CN112377193B - Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate - Google Patents
Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate Download PDFInfo
- Publication number
- CN112377193B CN112377193B CN202011106611.6A CN202011106611A CN112377193B CN 112377193 B CN112377193 B CN 112377193B CN 202011106611 A CN202011106611 A CN 202011106611A CN 112377193 B CN112377193 B CN 112377193B
- Authority
- CN
- China
- Prior art keywords
- roof
- roadway
- side entry
- breaking
- gob
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/04—Directional drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/02—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection having means for indicating tension
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42D—BLASTING
- F42D3/00—Particular applications of blasting techniques
- F42D3/04—Particular applications of blasting techniques for rock blasting
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Remote Sensing (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
Description
技术领域technical field
本发明涉及煤矿开采技术领域,尤其是一种深井小煤柱沿空留巷的卸压和支护方法。The invention relates to the technical field of coal mining, in particular to a pressure relief and support method for gob-side entry retaining with small coal pillars in deep wells.
背景技术Background technique
随着煤矿浅部资源日趋枯竭,矿井开采深度逐年加大,煤层赋存条件越来越复杂,冲击地压、煤与瓦斯突出、高温热害等问题严重威胁矿井安全生产,同时采掘接续紧张问题也日益凸显,特别是对于老矿井及条件复杂矿井,严重制约矿井的安全高效生产。目前普遍采用的沿空掘巷布置方式,存在采掘接续紧张与高瓦斯矿井工作面串联通风的矛盾;采用宽煤柱护巷方式虽然可以解决上述问题,但这一方面会造成较大的煤炭损失,更重要的是在深井煤柱上必然形成高度应力集中,极易诱发冲击地压灾害事故。With the depletion of resources in the shallow part of the coal mine, the mining depth of the mine is increasing year by year, and the occurrence conditions of the coal seam are becoming more and more complicated. It is also increasingly prominent, especially for old mines and mines with complex conditions, which seriously restrict the safe and efficient production of mines. The currently commonly used gob-side roadway arrangement has the contradiction between the tight excavation continuity and the series ventilation of the high-gas mine working face; although the wide coal pillar roadway protection method can solve the above problems, it will cause a large coal loss on the one hand. , and more importantly, a high degree of stress concentration must be formed on the coal pillars of deep wells, which can easily induce rock burst disasters.
沿空留巷是采用一定技术手段将上一区段的回采巷道保留下来供下一区段使用,该技术具有减少巷道掘进量、提高煤炭资源回收率、实现Y型通风、降低工作面隅角瓦斯积聚等优势。但目前采用的不留煤柱的完全沿空留巷巷旁支护方式(木垛、密集支柱、矸石带、混凝土切块、膏体等),由于深部矿山压力大,所以现有的支护方式均不能有效解决深部厚煤层高瓦斯矿井通风困难、采空区漏风自然、支护困难等技术难题。另外切顶卸压自动成巷无煤柱开采技术也已经开始应用,切顶卸压自动成巷无煤柱开采技术通过顶板定向预裂切缝,强力支护回采巷道顶板,在采空区侧顶板岩层矿山压力作用下,顶板部分岩体沿预裂切缝切落,实现自动成巷和无煤柱开采。但切顶自成巷技术需对沿空留巷进行超强支护,支护的难度大、成本高,并且巷旁挡矸系统难以阻隔有害气体的渗入;此外切顶卸压自成巷无煤柱开采技术受高地压影响严重,所以在深部矿井开采中应用较少。Gob-side entry retention is to use certain technical means to reserve the mining roadway of the previous section for the next section. Gas accumulation and other advantages. However, the currently adopted support methods (wood stacks, dense pillars, gangue strips, concrete blocks, paste, etc.) that do not leave coal pillars completely gob-side entry retaining roadway, due to the high pressure in deep mines, the existing support methods None of them can effectively solve the technical problems such as difficulty in ventilation in deep thick coal seam and high gas mines, natural air leakage in goaf, and difficulty in support. In addition, the roof-cutting and pressure-relieving automatic roadway-free mining technology has also been applied. The roof-cutting and pressure-relieving automatic roadway-free mining technology uses the roof directional pre-splitting and cutting seam, and strongly supports the roof of the mining roadway. Under the action of the mine pressure of the roof stratum, the roof part of the rock mass is cut off along the pre-split slits to realize automatic road formation and coal pillar-free mining. However, the technology of roof cutting self-formed roadway requires super support for gob-side entry retention, which is difficult and costly, and the roadside gangue retaining system is difficult to block the infiltration of harmful gases; in addition, roof cutting and pressure relief self-formed roadway has no Coal pillar mining technology is seriously affected by high ground pressure, so it is less used in deep mine mining.
因此,为了解决深部矿井开采中沿空留巷采掘接续与巷道通风及巷道支护之间的矛盾,一方面不仅需要解决深井通风困难问题,特别是对于高瓦斯矿井,同时还要保证小煤柱起到了隔离上工作面采空区有害气体、水及矸石的作用;另一方面还需要解决采掘接续紧张难题,保证了矿井均衡高效生产。深井沿空留巷因本身地应力高,加上受上工作面和本工作面两次采动动压影响,小煤柱和沿空留巷受到很高的支承压力和采动作用影响,正常开采条件下留巷非常困难。Therefore, in order to solve the contradiction between the gob-side entry retaining mining and the roadway ventilation and roadway support in deep mine mining, it is not only necessary to solve the difficult problem of deep well ventilation, especially for high gas mines, but also to ensure small coal pillars. It plays the role of isolating the harmful gas, water and gangue in the goaf of the upper working face; on the other hand, it is necessary to solve the problem of continuous mining and ensure the balanced and efficient production of the mine. Due to the high in-situ stress of gob-side entry retention in deep wells and the influence of two mining dynamic pressures on the upper working face and this working face, small coal pillars and gob-side entry retention are affected by high support pressure and mining action, and normal It is very difficult to keep the roadway under the mining conditions.
发明内容SUMMARY OF THE INVENTION
为了改善深井沿空留巷中的通风和支护条件,保证小煤柱的稳定性,有效隔离上工作面的有害气体,本发明提供了一种基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法,具体的技术方案如下。In order to improve the ventilation and support conditions in the gob-side entry retaining of the deep well, ensure the stability of the small coal pillars, and effectively isolate the harmful gas in the upper working face, the present invention provides a deep well small coal mine based on the roof pressure relief of the key layer under the roof. The specific technical scheme of the coal pillar gob-side entry retaining method is as follows.
基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法,步骤包括:The gob-side entry retaining method for small coal pillars in deep wells based on the pressure relief of fault roof in key layers below the roof, the steps include:
A.确定煤层顶板的地质条件;A. Determine the geological conditions of the coal seam roof;
B.根据煤层顶板地质条件确定爆破的断顶参数,所述爆破的断顶参数包括下位关键层断顶的位置和厚度;B. Determine the fault roof parameters of blasting according to the geological conditions of the coal seam roof, and the fault roof parameters of the blasting include the position and thickness of the fault roof of the lower key layer;
C.数值模拟断顶厚度与断顶卸压后围岩变形量和巷道围岩应力之间的关系;C. Numerical simulation of the relationship between the thickness of the fault roof, the deformation of the surrounding rock after the pressure relief of the fault roof, and the surrounding rock stress of the roadway;
D.根据围岩变形量和巷道应力分布确定巷道的断顶参数;D. Determine the roof fault parameters of the roadway according to the deformation of the surrounding rock and the stress distribution of the roadway;
E.按照断顶参数在试验巷道内施工爆破,并在试验巷道内的围岩布置位移监测站、锚杆和锚索受力监测站;E. Carry out blasting in the test roadway according to the parameters of the broken roof, and arrange displacement monitoring stations, anchor rods and anchor cable force monitoring stations in the surrounding rock in the test roadway;
F.根据试验巷道表面位移曲线、锚杆受力监测曲线和锚索受力监测曲线修正支护参数;F. Correct the support parameters according to the surface displacement curve of the test roadway, the monitoring curve of the force of the bolt and the monitoring curve of the force of the anchor cable;
G.在沿空留巷的巷道内施工爆破断顶,并按照修正后的支护参数对沿空留巷的巷道进行支护。G. Carry out blasting and broken roof in the roadway of gob-side entry retention, and support the gob-side entry-retention roadway according to the revised support parameters.
优选的是,顶板的地质条件包括顶板岩性和顶板厚度,所述下位关键层传递来自上覆岩层的应力。Preferably, the geological conditions of the roof include roof lithology and roof thickness, and the underlying critical layer transmits stress from the overburden.
优选的是,断顶参数包括钻孔参数和炸药参数,其中所述钻孔参数包括钻孔超前工作面的距离、钻孔直径、钻孔角度、钻孔深度和钻孔间距,所述炸药参数包括爆破半径、装药量和封口长度。Preferably, the top breaking parameters include drilling parameters and explosive parameters, wherein the drilling parameters include the distance of the drilling ahead of the working face, the drilling diameter, the drilling angle, the drilling depth and the drilling spacing, and the explosive parameters Including blast radius, charge and seal length.
还优选的是,钻孔参数中钻孔与实体煤一侧巷帮距离大于200mm,钻孔直径取48-50mm;薄煤层中钻孔倾角为20°,中厚煤层或厚煤层中钻孔倾角为10°-15°;钻孔深度大于下位关键层的厚度;硬岩中钻孔的间距取500mm,软岩中钻孔间距取1000mm。It is also preferred that in the drilling parameters, the distance between the drilling and the roadway on one side of the solid coal is greater than 200 mm, and the diameter of the drilling is 48-50 mm; the inclination angle of the drilling in the thin coal seam is 20°, and the inclination angle of the drilling in the medium-thick coal seam or the thick coal seam is 20°. is 10°-15°; the drilling depth is greater than the thickness of the lower key layer; the spacing of drilling holes in hard rock is 500mm, and the spacing between drilling holes in soft rock is 1000mm.
还优选的是,炸药的爆破参数中,以钻孔为中心钻孔半径为R0,粉碎区的半径为R1,破裂区的半径为R2,震动区的半径为R3,其中破裂区的半径为爆破半径;爆破中药卷装药至下位关键层的位置。It is also preferred that, in the blasting parameters of the explosive, the radius of the drill hole is R 0 with the drill hole as the center, the radius of the crushing zone is R 1 , the radius of the rupture zone is R 2 , the radius of the vibration zone is R 3 , and the radius of the rupture zone is
进一步优选的是,爆破半径R2的取值为:Further preferably, the value of the blast radius R 2 is:
其中α为应力波衰减系数,且α=2-b;b为径向应力与切向应力的比值,且b=μ/(1-μ),P2为不耦合装药系数下的冲击波应力峰值,且rb为钻孔半径,ST为岩石的单轴抗拉强度,μ为泊松比,ρ0为炸药密度,D为爆炸速度,rc为装药半径;n为应力增大倍数,取8-11。where α is the stress wave attenuation coefficient, and α=2-b; b is the ratio of radial stress to tangential stress, and b=μ/(1-μ), P 2 is the shock wave stress without coupling charge coefficient peak, and r b is the borehole radius, S T is the uniaxial tensile strength of the rock, μ is the Poisson’s ratio, ρ 0 is the explosive density, D is the explosion velocity, rc is the charge radius; n is the stress increase multiple, take 8-11.
进一步优选的是,在爆破的钻孔中安装聚能管,聚能方向与巷道的走向平行。It is further preferred that an energy collecting pipe is installed in the blasted borehole, and the energy collecting direction is parallel to the direction of the roadway.
进一步优选的是,在所述数值模拟中具体是利用UDEC模拟所述深井小煤柱沿空留巷中顶板下位关键层断顶卸压,或者利用FLAC3D模拟所述深井小煤柱沿空留巷中顶板下位关键层断顶卸压。It is further preferred that, in the numerical simulation, UDEC is used to simulate the pressure relief of the key layer under the roof in the gob-side entry retention of the small coal pillar in the deep well, or FLAC3D is used to simulate the gob-side entry retention of the small coal pillar in the deep well. The key layer in the lower part of the mid-roof plate is fractured and the roof is relieved.
进一步优选的是,选取围岩变形量最小值和巷道应力分布最小值对应的断顶参数。It is further preferred that the top fault parameters corresponding to the minimum value of the deformation of the surrounding rock and the minimum value of the stress distribution of the roadway are selected.
进一步优选的是,所述支护参数包括锚杆长度、锚索长度、锚杆间排距和锚索间排距。Further preferably, the support parameters include the length of the anchor rod, the length of the anchor cable, the row spacing between the anchor rods and the row spacing between the anchor cables.
本发明提供的基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法有益效果是:The beneficial effects of the gob-side entry retaining method for small coal pillars in deep wells based on the pressure relief of fault roofs in key layers below the roof provided by the present invention are:
(1)通过提前切断“传递岩梁”的煤层顶板下位关键层,有效的将作用在小煤柱和沿空留巷上的高应力转移到更远处的煤岩层上,使得小煤柱和沿空留巷受到较低的应力作用和采动动压影响,有利于小煤柱的承载稳定性,大大降低了沿空留巷的支护难度。(1) By cutting off the key layer below the coal seam roof of the "transfer rock beam" in advance, the high stress acting on the small coal pillar and gob-side entry retaining is effectively transferred to the coal layer farther away, so that the small coal pillar and Gob-side entry retention is affected by lower stress and mining dynamic pressure, which is beneficial to the bearing stability of small coal pillars and greatly reduces the support difficulty of gob-side entry retention.
(2)小煤柱的稳定不仅可以隔离上一工作面采空区有害气体,还具有挡矸和挡水的作用;此外留设小煤柱解决了深部开采中采掘接续紧张的问题,能够保证矿井高效生产,并且避免了留设大煤柱,保证了采出率;(2) The stability of the small coal pillar can not only isolate the harmful gas in the goaf of the previous working face, but also have the function of retaining gangue and water; The mine is produced efficiently, and large coal pillars are avoided to ensure the recovery rate;
(3)利用数值模拟选择合适的断顶爆破参数,并且还在试验巷道内对支护的效果进行监测,通过分析确定合理的支护参数,保证沿空留巷的巷道安全;另外该方法还通过施工爆破断顶,并设置钻孔参数和炸药参数确保下位关键层断顶卸压的效果;避免应力集中,控制巷道变形量,保证通风安全。(3) Use numerical simulation to select appropriate blasting parameters for roof breaking, and monitor the effect of support in the test roadway, and determine reasonable support parameters through analysis to ensure the roadway safety of gob-side entry retention; in addition, this method also The roof is broken by construction blasting, and drilling parameters and explosive parameters are set to ensure the effect of pressure relief on the lower key layer; avoid stress concentration, control the deformation of the roadway, and ensure ventilation safety.
附图说明Description of drawings
图1是深井小煤柱沿空留巷布置示意图;Fig. 1 is the schematic diagram of gob-side entry retaining arrangement of small coal pillars in deep wells;
图2是工作面开采后沿空留巷示意图;Fig. 2 is the schematic diagram of gob-side entry retaining after the working face is mined;
图3是向实体煤一侧的侧向视图;Figure 3 is a side view towards the solid coal side;
图4是下位关键层断顶卸压前的应力分布示意图;Figure 4 is a schematic diagram of the stress distribution before the pressure relief of the lower key layer fault top;
图5是下位关键层断顶卸压后的应力分布示意图;Figure 5 is a schematic diagram of the stress distribution of the lower key layer after the fault top is relieved;
图6是爆破区域划分示意图;Fig. 6 is a schematic diagram of blasting area division;
图7是试验巷道内监测示意图;Figure 7 is a schematic diagram of monitoring in the test roadway;
图8是断顶卸压前后的顶板下沉量曲线图;Figure 8 is a graph of the subsidence amount of the roof before and after breaking the roof and releasing pressure;
图9是断顶卸压前后的实体煤侧巷帮移近量曲线图;Fig. 9 is a curve diagram of the approaching amount of the solid coal side roadway before and after the roof breaking and pressure relief;
图10是断顶卸压前后的煤柱侧的巷帮移近量曲线图;Fig. 10 is a curve diagram of the approaching amount of the roadway on the side of the coal pillar before and after the roof is broken and the pressure is relieved;
图11是断顶卸压前后的锚杆工作阻力变化图;Fig. 11 is the change diagram of the working resistance of the bolt before and after the top is broken and the pressure is relieved;
图12是测站工作面距离和顶板锚杆工作阻力的曲线图。Figure 12 is a graph of the distance between the working face of the station and the working resistance of the roof bolt.
图中:1-上位关键层,2-砂泥岩,3-下位关键层,4-直接顶,5-待采面,6-沿空留巷,7-采煤工作面回风巷,8-采煤工作面,9-预设钻孔,10-预裂切缝,11-小煤柱;12-锚杆受力监测,13-锚索受力监测。In the picture: 1-upper key layer, 2-sand mudstone, 3-lower key layer, 4-direct roof, 5-face to be mined, 6-gob retaining entry, 7-return airway at coal mining face, 8- Coal working face, 9-preset drilling, 10-pre-splitting slit, 11-small coal pillar; 12-bolt force monitoring, 13-anchor cable force monitoring.
具体实施方式Detailed ways
结合图1至图12所示,对本发明提供的基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法的具体实施方式进行说明。With reference to FIGS. 1 to 12 , the specific implementation of the method for gob-side entry retaining for small coal pillars in deep wells based on the pressure relief of the key layer under the roof provided by the present invention will be described.
实施例1Example 1
由于深井厚煤层特别是高瓦斯矿井,存在回采巷道通风困难以及采掘接续紧张的难题,须采用沿空留巷回采巷道布置方式,但是深井沿空留巷受地应力高、二次采动动压影响,小煤柱需要承受很高的支承压力和采动压力,小煤柱难以保持稳定。另外在小煤柱沿空留巷开采过程中,施工断顶卸压的参数以及支护参数难以确定,为此提供一种基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法,具体的步骤包括:Due to the deep coal seam in deep mines, especially in high gas mines, there are problems such as difficulty in ventilation of mining tunnels and tight mining continuity, so gob-side entry retention must be adopted. Influence, small coal pillars need to bear high bearing pressure and mining pressure, and it is difficult for small coal pillars to maintain stability. In addition, in the process of gob-side entry retaining of small coal pillars, the parameters of construction breaking roof pressure relief and support parameters are difficult to determine. Therefore, a deep well small coal pillar gob-side entry retaining method based on roof pressure relief of key layers under the roof is provided. method, the specific steps include:
步骤A.确定煤层顶板的地质条件;其中顶板的地质条件包括顶板岩性和顶板厚度,还包括顶板的节理构造、胶结程度、构造发育(断层、褶曲等)和稳定性等,可以根据矿山工程测量和矿井地质勘探数据等确定,也可以在工作面位置实际勘探。Step A. Determine the geological conditions of the roof of the coal seam; wherein the geological conditions of the roof include roof lithology and roof thickness, and also include the joint structure, degree of cementation, structural development (faults, folds, etc.) and stability of the roof. The measurement and mine geological exploration data are determined, and the actual exploration can also be performed at the working face position.
步骤B.根据煤层顶板地质条件,通过理论计算确定爆破的断顶参数,爆破的断顶参数包括下位关键层断顶的位置和厚度,下位关键层传递来自上覆岩层的应力。Step B. According to the geological conditions of the coal seam roof, theoretical calculation is used to determine the parameters of the fault roof for blasting. The fault roof parameters for blasting include the position and thickness of the fault roof of the lower key layer, and the lower key layer transmits the stress from the overlying rock layer.
一般深部矿井的煤层埋深大于600m,受到高地应力的影响;其中下位关键层为直接顶上方距直接顶最近,并且厚度较大、岩石坚硬,能够传递上覆岩层应力的岩层;如图1和图2所示,在泥砂岩之上的第一个坚硬岩层为下位关键层,上位关键层在下位关键层之上。根据“传递岩梁”理论,直接顶不能传递应力。Generally, the buried depth of coal seams in deep mines is more than 600m, which is affected by high in-situ stress; among them, the lower key layer is the rock layer that is closest to the direct roof above the direct roof, has large thickness and hard rock, and can transmit the stress of the overlying layer; as shown in Figure 1 and As shown in Figure 2, the first hard rock layer above the mudstone is the lower key layer, and the upper key layer is above the lower key layer. According to the theory of "transfer rock beam", the direct roof cannot transfer stress.
步骤C.数值模拟断顶厚度与断顶卸压后围岩变形量和巷道围岩应力之间的关系。在数值模拟中具体是利用UDEC(Universal Distinct Element Code,基于离散单元法理论的计算分析程序)模拟深井小煤柱沿空留巷中顶板下位关键层断顶卸压,结合开采设计参数确定工作面参数和巷道参数,确定断顶的厚度和位置,然后利用软件模拟断顶厚度与断顶卸压后围岩变形量和巷道围岩应力之间的关系;或者利用FLAC3D(三维有限差分程序,进行三维结构受力特性模拟和塑性流动分析)模拟深井小煤柱沿空留巷中顶板下位关键层断顶卸压,结合开采设计参数确定工作面参数和巷道参数,确定断顶的厚度和位置,然后利用软件模拟断顶厚度与断顶卸压后围岩变形量和巷道围岩应力之间的关系。Step C. Numerically simulate the relationship between the thickness of the fault roof, the deformation of the surrounding rock after the pressure relief of the fault roof, and the surrounding rock stress of the roadway. In the numerical simulation, UDEC (Universal Distinct Element Code, a calculation and analysis program based on the discrete element method theory) is used to simulate the pressure relief of the key layer under the roof in the middle roof of the gob-side entry retaining of small coal pillars in deep wells, and the working face is determined according to the mining design parameters. parameters and roadway parameters, determine the thickness and position of the top of the fault, and then use the software to simulate the relationship between the thickness of the top of the fault and the deformation of the surrounding rock and the stress of the roadway after the pressure relief of the top of the fault; or use FLAC3D (three-dimensional finite difference program to carry out Three-dimensional structural stress characteristics simulation and plastic flow analysis) simulation of small coal pillar gob-side entry retention in deep wells for the pressure relief of the key layer under the roof of the roof, combined with the mining design parameters to determine the working face parameters and roadway parameters, determine the thickness and location of the fault roof, Then the software is used to simulate the relationship between the thickness of the fault roof, the deformation of the surrounding rock after the pressure relief of the fault roof and the surrounding rock stress of the roadway.
步骤D.根据围岩变形量和巷道应力分布确定巷道的断顶参数。具体是选取围岩变形量最小值和巷道应力分布最小值对应的断顶参数。Step D. Determine the parameters of the broken roof of the roadway according to the deformation amount of the surrounding rock and the stress distribution of the roadway. Specifically, the fault roof parameters corresponding to the minimum value of the deformation of the surrounding rock and the minimum value of the stress distribution of the roadway are selected.
其中其中断顶参数包括钻孔参数和炸药参数,钻孔参数包括钻孔超前工作面的距离(钻孔的位置)、钻孔直径、钻孔角度、钻孔深度和钻孔间距等,炸药参数包括爆破半径、装药量、封口方式和封口长度等。Among them, its top parameters include drilling parameters and explosive parameters. The drilling parameters include the distance of the drilling ahead of the working surface (the position of the drilling), the diameter of the drilling, the angle of drilling, the depth of the drilling and the spacing between the drillings, etc., and the parameters of the explosive Including blasting radius, charge amount, sealing method and sealing length, etc.
钻孔参数中钻孔与实体煤一侧巷帮距离大于200mm,爆破用的钻孔在首采工作面的回风巷道(沿空留巷)顶板布置,并且偏向实体煤一侧;钻孔直径取48-50mm;钻孔在巷道顶板上倾斜向上布置,薄煤层中钻孔倾角为20°,中厚煤层或厚煤层中钻孔倾角为10°-15°;钻孔深度大于下位关键层的厚度,从而保证爆破后能够切断下位关键层;硬岩中钻孔的间距取500mm,软岩中钻孔间距取1000mm。In the drilling parameters, the distance between the drilled hole and the roadway on the side of the solid coal is greater than 200mm, and the drill hole for blasting is arranged on the roof of the return air roadway (gob-side entry) in the first mining face, and is biased to the side of the solid coal; the diameter of the drill hole is Take 48-50mm; drill holes are arranged obliquely upward on the roof of the roadway, the inclination angle of the drill holes in the thin coal seam is 20°, and the inclination angle of the drill holes in the medium-thick coal seam or thick coal seam is 10°-15°; the drill hole depth is greater than that of the lower key layer. Thickness, so as to ensure that the lower key layer can be cut off after blasting; the spacing of drilling holes in hard rock is 500mm, and the spacing between drilling holes in soft rock is 1000mm.
炸药的爆破参数中,以钻孔为中心钻孔半径为R0,粉碎区的半径为R1,破裂区的半径为R2,震动区的半径为R3,其中破裂区的半径为爆破半径;爆破中药卷装药至下位关键层的位置。爆破半径R2的取值为:In the blasting parameters of the explosive, the radius of the drill hole is R 0 , the radius of the crushing area is R 1 , the radius of the rupture area is R 2 , the radius of the vibration area is R 3 , and the radius of the rupture area is the blasting radius. ; Blasting the traditional Chinese medicine roll to the position of the lower key layer. The value of the blast radius R 2 is:
其中α为应力波衰减系数,且α=2-b;b为径向应力与切向应力的比值,且b=μ/(1-μ),P2为不耦合装药系数下的冲击波应力峰值,且rb为钻孔半径,ST为岩石的单轴抗拉强度,μ为泊松比,ρ0为炸药密度,D为爆炸速度,rc为装药半径;n为应力增大倍数,取8-11。where α is the stress wave attenuation coefficient, and α=2-b; b is the ratio of radial stress to tangential stress, and b=μ/(1-μ), P 2 is the shock wave stress without coupling charge coefficient peak, and r b is the borehole radius, S T is the uniaxial tensile strength of the rock, μ is the Poisson’s ratio, ρ 0 is the explosive density, D is the explosion velocity, rc is the charge radius; n is the stress increase multiple, take 8-11.
另外,通过预设钻孔并进行钻孔爆破可以实现预裂,还可以在爆破的钻孔中安装聚能管,聚能方向与巷道的走向平行,从而可以更好的形成切缝,实现对下位关键层的致裂。In addition, pre-splitting can be achieved by pre-drilling and drilling and blasting, and energy-gathering pipes can also be installed in the blasting holes, and the direction of energy-concentration is parallel to the direction of the roadway, so that the slit can be better formed and the lower position can be realized. Cracking of critical layers.
步骤E.按照断顶参数在试验巷道内施工爆破,试验段巷道是选取的沿空留巷的采煤工作面60m长度左右的巷道进行试验,并在试验巷道内的围岩布置位移监测站、锚杆和锚索受力监测站,通过监测站确定巷道在当前支护下的巷道表面位移曲线、锚杆受力监测曲线和锚索受力监测曲线。Step E. Carry out blasting in the test roadway according to the parameters of the broken roof. The roadway in the test section is the roadway with a length of about 60m in the coal mining face of the gob-retained roadway for testing, and the surrounding rock in the test roadway is arranged with displacement monitoring stations, Bolt and anchor cable force monitoring station, through the monitoring station to determine the roadway surface displacement curve, bolt force monitoring curve and anchor cable force monitoring curve under the current support.
步骤F.根据试验巷道表面位移曲线、锚杆受力监测曲线和锚索受力监测曲线修正支护参数。支护参数包括锚杆长度、锚索长度、锚杆间排距和锚索间排距,当巷道表面位移过大是需要调整支护参数,加强支护;保证锚杆受力和锚索受力在设定的有效支护范围之内。Step F. Amend the support parameters according to the test roadway surface displacement curve, the anchor force monitoring curve and the anchor cable force monitoring curve. The support parameters include the length of the anchor rod, the length of the anchor cable, the row spacing between the anchor rods and the row spacing between the anchor cables. When the surface displacement of the roadway is too large, it is necessary to adjust the support parameters and strengthen the support; The force is within the set effective support range.
步骤G.继续开采,在沿空留巷的巷道内施工爆破断顶,并按照修正后的支护参数对沿空留巷的巷道进行支护。Step G. Continue mining, construct blasting and break the roof in the roadway of the gob-side entry retention, and support the gob-side entry-retention roadway according to the revised support parameters.
实施例2Example 2
在实施例1的基础上,以某矿采取基于顶板下位关键层断顶卸压的深井小煤柱沿空留巷方法的工作面为例,通过监测情况对本方法的支护效果做进一步的说明。On the basis of Example 1, taking the working face of a mine adopting the method of gob-side entry retaining in deep wells with small coal pillars based on the pressure relief of the key layer under the roof as an example, the support effect of this method is further explained by monitoring the situation. .
结合图7至图10所示,对比断顶卸压前后的顶板下沉量、实体煤侧巷帮移近量、巷帮移近量和锚杆工作阻力变化情况可见,通过提前切断“传递岩梁”的煤层顶板下位关键层,有效的将作用在小煤柱和沿空留巷上的高应力转移到更远处的煤岩层上,使得小煤柱和沿空留巷受到较低的应力作用和采动动压影响,从而有利于小煤柱的承载稳定性,大大降低了沿空留巷的支护难度;另外小煤柱的稳定不仅可以隔离上一工作面采空区有害气体,还具有挡矸和挡水的作用;此外留设小煤柱解决了深部开采中采掘接续紧张的问题,能够保证矿井高效生产,并且避免了留设大煤柱,保证了采出率;该方法还可以有效的避免应力集中,控制巷道变形量,保证通风安全。在工作面开始推进后,超前支承压力及侧向支承压力集中区由基本顶上覆未断裂岩层(上位关键层)向下一工作面中心位置处转移,沿空留巷位置处应力较小;该方法可以有效的转移沿空留巷位置处的应力集中区,沿空留巷变形量小。Combining with Fig. 7 to Fig. 10, comparing the roof subsidence amount, the moving amount of solid coal side roadway, the moving amount of roadway and the working resistance of the bolt before and after the pressure relief of the broken roof can be seen. The key layer under the roof of the coal seam with "beam" effectively transfers the high stress acting on the small coal pillars and gob-side entry retention to the coal strata farther away, so that the small coal pillars and gob-side entry retention are subject to lower stress. Therefore, it is beneficial to the bearing stability of the small coal pillar and greatly reduces the support difficulty of gob-side entry retaining; in addition, the stability of the small coal pillar can not only isolate the harmful gas in the gob of the previous working face, but also It also has the functions of retaining gangue and water; in addition, leaving small coal pillars solves the problem of tight mining continuity in deep mining, which can ensure efficient mine production, and avoid leaving large coal pillars to ensure recovery rate; this method It can also effectively avoid stress concentration, control the deformation of the roadway, and ensure ventilation safety. After the working face starts to advance, the concentration area of the leading bearing pressure and the lateral bearing pressure is transferred from the unfractured rock layer (upper key layer) overlying the basic top to the center of the next working face, and the stress at the gob-side entry retaining position is relatively small; This method can effectively transfer the stress concentration area at the position of gob-side entry retention, and the deformation of gob-side entry retention is small.
当然,上述说明并非是对本发明的限制,本发明也并不仅限于上述举例,本技术领域的技术人员在本发明的实质范围内所做出的变化、改型、添加或替换,也应属于本发明的保护范围。Of course, the above description is not intended to limit the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by those skilled in the art within the essential scope of the present invention should also belong to the present invention. the scope of protection of the invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011106611.6A CN112377193B (en) | 2020-10-16 | 2020-10-16 | Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011106611.6A CN112377193B (en) | 2020-10-16 | 2020-10-16 | Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112377193A CN112377193A (en) | 2021-02-19 |
CN112377193B true CN112377193B (en) | 2022-05-31 |
Family
ID=74581581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011106611.6A Expired - Fee Related CN112377193B (en) | 2020-10-16 | 2020-10-16 | Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112377193B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113062747B (en) * | 2021-03-19 | 2024-08-30 | 重庆交通大学 | Multifunctional construction trolley and hydraulic blasting method for soft and hard alternate complex layered stratum tunnel |
CN112922598B (en) * | 2021-03-23 | 2024-11-22 | 中矿科创(北京)煤炭技术有限公司 | A method for reducing roof pressure in gob-side tunneling by removing pressure from the roof |
CN114577078A (en) * | 2022-01-26 | 2022-06-03 | 安徽理工大学 | Positive fault blasting method for fully mechanized excavation face through hard rock |
CN114575844B (en) * | 2022-02-25 | 2025-03-14 | 天地科技股份有限公司 | Sectional pressure relief and reinforcement control method of tunnel roof based on double tunneling |
CN114858019B (en) * | 2022-06-24 | 2023-10-20 | 贵州盘江精煤股份有限公司 | Roof cutting blasting method for transportation lane |
CN115234287A (en) * | 2022-07-13 | 2022-10-25 | 安徽理工大学 | A method for pressure relief and permeability enhancement of soft coal seam roof by building energy blasting in reverse fault structure area |
CN115434706A (en) * | 2022-08-08 | 2022-12-06 | 平顶山天安煤业股份有限公司六矿 | Mining method for changing large coal pillar working face into small coal pillar working face |
CN117145475B (en) * | 2023-09-12 | 2024-10-01 | 云南滇东雨汪能源有限公司 | Gob-side entry retaining roof cutting pressure relief method and bracket |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101713290A (en) * | 2009-12-10 | 2010-05-26 | 天地科技股份有限公司 | Method for clearing rock burst of full-mine laneway deep in mine |
CN101881167A (en) * | 2010-06-04 | 2010-11-10 | 山东华恒矿业有限公司 | Coal face stump mining method |
CN104763425A (en) * | 2015-02-03 | 2015-07-08 | 杨洪兴 | Pressure relief presplitting blasting gob-side entry retaining pillar-free mining method |
-
2020
- 2020-10-16 CN CN202011106611.6A patent/CN112377193B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101713290A (en) * | 2009-12-10 | 2010-05-26 | 天地科技股份有限公司 | Method for clearing rock burst of full-mine laneway deep in mine |
CN101881167A (en) * | 2010-06-04 | 2010-11-10 | 山东华恒矿业有限公司 | Coal face stump mining method |
CN104763425A (en) * | 2015-02-03 | 2015-07-08 | 杨洪兴 | Pressure relief presplitting blasting gob-side entry retaining pillar-free mining method |
Also Published As
Publication number | Publication date |
---|---|
CN112377193A (en) | 2021-02-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112377193B (en) | Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate | |
Wang et al. | Safe strategy for coal and gas outburst prevention in deep-and-thick coal seams using a soft rock protective layer mining | |
CN113914862B (en) | Roof-cutting pressure-relief coal-pillar-free self-entry mining design and evaluation method | |
Zhang et al. | Fixed-length roof cutting with vertical hydraulic fracture based on the stress shadow effect: A case study | |
Yang et al. | Study on presplitting blasting the roof strata of adjacent roadway to control roadway deformation | |
CN112780340B (en) | Method for preventing rock burst in advance in underground coal mine area | |
Fan et al. | An innovative approach for gob‐side entry retaining in deep coal mines: a case study | |
Huang et al. | Hydraulic fracturing stress transfer methods to control the strong strata behaviours in gob-side gateroads of longwall mines | |
CN112922598A (en) | Method for reducing gob-side entry driving roof pressure through roof cutting and pressure relief | |
CN116771348A (en) | A method to reduce the impact of dynamic pressure in the main roadway at the end of mining and optimize coal pillars in the stop-mining line | |
Shen et al. | Research on novel method of gob-side entry retaining under the synergistic effect of roof cutting and roadside filling in thick coal seams | |
Li et al. | Trial of small gateroad pillar in top coal caving longwall mining of large mining height | |
Yang et al. | Research on the technology of small coal pillars of gob‐side entry retained in deep mines based on the roof cutting for pressure unloading in the lower key stratum | |
Huang et al. | Parameter determination and effect evaluation of gob-side entry retaining by directional roof cutting and pressure releasing | |
CN118030107A (en) | Multistage pressure relief constant-resistance energy release coupling supporting method and system for strong dynamic pressure gob-side entry | |
Zheng et al. | Analysis of hydro-fracturing technique using ultra-deep boreholes for coal mining with hard roofs: a case study | |
CN105911606B (en) | A kind of mining overburden characteristics of motion in-situ observation drilling method for arranging | |
CN111238329A (en) | Method for performing geometric forming blasting on semi-coal rock roadway by adopting instantaneous bursting device | |
CN114575846A (en) | Goaf roof caving and crushing expansion control device and method | |
Yu et al. | Innovative Control Technique for the Floor Heave in Goaf‐Side Entry Retaining Based on Pressure Relief by Roof Cutting | |
Konicek | Destressing | |
Zhai et al. | Strong strata behavior mechanism and roof cutting control of small pillar gob-side roadway in extra-thick coal seam | |
CN111677514B (en) | Roof weakening method | |
Wang et al. | Numerical investigation into evolution of crack and stress in residual coal pillars under the influence of longwall mining of the adjacent underlying coal seam | |
CN117703493A (en) | Deep coal-based stratum co-associated resource, coal and gas co-mining method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220531 |
|
CF01 | Termination of patent right due to non-payment of annual fee |