- CN113420353B CN113420353B CN202110638650.9A CN202110638650A CN113420353B CN 113420353 B CN113420353 B CN 113420353B CN 202110638650 A CN202110638650 A CN 202110638650A CN 113420353 B CN113420353 B CN 113420353B
- Authority
- CN
- China
- Prior art keywords
- steel bar
- dimensional
- bar
- arrangement
- dimensional model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Civil Engineering (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Computer Graphics (AREA)
- Software Systems (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention relates to the technical field of engineering construction, in particular to a method and a device for arranging reinforcing steel bars and electronic equipment, wherein the method comprises the steps of obtaining a three-dimensional model of the reinforcing steel bars; generating a steel bar layout diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar layout diagram; acquiring modification of the reinforcement bar layout; and adjusting the three-dimensional model of the steel bar based on the modification. And the three-dimensional model of the steel bar can be synchronously adjusted when the steel bar layout is modified, so that the steel bar layout efficiency is improved.
Description
Technical Field
The invention relates to the technical field of engineering construction, in particular to a method and a device for arranging reinforcing steel bars and electronic equipment.
Background
In the field steel bar construction process of engineering projects, a steel bar material list can meet the field blanking requirement, but cannot completely meet the field construction requirement, and the arrangement information of the steel bars is needed during field construction, so that the steel bar construction is conveniently guided. In the process of carrying out the sample according to the drawing, a sample overturning person needs to express the arrangement condition of the steel bars through a layout diagram for guiding site construction, meanwhile, whether a bill is reasonable or not needs to be checked through the layout diagram, whether the standard requirement is met or not, whether site construction is convenient or not is required, and the bill can be quickly modified and updated after the problem is found.
The method for arranging the reinforcing steel bars is commonly adopted in the prior art, and a three-dimensional model and a two-dimensional arrangement diagram of the reinforcing steel bars are simultaneously generated through automatic calculation of a BIM model. However, in the above technical solution, since the three-dimensional model and the two-dimensional layout of the reinforcing steel bar are generated based on the BIM model at the same time, the two models are independent from each other. If the two-dimensional arrangement diagram of the reinforcing steel bars is modified, the three-dimensional model of the reinforcing steel bars is required to be modified, so that the arrangement efficiency of the reinforcing steel bars is low.
Disclosure of Invention
In view of the above, the embodiment of the invention provides a method and a device for arranging reinforcing steel bars and electronic equipment, so as to solve the problem of lower reinforcing steel bar arrangement efficiency.
According to a first aspect, an embodiment of the present invention provides a method for arranging reinforcing bars, including:
obtaining a three-dimensional model of the steel bar;
generating a steel bar layout diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar layout diagram;
acquiring modification of the reinforcement bar layout;
and adjusting the three-dimensional model of the steel bar based on the association relation and the modification.
According to the reinforcement bar arrangement method provided by the embodiment of the invention, the reinforcement bar arrangement diagram is generated based on the reinforcement bar three-dimensional model, and the reinforcement bar three-dimensional model have an association relationship, so that the reinforcement bar three-dimensional model can be synchronously adjusted when the reinforcement bar arrangement diagram is modified, and the reinforcement bar arrangement efficiency is improved.
With reference to the first aspect, in a first implementation manner of the first aspect, the generating a reinforcement bar layout diagram based on the reinforcement bar three-dimensional model and determining an association relationship between the reinforcement bar three-dimensional model and the reinforcement bar layout diagram includes:
acquiring BIM model primitives in the three-dimensional model of the steel bar;
and converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional arrangement diagram data based on the three-dimensional steel bar models so as to generate the steel bar arrangement diagram and determine the association relation.
According to the reinforcement bar arrangement method provided by the embodiment of the invention, the BIM model graphic elements needing to be arranged are acquired before the reinforcement bar arrangement is generated, instead of generating the reinforcement bar arrangement for all graphic elements, namely, the arrangement method can be used for creating the arrangement according to the range so as to solve the problem of operation blocking under the condition of large area.
With reference to the first embodiment of the first aspect, in a second embodiment of the first aspect, the converting, based on the rebar three-dimensional model, a rebar three-dimensional line of the BIM model primitive into two-dimensional layout data to generate the rebar layout includes:
determining the steel bar information of each steel bar three-dimensional line in the BIM model graphic element by utilizing the steel bar three-dimensional model;
Determining starting point coordinates and rotation angles of the three-dimensional lines of the steel bars after being converted into two dimensions based on the steel bar information;
determining an adjustment angle by using the range of the rotation angle;
determining a conversion matrix based on the starting point coordinates, the rotation angle and the adjustment angle to determine the association relation, wherein the conversion matrix comprises a first conversion matrix from three-dimensional to two-dimensional and a second conversion matrix from two-dimensional to three-dimensional;
and generating the steel bar layout diagram by using the conversion matrix.
According to the reinforcement bar arrangement method provided by the embodiment of the invention, the conversion matrix is determined by utilizing the reinforcement bar information of each reinforcement bar three-dimensional line in the BIM model graphic element, so that the first conversion matrix from three-dimensional to two-dimensional and the second conversion matrix from two-dimensional to three-dimensional are realized, the two-dimensional arrangement diagram can be converted into the three-dimensional reinforcement bar three-dimensional model through the second conversion matrix after the arrangement diagram is edited, and the reinforcement bar arrangement efficiency is improved.
With reference to the second embodiment of the first aspect, in a third embodiment of the first aspect, the reinforcement information includes a start end coordinate and a bending length, and the determining, based on the reinforcement information, the start end coordinate and the rotation angle after the three-dimensional line of each reinforcement is converted into two dimensions includes:
Deducting the bending length from the initial end to obtain a bent steel bar section;
based on the coordinates of the bent steel bar segments, obtaining starting point coordinates after the three-dimensional lines of the steel bars are converted into two dimensions;
and determining the rotation angle by utilizing the included angle between the projection of the bent steel bar section and the coordinate axis.
According to the method for arranging the reinforcing steel bars, when the starting point coordinates of the three-dimensional lines of the reinforcing steel bars are calculated and converted into two dimensions, the bending length of the three-dimensional lines of the reinforcing steel bars is deducted, so that the accuracy of the starting point coordinates and the rotating angle is guaranteed.
With reference to the first embodiment of the first aspect, in a fourth embodiment of the first aspect, the obtaining a BIM model primitive in the three-dimensional model of the steel reinforcement includes:
judging whether an arrangement range is selected or not;
and when the arrangement range is not selected, acquiring a primitive list of the current component type of the current layer to determine the BIM model primitive.
According to the method for arranging the reinforcing steel bars, when the arrangement range is not selected, only the primitives in the primitive list of the current component type of the current layer are used as BIM model primitives, instead of carrying out reinforcing steel bar arrangement on all the primitives, so that the data processing amount of reinforcing steel bar arrangement is reduced, and the problem of operation blocking under the condition of large area can be avoided.
With reference to the first aspect or any one of the first to fourth implementation manners of the first aspect, in a fifth implementation manner of the first aspect, the association relationship includes a second conversion matrix from two dimensions to three dimensions, and the adjusting the three-dimensional model of the reinforcing steel bar based on the association relationship and the modification includes:
acquiring coordinates of each reinforcing steel bar line in the modified reinforcing steel bar layout;
based on the coordinates of each reinforcement wire and the two-dimensional to three-dimensional second transformation matrix, adjusting the reinforcement three-dimensional model;
and displaying the adjusted reinforcement bar layout.
According to the reinforcement bar arrangement method provided by the embodiment of the invention, the modified reinforcement bar arrangement diagram is mapped into the reinforcement bar three-dimensional model by using the second conversion matrix, so that synchronous modification of the reinforcement bar three-dimensional model is realized, and the modified reinforcement bar arrangement diagram is displayed, so that the reinforcement bar arrangement diagram is edited again.
With reference to the fifth implementation manner of the first aspect, in a sixth implementation manner of the first aspect, the displaying the adjusted rebar layout includes:
acquiring graphic elements which are displayed in batches in the steel bar arrangement diagram;
and processing the primitives in batch display to perform batch display.
According to the reinforcement bar arrangement method provided by the embodiment of the invention, the graphic elements are displayed in batches in the same arrangement diagram, and each graphic element does not need to be displayed separately, so that the modification efficiency is improved.
With reference to the sixth implementation manner of the first aspect, in a seventh implementation manner of the first aspect, when the primitive displayed in batch is a column primitive, the processing the primitive displayed in batch to perform batch display includes:
classifying the column primitives by utilizing attribute information of each column primitive;
and for the column primitives in the same classification, when the three-dimensional lines of the steel bars of the column primitives are consistent with other data except for positioning points, merging and displaying the column primitives in the same classification, and recording merging sources.
According to the method for arranging the reinforcing steel bars, provided by the embodiment of the invention, a batch capture map display mode and a single multi-layer display mode are provided for the columns, so that batch modification of column primitives can be ensured.
With reference to the sixth implementation manner of the first aspect, in an eighth implementation manner of the first aspect, when the primitive displayed in batch is a wall primitive, the processing the primitive displayed in batch to perform batch display includes:
Acquiring an arrangement diagram of each wall primitive under at least one view angle;
and carrying out batch display based on the arrangement diagram under the at least one view angle.
According to the method for arranging the reinforcing steel bars, provided by the embodiment of the invention, the wall arrangement diagram is constructed in a batch display mode aiming at the wall primitives, namely, the arrangement diagram of the wall primitives under at least one view angle is displayed in batch, positioning information is provided, and the modification efficiency is higher.
With reference to the fifth implementation manner of the first aspect, in a ninth implementation manner of the first aspect, the displaying the adjusted rebar layout includes:
obtaining the short-cut operation of the blanking length;
and sequentially arranging the information of the steel bar wires at the end positions of each steel bar wire in the steel bar arrangement diagram.
The method for arranging the reinforcing steel bars provided by the embodiment of the invention provides information of arranging the reinforcing steel bar lines by the arrangement diagram, namely provides a scheme for labeling and abbreviated as the reinforcing steel bars by the arrangement diagram, and optimizes the information display effect of the arrangement diagram.
According to a second aspect, an embodiment of the present invention further provides a rebar arranging apparatus, including:
the acquisition module is used for acquiring the three-dimensional model of the steel bar;
the generation module is used for generating a steel bar arrangement diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar arrangement diagram;
The modification module is used for acquiring modification of the steel bar arrangement diagram;
and the adjusting module is used for adjusting the three-dimensional model of the steel bar based on the association relation and the modification.
According to the reinforcing steel bar arrangement device provided by the embodiment of the invention, the reinforcing steel bar arrangement diagram is generated based on the reinforcing steel bar three-dimensional model, and the reinforcing steel bar three-dimensional model have an association relationship, so that the reinforcing steel bar three-dimensional model can be synchronously adjusted when the reinforcing steel bar arrangement diagram is modified, and the reinforcing steel bar arrangement efficiency is improved.
According to a third aspect, an embodiment of the present invention provides an electronic device, including: the device comprises a memory and a processor, wherein the memory and the processor are in communication connection, the memory stores computer instructions, and the processor executes the computer instructions so as to execute the reinforcement bar arrangement method in the first aspect or any implementation manner of the first aspect.
According to a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium storing computer instructions for causing the computer to perform the rebar arrangement method of the first aspect or any one of the embodiments of the first aspect.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are needed in the description of the embodiments or the prior art will be briefly described, and it is obvious that the drawings in the description below are some embodiments of the present invention, and other drawings can be obtained according to the drawings without inventive effort for a person skilled in the art.
Fig. 1 is a flowchart of a rebar arrangement method according to an embodiment of the present invention;
fig. 2 is a flowchart of a rebar arrangement method according to an embodiment of the present invention;
fig. 3 is a flowchart of a rebar arrangement method according to an embodiment of the present invention;
fig. 4 is a flowchart of a rebar arrangement method according to an embodiment of the present invention;
fig. 5 is a flowchart of a rebar arrangement method according to an embodiment of the present invention;
FIGS. 6 a-6 b are schematic diagrams before and after blanking length shorthand according to an embodiment of the present invention;
fig. 7 is a block diagram illustrating a construction of a reinforcing bar arrangement apparatus according to an embodiment of the present invention;
fig. 8 is a schematic diagram of a hardware structure of an electronic device according to an embodiment of the present invention.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present invention more apparent, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is apparent that the described embodiments are some embodiments of the present invention, but not all embodiments of the present invention. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
According to an embodiment of the present invention, there is provided an embodiment of a rebar arrangement method, it being noted that the steps shown in the flowchart of the drawings may be performed in a computer system such as a set of computer executable instructions, and that although a logical order is shown in the flowchart, in some cases the steps shown or described may be performed in an order other than that shown or described herein.
In this embodiment, a method for arranging reinforcing bars is provided, which may be used in electronic devices, such as a computer, a mobile phone, a tablet computer, etc., fig. 1 is a flowchart of a method for arranging reinforcing bars according to an embodiment of the present invention, as shown in fig. 1, where the flowchart includes the following steps:
s11, obtaining a three-dimensional model of the steel bar.
The three-dimensional model of the steel bar can be obtained by the electronic equipment from the outside, or can be calculated by the electronic equipment by using a construction BIM model. Specifically, the electronic equipment can automatically calculate and generate the three-dimensional reinforcing steel bar model according to the construction BIM model and the flat method information by adding reinforcing steel bar flat method information to the construction BIM model. Of course, the manner of generating the three-dimensional model of the rebar is not limited to that described above, and may be generated in other ways.
The construction BIM model can be obtained by manually modeling on the electronic equipment by a user, can be obtained by modeling the electronic equipment through CAD recognition, can be obtained by importing the GTJ model into the electronic equipment, and the like. The method for acquiring the construction BIM model by the electronic equipment is not limited, and the method can be set correspondingly according to actual requirements.
And S12, generating a steel bar layout diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar layout diagram.
The steel bar arrangement pattern is a two-dimensional data line of the steel bars, and in the three-dimensional model of the steel bars, each steel bar line is represented in a three-dimensional line mode of the steel bars, so that the three-dimensional line of the steel bars is required to be mapped into the two-dimensional data line, and the association relationship between the three-dimensional model of the steel bars and the steel bar arrangement pattern is determined to generate the steel bar arrangement pattern. Based on the above, the association relationship may be determined by using a coordinate conversion manner or a projection manner, and accordingly, the electronic device may generate the rebar layout diagram by using a coordinate conversion manner, may generate the rebar layout diagram by using a projection manner, or may generate the rebar layout diagram by using other manners, and so on. The method is not limited at all, and the electronic equipment is only required to generate a steel bar layout diagram based on the steel bar three-dimensional model, namely, the association relation between the steel bar three-dimensional model and the steel bar layout diagram is established.
This step will be described in detail later in detail.
S13, modification of the reinforcement bar layout diagram is obtained.
After the electronic device generates the rebar layout, it provides a user modification interface on which the user modifies the rebar layout, and accordingly, the electronic device may obtain the modification to the rebar layout.
The modification may be modification of the information of the steel bars, modification of the arrangement of the steel bars, and the like, and the corresponding modification may be specifically performed according to actual requirements, but no modification is specified.
And S14, adjusting the three-dimensional model of the steel bar based on the association relation and the modification.
As described above, the rebar layout diagram is generated based on a rebar three-dimensional model, and then there is an association between the two. When the reinforcement bar layout is modified, the reinforcement bar three-dimensional model can be automatically and correspondingly adjusted, so that the linkage adjustment of the reinforcement bar three-dimensional model and the reinforcement bar three-dimensional model is realized.
For example, when the rebar placement diagram is generated using a coordinate transformation, the electronics can utilize the inverse coordinate transformation to adjust the rebar three-dimensional model using modifications of the rebar placement diagram.
According to the reinforcement bar arrangement method, the reinforcement bar arrangement diagram is generated based on the reinforcement bar three-dimensional model, the association relationship exists between the reinforcement bar three-dimensional model and the reinforcement bar three-dimensional model, and when the reinforcement bar arrangement diagram is modified, the reinforcement bar three-dimensional model can be synchronously adjusted, so that the reinforcement bar arrangement efficiency is improved.
In this embodiment, a method for arranging reinforcing bars is provided, which may be used in electronic devices, such as computers, mobile phones, tablet computers, etc., fig. 2 is a flowchart of a method for arranging reinforcing bars according to an embodiment of the present invention, as shown in fig. 2, where the flowchart includes the following steps:
S21, obtaining a three-dimensional model of the steel bar.
As shown in fig. 3, a project is newly built in the electronic device to obtain a construction BIM model. For example, manual modeling, CAD-identified modeling, or importing a GTJ model, etc. may be employed.
And after the electronic equipment obtains the construction BIM model, adding reinforcement leveling information to the construction BIM model, and then summarizing and calculating to obtain the reinforcement three-dimensional model.
Please refer to S11 in the embodiment shown in fig. 1 for the rest details, which will not be described herein.
S22, generating a steel bar arrangement diagram based on the steel bar three-dimensional model and determining the association relation between the steel bar three-dimensional model and the steel bar arrangement diagram.
Specifically, the step S22 may include:
s221, obtaining BIM model primitives.
The electronic device obtains a BIM model, wherein the three-dimensional model of the reinforcing steel bar is attached to the primitives of the BIM model. That is, after the electronic device obtains the BIM model, the selection of BIM model primitives may be provided. Specifically, the user may make a box selection, or click, etc. in the BIM model. Accordingly, the electronic device may obtain the BIM model primitive.
Or the electronic device may directly determine the primitive in the primitive list corresponding to the current component type of the current layer as the BIM model primitive; alternatively, the electronic device may determine the BIM model primitive in other ways.
In some optional implementations of this embodiment, as shown in fig. 4, S221 may include:
(1) Judging whether an arrangement range is selected or not;
when the arrangement range is not selected, executing the step (2); otherwise, executing the step (3).
(2) And obtaining a primitive list of the current component type of the current layer to determine BIM model primitives.
(3) And acquiring the selected arrangement range.
Specifically, the determination of BIM model primitives is divided into two operational scenarios: firstly, when a user does not select an arrangement range, BIM model primitives are all primitives of the current component type of the current layer, namely, only the arrangement diagram information of the primitives is displayed; secondly, when a user selects an arrangement range, only the information of the arrangement diagram of the primitives in the arrangement range is displayed when the user enters the arrangement diagram.
When the arrangement range is not selected, only the primitives in the primitive list of the current component type of the current layer are used as BIM model primitives, instead of carrying out steel bar arrangement on all the primitives, the data processing amount of steel bar arrangement is reduced, and the problem of operation blocking under the condition of large area can be avoided.
S222, converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional arrangement diagram data based on the three-dimensional steel bar models so as to generate a steel bar arrangement diagram and determine association relations.
For the generation of the reinforcement bar layout, in this embodiment, the association relationship is calculated by adopting a coordinate transformation method, that is, a transformation matrix from a three-dimensional model to two dimensions is used to transform the reinforcement bar three-dimensional line into two-dimensional layout data.
Further, a conversion matrix for converting the two-dimensional arrangement data into the three-dimensional model of the reinforcing steel bar can be reversely calculated according to the generation process, so that the two-dimensional arrangement diagram data can be converted into the three-dimensional model of the reinforcing steel bar through the conversion matrix after the arrangement diagram is edited.
In some optional implementations of this embodiment, the step S222 may include:
(1) And determining the steel bar information of each steel bar three-dimensional line in the BIM model graphic element by using the steel bar three-dimensional model.
The reinforcement information of the reinforcement three-dimensional line can be obtained from the reinforcement three-dimensional model, and the reinforcement information can comprise the initial end coordinates, the bending length and the like of each reinforcement three-dimensional line.
(2) And determining starting point coordinates and rotation angles of the three-dimensional lines of the steel bars after the three-dimensional lines of the steel bars are converted into two dimensions based on the steel bar information.
The electronic equipment determines the starting point coordinates and the rotation angles of the three-dimensional lines of the steel bars after being converted into two dimensions, so that the corresponding conversion matrix is obtained by utilizing the translation and rotation of the coordinates.
As an alternative implementation manner of this embodiment, step (2) of S222 may include:
2.1 Deducting the bending length from the initial end to obtain the bent steel bar section.
When the three-dimensional model of the steel bar is generated, the bending lengths of the starting end and the tail end of each three-dimensional line of the steel bar are calculated, and the starting end and the bending lengths are recorded in the three-dimensional model of the steel bar at the moment, so that the electronic equipment can acquire the starting end and the bending lengths. When the layout diagram is generated, the bending length is deducted by the starting end, and the bent steel bar section can be obtained.
2.2 Based on the coordinates of the bent steel bar segments, the starting point coordinates of the steel bar three-dimensional line converted into two dimensions are obtained.
And subtracting the starting point of the three-dimensional line of the steel bar after the bending length from the starting end of the three-dimensional line of the steel bar, namely obtaining the values of the corresponding coordinate points x, y and z. The starting point position of the steel bar after three-dimensional conversion into two dimensions can be determined, and the three-dimensional coordinate position can be marked as (x, y, z).
2.3 The rotation angle is determined by utilizing the included angle between the projection of the bent steel bar section and the coordinate axis.
The electronic equipment can calculate the three-dimensional deduction of the bent steel bar segments of the steel bar according to the initial bending length of the steel bar, the initial segments of the deduction of the bent steel bar segments are projected in a overlooking mode, the initial segment two-dimensional line can be obtained, and the included angle between the initial segment two-dimensional line and the X axis is the rotation angle and is marked as a. Wherein the rotation angle is expressed in radians.
And when the starting point coordinates of the three-dimensional line of the steel bar are calculated and converted into two dimensions, deducting the bending length of the three-dimensional line of the steel bar so as to ensure the accuracy of the starting point coordinates and the rotation angle.
(3) The adjustment angle is determined using the range of rotation angles.
And comparing the rotation angle with a preset value, and determining a corresponding adjustment angle theta. For example, if a is greater than or equal to 3 pi/4 and less than 7 pi/4, θ is pi/2, otherwise θ is-pi/2.
(4) And determining a conversion matrix based on the starting point coordinates, the rotation angle and the adjustment angle to determine the association relation, wherein the conversion matrix comprises a first conversion matrix from three dimensions to two dimensions and a second conversion matrix from two dimensions to three dimensions. The association relation is represented by the first conversion matrix and the second conversion matrix.
Specifically, the three-dimensional to two-dimensional first transformation matrix can be calculated by the following formula:
the two-dimensional to three-dimensional second transformation matrix can be calculated by the following formula:
further, when the reinforcement wire is in the XOY plane, the three-dimensional to two-dimensional first transformation matrix may be expressed as:
the second transformation matrix from two dimensions to three dimensions can be expressed as:
whether the reinforcement line is in the XOY plane is determined by the type of reinforcement, for example, the side reinforcement of the plate and the horizontal reinforcement of the wall are all in the XOY plane.
(5) And generating a reinforcement bar layout diagram by using the conversion matrix.
And determining a conversion matrix by utilizing the reinforcement information of each reinforcement three-dimensional line in the BIM model graphic element, and realizing a first conversion matrix from three-dimensional to two-dimensional and a second conversion matrix from two-dimensional to three-dimensional, so that the two-dimensional arrangement diagram can be converted into a three-dimensional reinforcement three-dimensional model through the second conversion matrix after the arrangement diagram is edited, and the arrangement efficiency of the reinforcement is improved.
In some optional implementations of this embodiment, when the electronic device generates the reinforcement bar layout plan using the reinforcement bar three-dimensional model, the electronic device may also generate a reinforcement bar contour line, so as to be used for primarily defining the reinforcement bar in the subsequent construction process, or facilitate a subsequent confirmation of whether each reinforcement bar line meets a construction requirement, or the like.
Specifically, contour lines of the component model (top-view contour lines of walls, beams, plates, etc., top or bottom contour lines of rafts, catchments) reinforcing bar lines, reinforcing bar size information, lap joint information may be displayed. When the layout data is generated through the three-dimensional model, the contour lines of the wall, the beam, the plate and the like are directly realized by adopting the overlooking projection polygons of the model; the bottom surface or the top surface contour line of the water pit and the raft plate is realized by adopting a blanking line algorithm, the top surface contour line is realized by adopting a mode of observing from the positive direction to the negative direction of the Z axis, and the bottom surface contour line is realized by adopting a mode of observing from the negative direction to the positive direction of the Z axis. The above manner of generating the contour lines of the respective members is merely an example, and the scope of the present invention is not limited thereto, and may be adjusted accordingly according to actual needs.
S23, modification of the reinforcement bar layout diagram is obtained.
The modification of the reinforcement bar layout diagram can involve the following points:
(1) Setting and bending: the support sets up multistage buckling, and operating point sets up the button of buckling, selects the reinforcing bar bending point to revise or add the buckling, can realize the modification of buckling length after input bending angle and length are confirmed, supports batch operation, and the bending angle is the contained angle of reinforcing bar line clockwise and bending line, and positive value represents clockwise, and negative value represents anticlockwise. Setting the bending is to reset the selected end point, and the original bending with joints or other bending will disappear and reset according to the input value. When both ends of the selected end point are straight sections, the two ends are compared with the straight sections, and the shorter end is reset.
(2) Text modification optimization: the text parameters can be modified by double clicking, compared with the existing market scheme, the method supports direct input of 0 to delete a certain section of reinforcing steel bar, supports tab jump and is convenient for rapidly switching texts; when 0 is input into the bending section, if the bending section is left bending, the left reinforcing steel bar section of the modifying section is deleted, if the bending section is right bending, the right reinforcing steel bar section of the modifying section is deleted, and when 0 is input into the main section, the reinforcing steel bar line with the small length of the remaining section is deleted; and when the tab key is pressed, calculating the position of the next editable text according to the position of the current editing box.
(3) Recalculating and back-calculating: the joint positions are quickly adjusted in batches to meet the field construction requirements, the modification efficiency is high, and the operation mode is simple and convenient; automatically arranging lap joints on the steel bar wires according to the input blanking length sequence during recalculation, and segmenting the steel bar according to 9000+9000. The blanking length when an integer form is input, for example 9000, until the residual steel bar is less than 9000; when an integer +integer + … … is input, for example 9000+5000, the reinforcing steel bars are segmented according to the blanking length modulus of 9000+5000+5000+50000+5000 according to the sequence until the corresponding modulus of the residual reinforcing steel bars is insufficient; the back calculation function is provided, so that a user can turn around the blanking length of the steel bars quickly, the requirement of 50% staggering is met, a plurality of steel bars can be selected or framed during operation, right keys are determined, software automatically calculates a blanking length list according to the existing lap joint position of the selected steel bars, then the blanking length list is in reverse order, and lap joints are arranged on the steel bars again, for example, the original blanking length is 9000+6000+3000, and 3000+6000+9000 is obtained after back calculation.
(4) One-by-one and three-by-one: and matching with other modification commands, and rapidly selecting the reinforcing steel bars for modification operation.
(5) Rotating the arrangement diagram: the view port of the arrangement diagram rotates, so that the view port can be rotated to a horizontal state when the raft and the board Y-direction steel bars are modified, and the observation and the operation are convenient.
(6) Number of ribs and modification: the reinforcing steel bars are quickly numbered and modified, and quick material selection construction is facilitated during site construction.
(7) And (5) reducing and merging: and the steel bars meeting the arithmetic series are expressed in a reduced form, so that the display definition of the layout diagram is improved.
It should be noted that the above modification is merely an example, and the scope of the present invention is not limited thereto, and the present invention may be specifically set according to actual requirements.
And S24, adjusting the three-dimensional model of the steel bar based on modification.
Please refer to the embodiment S14 in fig. 1 in detail, which is not described herein.
According to the reinforcement bar arrangement method provided by the embodiment, BIM model graphic elements needing to be arranged are obtained before the reinforcement bar arrangement is generated, instead of generating the reinforcement bar arrangement for all graphic elements, namely, the arrangement method can be used for creating the arrangement according to the range so as to solve the problem of operation blocking under the condition of large area.
In this embodiment, a method for arranging reinforcing bars is provided, which may be used in electronic devices, such as computers, mobile phones, tablet computers, etc., fig. 5 is a flowchart of a method for arranging reinforcing bars according to an embodiment of the present invention, as shown in fig. 5, where the flowchart includes the following steps:
s31, obtaining a three-dimensional model of the steel bar.
Please refer to the embodiment S21 shown in fig. 2 in detail, which is not described herein.
S32, generating a steel bar arrangement diagram based on the steel bar three-dimensional model and determining the association relation between the steel bar three-dimensional model and the steel bar arrangement diagram.
Please refer to the embodiment S22 shown in fig. 2 in detail, which is not described herein.
S33, modification of the reinforcement bar layout diagram is obtained.
Please refer to the embodiment S23 shown in fig. 2 in detail, which is not described herein.
And S34, adjusting the three-dimensional model of the steel bar based on the association relation and the modification.
The association relation comprises a second conversion matrix from two dimensions to three dimensions. Specifically, the step S34 may include:
s341, obtaining the coordinates of each reinforcement wire in the modified reinforcement bar layout.
As described above, if the electronic device adjusts the arrangement of the individual reinforcement wires in the reinforcement bar arrangement chart, the electronic device may obtain the coordinates of the modified individual reinforcement wires.
And S342, adjusting the three-dimensional model of the steel bar based on the coordinates of each steel bar line and the two-dimensional to three-dimensional second conversion matrix.
After the coordinates of each modified reinforcing steel bar line are obtained, the electronic equipment can correspondingly adjust the reinforcing steel bar three-dimensional model by utilizing a two-dimensional to three-dimensional second conversion matrix. For the second conversion matrix from two dimensions to three dimensions, please refer to the related description in the embodiment shown in fig. 2 in detail, and the detailed description is omitted herein.
S343, displaying the adjusted reinforcement bar layout.
After the electronic device generates the rebar placement layout, the rebar placement layout may be displayed on an interface; alternatively, the adjusted rebar placement pattern or the like may be displayed. When the steel bar arrangement diagram is displayed, the graphic elements can be displayed in batches.
According to the reinforcement bar arrangement method provided by the embodiment, the modified reinforcement bar arrangement diagram is mapped into the reinforcement bar three-dimensional model by using the second conversion matrix, so that synchronous modification of the reinforcement bar three-dimensional model is realized, and the modified reinforcement bar arrangement diagram is displayed, so that the reinforcement bar arrangement diagram is edited again.
In some optional implementations of this embodiment, the step S343 may include:
(1) And obtaining the graphic elements displayed in batches in the steel bar arrangement diagram.
The graphic elements displayed in batch can be selected by a user, customized by electronic equipment, and the like, and the graphic elements are not limited at all, and the electronic equipment can be ensured to acquire the graphic elements required to be displayed in batch.
(2) And processing the primitives displayed in batches to display in batches.
After the primitives for the batch display are acquired, they may be combined, or the layout diagram at a certain viewing angle or at certain viewing angles may be displayed, so as to display the primitives for the batch display.
The primitives are displayed in batches in the same layout, and each primitive does not need to be displayed separately, so that the modification efficiency is improved.
The conventional column and wall layout schemes are generally single walls or multiple layers of columns are displayed together, so that the problems caused by the scheme are low inspection and modification efficiency, the layout is mostly vertical layout information, and plane positioning information is lacked. In this embodiment, a batch layout display mode and a single multi-layer display mode are provided for column primitives; aiming at the wall primitives, the invention constructs the wall layout in a batch display mode.
When the primitives displayed in batch are column primitives, step (2) of S343 may include:
2.1 Classifying the column primitives using attribute information of each column primitive.
The electronic equipment classifies the columns according to the basic bottom, basic thickness, basic top/layer bottom, the net height of the layer, beam height, upper net height and the like according to the primitive range selected by the user, and the columns with the same information are classified into one type.
2.2 For the column primitives with the same classification, when the three-dimensional lines of the reinforcing steel bars of the column primitives are consistent with other data except for positioning points, the column primitives with the same classification are combined and displayed, and the combined sources are recorded.
And if the data of the three-dimensional lines of the steel bars except the positioning points are consistent, merging the column graphic elements of the same classification into a steel bar to be displayed in a layout diagram, recording merging sources, and synchronizing the three-dimensional models of the steel bars according to the merging sources during modification.
And a batch capture map display mode and a single multi-layer display mode are provided for the column, so that batch modification of column primitives can be ensured.
The existing display for the wall layout is a single component layout, which is essentially different from the present solution. The present solution eliminates the display of a single layout, but displays a wall layout at least one viewing angle. Specifically, when the primitives displayed in batch are wall primitives, step (2) of S343 may include:
2.1 A row pattern of each wall primitive at least one viewing angle is obtained.
2.2 Based on a layout at least one viewing angle).
The method comprises the steps of displaying a steel bar arrangement diagram according to a wall overlooking position by default, arranging horizontal steel bars on the left side and the right side of a wall contour line according to elevation sequences and arrangement numbers, arranging the first row on the left side, arranging the other rows on the right side according to sequences, displaying vertical steel bars in the wall contour line in a top view by using coils, adding capping, communicating and dowel bar marks to mark the construction scheme, and displaying blanking information of the vertical steel bars by using a centralized marking table. Under the condition that the vertical rib structure of the wall is complex, the side view drawing function can be used for drawing the side view information of the vertical rib of a certain wall, so that the vertical rib can be conveniently inspected and modified.
The wall layout is constructed in a batch display mode aiming at the wall primitives, namely, the layout of the wall primitives under at least one view angle is displayed in batch, positioning information is provided, and the modification efficiency is high.
Because the steel bars are often lifted by hands, the steel bars are often rusted on the hands after the steel bars are lifted, the layout diagram is frequently dirty locally, and the length data of the local steel bars can not be seen. If the display of the overlong steel bars is concentrated on the left side, the first view is more concentrated and convenient, the second view can prevent the pollution to the position with data on the left side as much as possible, and the position with data is more fixed. Often have the construction evening, connect the data of overlength reinforcing bar and concentrate on the left side, under the not good circumstances of light evening, look over the advantage that the map data has more obvious. Based on this, in other optional implementation manners of this embodiment, S343 may include:
(1) And obtaining the short operation of the blanking length.
(2) And sequentially arranging the information of the reinforcing steel bars at the end positions of each reinforcing steel bar line in the reinforcing steel bar arrangement diagram.
When the user selects the shorthand of the blanking length, the shorthand of the steel bar information is regenerated at the initial position of the steel bar line according to a certain sequence, and the original scattered steel bar information is hidden. When the short choice of the blanking length is removed, the blanking length is shortened and hidden, the original steel bar information is displayed, and the short choice is only for intensively displaying the scattered steel bar blanking information in the existing scheme. The arrangement sequence of the steel bar information can sequentially comprise the sequence of the number of the steel bars, the blanking length and the lap joint type.
For example, see fig. 6a before shorthand, and fig. 6b for a post shorthand effect.
Providing information of the arrangement diagram for arranging the steel bar lines, namely providing a scheme for labeling and abbreviated arrangement diagram steel bars, and optimizing the information display effect of the arrangement diagram. The simple and written scheme of the steel bar label enables the label information to be more concise and clear, and is convenient for field viewing.
Further alternatively, as shown in fig. 3, the electronic device may output the rebar layout in a CAD drawing after generating it, so as to guide site operations.
In this embodiment, a reinforcing steel bar arrangement device is further provided, and the device is used to implement the foregoing embodiments and preferred embodiments, and is not described in detail. As used below, the term "module" may be a combination of software and/or hardware that implements a predetermined function. While the means described in the following embodiments are preferably implemented in software, implementation in hardware, or a combination of software and hardware, is also possible and contemplated.
This embodiment provides a rebar arranging device, as shown in fig. 7, including:
an acquisition module 41, configured to acquire a three-dimensional model of the steel bar;
a generating module 42, configured to generate a rebar arrangement diagram based on the rebar three-dimensional model and determine an association relationship between the rebar three-dimensional model and the rebar arrangement diagram;
A modification module 43, configured to obtain modification to the rebar arrangement plan;
an adjustment module 44 for adjusting the three-dimensional model of the rebar based on the modification.
According to the reinforcing steel bar arrangement device, the reinforcing steel bar arrangement diagram is generated based on the reinforcing steel bar three-dimensional model, the association relationship exists between the reinforcing steel bar three-dimensional model and the reinforcing steel bar three-dimensional model, and the reinforcing steel bar three-dimensional model can be synchronously adjusted when the reinforcing steel bar arrangement diagram is modified, so that the reinforcing steel bar arrangement efficiency is improved.
The rebar placement device in this embodiment is presented as a functional unit, where the unit refers to an ASIC circuit, a processor and memory that execute one or more software or firmware programs, and/or other devices that provide the functionality described above.
Further functional descriptions of the above respective modules are the same as those of the above corresponding embodiments, and are not repeated here.
The embodiment of the invention also provides electronic equipment, which is provided with the steel bar arrangement device shown in the figure 7.
Referring to fig. 8, fig. 8 is a schematic structural diagram of an electronic device according to an alternative embodiment of the present invention, as shown in fig. 8, the electronic device may include: at least one processor 51, such as a CPU (Central Processing Unit ), at least one communication interface 53, a memory 54, at least one communication bus 52. Wherein the communication bus 52 is used to enable connected communication between these components. The communication interface 53 may include a Display screen (Display) and a Keyboard (Keyboard), and the selectable communication interface 53 may further include a standard wired interface and a wireless interface. The memory 54 may be a high-speed RAM memory (Random Access Memory, volatile random access memory) or a non-volatile memory (non-volatile memory), such as at least one disk memory. The memory 54 may alternatively be at least one memory device located remotely from the aforementioned processor 51. Wherein the processor 51 may be as described in connection with fig. 7, the memory 54 stores an application program, and the processor 51 invokes the program code stored in the memory 54 for performing any of the method steps described above.
The communication bus 52 may be a peripheral component interconnect standard (peripheral component interconnect, PCI) bus or an extended industry standard architecture (extended industry standard architecture, EISA) bus, among others. The communication bus 52 may be classified as an address bus, a data bus, a control bus, or the like. For ease of illustration, only one thick line is shown in fig. 8, but not only one bus or one type of bus.
Wherein the memory 54 may include volatile memory (english) such as random-access memory (RAM); the memory may also include a nonvolatile memory (english: non-volatile memory), such as a flash memory (english: flash memory), a hard disk (english: hard disk drive, abbreviated as HDD) or a solid state disk (english: solid-state drive, abbreviated as SSD); memory 54 may also include a combination of the types of memory described above.
The processor 51 may be a central processor (English: central processing unit, abbreviated: CPU), a network processor (English: network processor, abbreviated: NP) or a combination of CPU and NP.
The processor 51 may further include a hardware chip, among others. The hardware chip may be an application-specific integrated circuit (ASIC), a Programmable Logic Device (PLD), or a combination thereof (English: programmable logic device). The PLD may be a complex programmable logic device (English: complex programmable logic device, abbreviated: CPLD), a field programmable gate array (English: field-programmable gate array, abbreviated: FPGA), a general-purpose array logic (English: generic array logic, abbreviated: GAL), or any combination thereof.
Optionally, the memory 54 is also used for storing program instructions. The processor 51 may call program instructions to implement the rebar arrangement method as shown in the embodiments of fig. 1 to 5 of the present application.
The embodiment of the invention also provides a non-transitory computer storage medium, which stores computer executable instructions, and the computer executable instructions can execute the method for arranging the reinforcing steel bars in any of the method embodiments. Wherein the storage medium may be a magnetic Disk, an optical Disk, a Read-Only Memory (ROM), a random access Memory (Random Access Memory, RAM), a Flash Memory (Flash Memory), a Hard Disk (HDD), or a Solid State Drive (SSD); the storage medium may also comprise a combination of memories of the kind described above.
Although embodiments of the present invention have been described in connection with the accompanying drawings, various modifications and variations may be made by those skilled in the art without departing from the spirit and scope of the invention, and such modifications and variations fall within the scope of the invention as defined by the appended claims.
Claims (11)
1. A method of arranging reinforcing bars, comprising:
obtaining a three-dimensional model of the steel bar;
Generating a steel bar layout diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar layout diagram;
acquiring modification of the reinforcement bar layout;
adjusting the three-dimensional model of the steel bar based on the association relation and the modification;
wherein, generating a reinforcement bar layout diagram based on the reinforcement bar three-dimensional model and determining an association relationship between the reinforcement bar three-dimensional model and the reinforcement bar layout diagram comprises:
acquiring a BIM model primitive;
converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional arrangement chart data based on the three-dimensional steel bar models so as to generate the steel bar arrangement chart and determine the association relation;
the step of converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional layout diagram data based on the three-dimensional steel bar models to generate the steel bar layout diagram and determine the association relation comprises the following steps:
determining the steel bar information of each steel bar three-dimensional line in the BIM model graphic element by utilizing the steel bar three-dimensional model;
determining starting point coordinates and rotation angles of the three-dimensional lines of the steel bars after being converted into two dimensions based on the steel bar information;
determining an adjustment angle by using the range of the rotation angle;
Determining a conversion matrix based on the starting point coordinates, the rotation angle and the adjustment angle to determine the association relation, wherein the conversion matrix comprises a first conversion matrix from three-dimensional to two-dimensional and a second conversion matrix from two-dimensional to three-dimensional;
and generating the steel bar layout diagram by using the conversion matrix.
2. The method of claim 1, wherein the bar information includes a start point coordinate and a bending length, and the determining the start point coordinate and the rotation angle after the three-dimensional line of each bar is converted into two dimensions based on the bar information includes:
deducting the bending length from the initial end to obtain a bent steel bar section;
based on the coordinates of the bent steel bar segments, obtaining starting point coordinates after the three-dimensional lines of the steel bars are converted into two dimensions;
and determining the rotation angle by utilizing the included angle between the projection of the bent steel bar section and the coordinate axis.
3. The method of claim 1, wherein the obtaining BIM model primitives comprises:
judging whether an arrangement range is selected or not;
and when the arrangement range is not selected, acquiring a primitive list of the current component type of the current layer to determine the BIM model primitive.
4. A method according to any one of claims 1-3, wherein the association comprises a two-to-three-dimensional second transformation matrix, and wherein the adjusting the rebar three-dimensional model based on the association and the modification comprises:
acquiring coordinates of each reinforcing steel bar line in the modified reinforcing steel bar layout;
based on the coordinates of each reinforcement wire and the two-dimensional to three-dimensional second transformation matrix, adjusting the reinforcement three-dimensional model;
and displaying the adjusted reinforcement bar layout.
5. The method of claim 4, wherein displaying the adjusted rebar layout includes:
acquiring graphic elements which are displayed in batches in the steel bar arrangement diagram;
and processing the primitives in batch display to perform batch display.
6. The method of claim 5, wherein when the batch displayed primitive is a column primitive, the processing the batch displayed primitive for batch display comprises:
classifying the column primitives by utilizing attribute information of each column primitive;
and for the column primitives in the same classification, when the three-dimensional lines of the steel bars of the column primitives are consistent with other data except for positioning points, merging and displaying the column primitives in the same classification, and recording merging sources.
7. The method of claim 5, wherein when the batch displayed primitive is a wall primitive, the processing the batch displayed primitive for batch display comprises:
acquiring an arrangement diagram of each wall primitive under at least one view angle;
and carrying out batch display based on the arrangement diagram under the at least one view angle.
8. The method of claim 4, wherein displaying the adjusted rebar layout includes:
obtaining the short-cut operation of the blanking length;
and sequentially arranging the information of the steel bar wires at the end positions of each steel bar wire in the steel bar arrangement diagram.
9. A rebar arranging device, comprising:
the acquisition module is used for acquiring the three-dimensional model of the steel bar;
the generation module is used for generating a steel bar arrangement diagram based on the steel bar three-dimensional model and determining the association relationship between the steel bar three-dimensional model and the steel bar arrangement diagram;
the modification module is used for acquiring modification of the steel bar arrangement diagram;
the adjusting module is used for adjusting the three-dimensional model of the steel bar based on the association relation and the modification;
the generating module is specifically configured to:
Acquiring a BIM model primitive;
converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional arrangement chart data based on the three-dimensional steel bar models so as to generate the steel bar arrangement chart and determine the association relation;
the step of converting the three-dimensional steel bar lines of the BIM model primitives into two-dimensional layout diagram data based on the three-dimensional steel bar models to generate the steel bar layout diagram and determine the association relation comprises the following steps:
determining the steel bar information of each steel bar three-dimensional line in the BIM model graphic element by utilizing the steel bar three-dimensional model;
determining starting point coordinates and rotation angles of the three-dimensional lines of the steel bars after being converted into two dimensions based on the steel bar information;
determining an adjustment angle by using the range of the rotation angle;
determining a conversion matrix based on the starting point coordinates, the rotation angle and the adjustment angle to determine the association relation, wherein the conversion matrix comprises a first conversion matrix from three-dimensional to two-dimensional and a second conversion matrix from two-dimensional to three-dimensional;
and generating the steel bar layout diagram by using the conversion matrix.
10. An electronic device, comprising:
the steel bar arranging method according to any one of claims 1 to 8, comprising a memory and a processor, wherein the memory and the processor are in communication connection, the memory stores computer instructions, and the processor executes the computer instructions, thereby executing the steel bar arranging method according to any one of claims 1 to 8.
11. A computer-readable storage medium storing computer instructions for causing a computer to perform the rebar arrangement method of any one of claims 1-8.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110638650.9A CN113420353B (en) | 2021-06-08 | 2021-06-08 | Method and device for arranging reinforcing steel bars and electronic equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110638650.9A CN113420353B (en) | 2021-06-08 | 2021-06-08 | Method and device for arranging reinforcing steel bars and electronic equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113420353A CN113420353A (en) | 2021-09-21 |
CN113420353B true CN113420353B (en) | 2024-01-09 |
Family
ID=77788019
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110638650.9A Active CN113420353B (en) | 2021-06-08 | 2021-06-08 | Method and device for arranging reinforcing steel bars and electronic equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113420353B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113821860B (en) * | 2021-09-30 | 2024-04-12 | 广联达科技股份有限公司 | Method, device, equipment and storage medium for determining break point on steel bar graphic element |
CN113919027B (en) * | 2021-10-12 | 2024-12-13 | 广联达科技股份有限公司 | Component adjustment method, device, computer equipment and storage medium in BIM model |
CN114048532B (en) * | 2021-11-10 | 2025-07-15 | 中交第二航务工程局有限公司 | Method for drawing the expansion diagram of steel mesh of bridge tower |
CN114386135A (en) * | 2021-11-22 | 2022-04-22 | 鲁班软件股份有限公司 | A method and system for arranging reinforcement for concrete slab construction |
CN114996823B (en) * | 2022-06-30 | 2025-03-14 | 广联达科技股份有限公司 | Steel bar sample drawing method, device, equipment and storage medium based on civil air defense door frame wall |
CN115182594B (en) * | 2022-07-21 | 2023-12-29 | 鲁班软件股份有限公司 | Longitudinal member cross-layer steel bar blanking method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0668212A (en) * | 1992-08-20 | 1994-03-11 | Haseko Corp | Automatic arrangement of reinforce designing system for building body |
CN104537191A (en) * | 2015-01-21 | 2015-04-22 | 中国电建集团华东勘测设计研究院有限公司 | Drawing method for three-dimensional rebar model schematic diagram |
KR101607886B1 (en) * | 2015-07-30 | 2016-04-11 | 단국대학교 산학협력단 | Automatic generation system of rebar shop drawing using 3D model |
CN106529039A (en) * | 2016-11-11 | 2017-03-22 | 中国电建集团成都勘测设计研究院有限公司 | Method for generating two-dimensional reinforcing steel bar type drawing from three-dimensional reinforcing steel bars |
CN107844677A (en) * | 2017-12-19 | 2018-03-27 | 中国电建集团成都勘测设计研究院有限公司 | Method for three-dimensional reinforcing bar editing and updating |
KR20190105365A (en) * | 2018-03-05 | 2019-09-17 | 주식회사 싸이픽소프트 | Method for automatic creating 3d design drawing from 2d design drawing and automatic creating device using the same |
CN111177831A (en) * | 2019-12-26 | 2020-05-19 | 沈阳工业大学 | A 3D modeling and automatic calculation method of steel bars based on BIM technology |
-
2021
- 2021-06-08 CN CN202110638650.9A patent/CN113420353B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0668212A (en) * | 1992-08-20 | 1994-03-11 | Haseko Corp | Automatic arrangement of reinforce designing system for building body |
CN104537191A (en) * | 2015-01-21 | 2015-04-22 | 中国电建集团华东勘测设计研究院有限公司 | Drawing method for three-dimensional rebar model schematic diagram |
KR101607886B1 (en) * | 2015-07-30 | 2016-04-11 | 단국대학교 산학협력단 | Automatic generation system of rebar shop drawing using 3D model |
CN106529039A (en) * | 2016-11-11 | 2017-03-22 | 中国电建集团成都勘测设计研究院有限公司 | Method for generating two-dimensional reinforcing steel bar type drawing from three-dimensional reinforcing steel bars |
CN107844677A (en) * | 2017-12-19 | 2018-03-27 | 中国电建集团成都勘测设计研究院有限公司 | Method for three-dimensional reinforcing bar editing and updating |
KR20190105365A (en) * | 2018-03-05 | 2019-09-17 | 주식회사 싸이픽소프트 | Method for automatic creating 3d design drawing from 2d design drawing and automatic creating device using the same |
CN111177831A (en) * | 2019-12-26 | 2020-05-19 | 沈阳工业大学 | A 3D modeling and automatic calculation method of steel bars based on BIM technology |
Also Published As
Publication number | Publication date |
---|---|
CN113420353A (en) | 2021-09-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113420353B (en) | Method and device for arranging reinforcing steel bars and electronic equipment | |
CN112734641A (en) | Training method and device of target detection model, computer equipment and medium | |
CN113190894B (en) | Method, device, terminal equipment and medium for processing steel bar sample-turning data | |
CN112685998B (en) | Automatic labeling method, device, equipment and readable storage medium | |
CN114565703B (en) | Method, device and equipment for adjusting centralized labeling and readable storage medium | |
WO2024109959A1 (en) | Three-dimensional automatic design method and apparatus for trays and bearers in gallery, and medium and device | |
JP2002163681A (en) | Image processor | |
CN111985014B (en) | Modeling method and system based on standard atlas | |
CN113821860A (en) | Method, device and equipment for determining breakpoint on steel bar primitive and storage medium | |
US8149239B2 (en) | Image processing apparatus, image processing method, and storage medium storing a program for causing an image processing apparatus to execute an image processing method | |
CN115859412A (en) | BIM-based curtain wall rapid generation method, device and equipment | |
CN114444185B (en) | In-situ marking recognition method, device and electronic equipment | |
CN111062924A (en) | Image processing method, device, terminal and storage medium | |
CN114491720B (en) | Method and device for generating detailed steel structure diagram, electronic equipment and storage medium | |
CN116681792A (en) | Subgraph generation method, device and equipment of vector drawing and readable storage medium | |
CN113297645B (en) | Jewelry form generation method, system, terminal equipment and storage medium | |
CN116630555A (en) | Terrain height map generation method and device and electronic equipment | |
CN115830269A (en) | Tunnel point cloud normal direction adjusting method, device and equipment and readable access medium | |
CN113688454B (en) | Modeling method and device for protective housing, electronic equipment and readable storage medium | |
CN114329296B (en) | A page grid adjustment method, device, computer equipment and storage medium | |
CN111142707B (en) | A kind of ultra-large LED screen touch control method | |
EP4521335A1 (en) | Method and apparatus for image stitching | |
CN113220375A (en) | Method and system for generating hollow text silk screen based on Allegro software | |
CN120104509A (en) | CAD-oriented interactive and parametric modeling automatic testing method and system | |
CN119301641A (en) | Image processing device, image processing method, and program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |