术方案的工作原理:在进行施工前首先需要对桥梁桥路过渡段周围的土质进行采样及测量,以确定挖掘深度和挖掘范围,并对工作井和接收井进行放样规划;然后按照规划对工作井和接收井进行施工挖掘,将掘进机、顶进设备和替代填料的管道1设置在工作井内,准备齐全后便可以开始对路基进行挖掘并将替代填料的管道1随着掘进机顶入路基,直至替代填料的管道1贯穿路基为止,之后将替代填料的管道1与路基的填料之间进行浇筑加固处理后,封装替代填料的管道1的两端并将路面复原即可。The working principle of the above technical scheme: before construction, it is necessary to sample and measure the soil around the transition section of the bridge, bridge and road to determine the excavation depth and excavation range, and plan the working well and the receiving well; The working well and the receiving well are excavated, and the roadheader, jacking equipment and the pipeline 1 of the substitute filler are set in the work well. After the preparation is complete, the excavation of the roadbed can be started and the pipeline 1 of the substitute filler can be jacked in with the roadheader. Subgrade until the pipe 1 of the substitute filler penetrates the subgrade, and then pouring and reinforcement treatment is performed between the pipe 1 of the substitute filler and the filler of the roadbed, and then the two ends of the pipe 1 of the substitute filler are encapsulated and the road surface can be restored.

上述技术方案的有益效果:利用替代填料的管道1所具有的良好的承载性能和变形能力,可以有效减小路基内填料的沉降,同时桥梁桥路过渡段通过替代填料的管道1替代了部分路基内的填料,因此可以有效减少填料的自重从而降低地基上的载荷进而减少地基的沉降,并且通过上述方法不需要将路面全部挖开进行替代填料的管道1的填埋工作,能够在不中断交通的条件下进行,并且还可以避免由于路基被挖开而引起的其他问题。The beneficial effects of the above technical solutions: the good bearing performance and deformation capacity of the pipeline 1 that replaces the filler can effectively reduce the settlement of the filler in the roadbed, and at the same time, the transition section of the bridge and bridge is replaced by the pipeline 1 that replaces the filler. Part of the roadbed Therefore, the self-weight of the filler can be effectively reduced, thereby reducing the load on the foundation and reducing the settlement of the foundation, and the above method does not need to excavate all the road surface for the filling of the pipeline 1 to replace the filler, which can be used without interruption of traffic. It can also be carried out under the conditions of excavation, and other problems caused by the excavation of the roadbed can also be avoided.

在一个实施例中,步骤S1中还包括如下步骤:In one embodiment, step S1 further includes the following steps:

S101:根据既有桥梁桥路过渡段现场的平面布置和空间位置,测放出工作井、接收井位置及替代填料的管道1的位置和走向;S101: According to the plane layout and spatial position of the existing bridge and bridge transition section site, measure and release the position and direction of the working well, the receiving well and the pipeline 1 for replacing the filler;

S102:设置临时水准点,测设出工作井、接收井的开挖范围及深度。S102: Set a temporary leveling point, and measure the excavation range and depth of the working well and the receiving well.

上述技术方案的工作原理及有益效果:在进行测量放样的时候首先需要对既有桥梁桥路过渡段现场的平面布置和空间位置进行测算,并对工作井和接收井的位置进行放样规划,同时对替代填料的管道1的位置、长度及走向进行规划,随后设置临时水准点,并根据现场的环境、土质、地质计算出工作井和接收井的开挖范围和深度,以便后续的施工中可以根据土质和地质对工作井和接收井进行即时支护防止塌方。The working principle and beneficial effects of the above technical solutions: when measuring and setting out, firstly, it is necessary to measure and calculate the layout and spatial position of the existing bridge, bridge and road transition section site, and plan the position of the working well and the receiving well. Plan the position, length and direction of the pipeline 1 to replace the filler, then set up temporary benchmarking points, and calculate the excavation range and depth of the working well and the receiving well according to the site environment, soil quality and geology, so that the subsequent construction can be carried out. According to the soil quality and geology, the working well and the receiving well are immediately supported to prevent landslides.

在一个实施例中,步骤S2中还包括如下步骤:In one embodiment, step S2 also includes the following steps:

S201:根据地质情况及现场条件,在确定的工作井位置和范围内进行开挖,并采用支护钢板8进行即时支护;S201: According to the geological conditions and site conditions, excavate within the determined position and scope of the working well, and use the support steel plate 8 for immediate support;

S202:待开挖至设计标高时,用混凝土浇筑底板和壁板,同时确定混凝土和钢板垫块的厚度以满足顶进要求。S202: When the excavation reaches the design elevation, use concrete to pour the bottom plate and wall plate, and at the same time determine the thickness of the concrete and steel plate pads to meet the jacking requirements.

步骤S3中还包括如下步骤:Step S3 also includes the following steps:

S301:根据地质情况及现场条件,在确定的接收井位置和范围内进行开挖,并采用支护钢板8进行即时支护;S301: According to the geological conditions and site conditions, excavate within the determined location and range of the receiving well, and use the support steel plate 8 for immediate support;

S302:待开挖至设计标高时,用混凝土浇筑底板和壁板,满足强度和稳定性要求即可。S302: When the excavation reaches the design elevation, the bottom plate and wall plate shall be poured with concrete to meet the requirements of strength and stability.

上述技术方案的工作原理及有益效果:根据放样和规划的范围对工作井和接收井进行挖掘,同时对侧壁的土体9通过支护钢板8进行支护,避免在挖掘过程中出现塌方造成人员伤亡和设备损坏,在挖至设计标高时,对底板和壁板用混凝土进行浇筑,避免塌方,因为工作井中需要架设相关设备,所以需要在底部铺设钢板垫块,并确保钢板垫块的厚度可以满足设备需求,接收井仅用于设备的接收,所以浇筑的强度和稳定性满足相关地质情况和现场条件的要求即可。The working principle and beneficial effects of the above technical solutions: according to the scope of stakeout and planning, the working well and the receiving well are excavated, and the soil body 9 of the side wall is supported by the supporting steel plate 8 at the same time, so as to avoid landslides during the excavation process. In case of casualties and equipment damage, when digging to the design level, pour concrete for the bottom plate and wall plate to avoid collapse. Because related equipment needs to be erected in the working well, it is necessary to lay steel plate pads at the bottom and ensure the thickness of the steel plate pads. It can meet the equipment requirements, and the receiving well is only used for receiving equipment, so the strength and stability of the pouring can meet the requirements of the relevant geological conditions and site conditions.

在一个实施例中,步骤S4中还包括如下步骤:In one embodiment, step S4 also includes the following steps:

S401:在工作井内设置顶管机导轨和液压千斤顶;S401: Set up pipe jacking machine guide rails and hydraulic jacks in the working well;

S402:在替代填料的管道1的最前端安装掘进机,根据填土性质、覆盖层厚度等进行掘进速度和顶进速度的选择和设置。S402: Install a roadheader at the foremost end of the pipeline 1 that replaces the filling, and select and set the driving speed and the jacking speed according to the properties of the filling and the thickness of the covering layer.

上述技术方案的工作原理及有益效果:在进行准备工作的时候需要将顶管机导轨和液压千斤顶提前在工作井内进行安装,然后将第一节替代填料的管道1的前端安装在掘进机上,并根据填土性质和覆盖层厚度等测算出掘进速度和顶进速度。The working principle and beneficial effects of the above technical solutions: during the preparation work, it is necessary to install the guide rail of the pipe jacking machine and the hydraulic jack in the working well in advance, and then install the front end of the first section of the pipeline 1 that replaces the filler on the roadheader, and According to the properties of the filling and the thickness of the covering layer, the excavation speed and jacking speed are calculated.

在一个实施例中,步骤S5中还包括如下步骤:In one embodiment, step S5 also includes the following steps:

S501:待准备工作完成后,开始掘进、顶管,替代填料的管道1顶进时应根据地面监测数据及时调整顶进参数;初始顶进速度宜控制在10~20mm/min;正常顶进期间,顶进速度宜控制在20~30mm/min;S501: After the preparatory work is completed, start excavation and pipe jacking. When the pipe 1 replacing the filler is jacked, the jacking parameters should be adjusted in time according to the ground monitoring data; the initial jacking speed should be controlled at 10-20mm/min; during normal jacking , the jacking speed should be controlled at 20 ~ 30mm/min;

S502:在掘进过程中,将所掘填料输出到地面;S502: During the excavation process, output the excavated filler to the ground;

S503:在第一节替代填料的管道1顶进后,与下一节替代填料的管道1拼装从而延长替代填料的管道1的长度,继而进行下一节顶进,周而复始,直至掘进机从工作井内穿过路基到达接收井内,将掘进机吊起回收;S503: After the first section of the pipeline 1 for filling replacement is jacked, it is assembled with the pipeline 1 for replacing the filling in the next section to extend the length of the pipeline 1 for replacing the filling, and then the next section is jacked. The well goes through the roadbed to the receiving well, and the roadheader is hoisted and recovered;

S504:与此同时,紧随掘进机后的替代填料的管道1埋设在工作井与接收井之间,且需把第一节替代填料的管道1的端部从路基内推出到接收井内一定长度,整个顶进施工结束,替代填料的管道1全线贯通。S504: At the same time, the pipeline 1 of the substitute filler following the roadheader is buried between the working well and the receiving well, and the end of the pipeline 1 of the first section of substitute filler needs to be pushed out from the roadbed to the receiving well for a certain length , the entire jacking construction is over, and the pipeline 1 replacing the filler is fully connected.

上述技术方案的工作原理及有益效果:贯穿路基的替代填料的管道1是由若干根两两连接而成,这样替代填料的管道1便不会受总长度的限制,可以尽可能的减小工作井的面积,从而减少对附近道路或场地的占用,掘进的时候为避免掘进力量过大导致桥体发生垮塌,顶进速度不宜过快,当掘进机全部进入桥体的路基之后便可以适当加快顶进速度,当掘进机从接收井内取出之后,需要继续对替代填料的管道1进行顶进,直至第一节替代填料的管道1有一部分延伸至接收井内,由此可以确保替代填料的管道1将路基全线贯通,避免替代填料的管道1未将路基全部贯通,导致路基因缺少支撑或受力不均而塌方的情况出现。The working principle and beneficial effects of the above technical solutions: the pipelines 1 of the substitute fillers running through the roadbed are formed by connecting several pipes in twos, so that the pipelines 1 of the substitute fillers will not be limited by the total length, and the work can be reduced as much as possible. The area of the well can reduce the occupation of nearby roads or sites. In order to avoid the collapse of the bridge due to excessive driving force, the jacking speed should not be too fast. When all the roadheaders enter the subgrade of the bridge, it can be appropriately accelerated. The jacking speed. After the roadheader is taken out of the receiving well, it is necessary to continue to jack up the pipeline 1 of the substitute filler until a part of the pipeline 1 of the substitute filler of the first section extends into the receiving well, thus ensuring the pipeline 1 of the substitute filler. The roadbed shall be penetrated all the way to avoid that the subgrade is not fully penetrated by the pipeline 1 of the substitute filler, resulting in the collapse of the roadbed due to lack of support or uneven force.

在一个实施例中,步骤S6中还包括如下步骤:In one embodiment, step S6 also includes the following steps:

S601:待贯通完成后,在替代填料的管道1和路基的填料之间进行灌浆处理,以加强替代填料的管道1与填料的耦合;S601: After the penetration is completed, grouting is performed between the pipeline 1 of the substitute filler and the filler of the roadbed, so as to strengthen the coupling between the pipeline 1 of the substitute filler and the filler;

S602:最后封堵替代填料的管道1的端口,将路面恢复。S602: Finally, plug the port of the pipeline 1 for replacing the filler, and restore the road surface.

上述技术方案的工作原理及有益效果:贯通完成之后将替代填料的管道1和路基的填料之间进行灌浆处理,可以增加替代填料的管道1与填料之间的耦合,防止其发生位移同时通过灌浆与填料连接为整体可以使受力更加均匀,最后将替代填料的管道1的端口封闭并恢复路面。The working principle and beneficial effects of the above technical solutions: after the completion of the penetration, grouting is performed between the pipeline 1 of the substitute filler and the filler of the roadbed, which can increase the coupling between the pipeline 1 of the substitute filler and the filler, prevent its displacement and pass the grouting at the same time. Connecting with the filler as a whole can make the force more uniform, and finally close the port of the pipe 1 that replaces the filler and restore the road surface.

在一个实施例中,所述替代填料的管道1为钢波纹管;In one embodiment, the pipeline 1 for replacing the filler is a steel corrugated pipe;

由于钢波纹管的厚度较薄,需进行处理来进行顶进,在钢波纹管内部沿轴向对称布置若干根加强钢管12以提高钢波纹管的轴线刚度,加强钢管12与钢波纹管可拆卸连接;Due to the thin thickness of the steel bellows, it needs to be processed for jacking. Several reinforcing steel pipes 12 are arranged symmetrically in the axial direction inside the steel bellows to improve the axial rigidity of the steel bellows. The reinforced steel pipes 12 and the steel bellows can be disassembled. connect;

每节钢波纹管长度根据具体情况设定,一般可设置为2~3m。The length of each section of steel corrugated pipe is set according to the specific situation, generally can be set to 2 ~ 3m.

上述技术方案的工作原理及有益效果:替代填料的管道1采用钢波纹管,由于钢波纹管的厚度较薄,所以在顶进的过程中需要在其内部设置加强钢管12来提高钢波纹管的轴向刚度避免在顶进的过程中钢波纹管出现破裂,在贯通之后将加强钢管12拆掉即可,钢波纹管具有较好的承载性能和变形能力,在汽车从过渡段路过的时候可以将汽车对路基的作用力通过钢波纹管的径向的变形起到分散应力的作用,当多辆汽车从过渡段路过的时候,钢波纹管通过波峰和波谷之间的挤压形变将轴向的应力进行分散,从而减少地基的沉降,同时还减少了填料的质量。The working principle and beneficial effects of the above technical solutions: the pipe 1 that replaces the filler adopts the steel corrugated pipe. Since the thickness of the steel corrugated pipe is relatively thin, it is necessary to set a reinforcing steel pipe 12 inside it during the jacking process to improve the strength of the steel corrugated pipe. Axial stiffness prevents the steel corrugated pipe from breaking during the jacking process. After the penetration, the reinforcing steel pipe 12 can be removed. The steel corrugated pipe has good bearing performance and deformation ability, and can be used when the car passes through the transition section. The force of the car on the roadbed is used to disperse the stress through the radial deformation of the steel bellows. When multiple cars pass through the transition section, the steel bellows will axially disperse through the extrusion deformation between the wave crest and the wave trough. The stress is dispersed, thereby reducing the settlement of the foundation, and also reducing the quality of the filler.

在一个实施例中,所述钢波纹管之间通过连接件13进行连接,In one embodiment, the steel corrugated pipes are connected by connecting pieces 13,

所述钢波纹管的端部设置有若干个爪扣14,所述爪扣14沿所述钢波纹管的径向向外凸起,若干个所述爪扣14在所述钢波纹管的端部形成与所述钢波纹管的波峰相适应的环扣,相邻的两个所述钢波纹管通过所述环扣与所述连接件13连接;The end of the steel bellows is provided with a plurality of claw buckles 14, the claw buckles 14 protrude outward along the radial direction of the steel bellows, and a plurality of the claw buckles 14 are located at the ends of the steel bellows. A ring is formed in the part that is adapted to the crest of the steel corrugated pipe, and two adjacent steel corrugated pipes are connected to the connecting piece 13 through the ring;

所述连接件13包括管体15,所述管体15内设有阻尼管16,所述阻尼管16的外壁通过簧片17与所述管体15的内壁连接;所述簧片17包括具有初始和拉伸两种状态的弹片,所述管体15的外壁上设置有插接卡头18和顶进卡头19,所述插接卡头18与所述管体15的一端形成插入端20,所述顶进卡头19设置在所述管体15的另一端,所述插接卡头18和所述顶进卡头19之间形成压合腔21,所述相互插接的两个钢波纹管的所述环扣均卡接在所述压合腔21内并压缩变形,所述插入端20插入在先顶进的所述钢波纹管的末端,并且所述管体15的端部与所述加强钢管12抵接,在后顶进的所述钢波纹管内的所述加强钢管12与所述顶进卡头19抵接。The connecting piece 13 includes a tube body 15, and the tube body 15 is provided with a damping tube 16. The outer wall of the damping tube 16 is connected with the inner wall of the tube body 15 through a reed 17; For the elastic pieces in the initial and stretched states, the outer wall of the tube body 15 is provided with a plug-in clip 18 and a push-in clip 19, and the plug-in clip 18 and one end of the tube body 15 form an insertion end 20. The push-in chuck 19 is disposed at the other end of the pipe body 15, a pressing cavity 21 is formed between the plug-in chuck 18 and the push-in chuck 19, and the two mutually inserted The buckles of each steel bellows are snapped into the pressing cavity 21 and compressively deformed. The end portion is in contact with the reinforced steel pipe 12 , and the reinforced steel pipe 12 in the steel corrugated pipe that is pushed back in contact with the jacking chuck 19 .

上述技术方案的工作原理:在两个钢波纹管进行连接的时候,首先将连接件13的插入端20插入在先的钢波纹管内,此时在先的钢波纹管的环扣会通过插接卡头18与管体15进行卡接,因为爪扣14上设置有凸起并且环扣与钢波纹管的波峰相适应,所以插接卡头18的外壁会卡接在环扣的内壁上,然后将在后的钢波纹管的环扣通过顶进卡头19进行卡接,此时两个钢波纹管的环扣均位于压合腔21内,在液压千斤顶的作用下,在后的钢波纹管内部的加强钢管12会抵接在顶进卡头19上,通过推动顶进卡头19来推动管体15进而推动插入端20更加深入在先的钢波纹管内,并使插入端20的管体15的端部与在先的钢波纹管内的加强钢管12的末端抵接进而推动在先的钢波纹管移动,在连接件13移动至掘进机挖开的隧道内的时候,隧道内壁会将压合腔21处凸出的爪扣14挤压变形,从而使两个钢波纹管的环扣因挤压变形而固定在压合腔21内从而实现两个钢波纹管的连接。The working principle of the above technical solution: when two steel corrugated pipes are connected, first insert the insertion end 20 of the connecting piece 13 into the previous steel corrugated pipe, at this time, the ring buckle of the previous steel corrugated pipe will be inserted through the plug connection. The clamp head 18 is clamped with the pipe body 15, because the claw buckle 14 is provided with a protrusion and the ring buckle is adapted to the wave crest of the steel corrugated pipe, so the outer wall of the plug-in clamp head 18 will be clamped on the inner wall of the ring buckle, Then, the loops of the steel bellows at the back are clamped through the jacking head 19. At this time, the loops of the two steel bellows are located in the pressing cavity 21. Under the action of the hydraulic jack, the steel bellows behind The reinforced steel pipe 12 inside the corrugated pipe will abut on the jacking head 19, push the jacking head 19 to push the pipe body 15 and then push the insertion end 20 to go deeper into the previous steel corrugated pipe, and make the insertion end 20 move further. The end of the pipe body 15 is in contact with the end of the reinforcing steel pipe 12 in the preceding steel corrugated pipe and pushes the preceding steel corrugated pipe to move. The claw buckle 14 protruding from the pressing cavity 21 is squeezed and deformed, so that the loops of the two steel bellows are fixed in the pressing cavity 21 due to the squeeze deformation, thereby realizing the connection of the two steel bellows.

上述技术方案的有益效果:通过上述结构的设计,在先的钢波纹管内的加强钢管12因已经被液压千斤顶挤压顶进过,所以会完美贴合在钢波纹管的内壁上不容易发生形变,所以仅靠管体15的端部便可以推动,在后的钢波纹管内的加强钢管12因为安装的时候并不能保证所有端面平齐且所有加强钢管12均处在与钢波纹管的中心轴线平行的位置上,所以挤压顶进时会与在后的钢波纹管之间出现相对移动,因此需要在后的钢波纹管内的加强钢管12的前端具有足够大的接触面积以防止与连接件13脱离,压合腔21可以利用环扣自身的性质在隧道的挤压下通过变形填满压合腔21从而实现两个钢波纹管的连接,当路面有车辆行驶的时候,汽车会对路基内的填料产生压力,压力经传导到达钢波纹管可以通过其自身的环形和波峰、波谷将径向和轴向的应力发散,连接件13则可以将受到的应力经由簧片17传递至阻尼管16上,通过阻尼管16的摆动将所受的应力进行发散,从而使连接件13也可以对所受的应力进行发散进而增加连接件13的使用寿命,避免长时间反复受力出现疲劳损坏的情况。The beneficial effects of the above technical solutions: through the design of the above structure, the reinforced steel pipe 12 in the previous steel bellows has been squeezed and pushed by the hydraulic jack, so it will perfectly fit on the inner wall of the steel bellows and is not easily deformed. , so only the end of the pipe body 15 can be pushed, and the reinforcing steel pipes 12 in the steel bellows after installation cannot ensure that all the end faces are flush and all the reinforcing steel pipes 12 are in the center axis of the steel bellows. In the parallel position, there will be relative movement between the steel bellows and the steel bellows after extrusion, so the front end of the reinforcing steel pipe 12 in the steel bellows needs to have a large enough contact area to prevent contact with the connecting piece. 13. Disengaged, the pressing cavity 21 can use the properties of the buckle itself to fill the pressing cavity 21 through deformation under the extrusion of the tunnel to realize the connection of the two steel bellows. The packing inside generates pressure, and the pressure is transmitted to the steel bellows, which can dissipate the radial and axial stress through its own ring and wave peaks and troughs, and the connecting piece 13 can transmit the stress to the damping tube through the reed 17 16, through the oscillation of the damping tube 16 to dissipate the stress, so that the connector 13 can also diffuse the stress to increase the service life of the connector 13, to avoid fatigue damage caused by repeated stress for a long time. Happening.

在一个实施例中,在选用替代填料的管道1的时候需要先根据过渡段的地理环境测算出填料对替代填料的管道1的管壁可以产生的径向弯曲最大应变值δ,然后通过如下公式计算出替代填料的管道1的直径RIn one embodiment, when selecting the pipeline 1 with the replacement filler, it is necessary to first calculate the maximum radial bending strain value δ that the filler can produce on the pipe wall of the pipeline 1 with the replacement filler according to the geographical environment of the transition section, and then use the following formula Calculate the diameter R of the pipe 1 that replaces the packing

R=±(C/δ)((3ΔY/R)/1-(2ΔY/R))R=±(C/δ)((3ΔY/R)/1-(2ΔY/R))

其中R为替代填料的管道1的直径;C为替代填料的管道1的厚度;δ为管壁由于径向弯曲产生的最大应变值;ΔY为替代填料的管道1的管径的径向减值;where R is the diameter of the pipe 1 that replaces the filler; C is the thickness of the pipe 1 that replaces the filler; δ is the maximum strain value of the pipe wall due to radial bending; ΔY is the radial decrease of the pipe diameter of the pipe 1 that replaces the filler ;

通过上述公式可以根据所需的直径计算出相对应厚度或者通过所需的厚度计算对应的直径。Through the above formula, the corresponding thickness can be calculated according to the required diameter or the corresponding diameter can be calculated according to the required thickness.

上述技术方案的工作原理及有益效果:通过上述公式可以根据施工的需要选择对应的直径或者厚度,从而保证替代填料的管道1可以有足够的径向弯曲应变值,避免出现厚度和直径的选择无法满足应变值的需求,导致替代填料的管道1无法承受地基中填料的重量出现塌方。The working principle and beneficial effects of the above technical solutions: through the above formula, the corresponding diameter or thickness can be selected according to the needs of the construction, so as to ensure that the pipe 1 that replaces the filler can have sufficient radial bending strain value, and avoid the inability to select the thickness and diameter. Meeting the requirements of the strain value causes the pipe 1 to replace the filler to collapse due to the inability to bear the weight of the filler in the foundation.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " Rear, Left, Right, Vertical, Horizontal, Top, Bottom, Inner, Outer, Clockwise, Counterclockwise, Axial, The orientations or positional relationships indicated by "radial direction", "circumferential direction", etc. are based on the orientations or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the indicated devices or elements. It must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as a limitation of the present invention.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接或彼此可通讯;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系,除非另有明确的限定。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise expressly specified and limited, the terms "installed", "connected", "connected", "fixed" and other terms should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection , or integrated; it can be a mechanical connection or an electrical connection or can communicate with each other; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two components or the interaction relationship between the two components, unless otherwise expressly qualified. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节与这里示出与描述的图例。Although the embodiment of the present invention has been disclosed as above, it is not limited to the application listed in the description and the embodiment, and it can be applied to various fields suitable for the present invention. For those skilled in the art, it can be easily Therefore, the invention is not limited to the specific details and illustrations shown and described herein without departing from the general concept defined by the appended claims and the scope of equivalents.

Claims (7)

1. A method for reinforcing the transition section of an existing bridge and a bridge under the condition of not interrupting traffic is characterized by comprising the following specific steps of:
s1: measuring and lofting;
s2: constructing a working well;
s3: constructing a receiving well;
s4: preparing jacking;
s5: jacking construction, wherein a pipeline (1) for replacing the filler penetrates through the roadbed;
s6: reinforcement treatment;
the step S5 also comprises the following steps:
s501: after the preparation work is finished, starting tunneling and jacking, and adjusting jacking parameters in time according to ground monitoring data when the pipeline (1) replacing the filler is jacked;
s502: during the tunneling process, the dug filler is output to the ground;
s503: after the first section of pipeline (1) for replacing the filler is jacked, the first section of pipeline is spliced with the next section of pipeline (1) for replacing the filler so as to prolong the length of the pipeline (1) for replacing the filler, then the next section of pipeline is jacked, and the process is repeated until the heading machine passes through the roadbed from the working well to the receiving well, and the heading machine is hoisted and recovered;
s504: meanwhile, a pipeline (1) for replacing the filler, which is arranged behind the heading machine, is buried between the working well and the receiving well, the end part of the first section of pipeline (1) for replacing the filler needs to be pushed out from the roadbed to the receiving well for a certain length, the whole jacking construction is finished, and the pipeline (1) for replacing the filler is completely communicated;
the pipeline (1) for replacing the filler is a steel corrugated pipe;
because the thickness of the steel corrugated pipe is thin, the steel corrugated pipe needs to be processed for jacking, a plurality of reinforcing steel pipes (12) are symmetrically arranged in the steel corrugated pipe along the axial direction to improve the axial rigidity of the steel corrugated pipe, and the reinforcing steel pipes (12) are detachably connected with the steel corrugated pipe;
the corrugated steel pipes are connected through a connecting piece (13),
the end part of the corrugated steel pipe is provided with a plurality of claws (14), the claws (14) are outwards protruded along the radial direction of the corrugated steel pipe, the claws (14) form buckles matched with wave crests of the corrugated steel pipe at the end part of the corrugated steel pipe, and two adjacent corrugated steel pipes are connected with the connecting piece (13) through the buckles;
the connecting piece (13) comprises a pipe body (15), a damping pipe (16) is arranged in the pipe body (15), and the outer wall of the damping pipe (16) is connected with the inner wall of the pipe body (15) through a reed (17); the reed (17) comprises elastic sheets in an initial state and a stretching state, a plug-in chuck (18) and a jacking chuck (19) are arranged on the outer wall of the pipe body (15), the plug-in chuck (18) and one end of the pipe body (15) form a plug-in end (20), the jacking chuck (19) is arranged at the other end of the pipe body (15), a pressing cavity (21) is formed between the plug-in chuck (18) and the jacking chuck (19), the buckles of the two steel corrugated pipes which are mutually plugged are clamped in the pressing cavity (21) and are compressed and deformed, the plug-in end (20) is inserted into the tail end of the steel corrugated pipe which is firstly jacked, the end of the pipe body (15) is abutted to the reinforced steel pipe (12), and the reinforced steel pipe (12) in the steel corrugated pipe which is secondly jacked is abutted to the jacking chuck (19).
2. The method for reinforcing the transition section of the existing bridge and road bridge under the condition of not interrupting traffic as claimed in claim 1, wherein the step S1 further comprises the steps of:
s101: measuring the positions of a working well and a receiving well and the position and the trend of a pipeline (1) for replacing fillers according to the on-site plane arrangement and the space position of the transition section of the bridge and the road of the existing bridge;
s102: and setting a temporary leveling point, and measuring the excavation range and depth of the working well and the receiving well.
3. The method for reinforcing the transition section of the existing bridge and road bridge without traffic interruption of claim 1, wherein the step S2 further comprises the steps of:
s201: excavating in the determined position and range of the working well according to the geological condition and the field condition, and carrying out instant supporting by adopting a supporting steel plate (8);
s202: when the designed elevation is to be excavated, the bottom plate and the wall plate are poured by concrete, and the thickness of the concrete and the steel plate cushion block is determined to meet the jacking requirement.
4. The method for reinforcing a bridge transition section of an existing bridge without interrupting traffic as set forth in claim 1, wherein the step S3 further comprises the steps of:
s301: excavating in the determined position and range of the receiving well according to the geological condition and the field condition, and carrying out instant supporting by adopting a supporting steel plate (8);
s302: when the designed elevation is excavated, the bottom plate and the wall plate are poured by concrete, and the requirements on strength and stability are met.
5. The method for reinforcing the transition section of the existing bridge and road bridge without traffic interruption of claim 1, wherein the step S4 further comprises the steps of:
s401: arranging a pipe jacking machine guide rail and a hydraulic jack in the working well;
s402: and installing a tunneling machine at the foremost end of the pipeline (1) for replacing the filler, and selecting and setting the tunneling speed and the jacking speed according to the filling property and the thickness of the covering layer.
6. The method for reinforcing a bridge transition section of an existing bridge without interrupting traffic as claimed in claim 1, wherein the step S501 further comprises: the initial jacking speed is preferably controlled to be 10-20 mm/min; during the normal jacking period, the jacking speed is preferably controlled to be 20-30 mm/min.
7. The method for reinforcing a bridge transition section of an existing bridge without interrupting traffic of claim 1,
the step S6 also comprises the following steps:
s601: after the penetration is finished, grouting treatment is carried out between the pipeline (1) for replacing the filler and the filler of the roadbed so as to strengthen the coupling between the pipeline (1) for replacing the filler and the filler;
s602: finally, plugging the port of the pipeline (1) for replacing the filler, and recovering the pavement; the length of each section of the steel corrugated pipe is set according to specific conditions.
CN202111209208.0A 2021-10-18 2021-10-18 Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic Active CN113957758B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111209208.0A CN113957758B (en) 2021-10-18 2021-10-18 Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111209208.0A CN113957758B (en) 2021-10-18 2021-10-18 Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic

Publications (2)

Publication Number Publication Date
CN113957758A CN113957758A (en) 2022-01-21
CN113957758B true CN113957758B (en) 2022-10-04

Family

ID=79465068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111209208.0A Active CN113957758B (en) 2021-10-18 2021-10-18 Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic

Country Status (1)

Country Link
CN (1) CN113957758B (en)

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3736920B2 (en) * 1996-10-29 2006-01-18 Jfeエンジニアリング株式会社 Screw joint type propulsion pipe and anticorrosion method for screw joint type propulsion pipe
JP2002293233A (en) * 2001-03-30 2002-10-09 Kurimoto Ltd Sheath pipe jacking method, and truck used therefor
DE10310938A1 (en) * 2003-03-13 2004-09-23 Brugg Rohr Ag, Holding Method of making a connection between a corrugated pipe and a connector
CN103938703B (en) * 2014-05-07 2015-11-25 中国五冶集团有限公司 A kind of pipe jacking construction method
CN104594329B (en) * 2014-12-17 2016-05-25 河海大学 A kind of off-load is processed the devices and methods therefor of road-bridge transition section differential settlement
CN108086349A (en) * 2018-02-01 2018-05-29 沈阳建筑大学 A kind of corrugated steel pipe overlaps cross section structure
CN110439590A (en) * 2019-08-06 2019-11-12 中铁十四局集团有限公司 Method for tunnel construction
CN110485316A (en) * 2019-08-27 2019-11-22 山东交通学院 A kind of method of multiple slip casting to administer bumping at bridge-head

Also Published As

Publication number Publication date
CN113957758A (en) 2022-01-21

Similar Documents

Publication Publication Date Title
KR101179778B1 (en) Method for constructing underground structure
KR101006900B1 (en) Construction method of backfill reinforcement structure of rigid structure
KR101069705B1 (en) Method for installing waterproofing steel plate in construction of undergound tunnel
WO2010019014A2 (en) Method for constructing a chair-type, self-supported earth retaining wall
CN113417649B (en) Underground tunnel small-section to large-section expanding excavation method
KR100805189B1 (en) Underground structure construction method that combines wall construction and excavation
CN110685234B (en) Construction method of corrugated steel pipe culvert
CN113957758B (en) Method for reinforcing bridge and road transition section of existing bridge under condition of uninterrupted traffic
CN104818658A (en) Road widening system and road widening method for collapsible yellow earth foundation layer
KR101710718B1 (en) Method for connecting precast wall and slab, and underground structure constructed by the same
CN116181342A (en) Integrated originating construction method for U-shaped shield machine shield frame
CN115012947A (en) Reverse method prefabricated shaft and its construction method
CN114412526A (en) Tunnel surrounding rock supporting system
CN113931169A (en) Bias multi-arch tunnel portal soft foundation zone combined structure and construction method
KR20210124654A (en) Construction method for undergroud structures using steel pipes
CN219547819U (en) Existing building protection structure of shallow foundation immediately adjacent to foundation pit
KR101710716B1 (en) Modular Underground Structures using PC Walls with Supported Steel Beams
CN116906055B (en) Construction methods and scaffolding support structures to control deformation of tunnels passing through railway subgrade
KR102782280B1 (en) Semi-shield method using a straight-forward device to maintain the direction of propulsion work
CN118029216B (en) Active isolation type differential settlement control structure and method for new and old spliced roadbed
CN221504152U (en) A composite structure of pipe jacking reaction wall in soft soil area
CN116591148B (en) Construction method of underground continuous wall system
CN114892711B (en) Construction method of retaining wall in deep and weak soil stratum and side slope supporting structure
CN110318372B (en) Anchor rod butt joint method
KR101664103B1 (en) Modular Underground Structures with PC Walls Using Support Beams

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant