CN113914909A - A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method - Google Patents

A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method Download PDF

Info

Publication number
CN113914909A
CN113914909A CN202111437247.6A CN202111437247A CN113914909A CN 113914909 A CN113914909 A CN 113914909A CN 202111437247 A CN202111437247 A CN 202111437247A CN 113914909 A CN113914909 A CN 113914909A
Authority
CN
China
Prior art keywords
grouting
water
retaining wall
tunnel
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111437247.6A
Other languages
Chinese (zh)
Inventor
王聪
李晓佳
刘敬
张君雨
石浩宇
曲贺
谭斌
路光
王军伟
韩浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 9 Co Ltd
Original Assignee
Sinohydro Bureau 9 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 9 Co Ltd filed Critical Sinohydro Bureau 9 Co Ltd
Priority to CN202111437247.6A priority Critical patent/CN113914909A/en
Publication of CN113914909A publication Critical patent/CN113914909A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an emergency rescue plugging structure for a tunnel water inrush point and a construction method thereof, and is characterized in that: the water-retaining wall comprises a water-retaining wall body, wherein bagged cement masonry is arranged on two sides of the water-retaining wall body, an inclined support is arranged in the bagged cement masonry on one side, a plurality of cofferdams are arranged on one side of the water-retaining wall body, a plurality of drainage tubes are arranged on the water-retaining wall body, one ends of the drainage tubes penetrate through the water-retaining wall body and the bagged cement masonry, and the other ends of the drainage tubes freely stretch into the water-retaining wall body and are provided with valves. The invention adopts the modes of centralized drainage, rock mass reinforcement and grouting plugging to control water, and plugs the water-inrush point of the tunnel face and the front un-excavated tunnel section, so that a waterproof curtain wall is formed at the periphery of the working face, and the purpose of water plugging is achieved.

Description

Tunnel water inrush point emergency rescue plugging structure and construction method thereof
Technical Field
The invention belongs to the field of tunnel construction, and particularly relates to an emergency rescue plugging structure for a tunnel water inrush point and a construction method thereof.
Background
In some tunnel work progress, the proruption condition of gushing water can appear often, leads to the tunnel to be submerged, influences the construction, and for this reason people have designed some sudden water spot block structure, and chinese patent that application number is 201810087642.8 for example discloses a prevention and cure high pressure sudden water spot non-pressure shutoff wall, including ending thick liquid wall main part and breakwater main part, it is equipped with the slip casting pipe to end thick liquid wall main part lower part, it is equipped with two sets of outlet pipes in the main part to end thick liquid wall, the outlet pipe runs through only thick liquid wall main part and breakwater main part, the outlet pipe both ends are run through to the outside and are extended, it divide into upper and lower two parts to end thick liquid wall main part and breakwater main part through the lift tank. But this type of barricade can't carry out effectual shutoff when water pressure is too big, consequently needs a tunnel water spot emergency rescue block structure, can block the water spot suddenly when the tunnel gushes water, carries out the rock mass to the dug section and consolidates and strengthen strutting, eliminates quality safety hidden danger, guarantees that later stage excavation work develops smoothly.
Disclosure of Invention
In order to solve the technical problems, the invention provides an emergency rescue plugging structure for a tunnel water inrush point, which can solve the problem that effective plugging cannot be performed when water pressure is too high in the prior art.
The invention is realized by the following technical scheme.
The invention provides an emergency rescue plugging structure for a tunnel water inrush point, which is characterized in that: including the breakwater, the breakwater both sides are equipped with bagged cement and build by laying bricks or stones, and are equipped with the bearing diagonal in the bagged cement of one side is built by laying bricks or stones, breakwater one side is equipped with many stifled cofferdams, is equipped with many drainage tubes on the breakwater, and drainage tube one end is run through the breakwater and bagged cement and is built by laying bricks or stones, and the drainage tube other end freely stretches into and installs the valve, be equipped with many grout pipes in the breakwater, the grout pipe runs through the breakwater and bagged cement is built by laying bricks or stones.
Be equipped with reinforcing bar net and I-steel support in the breakwater, reinforcing bar net and I-steel support interconnect constitute frame construction, and breakwater upper portion and lower part all are equipped with the bar planting.
A construction method of a tunnel water inrush point emergency rescue plugging structure is characterized by comprising the following steps:
step S1, construction preparation;
step S2, building a construction channel and an operation platform;
step S3, pouring the water retaining wall;
step S4, reinforcing and strengthening the support of the rock mass in the tunnel;
step S5, sealing the tunnel face and the periphery, and plugging water inrush points;
step S6, grouting effect inspection and vault advance support;
step S7, dredging after grouting, removing temporary measures and building permanent facilities;
and step S8, blasting and removing the retaining wall and the consolidation body.
In the step S2, cofferdams are arranged at intervals of 5.5m, the construction channels and the operation platforms are formed by erecting steel pipes, steel bars and wood boards above the cofferdams, the steel bars and the steel pipes are firmly bound and stably erected above the cofferdams, and then the wood boards are laid above the steel bars.
And S3, during construction, a water retaining bank is built at the bottom of the face by sand bags, 8 DN200 drainage tubes and 5 DN32 grouting tubes are pre-embedded, one grouting tube extends into the top arch for 6m, the other grouting tube extends into the top arch for 9m, and bagged cement stacks are used as supporting templates before the water retaining wall is poured.
In the step S4, a full frame is erected by adopting a phi 50 steel pipe as an operation platform, in the step S4, consolidation grouting is carried out on the side arch of the tunnel, cement-water glass double-liquid slurry is adopted for consolidation grouting, the water cement ratio W: C is 0.5:1, and cement: the ratio of the water glass is 1:0.03, grouting holes are arranged at intervals of 3m to 3m, the depth of the grouting holes is 5m to 6m, the inner diameter is phi 50 to phi 60, the grouting pressure is linearly increased, the maximum grouting pressure is 0.8MPa, the minimum grout-feed quantity when the final grouting pressure is reached is 10-20L/min, the time is kept for 10-15 min, grouting is stopped, after consolidation grouting is finished, phi 32 to phi 36 prestressed anchors are arranged on a tunnel top arch and a side wall, the length specifications of the prestressed anchors are 6m and 9m, the prestressed anchors are exposed by 20cm, the prestressed anchors are arranged at intervals of 3m to 3m and are fixed by steel supporting plates, and holes are drilled by adopting down-the-hole anchors.
In the step S5, after the concrete of the retaining wall reaches the designed strength, grouting construction is started, when the lower half part of the retaining wall is grouted, a gate valve of a water diversion steel pipe at the bottom is closed, a steel pipe at the top is used for centralized drainage, so that the lower water behind the retaining wall is in a static state, firstly, double-liquid-slurry grouting is carried out through 3 grouting pipes pre-embedded at the bottom, after the pre-embedded pipe grouting is finished, holes are drilled at the bottom and two sides of the retaining wall by a hand drill, the hole diameter phi 32, the hole depth 3m and the space 1m are used as double-liquid-slurry grouting holes of the walls at the bottom and two sides, grouting at the bottom and the periphery of the retaining wall is continued until water gushing at the bottom and the periphery of the retaining wall is completely blocked, after grouting at the bottom and the periphery, water plugging grouting is carried out by utilizing the grouting pipes pre-embedded at the top to block water, grouting is carried out by utilizing the grouting pipes deep into the top arch 6m during grouting, the upper water discharge pipe gate valve is closed one by one and various measures and the stable conditions and the peripheral water seepage conditions are observed, if necessary, local reinforcement is carried out, only a slurry return pipe which is deep into the top arch by 9m is left for drainage until the water conduit is completely closed, and cement-water glass double-liquid slurry is adopted.
In the step S5, the grouting material is p.042.5 portland cement, the water cement ratio W: C is 0.5:1, the water glass ratio is 1:0.03, the tunnel face and the surrounding closed grouting pressure is 0.2 to 0.6MPa, the grouting is performed in a small-to-large step-by-step manner, the lifting pressure is 0.02MPa each time, the minimum grout-feeding amount is 10 to 20L/min for 15min of continuous grouting or the grouting pressure is stabilized at 0.6MPa, the hole grouting operation can be ended, and the lower hole grouting is performed.
In the step S6, 1 advance probing hole is respectively arranged at the top and the bottom of the water retaining wall, whether water seeps or not is checked, the strength of a condensate is judged according to the drilling speed, if water gushes or the condensate is insufficient in the drilled hole, grouting consolidation plugging is carried out again before excavation, 12 advance probing holes with the length of 20m are arranged at the arch crown at the back of the water retaining wall, the grouting effect at the positions 3m, 5m and 7m above the water gushing point of the tunnel face is checked, if no water gushing phenomenon exists, a phi 32 advance anchor rod is installed and grouted for anchoring by using the probing holes, the length of the anchor rod is 20m, if water gushing occurs in the drilled hole, grouting consolidation plugging is carried out continuously, and after grouting plugging is finished, holes are punched again to form the advance anchor rod.
In the step S8, after the water burst channel is completely closed and a stable water-proof layer is formed, blasting and dismantling the water-retaining wall and the consolidation body, blasting with multiple holes, small dosage and short feed-length, and cutting off the connecting part of the steel bar and the section steel by oxygen welding after blasting.
The invention has the beneficial effects that: the water control method comprises the steps of adopting a centralized drainage, rock mass reinforcement and grouting plugging mode to control water, plugging a tunnel face water inrush point and a front un-excavated tunnel section, forming a water-proof curtain wall on the periphery of a working face, achieving the purpose of water plugging, reducing water yield through plugging after grouting is finished, reducing drainage, enabling the working face to be normally constructed, accelerating tunneling speed, reinforcing and strengthening support on the excavated section, eliminating quality safety hazards, and ensuring that later-stage excavation work is smoothly carried out.
Drawings
FIG. 1 is a schematic structural view of the present invention;
in the figure: 1-water retaining wall, 2-bagged cement masonry, 3-diagonal bracing, 4-cofferdam, 5-drainage tube, 6-grouting tube, 7-reinforcing mesh, 8-I-steel bracing and 9-bar planting.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the described.
As shown in figure 1, a tunnel water inrush point emergency rescue block structure, its characterized in that: including breakwater 1, 1 both sides of breakwater are equipped with bagged cement and build 2 by laying bricks or stones, and the bagged cement in one side builds 2 and is equipped with bearing diagonal 3, 1 one side of breakwater is equipped with many stifled cofferdams 4, is equipped with many drainage tubes 5 on the breakwater 1, and drainage tube 5 one end runs through breakwater 1 and bagged cement and builds 2 by laying bricks or stones, and the drainage tube 5 other end freely stretches into and installs the valve, be equipped with many grout pipes 6 in the breakwater 1, grout pipe 6 runs through breakwater 1 and bagged cement builds 2 by laying bricks or stones.
The tunnel face in the hole has large water burst, and water plugging and grouting can be carried out after a concrete water retaining wall is poured. The concrete retaining wall is cast by C25 concrete with the casting thickness of 5 m. Before concrete pouring, manual foundation cleaning is firstly adopted. And after manual foundation cleaning is finished, water gushing, drainage and concrete pouring are carried out. And the water retaining wall 1 cannot be provided with a template during pouring due to the limitation of field conditions, so that bagged cement masonry 2 is formed by piling bagged cement on the face side of the water retaining wall 1, and the bagged cement masonry serves as a supporting template and simultaneously reduces the later cavity backfill grouting engineering amount. The concrete side of the water retaining wall 1 close to the branch hole is built into a step shape by adopting bagged cement 2 to serve as a supporting template, and meanwhile, the concrete is convenient to enter the warehouse manually. In order to ensure the safety of grouting construction personnel and equipment, all water guiding and discharging pipes and grouting pipes are connected to the construction branch hole expanding excavation section, a gate valve is arranged, and grouting construction operation is carried out on the construction branch hole expanding excavation section. In order to avoid adverse effects such as structural damage and strength reduction caused by impact of water burst on a newly-poured concrete retaining wall, a water blocking ridge is built at the bottom near a tunnel face by adopting sand bags, 8 DN200 drainage tubes 5 are embedded in the bottom, water burst drainage is carried out at the middle lower part, accumulated water behind the retaining wall 1 is ensured to be timely discharged, and 5 DN32 steel tubes are arranged to serve as grouting tubes 6. Set up 5 DN200 drainage tubes 5 at waterwall 1 top, carry out the top and gush water and draw and arrange, set up 2 DN32 grouting pipes 6 at the face top for the convenience of later stage grout, one is deep into top arch 6m and is used for the grout, one is deep into top arch 9m and is used for the mud return pipe.
The water retaining wall is characterized in that a reinforcing mesh 7 and an I-shaped steel support 8 are arranged in the water retaining wall 1, the reinforcing mesh 7 and the I-shaped steel support 8 are connected with each other to form a frame structure, and the upper portion and the lower portion of the water retaining wall 1 are provided with embedded bars 9. In order to ensure the concrete stability of the water retaining wall 1, reinforcing steel bars and section steel are arranged in the concrete of the water retaining wall 1, three rows of embedded bars 9 with the diameter of phi 25 and the length of L2 m are arranged on a bottom plate and a side top arch at the position of pouring the water retaining wall, and the embedded bars 9 are embedded into rock for 1m and exposed for 1m, the spacing is 30cm, and the row spacing is 200 cm. Because of the poor geological condition of surrounding rock, the bottom plate pore-forming is easy to take place and is collapsed the hole and hardly become the hole, and the bottom plate utilizes the drilling rod directly as bar planting 9, utilizes the drilling rod hole to carry out the slip casting. The double-layer phi 25 reinforcing mesh 7@20cm is arranged in the tunnel face direction of the water retaining wall 1
The distance between the two layers is 200cm, two layers of I20I-steel supports 8 are arranged inside the water retaining wall 1 in the direction close to the branch hole, the distance between the two layers of I-steel supports 8 is 200cm, the distance between each I-steel support 8 is 50cm, and the I-steel supports 8 and the original chamber supporting I-steel are firmly welded. The outer side of the water retaining wall is also provided with I-shaped steel to form an inclined support 3. The reinforcing mesh, the embedded steel bars, the I-shaped steel supports 8, the inclined supports 3 and the original steel arch frames of the expanded excavation section are firmly welded with each other.
A construction method of a tunnel water inrush point emergency rescue plugging structure is characterized by comprising the following steps:
and step S1, construction preparation, including construction air supply, construction electricity utilization, preparation of a pulping system and the like, is convenient for smooth construction.
And step S2, building a construction channel and an operation platform, and building a 1.5m wide pedestrian trestle from a branch tunnel to a working surface for the convenience of water plugging construction due to the large water inflow in the tunnel. In order to effectively carry out water inrush and grouting wastewater sedimentation, prevent blockage and damage of a water pump and reduce water pollution, one cofferdam 4 is arranged in the hole at intervals of 5.5m, and the cofferdams 4 are manually bagged and piled up to be 1.4m high to form a multistage sedimentation tank; the pedestrian trestle is formed by erecting a steel pipe, phi 25 steel bars and a wood board above a water blocking wall, the steel bars and the steel pipe are firmly bound and stably erected above the water blocking wall, and then the wood board is laid above the steel bars.
And step S3, pouring the water retaining wall, and plugging the water flow by forming the concrete water retaining wall 1 through pouring.
And step S4, reinforcing and supporting the rock mass in the hole, wherein the rock mass reinforcing and supporting reinforcement treatment is carried out on the branch hole expanding section and the main hole expanding section before water plugging grouting in order to prevent new large water gushing points caused by safety accidents or rock mass breakdown due to the fact that geological conditions of the branch hole expanding section and the main hole expanding section are poor and rock mass structure damage and supporting failure caused by high-pressure grouting. A phi 50 steel pipe is adopted to set up a full frame as an operation platform, and simultaneously, a certain supporting effect can be achieved, consolidation grouting treatment is firstly carried out on side arch tops of a branch tunnel expanding excavation section and a main tunnel expanding excavation section, the stability of a rock mass is enhanced, a water-resisting layer is formed, the grout leakage phenomenon is prevented, cement-water glass double-liquid grout is adopted for consolidation grouting, the water cement ratio W to C is 0.5:1, and cement: the ratio of the water glass is 1:0.03, the grouting holes are distributed in each circle, the row spacing is preferably 3m x 3m, the grouting holes are in a quincunx shape, the depth of the phi 50 grouting holes is 5m, the maximum grouting pressure is 0.8MPa, the grouting pressure is increased regularly, the designed grouting final pressure is reached, the minimum grout-feeding amount when the grouting final pressure is reached is 10-20L/min, and the grouting is stopped after the time is maintained for 10-15 min. After the consolidation grouting is finished, phi 32 prestressed anchor rods are arranged on the top arch and the side wall of the expanding excavation section, L is 6.0m/9.0m, the top arch and the side wall are exposed for 20cm, the prestressed anchor rods are arranged at intervals, steel supporting plates are adopted for fixing, the row spacing is preferably 1.5m by 1.5m, the prestressed anchor rods are in a quincunx shape, and down-the-hole drills are adopted.
And step S5, sealing the tunnel face and the periphery, plugging water inrush points, and starting grouting construction after the concrete of the water retaining wall reaches the designed strength. Closing a gate valve of a bottom water diversion steel pipe when the lower half part of the retaining wall is grouted, and then using a top steel pipe for centralized drainage to enable the lower water part behind the retaining wall to be in a static state, firstly performing double-liquid-slurry grouting through 5 pre-embedded grouting pipes at the bottom, after the pre-embedded pipe grouting is completed, drilling holes at the bottom and two side foundation faces of the retaining wall by using a hand-powered drill, wherein the hole diameter is phi 32, the hole depth is 3m, and the interval is 1m, and the holes are used as double-liquid-slurry grouting holes for the bottom and two side walls, and the bottom and periphery of the retaining wall are continuously grouted until all water gushes at the bottom and the periphery of the retaining wall are blocked.
And after the bottom and periphery grouting is finished, the face water plugging grouting is carried out by utilizing the top pre-embedded grouting pipe, the grouting is carried out by utilizing the grouting pipe which extends into the crown arch by 6m during grouting, the upper drain pipe gate valve is closed one by one, the stable condition and the peripheral water seepage condition of various measures are observed, local reinforcement is carried out if necessary, only the grout returning pipe which extends into the crown arch by 9m is left for draining until the water diversion pipe is completely closed, and pure water slurry is adopted for grouting.
(1) Grouting materials: p.042.5 ordinary portland cement is adopted, the water cement ratio W to C is 0.5:1, the water glass ratio is 1:0.03, and the cement can be properly adjusted according to the actual situation on site.
(2) Grouting equipment: the grouting equipment adopts a high-pressure grouting pump.
(3) A measuring tool: the on-site measuring tool adopts a grouting recorder, a measuring tank, an electronic scale and the like.
(4) Sealing grouting pressure on the tunnel face and the periphery: grouting pressure is 0.2-0.6 MPa, the grouting pressure is gradually increased from small to large, the pressure is increased by 0.02MPa each time, grouting is slow and urgent is avoided; and (4) when the minimum slurry-feeding amount is 10-20L/min or the grouting pressure is stabilized at 0.6 mMpa after continuous grouting for 15min, finishing the hole grouting work and entering lower hole grouting.
(5) And (3) stopping the water inrush point and grouting to finish the standard: and stopping grouting the grouting pipe (or finishing grouting according to the instructions of owners and supervision) after the grout return pipe returns the thick grout.
And step S6, grouting effect inspection and vault advance support, grouting completion, advanced exploratory hole drilling inspection, if the water burst of the exploratory hole is large, deep hole drilling is continued for water shutoff grouting, and if the water volume is small or no water exists, subsequent construction can be carried out.
Checking the grouting effect from the water retaining wall to the tunnel face: 1 advance exploratory hole is laid respectively near top and bottom to the waterwall, whether seepage gushes water and judges the strength of the condensate according to the drilling speed, if gushing water or insufficient strength of the condensate appears in the drilling hole, grouting consolidation plugging is carried out again before excavation.
And (3) checking the grouting effect of the vault: 12 advanced detection holes with the length of 20m (the aperture is phi 50, the distance is 0.8m, the external deflection angle is 14 degrees, 22 degrees and 30 degrees and is 4 respectively) are arranged on the arch top of the main tunnel expanding excavation section, the grouting effect at the positions 3m, 5m and 7m above the water burst point of the tunnel face can be checked, if no water burst phenomenon exists, the detection holes are used for carrying out phi 32 advanced anchor rod installation and grouting anchoring, the anchor rod length is 20m, the advanced support effect can be achieved, and later excavation is facilitated; and if water gushes in the drilled hole, grouting, solidifying and plugging are continuously carried out, and after grouting and plugging are finished, the hole is punched again to construct the advanced anchor rod.
The advanced prospecting hole is drilled by a down-the-hole drill, the hole diameter is 50mm, and grouting is carried out in time if water seepage and gushing occur in the drilling process.
Step S7, dredging after grouting, removing temporary measures, building permanent facilities, and gradually dredging and removing construction channels and platforms from inside to outside manually; excavating and supporting a main water collecting well, and transferring and installing a water pump regularly; and finally pouring the bottom plate cushion layer.
And step S8, blasting and removing the retaining wall and the consolidation body, blasting and removing the downstream retaining wall and the consolidation body after the water burst channel is completely closed and a stable water-resisting layer is formed, and blasting with multiple holes, small dosage and short footage for reducing disturbance. And (4) cutting off the connecting part of the steel bar and the section steel by oxygen welding after blasting.
In the step S2, one cofferdam 4 is arranged at intervals of 5.5m, the construction channel and the operation platform are formed by erecting steel pipes, steel bars and wood plates above the cofferdam 4, the steel bars and the steel pipes are firmly bound and stably erected above the cofferdam 4, then the wood plates are laid above the steel bars, the cofferdam 4 is utilized to form a multistage sedimentation tank, the sand content is reduced when water burst is discharged conveniently, and the construction channel and the operation platform are convenient for workers to construct.
When the step S3 is carried out, a water blocking ridge is built at the bottom of the face by sand bags, 8 DN200 drainage tubes and 5 DN32 grouting tubes are pre-embedded, one grouting tube extends into the top arch 6m, the other grouting tube extends into the top arch 9m, before the water retaining wall is poured, bagged cement is used for stacking as a supporting template, one water blocking ridge is built by sand bags, water flow can be temporarily blocked, the water flow is prevented from influencing the building of the water retaining wall 1, meanwhile, the template is convenient to fix, the fixing of the pouring mold of the water retaining wall 1 is realized, water gushing can be extracted by the drainage tubes, water gushing accumulation is avoided, the grouting tubes are used for grouting water gushing points after the water retaining wall is poured, the grouting tubes extending into the top arch 6m are used for final grouting operation, and the grouting tubes extending into the top arch 9m are used for grout return.
In the step S4, a full frame is erected by adopting a phi 50 steel pipe as an operation platform to improve the strength of a supporting structure, in the step S4, consolidation grouting is performed on the side top arch of the tunnel, cement-water glass double-liquid slurry is adopted for consolidation grouting, the water cement ratio W: C is 0.5:1, and cement: the water glass is prepared from
The grouting holes are arranged at intervals of 3m by 3m, the depth of each grouting hole is 5m to 6m, the inner diameter is phi 50 to phi 60, the grouting pressure is linearly increased, the maximum grouting pressure is 0.8MPa, the minimum grout-feed quantity when the final grouting pressure is reached is 10L/min to 20L/min, the grouting is stopped for 10 min to 15min, after the consolidation grouting is finished, phi 32 to phi 36 prestressed anchor rods are arranged on a tunnel top arch and a side wall, the length specification of the prestressed anchor rods is 6m and 9m, the prestressed anchor rods are exposed by 20cm, the prestressed anchor rods are arranged at intervals of 3m by 3m and are fixed by steel supporting plates, the prestressed anchor rods adopt down-the-hole drilling for hole forming, the stability of a rock body can be enhanced after the grouting, and a water-proof layer is formed to prevent the grout leakage phenomenon.
In the step S5, after the concrete of the retaining wall reaches the designed strength, grouting construction is started, when the lower half part of the retaining wall is grouted, a gate valve of a water diversion steel pipe at the bottom is closed, a steel pipe at the top is used for centralized drainage, so that the lower water behind the retaining wall is in a static state, firstly, double-liquid-slurry grouting is carried out through 3 grouting pipes pre-embedded at the bottom, after the pre-embedded pipe grouting is finished, holes are drilled at the bottom and two sides of the retaining wall by a hand drill, the hole diameter phi 32, the hole depth 3m and the space 1m are used as double-liquid-slurry grouting holes of the walls at the bottom and two sides, grouting at the bottom and the periphery of the retaining wall is continued until water gushing at the bottom and the periphery of the retaining wall is completely blocked, after grouting at the bottom and the periphery, water plugging grouting is carried out by utilizing the grouting pipes pre-embedded at the top to block water, grouting is carried out by utilizing the grouting pipes deep into the top arch 6m during grouting, the upper water discharge pipe gate valve is closed one by one and various measures and the stable conditions and the peripheral water seepage conditions are observed, if necessary, local reinforcement is carried out, only a grout returning pipe which extends into the top arch by 9m is reserved for drainage until the water conduit is completely closed, cement-water glass double-liquid grout is adopted, and water inrush points are blocked through grouting, so that the influence of water inrush on tunnel construction is avoided.
In the step S5, the grouting material is p.042.5 portland cement, the water cement ratio W: C is 0.5:1, the water glass ratio is 1:0.03, the tunnel face and the surrounding closed grouting pressure is 0.2 to 0.6MPa, the grouting pressure is increased from small to large, the pressure is increased from 0.02MPa each time, the minimum grout consumption is 10 to 20L/min after continuous grouting for 15min or the grouting pressure is stabilized at 0.6MPa, the hole grouting operation can be ended, the lower hole grouting can be started, the grouting plugging effect is improved, the timing of stopping grouting can be accurately judged according to the grout consumption, and the grouting quality is improved.
In the step S6, 1 advance probing hole is respectively arranged at the top and the bottom of the water retaining wall, whether water seeps or not is checked, the strength of the condensate is judged according to the drilling speed, if water gushes or the condensate is insufficient in the drilled hole, grouting consolidation plugging is carried out again before excavation, 12 advance probing holes with the length of 20m are arranged at the arch crown at the back of the water retaining wall, the grouting effect at the positions 3m, 5m and 7m above the water gushing point of the tunnel face is checked, if no water gushing phenomenon exists, a phi 32 advance anchor rod is installed and grouted for anchoring by using the probing holes, the length of the anchor rod is 20m, grouting consolidation plugging is carried out continuously if water gushes in the drilled hole, after grouting plugging is finished, the advance anchor rod is drilled again, the plugging effect is judged by the probing holes, and necessary conditions are provided for the designation of a construction scheme conveniently.
In the step S8, after the water burst channel is completely closed and a stable water-proof layer is formed, blasting and dismantling the water-retaining wall and the consolidation body, blasting with multiple holes, small dosage and short feed-length, and cutting off the connecting part of the steel bar and the section steel by oxygen welding after blasting.

Claims (10)

1.一种隧洞突水点应急抢险封堵结构,其特征在于:包括挡水墙(1),所述挡水墙(1)两侧设有袋装水泥砌筑(2),且在一侧的袋装水泥砌筑(2)内设有斜支撑(3);所述挡水墙(1)一侧设有多堵围堰(4),挡水墙(1)上设有多根引流管(5),引流管(5)一端贯穿挡水墙(1)和袋装水泥砌筑(2),引流管(5)另一端自由伸入并安装阀门;所述挡水墙(1)中设有多根灌浆管(6),灌浆管(6)贯穿挡水墙(1)和袋装水泥砌筑(2)。1. A tunnel water inrush point emergency rescue and blocking structure is characterized in that: comprising a water retaining wall (1), both sides of the retaining wall (1) are provided with bagged cement masonry (2), and a The side bagged cement masonry (2) is provided with an inclined support (3); one side of the water retaining wall (1) is provided with a plurality of cofferdams (4), and the water retaining wall (1) is provided with a plurality of cofferdams (4). A drainage pipe (5), one end of the drainage pipe (5) penetrates the retaining wall (1) and the bagged cement masonry (2), and the other end of the drainage pipe (5) freely extends into and installs a valve; the retaining wall (1) ) is provided with a plurality of grouting pipes (6), and the grouting pipes (6) penetrate through the retaining wall (1) and the bagged cement masonry (2). 2.如权利要求1所述的一种隧洞突水点应急抢险封堵结构,其特征在于:所述挡水墙(1)内设有钢筋网(7)和工字钢支撑(8),钢筋网(7)和工字钢支撑(8)相互连接组成框架结构,且挡水墙(1)上部和下部均设有植筋(9)。2. An emergency rescue and blocking structure for a tunnel water inrush point as claimed in claim 1, characterized in that: said water retaining wall (1) is provided with a steel mesh (7) and an I-beam support (8), The steel mesh (7) and the I-beam support (8) are connected to each other to form a frame structure, and the upper and lower parts of the retaining wall (1) are provided with planting bars (9). 3.如权利要求1至2任意一项所述一种隧洞突水点应急抢险封堵结构的施工方法,其特征包括以下步骤:3. the construction method of a kind of tunnel water inrush point emergency rescue plugging structure as described in any one of claim 1 to 2, it is characterized in that comprising the following steps: 步骤S1,施工准备;Step S1, construction preparation; 步骤S2,施工通道及操作平台搭建;Step S2, construction of a construction channel and an operation platform; 步骤S3,挡水墙浇筑;Step S3, the retaining wall is poured; 步骤S4,洞内岩体加固及加强支护;Step S4, the rock mass in the cave is reinforced and the support is strengthened; 步骤S5,掌子面及周边封闭、突水点封堵;Step S5, the face and the surrounding area are closed, and the water inrush point is blocked; 步骤S6,灌浆效果检查及拱顶超前支护;Step S6, check the grouting effect and advance the support of the vault; 步骤S7,灌浆后清淤、临时措施拆除、永久设施建设;Step S7, dredging after grouting, demolition of temporary measures, and construction of permanent facilities; 步骤S8,挡墙、固结体爆破拆除。Step S8, the retaining wall and the consolidation body are demolished by blasting. 4.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S2中,每隔5.5m设置一道围堰(4),施工通道及操作平台采用钢管、钢筋及木板在围堰(4)上方搭设形成,钢筋与钢管绑扎牢靠并稳定架设在围堰(4)上方,然后将木板铺设在钢筋上方。4. The construction method of a tunnel water inrush point emergency rescue and blocking structure as claimed in claim 3, characterized in that: in the step S2, a cofferdam (4) is set every 5.5m, and the construction access and operation The platform is formed by using steel pipes, steel bars and wooden boards to be erected above the cofferdam (4). The steel bars and steel pipes are firmly and stably erected above the cofferdam (4), and then the wooden boards are laid over the steel bars. 5.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S3施工时在掌子面底部采用砂袋砌筑一道拦水坎,预埋8根DN200引流管和5根DN32灌浆管,且其中一根灌浆管深入顶拱6m,一根深入顶拱9m,挡水墙浇筑前,使用袋装水泥堆叠作为支撑模板。5. The construction method of a tunnel water inrush point emergency rescue and blocking structure as claimed in claim 3, characterized in that: during the construction of the step S3, a sand bag is used to build a water retaining sill at the bottom of the tunnel face, and Bury 8 DN200 drainage pipes and 5 DN32 grouting pipes, and one of the grouting pipes is 6m deep into the top arch and the other is 9m deep into the top arch. Before the retaining wall is poured, bagged cement stacks are used as supporting templates. 6.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S4中采用φ50钢管搭设满堂架作为操作平台,步骤S4中对隧洞边顶拱进行固结灌浆处理,固结灌浆采用水泥-水玻璃双液浆,水灰比W:C=0.5:1,水泥:水玻璃配比为=1:0.03,灌浆孔以3m*3m间隔排布,灌浆孔深5m至6m,内径为φ50至φ60,灌浆压力呈线性增加,最大灌浆压力为0.8MPa,达到灌浆终压时的最小吃浆量为10~20L/min,时间维持10~15min停止灌浆,固结灌浆完成后,在隧洞顶拱及边墙布设φ32至φ36预应力锚杆,预应力锚杆长度规格为6m和9m,且预应力锚杆外露20cm,预应力锚杆以3m*3m间隔排布,且采用钢托板固定,预应力锚杆采用潜孔钻造孔。6. the construction method of a kind of tunnel water inrush point emergency rescue and blocking structure as claimed in claim 3, it is characterized in that: in described step S4, adopt φ50 steel pipe to erect full hall frame as operating platform, in step S4, to the tunnel side roof The arch is treated with consolidation grouting. The consolidation grouting adopts cement-water glass double-liquid slurry, the water-cement ratio is W:C=0.5:1, the cement:water glass ratio is 1:0.03, and the grouting holes are arranged at intervals of 3m*3m. Cloth, the depth of the grouting hole is 5m to 6m, the inner diameter is φ50 to φ60, the grouting pressure increases linearly, the maximum grouting pressure is 0.8MPa, the minimum grouting amount when the final grouting pressure is reached is 10 ~ 20L/min, and the time is maintained for 10 ~ 15min Stop grouting, and after the consolidation grouting is completed, lay φ32 to φ36 prestressed anchors on the top arch and side wall of the tunnel. The lengths of the prestressed anchors are 6m and 9m, and the prestressed anchors are exposed by 20cm, and the prestressed anchors are 3m *It is arranged at intervals of 3m, and is fixed by steel pallets, and the prestressed anchors are drilled through down-the-hole. 7.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S5中,在挡水墙混凝土达到设计强度后,开始进行灌浆施工,挡水墙下半部灌浆时将底部引水钢管闸阀关闭,转而使用顶部钢管集中排水,使挡水墙后下部水处于静态,先通过底部预埋的3个注浆管进行双液浆灌浆,预埋管灌浆完成后,再采用手风钻在挡墙底部及两侧基础面钻孔,孔径φ32,孔深3m,间距1m,作为底部及两侧墙双液浆灌浆灌浆孔,继续进行挡墙底部及周边灌浆,直至挡墙底部及周边涌水全部堵住,底部及周边灌浆完成后,利用顶部预埋灌浆管进行掌子面堵水灌浆,灌浆时利用深入顶拱6m的灌浆管进行灌浆,并逐个关闭上部排水管闸阀并观察各类措施稳定状况及周边渗水情况,如有必要进行局部加固,直至引水管全部关闭只有留深入顶拱9m的回浆管排水,采取水泥-水玻璃双液浆。7. The construction method of a tunnel water inrush point emergency rescue and plugging structure according to claim 3, characterized in that: in the step S5, after the concrete of the retaining wall reaches the design strength, grouting construction is started, and the retaining wall When grouting the lower part of the water wall, close the gate valve of the bottom water diversion steel pipe, and use the top steel pipe for centralized drainage, so that the water in the lower part of the retaining wall is static. After the buried pipe grouting is completed, use a hand pneumatic drill to drill holes at the bottom of the retaining wall and the foundation surfaces on both sides, with a diameter of φ32, a hole depth of 3m, and a spacing of 1m, as the double-liquid grouting grouting holes for the bottom and both sides of the wall, and continue to carry out the bottom of the retaining wall. and the surrounding grouting until the bottom of the retaining wall and the surrounding water are all blocked. After the bottom and surrounding grouting is completed, use the top pre-buried grouting pipe for water blocking and grouting on the face of the tunnel. When grouting, use the grouting pipe 6m deep into the top arch for grouting. Close the gate valve of the upper drainage pipe one by one and observe the stability of various measures and the surrounding water seepage. If necessary, perform local reinforcement until all the water diversion pipes are closed. Only the slurry return pipe that is 9m deep into the top arch is used for drainage, and cement-water glass double slurry is used. . 8.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S5中,灌浆材料采用P.042.5普通硅酸盐水泥,水灰比W:C=0.5:1,水玻璃配比为=1:0.03,掌子面及周边封闭灌浆压力采用0.2~0.6MPa,先小后大逐级提升,每次提升压力为0.02Mpa,连续灌注15min最小吃浆量为10~20L/min或灌浆压力稳定在0.6Mpa时,可以结束该孔灌浆工作,进入下孔灌浆。8. The construction method of a tunnel water inrush point emergency rescue and plugging structure as claimed in claim 3, characterized in that: in the step S5, the grouting material adopts P.042.5 ordinary Portland cement, and the water-cement ratio is W : C = 0.5: 1, the ratio of water glass = 1: 0.03, the closed grouting pressure of the face and surrounding area is 0.2 ~ 0.6 MPa, and the pressure is gradually increased. When the minimum amount of grouting is 10-20L/min or the grouting pressure is stable at 0.6Mpa, the grouting work of this hole can be ended and the grouting can be entered into the lower hole. 9.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S6中,挡水墙靠近顶部和底部分别布设1个超前探孔,检查是否有渗涌水并根据钻进速度判断凝结体强度,如钻孔中出现涌水或凝结体强度不足,开挖前再次进行灌浆固结封堵,挡水墙后拱顶布设12个20m长超前探孔,检查掌子面涌水点上方3m、5m、7m处的灌浆效果,若无涌水现象则利用探孔进行φ32超前锚杆安装并注浆锚固,锚杆长度20m,若钻孔中出现涌水则继续进行灌浆固结封堵,灌浆封堵完成后,重新打孔施做超前锚杆。9. The construction method of a tunnel water inrush point emergency rescue and plugging structure as claimed in claim 3, characterized in that: in the step S6, a water-retaining wall is respectively arranged with one advance exploration hole near the top and the bottom, and the inspection Whether there is seepage of water and judge the strength of the condensate according to the drilling speed. If there is water inflow in the borehole or the strength of the condensate is insufficient, grouting and consolidation shall be performed again before excavation, and 12 20m long advance probes shall be arranged on the dome behind the retaining wall. Check the grouting effect at 3m, 5m and 7m above the water gushing point on the face of the face. If there is no water gushing phenomenon, use the probe hole to install the φ32 advanced bolt and grouting anchor. The length of the bolt is 20m. Continue grouting consolidation and plugging. After the grouting and plugging are completed, re-drill holes and apply advanced bolts. 10.如权利要求3所述的一种隧洞突水点应急抢险封堵结构的施工方法,其特征在于:所述步骤S8中,待涌水通道完全封闭且形成稳定隔水层后,对挡水墙及固结体进行爆破拆除,采取多布孔、小药量、短进尺爆破,爆破后钢筋及型钢连接部位采用氧焊割除。10. The construction method of a tunnel water inrush point emergency rescue and plugging structure according to claim 3, characterized in that: in the step S8, after the water inrush channel is completely closed and a stable water barrier is formed, The wall and the consolidation body shall be blasted and demolished by blasting with multiple holes, small charge and short footage. After blasting, the connecting parts of steel bars and section steels shall be cut by oxygen welding.
CN202111437247.6A 2021-11-29 2021-11-29 A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method Pending CN113914909A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111437247.6A CN113914909A (en) 2021-11-29 2021-11-29 A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111437247.6A CN113914909A (en) 2021-11-29 2021-11-29 A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method

Publications (1)

Publication Number Publication Date
CN113914909A true CN113914909A (en) 2022-01-11

Family

ID=79248331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111437247.6A Pending CN113914909A (en) 2021-11-29 2021-11-29 A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method

Country Status (1)

Country Link
CN (1) CN113914909A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114562275A (en) * 2022-02-28 2022-05-31 中电建十一局工程有限公司 A method for secondary expansion and excavation of loose-body stratum lining tunnels

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1858405A (en) * 2006-06-06 2006-11-08 宋彦波 Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel
JP2009174171A (en) * 2008-01-23 2009-08-06 Kajima Corp Water stop grout method and system under high water pressure
CN201554493U (en) * 2009-07-31 2010-08-18 中冶集团华冶资源开发有限责任公司 Quick water-retaining wall in mine
CN205422815U (en) * 2016-03-14 2016-08-03 河北钢铁集团矿业有限公司 Big flood underground mine tunnel waterwall
CN108316260A (en) * 2018-02-28 2018-07-24 中国能源建设集团广西水电工程局有限公司 Plugging structure for diversion tunnel based on karst landform and method
CN109853477A (en) * 2018-12-21 2019-06-07 长江勘测规划设计研究有限责任公司 Change the concentrative seepage plugging structure and method that dynamic water is hydrostatic in gallery
CN209129631U (en) * 2018-11-20 2019-07-19 河北钢铁集团矿业有限公司 The wall for grouting speedily carried out rescue work for Water-rich deposit tunnel gushing water
CN216130944U (en) * 2021-11-29 2022-03-25 中国水利水电第九工程局有限公司 Emergent plugging structure that speedily carries out rescue work of tunnel water spot

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1858405A (en) * 2006-06-06 2006-11-08 宋彦波 Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel
JP2009174171A (en) * 2008-01-23 2009-08-06 Kajima Corp Water stop grout method and system under high water pressure
CN201554493U (en) * 2009-07-31 2010-08-18 中冶集团华冶资源开发有限责任公司 Quick water-retaining wall in mine
CN205422815U (en) * 2016-03-14 2016-08-03 河北钢铁集团矿业有限公司 Big flood underground mine tunnel waterwall
CN108316260A (en) * 2018-02-28 2018-07-24 中国能源建设集团广西水电工程局有限公司 Plugging structure for diversion tunnel based on karst landform and method
CN209129631U (en) * 2018-11-20 2019-07-19 河北钢铁集团矿业有限公司 The wall for grouting speedily carried out rescue work for Water-rich deposit tunnel gushing water
CN109853477A (en) * 2018-12-21 2019-06-07 长江勘测规划设计研究有限责任公司 Change the concentrative seepage plugging structure and method that dynamic water is hydrostatic in gallery
CN216130944U (en) * 2021-11-29 2022-03-25 中国水利水电第九工程局有限公司 Emergent plugging structure that speedily carries out rescue work of tunnel water spot

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张晓静: "强透水地基上水闸底板施工新方法", 黑龙江水专学报, vol. 30, no. 02, 30 June 2003 (2003-06-30), pages 100 - 101 *
胡文武等: "矿井巷道突水封堵技术的研究与应用", 煤矿现代化, no. 1, 31 January 2019 (2019-01-31), pages 64 - 66 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114562275A (en) * 2022-02-28 2022-05-31 中电建十一局工程有限公司 A method for secondary expansion and excavation of loose-body stratum lining tunnels

Similar Documents

Publication Publication Date Title
WO2022100346A1 (en) Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method
CN205742213U (en) Foundation pit supporting construction
CN107542108A (en) A kind of reverse construction method of building basement structure
CN111997624A (en) Shallow-buried large-section underground excavation rectangular tunnel construction method
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN107869351A (en) A kind of method of the high narrow large-scale solution cavity Cavity treatment security protection of type
CN110700280A (en) A kind of diversion device and construction method for foundation pit support construction in narrow area
CN110080248A (en) Nearly depth of water foundation pit supporting construction
CN113266392A (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN114541408B (en) Front upper part wind-containing well structure of underground station end well and underpass construction method thereof
CN110777775A (en) Foundation pit structure and construction method thereof
CN215105880U (en) Concrete inverted well suitable for connecting new and old water supply and drainage pipelines
CN114542086A (en) Construction method of large-span section underground excavation tunnel influenced by underground water
CN113914909A (en) A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method
CN211816279U (en) New and old ground is wall interface processing structure even
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN216130944U (en) Emergent plugging structure that speedily carries out rescue work of tunnel water spot
CN104480945A (en) Inversed construction method for foundation pit
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN106013168A (en) Slag trough structure and construction method for same
CN216664152U (en) Water sealing structure for anchorage support
CN116876518A (en) Construction method suitable for foundation pit supporting of assembled subway entrance and exit in soft soil area
CN205804366U (en) A kind of slag runner structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination