CN113608160A CN202110881014.9A CN202110881014A CN113608160A CN 113608160 A CN113608160 A CN 113608160A CN 202110881014 A CN202110881014 A CN 202110881014A CN 113608160 A CN113608160 A CN 113608160A
Authority
CN
China
Prior art keywords
knob switch
junction box
meter
circuit
jumper wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110881014.9A
Other languages
Chinese (zh)
Inventor
李贺龙
卢达
陈昊
王兴媛
刘佳
王春雨
王春妍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN202110881014.9A priority Critical patent/CN113608160A/en
Publication of CN113608160A publication Critical patent/CN113608160A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Connections Arranged To Contact A Plurality Of Conductors (AREA)

Abstract

The invention discloses a combined junction box for metering a gateway electric energy meter, which consists of a main body shell, a circuit component, a knob switch and a jumper, wherein the main body shell is made of fireproof materials and is used for protecting internal circuits of the junction box; the circuit assembly is used for conducting and switching a circuit in combination with the operation of the knob switch; the knob switch comprises 3 gears of a current measuring meter, a current measuring meter and a power changing meter, and when the knob switch is positioned at the gear of the power changing meter, a voltage line is disconnected; 1 jumper wire, which is connected with the circuit of the knob switch in parallel under normal state; when the knob switch is switched instantly, the jumper wire is pulled off, and the semi-external test equipment is switched into a loop. The problem of junction box safety coefficient low, complex operation, life hang down under the prior art is solved.

Description

Joint junction box for metering gateway electric energy meter
Technical Field
The application relates to the technical field of electric energy meter metering equipment, in particular to a joint junction box for metering a gateway electric energy meter.
Background
The joint junction box for metering electric energy for the gateway electric energy meter is an important component of a metering secondary circuit, and has the functions of connecting secondary wires led out by a mutual inductor to the terminals of the electric energy meter after being connected in series and in parallel through the terminals at the joint junction box end, changing the on-off state of a testing circuit by changing the position of a poking piece on the junction box, and providing necessary conditions for on-site calibration with load, electricity utilization inspection and replacement of the electric energy meter of a metering device.
However, the combined junction box for measuring the electric energy used by the existing gateway electric energy meter has the following problems in the use process: when the field detection/meter change operation is carried out, the voltage plectrum needs to be disconnected, the current plectrum needs to be in short circuit, and the voltage plectrum and the current plectrum are restored to the original states after the work of the field detection/meter change operation is finished. However, due to the non-standard operation, the voltage and current plectrum are not reliably connected, which results in the omission and error recording of the electric quantity. Secondly, because the plectrum is through the copper bar lug connection in screw and the terminal box, so plectrum itself is electrified, when the staff operates the plectrum, just live working has brought the hidden danger for the safety work. Finally, when the voltage and current test wires are connected into the loop of the electric energy meter, a plurality of groups of screws in the junction box need to be operated respectively, the operation is time-consuming and labor-consuming on one hand, and on the other hand, the screw end parts are abraded due to the fact that the meter is checked and replaced at each time, screw failure is finally caused, and the risk of screw tripping is also accompanied.
Disclosure of Invention
In order to solve the problems, the application provides a combined junction box for metering a gateway electric energy meter, which consists of a main body shell, a circuit assembly, a knob switch and a jumper, wherein the main body shell is made of fireproof materials and is used for protecting internal circuits of the junction box;
the circuit assembly is used for conducting and switching a circuit in combination with the operation of the knob switch;
the knob switch comprises 3 gears of a current measuring meter, a current measuring meter and a power changing meter, and when the knob switch is positioned at the gear of the power changing meter, a voltage line is disconnected;
the jumper wire is connected with the circuit of the knob switch in parallel under the normal state; when the knob switch is switched instantly, the jumper wire is pulled off, and the semi-external test equipment is switched into a loop.
Preferably, the circuit assembly is wired with the wiring terminal and the test terminal through a PCB (printed Circuit Board) wire.
Preferably, the knob switch is composed of a knob shell, a rotating shaft, a knob cap, a metal terminal, a spring and a steel ball.
Preferably, when the current is measured through the junction box, the jumper wire is pulled out, the ammeter is inserted into the jumper wire hole, and the knob switch is adjusted to the current measuring gear.
Preferably, the knob switch is normally in the 0 gear, and the jumper is normally closed.
Drawings
FIG. 1 is a schematic structural diagram of a joint junction box for metering a gateway electric energy meter according to an embodiment of the present application;
FIG. 2 is a schematic diagram of the effect of a main board of the joint junction box for metering the gateway electric energy meter according to the embodiment of the present application;
FIG. 3 is a top view of a combined junction box for metering of gateway electric energy meters according to an embodiment of the present application;
FIG. 4 is a three-dimensional schematic diagram of a combined junction box for metering gateway electric energy meters according to an embodiment of the present application;
FIG. 5 is a dimension diagram of a combined junction box for metering of gateway electric energy meters according to an embodiment of the present application; (ii) a
FIG. 6 is an assembly drawing of the united junction box for gateway electric energy meter metering according to the embodiment of the present application;
Detailed Description
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present application. This application is capable of implementation in many different ways than those herein set forth and of similar import by those skilled in the art without departing from the spirit of this application and is therefore not limited to the specific implementations disclosed below.
The application provides a combined junction box for metering a gateway electric energy meter, the structural schematic diagram of which is shown in figure 1, the junction box consists of a main body shell, a circuit component, a knob switch and a jumper,
the main body shell is made of fireproof materials and is used for protecting internal circuits of the junction box; 2
The circuit assembly is used for conducting and switching a circuit in combination with the operation of the knob switch;
the knob switch comprises 3 gears of a current measuring meter, a current measuring meter and a power changing meter, and when the knob switch is positioned at the gear of the power changing meter, a voltage line is disconnected;
the jumper wire is connected with the circuit of the knob switch in parallel under the normal state; when the knob switch is switched instantly, the jumper wire is pulled off, and the semi-external test equipment is switched into a loop.
The main body shell is made of fireproof materials, and the shell has the characteristics of impact resistance, high strength, high temperature resistance, ageing resistance, corrosion resistance and the like.
The circuit assembly is wired with the wiring terminal and the test terminal through the PCB and is combined with the operation of a knob switch to conduct and switch the circuit.
The knob switch consists of a knob shell, a rotating shaft, a knob cap, a metal terminal, a spring, a steel ball and the like. And the knob switch is normally in a 0 gear, and the jumper is normally closed.
The working principle is as follows:
1A "0" gear state: the knob is normally at the 0 gear, the jumper plug-in is normally closed,
the current trend is as follows: 1, feeding to a-3-ammeter-4-5-6-7-8; voltage trend: 10 in-11-12-13-14 out.
2B "current measuring" gear state: when measuring current, firstly, the 'jumper wire' is pulled out, then the ammeter is inserted into the jumper wire hole (the ammeter is connected in series on the circuit), then the knob is screwed to the 'current measuring' gear,
the current trend is as follows: 1 in-3-4-5-9 (by an ammeter) -7-8 out; voltage trend: 10 in-11-12-13-14 out.
(after the current is measured, the gear is screwed to the '0' gear, the ammeter is pulled out, and a 'jumper' is plugged in at the same time), and the current trend is like '1A'.
3C3 "Change Meter" Shift State: when the meter is changed, the knob is screwed to the gear of the electricity changing meter (2-6 points of short circuit),
the current trend is as follows: 1, enter-2-6-7-8 and exit; voltage trend: 12-13 are disconnected.
(note: ensuring that a jumper wire is inserted into a jumper wire hole during meter replacement to prevent the switching circuit from being instantly broken, and screwing the gear to '0' after the meter replacement is finished).
The labels "A", "B" and "C" are three voltage testing holes. The red voltage line is on the top layer of the PCB and the cyan is on the bottom layer of the PCB.
Fig. 2 shows a main board effect schematic diagram of the junction box, and fig. 3 and 4 show a top view and a three-dimensional effect schematic diagram of the combined junction box for gateway electric energy meter metering. The size of the terminal box is preferably as shown in fig. 5, and the unit is: and (4) millimeter.
Fig. 6 shows a schematic diagram of a combined junction box device for metering gateway electric energy meters, which illustrates how each component is assembled and connected, and names of each component.
The application provides a be used for joint terminal box for gateway electric energy meter measurement has following advantage and effect: 1) appearance design is simple and clear, cancels numerous screw nodes, and factor of safety is high.
2) The fixing screw of the binding post adopts a countersunk head structure design, so that short circuit caused by easy touch of metal is avoided;
3) when the current is measured and the meter is changed, the operation of wearing an insulating glove is not needed, and the circuit is switched by shifting directly through a knob switch, so that the live operation is avoided, and the safety and the reliability are realized;
4) the inner part is wired through a PCB, the installation is convenient and rapid, the operation is simple, the time and the labor are saved, and the working efficiency is improved by more than 60 percent;
5) size, volume dimension, wall mounting screw hole position etc. are compatible with current terminal box, can directly replace.
Finally, it should be noted that: although the present invention has been described in detail with reference to the above embodiments, it should be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the spirit and scope of the invention.

Claims (5)

1. A combined junction box for metering a gateway electric energy meter comprises a main body shell, a circuit component, a knob switch and a jumper wire, and is characterized in that,
the main body shell is made of fireproof materials and is used for protecting internal circuits of the junction box;
the circuit assembly is used for conducting and switching a circuit in combination with the operation of the knob switch;
the knob switch comprises 3 gears of a current measuring meter, a current measuring meter and a power changing meter, and when the knob switch is positioned at the gear of the power changing meter, a voltage line is disconnected;
the jumper wire is connected with the circuit of the knob switch in parallel under the normal state; when the knob switch is switched instantly, the jumper wire is pulled off, and the semi-external test equipment is switched into a loop.
2. The connector of claim 1, wherein the circuit assembly is wired to the wire terminals and the test terminals by PCB traces.
3. The connector of claim 1, wherein the turn button switch is comprised of a turn button housing, a shaft, a turn button cap, a metal terminal, a spring, and a steel ball.
4. The junction box of claim 1, wherein when the junction box is used for measuring current, the jumper wire is pulled out, the ammeter is inserted into the jumper wire hole, and the knob switch is adjusted to a current measuring gear.
5. The junction box of claim 1, wherein said knob switch is normally in 0 position and the jumper is normally closed.
CN202110881014.9A 2021-08-02 2021-08-02 Joint junction box for metering gateway electric energy meter Pending CN113608160A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110881014.9A CN113608160A (en) 2021-08-02 2021-08-02 Joint junction box for metering gateway electric energy meter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110881014.9A CN113608160A (en) 2021-08-02 2021-08-02 Joint junction box for metering gateway electric energy meter

Publications (1)

Publication Number Publication Date
CN113608160A true CN113608160A (en) 2021-11-05

Family

ID=78339042

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110881014.9A Pending CN113608160A (en) 2021-08-02 2021-08-02 Joint junction box for metering gateway electric energy meter

Country Status (1)

Country Link
CN (1) CN113608160A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102723774A (en) * 2012-06-29 2012-10-10 黑龙江省电力有限公司检修公司 Bridge type current switching device and current switching method using same
CN103558429A (en) * 2013-10-31 2014-02-05 国网山东省电力公司泰安供电公司 Switch type electric energy measuring terminal box
CN203551766U (en) * 2013-10-31 2014-04-16 国网山东省电力公司泰安供电公司 Button type electric energy metering junction box
CN104007294A (en) * 2014-06-06 2014-08-27 国家电网公司 Overhead line parameter measurement wiring device
CN203849316U (en) * 2014-05-27 2014-09-24 国家电网公司 Multifunctional current signal sampling box used for relative dielectric loss and capacitance ratio measurement
CN204522904U (en) * 2015-02-12 2015-08-05 广东恒联食品机械有限公司 A kind of speed regulator for mixer
CN107345976A (en) * 2017-09-07 2017-11-14 贵州电网有限责任公司 A kind of metering secondary terminal box
CN207817028U (en) * 2017-12-20 2018-09-04 上海国缆智能电气有限公司 A kind of three-phase separated time electric energy meter novel integrated terminal box
CN108548947A (en) * 2018-03-30 2018-09-18 上海电力学院 A kind of guillotine type electric energy metering combined wiring box
CN109085396A (en) * 2018-08-30 2018-12-25 中国电力科学研究院有限公司 With the multifunctional combined terminal box of electrical energy measurement for changing table tooling
CN109085402A (en) * 2018-08-30 2018-12-25 中国电力科学研究院有限公司 The multifunctional combined terminal box of electrical energy measurement
CN109387805A (en) * 2018-10-24 2019-02-26 国网山东省电力公司海阳市供电公司 A kind of terminal box of three-level metering device series wiring band scene series connection verifying function
CN110196347A (en) * 2019-05-27 2019-09-03 国家电网有限公司 A kind of electrical energy measurement joint connecting terminal block
CN113125821A (en) * 2021-04-07 2021-07-16 国网河北省电力有限公司邯郸供电分公司 Junction box for metering secondary circuit safety arc extinction

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102723774A (en) * 2012-06-29 2012-10-10 黑龙江省电力有限公司检修公司 Bridge type current switching device and current switching method using same
CN103558429A (en) * 2013-10-31 2014-02-05 国网山东省电力公司泰安供电公司 Switch type electric energy measuring terminal box
CN203551766U (en) * 2013-10-31 2014-04-16 国网山东省电力公司泰安供电公司 Button type electric energy metering junction box
CN203849316U (en) * 2014-05-27 2014-09-24 国家电网公司 Multifunctional current signal sampling box used for relative dielectric loss and capacitance ratio measurement
CN104007294A (en) * 2014-06-06 2014-08-27 国家电网公司 Overhead line parameter measurement wiring device
CN204522904U (en) * 2015-02-12 2015-08-05 广东恒联食品机械有限公司 A kind of speed regulator for mixer
CN107345976A (en) * 2017-09-07 2017-11-14 贵州电网有限责任公司 A kind of metering secondary terminal box
CN207817028U (en) * 2017-12-20 2018-09-04 上海国缆智能电气有限公司 A kind of three-phase separated time electric energy meter novel integrated terminal box
CN108548947A (en) * 2018-03-30 2018-09-18 上海电力学院 A kind of guillotine type electric energy metering combined wiring box
CN109085396A (en) * 2018-08-30 2018-12-25 中国电力科学研究院有限公司 With the multifunctional combined terminal box of electrical energy measurement for changing table tooling
CN109085402A (en) * 2018-08-30 2018-12-25 中国电力科学研究院有限公司 The multifunctional combined terminal box of electrical energy measurement
CN109387805A (en) * 2018-10-24 2019-02-26 国网山东省电力公司海阳市供电公司 A kind of terminal box of three-level metering device series wiring band scene series connection verifying function
CN110196347A (en) * 2019-05-27 2019-09-03 国家电网有限公司 A kind of electrical energy measurement joint connecting terminal block
CN113125821A (en) * 2021-04-07 2021-07-16 国网河北省电力有限公司邯郸供电分公司 Junction box for metering secondary circuit safety arc extinction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
霍北季;: "实用新型接线盒―更换表计或处理有关故障时减少电量损失及计量准确性", 中国新技术新产品, no. 22, pages 50 - 51 *

Similar Documents

Publication Publication Date Title
CA2300522C (en) Revenue meter bayonet assembly and method of attachment
CN111190036B (en) Shunt lead structure, electric power meter and shunt lead structure manufacturing method
KR101856670B1 (en) A bus bar for a distribution board capable of measuring a current by combining a shunt resistor and a method of manufacturing the same, and a bus bar module
KR200454242Y1 (en) High Voltage Electronic Voltmeter Uninterruptible Replacement
CN113608160A (en) Joint junction box for metering gateway electric energy meter
CN108037479B (en) Novel intelligent test junction box
CN103825117B (en) A kind of Quick Connect Kit for instrument ageing test
CN214150862U (en) Manual programmable matrix test system
CN214845483U (en) Multi-contact-surface test auxiliary device for loop resistance meter
CN212872605U (en) Integrated relay transformer assembly for electric energy meter
CN201583577U (en) Universal meter capable of testing twisted pairs
CN208580169U (en) Simple line pairer
JP6323778B2 (en) Distribution board cabinet and distribution board using the same
CN207424157U (en) The centralizer internal wiring testing cassete of directional tool
CN207301293U (en) Multiple power supplies mechanism for testing
CN217181012U (en) Unique number confirmation indicating device of cable copper core
CN111323664B (en) A high-voltage switchgear test module
CN221240550U (en) Aviation plug socket and terminal integrated mounting structure and feeder terminal
CN208334621U (en) A kind of current mutual inductor testing apparatus facilitating clamping
CN221040987U (en) Circuit breaker and power system
CN222070701U (en) Distribution transformer fault diagnosis device
CN215833587U (en) On-load capacity and voltage regulating transformer testing device
CN216771920U (en) Pull electronic isolator divide-shut brake circuit detection device of power supply
KR20110004056U (en) MV Electronic Meter Adapter
CN2572412Y (en) Safety electricity use tester

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20211105