[go: up one dir, main page]

CN113215995B - Method for constructing bridge road in narrow space - Google Patents

Method for constructing bridge road in narrow space Download PDF

Info

Publication number
CN113215995B
CN113215995B CN202110511873.9A CN202110511873A CN113215995B CN 113215995 B CN113215995 B CN 113215995B CN 202110511873 A CN202110511873 A CN 202110511873A CN 113215995 B CN113215995 B CN 113215995B
Authority
CN
China
Prior art keywords
retaining wall
bridge
slope
constructing
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110511873.9A
Other languages
Chinese (zh)
Other versions
CN113215995A (en
Inventor
曹建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Original Assignee
Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Engineering Design & Research Institute Co Ltd filed Critical Guangzhou Municipal Engineering Design & Research Institute Co Ltd
Priority to CN202110511873.9A priority Critical patent/CN113215995B/en
Publication of CN113215995A publication Critical patent/CN113215995A/en
Application granted granted Critical
Publication of CN113215995B publication Critical patent/CN113215995B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Road Paving Structures (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种在狭窄空间施工桥梁道路的方法,包括以下步骤:开挖现状挡土墙墙背的山体,开挖后的山体包括上面、底面和坡面,上面开挖至路基顶面标高,底面开挖至现状挡土墙的基础标高,上面和底面之间通过坡面过渡;拆除现状挡土墙;在现状挡土墙的原址施工新建挡土墙,在底面施工靠近新建挡土墙的第一排桥梁桩基;第一次回填土至新建挡土墙的墙顶标高;在回填的土层和坡面形成的基础上,施工第二排桥梁桩基、承台、桥墩和桥梁上部结构;第二次回填土至路基顶面标高,在回填的土层和上面顶部实施路面结构。本方案开辟了一种新的思路,既能保证施工期间山体的安全,又为墙顶路基提供了安全的路基和支挡结构。

Figure 202110511873

The invention discloses a method for constructing a bridge road in a narrow space, which comprises the following steps: excavating a mountain body at the back of the existing retaining wall; the excavated mountain body includes an upper surface, a bottom surface and a slope surface; Elevation, the bottom surface is excavated to the foundation level of the existing retaining wall, and the transition between the top and the bottom surface is through the slope; the existing retaining wall is removed; the new retaining wall is constructed on the original site of the existing retaining wall, and the bottom surface is constructed close to the new retaining wall The first row of bridge pile foundations of the wall; the first backfill to the top elevation of the new retaining wall; on the basis of the backfilled soil layer and slope, the second row of bridge pile foundations, caps, piers and Bridge superstructure; the second time backfill soil to the elevation of the top surface of the subgrade, and implement the pavement structure on the backfilled soil layer and the top of the upper surface. This scheme opens up a new idea, which can not only ensure the safety of the mountain during construction, but also provide a safe subgrade and support structure for the subgrade on the top of the wall.

Figure 202110511873

Description

一种在狭窄空间施工桥梁道路的方法A method of constructing bridge roads in narrow spaces

技术领域technical field

本发明用于城市道路施工领域,特别是涉及一种在狭窄空间施工桥梁道路的方法。The invention is used in the field of urban road construction, and particularly relates to a method for constructing bridge roads in narrow spaces.

背景技术Background technique

挡土墙是城市道路工程建设中常见的结构物,其作用是保证城市道路在使用过程中的安全。就挡土墙的位置而言,一般可分为路肩墙和路堑墙。按照实施的次序,首先处理路床以下的软基,当路基的强度和工后沉降满足要求之后,再实施挡土墙,最后实施路面结构,挡土墙为路面结构提供安全保障。挡土墙和路面结构对路基的强度和工后沉降,均有相应的要求。城市道路中常见的挡土墙形式主要有重力式、悬臂式、扶壁式等,重力式挡土墙高度可以达到12m,但是墙身材料数量较大,承载力要求高;悬臂式挡土墙墙高一般不超过5m,比较轻薄,但是基础宽度较大,地基承载力要求相对较低;扶壁式挡土墙墙高不超过15m,材料较省,但是基础宽度较大,地基承载力要求相对较低。Retaining wall is a common structure in urban road engineering construction, and its function is to ensure the safety of urban roads during use. As far as the location of the retaining wall is concerned, it can generally be divided into shoulder wall and cutting wall. According to the order of implementation, first deal with the soft foundation below the roadbed, when the strength of the roadbed and post-construction settlement meet the requirements, then implement the retaining wall, and finally implement the pavement structure. The retaining wall provides security for the pavement structure. Retaining walls and pavement structures have corresponding requirements for the strength of the subgrade and post-construction settlement. The common retaining wall forms in urban roads mainly include gravity type, cantilever type, buttress type, etc. The height of gravity type retaining wall can reach 12m, but the number of wall materials is large, and the bearing capacity requirements are high; cantilever type retaining wall The wall height is generally not more than 5m, which is relatively thin, but the width of the foundation is large, and the bearing capacity of the foundation is relatively low; the height of the buttress retaining wall is not more than 15m, and the material is less, but the width of the foundation is large, and the bearing capacity of the foundation is required. relatively low.

挡土墙的实施方式一般是现场搭支架做模板,要求宽敞的场地,特别是基础较大的挡土墙形式。城市道路常见的几种挡土墙形式,在应用过程中,积累了丰富的经验,技术成熟,但是也暴露出了各自的问题。重力式挡土墙石材用量大,当前环保理念越来越被人们所重视,节省石料是一个发展方向;悬臂式和扶壁式挡土墙基础较大,需要较大的施工用地,对现状交通的影响较大,用地较多。The implementation of the retaining wall is generally a formwork with brackets on site, which requires a spacious site, especially in the form of a retaining wall with a large foundation. Several common retaining wall forms on urban roads have accumulated rich experience and mature technology in the application process, but also exposed their own problems. Gravity retaining walls use a large amount of stone, and people pay more and more attention to the current environmental protection concept. Stone saving is a development direction; The impact is greater and the land is used more.

参见图1,位于山体坡脚的挡土墙,一侧为山体,另一侧为建筑物,类似于城市道路中的路堑挡土墙,城市道路工程的线位经过挡土墙上方的山体。为避免占用建筑物,城市道路线位与挡土墙平行,路基宽度延伸至山体边坡上方,此时形成了半填半挖路基,靠近山体一侧需开挖山体,边坡上方需要填土,形成路基平面。在用地不增加、不用拆迁建筑物的前提下,此时的挡土墙高度高于现状挡土墙,且挡土墙的形式由路堑挡土墙变化为路堤挡土墙。这为在狭小空间内的挡土墙重建以及城市道路施工提出了难题。Referring to Figure 1, the retaining wall at the foot of the mountain slope has a mountain on one side and a building on the other, similar to a cutting retaining wall in an urban road. The line position of the urban road project passes through the mountain above the retaining wall. In order to avoid occupying buildings, the line of the urban road is parallel to the retaining wall, and the width of the roadbed extends to the top of the mountain slope. At this time, a half filled and half excavated roadbed is formed. , forming a subgrade plane. On the premise that the land use is not increased and the buildings are not demolished, the height of the retaining wall at this time is higher than the existing retaining wall, and the form of the retaining wall is changed from a cutting retaining wall to an embankment retaining wall. This poses a challenge for the reconstruction of retaining walls in small spaces and for urban road construction.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于至少解决现有技术中存在的技术问题之一,提供一种在狭窄空间施工桥梁道路的方法。The purpose of the present invention is to solve at least one of the technical problems existing in the prior art, and to provide a method for constructing a bridge road in a narrow space.

本发明解决其技术问题所采用的技术方案是:The technical scheme adopted by the present invention to solve its technical problems is:

一种在狭窄空间施工桥梁道路的方法,包括以下步骤:A method of constructing a bridge road in a narrow space, comprising the following steps:

开挖现状挡土墙墙背的山体,开挖后的山体包括上面、底面和坡面,所述上面开挖至路基顶面标高,所述底面开挖至所述现状挡土墙的基础标高,所述上面和底面之间通过所述坡面过渡;Excavate the mountain behind the existing retaining wall. The excavated mountain includes the upper surface, the bottom surface and the slope surface. The upper surface is excavated to the elevation of the top surface of the roadbed, and the bottom surface is excavated to the foundation elevation of the existing retaining wall. , the transition between the upper surface and the bottom surface is through the slope surface;

拆除所述现状挡土墙;remove said existing retaining wall;

在所述现状挡土墙的原址施工新建挡土墙,在所述底面施工靠近所述新建挡土墙的第一排桥梁桩基;Construct a new retaining wall at the original site of the existing retaining wall, and construct the first row of bridge pile foundations close to the new retaining wall on the bottom surface;

第一次回填土至所述新建挡土墙的墙顶标高;Backfill soil for the first time to the top elevation of the new retaining wall;

在回填的土层和所述坡面形成的基础上,施工第二排桥梁桩基、承台、桥墩和桥梁上部结构;On the foundation formed by the backfilled soil layer and the slope surface, construct the second row of bridge pile foundations, caps, bridge piers and bridge superstructure;

第二次回填土至路基顶面标高,在回填的土层和所述上面顶部实施路面结构。Backfill the soil to the top level of the subgrade for the second time, and implement the pavement structure on the backfilled soil layer and the top of the upper surface.

在一些实施例中,在开挖山体形成的所述坡面上开挖台阶,并在所述坡面喷射混凝土。In some embodiments, steps are excavated on the slope formed by excavating the mountain, and concrete is sprayed on the slope.

在一些实施例中,所述新建挡土墙包括多个抗滑桩,所述抗滑桩沿所述新建挡土墙的延伸方向间隔分布,相邻的所述抗滑桩之间设有预制挡土板,所述抗滑桩侧面设有插槽,多个所述预制挡土板沿高度方向拼装在所述插槽中。In some embodiments, the newly constructed retaining wall includes a plurality of anti-sliding piles, the anti-sliding piles are distributed at intervals along the extending direction of the newly constructed retaining wall, and prefabricated anti-sliding piles are arranged between adjacent anti-sliding piles. A soil retaining plate, the side of the anti-sliding pile is provided with a slot, and a plurality of the prefabricated soil retaining plates are assembled in the slot along the height direction.

在一些实施例中,所述预制挡土板分布多个沿上下布置的泄水孔,所述泄水孔在所述新建挡土墙的外侧通过竖向排水管接入排水沟,所述泄水孔在所述新建挡土墙的背侧设有反滤层。In some embodiments, the prefabricated retaining plate is distributed with a plurality of scuppers arranged up and down, the scuppers are connected to a drainage ditch through a vertical drainage pipe on the outer side of the newly built retaining wall, and the scupper is connected to a drainage ditch. The water hole is provided with a reverse filter layer on the back side of the newly built retaining wall.

在一些实施例中,第一次回填土采用气泡轻质土。In some embodiments, bubble light soil is used for the first backfill.

在一些实施例中,在第二次回填土前铺设道路管线。In some embodiments, the road line is laid before the second backfill.

在一些实施例中,第二次回填土采用气泡轻质土。In some embodiments, the second backfill is air-bubble lightweight soil.

在一些实施例中,第二次回填土在路基外侧设置过渡至所述新建挡土墙墙顶的稳定边坡。In some embodiments, the second backfill is provided with a stable slope on the outside of the roadbed that transitions to the top of the newly built retaining wall.

在一些实施例中,所述稳定边坡设置台阶,并覆盖包边土,包边土种植植被。In some embodiments, the stable side slope is provided with steps and covered with edging soil, and the edging soil is planted with vegetation.

上述技术方案中的一个技术方案至少具有如下优点或有益效果之一:挡土墙距离建筑物较近,无施工空间,需要在山体一侧寻找施工空间。同时山体一侧距离待建桥梁桩基较近,无法实现在不拆除现状挡土墙的前提下,在现状挡土墙靠山体一侧实施挡土墙。本方案提供了解决这种特定情况的成套措施,在现状挡墙靠近山体一侧开辟施工空间,同时保证山体边坡的稳定性,为挡土墙的拆除重建和桥梁施工提供空间。本方案为狭小空间内的挡土墙重建、桥梁道路的设计和施工,开辟了一种新的思路,既能保证施工期间山体的安全,又为墙顶路基提供了安全的路基和支挡结构。One of the above technical solutions has at least one of the following advantages or beneficial effects: the retaining wall is relatively close to the building, there is no construction space, and a construction space needs to be found on the side of the mountain. At the same time, the side of the mountain is relatively close to the pile foundation of the bridge to be built, so it is impossible to implement the retaining wall on the side of the current retaining wall on the side of the mountain without removing the existing retaining wall. This scheme provides a complete set of measures to solve this specific situation, opening up construction space on the side of the existing retaining wall close to the mountain, while ensuring the stability of the mountain slope, providing space for the demolition and reconstruction of the retaining wall and bridge construction. This scheme opens up a new idea for the reconstruction of retaining walls in a narrow space, the design and construction of bridges and roads, which can not only ensure the safety of the mountain during construction, but also provide a safe roadbed and supporting structure for the roadbed at the top of the wall. .

本发明的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the present invention will be set forth, in part, from the following description, and in part will be apparent from the following description, or may be learned by practice of the invention.

附图说明Description of drawings

本发明的上述和/或附加的方面和优点从结合下面附图对实施例的描述中将变得明显和容易理解,其中:The above and/or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of embodiments taken in conjunction with the accompanying drawings, wherein:

图1是本发明一个实施例初始状态示意图;1 is a schematic diagram of an initial state of an embodiment of the present invention;

图2是图1所示的一个实施例开挖山体示意图;Fig. 2 is a schematic diagram of excavating mountain body according to an embodiment shown in Fig. 1;

图3是图1所示的一个实施例拆除现状挡土墙示意图;Figure 3 is a schematic diagram of the current retaining wall dismantled according to an embodiment shown in Figure 1;

图4是图1所示的一个实施例施工新建挡土墙和第一排桥梁桩基示意图;Figure 4 is a schematic diagram of the construction of a new retaining wall and a first row of bridge pile foundations according to an embodiment shown in Figure 1;

图5是图1所示的一个实施例第一次回填土至新建挡土墙的墙顶标高示意图;5 is a schematic diagram of the top elevation of the first backfill to the newly built retaining wall according to an embodiment shown in FIG. 1;

图6是图1所示的一个实施例施工第二排桥梁桩基、承台、桥墩和桥梁上部示意图;Fig. 6 is a schematic diagram of the construction of the second row of bridge pile foundations, caps, piers and the upper part of the bridge according to an embodiment shown in Fig. 1;

图7是图1所示的一个实施例第二次回填土至路基顶面标高示意图;7 is a schematic diagram of the second backfill to the elevation of the top surface of the roadbed according to an embodiment shown in FIG. 1;

图8是图1所示的一个实施例实施路面结构示意图;FIG. 8 is a schematic diagram of a road surface structure according to an embodiment shown in FIG. 1;

图9是图1所示的一个实施例新建挡土墙结构平面图;FIG. 9 is a plan view of a newly constructed retaining wall structure according to an embodiment shown in FIG. 1;

图10是图1所示的一个实施例新建挡土墙结构俯视图。FIG. 10 is a top view of a newly constructed retaining wall structure according to an embodiment shown in FIG. 1 .

具体实施方式Detailed ways

本部分将详细描述本发明的具体实施例,本发明之较佳实施例在附图中示出,附图的作用在于用图形补充说明书文字部分的描述,使人能够直观地、形象地理解本发明的每个技术特征和整体技术方案,但其不能理解为对本发明保护范围的限制。This part will describe the specific embodiments of the present invention in detail. The preferred embodiments of the present invention are shown in the accompanying drawings. The function of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand the present invention. Each technical feature and overall technical solution of the invention should not be construed as limiting the protection scope of the invention.

本发明中,如果有描述到方向(上、下、左、右、前及后)时,其仅是为了便于描述本发明的技术方案,而不是指示或暗示所指的技术特征必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the present invention, if there is a description of a direction (up, down, left, right, front and rear), it is only for the convenience of describing the technical solution of the present invention, rather than indicating or implying that the technical features referred to must have specific characteristics Orientation, construction and operation in a particular orientation, and therefore should not be construed as limiting the invention.

本发明中,“若干”的含义是一个或者多个,“多个”的含义是两个以上,“大于”“小于”“超过”等理解为不包括本数;“以上”“以下”“以内”等理解为包括本数。在本发明的描述中,如果有描述到“第一”“第二”仅用于区分技术特征为目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量或者隐含指明所指示的技术特征的先后关系。In the present invention, "several" means one or more, "multiple" means two or more, "greater than", "less than", "exceeding", etc. are understood as not including this number; "above", "below" and "within" " etc. are understood to include the original number. In the description of the present invention, if it is described that "first" and "second" are only used for the purpose of distinguishing technical features, it should not be understood as indicating or implying relative importance or implying the number of indicated technical features or Implicitly indicates the order of the indicated technical features.

本发明中,除非另有明确的限定,“设置”“安装”“连接”等词语应做广义理解,例如,可以是直接相连,也可以通过中间媒介间接相连;可以是固定连接,也可以是可拆卸连接,还可以是一体成型;可以是机械连接,也可以是电连接或能够互相通讯;可以是两个元件内部的连通或两个元件的相互作用关系。所属技术领域技术人员可以结合技术方案的具体内容合理确定上述词语在本发明中的具体含义。In the present invention, unless otherwise expressly defined, words such as "setting", "installing" and "connecting" should be understood in a broad sense, for example, it may be directly connected or indirectly connected through an intermediate medium; it may be a fixed connection or a The detachable connection can also be integrally formed; it can be a mechanical connection or an electrical connection or can communicate with each other; it can be the internal communication between the two elements or the interaction relationship between the two elements. Those skilled in the art can reasonably determine the specific meanings of the above words in the present invention in combination with the specific content of the technical solutions.

参见图1,现状挡土墙1高度约为6m,距离现状建筑物距离约为2m,距离待建桥梁的桩基约为2m,新建挡土墙2高度为10m,其位置与现状挡土墙1重合。现状挡土墙1距离建筑物3较近,没有施工空间;其与待建桥梁桩基之间的距离较近,没有实施其他形式挡土墙的空间。Referring to Figure 1, the height of the existing retaining wall 1 is about 6m, the distance from the existing building is about 2m, and the distance from the pile foundation of the bridge to be built is about 2m. 1 coincides. The existing retaining wall 1 is relatively close to the building 3, and there is no construction space; the distance between it and the pile foundation of the bridge to be built is relatively short, and there is no space for implementing other forms of retaining walls.

鉴于此,本发明的实施例提供了一种在狭窄空间施工桥梁道路的方法,施工完成后的桥梁道路如图8所示,包括位于挡土墙外侧并与挡土墙平行的桥梁和位于桥梁靠近山体侧的路面。具体的,在狭窄空间施工桥梁道路的方法包括以下步骤:In view of this, an embodiment of the present invention provides a method for constructing a bridge road in a narrow space. The bridge road after construction is shown in FIG. 8 , including a bridge located outside the retaining wall and parallel to the retaining wall and a bridge located in the bridge Road near the side of the mountain. Specifically, the method for constructing a bridge road in a narrow space includes the following steps:

参见图2,为保证山体边坡的稳定性,且保证挡土墙和桥梁桩基的施工空间,开挖现状挡土墙1墙背的山体4,开挖后的山体4包括上面5、底面6和坡面7,上面5开挖至路基顶面标高,底面6开挖至现状挡土墙1的基础标高,上面5和底面6之间通过坡面7过渡,具体在一些实施例中,坡面7的坡度,石质坡面7不大于1:1,土质坡面7不大于1:1.5。Referring to Figure 2, in order to ensure the stability of the mountain slope and the construction space of the retaining wall and the bridge pile foundation, the existing retaining wall 1 and the mountain 4 behind the wall are excavated. The excavated mountain 4 includes the upper surface 5 and the bottom surface. 6 and the slope 7, the upper surface 5 is excavated to the elevation of the top surface of the roadbed, the bottom surface 6 is excavated to the foundation elevation of the existing retaining wall 1, and the slope 7 transitions between the upper surface 5 and the bottom surface 6, specifically in some embodiments, The slope of the slope 7, the stone slope 7 is not more than 1:1, and the soil slope 7 is not more than 1:1.5.

参见图3,拆除现状挡土墙1,拆除之前需掌握建筑物3的基础形式、宽度和深度,挡土墙的基础底面6不应超过建筑物3基础底标高,避免拆除挡土墙对现状建筑物3的影响。Referring to Figure 3, the existing retaining wall 1 should be demolished. Before demolishing, the foundation form, width and depth of the building 3 should be mastered. The foundation bottom surface 6 of the retaining wall should not exceed the foundation bottom elevation of the building 3. Impact of Building 3.

参见图4,在现状挡土墙1的原址施工新建挡土墙2,新建挡土墙2完工后,在底面6施工靠近新建挡土墙2的第一排桥梁桩基8。Referring to FIG. 4 , a new retaining wall 2 is constructed on the original site of the existing retaining wall 1 . After the new retaining wall 2 is completed, the first row of bridge pile foundations 8 close to the new retaining wall 2 are constructed on the bottom surface 6 .

参见图5,第一次回填土9至新建挡土墙2的墙顶标高。Referring to Figure 5, backfill soil 9 for the first time to the top elevation of the new retaining wall 2.

参见图6,在回填的土层和坡面7形成的基础上,施工第二排桥梁桩基、承台、桥墩和桥梁上部结构。Referring to Fig. 6, on the foundation formed by the backfilled soil layer and the slope 7, the second row of bridge pile foundations, caps, bridge piers and bridge superstructure are constructed.

参见图7、图8,第二次回填土10至路基顶面标高,在回填的土层和上面5顶部实施路面结构11。Referring to Figures 7 and 8, backfill soil 10 to the elevation of the top surface of the roadbed for the second time, and implement pavement structure 11 on top of the backfilled soil layer and the top surface 5.

挡土墙距离建筑物3较近,无施工空间,需要在山体4一侧寻找施工空间。同时山体4一侧距离待建桥梁桩基较近,无法实现在不拆除现状挡土墙1的前提下,在现状挡土墙1靠山体4一侧实施挡土墙。本方案提供了解决这种特定情况的成套措施,在现状挡墙靠近山体4一侧开辟施工空间,同时保证山体4边坡的稳定性,为挡土墙的拆除重建和桥梁施工提供空间。本方案为狭小空间内的挡土墙重建、桥梁道路的设计和施工,开辟了一种新的思路,既能保证施工期间山体4的安全,又为墙顶路基提供了安全的路基和支挡结构。The retaining wall is relatively close to the building 3, and there is no construction space. It is necessary to find a construction space on the side of the mountain 4. At the same time, the side of the mountain 4 is relatively close to the pile foundation of the bridge to be built, and it is impossible to implement a retaining wall on the side of the existing retaining wall 1 close to the mountain 4 without removing the existing retaining wall 1 . This scheme provides a complete set of measures to solve this specific situation, opening up construction space on the side of the existing retaining wall close to the mountain 4, while ensuring the stability of the slope of the mountain 4, providing space for the demolition and reconstruction of the retaining wall and bridge construction. This scheme opens up a new way of thinking for the reconstruction of retaining walls and the design and construction of bridges and roads in a narrow space, which can not only ensure the safety of the mountain 4 during construction, but also provide a safe roadbed and support for the roadbed at the top of the wall. structure.

在一些实施例中,参见图2、图3,在开挖山体4形成的坡面7上开挖台阶,台阶的高度与宽度可以根据需要设置,例如均为50cm,台阶用于保证回填材料与山体4边坡更好地咬合形成稳定的基础。在坡面7喷射混凝土,做好施工期间的防水措施,保证边坡的稳定性。In some embodiments, referring to FIGS. 2 and 3 , steps are excavated on the slope 7 formed by the excavation of the mountain body 4 . The height and width of the steps can be set as required, for example, both are 50 cm. The slopes of mountain 4 are better occluded to form a stable foundation. Spray concrete on the slope 7, and take waterproof measures during construction to ensure the stability of the slope.

在一些实施例中,参见图9、图10,新建挡土墙2包括多个抗滑桩12,抗滑桩12沿新建挡土墙2的延伸方向间隔分布,抗滑桩12即起到支挡山体4和路基的稳定作用,又可作为挡土板两侧的支撑。相邻的抗滑桩12之间设有预制挡土板13,抗滑桩12侧面设有插槽,多个预制挡土板13沿高度方向拼装在插槽中。为了节约工期,减少石材用量,挡土板在工厂预制,现场进行拼装。本实施例通过采用桩板式挡土墙结构,挡土板为工厂预制现场安装,减少了现场支架,节约了工期。In some embodiments, referring to FIGS. 9 and 10 , the newly built retaining wall 2 includes a plurality of anti-sliding piles 12 , and the anti-sliding piles 12 are distributed at intervals along the extending direction of the newly built retaining wall 2 , and the anti-sliding piles 12 serve to support The stabilizing effect of the retaining body 4 and the roadbed can also be used as the support on both sides of the retaining plate. A prefabricated earth retaining plate 13 is arranged between adjacent anti-sliding piles 12 , a slot is provided on the side of the anti-sliding pile 12 , and a plurality of prefabricated earth retaining plates 13 are assembled in the slot along the height direction. In order to save the construction period and reduce the amount of stone, the retaining plate is prefabricated in the factory and assembled on site. In this embodiment, the pile plate type retaining wall structure is adopted, and the retaining plate is prefabricated and installed in the factory, which reduces the on-site support and saves the construction period.

进一步的,预制挡土板13分布多个沿上下布置的泄水孔14,泄水孔14在新建挡土墙2的外侧通过竖向排水管15接入带有盖板的排水沟16,泄水孔14在新建挡土墙2的背侧设有反滤层17。用排水管连接泄水孔14,将排水管接入排水沟16,改善了泄水孔14流水污染墙体的问题,有利于形成好的景观。Further, the prefabricated retaining plate 13 is distributed with a plurality of drainage holes 14 arranged up and down. The drainage holes 14 are connected to the drainage ditch 16 with a cover plate on the outside of the newly built retaining wall 2 through the vertical drainage pipe 15, and the drainage holes 14 The water hole 14 is provided with a reverse filter layer 17 on the back side of the newly built retaining wall 2 . The drain hole 14 is connected with a drain pipe, and the drain pipe is connected to the drain ditch 16, which improves the problem that the water from the drain hole 14 pollutes the wall, and is conducive to the formation of a good landscape.

在一些实施例中,第一次回填土9采用气泡轻质土,挡土墙的挡土板可以作为气泡轻质土的外墙,由于气泡轻质土形成强度之后,可垂直直立,临空面的侧向压力接近于0,相比于回填普通土是更有利的,减小了侧向压力。该处实施了桥梁桩基,且一侧位于边坡,用气泡轻质土,解决了普通土难以压实的问题。In some embodiments, the first backfill 9 is made of air-bubble light soil, and the retaining plate of the retaining wall can be used as the outer wall of the air-bubble light-weight soil. After the air-bubble light-weight soil has formed its strength, it can stand vertically and stand in the air. The lateral pressure of the face is close to 0, which is more favorable than backfilling with ordinary soil, reducing the lateral pressure. The bridge pile foundation is implemented here, and one side is located on the slope, and the bubble light soil is used to solve the problem that ordinary soil is difficult to compact.

在一些实施例中,在第二次回填土10前铺设道路管线。In some embodiments, road lines are laid before the second backfill 10 .

进一步的,第二次回填土10采用气泡轻质土,城市道路管线较多,采用气泡轻质土,解决了普通土路基难以压实的问题。Further, the second backfill 10 adopts bubble light soil, and there are many urban road pipelines, so bubble light soil is adopted, which solves the problem that the ordinary soil roadbed is difficult to compact.

在一些实施例中,参见图7,第二次回填土10在路基外侧设置过渡至新建挡土墙2墙顶的稳定边坡。In some embodiments, referring to FIG. 7 , the second backfill 10 is provided with a stable slope transitioning to the top of the newly built retaining wall 2 on the outside of the roadbed.

进一步的,稳定边坡设置台阶,并覆盖包边土,包边土种植植被。在气泡轻质土靠近稳定边坡处设置防撞护栏。Further, the stable slope is set with steps and covered with edging soil, and the edging soil is planted with vegetation. Set up anti-collision guardrails near the stable slope of the bubble light soil.

本发明实施例技术方案的创新点主要有三点,第一点是对于两侧分别受到建筑物3和桥梁桩基限制,位于山体4坡脚的路堑挡土墙改建为路堤挡土墙,提出了切实可行的方案。将挡土墙和边坡的实施顺序由常规的由下至上改为由上至下,既保证了各个工程内容井然有序的开展,又保证了施工过程中山体4的安全性。第二点是该方案的回填材料采用气泡轻质土代替普通路基土,解决了桩基较多、存在各种地下管线、斜坡等条件下压实困难的问题。气泡轻质土强度大于普通土,且具有形成强度后可直立的特点,减小了边坡对挡土墙的侧向压力,是有利的。第三点是采用桩板式挡土墙结构,挡土板为工厂预制现场安装,减少了现场支架,节约了工期。用排水管连接泄水孔14,将排水管接入排水沟16,改善了泄水孔14流水污染墙体的问题,有利于形成好的景观。The innovation points of the technical solutions of the embodiments of the present invention mainly include three points. The first point is that the cutting retaining wall located at the foot of the slope of the mountain body 4, which is restricted by the building 3 and the bridge pile foundation on both sides respectively, is converted into an embankment retaining wall. practical solutions. The order of implementation of retaining walls and side slopes is changed from the conventional bottom-to-top to top-to-bottom, which not only ensures the orderly development of each project, but also ensures the safety of the mountain 4 during the construction process. The second point is that the backfill material of this scheme uses bubble light soil instead of ordinary subgrade soil, which solves the problem of difficult compaction under the conditions of many piles and various underground pipelines and slopes. The strength of the bubble light soil is higher than that of the ordinary soil, and it can stand upright after the strength is formed, which is beneficial to reduce the lateral pressure of the slope on the retaining wall. The third point is the use of pile-plate retaining wall structure. The retaining plate is prefabricated and installed in the factory, which reduces the on-site support and saves the construction period. The drain hole 14 is connected with a drain pipe, and the drain pipe is connected to the drain ditch 16, which improves the problem that the water from the drain hole 14 pollutes the wall, and is conducive to the formation of a good landscape.

在本说明书的描述中,参考术语“示例”、“实施例”或“一些实施例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of this specification, description with reference to the terms "example", "embodiment" or "some embodiments" etc. means that a particular feature, structure, material or characteristic described in connection with the embodiment or example is included in at least one aspect of the present invention in one embodiment or example. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

当然,本发明创造并不局限于上述实施方式,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出等同变形或替换,这些等同的变形或替换均包含在本申请权利要求所限定的范围内。Of course, the present invention is not limited to the above-mentioned embodiments, and those skilled in the art can make equivalent modifications or replacements without departing from the spirit of the present invention, and these equivalent modifications or replacements are included in the claims of the present application. within a limited range.

Claims (9)

1.一种在狭窄空间施工桥梁道路的方法,其特征在于,包括以下步骤:1. a method for constructing bridge roads in narrow space, is characterized in that, comprises the following steps: 开挖现状挡土墙墙背的山体,开挖后的山体包括上面、底面和坡面,所述上面开挖至路基顶面标高,所述底面开挖至所述现状挡土墙的基础标高,所述上面和底面之间通过所述坡面过渡;Excavate the mountain behind the existing retaining wall. The excavated mountain includes the upper surface, the bottom surface and the slope surface. The upper surface is excavated to the elevation of the top surface of the roadbed, and the bottom surface is excavated to the foundation elevation of the existing retaining wall. , the transition between the upper surface and the bottom surface is through the slope surface; 拆除所述现状挡土墙;remove said existing retaining wall; 在所述现状挡土墙的原址施工新建挡土墙,在所述底面施工靠近所述新建挡土墙的第一排桥梁桩基;Construct a new retaining wall at the original site of the existing retaining wall, and construct the first row of bridge pile foundations close to the new retaining wall on the bottom surface; 第一次回填土至所述新建挡土墙的墙顶标高;Backfill soil for the first time to the top elevation of the new retaining wall; 在回填的土层和所述坡面形成的基础上,施工第二排桥梁桩基、承台、桥墩和桥梁上部结构;On the foundation formed by the backfilled soil layer and the slope surface, construct the second row of bridge pile foundations, caps, bridge piers and bridge superstructure; 第二次回填土至路基顶面标高,在回填的土层和所述上面顶部实施路面结构。Backfill the soil to the top level of the subgrade for the second time, and implement the pavement structure on the backfilled soil layer and the top of the upper surface. 2.根据权利要求1所述的在狭窄空间施工桥梁道路的方法,其特征在于,在开挖山体形成的所述坡面上开挖台阶,并在所述坡面喷射混凝土。2 . The method for constructing a bridge road in a narrow space according to claim 1 , wherein steps are excavated on the slope formed by excavating a mountain, and concrete is sprayed on the slope. 3 . 3.根据权利要求1所述的在狭窄空间施工桥梁道路的方法,其特征在于,所述新建挡土墙包括多个抗滑桩,所述抗滑桩沿所述新建挡土墙的延伸方向间隔分布,相邻的所述抗滑桩之间设有预制挡土板,所述抗滑桩侧面设有插槽,多个所述预制挡土板沿高度方向拼装在所述插槽中。3 . The method for constructing a bridge road in a narrow space according to claim 1 , wherein the newly constructed retaining wall comprises a plurality of anti-sliding piles, and the anti-sliding piles are along the extension direction of the newly constructed retaining wall. 4 . Spaced distribution, prefabricated earth retaining plates are arranged between the adjacent anti-sliding piles, slots are arranged on the sides of the anti-sliding piles, and a plurality of the prefabricated earth retaining plates are assembled in the slots along the height direction. 4.根据权利要求3所述的在狭窄空间施工桥梁道路的方法,其特征在于,所述预制挡土板分布多个沿上下布置的泄水孔,所述泄水孔在所述新建挡土墙的外侧通过竖向排水管接入排水沟,所述泄水孔在所述新建挡土墙的背侧设有反滤层。4 . The method for constructing a bridge road in a narrow space according to claim 3 , wherein the prefabricated earth retaining plate is distributed with a plurality of drainage holes arranged up and down, and the drainage holes are located in the newly built earth retaining plate. 5 . The outer side of the wall is connected to a drainage ditch through a vertical drainage pipe, and the drainage hole is provided with a reverse filter layer on the back side of the newly built retaining wall. 5.根据权利要求1所述的在狭窄空间施工桥梁道路的方法,其特征在于,第一次回填土采用气泡轻质土。5 . The method for constructing bridge roads in narrow spaces according to claim 1 , wherein the first backfill is made of air-bubble light soil. 6 . 6.根据权利要求1所述的在狭窄空间施工桥梁道路的方法,其特征在于,在第二次回填土前铺设道路管线。6 . The method for constructing bridge roads in narrow spaces according to claim 1 , wherein road pipelines are laid before the second backfilling. 7 . 7.根据权利要求6所述的在狭窄空间施工桥梁道路的方法,其特征在于,第二次回填土采用气泡轻质土。7 . The method for constructing bridge roads in a narrow space according to claim 6 , wherein the second backfill is made of air-bubble light soil. 8 . 8.根据权利要求1所述的在狭窄空间施工桥梁道路的方法,其特征在于,第二次回填土在路基外侧设置过渡至所述新建挡土墙墙顶的稳定边坡。8 . The method for constructing a bridge road in a narrow space according to claim 1 , wherein the second backfill is provided with a stable slope on the outside of the roadbed that transitions to the top of the newly built retaining wall. 9 . 9.根据权利要求8所述的在狭窄空间施工桥梁道路的方法,其特征在于,所述稳定边坡设置台阶,并覆盖包边土,包边土种植植被。9 . The method for constructing a bridge road in a narrow space according to claim 8 , wherein steps are arranged on the stable side slope, and the edging soil is covered, and the edging soil is planted with vegetation. 10 .
CN202110511873.9A 2021-05-11 2021-05-11 Method for constructing bridge road in narrow space Active CN113215995B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110511873.9A CN113215995B (en) 2021-05-11 2021-05-11 Method for constructing bridge road in narrow space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110511873.9A CN113215995B (en) 2021-05-11 2021-05-11 Method for constructing bridge road in narrow space

Publications (2)

Publication Number Publication Date
CN113215995A CN113215995A (en) 2021-08-06
CN113215995B true CN113215995B (en) 2022-06-10

Family

ID=77094709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110511873.9A Active CN113215995B (en) 2021-05-11 2021-05-11 Method for constructing bridge road in narrow space

Country Status (1)

Country Link
CN (1) CN113215995B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863145B (en) * 2021-09-29 2023-07-25 中建一局集团华南建设有限公司 Bridge construction method and bridge on slope for easy-sliding slope
CN113863125B (en) * 2021-09-29 2023-04-28 中国建筑一局(集团)有限公司 Bridge supporting structure on slope for easy-sliding slope and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1448370A (en) * 2003-05-07 2003-10-15 河海大学 Air bubble mixed light-weight earth and production method thereof
JP2010116715A (en) * 2008-11-13 2010-05-27 Asurakku:Kk Retaining wall construction method
CN102352590A (en) * 2011-07-27 2012-02-15 河南省交通规划勘察设计院有限责任公司 Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN105019326A (en) * 2015-06-29 2015-11-04 河南华泰建材开发有限公司 Roadbed structure applied to road widening and construction method
CN106120501A (en) * 2016-08-10 2016-11-16 浙江大学城市学院 Existing barricade section roadbed is spelled width and is increased structure and construction method
CN207987960U (en) * 2018-02-01 2018-10-19 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN208379357U (en) * 2018-03-20 2019-01-15 中交二公局第一工程有限公司 Change the embankment structure for widening road
CN210395432U (en) * 2019-07-17 2020-04-24 福建第一公路工程集团有限公司 A Gravity Retaining Wall for Cutting Slope

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9359725B2 (en) * 2012-07-17 2016-06-07 Council Of Scientific & Industrial Research Stepwise repeated destabilization and stabilization of highly collapsible soil mass by ‘soil nailing technique’ used for construction of railway/road underpass

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1448370A (en) * 2003-05-07 2003-10-15 河海大学 Air bubble mixed light-weight earth and production method thereof
JP2010116715A (en) * 2008-11-13 2010-05-27 Asurakku:Kk Retaining wall construction method
CN102352590A (en) * 2011-07-27 2012-02-15 河南省交通规划勘察设计院有限责任公司 Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN105019326A (en) * 2015-06-29 2015-11-04 河南华泰建材开发有限公司 Roadbed structure applied to road widening and construction method
CN106120501A (en) * 2016-08-10 2016-11-16 浙江大学城市学院 Existing barricade section roadbed is spelled width and is increased structure and construction method
CN207987960U (en) * 2018-02-01 2018-10-19 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN208379357U (en) * 2018-03-20 2019-01-15 中交二公局第一工程有限公司 Change the embankment structure for widening road
CN210395432U (en) * 2019-07-17 2020-04-24 福建第一公路工程集团有限公司 A Gravity Retaining Wall for Cutting Slope

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
既有线旁深路堑滑坡群整治施工;杨怀志;《铁道建筑技术》;20010630(第03期);第35-37页 *
桩板墙结构加高挡土墙的应用;郑云刚等;《云南电力技术》;20070615(第03期);第40-41页 *
轻质土在高速公路建设中的探索与应用;罗吉庆;《路基工程》;20200220(第01期);第114-117页 *
钢管桩在陡坡路堤挡墙中的应用;唐正辉等;《西部交通科技》;20171030(第10期);第10-13、81页 *

Also Published As

Publication number Publication date
CN113215995A (en) 2021-08-06

Similar Documents

Publication Publication Date Title
CN107059774A (en) A kind of assembled high-rise pile cap revetment structure and construction method
CN106149625B (en) A kind of ecological self-purification type landscape revetment reconstruction structure and its construction method
CN104988948B (en) A kind of construction method of fin-plate type retaining wall
CN103510528A (en) Blind trench water discharging structure used for underground structure up-floating prevention
CN113215995B (en) Method for constructing bridge road in narrow space
CN104790410B (en) A kind of Support of Foundation Pit Excavation method that is applicable to shallow water mud river course
CN110241849A (en) An assembled concrete box retaining wall and its construction method
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN104846781A (en) Ecological interlocking block and ecological interlocking block type slope protection construction method
CN105239578A (en) Water-rich sand layer deep foundation pit underwater construction method
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN202730785U (en) Anti-floating blind ditch water drainage structure for underground structure
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN204780991U (en) Floor formula retaining wall
CN110258587A (en) The branch mark structure and construction method of side slope
CN217870559U (en) Inclined wall geomembrane earth-rock cofferdam structure suitable for higher manger plate flood peak of geomembrane
CN110258588A (en) The branch mark structure and its construction method of ground double-decked slope
CN217150063U (en) Novel desktop river lake dyke reinforced structure of viewing
CN114000475B (en) Farmland soil drainage system for loess plateau ditch construction and construction method thereof
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever
CN211872840U (en) Yonglin combined retaining wall structure in urban water conservancy projects
CN210395432U (en) A Gravity Retaining Wall for Cutting Slope
CN211547830U (en) Structure for preventing ground from being wetted
CN210482331U (en) Supporting structure of side slope
CN203452087U (en) Abrupt slope antiskid soil retaining supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant