[go: up one dir, main page]

CN111894033A - A construction method of pipe gallery with first curing and then excavation - Google Patents

A construction method of pipe gallery with first curing and then excavation Download PDF

Info

Publication number
CN111894033A
CN111894033A CN202010675635.7A CN202010675635A CN111894033A CN 111894033 A CN111894033 A CN 111894033A CN 202010675635 A CN202010675635 A CN 202010675635A CN 111894033 A CN111894033 A CN 111894033A
Authority
CN
China
Prior art keywords
pipe gallery
curing
soil
excavation
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010675635.7A
Other languages
Chinese (zh)
Inventor
陈龙
李德晟
陈永辉
孔纲强
沈政
林民国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN202010675635.7A priority Critical patent/CN111894033A/en
Publication of CN111894033A publication Critical patent/CN111894033A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/126Consolidating by placing solidifying or pore-filling substances in the soil and mixing by rotating blades

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a construction method of a pipe gallery which is solidified and excavated, in particular to a construction method of a pipe gallery which does not need supporting excavation in a soft soil area, and the construction method mainly comprises the following steps: curing agent ratio design, field treatment, in-situ curing treatment, pipe gallery excavation, pipe gallery construction and solidified soil backfilling. The method is used for solidifying the soft soil body in the pipe gallery excavation range to form solidified soil with certain self-supporting capacity, the pipe gallery is excavated in the solidified soil, the soil bodies on two sides can resist soil pressure generated by excavation, and engineering safety can be guaranteed. The excavated soil body can be used as backfill on the upper part of the pipe gallery after resource utilization, and can also provide high-quality fillers for other road projects. The method can avoid driving of the support piles, resource utilization of the waste soil body is achieved, economic benefits are higher, and environmental protection is facilitated.

Description

一种先固化后开挖的管廊施工方法A construction method of pipe gallery with first curing and then excavation

技术领域technical field

本发明属于城市地下管线布设与维护技术领域,具体涉及一种先固化后开挖的管廊施工方法。The invention belongs to the technical field of urban underground pipeline layout and maintenance, and in particular relates to a pipe gallery construction method of first curing and then excavating.

背景技术Background technique

管廊被用于放置管线,综合管廊将电力、电信、燃气、给水、热力等各种管线集于一体,具有综合性、长效性、可维护性、抗震防灾性、环保性、低成本性、投资多元性和营运可靠性等特点,是一项重要的城市市政基础工程。当今,随着城市化进程的加快和各种管线需求量的增大,城市内管廊的分布范围逐渐加大,有时不可避免地需要在软土地基上开挖管廊。The pipe gallery is used to place pipelines. The integrated pipe gallery integrates various pipelines such as electricity, telecommunications, gas, water supply, and heat, and has the advantages of comprehensiveness, long-term efficiency, maintainability, earthquake resistance and disaster prevention, environmental protection, and low cost. It is an important urban municipal infrastructure project with the characteristics of cost, investment diversity and operational reliability. Today, with the acceleration of urbanization and the increase in the demand for various pipelines, the distribution range of pipe corridors in cities is gradually increasing, and sometimes it is inevitable to excavate pipe corridors on soft soil foundations.

因施工场地的限制,城市管廊开挖多采用有支护开挖的形式。传统的管廊施工需要在施工区域两侧打设灌注桩、钢板桩进行周边支护,然后再开挖,这就要考虑大型施工设备的进场问题、城市限高问题和支护费用问题等。软土地区管廊开挖则产生大量废弃土,这些废弃土往往因其高含水量、高粘、排水性差、强度低、孔隙比大等特点难以处理,软土在运输过程需要特别注意运输车辆的密封问题,堆放时又会造成土地的占用和环境破坏。另一方面,管廊建成后的回填需要优质的填料,常规填料如宕渣的生产需要额外开山采石。目前的环境保护战略中提出了废弃土的资源化利用,如何将土进行合理的利用是主要热点。Due to the limitation of the construction site, the excavation of urban pipe gallery is mostly in the form of excavation with support. The traditional pipe gallery construction needs to drive cast-in-place piles and steel sheet piles on both sides of the construction area for peripheral support, and then excavate. This requires consideration of the entry of large construction equipment, urban height restrictions, and support costs. . Excavation of pipe gallery in soft soil area produces a large amount of waste soil. These waste soils are often difficult to handle due to their high water content, high viscosity, poor drainage, low strength, and large void ratio. During transportation of soft soil, special attention should be paid to transport vehicles. It will cause land occupation and environmental damage when stacking. On the other hand, the backfill after the completion of the pipe gallery requires high-quality fillers, and the production of conventional fillers such as slag requires additional quarrying. In the current environmental protection strategy, the resource utilization of waste soil is proposed, and how to use the soil rationally is the main focus.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供一种施工方法简单,资源化利用废弃土体,保护环境,经济效益更高的管廊施工方法。The technical problem to be solved by the present invention is to provide a pipe gallery construction method with simple construction method, resource utilization of waste soil, environmental protection and higher economic benefits.

为了解决上述技术问题,本发明采用如下技术方案:一种先固化后开挖的管廊施工方法,包括以下步骤:In order to solve the above-mentioned technical problems, the present invention adopts the following technical scheme: a construction method of a pipe gallery for excavation after curing, comprising the following steps:

步骤1,设计计算:包括固化剂配比确定和固化区域设计;Step 1, design calculation: including curing agent ratio determination and curing area design;

步骤1a,固化剂配比的确定:通过室内试验确定固化剂的配比;Step 1a, determination of the ratio of the curing agent: determine the ratio of the curing agent through an indoor test;

步骤1b,固化区域设计:对原位固化施工区域进行设计计算;Step 1b, curing area design: design and calculate the in-situ curing construction area;

步骤2,场地处理:包括清理场地和组装设备进场;Step 2, site treatment: including cleaning the site and assembling equipment into the site;

步骤2a,场地准备:主要包括原位固化施工区域场地表面的排水以及表层石块等杂物的清理;Step 2a, site preparation: mainly includes the drainage of the site surface of the in-situ curing construction area and the cleaning of surface stones and other debris;

步骤2b,组装设备进场:将供电系统、供料系统以及搅拌设备进行组装后进入步骤2a的原位固化施工区域场地;Step 2b, the assembly equipment enters the site: the power supply system, the feeding system and the stirring equipment are assembled and then enter the in-situ curing construction area site in step 2a;

步骤3,原位固化处理:对步骤2b原位固化施工区域场地的软土进行原位固化处理,所述原位固化处理是利用就地固化设备将软土与固化剂搅拌混合实现固化;Step 3, in-situ solidification treatment: perform in-situ solidification treatment on the soft soil of the in-situ solidification construction site in step 2b, and the in-situ solidification treatment is to use in-situ solidification equipment to stir and mix the soft soil and the solidifying agent to achieve solidification;

步骤4,管廊开挖:在步骤3固化后的固化土强度达到要求后,使用普通挖掘机进场开挖管廊,保留挖出的固化土;Step 4, excavation of the pipe gallery: After the strength of the solidified soil after curing in step 3 meets the requirements, use an ordinary excavator to enter the site to excavate the pipe gallery, and retain the excavated solidified soil;

步骤5,管廊施工:对步骤4开挖后的管廊进场施工;Step 5, construction of pipe gallery: enter the construction of the pipe gallery after excavation in step 4;

步骤6,固化土回填:管廊施工完成后使用步骤4保留的固化土回填。Step 6, backfill with solidified soil: After the construction of the pipe gallery is completed, backfill with the solidified soil retained in Step 4.

进一步的,所述步骤1b原位固化施工区域为梯形或者阶梯型。依据不同的固化剂配比和现场情况,固化区域需要具体设计,可以为梯形或者阶梯型,设计参数包括附图1中的B1、H、H1和坡脚α等。Further, the in-situ curing construction area in step 1b is trapezoidal or stepped. According to different curing agent ratios and site conditions, the curing area needs to be specifically designed, which can be trapezoidal or stepped. The design parameters include B1, H, H1 and slope foot α in Figure 1.

进一步的,B1〉50厘米、150厘米〉H1〉50厘米满足管廊的通水或者供电等功能。Further, B 1 > 50 cm, 150 cm > H 1 > 50 cm satisfies the functions of water passage or power supply of the pipe gallery.

进一步的,其特征在于,所述的步骤3固化剂包括粉剂或浆剂,所述步骤3中软土含水质量百分比在30%~100%,固化剂质量掺量为原土质量的6%~20%。Further, it is characterized in that the solidifying agent in step 3 includes powder or slurry, the water content of soft soil in step 3 is 30% to 100%, and the mass content of the solidifying agent is 6% to 6% of the original soil. 20%.

进一步的,所述的固化剂为常规固化剂,可市售获得。Further, the curing agent is a conventional curing agent, which is commercially available.

进一步的,所述步骤3原位固化处理可就地在清理后的场地上直接进行固化。Further, the in-situ curing treatment in step 3 may be directly cured in situ on the cleaned site.

进一步的,所述步骤3中固化方式为采用就地固化设备对淤泥竖直上下机械搅拌固化或采用分层搅拌再固化,固化处理深度至少要达到优质土层。Further, in the step 3, the solidification method is to use in-situ solidification equipment to mechanically stir and solidify the silt vertically up and down, or use layered stirring to solidify the sludge, and the solidification treatment depth must at least reach a high-quality soil layer.

进一步的,所述步骤4管廊开挖后侧面挖出的固化土可作为永久受力结构进行使用,避免多余支护,可直接使用普通挖掘机开挖。Further, the solidified soil excavated on the side after the excavation of the pipe gallery in step 4 can be used as a permanent stress-bearing structure to avoid redundant support, and can be excavated directly by ordinary excavators.

进一步的,就地固化搅拌设备可包括搅拌臂、混合滚轴、刀片机构、固化剂输料管、喷雾装置等。搅拌臂底部两侧具有向内倾斜的两斜面,在每个斜面上分别设置有至少一个混合滚轴,混合滚轴由驱动设备驱动旋转,混合滚轴呈截顶圆锥形;所述混合滚轴上分布有刀片机构;所述搅拌臂内部安装有可伸缩式的固化剂输料管。所述固化剂输料管的末端设置有喷雾装置。Further, the in-situ curing stirring equipment may include stirring arms, mixing rollers, blade mechanisms, curing agent feeding pipes, spraying devices, and the like. The two sides of the bottom of the stirring arm have two inclined surfaces inclined inward, and at least one mixing roller is respectively provided on each inclined surface. The mixing roller is driven to rotate by the driving device, and the mixing roller is in the shape of a truncated cone; the mixing roller A blade mechanism is distributed on the upper part; a retractable curing agent feeding pipe is installed inside the stirring arm. A spray device is provided at the end of the curing agent feeding pipe.

本发明有以下积极的效果:The present invention has the following positive effects:

(1)本发明是在管廊开挖前,利用搅拌设备将软土与固化剂搅拌混合固化,固化速度快,效率高。(1) In the present invention, before the excavation of the pipe gallery, the soft soil and the curing agent are stirred, mixed and cured by using a stirring device, and the curing speed is fast and the efficiency is high.

(2)本发明在管廊开挖施工中避免了支护桩的打设,操作简单,经济效益高。(2) The present invention avoids the construction of supporting piles in the excavation construction of the pipe gallery, and has the advantages of simple operation and high economic benefit.

(3)本发明实现了开挖后废弃土的再利用,节约资源,利于环保。(3) The present invention realizes the reuse of waste soil after excavation, saves resources and is beneficial to environmental protection.

附图说明Description of drawings

图1为先固化后开挖的管廊施工流程图;Figure 1 is the construction flow chart of the pipe gallery that is first cured and then excavated;

图2为先固化后开挖的管廊施工示意图;Figure 2 is a schematic diagram of the construction of the pipe gallery excavated after curing;

图3为固化区域断面图;Figure 3 is a cross-sectional view of the curing area;

图4为原位固化设备示意图。FIG. 4 is a schematic diagram of the in-situ curing equipment.

其中,B1为顶面宽度、H为底部距顶面的高度、H1为底部距管廊区域底端的高度、α为坡脚。Among them, B 1 is the width of the top surface, H is the height of the bottom from the top surface, H 1 is the height of the bottom from the bottom of the pipe gallery area, and α is the toe of the slope.

具体实施方式Detailed ways

下面结合附图和具体实施方式对本发明做进一步的详细说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. These drawings are all simplified schematic diagrams, and only illustrate the basic structure of the present invention in a schematic manner, so they only show the structures related to the present invention.

实施例1Example 1

参照图1,本发明所述先固化后开挖的管廊施工方法包括以下步骤:固化剂配比确定、固化区域设计计算、清理场地、组装设备进场、原位固化处理、管廊开挖、管廊施工、固化土回填。具体展开如下所示:Referring to Fig. 1, the construction method of the pipe gallery of the present invention for first curing and then excavation includes the following steps: determining the proportion of curing agent, designing and calculating the curing area, cleaning the site, entering the assembly equipment, in-situ curing treatment, and excavating the pipe gallery. , Pipe gallery construction, backfilling with solidified soil. The specific expansion is as follows:

步骤1,设计计算:包括固化剂配比确定和固化区域设计。Step 1, design calculation: including the determination of the curing agent ratio and the design of the curing area.

步骤1a,固化剂配比的确定:通过室内试验确定固化剂的配比。Step 1a, determination of the ratio of the curing agent: determine the ratio of the curing agent through an indoor test.

步骤1b,固化区域设计:对原位固化施工区域进行设计计算。Step 1b, curing area design: design and calculate the in-situ curing construction area.

具体地,现场取土回实验室进行强度试验,根据土体性质添加不同掺量的固化剂。一般将土样制作成直径为39.1mm,高度为80mm的圆柱样,并进行无侧限抗压强度试验,检验是否达到设计或者使用要求。无侧限抗压强度试验可以换算土体的承载力,是固化土配合比的主要试验方式之一。Specifically, the soil was taken back to the laboratory for strength tests, and different dosages of curing agents were added according to the properties of the soil. Generally, the soil sample is made into a cylindrical sample with a diameter of 39.1mm and a height of 80mm, and an unconfined compressive strength test is carried out to check whether it meets the design or use requirements. The unconfined compressive strength test can convert the bearing capacity of the soil and is one of the main test methods for the mix ratio of solidified soil.

其中,本申请所述的固化区域需要根据不同固化剂配合比进行设计,固化区域可以是梯形,也可以是阶梯型,设计参数包括B1、H、H1和坡脚α等。管廊下部留有一定的厚度保证地基承载力能够满足要求。Wherein, the curing area described in this application needs to be designed according to the mixing ratio of different curing agents. The curing area can be trapezoidal or stepped, and the design parameters include B 1 , H , H 1 and slope foot α. A certain thickness is reserved at the lower part of the pipe gallery to ensure that the bearing capacity of the foundation can meet the requirements.

各参数指标满足下述条件:B1〉50厘米、150厘米〉H1〉50厘米满足管廊的通水或者供电等功能。Each parameter index satisfies the following conditions: B 1 > 50 cm, 150 cm > H 1 > 50 cm to meet the functions of water passage or power supply of the pipe gallery.

步骤2,场地处理:包括清理场地和组装设备进场。Step 2, site treatment: including cleaning the site and assembling equipment to enter the site.

步骤2a,场地准备:主要包括原位固化施工区域场地表面的排水以及表层石块等杂物的清理;Step 2a, site preparation: mainly includes the drainage of the site surface of the in-situ curing construction area and the cleaning of surface stones and other debris;

步骤2b,组装设备进场:将供电系统、供料系统以及搅拌设备进行组装后进入步骤2a的原位固化施工区域场地。Step 2b, the assembly equipment enters the site: the power supply system, the feeding system and the stirring equipment are assembled and then enter the site of the in-situ curing construction area in step 2a.

步骤3,原位固化。根据前述步骤确定的土体固化区域进行原位固化。原位固化可采用强力搅拌就地固化或者常规土体拌合施工方式,通过搅拌装置将固化剂与土体进行均匀拌合,以达到土体加固的目的。Step 3, in-situ curing. Perform in-situ solidification according to the soil solidification area determined in the preceding steps. In-situ solidification can use strong stirring in-situ solidification or conventional soil mixing construction methods, and the solidifying agent is uniformly mixed with the soil through a stirring device to achieve the purpose of soil reinforcement.

具体地,所述采用就地固化设备对软土进行固化处理时,选用的固化剂为粉剂或浆液,根据软土含水量和环境要求进行选择。将固化剂与软土进行搅拌处理,使其快速固化。Specifically, when the in-situ solidification equipment is used to solidify the soft soil, the selected solidifying agent is powder or slurry, which is selected according to the water content of the soft soil and environmental requirements. The curing agent is mixed with soft soil for rapid curing.

本实施例采用常规混凝土密封固化剂,可市售获得。In this example, a conventional concrete sealing and curing agent is used, which is commercially available.

参照图4所示,本申请所述的原位固化设备包括供电系统、供料系统以及搅拌设备,可根据现场情况选择外接电源或自行发电。Referring to FIG. 4 , the in-situ curing equipment described in this application includes a power supply system, a material supply system, and a stirring device, and an external power supply or self-generated power can be selected according to on-site conditions.

具体地,所述就地固化搅拌设备包括搅拌臂、混合滚轴、刀片机构、固化剂输料管、喷雾装置等。搅拌臂底部两侧具有向内倾斜的两斜面,在每个斜面上分别设置有至少一个混合滚轴,混合滚轴由驱动设备驱动旋转,混合滚轴呈截顶圆锥形;所述混合滚轴上分布有刀片机构;所述搅拌臂内部安装有可伸缩式的固化剂输料管。所述固化剂输料管的末端设置有喷雾装置。Specifically, the in-situ curing and stirring equipment includes a stirring arm, a mixing roller, a blade mechanism, a curing agent feeding pipe, a spray device, and the like. The two sides of the bottom of the stirring arm have two inclined surfaces inclined inward, and at least one mixing roller is respectively provided on each inclined surface. The mixing roller is driven to rotate by the driving device, and the mixing roller is in the shape of a truncated cone; the mixing roller A blade mechanism is distributed on the upper part; a retractable curing agent feeding pipe is installed inside the stirring arm. A spray device is provided at the end of the curing agent feeding pipe.

具体地,所述固化方式为采用就地固化设备对淤泥竖直上下机械搅拌固化或采用分层搅拌再固化,固化处理深度至少要达到优质土层。Specifically, the solidification method is to use in-situ solidification equipment to mechanically stir and solidify the silt vertically up and down, or use layered stirring to solidify the sludge, and the solidification treatment depth must at least reach a high-quality soil layer.

步骤4,管廊开挖。土体固化区域强度满足相应的承载力要求后,即可使用普通的挖掘机进场,在管廊区域进行开挖。管廊周边的土体由于具有一定的强度,能够抵抗由于管廊开挖产生的土压力,保持固化区域土体的稳定。该方式能够减少内部支撑的设置,为管廊施工提供足够的空间。Step 4, pipe gallery excavation. After the strength of the solidified soil area meets the corresponding bearing capacity requirements, ordinary excavators can be used to approach the site and excavate in the pipe gallery area. Because the soil around the pipe gallery has a certain strength, it can resist the earth pressure caused by the excavation of the pipe gallery and maintain the stability of the soil in the solidified area. This method can reduce the setting of internal supports and provide enough space for the construction of the pipe gallery.

步骤5,管廊施工。管当廊区域挖出后,即可进行管廊的施工,进行管廊浇筑或者管廊的拼接,形成管廊。Step 5, pipe gallery construction. After the pipe gallery area is excavated, the construction of the pipe gallery can be carried out, and the pipe gallery can be poured or spliced to form the pipe gallery.

步骤6,固化土回填。当管廊施工完成后,管廊侧与管廊顶部的回填材料可以使用开挖出来的土料进行填筑,也可对固化土进行运输再利用,实现废弃土的资源化利用。Step 6, backfill with solidified soil. When the construction of the pipe gallery is completed, the backfill materials on the side of the pipe gallery and the top of the pipe gallery can be filled with excavated soil materials, or the solidified soil can be transported and reused to realize the resource utilization of waste soil.

Claims (5)

1.一种先固化后开挖的管廊施工方法,其特征在于,包括以下步骤:1. a pipe gallery construction method for excavation after first curing, is characterized in that, comprises the following steps: 步骤1,设计计算:包括固化剂配比确定和固化区域设计;Step 1, design calculation: including curing agent ratio determination and curing area design; 步骤1a,固化剂配比的确定:通过室内试验确定固化剂的配比;Step 1a, determination of the ratio of the curing agent: determine the ratio of the curing agent through an indoor test; 步骤1b,固化区域设计:对原位固化施工区域进行设计计算;Step 1b, curing area design: design and calculate the in-situ curing construction area; 步骤2,场地处理:包括清理场地和组装设备进场;Step 2, site treatment: including cleaning the site and assembling equipment into the site; 步骤2a,场地准备:主要包括原位固化施工区域场地表面的排水以及表层石块等杂物的清理;Step 2a, site preparation: mainly includes the drainage of the site surface of the in-situ curing construction area and the cleaning of surface stones and other debris; 步骤2b,组装设备进场:将供电系统、供料系统以及搅拌设备进行组装后进入步骤2a的原位固化施工区域场地;Step 2b, the assembly equipment enters the site: the power supply system, the feeding system and the stirring equipment are assembled and then enter the in-situ curing construction area site in step 2a; 步骤3,原位固化处理:对步骤2b原位固化施工区域场地的软土进行原位固化处理,所述原位固化处理是利用就地固化设备将软土与固化剂搅拌混合实现固化;Step 3, in-situ solidification treatment: perform in-situ solidification treatment on the soft soil of the in-situ solidification construction site in step 2b, and the in-situ solidification treatment is to use in-situ solidification equipment to stir and mix the soft soil and the solidifying agent to achieve solidification; 步骤4,管廊开挖:在步骤3固化后的固化土强度达到要求后,使用普通挖掘机进场开挖管廊,保留挖出的固化土;Step 4, excavation of the pipe gallery: After the strength of the solidified soil after curing in step 3 meets the requirements, use an ordinary excavator to enter the site to excavate the pipe gallery, and retain the excavated solidified soil; 步骤5,管廊施工:对步骤4开挖后的管廊进场施工;Step 5, construction of pipe gallery: enter the construction of the pipe gallery after excavation in step 4; 步骤6,固化土回填:管廊施工完成后使用步骤4保留的固化土回填。Step 6, backfill with solidified soil: After the construction of the pipe gallery is completed, backfill with the solidified soil retained in Step 4. 2.根据权利要求1所述的先固化后开挖的管廊施工方法,其特征在于,所述步骤1b原位固化施工区域为梯形或者阶梯型。2 . The method for constructing a pipe gallery with first curing and then excavation according to claim 1 , wherein the in-situ curing construction area in the step 1b is a trapezoid or a stepped shape. 3 . 3.根据权利要求1所述的先固化后开挖的管廊施工方法,其特征在于,所述的步骤3固化剂包括粉剂或浆剂,所述步骤3中软土含水质量百分比在30%~100%,固化剂质量掺量为原土质量的6%~20%,所述固化剂可市售获得。3. The pipe gallery construction method for excavation after first curing according to claim 1, is characterized in that, described step 3 solidifying agent comprises powder or slurry, and in described step 3, soft soil moisture mass percentage is 30% ~100%, the mass dosage of the curing agent is 6% ~ 20% of the original soil mass, and the curing agent is commercially available. 4.根据权利要求1所述的先固化后开挖的管廊施工方法,其特征在于,所述步骤3原位固化处理可就地在清理后的场地上直接进行固化。4. The pipe gallery construction method of first curing and then excavating according to claim 1, characterized in that, the in-situ curing treatment in step 3 can be directly cured in situ on the cleaned site. 5.根据权利要求1所述的先固化后开挖的管廊施工方法,其特征在于,所述步骤4管廊开挖后侧面挖出的的固化土可置于原来的支护桩位置作为永久受力结构进行使用,避免多余支护可直接使用普通挖掘机开挖。5. The pipe gallery construction method of first curing and then excavating according to claim 1, is characterized in that, the solidified soil excavated on the side after the excavation of the pipe gallery in the step 4 can be placed in the original supporting pile position as The permanent stress structure is used to avoid unnecessary support, and ordinary excavators can be directly used for excavation.
CN202010675635.7A 2020-07-14 2020-07-14 A construction method of pipe gallery with first curing and then excavation Pending CN111894033A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010675635.7A CN111894033A (en) 2020-07-14 2020-07-14 A construction method of pipe gallery with first curing and then excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010675635.7A CN111894033A (en) 2020-07-14 2020-07-14 A construction method of pipe gallery with first curing and then excavation

Publications (1)

Publication Number Publication Date
CN111894033A true CN111894033A (en) 2020-11-06

Family

ID=73191757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010675635.7A Pending CN111894033A (en) 2020-07-14 2020-07-14 A construction method of pipe gallery with first curing and then excavation

Country Status (1)

Country Link
CN (1) CN111894033A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1517495A (en) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 Continuous redlizing method of underground engieering, tunnel and underground tunnel, reinforced engineering, sealing engineering and drainage work obtained by guide punching
JP2006138091A (en) * 2004-11-11 2006-06-01 Elf:Kk Construction method for burying tank and the like
CN105178355A (en) * 2015-10-20 2015-12-23 重庆交通大学 Stratum pre-reinforcement treatment method for underground space construction
CN104863113B (en) * 2015-06-04 2017-08-22 杭州特诚基础工程科技有限公司 The method and mixing plant of original place curing process are carried out to in-situ soil
CN110847929A (en) * 2019-11-20 2020-02-28 中铁二十局集团有限公司 Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1517495A (en) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 Continuous redlizing method of underground engieering, tunnel and underground tunnel, reinforced engineering, sealing engineering and drainage work obtained by guide punching
JP2006138091A (en) * 2004-11-11 2006-06-01 Elf:Kk Construction method for burying tank and the like
CN104863113B (en) * 2015-06-04 2017-08-22 杭州特诚基础工程科技有限公司 The method and mixing plant of original place curing process are carried out to in-situ soil
CN105178355A (en) * 2015-10-20 2015-12-23 重庆交通大学 Stratum pre-reinforcement treatment method for underground space construction
CN110847929A (en) * 2019-11-20 2020-02-28 中铁二十局集团有限公司 Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting

Similar Documents

Publication Publication Date Title
CN107419630B (en) Soft soil foundation high-filling embankment capable of effectively controlling post-construction settlement and construction method
CN108560542B (en) A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof
CN102926398B (en) A kind of for Salt Lake Area iron tower of power transmission line bolts of inclined column type anti-corrosion foundation construction method
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN105019422A (en) Foundation construction method for local solidification of topsoil and composite pile bearing
CN206070508U (en) Device for reinforcing foundation
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN110886317B (en) Foundation trench earthwork backfill construction method for steel sheet pile supporting structure of urban comprehensive pipe gallery
CN109252542B (en) A kind of tree root stump lightweight retaining wall for road widening and construction method thereof
CN108412016A (en) Underground tube body assures construction method
CN108930284A (en) Assembled retaining wall structure and backfilling method
CN109706952A (en) Large-scale well-sinking construction method
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN105780764A (en) Light cemented soil composite mixing pile
CN114197261B (en) Road widening roadbed filling method for immersed road section
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN108104150A (en) Transmission tower cast-in-situ reinforced concrete hollow borehole class basis and its construction method
CN113308954B (en) Construction method of anchor rod foam concrete widening roadbed
CN207211188U (en) Outer wall of underground structure HCMW engineering methods overlap wall
CN111894033A (en) A construction method of pipe gallery with first curing and then excavation
CN117127642A (en) Fluidized solidified soil bearing platform structure and manufacturing method
CN215051733U (en) Construction access road structure in deep soft soil area
CN111663391B (en) Roadbed double-crust layer on-site reinforcing and filling structure and method in muddy soft soil area
CN220486480U (en) Soft soil foundation pipeline trench support-free structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201106