CN113463900A - Multifunctional slidable hanging rack for staircase and construction method thereof - Google Patents

Multifunctional slidable hanging rack for staircase and construction method thereof Download PDF

Info

Publication number
CN113463900A
CN113463900A CN202110748548.4A CN202110748548A CN113463900A CN 113463900 A CN113463900 A CN 113463900A CN 202110748548 A CN202110748548 A CN 202110748548A CN 113463900 A CN113463900 A CN 113463900A
Authority
CN
China
Prior art keywords
steel
staircase
hanger
multifunctional
slidable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110748548.4A
Other languages
Chinese (zh)
Inventor
张鹏
齐从月
王火华
钱世清
周红卫
龚文韬
李明
刘汉文
许国伟
刘恒
周鹏程
王艺涵
王纪峰
周游
刘民康
王泽华
覃思华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
Third Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Third Engineering Division filed Critical Third Construction Co Ltd of China Construction Third Engineering Division
Priority to CN202110748548.4A priority Critical patent/CN113463900A/en
Publication of CN113463900A publication Critical patent/CN113463900A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3261Safety-nets; Safety mattresses; Arrangements on buildings for connecting safety-lines
    • E04G21/3266Safety nets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention relates to a multifunctional slidable hanging rack for a staircase and a construction method thereof. The hanging rack can move axially along the bearing I-shaped steel, and all core barrel aluminum mould construction is considered; the upper and lower step walkway plates are arranged, the height of the hanging rack and the walkway plates can be freely combined, and the operation personnel can be ensured to conveniently install and detach the aluminum mould and the back edge; provide recoverable facade and horizontal plane protection, prevent personnel and article and fall the core section of thick bamboo and do not influence core section of thick bamboo hoist and mount operation.

Description

Multifunctional slidable hanging rack for staircase and construction method thereof
Technical Field
The invention relates to the field of building construction, in particular to a multifunctional slidable hanging frame for a staircase and a construction method thereof.
Background
At present, the aluminum mould used at the core tube part of the high-rise building needs to be disassembled, disassembled and spliced under the common condition during the construction of each layer of structure, and no operation platform is arranged in the core tube for the disassembly, the splicing and the back edge installation of the aluminum mould, so that the operation of erecting a scaffold in the core tube and the arrangement of protection such as reinforcing mesh sheets are needed during the construction of each layer of structure. Therefore, the core barrel aluminum mould operation and the safety protection process are complex and difficult, and the construction cost is increased.
Disclosure of Invention
The invention aims to solve the technical problem of providing a multifunctional slidable hanging rack for a staircase and a construction method thereof, so that the construction efficiency is improved, and the construction safety is ensured.
The technical scheme adopted by the invention for solving the technical problems is as follows: the utility model provides a multi-functional stores pylon that can slide in stairwell installs in major structure core section of thick bamboo, includes the stores pylon support body, bears the I-steel, walks guidance tape, horizontal protection network and facade protection network, bear the I-steel and fix in building machine bailey frame platform bottom, the stores pylon support body is installed bear the I-steel below and with bear I-steel sliding fit, the guidance tape is walked to the last multilayer that is equipped with of stores pylon support body, walk the guidance tape and fix on the crossbeam of stores pylon support body, stores pylon support body bottom is equipped with horizontal protection network, stores pylon support body side is equipped with the facade protection network.
In the scheme, the hanger frame body is connected with the cross beam and the walkway plate through bolts.
In the scheme, a plurality of mounting holes are formed in the vertical rod of the hanger frame body at intervals.
In the scheme, one side of the horizontal protective net is hinged to the hanger frame body through a hinge, and the other side of the horizontal protective net is connected with the hanger frame body through an inclined pull chain.
In the scheme, the hanger frame body is connected with the bearing I-shaped steel through the pulley hoisting point.
In the scheme, the bearing I-steel is welded at the bottom of the bailey truss platform of the building machine.
In the scheme, the bearing I-shaped steel is fixed at the bottom of the bailey truss platform of the building machine through the U-shaped bolt and the clamping plate.
In the above scheme, the bottom of the bailey frame platform of the building machine is provided with a clamping groove, and the bearing I-steel penetrates into the clamping groove.
The invention also provides a construction method of the multifunctional slidable hanging rack for the staircase, which comprises the following steps:
s1, selecting a proper position on the lower chord of the bailey truss to bear I-shaped steel, and then installing the vertical rod of the hanger body;
s2, determining the height of the two-step walkway plates according to requirements, connecting the inner and outer side hanging rack vertical rods by using a cross beam, and then installing the walkway plates;
s3, welding walkway plate guardrails, installing a vertical surface protective net according to the floor height and the height of a stair rest platform, and installing a horizontal protective net on the lowest walkway plate;
s4, the hanger frame body moves along the bearing I-shaped steel according to the position of the construction aluminum mould, the vertical face protective net and the horizontal protective net are kept in an open state when other constructions are not influenced, and the bolt is locked.
The multifunctional slidable hanging rack for the staircase and the construction method thereof have the following beneficial effects:
1. the permanent hanging rack is arranged on the core cylinder part, and the permanent hanging rack is not required to be installed and disassembled after one-time molding. The hanging rack needs to provide an operation platform for all aluminum mould construction of the core barrel, but if the core barrel is fully covered, other operations are blocked, so that the hanging rack can be designed into a movable hanging rack so as to reduce the size; on the premise that the rack is permanently accompanied with the core barrel, the protection of the original core barrel is considered to be added to the rack, and the difficult problem that the core barrel is large in protection amount and complex is solved.
2. According to the characteristic that the relative position of the bailey truss steel platform on the upper part of the light building machine and the core tube part is fixed, the bearing I-shaped steel is arranged in the opening of the bailey truss steel platform above the core tube, and the hanger body is connected with the cross beam through the pulley hoisting point, so that the permanent hanger is installed and moved.
3. The invention provides an operation platform for all aluminum mould construction of the core cylinder, and the operation platform has the advantages of proper size, safety and humanization. The vertical and horizontal protection is provided for the core cylinder part, and the hoisting operation of the core cylinder part is not influenced.
Drawings
The invention will be further described with reference to the accompanying drawings and examples, in which:
FIG. 1 is a schematic structural view of a multi-functional slidable pylon for a staircase according to the present invention;
FIG. 2 is a schematic view of the connection of a hanger body and a bearing I-shaped steel;
FIG. 3 is a schematic view of the connection of the walkway plate and the hanger frame;
FIG. 4 is a schematic view of the connection between a vertical protective net and a rack body;
fig. 5 is a schematic view of the connection between the planar protective net and the walkway plate.
Detailed Description
For a more clear understanding of the technical features, objects and effects of the present invention, embodiments of the present invention will now be described in detail with reference to the accompanying drawings.
As shown in fig. 1-5, the multifunctional slidable hanging rack for a staircase is installed in a core tube of a main structure, and comprises a rack body 2, a bearing joist steel 1, a walkway plate 3, a horizontal protective net 6 and a vertical protective net 5. Bear I-steel 1 and fix in building machine bailey frame platform bottom, the stores pylon support body 2 is installed and is born I-steel 1 below and with bear I-steel 1 sliding fit, is equipped with multilayer walkways board 3 on the stores pylon support body 2, walks the walkways board 3 and fixes on the crossbeam 8 of stores pylon support body 2, and stores pylon support body 2 bottom is equipped with horizontal protection network 6, and stores pylon support body 2 side is equipped with facade protection network 5.
The core barrel is designed according to the core barrel part, the permanent hanging rack is arranged in the core barrel, the aluminum die operation platform and the core barrel protection are provided, and the problems that the core barrel is difficult to operate on an aluminum die, large in protection amount and large in temporary erection amount are solved.
Two bearing I-beams 1 with the specification of 14# are arranged in the hole of the bailey truss steel platform above the core tube, and the length of the bearing I-beam 1 is confirmed according to the width of the hole of the steel platform. The connection form of the bearing I-steel 1 and the bailey truss is three: the first type is that a bearing I-shaped steel 1 is placed on the lower chord of the bailey truss and welded; the second type is that the bearing I-steel 1 is placed on the lower chord of the bailey truss and is fixed through a U-shaped bolt and a clamping plate. Both of these methods require pre-threading of the sheave suspension points 7. And thirdly, mounting a clamping groove on the lower chord of the bailey truss, penetrating the bearing I-shaped steel 1, and limiting the two ends by bolts.
The hanger frame body 2 is connected with the bearing I-shaped steel 1 through a pulley hanging point 7 in a welding mode or a bolt connection mode with the diameter of 10 mm; the stores pylon support body 2 can be followed and is born 1 axial displacement of I-steel, takes into account the construction of all templates of a core section of thick bamboo, and the size of effective control stores pylon platform prevents that the stores pylon from influencing other constructions of a core section of thick bamboo simultaneously.
The lowest part of the hanger frame body 2 is lower than the core tube aluminum mould and is provided with two step walkway plates 3 50cm below, and the walkway plates 3 are connected with the hanger frame body 2 through cross beams 8 and bolts. The height of the walkway plate 3 is adjusted according to the layer height and the operation comfort, and the width is considered to be 1m-1.2 m. A protective guard 4 rod is arranged 1m above each walking board 3.
The hanging rack body 2 is provided with vertical surface protective nets 5 at two sides of the height of a horizontal floor and at the positions of stair rest platforms, and the protective nets are connected with the rack body through trips 9. The release 9 is connected with the frame body by a bolt of 10mm, and the facade protective net 5 is connected with the release 9 by a bolt 10 of 10 mm. The vertical face protective net 5 can rotate in the vertical face, when the vertical face protective net 5 is used, the vertical face protective net 5 is opened, and a transverse bolt 10 arranged on the vertical rod of the hanging rack body 2 is inserted into an insertion opening on the vertical rod of the hanging rack body 5, so that the vertical face protective net 5 is fixed. The vertical surface protective net 5 can effectively prevent the casualties caused by the personnel falling into the core barrel, and provides a safer operation environment.
The lowest pavement board 3 of the hanger body 2 is provided with a horizontal protective net 6, the near end of the horizontal protective net 6 is fixed by a hinge 11, and the far end is obliquely pulled by a chain 12 with qualified stress strength. The horizontal protective net 6 covers the whole core barrel to prevent personnel or objects from falling; when not in use, the hanging frame body 2 can be pulled back to be tightly attached to the hanging frame body, and the hoisting and the installation of the components such as the prefabricated staircase and the like are not influenced.
The hanger frame body 2 is formed in one step, and the functions of an aluminum die operation platform and protection have predictability and adjustability; after the light building machine is jacked, the aluminum mold of the hanging frame service core tube is installed, after concrete is poured, the aluminum mold of the hanging frame service core tube is dismantled, and the whole construction process, the vertical surface and the horizontal protection can well play the role. Simultaneously when other operations are carried out on the core barrel, the hanging rack can move or be closed for protection, the negative influence of the hanging rack on the core barrel is eliminated to the maximum extent, and the safe and rapid construction of the core barrel can be assisted by the hanging rack.
The invention also provides a construction method of the multifunctional slidable hanging rack for the staircase, which comprises the following steps:
step 1, designing and processing: according to the floor height, the size of the core tube, the stair direction and the like, the sizes of all parts of the core tube hanging rack are confirmed, processing drawings are drawn, and the core tube hanging rack is processed according to the drawings and the quantity.
Step 2, main support body installation: and selecting a proper position at the lower chord of the bailey truss, selecting a mounting mode of bearing the I-steel for mounting and bearing the I-steel, and then mounting the vertical rod of the hanger body.
Step 3, installing a walkway plate: and determining the height of the two-step walkway plates as required, connecting the inner side hanger vertical rod and the outer side hanger vertical rod by using the cross beam, and then installing the walkway plates.
And 4, forming protection: welding walkway plate guardrails, installing a vertical surface protective net according to the height of a floor and the height of a stair rest platform, and installing a horizontal protective net on the lowest walkway plate.
Step 5, use: the core barrel hanging frame can move according to the position of the construction aluminum mould; the vertical surface and the horizontal protection are kept in an open state when other construction is not influenced, and the bolt is locked.
While the present invention has been described with reference to the embodiments shown in the drawings, the present invention is not limited to the embodiments, which are illustrative and not restrictive, and it will be apparent to those skilled in the art that various changes and modifications can be made therein without departing from the spirit and scope of the invention as defined in the appended claims.

Claims (9)

1. The utility model provides a multi-functional stores pylon that can slide in stairwell installs in major structure core section of thick bamboo, its characterized in that, includes the stores pylon support body, bears the I-steel, walks guidance tape, horizontal protection network and facade protection network, bear the I-steel and fix in building machine bailey frame platform bottom, the stores pylon support body is installed bear the I-steel below and with bear I-steel sliding fit, be equipped with the multilayer on the stores pylon support body and walk the guidance tape, walk the guidance tape and fix on the crossbeam of stores pylon support body, stores pylon support body bottom is equipped with horizontal protection network, stores pylon support body side is equipped with the facade protection network.
2. The staircase multi-functional slidable hanger according to claim 1, wherein the hanger body is connected with the cross beam and the walkway plate by bolts.
3. The staircase multifunctional slidable hanger according to claim 1, wherein the vertical rod of the hanger body is provided with a plurality of mounting holes at intervals.
4. The staircase multifunctional slidable hanger according to claim 1, wherein one side of the horizontal protective net is hinged to the hanger frame body through a hinge, and the other side is connected to the hanger frame body through a diagonal chain.
5. The staircase multifunctional slidable hanger according to claim 1, wherein the hanger body is connected to the carrying i-steel by means of a pulley hanging point.
6. The staircase multifunctional slidable hanger according to claim 1, wherein the carrying i-steel is welded to the bottom of the building machine bailey frame platform.
7. The staircase multifunctional slidable hanger according to claim 1, wherein the carrying i-steel is fixed to the bottom of the building machine bailey frame platform by U-bolts and clamping plates.
8. The multifunctional sliding hanging rack for the staircase according to claim 1, wherein a clamping groove is arranged at the bottom of the platform of the Bailey truss of the building machine, and the bearing I-steel penetrates into the clamping groove.
9. The construction method of the multifunctional slidable staircase hanging frame of claim 1, characterized by comprising the following steps:
s1, selecting a proper position on the lower chord of the bailey truss to bear I-shaped steel, and then installing the vertical rod of the hanger body;
s2, determining the height of the two-step walkway plates according to requirements, connecting the inner and outer side hanging rack vertical rods by using a cross beam, and then installing the walkway plates;
s3, welding walkway plate guardrails, installing a vertical surface protective net according to the floor height and the height of a stair rest platform, and installing a horizontal protective net on the lowest walkway plate;
s4, the hanger frame body moves along the bearing I-shaped steel according to the position of the construction aluminum mould, the vertical face protective net and the horizontal protective net are kept in an open state when other constructions are not influenced, and the bolt is locked.
CN202110748548.4A 2021-07-02 2021-07-02 Multifunctional slidable hanging rack for staircase and construction method thereof Pending CN113463900A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110748548.4A CN113463900A (en) 2021-07-02 2021-07-02 Multifunctional slidable hanging rack for staircase and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110748548.4A CN113463900A (en) 2021-07-02 2021-07-02 Multifunctional slidable hanging rack for staircase and construction method thereof

Publications (1)

Publication Number Publication Date
CN113463900A true CN113463900A (en) 2021-10-01

Family

ID=77877373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110748548.4A Pending CN113463900A (en) 2021-07-02 2021-07-02 Multifunctional slidable hanging rack for staircase and construction method thereof

Country Status (1)

Country Link
CN (1) CN113463900A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115788000A (en) * 2022-12-14 2023-03-14 中建三局集团有限公司 Hanging frame first-installation construction method of intelligent construction equipment integration platform

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203669395U (en) * 2013-12-13 2014-06-25 中建三局第一建设工程有限责任公司 Protective operation hanging frame for top die system
US20150145156A1 (en) * 2012-05-08 2015-05-28 Kunshan Ecological Building Technology Co., Ltd. Method of casting in-situ ferrocement ribbed slab with spliced rack and suspended formwork
CN205918084U (en) * 2016-05-19 2017-02-01 中国建筑第八工程局有限公司 High -rise building core section of thick bamboo protector
CN209040525U (en) * 2018-10-11 2019-06-28 合肥翎艺建筑有限公司 A kind of full assembled external scaffolding
CN211647239U (en) * 2019-10-23 2020-10-09 上海建工集团股份有限公司 Lower hanging device for steel platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150145156A1 (en) * 2012-05-08 2015-05-28 Kunshan Ecological Building Technology Co., Ltd. Method of casting in-situ ferrocement ribbed slab with spliced rack and suspended formwork
CN203669395U (en) * 2013-12-13 2014-06-25 中建三局第一建设工程有限责任公司 Protective operation hanging frame for top die system
CN205918084U (en) * 2016-05-19 2017-02-01 中国建筑第八工程局有限公司 High -rise building core section of thick bamboo protector
CN209040525U (en) * 2018-10-11 2019-06-28 合肥翎艺建筑有限公司 A kind of full assembled external scaffolding
CN211647239U (en) * 2019-10-23 2020-10-09 上海建工集团股份有限公司 Lower hanging device for steel platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115788000A (en) * 2022-12-14 2023-03-14 中建三局集团有限公司 Hanging frame first-installation construction method of intelligent construction equipment integration platform

Similar Documents

Publication Publication Date Title
CN202090591U (en) Lift type climbing formwork of building operations
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN108033367B (en) Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane
CN103422668A (en) Construction method of super-thick large-slope shear wall and hydraulic self-jacking inclined creeping framework thereof
CN109184190B (en) Climbing and bearing integrated beam type hydraulic climbing platform and mounting method thereof
CN102912996B (en) Steel tube concrete column high-altitude construction safety protection system
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN107100361B (en) Inner support aluminum dipping form device and its installation method are climbed outside a kind of
CN112031401B (en) Two-way adjustable automatic template opening and closing system of climbing formwork and use method thereof
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN113463900A (en) Multifunctional slidable hanging rack for staircase and construction method thereof
CN113896124B (en) Attached hydraulic self-climbing hard protection platform at bottom of super high-rise tower crane, mounting process and climbing method thereof
KR20190041189A (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
CN105776092A (en) Stretching type basket device and construction method thereof
JPH09317183A (en) Building construction method
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN110700112A (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method
CN1048066C (en) Method and apparatus for integrally self-lifting scaffold
CN115369748B (en) Construction method of formwork system for integrally pouring bridge pier and tie beam
CN216713867U (en) Fixed bolster of prefabricated wallboard and contain braced system of this support
CN216196475U (en) Outer hanging protective scaffold suitable for cast-in-place vestibule construction of assembled
CN116181041A (en) Building machine of multilayer quick construction
CN111794074B (en) Arch bridge concrete beam and beam forming method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Qi Congyue

Inventor after: Liu Heng

Inventor after: Zhou Pengcheng

Inventor after: Wang Yihan

Inventor after: Wang Jifeng

Inventor after: Zhou You

Inventor after: Liu Minkang

Inventor after: Wang Zehua

Inventor after: Qin Sihua

Inventor after: Zhang Peng

Inventor after: Wang Huohua

Inventor after: Qian Shiqing

Inventor after: Zhou Hongwei

Inventor after: Gong Wentao

Inventor after: Li Ming

Inventor after: Liu Hanwen

Inventor after: Xu Guowei

Inventor before: Zhang Peng

Inventor before: Liu Heng

Inventor before: Zhou Pengcheng

Inventor before: Wang Yihan

Inventor before: Wang Jifeng

Inventor before: Zhou You

Inventor before: Liu Minkang

Inventor before: Wang Zehua

Inventor before: Qin Sihua

Inventor before: Qi Congyue

Inventor before: Wang Huohua

Inventor before: Qian Shiqing

Inventor before: Zhou Hongwei

Inventor before: Gong Wentao

Inventor before: Li Ming

Inventor before: Liu Hanwen

Inventor before: Xu Guowei

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20211001