CN112666931A - Programmable controller integrated test system - Google Patents

Programmable controller integrated test system Download PDF

Info

Publication number
CN112666931A
CN112666931A CN202011630968.4A CN202011630968A CN112666931A CN 112666931 A CN112666931 A CN 112666931A CN 202011630968 A CN202011630968 A CN 202011630968A CN 112666931 A CN112666931 A CN 112666931A
Authority
CN
China
Prior art keywords
power supply
terminal
input
data processing
programmable controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011630968.4A
Other languages
Chinese (zh)
Inventor
夏越超
杨南
佘丽萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Renergy Electric Tianjin Ltd
Original Assignee
Renergy Electric Tianjin Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Renergy Electric Tianjin Ltd filed Critical Renergy Electric Tianjin Ltd
Priority to CN202011630968.4A priority Critical patent/CN112666931A/en
Publication of CN112666931A publication Critical patent/CN112666931A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Programmable Controllers (AREA)

Abstract

本发明创造提供了一种可编程控制器集成测试系统,包括总电源供电保护模块、数据处理模块U1、数据显示设备U5;所述数据处理模块U1电源端与总电源供电保护模块输出端连接,所述数据处理模块U1的输出端与数据显示设备U5输入端连接,所述数据显示设备U5的电源端与总电源供电保护模块输出端连接;所述数据处理模块U1包括多个信号输入端,每个信号输入端连接有相应的信号端。本发明创造所述的集成测试系统,将230VAC输入电源进行电源变换及分配,搭建24VDC供电系统,可为可编程控制器、测试回路、数据处理等系统提供电源供电,且根据模块的类型,数量及基础电气性能,提供不同的测试负载和输入设备,适用性较强。

Figure 202011630968

The present invention creates and provides a programmable controller integrated testing system, comprising a mains power supply protection module, a data processing module U1, and a data display device U5; the power supply end of the data processing module U1 is connected to the output end of the mains power supply protection module, The output end of the data processing module U1 is connected to the input end of the data display device U5, and the power supply end of the data display device U5 is connected to the output end of the general power supply protection module; the data processing module U1 includes a plurality of signal input ends, Each signal input terminal is connected with a corresponding signal terminal. The invention creates the integrated test system, which converts and distributes the 230VAC input power supply to build a 24VDC power supply system, which can provide power supply for programmable controllers, test circuits, data processing and other systems, and according to the type of modules, the number of and basic electrical performance, provide different test loads and input devices, and have strong applicability.

Figure 202011630968

Description

Programmable controller integrated test system
Technical Field
The invention belongs to the field of electric power product testing, and particularly relates to a programmable controller integrated test system.
Background
The programmable controller is used as a core component of the wind power generation control system to control communication and signal transmission of each electric control cabinet, the programmable controller is internally composed of electronic elements and plates, the performance of the programmable controller is influenced by factors such as temperature and load, and the programmable controller needs to be built for different types of programmable controller module type tools in common test seeds, so that the operation is complicated.
The common test method has several disadvantages:
1. different testing tools need to be built according to different types of modules, and the testing is complicated
Because of the many module types that programmable controller contains, modules such as DI, DO, AI need set up different test fixtures according to different module functions, and the test is loaded down with trivial details.
2. The environmental test data is single and the performance of the environmental test data cannot be fully verified
In a common test, the function test is only carried out at normal temperature, and the related performance test is not carried out under the conditions of high temperature and low temperature, but the operation temperature of the electric control cabinet is wider from minus 30 ℃ to plus 55 ℃, and the common test cannot verify the performance at other temperatures; meanwhile, for a DO module, a DO point is forced through ordinary testing, only the attraction of an indicator lamp or a coil is observed, and the DO module is not fully verified according to the maximum output current of the DO module.
3. The efficiency of the test is low, and the test data is not convenient to record and check
Because the DI and DO modules contain more channels, the common method can only perform inspection test on one channel at a time, and the test efficiency is low. And the experimental data needs to be manually detected and recorded, so that the data is inconvenient to check and count.
Disclosure of Invention
In view of the above, the present invention provides an integrated test system for a programmable controller, so as to solve the problems that the common test method is complicated in test, the environment test data is single, the performance of the test method cannot be fully verified, the test efficiency is low, the test data is not convenient to record and view, and the like.
In order to achieve the purpose, the technical scheme of the invention is realized as follows:
a programmable controller integrated test system comprises a main power supply protection module, a data processing module U1 and a data display device U5;
the power supply end of the data processing module U1 is connected with the output end of the main power supply protection module, the output end of the data processing module U1 is connected with the input end of the data display device U5, and the power supply end of the data display device U5 is connected with the output end of the main power supply protection module;
the data processing module U1 includes a plurality of signal input terminals, each connected to a respective signal terminal.
Further, the plurality of signal input ends comprise a digital quantity input end DI, a digital quantity output end DO and an analog quantity input end AI, the signal ends comprise a signal generator U2, an electronic load U3 and a multi-channel resistor U4, the output end of the signal generator U2 is connected with the digital quantity input end DI, the output end of the electronic load U3 is connected with the digital quantity output end DO, and the output end of the multi-channel resistor U4 is connected with the analog quantity input end AI.
Further, total power supply protection module includes two power ends, uninterrupted power source G1, two sets of binding post, two power ends include alternating current power end, battery G2, uninterrupted power source G1 includes first input, second input, output, the alternating current power end is connected with uninterrupted power source G1's first input, and battery G2 is connected with uninterrupted power source G1's second input, and two sets of binding post connect the output at uninterrupted power source G1.
Further, the two groups of connecting terminals comprise a first connecting terminal XP1 and a second connecting terminal XP2, the interface of the first connecting terminal XP11 is connected with the positive pole of the output end of the uninterruptible power supply G1, and the interface 1 of the second connecting terminal XP2 is connected with the negative pole of the output end of the uninterruptible power supply G1.
Further, the positive terminal of the power supply terminal of the data processing module U1 is connected to the 2 interface of the first connection terminal XP1, and the negative terminal of the power supply terminal of the data processing module U1 is connected to the 2 interface of the second connection terminal XP 2.
Further, the positive end of the power supply terminal of the data display device U5 is connected to the 3 interface of the first connection terminal XP1, and the negative end of the power supply terminal of the data display device U5 is connected to the 3 interface of the second connection terminal XP 2.
Further, a protection switch F1 and a switching power supply V1 are connected between the alternating current power supply end and the first input end of the uninterruptible power supply G1, a control end of the protection switch F1 is connected with the alternating current power supply end, a controlled end of the protection switch F1 is connected with an input end of the switching power supply V1, and an output end of the switching power supply V1 is connected with the first input end of the uninterruptible power supply G1.
Compared with the prior art, the programmable controller integrated test system has the following advantages:
(1) the integrated test system provided by the invention has the advantages that the 230VAC input power supply is subjected to power conversion and distribution, a 24VDC power supply system is built, power supply can be provided for systems such as a programmable controller, a test loop and data processing, different test loads and input equipment are provided according to the type, the number and the basic electrical performance of modules, and the applicability is strong;
(2) the invention creates the integrated test system, the programmable controller is placed in an environment test box, and the performance conditions of the programmable controller under different environment conditions are fully verified by setting parameters such as relevant temperature, humidity and the like according to the actual operation environment on site; through using CX5130 controller to handle AI, DI data to show data to PC end, can directly observe experimental data, improve whole efficiency of software testing.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and, together with the description, serve to explain the invention without limitation. In the drawings:
fig. 1 is a flowchart of a programmable controller integration test system according to an embodiment of the present invention.
Description of reference numerals:
f1, a protection switch; v1, a switching power supply; g1, uninterrupted power supply; g2, a storage battery; XP1, a first connecting terminal; XP2, a second connecting terminal; DI. A digital value input terminal; DO, digital output end; AI. An analog input end; u1, a data processing module; u2, signal generator; u3, electronic load; u4, multichannel resistor; u5, data display equipment.
Detailed Description
It should be noted that the embodiments and features of the embodiments of the present invention may be combined with each other without conflict.
In the description of the present invention, it is to be understood that the terms "central," "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientation or positional relationship indicated in the drawings, which are merely for convenience in describing the invention and to simplify the description, and are not intended to indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and are therefore not to be construed as limiting the invention. Furthermore, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the invention, the meaning of "a plurality" is two or more unless otherwise specified.
In the description of the invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "connected" and "connected" are to be construed broadly, e.g. as being fixed or detachable or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the creation of the present invention can be understood by those of ordinary skill in the art through specific situations.
The invention will be described in detail with reference to the following embodiments with reference to the attached drawings.
As shown in fig. 1, a programmable controller integrated test system includes a temperature control environment box for operating the programmable controller integrated test system, where the integrated test system includes a main power supply protection module, a data processing module U1, and a data display device U5;
the power supply end of the data processing module U1 is connected with the output end of the main power supply protection module, the output end of the data processing module U1 is connected with the input end of the data display device U5, and the power supply end of the data display device U5 is connected with the output end of the main power supply protection module;
the data processing module U1 comprises a plurality of signal input ends, and each signal input end is connected with a corresponding signal end;
the data processing module model is CX 5130.
The signal input ends comprise a digital quantity input end DI, a digital quantity output end DO and an analog quantity input end AI, the signal input ends comprise a signal generator U2, an electronic load U3 and a multi-channel resistor U4, the output end of the signal generator U2 is connected with the digital quantity input end DI, the output end of the electronic load U3 is connected with the digital quantity output end DO, and the output end of the multi-channel resistor U4 is connected with the analog quantity input end AI;
the data display device U5 is a PC display; the data processing module is a CX5130 controller.
As shown in fig. 1, U1 is a programmable controller, 24V and 0V are power supplies, and the terminal row of U1: X1 is a DI input signal point; the X2 terminal row is a DO output signal point, the X3 terminal row is an AI signal point, and the X100 terminal row is a communication connection point with the PC terminal;
u2 is a signal generator, except for verifying normal 24V power-on function test, it can also set output according to the input voltage and current parameters of different products, for fully verifying DI performance test;
the signal generator model is: AWG 5200.
U3 is an electronic load, a DO point is forced only through software in a conventional test, the coil of the rear-end intermediate relay can be controlled to be electrified and attracted, the scheme can be used for testing according to the output capacity of the DO point, such as 24V and 300mA, and whether the test requirement of 300mA can be met or not can be checked by setting the electronic load;
the electronic load model is IT 852B.
U4 is a multi-channel resistor, and can be set to different resistance values according to the capacity of AI signal channel to fully verify its performance.
The general power supply protection module comprises two power ends, an uninterruptible power supply G1 and two sets of wiring terminals, wherein the two power ends comprise an alternating current power end and a storage battery G2, the uninterruptible power supply G1 comprises a first input end, a second input end and an output end, the alternating current power end is connected with the first input end of the uninterruptible power supply G1, the storage battery G2 is connected with the second input end of the uninterruptible power supply G1, and the two sets of wiring terminals are connected at the output end of the uninterruptible power supply G1.
The two groups of connecting terminals comprise a first connecting terminal XP1 and a second connecting terminal XP2, an interface of the first connecting terminal XP11 is connected with the positive pole of the output end of the uninterruptible power supply G1, and an interface 1 of the second connecting terminal XP2 is connected with the negative pole of the output end of the uninterruptible power supply G1;
the positive end of the power supply end of the data processing module U1 is connected with the 2 interface of the first wiring terminal XP1, and the negative end of the power supply end of the data processing module U1 is connected with the 2 interface of the second wiring terminal XP 2;
the positive end of the power supply end of the data display device U5 is connected with the 3 interface of the first wiring terminal XP1, and the negative end of the power supply end of the data display device U5 is connected with the 3 interface of the second wiring terminal XP 2;
a protection switch F1 and a switching power supply V1 are further connected between the alternating current power supply end and the first input end of the uninterruptible power supply G1, the control end of the protection switch F1 is connected with the alternating current power supply end, the controlled end of the protection switch F1 is connected with the input end of the switching power supply V1, and the output end of the switching power supply V1 is connected with the first input end of the uninterruptible power supply G1;
f1 is a protection switch of a control loop power supply system, V1 is a switch power supply, a 230V AC power supply is converted into a 24V DC power supply, 24V DC power supply is provided for the control loop and the data processing unit, certain redundancy is provided for the number of 24V DC power supply interfaces, and power supply can be provided for other 24V DC equipment during testing; the G1 bit UPS can provide stable 24V DC power supply for the back end equipment, the G2 is 12Ah accumulator, it can provide corresponding power supply for the back end data processing module when the system is abnormal power off, and it can ensure the normal storage and transmission of data. XP 1: 1-X +1 is a 24V wiring terminal, XP 2: 1-X +1 is a 0V wiring terminal, and supplies 24V DC power supply to part of the control loop and the data processing unit.
The environmental temperature is controlled by using the environmental test chamber, and the reliability of test data is improved by adjusting the temperature set value to simulate the field environmental temperature.
The examples are as follows:
taking the DO channel as an example:
placing a programmable controller in an environment test box, and simulating the actual operation temperature of the electric control cabinet by adjusting a temperature set value; the main power protection switch F1 is closed, the 24VDC switch power supply is powered on, the XP1 terminal and the XP2 terminal are powered off, the rear end data processor and the PC display the power on and work, the electronic load is set through the DO type, such as 24VDC,300A, and whether the performance meets the application requirement is displayed through the electronic load and the DO module channel.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and should not be taken as limiting the invention, so that any modifications, equivalents, improvements and the like, which are within the spirit and principle of the present invention, should be included in the scope of the present invention.

Claims (7)

1.一种可编程控制器集成测试系统,其特征在于:集成测试系统包括总电源供电保护模块、数据处理模块U1、数据显示设备U5;1. a programmable controller integrated testing system, is characterized in that: the integrated testing system comprises a total power supply protection module, a data processing module U1, a data display device U5; 所述数据处理模块U1电源端与总电源供电保护模块输出端连接,所述数据处理模块U1的输出端与数据显示设备U5输入端连接,所述数据显示设备U5的电源端与总电源供电保护模块输出端连接;The power supply terminal of the data processing module U1 is connected to the output terminal of the main power supply protection module, the output terminal of the data processing module U1 is connected to the input terminal of the data display device U5, and the power supply terminal of the data display device U5 is connected to the main power supply protection module. module output connection; 所述数据处理模块U1包括多个信号输入端,每个信号输入端连接有相应的信号端。The data processing module U1 includes a plurality of signal input terminals, and each signal input terminal is connected with a corresponding signal terminal. 2.根据权利要求1所述的一种可编程控制器集成测试系统,其特征在于:所述多个信号输入端包括数字量输入端DI、数字量输出端DO、模拟量输入端AI,信号端包括信号发生器U2、电子负载U3、多通道电阻U4,所述信号发生器U2的输出端与数字量输入端DI连接,所述电子负载U3的输出端与数字量输出端DO连接,所述多通道电阻U4输出端与模拟量输入端AI连接。2. A programmable controller integrated testing system according to claim 1, characterized in that: the plurality of signal input ends comprises a digital input end DI, a digital output end DO, an analog input end AI, and a signal The terminal includes a signal generator U2, an electronic load U3, and a multi-channel resistor U4. The output terminal of the signal generator U2 is connected to the digital input terminal DI, and the output terminal of the electronic load U3 is connected to the digital quantity output terminal DO. The output terminal of the multi-channel resistor U4 is connected to the analog input terminal AI. 3.根据权利要求1所述的一种可编程控制器集成测试系统,其特征在于:所述总电源供电保护模块包括两个电源端、不间断电源G1、两组接线端子,所述两个电源端包括交流电电源端、蓄电池G2,所述不间断电源G1包括第一输入端、第二输入端、输出端,所述交流电电源端与不间断电源G1的第一输入端连接,蓄电池G2与不间断电源G1的第二输入端连接,两组接线端子连接在不间断电源G1的输出端。3. A programmable controller integrated test system according to claim 1, characterized in that: the general power supply protection module comprises two power supply terminals, an uninterruptible power supply G1, two groups of connection terminals, and the two The power supply terminal includes an AC power supply terminal and a battery G2. The uninterruptible power supply G1 includes a first input terminal, a second input terminal, and an output terminal. The AC power supply terminal is connected to the first input terminal of the uninterruptible power supply G1. The storage battery G2 is connected to the first input terminal. The second input end of the uninterruptible power supply G1 is connected, and the two sets of connection terminals are connected to the output end of the uninterruptible power supply G1. 4.根据权利要求1所述的一种可编程控制器集成测试系统,其特征在于:两组接线端子包括第一接线端子XP1、第二接线端子XP2,第一接线端子XP11接口与不间断电源G1的输出端的正极连接,第二接线端子XP2的1接口与不间断电源G1的输出端的负极连接。4. A programmable controller integrated testing system according to claim 1, characterized in that: the two groups of terminals comprise a first terminal XP1, a second terminal XP2, an interface of the first terminal XP11 and an uninterruptible power supply The positive pole of the output terminal of G1 is connected, and the 1 interface of the second connection terminal XP2 is connected to the negative pole of the output terminal of the uninterruptible power supply G1. 5.根据权利要求4所述的一种可编程控制器集成测试系统,其特征在于:数据处理模块U1电源端的正极端与第一接线端子XP1的2接口连接,数据处理模块U1的电源端的负极端与第二接线端子XP2的2接口连接。5. a kind of programmable controller integrated testing system according to claim 4 is characterized in that: the positive terminal of the power supply end of the data processing module U1 is connected with the 2 interface of the first connection terminal XP1, and the negative terminal of the power supply terminal of the data processing module U1 is connected. The pole is connected to the 2 interface of the second terminal XP2. 6.根据权利要求4所述的一种可编程控制器集成测试系统,其特征在于:所述数据显示设备U5电源端的正极端与第一接线端子XP1的3接口连接,所述数据显示设备U5电源端的负极端与第二接线端子XP2的3接口连接。6. a kind of programmable controller integrated testing system according to claim 4 is characterized in that: the positive terminal of the power supply end of the data display device U5 is connected with the 3 interface of the first connection terminal XP1, and the data display device U5 The negative terminal of the power supply terminal is connected to the 3 interface of the second connection terminal XP2. 7.根据权利要求3所述的一种可编程控制器集成测试系统,其特征在于:所述交流电电源端与不间断电源G1第一输入端之间还连接有保护开关F1、开关电源V1,所述保护开关F1控制端与交流电电源端连接,保护开关F1的被控制端与开关电源V1的输入端连接,开关电源V1的输出端与不间断电源G1第一输入端连接。7. A programmable controller integrated testing system according to claim 3, characterized in that: a protection switch F1 and a switching power supply V1 are also connected between the AC power supply terminal and the first input terminal of the uninterruptible power supply G1, The control terminal of the protection switch F1 is connected to the AC power terminal, the controlled terminal of the protection switch F1 is connected to the input terminal of the switching power supply V1, and the output terminal of the switching power supply V1 is connected to the first input terminal of the uninterruptible power supply G1.
CN202011630968.4A 2020-12-30 2020-12-30 Programmable controller integrated test system Pending CN112666931A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011630968.4A CN112666931A (en) 2020-12-30 2020-12-30 Programmable controller integrated test system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011630968.4A CN112666931A (en) 2020-12-30 2020-12-30 Programmable controller integrated test system

Publications (1)

Publication Number Publication Date
CN112666931A true CN112666931A (en) 2021-04-16

Family

ID=75413032

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011630968.4A Pending CN112666931A (en) 2020-12-30 2020-12-30 Programmable controller integrated test system

Country Status (1)

Country Link
CN (1) CN112666931A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113238909A (en) * 2021-06-21 2021-08-10 天津瑞能电气有限公司 Integrated test system of temperature converter

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101968503A (en) * 2010-09-14 2011-02-09 青岛海信电器股份有限公司 Load circuit and load testing device with same
CN202008519U (en) * 2011-01-30 2011-10-12 深圳创维数字技术股份有限公司 Test device
CN203287492U (en) * 2013-04-17 2013-11-13 西门子工厂自动化工程有限公司 Test board for testing X121 input/output port of numeric control unit
CN203337792U (en) * 2013-05-30 2013-12-11 天津出入境检验检疫局工业产品安全技术中心 Motor type test system
CN104931895A (en) * 2015-05-25 2015-09-23 常州大学 Load test device for rail vehicle power panels
CN105445601A (en) * 2014-09-30 2016-03-30 株洲变流技术国家工程研究中心有限公司 Current transformer interface testing device and method
CN106527406A (en) * 2016-12-20 2017-03-22 中核控制系统工程有限公司 Security-level DCS product automated testing device
CN106969674A (en) * 2017-05-03 2017-07-21 北京电子工程总体研究所 A kind of generalization ground checkout equipment based on PLC module
CN107615076A (en) * 2015-12-28 2018-01-19 深圳配天智能技术研究院有限公司 Multi-channel interface test device
CN110095718A (en) * 2018-01-30 2019-08-06 北京金风慧能技术有限公司 Multifunctional wind power generator group electron detection device
CN111579980A (en) * 2020-05-26 2020-08-25 天津瑞能电气有限公司 Speed relay integrated test system
CN214253003U (en) * 2020-12-30 2021-09-21 天津瑞能电气有限公司 Programmable controller integrated test system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101968503A (en) * 2010-09-14 2011-02-09 青岛海信电器股份有限公司 Load circuit and load testing device with same
CN202008519U (en) * 2011-01-30 2011-10-12 深圳创维数字技术股份有限公司 Test device
CN203287492U (en) * 2013-04-17 2013-11-13 西门子工厂自动化工程有限公司 Test board for testing X121 input/output port of numeric control unit
CN203337792U (en) * 2013-05-30 2013-12-11 天津出入境检验检疫局工业产品安全技术中心 Motor type test system
CN105445601A (en) * 2014-09-30 2016-03-30 株洲变流技术国家工程研究中心有限公司 Current transformer interface testing device and method
CN104931895A (en) * 2015-05-25 2015-09-23 常州大学 Load test device for rail vehicle power panels
CN107615076A (en) * 2015-12-28 2018-01-19 深圳配天智能技术研究院有限公司 Multi-channel interface test device
CN106527406A (en) * 2016-12-20 2017-03-22 中核控制系统工程有限公司 Security-level DCS product automated testing device
CN106969674A (en) * 2017-05-03 2017-07-21 北京电子工程总体研究所 A kind of generalization ground checkout equipment based on PLC module
CN110095718A (en) * 2018-01-30 2019-08-06 北京金风慧能技术有限公司 Multifunctional wind power generator group electron detection device
CN111579980A (en) * 2020-05-26 2020-08-25 天津瑞能电气有限公司 Speed relay integrated test system
CN214253003U (en) * 2020-12-30 2021-09-21 天津瑞能电气有限公司 Programmable controller integrated test system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113238909A (en) * 2021-06-21 2021-08-10 天津瑞能电气有限公司 Integrated test system of temperature converter

Similar Documents

Publication Publication Date Title
CN201314921Y (en) Socket box used for relay testing
JP6289803B2 (en) Storage battery device, storage battery device management method, and storage battery system
EP3346541A1 (en) Cell agnostic battery pack
EP3014726B1 (en) Energy storage system
CN214253003U (en) Programmable controller integrated test system
CN112666931A (en) Programmable controller integrated test system
CN212569000U (en) Parametric simulation circuit and battery management device
CN210294487U (en) Nickel-hydrogen battery package assembly function test equipment
CN207663018U (en) Switch the detection device of relay and its wiring
CN217386205U (en) Fault detection device and system
CN215641727U (en) Lithium battery protection board testing device
CN215576274U (en) Novel BMU slave control module aging vehicle
CN210465626U (en) A relay test platform
CN103415973A (en) Power storage system and method for controlling power storage module
CN115389831A (en) Programmable burn-in system
JP4842734B2 (en) Battery powered equipment
CN222896255U (en) Precision calibration tool and system for blade lithium battery formation component equipment
CN113964397B (en) Battery cell sampling device, method, battery management system and battery pack
CN205335921U (en) Stand -by power supply of family device
CN109842200A (en) Mobile pin-connected panel lithium battery UPS power supply system
CN218727923U (en) Cable conduction testing device
CN216133325U (en) Integrated test system of switch power supply for energy storage
CN221263387U (en) Novel battery parallel operation summarizing device
CN222439563U (en) Portable testing device and testing system
CN114204620B (en) Power supply system suitable for multiple power supply modes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination