CN113833020B - Construction method of large fish-belly inclined column structure in underground space - Google Patents
Construction method of large fish-belly inclined column structure in underground space Download PDFInfo
- Publication number
- CN113833020B CN113833020B CN202111160389.2A CN202111160389A CN113833020B CN 113833020 B CN113833020 B CN 113833020B CN 202111160389 A CN202111160389 A CN 202111160389A CN 113833020 B CN113833020 B CN 113833020B
- Authority
- CN
- China
- Prior art keywords
- column
- columns
- reserved
- slanted
- joints
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 69
- 238000009412 basement excavation Methods 0.000 claims abstract description 21
- 229910000831 Steel Inorganic materials 0.000 claims description 76
- 239000010959 steel Substances 0.000 claims description 76
- 238000009434 installation Methods 0.000 claims description 21
- 238000000034 method Methods 0.000 claims description 21
- 238000013461 design Methods 0.000 claims description 13
- 238000005259 measurement Methods 0.000 claims description 10
- 230000008569 process Effects 0.000 claims description 10
- 238000003466 welding Methods 0.000 claims description 10
- 238000012545 processing Methods 0.000 claims description 4
- 238000012552 review Methods 0.000 claims description 4
- 230000035515 penetration Effects 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 238000005728 strengthening Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 abstract description 3
- 230000006872 improvement Effects 0.000 description 12
- 239000012780 transparent material Substances 0.000 description 5
- 238000011161 development Methods 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0007—Base structures; Cellars
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0007—Base structures; Cellars
- E04B1/0015—Cellars constructed from prefabricated units
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2220/00—Temporary installations or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Electromagnetism (AREA)
- Life Sciences & Earth Sciences (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明提供了一种地下空间大型鱼腹式斜柱结构施工方法。本发明摒弃传统的梁、柱体系,采用鱼腹式多层分段斜柱结构,包括各层斜柱预留接头、各层斜柱拼接段。本发明多层分段斜柱结构采用盖挖逆作结合盖挖顺作的施工方法,施工时先逆作各层斜柱预留接头、再顺作各层斜柱拼接段;鱼腹式的斜柱对称布置改善了地下结构的自然采光,增加了地下空间的使用面积。本发明施工方法克服了施工场地狭小、周边地上建筑物繁多、地面交通组成复杂等缺点,不仅方便了施工、提升了工程施工的安全性,且缩短了施工工期。
The invention provides a construction method for a large-scale fish-bellied inclined column structure in an underground space. The invention abandons the traditional beam and column system and adopts a fish-bellied multi-layered segmented inclined column structure, including reserved joints for each layer of inclined columns and splicing sections for each layer of inclined columns. The multi-layer segmented inclined column structure of the present invention adopts the construction method of cover and excavation combined with cover and excavation. During construction, the reserved joints of the inclined columns of each layer are first made inversely, and then the splicing sections of the inclined columns of each layer are made in parallel; The symmetrical arrangement of the inclined columns improves the natural lighting of the underground structure and increases the usable area of the underground space. The construction method of the invention overcomes the shortcomings of narrow construction site, many surrounding ground buildings, and complex ground traffic composition, which not only facilitates construction, improves the safety of construction, but also shortens the construction period.
Description
技术领域technical field
本发明涉及建筑施工技术领域,特别涉及一种地下空间大型鱼腹式斜柱结构施工方法。The invention relates to the technical field of building construction, in particular to a construction method for a large fish-belly oblique column structure in an underground space.
背景技术Background technique
如今,随着城市、甚至国家之间的竞争逐渐升级,其内部地区和城市之间的竞争变得更加激烈,从而导致城市交通拥堵问题日益突出。传统的交通枢纽由于缺乏特色、只满足于功能、结构形式单调等原因越来越不能满足人民的需求,解决此问题的手段之一就是建立立体化交通体系,建设地下综合交通枢纽,充分开发与利用城市地下空间资源。然而,在大城市的繁华闹市区进行地下综合枢纽开发工程项目,通常具有场地狭小、周边地上建筑物繁多、地面交通组成复杂等问题。Nowadays, with the gradual escalation of competition between cities and even countries, the competition between their internal regions and cities has become more intense, which has led to the increasingly prominent problem of urban traffic congestion. Traditional transportation hubs are increasingly unable to meet the needs of the people due to lack of characteristics, only satisfied with functions, and monotonous structural forms. One of the means to solve this problem is to establish a three-dimensional transportation system, build an underground comprehensive transportation hub, fully develop and Utilize urban underground space resources. However, the underground comprehensive hub development project in the bustling downtown area of a big city usually has problems such as a small site, many surrounding above-ground buildings, and complex ground transportation.
对于大型地下交通枢纽而言,如何改善其有限的通风采光并充分利用地下使用空间往往是设计焦点,但传统的梁柱结构受力体系并不能很好的满足地下交通枢纽功能性和美观性设计需求。复杂的路面疏解条件、严苛周边环境的限制,以及采用盖挖逆作法施工过程中地下结构独特的构造与逆作法冲突,更是对地下结构施工方法提出了很大的挑战。For large underground transportation hubs, how to improve its limited ventilation and lighting and make full use of the underground use space is often the focus of design, but the traditional beam-column structural stress system cannot well satisfy the functional and aesthetic design of underground transportation hubs need. Complex pavement deconstruction conditions, strict surrounding environment restrictions, and the unique structure of the underground structure during the construction process using the cover-and-excavation upside-down method conflict with the upside-down method, all of which pose great challenges to the construction method of the underground structure.
发明内容Contents of the invention
为满足现代建筑设计的地下交通枢纽有限的地下空间条件下的开敞、空间效果等设计需求并改善其通风采光条件,摒弃传统的梁、柱体系,本发明采用鱼腹式多层分段斜柱结构,提出一种地下空间大型鱼腹式斜柱结构施工方法。In order to meet the design requirements of openness and space effects in the limited underground space of the underground transportation hub in modern architectural design and to improve its ventilation and lighting conditions, and to abandon the traditional beam and column system, the present invention adopts a fish-belly multi-layer segmental oblique Column structure, a construction method of large fish-belly oblique column structure in underground space is proposed.
本发明的核心技术在于采用盖挖逆作法施工时先逆作各层斜柱预留接头,再顺作各层斜柱拼接段,各层斜柱预留接头和斜柱拼接段构成鱼腹式多层分段斜柱。在斜柱拼接段施工之前就已经确定了多层分段斜柱的倾角,极大的简化了施工,同时鱼腹式的斜柱对称布置形式也更有利于地下结构的自然采光。The core technology of the present invention is that when adopting the cover-and-excavation construction method, the reserved joints of the inclined columns of each layer are reversed first, and then the splicing sections of the inclined columns of each layer are made sequentially. Multi-storey segmented slanted columns. The inclination angle of the multi-layer segmented slanted columns has been determined before the construction of the slanted column splicing section, which greatly simplifies the construction. At the same time, the symmetrical arrangement of the fish-bellied slanted columns is also more conducive to the natural lighting of the underground structure.
本发明具体是通过如下技术方案实现的:The present invention is specifically achieved through the following technical solutions:
一种地下空间大型鱼腹式斜柱结构施工方法,包括以下步骤:A construction method for a large fish-belly inclined column structure in an underground space, comprising the following steps:
1)施工准备:根据设计尺寸在加工厂进行型钢梁、斜柱预留接头加工,将斜柱预留接头与主体结构横梁连接成整体;1) Construction preparation: According to the design size, the reserved joints of shaped steel beams and slanted columns are processed in the processing factory, and the reserved joints of slanted columns are connected with the main structural beams into a whole;
2)垫层及预埋件施工:施作盖板区域土方开挖,盖板基坑开挖清底后立即进行垫层混凝土浇筑;在斜柱下方施作开挖作为架设支撑的“基础”,然后在作为架设支撑的“基础”内放线、安装预埋钢板,用钢筋将钢板底部连接,浇筑混凝土;2) Cushion and embedded parts construction: Excavate the earthwork in the cover plate area, and pour the cushion concrete immediately after the foundation pit of the cover plate is excavated and cleared the bottom; excavate under the inclined column as the "foundation" for erecting support , and then lay out wires and install embedded steel plates in the "foundation" as the erection support, connect the bottom of the steel plates with steel bars, and pour concrete;
3)测量放样:对型钢梁、斜柱预留接头进行建模,根据设计坐标与安装位置标高计算安装接头坐标,当计算安装接头坐标与建模调出的坐标一致后作为测量放线的依据;在测量弹出的安装边线处焊接定位钢板,然后安装各层斜柱预留接头,安装完成后测量斜柱预留接头上下端控制点,据此制作各层斜柱拼接段;3) Measurement and setting out: model the reserved joints of shaped steel beams and inclined columns, calculate the coordinates of the installation joints according to the design coordinates and the elevation of the installation position, and when the coordinates of the calculated installation joints are consistent with the coordinates called out from the modeling, it will be used as the measurement setting out Basis; Weld the positioning steel plate at the installation side line that pops up, and then install the reserved joints of the inclined columns of each layer. After the installation is completed, measure the control points of the upper and lower ends of the reserved joints of the inclined columns, and make the splicing sections of the inclined columns of each layer accordingly;
4)型钢梁、斜柱预留接头吊装:根据步骤3)放样位置将斜柱预留接头安装至设计位置,斜柱预留接头安装完成后根据现场实际长度加工型钢梁并将其安装;4) Hoisting of the reserved joints of shaped steel beams and inclined columns: install the reserved joints of inclined columns to the design position according to the stakeout position in
5)型钢梁、斜柱预留接头定位加固:对型钢梁顶标高及斜柱预留接头轴线、垂直度、角度进行复核并微调,上述定位完成后进行加固措施;定位加固后需再对型钢梁和斜柱预留接头轴线、标高进行复核,无误后方可进入下一步;5) Positioning and strengthening of reserved joints of shaped steel beams and inclined columns: review and fine-tune the elevation of the top of shaped steel beams and the axis, verticality, and angle of reserved joints of inclined columns, and perform reinforcement measures after the above positioning is completed; Check the axes and elevations of the joints reserved for the shaped steel beams and inclined columns, and proceed to the next step only after they are correct;
6)斜柱拼接段施工:上述主体结构施工完毕后,将斜柱拼接段采用盖挖顺作法施工;将斜柱拼接段吊起移至拼接段位置,利用预留限位夹板调整斜柱拼接段与斜柱预留接头完全对位,准确定位后全熔透焊焊接。6) Construction of the splicing section of the inclined column: After the construction of the above main structure is completed, the splicing section of the inclined column shall be constructed by the method of cover and excavation; the splicing section of the inclined column shall be hoisted and moved to the position of the splicing section, and the splicing of the inclined column shall be adjusted by using the reserved limit splint The section and the reserved joint of the inclined column are completely aligned, and the full penetration welding is performed after accurate positioning.
作为上述技术方案的进一步改进,所述各层斜柱预留接头和所述各层斜柱拼接段构成鱼腹式多层分段斜柱。As a further improvement of the above technical solution, the reserved joints of the slanted columns of each layer and the spliced sections of the slanted columns of each layer constitute a fish-bellied multi-layer segmented slanted column.
作为上述技术方案的进一步改进,所述多层分段斜柱构成的鱼腹式对称布置,最大程度保证了地下空间的自然采光。As a further improvement of the above-mentioned technical solution, the fish-belly symmetrical arrangement of the multi-layer segmented inclined columns ensures the natural lighting of the underground space to the greatest extent.
作为上述技术方案的进一步改进,所述多层分段斜柱采用盖挖逆作与盖挖顺作结合的施工方法:施工时先逆作各层斜柱预留接头,再顺作各层斜柱拼接段。As a further improvement of the above-mentioned technical scheme, the multi-layer segmental slanted column adopts a construction method combining cover-excavation reverse operation and cover-excavation sequential operation: during construction, the slanted columns of each layer are first reversed to reserve joints, and then the slanted columns of each layer are constructed in an orderly manner. Column splicing segment.
考虑到鱼腹式斜柱数量多且重量大,给各层板施加荷载,从而导致临时柱的受力过大,本发明先盖挖逆作各层斜柱预留接头,可减小临时柱的受力,降低鱼腹式复杂的大型地下结构施工过程中围护结构的水平变形,减少临时支撑系统的工程量和大型开挖工作平台等临时设施的需求,从而降低对周边环境的影响,提高了工程施工的安全性并缩短了施工工期;逆作各层斜柱预留接头后再盖挖顺作各层斜柱拼接段可减少斜柱拼装过程中的交叉作业,降低多层拼装过程中上下层间的作业干扰,有效增加施工作业面,从而显著提升工程质量。Considering the large number and heavy weight of the fish-belly slanted columns, loads are applied to each layer of the slabs, resulting in excessive stress on the temporary columns. In this invention, the joints reserved for the slanted columns of each layer are covered first, which can reduce the number of temporary columns. reduce the horizontal deformation of the enclosure structure during the construction of a fish-belly complex large-scale underground structure, reduce the engineering volume of the temporary support system and the demand for temporary facilities such as large-scale excavation work platforms, thereby reducing the impact on the surrounding environment. The safety of the project construction is improved and the construction period is shortened; the reserved joints of the slanted columns of each layer are reversed, and then the splicing sections of the slanted columns of each layer are covered and excavated, which can reduce the cross operation during the assembling process of the slanting columns and reduce the multi-layer assembly process. The operation interference between the upper and lower floors can effectively increase the construction work area, thereby significantly improving the quality of the project.
作为上述技术方案的进一步改进,各层板之间安装有临时立柱,在斜柱拼接段施工之前为主体结构提供临时支撑。As a further improvement of the above technical solution, temporary columns are installed between the slabs to provide temporary support for the main structure before the construction of the inclined column splicing section.
作为上述技术方案的进一步改进,顶板处鱼腹式斜柱之间安装有透明材料的天窗,目的是为了提高地下结构的自然采光。As a further improvement of the above technical solution, a skylight of transparent material is installed between the fish-belly slanted columns on the roof, in order to improve the natural lighting of the underground structure.
作为上述技术方案的进一步改进,步骤2)所述施作盖板区域土方开挖4m,开挖至顶板底下2.2m处为止,其余各层开挖至层板底2m处;盖板基坑开挖至接近基底200mm处。As a further improvement of the above-mentioned technical solution, excavate 4m of the earthwork in the cover plate area described in step 2), and excavate to 2.2m below the top plate, and excavate the remaining layers to 2m at the bottom of the laminate; Dig to 200mm close to the base.
作为上述技术方案的进一步改进,步骤2)所述作为架设支撑的“基础”为3000mm*3000mm,深度为400mm,内部布设Φ14@200钢筋网片;“基础”顶部提前预埋4块钢板,钢板尺寸为1000mm*600mm*16mm;同时分别在斜柱倾斜方向及型钢梁方向预埋600mm*600mm*16mm支撑钢板。As a further improvement of the above technical solution, the "foundation" mentioned in step 2) as the erection support is 3000mm*3000mm, the depth is 400mm, and Φ14@200 steel mesh is arranged inside; 4 steel plates are pre-embedded on the top of the "foundation". The size is 1000mm*600mm*16mm; at the same time, 600mm*600mm*16mm supporting steel plates are pre-embedded in the inclined direction of the inclined column and the direction of the steel beam.
作为上述技术方案的进一步改进,步骤5)所述微调后需保证型钢梁顶标高偏差±2mm内、斜柱预留接头轴线偏差小于3mm、斜柱预留接头垂直度小于1mm。As a further improvement of the above technical solution, after the fine-tuning in step 5), it is necessary to ensure that the elevation deviation of the steel beam top is within ±2 mm, the axis deviation of the reserved joint of the inclined column is less than 3 mm, and the verticality of the reserved joint of the inclined column is less than 1 mm.
作为上述技术方案的进一步改进,步骤6)所述将斜柱拼接段吊起移至拼接段位置具体操作为利用钢梁设置的两个吊点分别平拉斜柱拼接段上下端,移至拼接段位置后吊钩缓慢卸载,收紧上下端平拉绳索使斜柱拼接段就位。As a further improvement of the above technical solution, in step 6), the specific operation of lifting the splicing section of the inclined column to the position of the splicing section is to use the two lifting points set by the steel beam to pull the upper and lower ends of the splicing section of the inclined column horizontally and move to the splicing section. After the segment position, the hook is slowly unloaded, and the upper and lower ends are tightened to flatten the rope to make the splicing segment of the inclined column in place.
作为上述技术方案的进一步改进,步骤6)所述斜柱拼接段焊接前需按施工要求搭好操作架,便于斜柱拼接段的安装焊接。As a further improvement of the above technical solution, before the welding of the slanted column splicing section in step 6), an operation frame needs to be set up according to the construction requirements, so as to facilitate the installation and welding of the slanting column splicing section.
作为上述技术方案的进一步改进,所述型钢梁与斜柱预留接头焊接时采用限位块对型钢梁进行固定,安装时先将钢柱及钢梁边线进行定位,钢柱底部采用限位板进行定位,最后还需进行标高复核,确保高程及平面位置准确无误。As a further improvement of the above-mentioned technical scheme, when the steel beam and the inclined column are welded, the limit block is used to fix the steel beam. When installing, the steel column and the edge of the steel beam are first positioned. The positioning board is used for positioning, and finally the elevation needs to be checked to ensure that the elevation and plane position are accurate.
与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:
1.本发明利用CAD建立坐标系以及全站仪测量得到斜柱预留接头顶部及底部各个控制点的位置坐标对斜柱进行精确定位放样,将斜柱顶部各个控制点在楼面上的投影采用光学垂准仪或吊线锤引至模板支撑架上以确定模板边线位置,提高了斜柱定位安装效率。1. The present invention utilizes CAD to establish a coordinate system and obtains the position coordinates of each control point at the top and bottom of the reserved joint of the slanted column by measuring with a total station to carry out precise positioning and lofting of the slanted column, and project the control points at the top of the slanted column on the floor An optical plummet or a hanging hammer is used to lead to the formwork support frame to determine the position of the formwork edge, which improves the efficiency of positioning and installation of the inclined column.
2.本发明采用盖挖逆作结合盖挖顺作的施工方法,克服了施工场地狭小、周边地上建筑物繁多、地面交通组成复杂等缺点,缩短了施工工期。2. The present invention adopts the construction method of cover-excavation reverse operation combined with cover-excavation sequential operation, which overcomes the shortcomings of narrow construction site, numerous surrounding buildings on the ground, complex ground traffic composition, etc., and shortens the construction period.
3.本发明通过将斜柱设计成多层分段的形式,极大的方便了施工,提升了工程施工安全性。同时鱼腹式的斜柱对称布置形式也为地下结构提供了充足的上部空间,增加了地下空间使用面积,有利于增加自然采光。3. The invention greatly facilitates the construction and improves the safety of engineering construction by designing the slanting columns into multi-layer and segmented forms. At the same time, the symmetrical arrangement of fish-belly inclined columns also provides sufficient upper space for the underground structure, increases the usable area of the underground space, and is conducive to increasing natural lighting.
附图说明Description of drawings
图1为本发明地下空间大型鱼腹式斜柱结构施工方法的流程示意图。Fig. 1 is a schematic flow chart of the construction method of the large-scale fish-belly inclined column structure in the underground space of the present invention.
图2为本发明地下空间大型鱼腹式斜柱结构三维图。Fig. 2 is a three-dimensional view of the structure of a large fish-belly oblique column in an underground space according to the present invention.
图3为本发明地下空间大型鱼腹式斜柱结构横断面图。Fig. 3 is a cross-sectional view of a large fish-belly oblique column structure in an underground space according to the present invention.
图4为本发明地下空间大型鱼腹式斜柱结构未安装斜柱拼接段三维示意图。Fig. 4 is a three-dimensional schematic diagram of the large fish-belly inclined column structure in the underground space of the present invention without installing the spliced section of the inclined column.
图5为本发明地下空间大型鱼腹式斜柱结构未安装斜柱拼接段横断面图。Fig. 5 is a cross-sectional view of the large fish-bellied slanted column structure in the underground space of the present invention without the splicing section of the slanted column installed.
图中:2、型钢梁;3、临时立柱;4、透明材料;11、斜柱拼接段;12、斜柱预留接头。In the figure: 2. Shaped steel beam; 3. Temporary column; 4. Transparent material; 11. Splicing section of inclined column; 12. Reserved joint for inclined column.
具体实施方式Detailed ways
下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本申请及其应用或使用的任何限制。基于本申请中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the application with reference to the drawings in the embodiments of the application. Apparently, the described embodiments are only some of the embodiments of the application, not all of them. The following description of at least one exemplary embodiment is merely illustrative in nature and in no way serves as any limitation of the application, its application or uses. Based on the embodiments in this application, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of this application.
除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、数字表达式和数值不限制本申请的范围。同时,应当明白,为了便于描述,附图中所示出的各个部分的尺寸并不是按照实际的比例关系绘制的。对于相关领域普通技术人员已知的技术、方法和设备可能不作详细讨论,但在适当情况下,所述技术、方法和设备应当被视为授权说明书的一部分。在这里示出和讨论的所有示例中,任何具体值应被解释为仅仅是示例性的,而不是作为限制。因此,示例性实施例的其它示例可以具有不同的值。应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步讨论。The relative arrangements of components and steps, numerical expressions and numerical values set forth in these embodiments do not limit the scope of the present application unless specifically stated otherwise. At the same time, it should be understood that, for the convenience of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship. Techniques, methods and devices known to those of ordinary skill in the relevant art may not be discussed in detail, but where appropriate, such techniques, methods and devices should be considered part of the Authorized Specification. In all examples shown and discussed herein, any specific values should be construed as exemplary only, and not as limitations. Therefore, other examples of the exemplary embodiment may have different values. It should be noted that like numerals and letters denote like items in the following figures, therefore, once an item is defined in one figure, it does not require further discussion in subsequent figures.
在本申请的描述中,需要理解的是,使用“第一”、“第二”等词语来限定零部件,仅仅是为了便于对相应零部件进行区别,如没有另行声明,上述词语并没有特殊含义,因此不能理解为对本申请保护范围的限制。In the description of this application, it should be understood that the use of words such as "first" and "second" to define parts is only for the convenience of distinguishing corresponding parts. Therefore, it should not be construed as a limitation of the protection scope of this application.
在本申请的描述中,需要理解的是,方位词如“前、后、上、下、左、右”、“横向、竖向、垂直、水平”和“顶、底”等所指示的方位或位置关系通常是基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,在未作相反说明的情况下,这些方位词并不指示和暗示所指的装置或元件必须具有特定的方位或者以特定的方位构造和操作,因此不能理解为对本申请保护范围的限制;方位词“内、外”是指相对于各部件本身的轮廓的内外。In the description of the present application, it should be understood that orientation words such as "front, back, up, down, left, right", "horizontal, vertical, vertical, horizontal" and "top, bottom" etc. indicate the orientation Or positional relationship is generally based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the application and simplifying the description. In the absence of a contrary statement, these orientation words do not indicate or imply the device or element referred to It must have a specific orientation or be constructed and operated in a specific orientation, so it should not be construed as limiting the protection scope of the present application; the orientation words "inner and outer" refer to the inner and outer relative to the outline of each component itself.
以下结合附图2对本申请进行详细说明。The present application will be described in detail below in conjunction with accompanying drawing 2 .
图2为本发明地下空间大型鱼腹式斜柱结构三维图,该结构除主体顶板、底板、各层层板外,还包括各层型钢梁2、临时立柱3、各层斜柱拼接段11、各层斜柱预留接头12,其中:Fig. 2 is a three-dimensional view of the large-scale fish-belly slanted column structure in the underground space of the present invention. In addition to the main roof, bottom plate, and laminates of each layer, the structure also includes
型钢梁2:各层型钢梁2与顶板、底板、各层层板相连接;Shaped steel beam 2: The shaped
临时立柱3:临时立柱3安装于顶板、底板、各层层板之间;Temporary column 3: the
透明材料4:透明材料4的天窗设于顶板处鱼腹式斜柱之间;Transparent material 4: The skylight of
斜柱预留接头12:各层斜柱预留接头12与各层型钢梁2焊接;
斜柱拼接段11:各层斜柱拼接段11与各层斜柱预留接头12焊接构成鱼腹式多层分段斜柱。Slanting column splicing section 11: The splicing
实施例Example
一种地下空间大型鱼腹式斜柱结构施工方法,包括如下步骤:A construction method for a large fish-belly inclined column structure in an underground space, comprising the following steps:
步骤一:step one:
施工准备:熟悉了解和审查施工图纸及其设计文件,做好施工组织设计交底,在专业钢构加工场进行型钢梁2、斜柱预留接头12的加工,将斜柱预留接头12与主体结构横梁连接成整体。Construction preparation: familiarize yourself with and review the construction drawings and design documents, do a good job in explaining the construction organization design, process the shaped
步骤二:Step two:
垫层及预埋件施工:Cushion and embedded parts construction:
1.土方开挖:主体结构盖板以上土方开挖采用明挖法自西向东施工;施作盖板区域土方开挖约4m,开挖至顶板底下2.2m处为止,其余各层开挖至层板底2m处;1. Earthwork excavation: The excavation of the earthwork above the cover plate of the main structure adopts the open cut method from west to east; the earthwork excavation in the area where the cover plate is constructed is about 4m, and the excavation ends at 2.2m below the roof, and the remaining layers are excavated to 2m from the bottom of the laminate;
2.垫层施工:盖板基坑开挖接近基底200mm时,人工配合挖机清底,清底后立即施工垫层混凝土,垫层采用C20混凝土浇筑,浇筑厚度为150mm;2. Cushion layer construction: when the excavation of the foundation pit of the cover plate is close to the base of 200mm, manually cooperate with the excavator to clear the bottom, and immediately construct the cushion layer concrete after cleaning the bottom layer. The cushion layer is poured with C20 concrete, and the pouring thickness is 150mm;
3.斜柱基础施工:施工时在斜柱下方施作扩大基础,基础为3000mm*3000mm,深度为400mm,内部布设Φ14@200钢筋网片,基础顶部提前预埋4块基础钢板,钢板尺寸1000mm*600mm*16mm;同时分别在斜柱倾斜方向及型钢梁2方向预埋600mm*600mm*16mm支撑钢板,作为架设支撑的基础;3. Slanted column foundation construction: during construction, an enlarged foundation is constructed under the slanted column. The foundation is 3000mm*3000mm, the depth is 400mm, and Φ14@200 steel mesh is laid inside, and 4 foundation steel plates are pre-embedded on the top of the foundation, and the steel plate size is 1000mm *600mm*16mm; at the same time, 600mm*600mm*16mm supporting steel plates are pre-embedded in the inclined direction of the inclined column and the 2 directions of the steel beam, as the basis for erecting the support;
4.预埋钢板定位施工:基础开挖完成后,先由测量组在基础内放线画出预埋钢板位置,然后在钢板4个角点处向土层内打入4根长度不小于1m的Φ22钢筋,随后安装预埋钢板,安装过程中测量组全程测量调整,标高误差不得大于5mm,4块预埋钢板安装完成后采用钢筋将钢板底部连接为整体,然后开始浇筑基础混凝土。4. Pre-embedded steel plate positioning construction: After the foundation excavation is completed, the measurement team will draw the position of the pre-embedded steel plate in the foundation, and then drive 4 steel plates into the soil layer at the 4 corner points with a length of not less than 1m. Φ22 steel bars, and then install the pre-embedded steel plates. During the installation process, the measurement team will measure and adjust the whole process. The elevation error should not exceed 5mm.
步骤三:Step three:
测量放样:Measurement Stakeout:
1.坐标计算:通过对型钢梁2、斜柱预留接头12进行建模随时调出斜柱预留接头12任意位置,任意标高的位置以及人工计算斜柱预留接头12位置的坐标,根据设计坐标和安装位置标高计算每个安装接头上下端各四个点位的坐标。计算出的坐标与建模调出的坐标完全一致后,作为测量放线的依据;1. Coordinate calculation: By modeling the
2.先由测量组在垫层上标记需要施工的型钢梁2或斜柱预留接头12的角点,并测出实际垫层标高,用来确定临时支撑高度,施工作业人员按照测量组所放出的轴线用尺量弹出斜柱预留接头12的安装边线,然后在安装边线处焊接定位钢板。在各层斜柱预留接头12安装完成后,对各层斜柱预留接头12上下端各测量4个控制点,根据实测情况进行厂家下料制作斜柱拼接段11。2. First, the measurement team marks the corner points of the shaped
步骤四:Step four:
各层型钢梁2、斜柱预留接头12吊装:斜柱预留接头12采用50t汽车吊进行吊装,将斜柱预留接头12吊装至带水平转动功能的地坦克移动工具上,动力采用5t卷扬机牵引,地坦克移动工具采用槽钢做轨道,根据放样位置进行移动,将斜柱预留接头12运至设计位置进行安装。斜柱预留接头12安装完成后,根据现场实际长度加工型钢梁2,加工完成后采用吊机安装。Hoisting of shaped
步骤五:Step five:
各层型钢梁2、斜柱预留接头12定位加固:斜柱预留接头12就位后,现场测量人员用全站仪对梁顶标高及轴线,斜柱预留接头12垂直度及角度进行复核,斜柱预留接头12轴线调整采用吊车配合人工左右移动的方法进行微调,确保轴线偏差小于3mm,梁顶标高采用临时支架进行微调,最终达到设计标高,保证梁顶标高偏差为±2mm,斜柱预留接头12垂直度小于1mm。斜柱预留接头12定位完成后,需要对斜柱预留接头12进行加固措施,在型钢梁2端头采用H型钢支撑柱支撑,确保型钢梁稳定,不晃动。Positioning and strengthening of shaped
步骤六:Step six:
测量复核:型钢梁2、斜柱预留接头12加固完成后采用全站仪再次对型钢梁2和斜柱预留接头12的轴线、标高进行复核,确定无误后方可进入下道工序。Measurement review: After the
步骤七:Step seven:
斜柱拼接段11施工:在完成地下空间所有主体结构施工后,将斜柱拼接段11顺作。Construction of
1.利用上部钢梁预设吊钩将斜柱拼接段11垂直吊起;1. Use the preset hook of the upper steel beam to vertically lift the
2.利用上部钢梁设置的两个吊点分别平拉斜柱拼接段11上下端,逐步移位至拼接段位置;垂直吊钩部位缓慢卸载。2. Use the two lifting points set on the upper steel beam to pull the upper and lower ends of the
3.收紧上下端平拉绳索,斜柱拼接段11缓慢就位,利用预留限位夹板等措施调整斜柱拼接段11并与斜柱预留接头12完全对位,斜柱预留接头12与斜柱拼接段11定位准确后使用全熔透焊焊接,保证焊接质量合格,焊接缝100%检测。3. Tighten the upper and lower flat pull ropes, the
本实施例中步骤七中,斜柱拼接段11焊接前按施工要求搭设好操作架,便于斜柱拼接段11的安装焊接。型钢梁2与斜柱预留接头12焊接时采用限位块对型钢梁2进行固定,焊接完成后运至现场进行安装,安装时先将钢柱及型钢梁2边线进行定位,钢柱底部采用限位板进行定位,最后进行标高复核,确保高程及平面位置准确无误。各层板之间安装有临时立柱3,在斜柱拼接段12施工之前为结构提供临时支撑。顶板处鱼腹式斜柱之间设有透明材料4的天窗,目的是为了地下结构的自然采光。In step 7 of this embodiment, before the welding of the
本发明提供的地下空间大型鱼腹式斜柱结构的施工方法克服了施工场地狭小、周边建筑物繁多、地面交通组成复杂等缺点,具有安全性高、施工工期短、施工效率高、对周边环境影响低等优点,适合当今竞争激烈、交通拥堵的大城市闹市区的工程开发。本发明先逆作各层斜柱预留接头,降低了施工过程围护结构的水平变形,减少了临时设施的工程量,降低了对周边环境的影响;然后顺作各层斜柱拼接段,降低了拼装过程的作业干扰,增加了作业面,提高了施工效率;各层斜柱预留接头与各层斜柱拼接段构成本发明鱼腹式多层分段斜柱,斜柱多层分段的形式方便了施工也提升了施工安全性。本发明施工方法构建的地下空间大型鱼腹式斜柱结构地下使用空间大,自然采光良好,具有良好的应用前景。The construction method of the large-scale fish-belly oblique column structure in the underground space provided by the present invention overcomes the shortcomings of the narrow construction site, numerous surrounding buildings, and complex ground traffic composition, and has the advantages of high safety, short construction period, high construction efficiency, and good influence on the surrounding environment. Low impact and other advantages, suitable for today's engineering development in the downtown area of big cities with fierce competition and traffic congestion. In the present invention, the reserved joints of the slanted columns of each layer are reversed first, which reduces the horizontal deformation of the enclosure structure during the construction process, reduces the engineering quantity of temporary facilities, and reduces the impact on the surrounding environment; The operation interference in the assembly process is reduced, the working area is increased, and the construction efficiency is improved; the joints reserved for each layer of inclined columns and the splicing sections of each layer of inclined columns constitute the fish-belly multi-layer segmented inclined columns of the present invention, and the multi-layered inclined columns are divided into multiple layers. The segmented form facilitates construction and improves construction safety. The large-scale fish-belly oblique column structure in the underground space constructed by the construction method of the present invention has large underground use space, good natural lighting, and good application prospects.
以上所描述的实施例仅为本发明优选实施例,并不用于限制本发明。对于本领域的技术人员来说,本发明可以有各种变化和更改,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The embodiments described above are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention can have various changes and modifications, and within the spirit and principles of the present invention, any modifications, equivalent replacements, improvements, etc., should be included in the protection of the present invention. within range.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111160389.2A CN113833020B (en) | 2021-09-30 | 2021-09-30 | Construction method of large fish-belly inclined column structure in underground space |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111160389.2A CN113833020B (en) | 2021-09-30 | 2021-09-30 | Construction method of large fish-belly inclined column structure in underground space |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113833020A CN113833020A (en) | 2021-12-24 |
CN113833020B true CN113833020B (en) | 2022-11-01 |
Family
ID=78967775
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111160389.2A Active CN113833020B (en) | 2021-09-30 | 2021-09-30 | Construction method of large fish-belly inclined column structure in underground space |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113833020B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114232786A (en) * | 2021-12-30 | 2022-03-25 | 中铁四局集团第五工程有限公司 | Underground structure type steel concrete inclined column construction method |
CN114673169A (en) * | 2022-05-13 | 2022-06-28 | 华东交通大学 | Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area |
CN115748984B (en) * | 2022-11-28 | 2024-04-26 | 中铁建设集团有限公司 | Reverse operation construction method for large-section fusiform double-inclined column |
CN115637872B (en) * | 2022-12-01 | 2023-03-21 | 北京市第三建筑工程有限公司 | Construction method for installing cross-floor inclined column in existing floor |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
CN106284665A (en) * | 2016-08-04 | 2017-01-04 | 中建钢构有限公司 | Double-spiral spatial structure of inclined steel column and construction method thereof |
CN106436760A (en) * | 2016-08-12 | 2017-02-22 | 武汉志和岩土工程有限公司 | Top-down construction method |
CN107542268A (en) * | 2017-09-30 | 2018-01-05 | 中建五洲工程装备有限公司 | The reverse construction method of installation of stage steel construction in a kind of grand theater room |
CN109025286A (en) * | 2018-07-20 | 2018-12-18 | 中建三局第三建设工程有限责任公司 | A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction |
CN112031406A (en) * | 2020-08-31 | 2020-12-04 | 上海宝冶集团有限公司 | Construction method for 360-degree rotary bending of snowmobile ski-racing track |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298143B (en) * | 2015-05-12 | 2019-06-21 | 江苏南通六建建设集团有限公司 | Polygon hyperboloid open type titanium composite plate curtain wall construction method |
-
2021
- 2021-09-30 CN CN202111160389.2A patent/CN113833020B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
CN106284665A (en) * | 2016-08-04 | 2017-01-04 | 中建钢构有限公司 | Double-spiral spatial structure of inclined steel column and construction method thereof |
CN106436760A (en) * | 2016-08-12 | 2017-02-22 | 武汉志和岩土工程有限公司 | Top-down construction method |
CN107542268A (en) * | 2017-09-30 | 2018-01-05 | 中建五洲工程装备有限公司 | The reverse construction method of installation of stage steel construction in a kind of grand theater room |
CN109025286A (en) * | 2018-07-20 | 2018-12-18 | 中建三局第三建设工程有限责任公司 | A kind of construction method of large span high-altitude three-dimensional canopy of the heavens steel construction |
CN112031406A (en) * | 2020-08-31 | 2020-12-04 | 上海宝冶集团有限公司 | Construction method for 360-degree rotary bending of snowmobile ski-racing track |
Also Published As
Publication number | Publication date |
---|---|
CN113833020A (en) | 2021-12-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113833020B (en) | Construction method of large fish-belly inclined column structure in underground space | |
CN102864737B (en) | Steel-structured passenger foot bridge | |
CN206503230U (en) | A kind of fabricated steel building | |
CN112900692B (en) | Large-span special-shaped steel structure building, supporting device thereof and construction method | |
CN105089178B (en) | A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls | |
CN106894639A (en) | The hanging reverse construction method of installation of steel construction under a kind of | |
CN204826308U (en) | Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall | |
CN112627434B (en) | Cross construction method for complex V-shaped stiff columns and irregular ring beams of large stadium | |
CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
CN105442839A (en) | Erecting method of cantilever structure formwork bent | |
CN101775844A (en) | Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering | |
CN111926910A (en) | Installation method of fabricated building | |
CN105332417A (en) | Method for constructing prefabricated steel frame composite structure with concrete wrapped outside | |
RU2616306C1 (en) | Method for construction of multistore buildings of three-dimensional blocks | |
CN110670722A (en) | Implementation method of beam-column connecting node of fabricated building | |
CN105201107A (en) | Construction method for stacked plate type shear wall of underground garage | |
CN102337782A (en) | Lift system for constructing truss platform on top of tall and large space and construction method for lift system | |
CN114790757A (en) | Cover-excavation top-down construction V-shaped column structure and construction method thereof | |
CN101759079A (en) | Method for integrally assembling and installing steel structure elevator derrick on the ground | |
KR20250036109A (en) | Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing | |
CN107299710A (en) | Integrated prefabricated lightweight floor slab and its construction method | |
CN114541632A (en) | Construction method for using laminated slab for prefabricated building roof layer floor slab | |
CN110512776B (en) | Construction method of assembled steel structure multi-cavity steel plate composite shear wall | |
CN100366855C (en) | Inclined triangular pyramid truss frame structure and its fabrication, installation and measurement methods | |
CN110258642A (en) | A kind of combined assembled underground structure of cut and cover method and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |