Disclosure of Invention
In order to overcome the defects of the existing waste mine plugging method in the background technology, the invention provides a waste mine acidic wastewater pollution blocking method.
The invention solves the technical problems by adopting the technical scheme that the method for blocking the pollution of the acidic wastewater of the abandoned mine adopts a construction method of mine cave body pressure grouting, anti-corrosion and anti-seepage blocking layer, anti-seepage concrete section support, clay wall water stop, concrete wellhead plugging backfill and in-hole top supplementary grouting to block the pollution of the water burst of the abandoned mine, and the pollution blocking method specifically comprises the following steps:
A. removing sludge in the cavity, namely removing ground sludge, residues and loose surrounding rocks in the abandoned mine, cleaning the ground sludge, residues and loose surrounding rocks to the fresh bedrock surface of the primary stratum of the footrill, and cleaning the rock wall in the cavity by adopting a high-pressure water gun after cleaning;
B. The anti-corrosion and anti-seepage barrier layer is that a brick blank wall is built in a mine to form a water retaining wall, a through water guide pipe is preset at the bottom of the water retaining wall to extend out of a wellhead, and the water guide pipe is used for guiding out water gushing in the well in the plugging construction process;
C. Grouting, solidifying and impervious the underground body, namely pumping the top wall and the side wall in the mine outside the water retaining wall into a rigid grouting pipe, performing pressure grouting, penetrating, diffusing, filling and compacting the grouting liquid in the rock stratum, penetrating and driving away water and air in loose particles among rock stratum cracks, filling the positions among the loose particles, solidifying the grouting liquid, and cementing the rock cracks and the loose soil particles among the original cracks into a whole to form a tunnel wall grouting section in the well;
D. C, pouring anti-corrosion and anti-seepage concrete in a grouting section of the wall of the well, reinforcing and supporting the cured wall of the grouting section of the wall of the well to form a reinforced integral blocking anti-seepage structure, and presetting a supplementary grouting pipe extending out of a wellhead of the well at the highest position of the top of the grouting section of the wall of the well before pouring;
E. d, filling clay, namely filling clay outside the grouting section of the hole wall in the step D to form a clay water-proof section, carrying out interval grooving on the hole wall before filling the clay, manually layering, filling and compacting the clay, and building a brick blank to form a clay sealing wall after the clay water-proof section is completed;
F. the method comprises the steps of plugging a concrete wellhead, pouring concrete after closing a mould outside a clay sealing wall of a clay water-proof section to form a concrete plugging section, and embedding a supplementary grouting pipe at the highest position of a hole top of the concrete plugging section before pouring and extending out of the mine wellhead;
G. After the strength of the concrete poured in the concrete plugging section reaches 75%, grouting material is filled in a gap between the grouting section of the hole wall in the hole and the top of the concrete plugging section outside the well through a preset supplementary grouting pipe, and a gap at the top of the hole formed by gravity sinking of the poured concrete is filled and sealed;
H. And C, injecting concrete outside the well plugging section, namely injecting fine stone concrete from the tail end of the concrete plugging section to the surface of the slag backfill area of the mine wellhead section area in the step F after the step G is completed, and preventing the surface water seeping into the cracks of the top of the hole from entering slag and mixing to form polluted wastewater.
In the step B, an emergency gate valve, a pressure gauge and a water quality detector are arranged at the water outlet end of the water guide pipe outside the mine mouth. After the mine is plugged, the water quality and the water level change condition in the mine after plugging can be monitored in real time through a pressure gauge and a water quality detector which are arranged on a water guide pipe outside a wellhead, and when the abnormal rise of the water level in a hole to a high water level which possibly causes environmental pollution or potential safety hazards such as secondary geological disasters and the like is monitored, the water level rise is controlled by opening an emergency gate valve for draining, so that precious time is strived for taking emergency disposal measures.
Further, in the step C, the grouting amount of the rigid grouting pipe is determined according to the following calculation formula:
grouting quantity of single rigid grouting pipe, Q is more than or equal to pi R 2 L n alpha beta
Wherein, Q is the grouting amount (m 3) of a single rigid grouting pipe, R is the diffusion radius (m), L is the grouting length of the rigid grouting pipe=the design length of the rigid grouting pipe-1 (m), n is the formation void ratio, alpha is the formation filling coefficient, and beta is the slurry consumption coefficient;
The hole wall grouting section is arranged according to a crack area of geotechnical engineering investigation, and can be used for realizing that grouting liquid fully permeates, diffuses, fills and compacts in the cracks of the rock stratum, so that the cracks and original loose soil particles are glued into a whole, the cracks are completely sealed, and water seepage of the cracks is blocked.
In the step C, the grouting pressure of the rigid grouting pipe is not less than 0.6Mpa, so that grouting liquid is fully permeated, diffused, filled and compacted in the rock stratum, and a radial blocking sector is formed.
Further, in the step C, the rigid grouting pipes are uniformly arranged and respectively inclined to the inside and outside of the mine hole. The rigid grouting pipe far away from the wellhead area is inclined towards the inside of the hole, the wall grouting formed by the rigid grouting pipe forms a conical blocking sector for water burst to be blocked, the rigid grouting pipe close to the wellhead area is inclined towards the outside of the hole, meanwhile, a strong shearing support is formed, and the rigid grouting pipe and the wall grouting section are cast with concrete to form higher integral structural strength, so that the optimal water blocking and seepage resisting effects are achieved.
Further, in the step E, the length of the clay water-blocking section is determined according to the following calculation formula:
L1≥P*KS*K/(A*γ*Q)
Wherein in the formula, L1 is the length (m) of a clay water-proof section, P is the water pressure (Kpa) near a water-gushing wellhead, A is the cross-section area (m 2),KS is the clay permeability coefficient (cm/s), gamma is the clay gravity (t/m 3), Q is the water-gushing wellhead water-gushing quantity (m 3/d), and K is the safety coefficient.
In step E, the clay is fully mixed after being added with water before filling, and the clay is manually filled in layers, so that the clay is compacted during filling, the compaction coefficient is not less than 0.85, and a good water blocking and seepage resisting effect is realized.
Further, in the step F, the length of the concrete plugging section is determined according to the following calculation formula:
L≥P*A*K/(C*frb)
Wherein in the formula, L is the length (m) of a concrete plugging section, P is the water pressure (Kpa) near a water gushing wellhead, A is the section area (m 2) of the water gushing wellhead, K is the safety coefficient, C is the section perimeter (m) of the water gushing wellhead, and Frb is the characteristic value (Kpa) of the bonding strength of a cave wall and concrete.
Further, in the step D and the step G, the supplementary grouting pipe is composed of a slurry pipe and an exhaust pipe, the slurry pipe is used for grouting slurry, the exhaust pipe is used for exhausting air in a hole top gap during grouting, casting hollows are avoided, and the grouting slurry adopts expansion cement with a water-cement ratio of 1:1.
In the step B, the water facing surface on the inner side of the water retaining wall is plastered by impermeable cement mortar, and the plastering thickness is 10mm, so that the impermeable effect is further enhanced.
In the step B, the water guide pipe is a stainless steel seamless pipe, the corrosion resistance of the stainless steel pipe is good, the longer service life of the water guide pipe can be guaranteed, the water guide pipe which is preset to be communicated at the bottom of the water retaining wall in the step B is 150mm higher than the footline of the footrill, the pipe diameter of the water guide pipe is larger than 60mm, the water guide pipe can be prevented from being blocked by sediments, and meanwhile, the water burst can be timely discharged in the blocking construction process.
And D, the concrete poured in the grouting section of the cavity wall is seepage-proofing and corrosion-resisting micro-expansion concrete, so that the seepage-proofing effect is enhanced, and the concrete poured in the concrete plugging section in the step F is common concrete, so that the structural strength of the concrete plugging section is ensured.
The method has the advantages that the method is innovated based on the existing concrete plugging, the pressure grouting is adopted to form a radial blocking sector for water burst in the hole, the optimal water blocking and seepage resisting effects are achieved, concrete is poured in the grouting section of the wall of the well, the solidified wall of the grouting section of the wall of the well is reinforced and supported to form the integral seepage resisting effect, and the integral plugging structure strength of the grouting section of the wall of the well is enhanced.
Meanwhile, a supplementary grouting pipe is arranged at the top of the hole wall, grouting is conducted in a top gap between the grouting section of the hole wall and the concrete plugging section through the preset supplementary grouting pipe outside the well, and a hole top gap formed by gravity sinking of poured concrete is filled and sealed.
Spraying and pouring fine stone concrete on the outer wall of the plugged wellhead and the ground surface through the out-of-well sprayed concrete to prevent pollution caused by mixing of surface water and mine water.
After the plugging is completed, the water pressure of water gushing in the well after the plugging is monitored by a pressure gauge on the water guide pipe outside the well mouth. The water inflow condition in the well can be monitored for a long time outside the well mouth, and the water quality change in the well after the plugging is monitored in real time through a water quality detector on a water guide pipe outside the well mouth.
The technical scheme of the invention is safe, reliable, efficient and quick, accords with the relevant national technical specifications, greatly improves the sealing performance and the firmness of the blocking of the mine water burst, has high safety and reliability, and greatly eliminates the environmental pollution risk of the abandoned mine water burst.
Detailed Description
The invention is further illustrated, but not limited, by the following figures and examples, any technical solution based on transformation or reasoning of the invention falling within the scope of protection of the invention.
Example 1
As shown in fig. 1-9, the blocking method is used for blocking the water burst pollution of the abandoned mine by adopting the construction methods of mine cave pressure grouting, anti-corrosion and anti-seepage blocking layer, anti-seepage concrete section support, clay wall water stopping, concrete wellhead blocking backfill and in-hole top supplementary grouting, and the blocking method specifically comprises the following steps:
A. removing sludge in the cavity, namely removing ground sludge, residues and loose surrounding rocks in the abandoned mine, cleaning the ground sludge, residues and loose surrounding rocks to the fresh bedrock surface of the primary stratum of the footrill, and cleaning the rock wall in the cavity by adopting a high-pressure water gun after cleaning;
B. An anti-corrosion and anti-seepage barrier layer is formed by building a brick blank wall in a mine to form a water retaining wall 1, a through water guide pipe 11 is preset at the bottom of the water retaining wall 1 to extend out of a wellhead, and the water guide pipe 11 is used for guiding out water gushing in the well in the plugging construction process;
C. Grouting, solidifying and impervious the underground body, namely, injecting the top wall and the side wall in the mine outside the water retaining wall 1 into a rigid grouting pipe 21, then performing pressure grouting, penetrating, diffusing, filling and compacting the grouting liquid in the rock stratum, filling the space between the loose particles among the rock stratum cracks after penetrating and driving away the water and the air in the loose particles, and after solidifying the grouting liquid, cementing the loose soil particles among the original cracks into a whole to form a tunnel wall grouting section 2 in the well;
The grouting amount of the rigid grouting pipe 21 is determined according to the following calculation formula:
Grouting quantity of single rigid grouting pipe 21, Q is more than or equal to pi R 2 Ln alpha beta
Wherein, Q is the grouting amount (m 3) of the single rigid grouting pipe 21, R is the diffusion radius (m), L is the grouting length of the rigid grouting pipe 21=the design length-1 (m) of the rigid grouting pipe 21, n is the formation void ratio, alpha is the formation filling coefficient, and beta is the slurry consumption coefficient;
The design length of the rigid grouting pipe 21 of the gateway coal mine No. 2 mine is 4m, the diffusion radius R is 0.3m, the formation void ratio n of the cavity wall is 0.4, the formation filling coefficient alpha is 0.8, the slurry consumption coefficient beta is 1.1, and the grouting amount of the single rigid grouting pipe 21 brought into the cavity wall grouting section 2 of the gateway coal mine No. 2 mine is calculated to be not less than 0.298 m 3.
The wall grouting section 2 is arranged according to a fracture area of a mine for geotechnical engineering investigation, and the grouting pressure of the rigid grouting pipe 21 is not less than 0.6Mpa. The grouting liquid is fully permeated, diffused, filled and compacted in the rock stratum fracture area, and the rock gaps and the original loose soil grains are glued into a whole.
D. c, pouring anti-corrosion and anti-seepage concrete in the grouting section 2 of the wall of the well, reinforcing and supporting the cured wall of the grouting section 2 of the wall of the well to form a reinforced integral blocking and anti-seepage structure, and presetting a supplementary grouting pipe 22 extending out of the wellhead of the well at the highest position of the top of the grouting section 2 of the wall of the well before pouring;
E. D, clay filling, namely filling clay outside the hole wall grouting section 2 in the step D to form a clay water-proof section 3, carrying out interval grooving 31 on the hole wall before clay filling, manually layering, filling and compacting the clay, and building green bricks to form a clay sealing wall 32 after the clay water-proof section 3 is completed;
the length of the clay water-proof section 3 is determined according to the following calculation formula:
L1≥P*KS*K/(A*γ*Q)
Wherein in the formula, L1 is the length (m) of the clay water-proof section 3, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-section area (m 2),KS is the clay permeability coefficient (cm/s), gamma is the clay gravity (t/m 3), Q is the water-gushing wellhead water-gushing quantity (m 3/d), K is the safety coefficient;
The water pressure P near the 2# wellhead of the gateway coal mine is 4700 Kpa, the section area A of the water inflow wellhead is 7.8 m 2, the clay permeability coefficient K s is 5 multiplied by 10 -5 cm/s, the clay gravity gamma is 1.7 t/m 3, the water inflow Q of the water inflow wellhead is 100 m 3/d, the safety coefficient K is 2, and the length L1 of the clay water-proof section 3 of the 2# wellhead of the gateway coal mine is calculated to be not less than 3.06 m.
In the step E, before clay filling, the clay is fully mixed after being added with water, and the clay is manually filled in layers, so that the clay is compacted during filling, and the compaction coefficient is not less than 0.85.
F. the method comprises the steps of (1) plugging a concrete wellhead, pouring concrete after closing a mold on the outer side of a clay sealing wall 32 of a clay water-proof section 3 to form a concrete plugging section 4, and embedding a supplementary grouting pipe 22 at the highest position of the top of a hole of the concrete plugging section 4 and extending out of the wellhead of a mine;
The length of the concrete plugging section 4 should meet the following formula requirement:
L≥P*A*K/(C*frb)
Wherein in the formula, L is the length (m) of a concrete plugging section 4 of the water-gushing wellhead, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-sectional area (m 2) of the water-gushing wellhead, K is the safety coefficient, C is the perimeter (m) of the cross-section of the water-gushing wellhead, and Frb is the characteristic value (Kpa) of the bonding strength of the chamber wall and the concrete.
The water pressure P near the 2# wellhead of the gateway coal mine is 4700 Kpa, the cross-sectional area A of the water inflow wellhead is 7.8 m 2, the safety coefficient K is 2, the circumference C of the water inflow wellhead is 9 m, the characteristic value Frb of the bonding strength of the cave wall and the concrete is 300 Kpa, and the length L of the 2# wellhead concrete plugging section 4 of the gateway coal mine is not less than 27.156 m.
G. After the strength of the concrete poured by the concrete plugging section 4 reaches 75%, grouting is carried out in a top gap between the hole wall grouting section 2 and the concrete plugging section 4 in the hole through a preset supplementary grouting pipe 22 outside the well, and a top gap of the hole formed by gravity sinking of the poured concrete is filled and sealed;
H. and C, injecting concrete outside the plugging section in the well, namely injecting fine stone concrete on the surface of the slag backfill area from the tail end of the concrete plugging section 4 to the mine wellhead section area in the step F after the step G is completed, and preventing the surface water seeping into the slag from entering the crack at the top of the hole to form polluted wastewater after slag mixing.
In the step B, the water conduit 11 is provided with an emergency gate valve 111, a pressure gauge 112 and a water quality detector 113 at the water outlet end outside the mine mouth. After the mine is plugged, the water quality and water level change condition in the plugged mine can be monitored in real time through a pressure gauge 112 and a water quality detector 113 which are arranged on a water guide pipe 11 outside a wellhead, and when the abnormal rise of the water level in a hole to a high water level which possibly causes environmental pollution or potential safety hazards such as secondary geological disasters and the like is monitored, the emergency gate valve 111 is opened to drain water to control the water level to rise, so that precious time is striven for taking emergency disposal measures.
In the step C, the grouting pressure of the rigid grouting pipe 21 is not less than 0.6Mpa. The length of the hole wall grouting section 2 is set according to the fissure area of a mine for geotechnical engineering investigation, the hole wall grouting section 2 can realize that grouting liquid fully permeates, diffuses, fills and compacts in rock stratum fissures, the rock fissures and original loose soil particles are glued into a whole, the fissures are completely sealed, and water seepage of the fissures is blocked.
The supplementary grouting pipe 22 is composed of a slurry pipe and an exhaust pipe, wherein the slurry pipe is used for grouting slurry, the exhaust pipe is used for exhausting air in a hole top gap during grouting, casting hollows are avoided, the grouting slurry adopts expansion cement, and the water cement ratio is 1:1.
In the step B, the water facing surface on the inner side of the water retaining wall 1 is plastered by impermeable cement mortar, and the plastering thickness is 10mm, so that the impermeability effect is further enhanced.
In the step B, the water guide pipe 11 is a stainless steel seamless pipe, and the stainless steel pipe has good corrosion resistance, so that the long-term service life of the water guide pipe 11 can be ensured. The water guide pipe 11 which is preset to be communicated with the bottom of the water retaining wall 1 is higher than the footline 150 mm of the footline, the pipe diameter of the water guide pipe 11 is larger than 60 mm, the blocking of the water guide pipe by sediments can be avoided, and meanwhile, the timely drainage of water burst in the blocking construction process is realized.
And D, the concrete poured in the grouting section 2 of the cavity wall is seepage-proofing and corrosion-resisting micro-expansion concrete, so that the seepage-proofing effect is enhanced, and the concrete poured in the concrete plugging section 4 in the step F is common concrete, so that the structural strength of the concrete plugging section 4 is ensured.
Example 2
As shown in fig. 10, the 4# well plugging of the Sichuan Guanguan coal mine is constructed by the blocking method of the invention, and the waste mine water pollution is blocked by adopting the construction method of mine cave body pressure grouting, anti-corrosion and anti-seepage blocking layer, anti-seepage concrete section support, clay wall water stop, concrete wellhead plugging backfill and hole top supplementary grouting, wherein the blocking method specifically comprises the following steps:
A. removing sludge in the cavity, namely removing ground sludge, residues and loose surrounding rocks in the abandoned mine, cleaning the ground sludge, residues and loose surrounding rocks to the fresh bedrock surface of the primary stratum of the footrill, and cleaning the rock wall in the cavity by adopting a high-pressure water gun after cleaning;
B. An anti-corrosion and anti-seepage barrier layer is formed by building a brick blank wall in a mine to form a water retaining wall 1, a through water guide pipe 11 is preset at the bottom of the water retaining wall 1 to extend out of a wellhead, and the water guide pipe 11 is used for guiding out water gushing in the well in the plugging construction process;
C. Grouting, solidifying and impervious the underground body, namely, injecting the top wall and the side wall in the mine outside the water retaining wall 1 into a rigid grouting pipe 21, then performing pressure grouting, penetrating, diffusing, filling and compacting the grouting liquid in the rock stratum, filling the space between the loose particles among the rock stratum cracks after penetrating and driving away the water and the air in the loose particles, and after solidifying the grouting liquid, cementing the loose soil particles among the original cracks into a whole to form a tunnel wall grouting section 2 in the well;
The grouting amount of the rigid grouting pipe 21 is determined according to the following calculation formula:
Grouting quantity of single rigid grouting pipe 21, Q is more than or equal to pi R 2 Ln alpha beta
Wherein, Q is the grouting amount (m 3) of the single rigid grouting pipe 21, R is the diffusion radius (m), L is the grouting length of the rigid grouting pipe 21=the design length-1 (m) of the rigid grouting pipe 21, n is the formation void ratio, alpha is the formation filling coefficient, and beta is the slurry consumption coefficient;
the design length of the rigid grouting pipe 21 of the gateway coal mine No. 4 mine is 4m, the diffusion radius R is 0.3m, the formation void ratio n of the cavity wall is 0.4, the formation filling coefficient alpha is 0.8, the slurry consumption coefficient beta is 1.1, and the grouting amount of the single rigid grouting pipe 21 brought into the cavity wall grouting section 2 of the gateway coal mine No. 4 mine is calculated to be not less than 0.298 m 3.
The length of the tunnel wall grouting section 2 is set according to a fracture area of geotechnical engineering investigation, and the grouting pressure of the rigid grouting pipe 21 is not less than 0.6Mpa. The grouting liquid is fully permeated, diffused, filled and compacted in the fracture area of the rock stratum, and the original loose soil particles are glued into a whole.
D. c, pouring anti-corrosion and anti-seepage concrete in the grouting section 2 of the wall of the well, reinforcing and supporting the cured wall of the grouting section 2 of the wall of the well to form a reinforced integral blocking and anti-seepage structure, and presetting a supplementary grouting pipe 22 extending out of the wellhead of the well at the highest position of the top of the grouting section 2 of the wall of the well before pouring;
E. D, clay filling, namely filling clay outside the hole wall grouting section 2 in the step D to form a clay water-proof section 3, carrying out interval grooving 31 on the hole wall before clay filling, manually layering, filling and compacting the clay, and building green bricks to form a clay sealing wall 32 after the clay water-proof section 3 is completed;
the length of the clay water-proof section 3 is determined according to the following calculation formula:
L1≥P*KS*K/(A*γ*Q)
Wherein in the formula, L1 is the length (m) of the clay water-proof section 3, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-section area (m 2),KS is the clay permeability coefficient (cm/s), gamma is the clay gravity (t/m 3), Q is the water-gushing wellhead water-gushing quantity (m 3/d), K is the safety coefficient;
The water pressure P near the water inflow well mouth of the coal mine 4# is 6000 Kpa, the cross-sectional area A of the water inflow well mouth is 7.8 m 2, the clay permeability coefficient K s is 5 multiplied by 10 -5 cm/s, the clay gravity gamma is 1.7 t/m 3, the water inflow quantity Q of the water inflow well mouth is 500 m 3/d, the safety coefficient K is 2, and the length L1 of the clay water-proof section 3 of the water inflow well mouth of the coal mine 4# is not less than 7.82 m when the water inflow well mouth is brought into the calculation.
In the step E, before clay filling, the clay is fully mixed after being added with water, and the clay is manually filled in layers, so that the clay is compacted during filling, and the compaction coefficient is not less than 0.85.
F. the method comprises the steps of (1) plugging a concrete wellhead, pouring concrete after closing a mold on the outer side of a clay sealing wall 32 of a clay water-proof section 3 to form a concrete plugging section 4, and embedding a supplementary grouting pipe 22 at the highest position of the top of a hole of the concrete plugging section 4 and extending out of the wellhead of a mine;
The length of the concrete plugging section 4 should meet the following formula requirement:
L≥P*A*K/(C*frb)
Wherein in the formula, L is the length (m) of a concrete plugging section 4 of the water-gushing wellhead, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-sectional area (m 2) of the water-gushing wellhead, K is the safety coefficient, C is the perimeter (m) of the cross-section of the water-gushing wellhead, and Frb is the characteristic value (Kpa) of the bonding strength of the chamber wall and the concrete.
The water pressure P near the gateway coal mine 4# wellhead is 6000Kpa, the water inflow wellhead cross-section area A is 7.8 m 2, the safety coefficient K is 2, the water inflow wellhead perimeter C is 9 m, the characteristic value Frb of the bonding strength between the cave wall and the concrete is 300 Kpa, and the length L of the gateway coal mine 4# wellhead concrete plugging section 4 is calculated to be not less than 34.667 m.
G. After the strength of the concrete poured by the concrete plugging section 4 reaches 75%, grouting is carried out in a top gap between the hole wall grouting section 2 and the concrete plugging section 4 in the hole through a preset supplementary grouting pipe 22 outside the well, and a top gap of the hole formed by gravity sinking of the poured concrete is filled and sealed;
H. and C, injecting concrete outside the plugging section in the well, namely injecting fine stone concrete on the surface of the slag backfill area from the tail end of the concrete plugging section 4 to the mine wellhead section area in the step F after the step G is completed, and preventing the surface water seeping into the slag from entering the crack at the top of the hole to form polluted wastewater after slag mixing.
In the step B, the water conduit 11 is provided with an emergency gate valve 111, a pressure gauge 112 and a water quality detector 113 at the water outlet end outside the mine mouth. After the mine is plugged, the water quality and water level change condition in the plugged mine can be monitored in real time through a pressure gauge 112 and a water quality detector 113 which are arranged on a water guide pipe 11 outside a wellhead, and when the abnormal rise of the water level in a hole to a high water level which possibly causes environmental pollution or potential safety hazards such as secondary geological disasters and the like is monitored, the emergency gate valve 111 is opened to drain water to control the water level to rise, so that precious time is striven for taking emergency disposal measures.
In the step B, the water guide pipe 11 is a stainless steel seamless pipe, and the stainless steel pipe has good corrosion resistance, so that the long-term service life of the water guide pipe 11 can be ensured. The water guide pipe 11 which is preset to be communicated with the bottom of the water retaining wall 1 is higher than the footline 150 mm of the footline, the pipe diameter of the water guide pipe 11 is larger than 60mm, the blocking of the water guide pipe 11 by sediments can be avoided, and meanwhile, the timely drainage of water burst in the blocking construction process is realized.
And D, the concrete poured in the grouting section 2 of the cavity wall is seepage-proofing and corrosion-resisting micro-expansion concrete, so that the seepage-proofing effect is enhanced, and the concrete poured in the concrete plugging section 4 in the step F is common concrete, so that the structural strength of the concrete plugging section 4 is ensured.
As shown in fig. 10, in the step C, the rigid grouting pipes 21 are uniformly arranged and respectively inclined toward the inside and outside of the mine hole. The rigid grouting pipe 21 far away from the wellhead area is inclined towards the inside of the hole, the hole wall grouting formed by the rigid grouting pipe 21 forms a conical blocking sector for water burst to be blocked, the rigid grouting pipe 21 close to the wellhead area is inclined towards the outside of the hole to form a strong shearing-resistant support, and the rigid grouting pipe and the hole wall grouting section 2 are cast with concrete to form higher integral structural strength, so that the optimal water blocking and seepage resisting effects are realized.
Example 3
As shown in fig. 11, the main wellhead plugging of the Sichuan Guangyuan Tuo coal mine is constructed by the blocking method of the invention, and the waste mine water pollution is blocked by adopting the construction method of mine cave body pressure grouting, anti-corrosion and anti-seepage blocking layer, anti-seepage concrete section support, clay wall water stopping, concrete wellhead plugging backfilling and hole top supplementary grouting, wherein the blocking method specifically comprises the following steps:
A. removing sludge in the cavity, namely removing ground sludge, residues and loose surrounding rocks in the abandoned mine, cleaning the ground sludge, residues and loose surrounding rocks to the fresh bedrock surface of the primary stratum of the footrill, and cleaning the rock wall in the cavity by adopting a high-pressure water gun after cleaning;
B. An anti-corrosion and anti-seepage barrier layer is formed by building a brick blank wall in a mine to form a water retaining wall 1, a through water guide pipe 11 is preset at the bottom of the water retaining wall 1 to extend out of a wellhead, and the water guide pipe 11 is used for guiding out water gushing in the well in the plugging construction process;
C. Grouting, solidifying and impervious the underground body, namely, injecting the top wall and the side wall in the mine outside the water retaining wall 1 into a rigid grouting pipe 21, then performing pressure grouting, penetrating, diffusing, filling and compacting the grouting liquid in the rock stratum, filling the space between the loose particles among the rock stratum cracks after penetrating and driving away the water and the air in the loose particles, and after solidifying the grouting liquid, cementing the loose soil particles among the original cracks into a whole to form a tunnel wall grouting section 2 in the well;
The grouting amount of the rigid grouting pipe 21 is determined according to the following calculation formula:
Grouting quantity of single rigid grouting pipe 21, Q is more than or equal to pi R 2 Ln alpha beta
Wherein, Q is the grouting amount (m 3) of the single rigid grouting pipe 21, R is the diffusion radius (m), L is the grouting length of the rigid grouting pipe 21=the design length-1 (m) of the rigid grouting pipe 21, n is the formation void ratio, alpha is the formation filling coefficient, and beta is the slurry consumption coefficient;
The design length of the rigid grouting pipe 21 of the main wellhead of the Ubbelopsis coal mine is 3m, the diffusion radius R is 0.3m, the void ratio n of the tunnel wall stratum is 0.3, the stratum filling coefficient alpha is 0.8, the slurry consumption coefficient beta is 1.1, and the grouting amount of the single rigid grouting pipe 21 of the tunnel wall grouting section 2 of the main wellhead of the Ubbelopsis coal mine is not less than 0.149 m 3.
The tunnel wall grouting section 2 is arranged according to a fracture area of geotechnical engineering investigation, and the grouting pressure of the rigid grouting pipe 21 is not less than 0.6Mpa. The grouting liquid is fully permeated, diffused, filled and compacted in the rock stratum fracture area, and the rock gaps and the original loose soil grains are glued into a whole.
D. c, pouring anti-corrosion and anti-seepage concrete in the grouting section 2 of the wall of the well, reinforcing and supporting the cured wall of the grouting section 2 of the wall to form a reinforced integral blocking and anti-seepage structure, and presetting a supplementary grouting pipe 22 extending out of the wellhead of the well at the highest position of the top of the grouting section 2 of the wall before pouring;
E. D, clay filling, namely filling clay outside the hole wall grouting section 2 in the step D to form a clay water-proof section 3, carrying out interval grooving 31 on the hole wall before clay filling, manually layering, filling and compacting the clay, and building green bricks to form a clay sealing wall 32 after the clay water-proof section 3 is completed;
the length of the clay water-proof section 3 is determined according to the following calculation formula:
L1≥P*KS*K/(A*γ*Q)
Wherein in the formula, L1 is the length (m) of the clay water-proof section 3, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-section area (m 2),KS is the clay permeability coefficient (cm/s), gamma is the clay gravity (t/m 3), Q is the water-gushing wellhead water-gushing quantity (m 3/d), K is the safety coefficient;
The water pressure P near the main wellhead of the Ubbelo coal mine is 1800 Kpa, the section area A of the water inflow wellhead is 8.2 m 2, the clay permeability coefficient K s is 5 multiplied by 10 -5 cm/s, the clay gravity gamma is 1.7 t/m 3, the water inflow Q of the water inflow wellhead is 50m 3/d, the safety coefficient K is 2, and the length L1 of the clay water-proof section 3 of the main wellhead of the Ubbelo coal mine is not less than 2.23m.
In the step E, before clay filling, the clay is fully mixed after being added with water, and the clay is manually filled in layers, so that the clay is compacted during filling, and the compaction coefficient is not less than 0.85.
F. the method comprises the steps of (1) plugging a concrete wellhead, pouring concrete after closing a mold on the outer side of a clay sealing wall 32 of a clay water-proof section 3 to form a concrete plugging section 4, and embedding a supplementary grouting pipe 22 at the highest position of the top of a hole of the concrete plugging section 4 and extending out of the wellhead of a mine;
The length of the concrete plugging section 4 should meet the following formula requirement:
L≥P*A*K/(C*frb)
Wherein in the formula, L is the length (m) of a concrete plugging section 4 of the water-gushing wellhead, P is the water pressure (Kpa) near the water-gushing wellhead, A is the cross-sectional area (m 2) of the water-gushing wellhead, K is the safety coefficient, C is the perimeter (m) of the cross-section of the water-gushing wellhead, and Frb is the characteristic value (Kpa) of the bonding strength of the chamber wall and the concrete.
The water pressure P near the main wellhead of the Ubbelopsis coal mine is 1800Kpa, the section area A of the water inflow wellhead is 8.2 m 2, the safety coefficient K is 2, the circumference C of the water inflow wellhead is 9.4 m, the characteristic value Frb of the bonding strength between the cave wall and the concrete is 320 Kpa, and the length L of the concrete plugging section 4 of the main wellhead of the Ubbelopsis coal mine is not less than 9.714 m.
G. After the strength of the concrete poured by the concrete plugging section 4 reaches 75%, grouting is carried out in a top gap between the hole wall grouting section 2 and the concrete plugging section 4 in the hole through a preset supplementary grouting pipe 22 outside the well, and a top gap of the hole formed by gravity sinking of the poured concrete is filled and sealed;
H. and C, injecting concrete outside the plugging section in the well, namely injecting fine stone concrete on the surface of the slag backfill area from the tail end of the concrete plugging section 4 to the mine wellhead section area in the step F after the step G is completed, and preventing the surface water seeping into the slag from entering the crack at the top of the hole to form polluted wastewater after slag mixing.
In the step B, the water conduit 11 is provided with an emergency gate valve 111, a pressure gauge 112 and a water quality detector 113 at the water outlet end outside the mine mouth. After the mine is plugged, the water quality and water level change condition in the plugged mine can be monitored in real time through a pressure gauge 112 and a water quality detector 113 which are arranged on a water guide pipe 11 outside a wellhead, and when the abnormal rise of the water level in a hole to a high water level which possibly causes environmental pollution or potential safety hazards such as secondary geological disasters and the like is monitored, the emergency gate valve 111 is opened to drain water to control the water level to rise, so that precious time is striven for taking emergency disposal measures.
In the step C, the grouting pressure of the rigid grouting pipe 21 is not less than 0.6Mpa. The grouting liquid is fully permeated, diffused, filled and compacted in the rock stratum, and the original loose soil particles are glued into a whole.
In the step D and the step G, the supplementary grouting pipe 22 is composed of a slurry pipe and an exhaust pipe, the slurry pipe is used for grouting slurry, the exhaust pipe is used for exhausting air in a hole top gap during grouting, casting hollows are avoided, and the grouting slurry adopts expansion cement with a water-cement ratio of 1:1.
In the step B, the water facing surface on the inner side of the water retaining wall 1 is plastered by impermeable cement mortar, and the plastering thickness is 10mm, so that the impermeability effect is further enhanced.
In the step B, the water guide pipe 11 is a stainless steel seamless pipe, and the stainless steel pipe has good corrosion resistance, so that the long-term service life of the water guide pipe 11 can be ensured. The water guide pipe 11 which is preset to be communicated with the bottom of the water retaining wall 1 is higher than the footline 150 mm of the footline, the pipe diameter of the water guide pipe 11 is larger than 60mm, the blocking of the water guide pipe 11 by sediments can be avoided, and meanwhile, the timely drainage of water burst in the blocking construction process is realized.
And D, the concrete poured in the grouting section 2 of the cavity wall is seepage-proofing and corrosion-resisting micro-expansion concrete, so that the seepage-proofing effect is enhanced, and the concrete poured in the concrete plugging section 4 in the step F is common concrete, so that the structural strength of the concrete plugging section 4 is ensured.
It should be understood that the foregoing examples of the present invention are provided merely for clearly illustrating the present invention and are not intended to limit the embodiments of the present invention, and that various other changes and modifications may be made therein by one skilled in the art without departing from the spirit and scope of the present invention as defined by the appended claims.