[go: up one dir, main page]

CN111997101A - Prestressed anti-corrosion and anti-floating anchor rod and construction method - Google Patents

Prestressed anti-corrosion and anti-floating anchor rod and construction method Download PDF

Info

Publication number
CN111997101A
CN111997101A CN202010998448.2A CN202010998448A CN111997101A CN 111997101 A CN111997101 A CN 111997101A CN 202010998448 A CN202010998448 A CN 202010998448A CN 111997101 A CN111997101 A CN 111997101A
Authority
CN
China
Prior art keywords
water stop
slow
cylinder
steel strand
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010998448.2A
Other languages
Chinese (zh)
Other versions
CN111997101B (en
Inventor
王凯
刘林凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou Bokangte Construction Engineering Co ltd
Shanghai Branch Of China Academy Of Building Sciences Co ltd
Original Assignee
Changzhou Bokangte Construction Engineering Co ltd
Shanghai Branch Of China Academy Of Building Sciences Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Bokangte Construction Engineering Co ltd, Shanghai Branch Of China Academy Of Building Sciences Co ltd filed Critical Changzhou Bokangte Construction Engineering Co ltd
Priority to CN202010998448.2A priority Critical patent/CN111997101B/en
Publication of CN111997101A publication Critical patent/CN111997101A/en
Application granted granted Critical
Publication of CN111997101B publication Critical patent/CN111997101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种预应力防腐抗浮锚杆以及施工方法,将多根缓粘结预应力钢绞线,缓粘结预应力钢绞线的下端、第一止水板和下承压板通过预灌浆浇注一体成型形成第一柱体,第一止水板的部分露出于第一柱体,在第一止水板露出的部分外侧继续浇注形成第二柱体后形成预制锚杆,第二柱体包裹第一止水板露出部分,缓粘结预应力钢绞线的上部套设有第二止水板,第二止水板内部和缓粘结预应力钢绞线之间通过补充浇注形成补浇柱体,使补浇柱体和第二柱体连接。通过上述方式,本发明预应力防腐抗浮锚杆及其施工方法,采用缓粘结预应力钢绞线,通过新型防水结构和施工方法避免锚杆整体被水腐蚀,避免出现抗浮锚杆失效的问题。

Figure 202010998448

The invention discloses a prestressed anti-corrosion and anti-floating anchor rod and a construction method. The first cylinder is integrally formed by pre-grouting casting, the part of the first water stop plate is exposed to the first cylinder body, and the second cylinder is formed by casting on the outside of the exposed part of the first water stop plate to form a prefabricated anchor rod. The exposed part of the first water stop plate is wrapped by the two cylinders, the upper part of the slow-bonding prestressed steel strand is sleeved with a second water-stop plate, and the interior of the second water stop plate and the slow-bonding prestressed steel strand are supplemented by pouring A supplementary pouring cylinder is formed, so that the supplementary pouring column and the second column are connected. Through the above method, the prestressed anti-corrosion and anti-floating anchor rod and its construction method of the present invention adopt slow-bonding prestressed steel strands, and the new waterproof structure and construction method are used to prevent the entire anchor rod from being corroded by water, and to avoid the failure of the anti-floating anchor rod. The problem.

Figure 202010998448

Description

预应力防腐抗浮锚杆以及施工方法Prestressed anti-corrosion and anti-floating anchor rod and construction method

技术领域technical field

本发明涉及预应力抗浮锚杆领域,特别是涉及一种预应力防腐抗浮锚杆以及施工方法。The invention relates to the field of prestressed anti-floating anchor rods, in particular to a prestressed anti-corrosion anti-floating anchor rod and a construction method.

背景技术Background technique

抗浮锚杆是地下结构物抵抗水浮力而采用的一种抗浮技术,在国内外应用都十分广泛,尤其是近些年来在国内,随着建筑地下室、地铁、地下交通枢纽、地下空间、水工建筑等地下工程的埋深越来越深,抗浮锚杆日益发挥着不可替代的重要作用。Anti-floating anchor is an anti-floating technology used by underground structures to resist water buoyancy. It is widely used at home and abroad, especially in China in recent years, with the construction of basements, subways, underground transportation hubs, underground spaces, The buried depth of hydraulic construction and other underground projects is getting deeper and deeper, and the anti-floating anchor is increasingly playing an irreplaceable and important role.

抗浮锚杆一般为永久性结构,分为预应力锚杆及全粘结锚杆(非预应力锚杆)两大类。采用预应力锚杆的施工工艺较为复杂、施工管理不便以及锚头穿过地下结构时需设置套管,套管内外均需采取防水措施且防水难度较大。因此抗浮锚杆中的钢绞线会受到地下水的侵蚀,逐渐被腐蚀,受拉承载力降低,严重时可能导致受力钢筋被拉断而使抗浮构件失效。Anti-floating anchors are generally permanent structures, which are divided into two categories: prestressed anchors and fully bonded anchors (non-prestressed anchors). The construction process of using prestressed bolts is relatively complicated, the construction management is inconvenient, and the casing needs to be set when the anchor head passes through the underground structure. Therefore, the steel strand in the anti-floating anchor will be eroded by groundwater, gradually corroded, and the tensile bearing capacity will be reduced.

发明内容SUMMARY OF THE INVENTION

本发明主要解决的技术问题是提供一种预应力防腐抗浮锚杆及其施工方法,采用缓粘结预应力钢绞线,通过新型防水结构和施工方法避免锚杆整体被水腐蚀,避免出现抗浮锚杆失效的问题。The main technical problem to be solved by the present invention is to provide a prestressed anti-corrosion and anti-floating anchor rod and a construction method thereof, adopting slow-bonding prestressed steel strands, and using a new waterproof structure and construction method to avoid the whole anchor rod being corroded by water and to avoid occurrence of The problem of anti-floating anchor failure.

为解决上述技术问题,本发明采用的一个技术方案是:提供一种预应力防腐抗浮锚杆,包括多根缓粘结预应力钢绞线,所述缓粘结预应力钢绞线在竖直方向上通过安装对中隔离架支撑,下端穿过下承压板并与挤压锚连接,所述缓粘结预应力钢绞线的上端与竖直方向呈倾斜弯折,所述缓粘结预应力钢绞线的下端套设有第一止水板,所述第一止水板、下承压板和缓粘结预应力钢绞线的下端通过预灌浆浇注一体成型形成第一柱体,所述第一止水板的部分露出于第一柱体,在第一止水板露出的部分外侧继续浇注形成第二柱体后形成预制锚杆,所述第二柱体包裹第一止水板露出部分,通过第一止水板使第一柱体和第二柱体一体连接,所述缓粘结预应力钢绞线的上部套设有第二止水板,所述第二止水板内部和缓粘结预应力钢绞线之间通过补充浇注形成补浇柱体。In order to solve the above-mentioned technical problems, a technical solution adopted in the present invention is to provide a prestressed anti-corrosion and anti-floating anchor rod, which includes a plurality of slow-bonding prestressed steel strands, and the slow-bonding prestressed steel strands are vertically mounted. It is supported by the installation centering spacer in the vertical direction, and the lower end passes through the lower bearing plate and is connected with the extrusion anchor. The upper end of the slow bonding prestressed steel strand is bent obliquely with The lower end of the prestressed steel strand is sleeved with a first water stop plate, and the first water stop plate, the lower bearing plate and the lower end of the slow-bonded prestressed steel strand are integrally formed by pre-grouting casting to form a first cylinder , the part of the first water stop plate is exposed to the first cylinder, and the prefabricated anchor rod is formed after casting the outside of the exposed part of the first water stop plate to form a second cylinder, and the second cylinder wraps the first stop In the exposed part of the water plate, the first cylinder and the second cylinder are integrally connected by the first water stop plate. The upper part of the slow-bonding prestressed steel strand is sleeved with a second water stop plate. The supplementary pouring column is formed by supplementary pouring between the interior of the water plate and the slow-bonded prestressed steel strand.

在本发明一个较佳实施例中,所述第二柱体直接在钻孔外部浇注完成后再将预制锚杆放入钻孔中,或者第一柱体浇注完成将上述部分放入钻孔中后再在钻孔中浇注第二柱体,所述第一柱体和第二柱体为圆柱形结构。In a preferred embodiment of the present invention, the second cylinder is directly poured outside the borehole and then the prefabricated bolt is put into the borehole, or the first cylinder is poured and the above-mentioned part is put into the borehole Then, a second cylinder is poured in the drilled hole, and the first cylinder and the second cylinder are cylindrical structures.

在本发明一个较佳实施例中,所述第一止水板为环形止水板,并且其上下两端呈漏斗状开口。In a preferred embodiment of the present invention, the first water stop plate is an annular water stop plate, and its upper and lower ends have funnel-shaped openings.

在本发明一个较佳实施例中,所述缓粘结预应力钢绞线之间以下承压板的中心间隔均匀排布,所述缓粘结预应力钢绞线的上端套设有遇水膨胀的止水环,所述缓粘结预应力钢绞线的上端穿过上承压板并且与成品锚具连接,所述缓粘结预应力钢绞线下端和下承压板之间安装有第一弹性,上端和上承压板之间安装有第二弹性件,缓粘结预应力钢绞线上端呈弯折状,并且其弯折曲率半径为5000mm。In a preferred embodiment of the present invention, the centers of the lower bearing plates are evenly spaced between the slow-bonding prestressed steel strands, and the upper ends of the slow-bonding prestressed steel strands are sleeved with water Expanded water stop ring, the upper end of the slow-bonding prestressed steel strand passes through the upper bearing plate and is connected with the finished anchorage, and the lower end of the slow-bonding prestressed steel strand is installed between the lower bearing plate There is a first elasticity, a second elastic piece is installed between the upper end and the upper bearing plate, the upper end of the slow-bonded prestressed steel strand is bent, and its bending radius is 5000mm.

为解决上述技术问题,本发明采用的另一个技术方案是:提供一种上述预应力防腐抗浮锚杆的施工方法,包括以下步骤:a.预制锚杆:至少三根缓粘结预应力钢绞线沿圆周均布,并通过多个沿竖直方向间隔布置的对中隔离架支撑固定,下端穿过第一止水板与下承压板、第一弹性件和挤压锚连接,将模具套设在钢绞线下端的外部,第一止水板的上半部分露出于模具,然后进行灌浆浇注形成第一柱体,浇注完成后拆除模具并进行养护,第一柱体外部进行防渗透处理,制成预制锚杆;b.钻孔:钻孔前,按照设计要求定出孔位,做出标记,采用湿式钻孔,钻孔后水清洗孔,直至孔口流出清水为止;c.灌注:将浇注导管和步骤a制成的预制锚杆一起放入钻孔中,采用注浆料一次性注浆完成,灌注时待孔口溢出,即可停止灌浆,浆体在终凝前应进行及时补浆,达到灌满为止,根据工程条件和设计要求确定灌注压力,确保浆体灌注密度,注浆后第二柱体和第一柱体通过第一止水环一体连接,使水只能向上渗透;d.端部处理:沿预制锚杆外周开挖,形成施工坑,将预制锚杆上端的浇注部破除,然后套上第二止水板,第二止水板的内部补充浇注成型,使补浇柱体和第二柱体连接,再浇注垫层,垫层浇注高度必须低于第二止水板,必须使第二止水板的上端部分露出,接着在垫层上沿纵向和横向绑扎钢筋,钢筋绑扎完成后在每根缓粘结预应力钢绞线上安装止水环、上承压板、第二弹性件和锚具并预留张拉槽,然后浇注底板和面层;e.张拉与封锚;待底板混凝土强度达到设计强度的100%之后,方可进行张拉,预应力筋张拉完成后做好封端处理。In order to solve the above-mentioned technical problems, another technical solution adopted by the present invention is to provide a construction method for the above-mentioned prestressed anti-corrosion and anti-floating anchor rod, which includes the following steps: a. Prefabricated bolts: at least three slow-bonded prestressed steel strands are evenly distributed along the circumference, supported and fixed by a plurality of centering spacers arranged at intervals in the vertical direction, and the lower end passes through the first water stop plate and the lower bearing plate , The first elastic member is connected with the extrusion anchor, the mold is sleeved on the outside of the lower end of the steel strand, and the upper half of the first water stop plate is exposed to the mold, and then the first cylinder is formed by grouting and casting, and removed after the casting is completed. Mold and maintenance, the first cylinder outside the anti-penetration treatment, made of prefabricated anchor; b. Drilling: Before drilling, determine the hole position according to the design requirements, make a mark, use wet drilling, and clean the hole with water after drilling until the hole flows out of clean water; c. Pouring: Put the casting conduit and the prefabricated anchor rod made in step a into the drilled hole together, and complete the grouting at one time with the grouting slurry. When the orifice overflows, the grouting can be stopped. The slurry should be grouted before the final setting. Fill in the grout in time until it is full, and determine the perfusion pressure according to the engineering conditions and design requirements to ensure the perfusion density of the slurry. Can penetrate upward; d. End treatment: excavate along the outer circumference of the prefabricated bolt to form a construction pit, break the pouring part at the upper end of the prefabricated bolt, and then put on the second water stop plate, and the inside of the second water stop plate is supplemented by pouring and molding, so that the supplementary pouring column is formed. The body and the second column are connected, and then the cushion is poured. The pouring height of the cushion must be lower than the second water stop, and the upper end of the second water stop must be exposed, and then the reinforcement is bound longitudinally and laterally on the cushion. After the steel bars are bound, install a water stop ring, an upper bearing plate, a second elastic member and an anchorage on each slow-bonded prestressed steel strand and reserve a tension groove, and then pour the bottom plate and surface layer; e. Tensioning and sealing anchors; after the concrete strength of the bottom plate reaches 100% of the design strength, the tensioning can be carried out, and the end sealing treatment is done after the prestressed tendons are tensioned.

在本发明一个较佳实施例中,所述步骤a中缓粘结预应力钢绞线下端剥除部分PE外套进行挤压,钢绞线露出挤压锚1~5mm,,清除缓粘结钢绞线表面的污渍,每隔1000mm安装一块隔离架对中,用绑扎固定,拆除模具后刷两道防水剂进行防渗透处理,通过C40混凝土进行灌浆浇注形成第一柱体。In a preferred embodiment of the present invention, in the step a, the lower end of the slow-bonding prestressed steel strand is peeled off part of the PE jacket and extruded, and the steel strand is exposed to 1-5 mm of the extrusion anchor, and the slow-bonding steel strand is removed. For the stains on the surface of the stranded wire, install a spacer frame every 1000mm to center, and fix it with binding. After removing the mold, brush two layers of waterproofing agent for anti-penetration treatment, and grouting and pouring through C40 concrete to form the first column.

在本发明一个较佳实施例中,所述步骤b中钻孔前,按设计要求定出孔位,做出标记,锚孔定位偏差不宜大于20mm,锚孔偏斜度不应大于1%,钻孔深度超过锚杆不应小于设计长度,也不大于设计长度。In a preferred embodiment of the present invention, before drilling in the step b, the hole position is determined according to the design requirements, and a mark is made. The positioning deviation of the anchor hole should not be greater than 20mm, and the deviation of the anchor hole should not be greater than 1%. The drilling depth beyond the anchor rod should not be less than the design length, nor greater than the design length.

在本发明一个较佳实施例中,所述步骤c中插放锚杆时,应防止预应力筋扭压、弯曲,杆体放入角度与钻孔角度保持一致,通过C35细石混凝土水下灌注形成第二柱体。In a preferred embodiment of the present invention, when the anchor rod is inserted in the step c, the prestressed tendons should be prevented from being twisted and bent, and the rod body is placed in the same angle as the drilling angle, and the C35 fine stone concrete is poured underwater. A second cylinder is formed.

在本发明一个较佳实施例中,所述步骤d中底板钢筋应主动避让或者绕行钢绞线,底板钢筋绑扎完成后,逐根安装橡胶止水环和焊接张拉端垫板,每根钢绞线在底板范围内防止两处止水环,用聚苯乙烯泡沫板预留张拉槽。In a preferred embodiment of the present invention, in the step d, the reinforcing bars on the bottom plate should actively avoid or bypass the steel strands, and after the reinforcing bars on the bottom plate are bound, install rubber water-stop rings and welding tension end pads one by one. The steel strand prevents two water-stop rings within the scope of the bottom plate, and a tension groove is reserved with a polystyrene foam board.

在本发明一个较佳实施例中,所述步骤f中封端处理中先将多余钢绞线采用砂轮片切除,剩余的外露钢绞线长度不小于30mm,再将张拉端及其周围清理干净,刷两道防水剂,最后用微膨胀细石混凝土封堵张拉端并振捣密实。In a preferred embodiment of the present invention, in the end-capping treatment in step f, the excess steel strand is first cut off with a grinding wheel, and the length of the remaining exposed steel strand is not less than 30mm, and then the tensioned end and its surroundings are cleaned Clean, brush two coats of waterproofing agent, and finally seal the tension end with micro-expanded fine stone concrete and vibrate to compact it.

本发明的有益效果是:本发明预应力防腐抗浮锚杆及其施工方法,采用缓粘结预应力钢绞线,通过新型防水结构和施工方法避免锚杆整体被水腐蚀,避免出现抗浮锚杆失效的问题,使用年限长达50年以上。The beneficial effects of the present invention are as follows: the prestressed anti-corrosion and anti-floating anchor rod and its construction method of the present invention adopt slow-bonding prestressed steel strands, and the whole anchor rod is prevented from being corroded by water through the new waterproof structure and construction method, and the occurrence of anti-floating The failure of the anchor rod has a service life of more than 50 years.

附图说明Description of drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图,其中:In order to illustrate the technical solutions in the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings used in the description of the embodiments. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, under the premise of no creative work, other drawings can also be obtained from these drawings, wherein:

图1是本发明预应力防腐抗浮锚杆及的施工方法一较佳实施例的结构示意图;Fig. 1 is the structural representation of a preferred embodiment of the prestressed anti-corrosion and anti-floating anchor rod and the construction method of the present invention;

图2是图1的局部结构示意图;Fig. 2 is the partial structure schematic diagram of Fig. 1;

图3是图1的局部结构示意图;Fig. 3 is the partial structure schematic diagram of Fig. 1;

图4是图1的局部结构示意图(图中缓粘结预应力钢绞线未画出);Figure 4 is a schematic diagram of the partial structure of Figure 1 (the slow-bonded prestressed steel strand is not shown in the figure);

附图中各部件的标记如下:1、缓粘结预应力钢绞线,2、对中隔离架,3、下承压板,4、挤压锚,5、第一止水板,6、第一柱体,7、第二柱体,8、第二止水板,9、补浇柱体,10、第一弹性件,11、第二弹性件,12、止水环,13、成品锚具,14、上承压板,15、垫层,16、基层,17、面层。The symbols of the components in the accompanying drawings are as follows: 1. Slowly bonded prestressed steel strand, 2. Centering spacer, 3. Lower bearing plate, 4. Extrusion anchor, 5. First water stop plate, 6. The first cylinder, 7, the second cylinder, 8, the second water stop plate, 9, the filling cylinder, 10, the first elastic piece, 11, the second elastic piece, 12, the water stop ring, 13, the finished product Anchorage, 14, upper bearing plate, 15, cushion layer, 16, base layer, 17, surface layer.

具体实施方式Detailed ways

下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

请参阅图1至图4,一种预应力防腐抗浮锚杆,包括多根缓粘结预应力钢绞线1,缓粘结预应力钢绞线1在竖直方向上通过安装对中隔离架2支撑,下端穿过下承压板3并与挤压锚4连接,缓粘结预应力钢绞线1的上端与竖直方向呈倾斜弯折,缓粘结预应力钢绞线1的下端套设有第一止水板5,第一止水板5、下承压板3和缓粘结预应力钢绞线1的下端通过预灌浆浇注一体成型形成预制锚杆,第一止水板5的部分露出于第一柱体6,预制锚杆和注浆管放入钻孔内再灌浆注浆形成第二柱体7,第二柱体7包裹第一止水板5露出部分,通过第一止水板5使第一柱体6和第二柱体7一体连接,缓粘结预应力钢绞线1的上部套设有第二止水板8,第二止水板8内部和缓粘结预应力钢绞线1之间通过补充浇注形成补浇柱体9,使补浇柱体9和第二柱体7连接。Please refer to Fig. 1 to Fig. 4, a prestressed anti-corrosion and anti-floating anchor rod, including a plurality of slow-bonded prestressed steel strands 1, and the slow-bonded prestressed steel strands 1 are vertically separated by installation and centering The frame 2 is supported, the lower end passes through the lower bearing plate 3 and is connected with the extrusion anchor 4, the upper end of the slow-bonding prestressed steel strand 1 is bent obliquely with the vertical direction, and the slow-bonding prestressed steel strand 1 is The lower end is sleeved with a first water stop plate 5. The lower end of the first water stop plate 5, the lower bearing plate 3 and the slow-bonding prestressed steel strand 1 are integrally formed by pre-grouting casting to form a prefabricated anchor rod. The part of 5 is exposed on the first cylinder 6, the prefabricated anchor rod and the grouting pipe are put into the borehole and then grouted to form the second cylinder 7, the second cylinder 7 wraps the exposed part of the first water stop plate 5, The first water stop plate 5 connects the first cylinder 6 and the second column body 7 integrally, and the upper part of the slow-bonding prestressed steel strand 1 is sleeved with a second water stop plate 8, and the second water stop plate 8 is gentle inside. A supplementary pouring cylinder 9 is formed between the bonded prestressed steel strands 1 through supplementary casting, so that the supplementary pouring column 9 and the second column 7 are connected.

另外,第一止水板5为环形止水板,并且其上下两端呈漏斗状开口。In addition, the first water stop plate 5 is an annular water stop plate, and its upper and lower ends are open in a funnel shape.

另外,缓粘结预应力钢绞线1之间以下承压板3的中心间隔均匀排布,缓粘结预应力钢绞线1的上端套设有遇水膨胀的止水环12,缓粘结预应力钢绞线1的上端穿过上承压板14并且与成品锚具13连接,缓粘结预应力钢绞线1下端和下承压板3之间安装有第一弹性件10,上端和上承压板14之间安装有第二弹性件11,缓粘结预应力钢绞线1上端呈弯折状,并且其弯折曲率半径为5000mm。In addition, the center of the lower bearing plate 3 is evenly spaced between the slow-bonding prestressed steel strands 1, and the upper end of the slow-bonding prestressed steel strand 1 is sleeved with a water-swelling water stop ring 12 to prevent the slow bonding The upper end of the prestressed steel strand 1 passes through the upper bearing plate 14 and is connected with the finished anchor 13, and a first elastic member 10 is installed between the lower end of the slow bonding prestressed steel strand 1 and the lower bearing plate 3, A second elastic member 11 is installed between the upper end and the upper bearing plate 14 , and the upper end of the slow-bonded prestressed steel strand 1 is bent, and its bending radius is 5000 mm.

另外,第一柱体6和第二柱体7为圆柱形结构。In addition, the first column body 6 and the second column body 7 are cylindrical structures.

一种预应力防腐抗浮锚杆的施工方法,包括以下步骤:A construction method for a prestressed anti-corrosion and anti-floating anchor rod, comprising the following steps:

a.预制锚杆:采用17.8mm规格缓粘结预应力钢绞线,其性能应满足《预应力混凝土用钢绞线》(GB/T5224-2014)的规定,缓凝粘合剂的标准张拉适用期为180d,标准固化时间为540d。缓粘结预应力钢绞线须在张拉适用期内完成张拉。缓粘结预应力钢绞线下端剥除部分PE外套进行挤压,钢绞线露出挤压锚1~5mm,清除缓粘结钢绞线表面的污渍,每隔1000mm安装一块隔离架对中,用绑扎固定,三根缓粘结预应力钢绞线沿圆周均布,并通过3个沿竖直方向间隔布置的对中隔离架支撑固定,下端穿过第一止水板与下承压板、第一弹性件和挤压锚连接,将模具套设在钢绞线下端的外部,第一止水板的上半部分露出于模具,然后通过C40混凝土进行灌浆浇注形成第一柱体,浇注完成后拆除模具并进行养护,第一柱体外部刷两道防水剂进行防渗透处理,制成预制锚杆拆;a. Prefabricated bolts: 17.8mm specification slow-bonded prestressed steel strands are used, and their performance should meet the requirements of "Steel Strands for Prestressed Concrete" (GB/T5224-2014), and the standard tension of the retarding adhesive is applicable. The curing period is 180d, and the standard curing time is 540d. The slow-bonded prestressed steel strand must be tensioned within the tensioning period. Peel off part of the PE jacket from the lower end of the slow-bonded prestressed steel strand and extrude the steel strand to expose the extrusion anchor 1-5mm, remove the stains on the surface of the slow-bonded steel strand, and install a spacer every 1000mm for centering. It is fixed by binding, and the three slow-bonding prestressed steel strands are evenly distributed along the circumference, and are supported and fixed by three centering spacers arranged at intervals in the vertical direction. The first elastic member is connected with the extrusion anchor, the mold is sleeved on the outside of the lower end of the steel strand, the upper half of the first water stop plate is exposed to the mold, and then the first cylinder is formed by grouting with C40 concrete, and the pouring is completed. After removing the mold and performing maintenance, the first cylinder is brushed with two layers of waterproofing agent for anti-penetration treatment to make a prefabricated bolt for dismantling;

b.钻孔:钻孔前,按照设计要求定出孔位,做出标记,孔定位偏差不宜大于20mm,锚孔偏斜度不应大于1%,采用湿式钻孔,钻孔后水清洗孔,直至孔口流出清水为止,孔直径大于200mm,钻孔深度超过锚杆不应小于设计长度,也不大于设计长度500mm,;b. Drilling: Before drilling, set the hole position according to the design requirements and make a mark. The hole positioning deviation should not be greater than 20mm, and the anchor hole deviation should not be greater than 1%. Wet drilling is used. Until clear water flows out of the orifice, the diameter of the hole is greater than 200mm, and the depth of the drilled hole exceeding the bolt should not be less than the design length, nor greater than the design length of 500mm;

c.灌注:将浇注导管和步骤a制成的预制锚杆一起放入钻孔中,应防止预应力筋扭压、弯曲,杆体放入角度与钻孔角度保持一致,浇注导管端头到固定端面层的距离不小于100mm,浇注导管灌注水泥基灌浆料或M40水泥复合砂浆,采用注浆料一次性注浆完成,导管埋入灌浆料中不小于1000mm,严禁产生夹泥缩颈,灌注时待孔口溢出,即可停止灌浆,浆体在终凝前应进行及时补浆,达到灌满为止,根据工程条件和设计要求确定灌注压力,确保浆体灌注密度,浆体强度检验用试块每30根锚杆不应小于一组,每组应不少于6个试块,试块强度符合设计要求,且强度不低于30Mpa注浆后第二柱体和第一柱体通过第一止水环一体连接,使水只能向上渗透;c. Pouring: Put the pouring conduit and the prefabricated anchor rod made in step a into the drilled hole. The prestressed tendons should be prevented from being twisted and bent. The angle of the rod body should be consistent with the drilling angle. The distance between the layers is not less than 100mm. The pouring conduit is filled with cement-based grouting material or M40 cement composite mortar. When the orifice overflows, the grouting can be stopped. The grout should be replenished in time before the final setting until it is full. The perfusion pressure should be determined according to the engineering conditions and design requirements to ensure the density of the grout. The 30 bolts should not be less than one group, and each group should have no less than 6 test blocks. The strength of the test blocks meets the design requirements, and the strength is not less than 30Mpa. After grouting, the second column and the first column pass the first stop. The water ring is integrally connected, so that the water can only penetrate upwards;

d.端部处理:沿预制锚杆外周开挖,形成施工坑,将预制锚杆上端的浇注部破除,然后套上第二止水板,第二止水板的内部补充浇注成型,使补浇柱体和第二柱体连接,再浇注垫层,垫层浇注高度必须低于第二止水板,至少使第二止水板的1/3部分露出,接着在垫层上沿纵向和横向绑扎钢筋,钢筋绑扎完成后在每根缓粘结预应力钢绞线上安装止水环、上承压板、第二弹性件和锚具并用聚苯乙烯泡沫板预留张拉槽,然后浇注底板和面层;d. End treatment: excavate along the outer circumference of the prefabricated bolt to form a construction pit, break the pouring part at the upper end of the prefabricated bolt, and then put on the second water stop plate, and the inside of the second water stop plate is supplemented by pouring and molding, so that the supplementary pouring column is formed. The body and the second cylinder are connected, and then the cushion layer is poured. The pouring height of the cushion layer must be lower than the second water stop plate, at least 1/3 of the second water stop plate is exposed, and then the cushion layer is bound longitudinally and laterally. Reinforcing bars, install water stop rings, upper bearing plates, second elastic parts and anchors on each slow-bonded prestressed steel strand after the reinforcing bars are bound, and reserve tension grooves with polystyrene foam boards, and then pour the bottom plate and surface layer;

e.张拉与封锚;待底板混凝土强度达到设计强度的100%之后,方可进行张拉,抗拔承载力特征值Nka取400KN,试桩锚杆张拉力F1按2倍测抗拔承载力特征值800KN控制;施工锚杆锁定张拉力F2按650KN控制,张拉时应采用应力控制为主、应变校核的方法进行,实测伸长值力记录,与计算值的偏差应在-6%~+6%范围之内,施工中应做好现场施加预应力记录。张拉应均匀、有序,避免局部区域内集中张拉对邻近锚杆的不利影响,张拉过程中禁止扰动筋体、千斤顶或其他锚夹具。预应力筋张拉完成后做好封端处理,先将多余钢绞线采用砂轮片切除,剩余的外露钢绞线长度不小于30mm,再将张拉端及其周围清理干净,刷两道防水剂,最后坑壁涂刷水泥基渗透结晶防水材料后用微膨胀细石混凝土封堵张拉端并振捣密实。预应力防腐抗浮锚杆施工完成后,如图2所示,由于第一止水板将第一柱体和第二柱体一体连接,底层水不会横向进入缓粘结预应力钢绞线内,而是沿竖直方向流动,不会对缓粘结预应力钢绞线造成腐蚀,如图3所示,同理,上层水也是沿竖直方向流动,不会对缓粘结预应力钢绞线造成腐蚀。e. Tensioning and sealing anchors; tensioning can be carried out after the concrete strength of the bottom plate reaches 100% of the design strength, the characteristic value of the pull-out bearing capacity Nka is 400KN, and the tensile force F1 of the test pile and anchor is measured by 2 times the pull-out bearing capacity characteristics The value of 800KN is controlled; the locking tension F2 of the construction anchor is controlled by 650KN, and the stress control should be used as the main method and the strain check method should be used for tensioning. Within the range of +6%, the on-site prestressing records should be made during construction. The tensioning should be uniform and orderly to avoid the adverse effects of concentrated tensioning in local areas on the adjacent anchor rods. It is forbidden to disturb the tendons, jacks or other anchor fixtures during the tensioning process. After the prestressed tendons are tensioned, the end capping treatment is done. First, the excess steel strands are cut off with a grinding wheel, and the length of the remaining exposed steel strands is not less than 30mm. Then, clean the tensioned end and its surroundings, and apply two coats of waterproofing. Finally, the pit wall is painted with cement-based permeable crystalline waterproof material, and then the tension end is sealed with micro-expanded fine stone concrete and vibrated for compaction. After the construction of the prestressed anti-corrosion and anti-floating anchor rod is completed, as shown in Figure 2, since the first water stop plate connects the first column and the second column together, the bottom water will not enter the slow-bonded prestressed steel strand laterally. It flows in the vertical direction, and will not cause corrosion to the slow-bonding prestressed steel strand, as shown in Figure 3. Similarly, the upper layer water also flows in the vertical direction, and will not cause corrosion to the slow-bonding prestressed steel strand. Steel strands cause corrosion.

实施例2,步骤c中在钻孔外对步骤a中浇注完成的第一柱体上继续进行第二柱体的浇注,第二柱体和第一柱体通过第一止水环一体连接,然后将上述部分再插入到钻孔中,补充浇注后继续进行步骤d。其余同实施例1。Example 2, in step c, the second cylinder is continuously poured on the first cylinder that has been poured in step a outside the borehole, and the second cylinder and the first cylinder are integrally connected by a first water stop ring, Then insert the above-mentioned part into the drilled hole again, and proceed to step d after supplementary pouring. The rest are the same as in Example 1.

区别于现有技术,本发明预应力防腐抗浮锚杆及其施工方法,采用缓粘结预应力钢绞线,通过新型防水结构和施工方法避免锚杆整体被水腐蚀,避免出现抗浮锚杆失效的问题,使用年限长达50年以上。Different from the prior art, the prestressed anti-corrosion and anti-floating anchor rod and its construction method of the present invention adopt slow-bonding prestressed steel strands, and the whole anchor rod is prevented from being corroded by water through a new waterproof structure and construction method, and the occurrence of anti-floating anchors is avoided. The problem of rod failure, the service life is more than 50 years.

以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书内容所作的等效结构或等效流程变换,或直接或间接运用在其它相关的技术领域,均同理包括在本发明的专利保护范围内。The above descriptions are only the embodiments of the present invention, and are not intended to limit the scope of the patent of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the description of the present invention, or directly or indirectly applied in other related technical fields, are all applicable. Similarly, it is included in the scope of patent protection of the present invention.

Claims (10)

1.一种预应力防腐抗浮锚杆,其特征在于,包括多根缓粘结预应力钢绞线,所述缓粘结预应力钢绞线在竖直方向上通过安装对中隔离架支撑,下端穿过下承压板并与挤压锚连接,所述缓粘结预应力钢绞线的上端与竖直方向呈倾斜弯折,所述缓粘结预应力钢绞线的下端套设有第一止水板,所述第一止水板、下承压板和缓粘结预应力钢绞线的下端通过预灌浆浇注一体成型形成第一柱体,所述第一止水板的部分露出于第一柱体,在第一止水板露出的部分外侧继续浇注形成第二柱体后形成预制锚杆,所述第二柱体包裹第一止水板露出部分,通过第一止水板使第一柱体和第二柱体一体连接,所述缓粘结预应力钢绞线的上部套设有第二止水板,所述第二止水板内部和缓粘结预应力钢绞线之间通过补充浇注形成补浇柱体。1. a prestressed anti-corrosion and anti-floating anchor rod is characterized in that, comprises a plurality of slow-bonding prestressed steel strands, and the slow-bonding prestressed steel strands are supported by installation centering spacers in the vertical direction , the lower end passes through the lower bearing plate and is connected with the extrusion anchor, the upper end of the slow-bonding prestressed steel strand is bent obliquely with the vertical direction, and the lower end of the slow-bonding prestressed steel strand is sleeved There is a first water stop plate, and the lower end of the first water stop plate, the lower bearing plate and the slow-bonding prestressed steel strand are integrally formed by pre-grouting casting to form a first cylinder, and the part of the first water stop plate is formed. It is exposed on the first cylinder, and the prefabricated anchor rod is formed by pouring on the outside of the exposed part of the first water stop to form a second cylinder. The second cylinder wraps the exposed part of the first water stop and passes through the first water stop. The plate makes the first cylinder and the second cylinder integrally connected, the upper part of the slow-bonding prestressed steel strand is sleeved with a second water stop plate, and the second water stop plate is inside the slow-bonding prestressed steel strand. The supplementary pouring column is formed between the lines by supplementary pouring. 2.根据权利要求1所述的预应力防腐抗浮锚杆,其特征在于,所述第二柱体直接在钻孔外部浇注完成后再将预制锚杆放入钻孔中,或者第一柱体浇注完成将上述部分放入钻孔中后再在钻孔中浇注第二柱体,所述第一柱体和第二柱体为圆柱形结构。2. The prestressed anti-corrosion and anti-floating anchor rod according to claim 1, characterized in that, after the second cylinder is directly poured outside the borehole, the prefabricated anchor rod is put into the borehole, or the first column After the body casting is completed, the above-mentioned parts are put into the drilled hole, and then the second cylinder is poured in the drilled hole, and the first and second cylinders are cylindrical structures. 3.根据权利要求1所述的预应力防腐抗浮锚杆,其特征在于,所述第一止水板为环形止水板,并且其上下两端呈漏斗状开口。3 . The prestressed anti-corrosion and anti-floating anchor rod according to claim 1 , wherein the first water stop plate is an annular water stop plate, and its upper and lower ends are open in a funnel shape. 4 . 4.根据权利要求1所述的预应力防腐抗浮锚杆,其特征在于,所述缓粘结预应力钢绞线之间以下承压板的中心间隔均匀排布,所述缓粘结预应力钢绞线的上端套设有遇水膨胀的止水环,所述缓粘结预应力钢绞线的上端穿过上承压板并且与成品锚具连接,所述缓粘结预应力钢绞线下端和下承压板之间安装有第一弹性,上端和上承压板之间安装有第二弹性件,缓粘结预应力钢绞线上端呈弯折状,并且其弯折曲率半径为5000mm。4. The prestressed anti-corrosion and anti-floating anchor rod according to claim 1, characterized in that, the center intervals of the lower bearing plates between the slow-bonding prestressed steel strands are evenly arranged, and the slow-bonding prestressed The upper end of the stress steel strand is sleeved with a water-swelling water stop ring, the upper end of the slow bonding prestressed steel strand passes through the upper bearing plate and is connected with the finished anchorage, and the slow bonding prestressed steel A first elastic piece is installed between the lower end of the strand and the lower pressure-bearing plate, and a second elastic piece is installed between the upper end and the upper pressure-bearing plate. The upper end of the slow-bonded prestressed steel strand is bent, and its bending curvature The radius is 5000mm. 5.一种如权利要求1所述的预应力防腐抗浮锚杆的施工方法,其特征在于,包括以下步骤:5. a construction method of prestressed anti-corrosion anti-floating anchor rod as claimed in claim 1, is characterized in that, comprises the following steps: a.预制锚杆:至少三根缓粘结预应力钢绞线沿圆周均布,并通过多个沿竖直方向间隔布置的对中隔离架支撑固定,下端穿过第一止水板与下承压板、第一止水板和挤压锚连接,将模具套设在钢绞线下端的外部,第一止水板的上半部分露出于模具,然后进行灌浆浇注形成第一柱体,浇注完成后拆除模具并进行养护,第一柱体外部进行防渗透处理;a. Prefabricated bolts: at least three slow-bonded prestressed steel strands are evenly distributed along the circumference, supported and fixed by a plurality of centering spacers arranged at intervals in the vertical direction, and the lower end passes through the first water stop plate and the lower bearing plate , The first water stop plate is connected with the extrusion anchor, the mold is sleeved on the outside of the lower end of the steel strand, the upper part of the first water stop plate is exposed to the mold, and then the first cylinder is formed by grouting and pouring. The mold is removed and maintained, and the outside of the first cylinder is treated with anti-penetration; b.钻孔:钻孔前,按照设计要求定出孔位,做出标记,采用湿式钻孔,钻孔后水清洗孔,直至孔口流出清水为止;b. Drilling: Before drilling, set the hole position according to the design requirements, make a mark, use wet drilling, and clean the hole with water after drilling until the hole flows out of clean water; c.灌注:将浇注导管和步骤a制成的锚杆一起放入钻孔中,采用注浆料一次性注浆完成,灌注时待孔口溢出,即可停止灌浆,浆体在终凝前应进行及时补浆,达到灌满为止,根据工程条件和设计要求确定灌注压力,确保浆体灌注密度,注浆后第二柱体和第一柱体通过第一止水环一体连接,使水只能向上渗透;c. Pouring: Put the pouring conduit and the anchor rod made in step a into the drilled hole, and complete the one-time grouting with grouting. When the orifice overflows, the grouting can be stopped. The slurry should be carried out before the final setting. Fill the grout in time until it is full. Determine the perfusion pressure according to the engineering conditions and design requirements to ensure the perfusion density of the slurry. After grouting, the second cylinder and the first cylinder are integrally connected through the first water stop ring, so that the penetrate upward; d.端部处理:沿预制锚杆外周开挖,形成施工坑,将预制锚杆上端的浇注部破除,然后套上第二止水板,第二止水板的内部补充浇注成型,使补浇柱体和第二柱体连接,再浇注垫层,垫层浇注高度必须低于第二止水板,必须使第二止水板的上端部分露出,接着在垫层上沿纵向和横向绑扎钢筋,钢筋绑扎完成后在每根缓粘结预应力钢绞线上安装止水环、上承压板、第二弹性件和锚具并预留张拉槽,然后浇注底板和面层;d. End treatment: excavate along the outer circumference of the prefabricated bolt to form a construction pit, break the pouring part at the upper end of the prefabricated bolt, and then put on the second water stop plate, and the inside of the second water stop plate is supplemented by pouring and molding, so that the supplementary pouring column is formed. The body and the second column are connected, and then the cushion is poured. The pouring height of the cushion must be lower than the second water stop, and the upper end of the second water stop must be exposed, and then the reinforcement is bound longitudinally and laterally on the cushion. After the steel bar is bound, install the water stop ring, the upper bearing plate, the second elastic member and the anchor on each slow-bonded prestressed steel strand, and reserve the tension groove, and then pour the bottom plate and surface layer; e.张拉与封锚;待底板混凝土强度达到设计强度的100%之后,方可进行张拉,预应力筋张拉完成后做好封端处理。e. Tensioning and sealing anchors; after the concrete strength of the bottom plate reaches 100% of the design strength, the tensioning can be carried out, and the end sealing treatment is done after the prestressed tendons are tensioned. 6.根据权利要求5所述的施工方法,其特征在于,所述步骤a中缓粘结预应力钢绞线下端剥除部分PE外套进行挤压,钢绞线露出挤压锚1~5mm,,清除缓粘结钢绞线表面的污渍,每隔1000mm安装一块隔离架对中,用绑扎固定,拆除模具后刷两道防水剂进行防渗透处理,通过C40混凝土进行灌浆浇注形成第一柱体。6 . The construction method according to claim 5 , wherein in the step a, the PE jacket is peeled off from the lower end of the slow-bonding prestressed steel strand for extrusion, and the steel strand is exposed to the extrusion anchor by 1-5 mm, , remove the stains on the surface of the slow-bonded steel strand, install a spacer frame every 1000mm to center, fix it with binding, remove the mold and brush two water repellants for anti-penetration treatment, and use C40 concrete for grouting to form the first cylinder. . 7.根据权利要求5所述的施工方法,其特征在于,所述步骤b中钻孔前,按设计要求定出孔位,做出标记,锚孔定位偏差不宜大于20mm,锚孔偏斜度不应大于1%,钻孔深度超过锚杆不应小于设计长度,也不大于设计长度。7. The construction method according to claim 5, characterized in that, before drilling in the step b, the hole positions are determined according to the design requirements, and marks are made, the anchor hole positioning deviation should not be greater than 20mm, and the anchor hole skewness It should not be greater than 1%, and the drilling depth exceeding the bolt should not be less than the design length, nor greater than the design length. 8.根据权利要求5所述的施工方法,其特征在于,所述步骤c中在钻孔外对步骤a中浇注完成的第一柱体上继续进行第二柱体的浇注,第二柱体和第一柱体通过第一止水环一体连接,然后将上述部分再插入到钻孔中,补充浇注后继续进行步骤d。8. The construction method according to claim 5, characterized in that, in the step c, the pouring of the second cylinder is continued on the first cylinder that has been poured in the step a outside the borehole, and the second cylinder is It is integrally connected with the first cylinder through the first water stop ring, and then the above part is inserted into the drilled hole again, and the step d is continued after supplementary pouring. 9.根据权利要求5所述的施工方法,其特征在于,所述步骤d中底板钢筋应主动避让或者绕行钢绞线,底板钢筋绑扎完成后,逐根安装橡胶止水环和焊接张拉端垫板,每根钢绞线在底板范围内防止两处止水环,用聚苯乙烯泡沫板预留张拉槽。9. construction method according to claim 5, is characterized in that, in the described step d, the reinforcement of the bottom plate should actively avoid or bypass the steel strand, and after the binding of the reinforcement of the bottom plate is completed, install the rubber water stop ring and the welding tension one by one. End pad, each steel strand prevents two water-stop rings within the scope of the bottom plate, and uses polystyrene foam board to reserve tension grooves. 10.根据权利要求5所述的施工方法,其特征在于,所述步骤f中封端处理中先将多余钢绞线采用砂轮片切除,剩余的外露钢绞线长度不小于30mm,再将张拉端及其周围清理干净,刷两道防水剂,最后坑壁涂刷水泥基渗透结晶防水材料后用微膨胀细石混凝土封堵张拉端并振捣密实。10. The construction method according to claim 5, characterized in that, in the end-capping treatment in the step f, the excess steel strands are first cut off with a grinding wheel piece, and the length of the remaining exposed steel strands is not less than 30mm, and then the The pulling end and its surroundings are cleaned up, and two coats of waterproofing agent are applied. Finally, the wall of the pit is painted with cement-based permeable crystalline waterproof material, and then the tension end is sealed with micro-expanded fine stone concrete and vibrated and compacted.
CN202010998448.2A 2020-09-22 2020-09-22 Prestressed anti-corrosion and anti-floating anchor rod and construction method Active CN111997101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010998448.2A CN111997101B (en) 2020-09-22 2020-09-22 Prestressed anti-corrosion and anti-floating anchor rod and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010998448.2A CN111997101B (en) 2020-09-22 2020-09-22 Prestressed anti-corrosion and anti-floating anchor rod and construction method

Publications (2)

Publication Number Publication Date
CN111997101A true CN111997101A (en) 2020-11-27
CN111997101B CN111997101B (en) 2025-02-18

Family

ID=73475658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010998448.2A Active CN111997101B (en) 2020-09-22 2020-09-22 Prestressed anti-corrosion and anti-floating anchor rod and construction method

Country Status (1)

Country Link
CN (1) CN111997101B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356195A (en) * 2021-06-18 2021-09-07 黄伟志 Prefabricated prestressed concrete hollow anchor rod and construction method thereof
CN113585360A (en) * 2021-07-28 2021-11-02 中国化学工程第十六建设有限公司 Anti-floating anchor rod device and construction method
CN113756358A (en) * 2021-09-04 2021-12-07 中铁十五局集团有限公司 Construction method and device for line iron tower foundation
CN115467241A (en) * 2022-10-08 2022-12-13 中铁十一局集团有限公司 Slow bonding prestress construction method for main tower stay cable anchoring area
CN115637739A (en) * 2022-10-08 2023-01-24 浙江东南网架股份有限公司 Prestress anti-floating anchor rod construction method based on digital simulation
CN116180731A (en) * 2023-03-14 2023-05-30 中交第三航务工程局有限公司 A combination structure and construction method of slow bonded prestressed anti-corrosion and anti-floating anchor rod construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202559345U (en) * 2012-02-23 2012-11-28 山东同圆设计集团有限公司 Bottom-expanded pre-stress anti-floating anchor rod
KR20140022304A (en) * 2012-08-14 2014-02-24 주식회사 동평 Using pc strand ground anchor and method for ground reinforcement using the same
CN104775428A (en) * 2015-04-23 2015-07-15 万军利 Compound-type prestressed anchor cable structure and construction method thereof
CN204898975U (en) * 2015-08-07 2015-12-23 江苏开来预应力工程有限公司 Basement bottom plate and outer wall prestressed structure
CN208618581U (en) * 2018-07-18 2019-03-19 云南建投第十七建设有限公司 Build steel plate for sealing water
CN213268016U (en) * 2020-09-22 2021-05-25 中国建筑科学研究院有限公司上海分公司 Prestressed anti-corrosion anti-floating anchor rod

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202559345U (en) * 2012-02-23 2012-11-28 山东同圆设计集团有限公司 Bottom-expanded pre-stress anti-floating anchor rod
KR20140022304A (en) * 2012-08-14 2014-02-24 주식회사 동평 Using pc strand ground anchor and method for ground reinforcement using the same
CN104775428A (en) * 2015-04-23 2015-07-15 万军利 Compound-type prestressed anchor cable structure and construction method thereof
CN204898975U (en) * 2015-08-07 2015-12-23 江苏开来预应力工程有限公司 Basement bottom plate and outer wall prestressed structure
CN208618581U (en) * 2018-07-18 2019-03-19 云南建投第十七建设有限公司 Build steel plate for sealing water
CN213268016U (en) * 2020-09-22 2021-05-25 中国建筑科学研究院有限公司上海分公司 Prestressed anti-corrosion anti-floating anchor rod

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356195A (en) * 2021-06-18 2021-09-07 黄伟志 Prefabricated prestressed concrete hollow anchor rod and construction method thereof
CN113585360A (en) * 2021-07-28 2021-11-02 中国化学工程第十六建设有限公司 Anti-floating anchor rod device and construction method
CN113756358A (en) * 2021-09-04 2021-12-07 中铁十五局集团有限公司 Construction method and device for line iron tower foundation
CN115467241A (en) * 2022-10-08 2022-12-13 中铁十一局集团有限公司 Slow bonding prestress construction method for main tower stay cable anchoring area
CN115637739A (en) * 2022-10-08 2023-01-24 浙江东南网架股份有限公司 Prestress anti-floating anchor rod construction method based on digital simulation
CN116180731A (en) * 2023-03-14 2023-05-30 中交第三航务工程局有限公司 A combination structure and construction method of slow bonded prestressed anti-corrosion and anti-floating anchor rod construction

Also Published As

Publication number Publication date
CN111997101B (en) 2025-02-18

Similar Documents

Publication Publication Date Title
CN111997101A (en) Prestressed anti-corrosion and anti-floating anchor rod and construction method
CN101343871B (en) Composite pile with high permanent stability protection layer and its production and construction method
CN103898900B (en) Band pull bar steel tube-concrete composite structure diaphragm wall and construction method thereof
CN105201514B (en) A kind of water-bearing stratum shaft wall structure and construction method
CN111851400B (en) Confined concrete column based on sea sand and seawater TRC prefabricated shell and preparation method
CN108867690B (en) Reverse construction method for pile plate retaining wall of large foundation pit
CN105604340A (en) Old house floor adding modifying method capable of improving seismic capacity and prolonging safe life
CN103924581A (en) Underground continuous wall with prefabricated concrete-filled steel tube composite structure and method for constructing underground continuous wall
CN110847167A (en) Combined enhanced uplift anchor rod device and construction method
CN213268016U (en) Prestressed anti-corrosion anti-floating anchor rod
CN105714678B (en) A kind of combined type gravity anchorage
CN110670632A (en) Construction method for horizontal construction joint of side wall of underground structure reverse construction method
CN111042832A (en) Concrete lining construction process for tunnel
CN114427224A (en) A kind of existing underground structure anti-floating reinforcement anchor rod and construction method
CN105821891B (en) For the construction method of prestress anchoraging side slope armored concrete panel and the template molding structure of concrete slab
CN210562124U (en) A kind of non-core-pulling hole-forming prestressed concrete hollow underground diaphragm wall
CN103174154A (en) A method and auxiliary dewatering device for solidly sealing underground building floor water gushing well pits
CN117947813A (en) Prestressed cantilever retaining wall structure and construction method thereof
CN203834476U (en) Waterproof structure of anti-floating steel anchor cables of basement
CN217480264U (en) Prestressing force anti-floating anchor rod pile head waterproof construction
CN214169172U (en) Self-waterproof structure without seam and wrapping structure
CN115897564A (en) Construction method for improving pile body rigidity of large-diameter bending-resistant cast-in-place pile
CN211547797U (en) Tower crane foundation structure suitable for basement raft foundation
CN114525781A (en) Prestressed rod core bag grouting combined anti-floating component and construction method
CN107100615A (en) A kind of radial direction prestressing force lining structure of drilling shaft and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant