[go: up one dir, main page]

CN111851307A - Construction method of large-span prefabricated corrugated web composite box girder transport frame - Google Patents

Construction method of large-span prefabricated corrugated web composite box girder transport frame Download PDF

Info

Publication number
CN111851307A
CN111851307A CN202010768725.0A CN202010768725A CN111851307A CN 111851307 A CN111851307 A CN 111851307A CN 202010768725 A CN202010768725 A CN 202010768725A CN 111851307 A CN111851307 A CN 111851307A
Authority
CN
China
Prior art keywords
prefabricated
box girder
composite box
span
web composite
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010768725.0A
Other languages
Chinese (zh)
Inventor
李可科
王成伟
刘伟
王坤杰
许涛
王涛
赵永忠
毋冬冬
樊森
伍琦
刘拯
刘祥元
杨纪硕
武迎宾
叶耿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, No6 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202010768725.0A priority Critical patent/CN111851307A/en
Publication of CN111851307A publication Critical patent/CN111851307A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60PVEHICLES ADAPTED FOR LOAD TRANSPORTATION OR TO TRANSPORT, TO CARRY, OR TO COMPRISE SPECIAL LOADS OR OBJECTS
    • B60P3/00Vehicles adapted to transport, to carry or to comprise special loads or objects
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种大跨径预制装配式波形腹板组合箱梁运架施工方法,包括以下步骤:步骤一,将模块运输车进行模块化组合成一套组合式模块运输车(1),总体宽度为两片梁的宽度;步骤二,将波形钢腹板组合箱梁安装于组合式模块运输车(1)的驼梁(2)上;步骤三,将波形钢腹板组合箱梁运至架桥机(4)的尾部喂梁区;步骤四,应用架桥机(4)进行全幅梁体架设;第五步,相邻梁体之间将横隔板及顶板位置钢筋安装,悬吊模板安装、浇筑混凝土。本发明的方法解决了大跨径预制装配式波形腹板组合箱梁利用机械设备运输及整孔架设问题,为装配式钢混组合桥梁的机械化建造开辟了新方式,推动了更加经济的大跨径预制装配式波形钢腹板梁的应用。

Figure 202010768725

A construction method for large-span prefabricated prefabricated corrugated web composite box girder transport frame, comprising the following steps: step 1, modularly combining a modular transport vehicle into a set of combined modular transport vehicles (1), the overall width of which is two pieces The width of the beam; Step 2, install the corrugated steel web composite box girder on the camel beam (2) of the combined modular transport vehicle (1); Step 3, transport the corrugated steel web composite box girder to the bridge erecting machine ( 4) at the rear of the beam feeding area; Step 4, use the bridge erecting machine (4) to erect the full beam body; Step 5, install the steel bars at the position of the diaphragm and the roof between the adjacent beam bodies, install the suspension formwork, and pour concrete. The method of the invention solves the problems of mechanical equipment transportation and whole hole erection of large-span prefabricated prefabricated corrugated web composite box beams, opens up a new way for the mechanized construction of prefabricated steel-concrete composite bridges, and promotes more economical large-span Application of prefabricated corrugated steel web beams.

Figure 202010768725

Description

一种大跨径预制装配式波形腹板组合箱梁运架施工方法Construction method of large-span prefabricated corrugated web composite box girder transport frame

技术领域technical field

本发明涉及预制装配式桥梁施工的技术领域,具体地,涉及一种大跨径预制装配式波形腹板组合箱梁运架施工方法。The invention relates to the technical field of prefabricated bridge construction, in particular to a large-span prefabricated prefabricated corrugated web composite box girder construction method.

背景技术Background technique

国内大跨度波形钢腹板组合梁桥目前均为悬索、斜拉、连续刚构桥桥型。波形钢腹板组合梁桥为40-60m跨径内预制装配式桥梁中最经济的梁型,与传统的梁桥相比,充分利用了波形钢板的褶皱效应和混凝土抗压强度高、波形钢腹板抗剪屈服强度高的优点,有效地将钢材、混凝土和预应力三种材料结合起来,能够提高材料的使用效率,降低工程造价。但国内外波形钢腹板组合梁桥主要采用支架现浇、挂篮悬臂浇筑或顶推等建造方式,施工工艺复杂,材料用量大,现场作业多。已建成预制装配式波形钢腹板桥梁多为吊车吊装架设工艺。因此,如何实现预制装配化的大跨度波形钢腹板组合梁桥进行运输、机械化整孔架设,以节约资源能源、减少施工污染、降低工程造价、提升劳动生产率和质量安全水平,尤为迫切。At present, domestic long-span corrugated steel web composite girder bridges are all suspension, cable-stayed and continuous rigid frame bridge types. The corrugated steel web composite beam bridge is the most economical beam type among prefabricated bridges with a span of 40-60m. Compared with the traditional beam bridge, it makes full use of the wrinkle effect of corrugated steel plates and the high compressive strength of concrete and corrugated steel. The high shear yield strength of the web plate effectively combines the three materials of steel, concrete and prestress, which can improve the efficiency of material use and reduce the project cost. However, the corrugated steel web composite girder bridges at home and abroad are mainly constructed by cast-in-place brackets, hanging basket cantilever casting or jacking. Most of the prefabricated corrugated steel web bridges that have been built are hoisted and erected by cranes. Therefore, how to realize prefabricated large-span corrugated steel web composite girder bridges for transportation and mechanized whole-hole erection to save resources and energy, reduce construction pollution, reduce project costs, and improve labor productivity and quality and safety is particularly urgent.

目前国内针对大跨径预制装配式波形梁运架施工方法描述甚少,如中国专利“装配式波形钢斜腹板组合梁的施工方法”(申请号201410201710.0)公开了装配式波形钢斜腹板组合梁架设时先施工桥台或桥墩,搭设临时支架,并分段将两片预制波形钢斜腹板边梁吊装至支撑体系上,连接钢筋,浇注两片边梁之间的纵向湿接缝以及顶板翼缘板,形成宽箱梁结构的组合梁,形成整体断面。所述待浇注的混凝土湿接缝达到一定强度值后,拆除支架,完成体系转换,结束施工。这种方式的缺点为:梁段较多,为满足架设,需要在各跨桥位现场搭设临时支架施工,将梁段架设后,在支架系统上绑扎底板及顶板钢筋,再浇筑混凝土,该方式工艺复杂,现场作业量大,且安全管理难度大,质量控制难度大,施工效率低,受地形水文限制多,在无条件搭设临时支架的桥梁中无法实施。并且未对运输方式及桥机架设进行说明。At present, there are few domestic descriptions about the construction method of large-span prefabricated corrugated beams. When erecting composite beams, first construct abutments or piers, set up temporary supports, and hoist two prefabricated corrugated steel sloping web edge beams to the support system in sections, connect steel bars, and pour longitudinal wet joints between the two edge beams And the roof flange plate, forming a composite beam of a wide box beam structure, forming an integral section. After the concrete wet joint to be poured reaches a certain strength value, the support is removed, the system conversion is completed, and the construction is ended. The disadvantage of this method is that there are many beam sections. In order to meet the erection requirements, temporary supports need to be erected on the site of each span bridge. After the beam sections are erected, the bottom plate and roof steel bars are bound on the support system, and then concrete is poured. This method The process is complex, the on-site workload is large, and the safety management is difficult, the quality control is difficult, the construction efficiency is low, and there are many restrictions on topography and hydrology, which cannot be implemented in bridges with unconditional temporary supports. And it does not explain the transportation method and the bridge frame installation.

发明内容SUMMARY OF THE INVENTION

为解决现有技术中存在的上述问题,本发明提供了一种大跨径预制装配式波形腹板组合箱梁运架施工方法。本发明的方法解决了大跨径预制装配式波形腹板组合箱梁利用机械设备运输及整孔架设问题,为装配式钢混组合桥梁的机械化建造开辟了新方式,推动了更加经济的大跨径预制装配式波形钢腹板梁的应用。In order to solve the above problems existing in the prior art, the present invention provides a large-span prefabricated and assembled corrugated web composite box girder construction method. The method of the invention solves the problems of mechanical equipment transportation and whole hole erection of large-span prefabricated prefabricated corrugated web composite box beams, opens up a new way for the mechanized construction of prefabricated steel-concrete composite bridges, and promotes more economical large-span Application of prefabricated corrugated steel web beams.

为实现上述目的,本发明提供了一种大跨径预制装配式波形腹板组合箱梁运架施工方法,包括以下步骤:In order to achieve the above purpose, the present invention provides a large-span prefabricated construction method for the corrugated web composite box girder transport frame, comprising the following steps:

步骤一,将模块运输车进行模块化组合,四台模块运输车组合成一套组合式模块运输车,组合式模块运输车的总体宽度为两片梁的宽度;Step 1, modularly combining the modular transport vehicles, four modular transport vehicles are combined into a set of combined modular transport vehicles, and the overall width of the combined modular transport vehicles is the width of two beams;

步骤二,将波形钢腹板组合箱梁安装于组合式模块运输车的驼梁上,并捆扎牢固;Step 2, install the corrugated steel web composite box girder on the camel girder of the combined modular transport vehicle, and bundle it firmly;

步骤三,组合模块运输车采用行走单幅运输方式将波形钢腹板组合箱梁运至架桥机的尾部喂梁区;In step 3, the combined module transport vehicle transports the corrugated steel web combined box girder to the rear beam feeding area of the bridge erecting machine by means of single-width walking;

步骤四,应用架桥机进行全幅梁体架设;架桥机的支腿无需移动,通过天车和主桁移动完成整孔梁体的架设;Step 4: The bridge erection machine is used to erect the full-width beam body; the outriggers of the bridge erection machine do not need to be moved, and the whole-hole beam body is erected by moving the crane and the main truss;

第五步,相邻梁体之间将横隔板及顶板位置钢筋安装,悬吊模板安装、浇筑混凝土。由此无需搭设支架,现场工作量小,成桥速度快。The fifth step is to install the steel bars at the positions of the diaphragm and the roof between the adjacent beam bodies, install the suspension formwork, and pour concrete. Therefore, there is no need to erect brackets, the workload on site is small, and the bridge forming speed is fast.

优选的,所述步骤二中,驼梁由型钢组焊形成箱型,与组合式模块运Preferably, in the second step, the camel beam is welded by section steel to form a box shape, and is transported with the combined module.

输车的连接部位为平衡轴。驼梁能在一定范围内通过平衡轴进行适当转动,可适应不同纵坡情况下进行运输时梁体的稳定性。The connecting part of the truck is the balance shaft. The camel beam can be properly rotated through the balance shaft within a certain range, and can adapt to the stability of the beam body during transportation under different longitudinal slope conditions.

在上述任一方案中优选的是,所述步骤三中,组合模块运输车在已完成架设梁体的两片梁上行走,轮胎运行轨迹为梁肋位置;箱梁的梁肋位置承载力大,结构更加安全。Preferably in any of the above solutions, in the third step, the combined module transport vehicle walks on the two beams on which the beam body has been erected, and the running track of the tires is the beam rib position; the beam rib position of the box beam has a large bearing capacity , the structure is more secure.

在上述任一方案中优选的是,所述步骤四中,架梁的顺序为内边梁、外边梁、中梁。In any of the above solutions, preferably, in the fourth step, the order of the beams is the inner side beam, the outer side beam, and the middle beam.

在上述任一方案中优选的是,所述步骤四中,架设内边梁时天车下发吊具与梁体进行连接、起吊,完成梁体的架设。In any of the above solutions, preferably, in the fourth step, when the inner side beam is erected, the hoist is connected and hoisted by the crane and the beam body to complete the erection of the beam body.

在上述任一方案中优选的是,所述步骤四中,外边梁架设时,在中梁的部位安装临时支座,其中临时支座顶面高于墩台顶部的设计挡块的高度。天车下发吊具与外边梁的梁体进行连接、起吊,临时存放于中梁处。In any of the above solutions, preferably, in the fourth step, when the outer side beams are erected, a temporary support is installed at the position of the middle beam, wherein the top surface of the temporary support is higher than the height of the designed block on the top of the pier. The spreader issued by the crane is connected and lifted with the beam body of the outer beam, and is temporarily stored at the middle beam.

在上述任一方案中优选的是,所述步骤四中,天车与外边梁的梁体解锁后归位,架桥机的左右两侧的主桁同步横移,待主桁到临时存放的外边梁的正上方时停止,主桁安装悬吊装置,与外边梁的梁体进行连接并进行提升;主桁再次横移,待主桁移至外边梁的设计位置后停止,悬吊装置下放至梁体设计高度,完成外边梁的梁体架设。In any of the above solutions, it is preferred that, in the fourth step, the crane and the beam bodies of the outer side beams are unlocked and returned to their positions, and the main trusses on the left and right sides of the bridge erecting machine are synchronously moved laterally, and the main trusses are temporarily stored until the main trusses are stored. When it stops just above the outer side beam, the main truss is installed with a suspension device to connect with the beam body of the outer side beam and lift; To the design height of the beam body, the beam body erection of the outer beam is completed.

在上述任一方案中优选的是,所述步骤四中,通过天车完成中梁的架设;若需要架设有多片中梁的桥梁时,可先利用天车将中梁架设完毕,最后一片与外边梁相邻的中梁最后架设。解决了当必须用天车吊装架设边梁时,桥机支腿横梁横向尺寸需设计足够长、主桁横移过多造成稳定性差的问题。该方式提高了桥机横向负重抗倾覆能力,保证了安全性。Preferably in any of the above solutions, in the step 4, the erection of the middle beam is completed by the overhead crane; if a bridge with multiple middle beams needs to be erected, the overhead crane can be used to complete the erection of the middle beam first, and the last one The middle beam adjacent to the outer side beam is erected last. It solves the problem that when the side beam must be hoisted and erected by the crane, the lateral dimension of the bridge outrigger beam needs to be designed to be long enough, and the main truss has too much lateral movement, resulting in poor stability. This method improves the lateral load-bearing and anti-overturning ability of the bridge crane and ensures the safety.

本发明的有益效果为:The beneficial effects of the present invention are:

1.本发明充分利用了模块车的快速组合特点,组合后承载能力更强,稳定性更好,轮胎接地总面积大,对运输通道承载力要求低。大跨度预制梁在运输时,驼梁的平衡轴能在一定范围转动,满足了在不同纵坡条件下的运输要求。采用行走半幅梁上运梁的方式将梁体整孔运至桥位,轮胎行走轨迹为两片梁的梁肋位置,对桥梁结构受力影响小。1. The present invention makes full use of the rapid combination characteristics of the modular vehicle, and after the combination, the bearing capacity is stronger, the stability is better, the total tire grounding area is large, and the requirements for the bearing capacity of the transportation channel are low. When the large-span prefabricated beam is transported, the balance shaft of the camel beam can be rotated within a certain range, which meets the transportation requirements under different longitudinal slope conditions. The whole hole of the beam body is transported to the bridge position by means of walking on the half-width beam, and the tire walking track is the position of the beam rib of the two beams, which has little influence on the bridge structure.

2.多数桥梁桥位无大吨位车辆运输条件,传统的搭设支架,吊车进行节段吊装对桥位处地基要求高。本发明采用梁上运梁方式对桥位下地形地貌无任何要求,解决了运输问题。并且本发明充分利用架桥机天车及主桁横移的方式架设整孔预制梁,支腿无需移动,桥机的安全性更好,能提高架设效率,同时为类似的小悬臂边梁的桥型梁板架设提供了一种新的技术思路。2. Most bridges do not have large-tonnage vehicle transportation conditions. The traditional erection of brackets and segmental hoisting by cranes have high requirements for the foundation of the bridge. The present invention adopts the method of transporting the beam on the beam without any requirement on the topography under the bridge position, and solves the transportation problem. In addition, the present invention makes full use of the way of the overhead crane and the main truss of the bridge erection machine to erect the whole-hole prefabricated beam, the outriggers do not need to be moved, the safety of the bridge machine is better, the erection efficiency can be improved, and at the same time, it can be used for similar small cantilever side beams. Bridge beam slab erection provides a new technical idea.

3.常规大跨度预制装配式梁分段吊装工艺,现场需搭设支架,之后对梁体进行顶底板连接,形成整体结构,现场作业时间长,工作量大,安全隐患多。本发明采用整孔架设能有效加快施工进度,降低安全风险。解决了大跨径装配式波形钢腹板组合箱梁整孔架设施工技术难题,提供了一种更适合跨河、跨路及桥位地势不适宜大型车辆通行的大跨径预制装配式波形钢腹板组合箱梁的运架施工方法。3. Conventional large-span prefabricated beams are hoisted in sections, and brackets need to be erected on site, and then the top and bottom plates of the beams are connected to form an overall structure. The on-site operation time is long, the workload is large, and there are many potential safety hazards. The invention adopts the whole hole erection, which can effectively speed up the construction progress and reduce the safety risk. It solves the technical problems in the construction of the whole hole frame of the long-span prefabricated corrugated steel web composite box girder, and provides a long-span prefabricated corrugated steel that is more suitable for crossing rivers, roads and bridges that are not suitable for large vehicles to pass through. Construction method of frame transport for web composite box girder.

4.本发明可适于应用到无航运条件的桥梁和市政工程中,在运输过程中采用梁上运梁的方式将波形钢腹板箱梁整孔运至桥位,避免对既有架设梁板的受力破坏,通过架桥机横移进行全幅整孔架设,降低现场工作量,更大的提升了预制装配式波形钢腹板桥梁机械化建造水平。4. The present invention can be applied to bridges and municipal projects without shipping conditions. During transportation, the corrugated steel web box girder is transported to the bridge position by means of beam-on-beam transportation to avoid damage to the existing erected beams. If it is damaged by force, the bridge erection machine is traversed to carry out full-width and whole-hole erection, which reduces the on-site workload and greatly improves the mechanized construction level of prefabricated corrugated steel web bridges.

5.本发明实施的运输、架设工艺,采用在单幅两片梁上运用组合式模块车运梁的方式将大跨径波形钢腹板箱梁运输至架桥机尾部,避免梁车在已架设梁板上行走时集中受力,引起桥梁质量病害。通过利用架桥机主桁横移兼具吊装功能解决整孔外边梁的架设问题,为大跨径预制装配式波形梁的运输快速架设开辟了新技术。5. The transportation and erection process implemented by the present invention adopts the method of using a combined modular truck to transport the beam on a single two-piece beam to transport the large-span corrugated steel web box girder to the rear of the bridge erecting machine, so as to avoid the girder truck in the When the beams are erected, the force is concentrated when walking, causing the quality of the bridge to be damaged. By utilizing the lateral movement of the main truss of the bridge erection machine and the hoisting function to solve the erection problem of the outer side beams of the whole hole, a new technology is opened up for the rapid erection of large-span prefabricated corrugated beams.

附图说明Description of drawings

图1是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法所使用的组合式模块运输车的断面图;1 is a cross-sectional view of a combined modular transport vehicle used in the large-span prefabricated corrugated web combined box girder transport frame construction method according to the present invention;

图2是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的组合式模块运输车梁上运梁的示意图;2 is a schematic diagram of the upper transport beam of the combined modular transport vehicle beam according to the large-span prefabricated prefabricated corrugated web combined box beam transport frame construction method of the present invention;

图3是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的波形钢腹板箱梁喂梁的示意图;3 is a schematic diagram of the corrugated steel web box girder feeding beam according to the large-span prefabricated corrugated web composite box girder transport frame construction method of the present invention;

图4是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的架桥机吊装波形钢腹板箱梁的示意图;4 is a schematic diagram of hoisting a corrugated steel web box girder by a bridge erecting machine according to a large-span prefabricated prefabricated corrugated web composite box girder frame transport construction method of the present invention;

图5-1是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的外边梁临时存放于中梁位置的示意图;Fig. 5-1 is a schematic diagram showing that the outer side beams are temporarily stored in the middle beam position according to the large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method of the present invention;

图5-2是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的外边梁临时存放于中梁位置的细部图;5-2 is a detailed view of the outer side beams temporarily stored in the middle beam position according to the large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method of the present invention;

图6-1是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的架桥机主桁横移后与外边梁连接的示意图;Figure 6-1 is a schematic diagram showing that the main truss of the bridge erecting machine is connected to the outer beam after the main truss of the bridge erecting machine is moved laterally according to the large-span prefabricated prefabricated corrugated web composite box girder construction method of the present invention;

图6-2是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的架桥机主桁横移后与外边梁连接构造的细部图;6-2 is a detailed view of the connection structure with the outer beam after the main truss of the bridge erecting machine is moved laterally according to the large-span prefabricated prefabricated corrugated web composite box girder construction method of the present invention;

图7-1是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的外边梁利用架桥机主桁横移安装的示意图;Figure 7-1 is a schematic diagram of the lateral beam installation of the main truss of the bridge erecting machine according to the large-span prefabricated prefabricated corrugated web composite box girder frame transport construction method of the present invention;

图7-2是根据本发明的大跨径预制装配式波形腹板组合箱梁运架施工方法的外边梁利用架桥机主桁横移、落梁的细部图。Figure 7-2 is a detailed view of the outer side beams using the main truss of the bridge erection machine to move laterally and drop the beams according to the large-span prefabricated prefabricated corrugated web composite box girder frame transport construction method of the present invention.

其中,1.组合式模块运输车;2.驼梁;3.平衡轴;4.架桥机;5.天车;6.主桁;7.吊具;8.临时支座;9.设计挡块;10.悬吊装置。Among them, 1. Combined modular transport vehicle; 2. Camel beam; 3. Balance shaft; 4. Bridge erecting machine; 5. Crane; 6. Main girder; 7. Spreader; Block; 10. Suspension device.

具体实施方式Detailed ways

下面将结合本申请的附图和具体实施方式,对本申请的技术方案进行详细的说明,但如下实施例仅是用以理解本发明,本申请中的实施例及实施例中的特征可以相互组合,本申请可以由权利要求限定和覆盖的多种不同方式实施。The technical solutions of the present application will be described in detail below with reference to the drawings and specific embodiments of the present application, but the following examples are only for understanding the present invention, and the examples in the present application and the features in the examples can be combined with each other , the application may be implemented in many different ways as defined and covered by the claims.

以某双向六车道黄河特大桥工程为例,进行技术说明。其堤内北引桥和南引桥均为预制装配式波形钢腹板组合箱梁、单孔共计6片梁,单片梁跨径50米,梁重380吨。Taking a two-way six-lane Yellow River super bridge project as an example, the technical description is given. The north approach bridge and the south approach bridge in the embankment are all prefabricated corrugated steel web composite box girders, a total of 6 beams with a single hole, a single beam span of 50 meters, and a beam weight of 380 tons.

根据工程实际情况及工期要求,施工中主要解决以下问题:预制梁板跨度大,桥梁纵坡最大为2.65%,桥梁墩位全部位于黄河滩内,地下水位高,大吨位吊装及运输设备无法通行。单片波形钢腹板组合箱梁长度为50米,重量380吨,整孔架设难度大。According to the actual situation of the project and the requirements of the construction period, the following problems are mainly solved in the construction: the span of prefabricated beams and slabs is large, the maximum longitudinal slope of the bridge is 2.65%, the bridge piers are all located in the Yellow River beach, the groundwater level is high, and the large-tonnage hoisting and transportation equipment cannot pass. . The single-piece corrugated steel web composite box girder has a length of 50 meters and a weight of 380 tons, so it is difficult to erect the whole hole.

采用本发明所述的一种大跨径预制装配式波形腹板组合箱梁运架施工方法,包括以下步骤:The construction method of the large-span prefabricated prefabricated corrugated web composite box girder transport frame according to the present invention includes the following steps:

步骤一,首先将模块运输车进行模块化组合,如图1所示。Step 1: First, modularize the modular transport vehicle, as shown in Figure 1.

模块运输车具有快速组合功能,四台模块运输车通过液压系统及电控系统组合成一套组合式模块运输车1,组合式模块运输车1投影呈矩形,总体长度及宽度根据需要进行调整,以列举工程为例,总宽度为8.5米,能够同时跨两片梁行走。组合式模块运输车1的顶部安装驼梁2,用于承载及固定箱梁用。The modular transporter has the function of quick combination. Four modular transporters are combined into a set of modular transporter 1 through hydraulic system and electronic control system. The projection of the modular transporter 1 is rectangular, and the overall length and width can be adjusted as Taking the project as an example, the total width is 8.5 meters, and it can walk across two beams at the same time. A camel beam 2 is installed on the top of the combined modular transport vehicle 1 for carrying and fixing the box beam.

步骤二,在梁厂利用提梁机将波形钢腹板组合箱梁安装于组合式模块运输车1的驼梁2上。驼梁2由型钢组焊形成箱型,与组合式模块运输车1的连接部位为平衡轴3,其能在一定范围内进行适当转动,以适应不同纵坡情况下运输时梁体的稳定性,如图1、图2所示。In step 2, the corrugated steel web composite box girder is installed on the camel girder 2 of the combined modular transport vehicle 1 by using a girder lifter in the beam factory. The camel beam 2 is welded by section steel to form a box shape, and the connection part with the combined modular transport vehicle 1 is the balance shaft 3, which can be properly rotated within a certain range to adapt to the stability of the beam body during transportation under different longitudinal slope conditions. , as shown in Figure 1 and Figure 2.

步骤三,梁上运梁。组合式模块运输车1采用行走单幅的运输轨迹将波形钢腹板组合箱梁运至架桥机4的尾部喂梁区。组合式模块运输车1在已完成架设梁体的两片梁上行走,轮胎运行轨迹为梁肋位置,保证桥梁结构受力安全,如图2所示。The third step is to transport the beam on the beam. The combined modular transport vehicle 1 transports the corrugated steel web composite box girder to the rear beam feeding area of the bridge erecting machine 4 by using a single-width transport track. The combined modular transport vehicle 1 walks on the two beams on which the beam body has been erected, and the running track of the tires is the position of the beam rib to ensure the safety of the bridge structure, as shown in Figure 2.

步骤四,应用架桥机4进行全幅梁体架设。In step 4, the bridge erection machine 4 is used to erect the full-width beam body.

架桥机4的支腿无需移动,通过天车5和主桁6完成整孔梁体架设。架梁顺序为内边梁、外边梁、中梁。The legs of the bridge erecting machine 4 do not need to be moved, and the whole-hole beam body is erected through the crane 5 and the main truss 6 . The order of frame beams is inner side beam, outer side beam, middle beam.

内边梁的架设情况如图3、图4所示。The erection of the inner side beam is shown in Figure 3 and Figure 4.

架设内边梁时天车5下发吊具7与梁体进行连接、起吊,完成梁体的架设。内边梁架设后提供了人员前后行走作业的安全通道。如图3、图4所示。When erecting the inner side beam, the crane 5 sends a spreader 7 to connect and lift the beam body to complete the erection of the beam body. After the inner side beam is erected, it provides a safe passage for people to walk forward and backward. As shown in Figure 3 and Figure 4.

外边梁架设时,在中梁部位安装临时支座8,其中临时支座8的顶面高于墩台顶部的设计挡块9的高度。天车5下发吊具7与梁体进行连接、起吊,临时存放于中梁的位置处。如图5-1、5-2所示。When the outer side beams are erected, a temporary support 8 is installed at the middle beam, wherein the top surface of the temporary support 8 is higher than the height of the designed block 9 at the top of the pier. The crane 5 sends a spreader 7 to connect and lift the beam body, and temporarily store it at the position of the middle beam. As shown in Figures 5-1 and 5-2.

天车5与梁体解锁后归位,架桥机4的左右两侧的主桁6同步横移,待主桁6移动到临时存放的外边梁的正上方时停止,主桁6安装悬吊装置10,与梁体进行连接并适当提升,如图6-1、6-2所示。The crane 5 and the beam are unlocked and returned to their positions, and the main trusses 6 on the left and right sides of the bridge erecting machine 4 move synchronously. When the main truss 6 moves to the top of the temporarily stored outer beam, it stops. The main truss 6 is installed and suspended. The device 10 is connected to the beam body and properly lifted, as shown in Figures 6-1 and 6-2.

主桁6再次横移,待主桁6移至外边梁设计位置后停止,悬吊装置10下放至设计高度,完成梁体架设。如图7-1、7-2所示。The main truss 6 is moved laterally again, and stops when the main truss 6 is moved to the design position of the outer beam, and the suspension device 10 is lowered to the design height to complete the beam erection. As shown in Figures 7-1 and 7-2.

通过天车5完成中梁的架设,若需要架设有多片梁体的桥梁时,可先利用天车5将中梁架设完毕,最后一片与外边梁相邻的中梁最后架设。The middle beam is erected by the overhead crane 5. If a bridge with multiple beams needs to be erected, the overhead crane 5 can be used to complete the erection of the middle beam first, and the last middle beam adjacent to the outer side beam is erected last.

步骤五,将相邻梁体之间的横隔板及顶板位置处的钢筋连接安装,悬吊模板安装、浇筑混凝土。Step 5: Connect and install the steel bars at the position of the diaphragm between the adjacent beam bodies and the top plate, install the suspension formwork, and pour concrete.

本发明充分利用了模块车的快速组合特点,组合后承载能力更强,稳定性更好,轮胎接地总面积大,对运输通道承载力要求低。大跨度预制梁在运输时,驼梁的平衡轴能在一定范围转动,满足了在不同纵坡条件下的运输要求。采用行走半幅梁上运梁的方式将梁体整孔运至桥位,轮胎行走轨迹为两片梁的梁肋位置,对桥梁结构受力影响小。The invention makes full use of the rapid combination feature of the modular vehicle, and after the combination, the bearing capacity is stronger, the stability is better, the total ground area of the tire is large, and the requirement for the bearing capacity of the transportation channel is low. When the large-span prefabricated beam is transported, the balance shaft of the camel beam can be rotated within a certain range, which meets the transportation requirements under different longitudinal slope conditions. The whole hole of the beam body is transported to the bridge position by means of walking on the half-width beam, and the tire walking track is the position of the beam rib of the two beams, which has little influence on the bridge structure.

本发明采用梁上运梁方式对桥位下地形地貌无任何要求,解决了运输问题。并且本发明充分利用架桥机天车及主桁横移的方式架设整孔预制梁,支腿无需移动,桥机的安全性更好,能提高架设效率,同时为类似的小悬臂边梁的桥型梁板架设提供了一种新的技术思路。The present invention adopts the method of transporting the beam on the beam without any requirement on the topography under the bridge position, and solves the transportation problem. In addition, the present invention makes full use of the way of the overhead crane and the main truss of the bridge erection machine to erect the whole-hole prefabricated beam, the outriggers do not need to be moved, the safety of the bridge machine is better, the erection efficiency can be improved, and at the same time, it can be used for similar small cantilever side beams. Bridge beam slab erection provides a new technical idea.

本发明采用整孔架设能有效加快施工进度,降低安全风险。解决了大跨径装配式波形钢腹板组合箱梁整孔架设施工技术难题,提供了一种更适合跨河、跨路及桥位地势不适宜大型车辆通行的大跨径预制装配式波形钢腹板组合箱梁的运架施工方法。The invention adopts the whole hole erection, which can effectively speed up the construction progress and reduce the safety risk. It solves the technical problems in the construction of the whole hole frame of the long-span prefabricated corrugated steel web composite box girder, and provides a long-span prefabricated corrugated steel that is more suitable for crossing rivers, roads and bridges that are not suitable for large vehicles to pass through. Construction method of frame transport for web composite box girder.

本发明可适于应用到无航运条件的桥梁和市政工程中,在运输过程中采用梁上运梁的方式将波形钢腹板箱梁整孔运至桥位,避免对既有架设梁板的受力破坏,通过架桥机横移进行全幅整孔架设,降低现场工作量,更大的提升了预制装配式波形钢腹板桥梁机械化建造水平。The present invention can be applied to bridges and municipal engineering without shipping conditions, and the whole hole of the corrugated steel web box girder is transported to the bridge position by means of beam-on-beam transportation during transportation, so as to avoid the stress on the existing erected beam plates. The bridge erection machine is traversed to carry out full-width and whole-hole erection, which reduces the on-site workload and greatly improves the mechanized construction level of prefabricated corrugated steel web bridges.

本发明实施的运输、架设工艺,采用在单幅两片梁上运用组合式模块车运梁的方式将大跨径波形钢腹板箱梁运输至架桥机尾部,避免梁车在已架设梁板上行走时集中受力,引起桥梁质量病害。通过利用架桥机主桁横移兼具吊装功能解决整孔外边梁的架设问题,为大跨径预制装配式波形梁的运输快速架设开辟了新技术。In the transportation and erection process implemented by the present invention, the large-span corrugated steel web box girder is transported to the rear of the bridge erecting machine by using a combined modular truck to transport the beam on a single two-piece beam, so as to avoid the girder truck running on the erected beam. When the board is walking, the force is concentrated, causing the quality of the bridge to be damaged. By utilizing the lateral movement of the main truss of the bridge erection machine and the hoisting function to solve the erection problem of the outer side beams of the whole hole, a new technology is opened up for the rapid erection of large-span prefabricated corrugated beams.

以上所述,仅是本发明的较佳实施例而已,并非是对本发明作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例。但是凡是未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本发明技术方案的保护范围。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention in other forms. Any person skilled in the art may use the technical content disclosed above to make changes or modifications to equivalent changes. Example. However, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solutions of the present invention still belong to the protection scope of the technical solutions of the present invention.

Claims (8)

1.一种大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,包括以下步骤:1. a large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method, is characterized in that, comprises the following steps: 步骤一,将模块运输车进行模块化组合,四台模块运输车组合成一套组合式模块运输车(1),组合式模块运输车(1)的总体宽度为两片梁的宽度;Step 1, modularly combining the modular transport vehicles, four modular transport vehicles are combined into a set of combined modular transport vehicles (1), and the overall width of the combined modular transport vehicles (1) is the width of two beams; 步骤二,将波形钢腹板组合箱梁安装于组合式模块运输车(1)的驼梁(2)上,并捆扎牢固;In step 2, the corrugated steel web composite box girder is installed on the camel beam (2) of the combined modular transport vehicle (1), and is bundled firmly; 步骤三,组合模块运输车(1)采用行走单幅运输方式将波形钢腹板组合箱梁运至架桥机(4)的尾部喂梁区;Step 3, the combined modular transport vehicle (1) adopts the single-width walking mode to transport the corrugated steel web combined box girder to the rear beam feeding area of the bridge erecting machine (4); 步骤四,应用架桥机(4)进行全幅梁体架设;架桥机(4)的支腿无需移动,通过天车(5)和主桁(6)移动完成整孔梁体的架设;In step 4, the bridge erection machine (4) is used to erect the full-width beam body; the outriggers of the bridge erection machine (4) do not need to be moved, and the erection of the whole-hole girder body is completed by moving the crane (5) and the main truss (6); 第五步,相邻梁体之间将横隔板及顶板位置钢筋安装,悬吊模板安装、浇筑混凝土。The fifth step is to install the steel bars at the positions of the diaphragm and the roof between the adjacent beam bodies, install the suspension formwork, and pour concrete. 2.根据权利要求1所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤二中,驼梁(2)由型钢组焊形成箱型,与组合式模块运输车(1)的连接部位为平衡轴(3)。2. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to claim 1, characterized in that, in the step 2, the camel beam (2) is assembled into a box shape by section steel welding, and The connecting part of the combined modular transport vehicle (1) is a balance shaft (3). 3.根据权利要求1-2其中之一所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤三中,组合模块运输车(1)在已完成架设梁体的两片梁上行走,轮胎运行轨迹为梁肋位置。3. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to one of claims 1-2, characterized in that, in the step 3, the combined module transport vehicle (1) is Walk on the two beams that have completed the erection of the beam body, and the running track of the tire is the position of the beam rib. 4.根据权利要求1-3其中之一所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤四中,架梁的顺序为内边梁、外边梁、中梁。4. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to one of claims 1-3, characterized in that, in the step 4, the order of the frame beams is inner side beam, Outer beam, middle beam. 5.根据权利要求4所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤四中,架设内边梁时天车(5)下发吊具(6)与梁体进行连接、起吊,完成梁体的架设。5. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to claim 4, characterized in that, in the step 4, when erecting the inner side beam, the crane (5) issues a spreader (6) ) to connect and lift the beam to complete the erection of the beam. 6.根据权利要求1-5其中之一所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤四中,外边梁架设时,在中梁的部位安装临时支座(8),其中临时支座(8)顶面高于墩台顶部的设计挡块(9)的高度;天车(5)下发吊具(6)与外边梁的梁体进行连接、起吊,临时存放于中梁处。6. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to one of claims 1-5, characterized in that, in the step 4, when the outer side beams are erected, at the middle beam Temporary support (8) is installed at the site, wherein the top surface of the temporary support (8) is higher than the height of the design block (9) at the top of the pier; The body is connected, hoisted, and temporarily stored at the middle beam. 7.根据权利要求6所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤四中,天车(5)与外边梁的梁体解锁后归位,架桥机(4)的左右两侧的主桁(6)同步横移,待主桁(6)到临时存放的外边梁的正上方时停止,主桁(6)安装悬吊装置(10),与外边梁的梁体进行连接并进行提升;主桁(6)再次横移,待主桁(6)移至外边梁的设计位置后停止,悬吊装置(10)下放至梁体设计高度,完成外边梁的梁体架设。7. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to claim 6, characterized in that, in the step 4, the crane (5) and the beam body of the outer side beam are unlocked and returned to position, the main trusses (6) on the left and right sides of the bridge erecting machine (4) move laterally synchronously, and stop when the main truss (6) is directly above the temporarily stored outer side beams, and the main truss (6) is installed with a suspension device ( 10), connect with the beam body of the outer side beam and lift it; the main truss (6) is moved laterally again, and stops after the main truss (6) is moved to the design position of the outer side beam, and the suspension device (10) is lowered to the beam body Design height, complete the beam body erection of the outer beam. 8.根据权利要求7所述的大跨径预制装配式波形腹板组合箱梁运架施工方法,其特征在于,所述步骤四中,通过天车(5)完成中梁的架设;若需要架设有多片中梁的桥梁时,可先利用天车(5)将中梁架设完毕,最后一片与外边梁相邻的中梁最后架设。8. The large-span prefabricated prefabricated corrugated web composite box girder transport frame construction method according to claim 7, characterized in that, in the step 4, the erection of the middle beam is completed by the overhead crane (5); if necessary When erecting a bridge with multiple middle beams, the middle beam can be erected first by using the overhead crane (5), and the last middle beam adjacent to the outer side beams is erected last.
CN202010768725.0A 2020-08-03 2020-08-03 Construction method of large-span prefabricated corrugated web composite box girder transport frame Pending CN111851307A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010768725.0A CN111851307A (en) 2020-08-03 2020-08-03 Construction method of large-span prefabricated corrugated web composite box girder transport frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010768725.0A CN111851307A (en) 2020-08-03 2020-08-03 Construction method of large-span prefabricated corrugated web composite box girder transport frame

Publications (1)

Publication Number Publication Date
CN111851307A true CN111851307A (en) 2020-10-30

Family

ID=72954408

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010768725.0A Pending CN111851307A (en) 2020-08-03 2020-08-03 Construction method of large-span prefabricated corrugated web composite box girder transport frame

Country Status (1)

Country Link
CN (1) CN111851307A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112853997A (en) * 2021-02-05 2021-05-28 中交一公局集团有限公司 Construction method of large-span steel-concrete bridge
CN113373816A (en) * 2021-06-30 2021-09-10 湖南路桥建设集团有限责任公司 Construction method for hoisting corrugated steel web segment beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01223204A (en) * 1988-02-29 1989-09-06 Yokokawa Koji Kk Bridge girder replacement method and device thereof
CN103015325A (en) * 2012-12-24 2013-04-03 中铁十七局集团第二工程有限公司 Construction method of cast-in-place concrete crash barrier with eaves
CN110820573A (en) * 2019-11-07 2020-02-21 中交路桥建设有限公司 Construction method of steel-concrete composite beam of high-pier long-span bridge in mountainous area
CN110847062A (en) * 2019-11-27 2020-02-28 中交一公局第六工程有限公司 Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
CN110878530A (en) * 2019-12-27 2020-03-13 中交二公局东萌工程有限公司 Installation and construction method of steel box girder of steel structure bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01223204A (en) * 1988-02-29 1989-09-06 Yokokawa Koji Kk Bridge girder replacement method and device thereof
CN103015325A (en) * 2012-12-24 2013-04-03 中铁十七局集团第二工程有限公司 Construction method of cast-in-place concrete crash barrier with eaves
CN110820573A (en) * 2019-11-07 2020-02-21 中交路桥建设有限公司 Construction method of steel-concrete composite beam of high-pier long-span bridge in mountainous area
CN110847062A (en) * 2019-11-27 2020-02-28 中交一公局第六工程有限公司 Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
CN110878530A (en) * 2019-12-27 2020-03-13 中交二公局东萌工程有限公司 Installation and construction method of steel box girder of steel structure bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
大河报: "《百度文库》", 30 November 2019 *
赵小东: "架桥机架设小半径曲线钢箱梁技术", 《中国建筑金属结构》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112853997A (en) * 2021-02-05 2021-05-28 中交一公局集团有限公司 Construction method of large-span steel-concrete bridge
CN113373816A (en) * 2021-06-30 2021-09-10 湖南路桥建设集团有限责任公司 Construction method for hoisting corrugated steel web segment beam

Similar Documents

Publication Publication Date Title
CN104097253B (en) Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system
CN109082998A (en) Integral prefabricated steel plate combination girder construction and construction method
CN110820594A (en) Symmetrical cantilever construction process suitable for expansion joint bridge pier
CN102154988B (en) Arch-after-girder construction method of large-span steel box tacked arch bridge
CN111364350A (en) A light-weight steel-concrete composite cover beam with quick installation of large cantilever arm
CN207244447U (en) Movable hanging basket for steel-concrete composite bridge
CN103938549A (en) Construction method for fabricated type corrugated steel inclined web combined beam
JP7429940B2 (en) Construction method of steel concrete main girder of cable-stayed bridge
CN111877182A (en) Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge
CN204109135U (en) Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system
CN115324366A (en) Hoisting method for overlong and overweight truss of framed bent structure system
CN111254800A (en) A composite beam suitable for urban bridges and its construction method
CN111851307A (en) Construction method of large-span prefabricated corrugated web composite box girder transport frame
CN107401125B (en) Traveling device of mobile trolley and using method
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
CN217204610U (en) Low multilayer does not need to support assembled ultra high performance concrete frame structure and building
CN112160246B (en) Method for installing composite beam
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
CN102535344A (en) Concrete transportation method for bridge body of high-pier bridge in gully region
CN206655141U (en) A kind of steel cantilever combined bridge deck widens reconstruction structure
CN112458879A (en) Bolt-welding mixed-connection segmented prefabricated assembled combination beam and construction method thereof
CN109235482B (en) Tower crane foundation based on bonded prestressed concrete and construction method thereof
CN110644380A (en) Mounting method for narrow space beam slab of widened engineering of large-span overpass
CN214737289U (en) Mounting structure for assembled elevated road and bridge
CN211171563U (en) An arch bridge between tunnels that is convenient for rapid construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201030

RJ01 Rejection of invention patent application after publication