- Publication number
- CN113152749A CN113152749A CN202110440153.8A CN202110440153A CN113152749A CN 113152749 A CN113152749 A CN 113152749A CN 202110440153 A CN202110440153 A CN 202110440153A CN 113152749 A CN113152749 A CN 113152749A
- Authority
- CN
- China
- Prior art keywords
- plate
- bolt
- cross beam
- curtain wall
- front side
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 10
- 238000010030 laminating Methods 0.000 claims abstract description 5
- 239000004927 clay Substances 0.000 claims description 14
- 230000000694 effects Effects 0.000 abstract description 5
- 239000000919 ceramic Substances 0.000 description 10
- 238000009434 installation Methods 0.000 description 7
- 238000000034 method Methods 0.000 description 3
- 238000009825 accumulation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
- Finishing Walls (AREA)
Abstract
The invention discloses a dry-hanging argil plate curtain wall structure which comprises a wall body, argil plates, a hanging plate and a first bolt, wherein an embedded part is embedded in the wall body, a connecting seat is fixedly arranged on the front side of the embedded part, a longitudinal beam is fixedly welded on the front side of the connecting seat, a connecting plate is welded on the front side of the longitudinal beam, a cross beam is arranged on the front side of the longitudinal beam in a laminating mode, the cross beam is fixedly arranged on the connecting plate through the connecting bolt, and the argil plates are arranged in front of the cross beam. This hang argil board curtain wall construction futilely, be provided with first bolt, slot and thread groove, rotate first bolt, first bolt promotes the crossbeam of ditch inslot and glides along the slot, play the effect of adjustment link plate and corresponding argil board vertical position, along crossbeam slip link plate, the second bolt slides in the thread groove this moment, press from both sides tight fixed cross beam through the cooperation of second bolt and clamp plate afterwards, play adjustment link plate and correspond argil board horizontal position's effect, be convenient for finely tune according to the in-service use demand, it has the practicality to use more.
Description
Technical Field
The invention relates to the technical field of curtain wall structures, in particular to a dry-hanging ceramic plate curtain wall structure.
Background
The curtain wall is the outer wall enclosure of building, is the light wall body that has decorative effect that high-rise building commonly used, mainly plays effects such as rain-proof, syllable-dividing and thermal-insulated, through the magnanimity retrieval, discovers current curtain wall structure typical, as patent number is: CN201220377387.9, curtain board and the joint formula curtain of joint formula curtain, it includes the curtain board body, and the curtain board of this joint formula curtain has simple structure, preparation simple to operate, can improve the advantage of installation effectiveness. The invention also discloses a clamping type curtain wall, the curtain wall plates are arranged on the clamping type curtain wall, and the adjacent curtain wall plates are tightly attached.
To sum up, current curtain wall construction does not usually be provided with fine setting structure, and in the building work progress, inevitable can produce the error, can cause the influence to the curtain installation after the error accumulation, make partial curtain need process again according to actual construction conditions, the work load has been increased, it has certain limitation to use, and current curtain wall construction need rotate bolt and nut simultaneously when the installation, but the clearance between curtain and the wall body is less, current fastening method operates the degree of difficulty greatly, it is not convenient enough to use, to above-mentioned problem, need improve current equipment.
Disclosure of Invention
The invention aims to provide a dry-hanging ceramic plate curtain wall structure, which solves the problems that the existing curtain wall structure proposed in the background technology is not provided with a fine adjustment structure, errors are inevitably generated in the construction process of a building, the curtain wall installation is influenced after the errors are accumulated, part of curtain walls need to be processed again according to the actual construction condition, the workload is increased, and the curtain wall structure has certain limitation in use.
In order to achieve the purpose, the invention provides the following technical scheme: a dry-hanging ceramic plate curtain wall structure comprises a wall body, a ceramic plate, a hanging plate and a first bolt,
an embedded part is embedded in the wall body, a connecting seat is fixedly installed on the front side of the embedded part, a longitudinal beam is fixedly welded on the front side of the connecting seat, a connecting plate is welded on the front side of the longitudinal beam, a cross beam is attached to the front side of the longitudinal beam, and the cross beam is fixedly installed on the connecting plate through a connecting bolt;
argil board sets up in crossbeam the place ahead, and argil board rear side has buried the back bolt underground, and the laminating of argil board rear side is provided with the link plate simultaneously, back bolt rear end runs through link plate and nut threaded connection, link plate outside sliding connection has the clamp plate, and the clamp plate upside is fixed with flexible gasket, the slot has been seted up to the link plate inside, and sets up the opening that is linked together with the slot on the link plate left side, the thread groove has been seted up to the crossbeam upside, and the crossbeam laminating sets up in the slot insidely, both sides threaded connection has the second bolt around the link plate, and the second bolt run through link plate, thread groove and elastic gasket in proper order and with clamp plate threaded connection.
Preferably, the rearmost end of the back bolt and the foremost end of the groove are located on the same vertical plane.
Preferably, the hanging plate is connected with a first bolt through central threads, and the lower end of the first bolt penetrates through the hanging plate and is attached to the top of the cross beam.
Preferably, the height dimension of the opening is greater than the height dimension of the cross beam.
Preferably, the width dimension of the thread groove is larger than the diameter dimension of the second bolt, and the width dimension of the thread groove is smaller than the diameter dimension of the first bolt.
Preferably, the front side and the rear side of the first bolt are symmetrically provided with two second bolts, and the two second bolts are simultaneously in threaded connection with the same pressing plate.
Compared with the prior art, the invention has the beneficial effects that: the dry hanging pottery clay plate curtain wall structure,
(1) the first bolt, the groove and the screw groove are arranged, the first bolt is rotated, the first bolt pushes the cross beam in the groove to slide downwards along the groove, the hanging plate is adjusted and the vertical position of the argil plate is corresponding to the vertical position of the argil plate, the hanging plate is slid along the cross beam, the second bolt slides in the screw groove at the moment, then the cross beam is clamped and fixed through the matching of the second bolt and the pressing plate, the hanging plate and the horizontal position of the argil plate are adjusted, fine adjustment can be conveniently carried out according to actual use requirements, and the practicability is high in use;
(2) be provided with clamp plate, link plate and second bolt, the second bolt runs through link plate, thread groove and elastic gasket and clamp plate threaded connection, rotates the second bolt, and second bolt pulling clamp plate is slided along the link plate, and tight crossbeam is pressed from both sides to clamp plate and second bolt cooperation, only relies on to rotate the second bolt and can accomplish the installation to argil board, and the installation step of simplifying is used more conveniently.
Drawings
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic diagram of a left side view cross-sectional structure of the present invention;
FIG. 3 is a schematic view of a hanging plate of the present invention;
FIG. 4 is a schematic view of a rear view cross section of the hanging plate of the present invention;
FIG. 5 is an enlarged view of the structure at A in FIG. 2 according to the present invention.
In the figure: 1. the wall body, 2, embedded parts, 3, connecting seats, 4, longitudinal beams, 5, connecting plates, 6, cross beams, 7, connecting bolts, 8, clay plates, 9, back bolts, 10, hanging plates, 11, nuts, 12, pressing plates, 13, elastic gaskets, 14, grooves, 15, openings, 16, screw grooves, 17, second bolts, 18 and first bolts.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: the utility model provides a hang argil board curtain wall construction futilely, as shown in fig. 1 and fig. 2, embedded part 2 has been buried underground to wall body 1 is inside, and 2 front sides fixed mounting of embedded part have a connecting seat 3, and 3 front sides welded fastening of connecting seat have longeron 4, and 4 front sides welded fastening of longeron have connecting plate 5, and 4 front side laminating of longeron are provided with crossbeam 6, and crossbeam 6 passes through connecting bolt 7 fixed mounting on connecting plate 5.
As shown in fig. 2, 3, 4 and 5, the clay plate 8 is disposed in front of the cross beam 6, a back bolt 9 is embedded in the rear side of the clay plate 8, a hanging plate 10 is attached to the rear side of the clay plate 8, the rearmost end of the back bolt 9 and the foremost end of the groove 14 are located on the same vertical plane, so as to prevent the back bolt 9 from obstructing the cross beam 6, so that the cross beam 6 slides more smoothly in the groove 14, a first bolt 18 is connected to the center of the hanging plate 10 through a thread, the lower end of the first bolt 18 penetrates through the hanging plate 10 and is attached to the top of the cross beam 6, the first bolt 18 is rotated, the first bolt 18 extends into the groove 14 and pushes the cross beam 6, so as to adjust the vertical position of the hanging plate 10, the rear end of the back bolt 9 penetrates through the hanging plate 10 and is connected to a nut 11 through the hanging plate 10, a pressing plate 12 is slidably connected to the outer side of the hanging plate 10, a resilient gasket 13 is fixed on the upper side of the pressing plate 12, the inside of the hanging plate 10 is provided with the groove 14, and the hanging plate 10 is provided with an opening 15 communicated with the groove 14 on the left side of the hanging plate 10, the height dimension of the opening 15 is larger than that of the cross beam 6, so that the cross beam 6 can conveniently enter the groove 14 through the opening 15, the upper side of the cross beam 6 is provided with a screw groove 16, the cross beam 6 is arranged inside the groove 14 in a fitting manner, the width dimension of the screw groove 16 is larger than that of the second bolt 17, the width dimension of the screw groove 16 is smaller than that of the first bolt 18, so that the second bolt 17 can conveniently slide in the screw groove 16, meanwhile, the first bolt 18 is prevented from extending into the screw groove 16, the front side and the rear side of the hanging plate 10 are in threaded connection with the second bolt 17, the second bolt 17 sequentially penetrates through the hanging plate 10, the screw groove 16 and the elastic gasket 13 and is in threaded connection with the pressing plate 12, the front side and the rear side of the first bolt 18 are symmetrically provided with two second bolts 17, the two second bolts 17 are simultaneously in threaded connection with the same pressing plate 12, the second bolts 17 are rotated, so that the second bolts 17 and the pressing plate 12 are matched with the cross beam 6, plays a role in fixing the hanging plate 10.
The working principle is as follows: when the dry hanging ceramic plate curtain wall structure is used, firstly, longitudinal beams 4 are installed on embedded parts 2 through connecting seats 3, connecting bolts 7 are rotated to enable cross beams 6 to be connected and fastened with connecting plates 5, the hanging plates 10 are attached to the rear sides of ceramic plates 8, nuts 11 are rotated, the nuts 11 are matched with back bolts 9 to enable the hanging plates 10 to be fixedly installed on the rear sides of the ceramic plates 8, the ceramic plates 8 are lifted, the cross beams 6 penetrate through openings 15 to enter the grooves 14, the ceramic plates 8 are hung on the cross beams 6 through the hanging plates 10 at the moment, first bolts 18 are rotated, the first bolts 18 extend into the grooves 14 and push the cross beams 6 to slide up and down along the grooves 14, the hanging plates 10 are adjusted to correspond to the vertical positions of the ceramic plates 8, the hanging plates 10 slide along the cross beams 6, second bolts 17 penetrate through the hanging plates 10, screw grooves 16 and elastic gaskets 13 to be in threaded connection with pressure plates 12, the second bolts 17 are rotated, the second bolts 17 pull the pressure plates 12 to slide up along the hanging plates 10, until the pressing plate 12 and the second bolt 17 are matched to clamp the cross beam 6 tightly, the effect of adjusting the horizontal positions of the hanging plate 10 and the corresponding argil plate 8 is achieved, through the operation, real-time adjustment according to actual use requirements is facilitated, the use is more practical, meanwhile, the installation steps are simplified, the device is suitable for a narrow operation environment between the argil plate 8 and the wall body 1, the use is more convenient, all work is completed, and the content which is not described in detail in the specification belongs to the prior art which is known by professionals in the field.
Claims (6)
1. The utility model provides a hang clay board curtain wall construction futilely, includes wall body (1), clay board (8), link plate (10) and first bolt (18), its characterized in that:
an embedded part (2) is embedded in the wall body (1), a connecting seat (3) is fixedly installed on the front side of the embedded part (2), a longitudinal beam (4) is fixedly welded on the front side of the connecting seat (3), a connecting plate (5) is welded on the front side of the longitudinal beam (4), a cross beam (6) is arranged on the front side of the longitudinal beam (4) in a fitting mode, and the cross beam (6) is fixedly installed on the connecting plate (5) through a connecting bolt (7);
the clay plate (8) is arranged in front of the cross beam (6), a back bolt (9) is embedded at the rear side of the clay plate (8), meanwhile, a hanging plate (10) is arranged at the rear part of the argil plate (8) in a laminating way, the rear end of the back bolt (9) penetrates through the hanging plate (10) to be in threaded connection with a nut (11), a pressing plate (12) is connected to the outer side of the hanging plate (10) in a sliding way, an elastic gasket (13) is fixed on the upper side of the pressure plate (12), a groove (14) is arranged in the hanging plate (10), an opening (15) communicated with the groove (14) is arranged at the left side of the hanging plate (10), a thread groove (16) is arranged at the upper side of the cross beam (6), the beam (6) is arranged in the groove (14) in a fitting manner, the front side and the rear side of the hanging plate (10) are in threaded connection with second bolts (17), and the second bolt (17) penetrates through the hanging plate (10), the thread groove (16) and the elastic gasket (13) in sequence and is in threaded connection with the pressing plate (12).
2. A dry-hang clay plate curtain wall structure as claimed in claim 1, wherein: the rearmost end of the back bolt (9) and the foremost end of the groove (14) are positioned on the same vertical plane.
3. A dry-hang clay plate curtain wall structure as claimed in claim 1, wherein: the hanging plate (10) is connected with a first bolt (18) through central threads, and the lower end of the first bolt (18) penetrates through the hanging plate (10) and is attached to the top of the cross beam (6).
4. A dry-hang clay plate curtain wall structure as claimed in claim 1, wherein: the height dimension of the opening (15) is larger than that of the cross beam (6).
5. A dry-hang clay plate curtain wall structure as claimed in claim 1, wherein: the width dimension of the thread groove (16) is larger than the diameter dimension of the second bolt (17), and the width dimension of the thread groove (16) is smaller than the diameter dimension of the first bolt (18).
6. A dry-hang clay plate curtain wall structure as claimed in claim 1, wherein: two second bolts (17) are symmetrically arranged on the front side and the rear side of the first bolt (18), and the two second bolts (17) are simultaneously in threaded connection with the same pressing plate (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110440153.8A CN113152749B (en) | 2021-04-22 | 2021-04-22 | A dry-hanging clay panel curtain wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110440153.8A CN113152749B (en) | 2021-04-22 | 2021-04-22 | A dry-hanging clay panel curtain wall structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113152749A true CN113152749A (en) | 2021-07-23 |
CN113152749B CN113152749B (en) | 2025-01-14 |
Family
ID=76869761
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110440153.8A Active CN113152749B (en) | 2021-04-22 | 2021-04-22 | A dry-hanging clay panel curtain wall structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113152749B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113463802A (en) * | 2021-08-17 | 2021-10-01 | 江苏和源兴建设股份有限公司 | Suspension type glass curtain wall |
CN113775087A (en) * | 2021-09-07 | 2021-12-10 | 苏州金螳螂幕墙有限公司 | Zipper argil plate curtain wall and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100031597A1 (en) * | 2008-01-24 | 2010-02-11 | Jong Gyoun Baek | Outer-wall construction apparatus for building |
CN202595973U (en) * | 2012-04-19 | 2012-12-12 | 福建华泰集团有限公司 | Installing structure for ceramic-plate combined curtain walls |
CN104612298A (en) * | 2013-11-04 | 2015-05-13 | 永升建设集团有限公司 | Improved ceramic plate curtain wall dry hanging construction method |
CN215054335U (en) * | 2021-04-22 | 2021-12-07 | 山西建筑工程集团有限公司 | Hang argil board curtain wall construction futilely |
-
2021
- 2021-04-22 CN CN202110440153.8A patent/CN113152749B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100031597A1 (en) * | 2008-01-24 | 2010-02-11 | Jong Gyoun Baek | Outer-wall construction apparatus for building |
CN202595973U (en) * | 2012-04-19 | 2012-12-12 | 福建华泰集团有限公司 | Installing structure for ceramic-plate combined curtain walls |
CN104612298A (en) * | 2013-11-04 | 2015-05-13 | 永升建设集团有限公司 | Improved ceramic plate curtain wall dry hanging construction method |
CN215054335U (en) * | 2021-04-22 | 2021-12-07 | 山西建筑工程集团有限公司 | Hang argil board curtain wall construction futilely |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113463802A (en) * | 2021-08-17 | 2021-10-01 | 江苏和源兴建设股份有限公司 | Suspension type glass curtain wall |
CN113775087A (en) * | 2021-09-07 | 2021-12-10 | 苏州金螳螂幕墙有限公司 | Zipper argil plate curtain wall and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN113152749B (en) | 2025-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113152749A (en) | Hang argil board curtain wall construction futilely | |
CN215054335U (en) | Hang argil board curtain wall construction futilely | |
CN218205089U (en) | Three-dimensional adjustable mechanism suitable for hyperbolic ribbon curtain wall | |
CN209799136U (en) | Mounting structure of stainless steel furred ceiling | |
CN220318902U (en) | Assembled photovoltaic BIPV curtain wall | |
CN204826342U (en) | Erection joint spare for construction | |
CN207525959U (en) | A new type of fast positioning and fixing device for unit curtain wall | |
CN210342356U (en) | Open type close-seam metal plate curtain wall system | |
CN210767387U (en) | Connection structure of little unit stone material curtain | |
CN217105717U (en) | Novel energy-saving unit type super high-rise building curtain wall mounting structure | |
CN209429347U (en) | A kind of connection structure of open type aluminium plate curtain wall | |
CN207974298U (en) | Island staggered floor construction at the top of a kind of integrated wall plate | |
CN208293841U (en) | Curtain wall system for outdoor ripple type aluminium sheet furred ceiling dry construction | |
CN209760615U (en) | Color steel tile fastener | |
CN220868537U (en) | Water batch plate for metal curtain wall | |
CN209603345U (en) | Side support point connected polycarbonate panel curtain wall | |
CN218374592U (en) | Glass curtain wall's handing-over adaptor | |
CN218265136U (en) | Telescopic steel support structure for building | |
CN219863540U (en) | Assembled curtain wall combined structure | |
CN213837291U (en) | Outer cover plate of energy-saving daylighting roof | |
CN222016439U (en) | A guide rail bracket for installing photovoltaic components | |
CN217949495U (en) | Double-layer suspended ceiling connecting mechanism with support structure | |
CN218116923U (en) | Adjustable curved surface decoration furred ceiling structure | |
CN219137770U (en) | Adjustable fixing device for steel plate water stop | |
CN218264710U (en) | Assembled dry-hanging equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |