[go: up one dir, main page]

CN111828042A - An intelligent shotcrete support method for wall over-excavation tunnel - Google Patents

An intelligent shotcrete support method for wall over-excavation tunnel Download PDF

Info

Publication number
CN111828042A
CN111828042A CN202010583062.5A CN202010583062A CN111828042A CN 111828042 A CN111828042 A CN 111828042A CN 202010583062 A CN202010583062 A CN 202010583062A CN 111828042 A CN111828042 A CN 111828042A
Authority
CN
China
Prior art keywords
spraying
tunnel
pit
wall surface
injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010583062.5A
Other languages
Chinese (zh)
Other versions
CN111828042B (en
Inventor
刘刚峰
孙宪超
李长乐
张学贺
刘玉斌
樊继壮
赵杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Institute of Technology Shenzhen
Original Assignee
Harbin Institute of Technology Shenzhen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Institute of Technology Shenzhen filed Critical Harbin Institute of Technology Shenzhen
Priority to CN202010583062.5A priority Critical patent/CN111828042B/en
Publication of CN111828042A publication Critical patent/CN111828042A/en
Application granted granted Critical
Publication of CN111828042B publication Critical patent/CN111828042B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00Measuring arrangements characterised by the use of optical techniques
    • G01B11/24Measuring arrangements characterised by the use of optical techniques for measuring contours or curvatures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提出一种壁面超挖隧道智能喷浆支护方法,属于隧道施工技术领域。所述方法包括以下步骤:步骤一、使用全站仪对湿喷台车进行定位,获取湿喷台车与隧道的空间关系,完成湿喷台车的智能定位工作;步骤二、识别出由于超挖产生的坑,对喷湿机械手进行运动规划,进行原始层补坑作业;步骤三、在岩面上安装多排并列设置的弧形钢拱架;步骤四、对安装了钢拱架的壁面进行轮廓扫描,划分喷射块并确定喷射点,提取喷射点的坐标信息和喷射块的体积信息;步骤五、对湿喷机械手进行运动规划,依次进行基底层支护、钢拱架层支护和表面层支护。本发明解决了由于壁面超挖给喷浆支护作业带来的壁面平整度低的问题,且实现了隧道喷浆支护自动化作业。

Figure 202010583062

The invention provides an intelligent shotcrete support method for a wall surface over-excavation tunnel, which belongs to the technical field of tunnel construction. The method includes the following steps: Step 1, use a total station to locate the wet spray trolley, obtain the spatial relationship between the wet spray trolley and the tunnel, and complete the intelligent positioning of the wet spray trolley; Dig the generated pit, plan the motion of the wet spray manipulator, and perform the original layer pit repair operation; step 3, install multiple rows of arc-shaped steel arches arranged side by side on the rock surface; step 4, install the steel arch on the wall surface. Carry out contour scanning, divide the injection block and determine the injection point, and extract the coordinate information of the injection point and the volume information of the injection block. Surface layer support. The invention solves the problem of low wall surface flatness caused by the over-excavation of the wall surface for the shotcrete support operation, and realizes the automatic operation of the tunnel shotcrete support.

Figure 202010583062

Description

一种壁面超挖隧道智能喷浆支护方法An intelligent shotcrete support method for wall over-excavation tunnel

技术领域technical field

本发明涉及基于一种壁面超挖隧道智能喷浆支护方法,属于隧道施工技术领域。The invention relates to an intelligent shotcrete support method based on a wall surface over-excavation tunnel, and belongs to the technical field of tunnel construction.

背景技术Background technique

目前,隧道喷浆支护作业大部分由人工操控喷浆机械臂,作业环境极其恶劣,工作条件差、工序耗时长,严重危害工人身体健康,且完成质量差,无法满足隧道支护高效率、高平整度的要求。At present, most of the tunnel shotcrete support operations are manually controlled by shotcrete manipulators. The operating environment is extremely harsh, the working conditions are poor, and the process is time-consuming, which seriously endangers the health of workers, and the quality of the completion is poor, which cannot meet the requirements of high efficiency and high efficiency of tunnel support. High flatness requirements.

壁面超挖隧道由于存在不同深度的超挖坑洞,工人肉眼难以精确预估,给喷浆支护造成了很大的困难,使平整度要求更加难以满足。Due to the existence of over-excavated pits of different depths in the wall surface over-excavation tunnel, it is difficult for workers to accurately predict with the naked eye, which causes great difficulties for shotcrete support and makes it more difficult to meet the flatness requirements.

专利201910567117.0提供了一种智能喷浆系统的喷浆支护方法,该方法由三维扫描、自动首次喷浆、扫描检测、判断扫描结果及自动精喷修正五个步骤组成。但其并未考虑爆破后壁面超挖的情况对喷浆支护的影响,造成作业后表面平整度低、工序耗时长,严重影响隧道支护的质量和效率。Patent 201910567117.0 provides a shotcrete support method for an intelligent shotcrete system. The method consists of five steps: three-dimensional scanning, automatic first shotcrete, scanning detection, judging scan results and automatic fine spray correction. However, it does not consider the impact of the over-excavation of the wall surface on the shotcrete support after blasting, resulting in low surface flatness after the operation and a long process time, which seriously affects the quality and efficiency of the tunnel support.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提出一种壁面超挖隧道智能喷浆支护方法,以解决现有的隧道喷浆支护技术存在的表面平整度低、工序耗时长的技术问题。The purpose of the present invention is to propose an intelligent shotcrete support method for wall surface over-excavation tunnels, so as to solve the technical problems of low surface flatness and long process time in the existing tunnel shotcrete support technology.

一种壁面超挖隧道智能喷浆支护方法,所述方法包括以下步骤:An intelligent shotcrete support method for an over-excavated tunnel on a wall surface, the method comprising the following steps:

步骤一、使用全站仪对湿喷台车进行定位,获取湿喷台车与隧道的空间关系,完成湿喷台车的智能定位工作;Step 1. Use the total station to locate the wet spray trolley, obtain the spatial relationship between the wet spray trolley and the tunnel, and complete the intelligent positioning of the wet spray trolley;

步骤二、对隧道环面轮廓进行原始扫描获得扫描轮廓,使扫描轮廓与设计轮廓对比识别出由于超挖产生的坑,对喷湿机械手进行运动规划,进行原始层补坑作业;Step 2: Perform an original scan on the contour of the tunnel torus to obtain the scan profile, so that the scan profile and the design profile are compared to identify the pits caused by over-excavation, and the motion planning of the wet spraying manipulator is performed to perform the original layer pit-filling operation;

步骤三、在岩面上安装多排并列设置的弧形钢拱架;Step 3. Install multiple rows of arc-shaped steel arches arranged side by side on the rock surface;

步骤四、对安装了钢拱架的壁面进行轮廓扫描,并将扫描得到的隧道轮廓点云数据上传至测控中心,划分喷射块并确定喷射点,提取喷射点的坐标信息和喷射块的体积信息;Step 4: Scan the contour of the wall with the steel arch, upload the scanned tunnel contour point cloud data to the measurement and control center, divide the injection block and determine the injection point, and extract the coordinate information of the injection point and the volume information of the injection block. ;

步骤五、根据所述坐标信息和体积信息对湿喷机械手进行运动规划,依次进行基底层支护、钢拱架层支护和表面层支护。Step 5: Carry out motion planning for the wet spraying manipulator according to the coordinate information and volume information, and perform base layer support, steel arch layer support and surface layer support in sequence.

进一步的,在步骤二中,具体包括以下步骤:Further, in step 2, the following steps are specifically included:

步骤二一、使用三维激光扫描仪对隧道环面轮廓进行原始扫描;Step 21. Use a three-dimensional laser scanner to perform an original scan on the contour of the tunnel torus;

步骤二二、利用三维轮廓重建自动处理软件对扫描得到的点云数据进行处理,将扫描轮廓与设计轮廓对比识别出由于超挖产生的坑,辨识坑的类型,并提取补坑所需信息;Step 22: Use the three-dimensional contour reconstruction automatic processing software to process the point cloud data obtained by scanning, compare the scanning contour with the design contour to identify the pits generated by over-excavation, identify the type of the pits, and extract the information required for filling the pits;

步骤二三、根据得到的补坑所需信息对湿喷机械手进行运动规划,进而控制湿喷机械臂进行原始层补坑作业。Steps 2 and 3: planning the motion of the wet spraying manipulator according to the obtained information required for filling the pit, and then controlling the wet spraying manipulator to perform the work of filling the pit with the original layer.

进一步的,所述补坑所需信息包括:坑面中心坐标、坑面的法向量和填坑所需要混凝土的方量。Further, the information required for filling the pit includes: the center coordinates of the pit surface, the normal vector of the pit surface, and the square quantity of concrete required for filling the pit.

进一步的,在步骤三中,弧形钢拱架的间距由壁面的围岩等级确定,在0.8~1.5m之间。Further, in step 3, the spacing of the curved steel arches is determined by the surrounding rock grade of the wall, and is between 0.8 and 1.5 m.

进一步的,在步骤四中,具体包括以下步骤:Further, in step 4, the following steps are specifically included:

步骤四一、使用三维激光扫描仪对隧道环面轮廓进行基底层扫描;Step 41. Use a three-dimensional laser scanner to scan the basal layer of the tunnel torus profile;

步骤四二、利用三维轮廓重建自动处理软件对扫描得到的点云数据进行处理,划分喷射区和喷射块并确定喷射点;Step 42: Use the 3D contour reconstruction automatic processing software to process the point cloud data obtained by scanning, divide the injection area and injection block, and determine the injection point;

步骤四三、提取喷射点的坐标信息和喷射块的体积信息。Step 43: Extract the coordinate information of the injection point and the volume information of the injection block.

进一步的,在步骤五中,基底层支护具体包括以下步骤:Further, in step 5, the base layer support specifically includes the following steps:

步骤五一、将待喷壁面划分为五个喷射区,在每个喷射区内划分喷射块,取每个喷射块的中心点作为喷射点,并提取喷射点的坐标信息和喷射块的体积信息;Step 51. Divide the wall surface to be sprayed into five injection areas, divide injection blocks in each injection area, take the center point of each injection block as the injection point, and extract the coordinate information of the injection point and the volume information of the injection block ;

步骤五二、湿喷台车控制系统根据得到的坐标信息和体积信息对湿喷机械手进行运动规划,进而控制湿喷机械臂进行基底层喷浆支护作业。Step 52: The wet spraying trolley control system plans the motion of the wet spraying manipulator according to the obtained coordinate information and volume information, and then controls the wet spraying manipulator to perform the base layer spraying support operation.

进一步的,在步骤五中,基底层支护作业和钢拱架层支护作业,作业时均采用累加薄喷的方式,单次喷射的厚度不超过20cm。Further, in step 5, both the base layer support operation and the steel arch layer support operation are carried out by means of cumulative thin spraying, and the thickness of a single spraying does not exceed 20cm.

本发明的主要优点是:本发明采用提前补坑的方式,解决了由于壁面超挖给喷浆支护作业带来的壁面平整度低的问题,提高了超挖壁面隧道喷浆支护的作业质量;本发明利用激光扫描和点云处理的技术手段,实现了隧道喷浆支护自动化作业,减少了人工作业给工人健康带来的危害,并提高了隧道喷浆支护作业的效率。The main advantages of the invention are as follows: the invention adopts the method of filling the pit ahead of time, which solves the problem of low wall flatness caused by the over-excavation of the wall surface for the shotcrete support operation, and improves the shotcrete support operation of the over-excavated wall surface tunnel. quality; the invention utilizes the technical means of laser scanning and point cloud processing to realize the automatic operation of the tunnel shotcrete support, reduce the harm to workers' health caused by the manual operation, and improve the efficiency of the tunnel shotcrete support operation.

附图说明Description of drawings

图1为定位工作示意图;Fig. 1 is a schematic diagram of positioning work;

图2为分区喷射示意图;Fig. 2 is a schematic diagram of partition injection;

图3为喷射区分块示意图;Fig. 3 is the block schematic diagram of injection zone;

图4为分阶段喷射示意图。Figure 4 is a schematic diagram of staged injection.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

一种壁面超挖隧道智能喷浆支护方法,所述方法包括以下步骤:An intelligent shotcrete support method for an over-excavated tunnel on a wall surface, the method comprising the following steps:

步骤一、使用全站仪对湿喷台车进行定位,获取湿喷台车与隧道的空间关系,完成湿喷台车的智能定位工作;Step 1. Use the total station to locate the wet spray trolley, obtain the spatial relationship between the wet spray trolley and the tunnel, and complete the intelligent positioning of the wet spray trolley;

步骤二、对隧道环面轮廓进行原始扫描获得扫描轮廓,使扫描轮廓与设计轮廓对比识别出由于超挖产生的坑,对喷湿机械手进行运动规划,进行原始层补坑作业;Step 2: Perform an original scan on the contour of the tunnel torus to obtain the scan profile, so that the scan profile and the design profile are compared to identify the pits caused by over-excavation, and the motion planning of the wet spraying manipulator is performed to perform the original layer pit-filling operation;

步骤三、在岩面上安装多排并列设置的弧形钢拱架;Step 3. Install multiple rows of arc-shaped steel arches arranged side by side on the rock surface;

步骤四、对安装了钢拱架的壁面进行轮廓扫描,并将扫描得到的隧道轮廓点云数据上传至测控中心,划分喷射块并确定喷射点,提取喷射点的坐标信息和喷射块的体积信息;Step 4: Scan the contour of the wall with the steel arch, upload the scanned tunnel contour point cloud data to the measurement and control center, divide the injection block and determine the injection point, and extract the coordinate information of the injection point and the volume information of the injection block. ;

步骤五、根据所述坐标信息和体积信息对湿喷机械手进行运动规划,依次进行基底层支护、钢拱架层支护和表面层支护。Step 5: Carry out motion planning for the wet spraying manipulator according to the coordinate information and volume information, and perform base layer support, steel arch layer support and surface layer support in sequence.

在步骤二中,具体包括以下步骤:In step 2, the following steps are specifically included:

步骤二一、使用三维激光扫描仪对隧道环面轮廓进行原始扫描;Step 21. Use a three-dimensional laser scanner to perform an original scan on the contour of the tunnel torus;

步骤二二、利用三维轮廓重建自动处理软件对扫描得到的点云数据进行处理,将扫描轮廓与设计轮廓对比识别出由于超挖产生的坑,辨识坑的类型,并提取补坑所需信息;Step 22: Use the three-dimensional contour reconstruction automatic processing software to process the point cloud data obtained by scanning, compare the scanning contour with the design contour to identify the pits generated by over-excavation, identify the type of the pits, and extract the information required for filling the pits;

步骤二三、根据得到的补坑所需信息对湿喷机械手进行运动规划,进而控制湿喷机械臂进行原始层补坑作业。Steps 2 and 3: planning the motion of the wet spraying manipulator according to the obtained information required for filling the pit, and then controlling the wet spraying manipulator to perform the work of filling the pit with the original layer.

所述补坑所需信息包括:坑面中心坐标、坑面的法向量和填坑所需要混凝土的方量。The information required for filling the pit includes: the center coordinates of the pit surface, the normal vector of the pit surface, and the square quantity of concrete required for filling the pit.

在步骤三中,弧形钢拱架的间距由壁面的围岩等级确定,在0.8~1.5m之间。In step 3, the spacing of the curved steel arches is determined by the surrounding rock grade of the wall, which is between 0.8 and 1.5m.

在步骤四中,具体包括以下步骤:In step 4, the following steps are specifically included:

步骤四一、使用三维激光扫描仪对隧道环面轮廓进行基底层扫描;Step 41. Use a three-dimensional laser scanner to scan the basal layer of the tunnel torus profile;

步骤四二、利用三维轮廓重建自动处理软件对扫描得到的点云数据进行处理,划分喷射区和喷射块并确定喷射点;Step 42: Use the 3D contour reconstruction automatic processing software to process the point cloud data obtained by scanning, divide the injection area and injection block, and determine the injection point;

步骤四三、提取喷射点的坐标信息和喷射块的体积信息。Step 43: Extract the coordinate information of the injection point and the volume information of the injection block.

在步骤五中,基底层支护具体包括以下步骤:In step 5, the support of the base layer specifically includes the following steps:

步骤五一、将待喷壁面划分为五个喷射区,在每个喷射区内划分喷射块,取每个喷射块的中心点作为喷射点,并提取喷射点的坐标信息和喷射块的体积信息;Step 51. Divide the wall surface to be sprayed into five injection areas, divide injection blocks in each injection area, take the center point of each injection block as the injection point, and extract the coordinate information of the injection point and the volume information of the injection block ;

步骤五二、湿喷台车控制系统根据得到的坐标信息和体积信息对湿喷机械手进行运动规划,进而控制湿喷机械臂进行基底层喷浆支护作业。Step 52: The wet spraying trolley control system plans the motion of the wet spraying manipulator according to the obtained coordinate information and volume information, and then controls the wet spraying manipulator to perform the base layer spraying support operation.

进一步的,在步骤五中,基底层支护作业和钢拱架层支护作业,作业时均采用累加薄喷的方式,单次喷射的厚度不超过20cm。Further, in step 5, both the base layer support operation and the steel arch layer support operation are carried out by means of cumulative thin spraying, and the thickness of a single spraying does not exceed 20cm.

下面提出一种具体实施范例:A specific implementation example is proposed below:

一种应用于超挖壁面隧道的智能型喷浆支护方法,该方法步骤如下:An intelligent shotcrete support method applied to an over-excavated wall tunnel, the method steps are as follows:

第一步,驾驶湿喷台车到达作业现场,在平稳位置支好前后腿。如图1所示,将全站仪放置于隧道中的点P1,通过测量隧道内预先放置的点P2设站,利用全站仪测量放置在台车上的棱镜点P3计算出湿喷台车与隧道的空间关系,完成湿喷台车的智能定位工作;The first step is to drive the wet spray trolley to the job site and support the front and rear legs in a stable position. As shown in Figure 1, place the total station at point P1 in the tunnel, set up the station by measuring the pre-placed point P2 in the tunnel, and use the total station to measure the prism point P3 placed on the trolley to calculate the wet spray trolley The spatial relationship with the tunnel, to complete the intelligent positioning of the wet spray trolley;

第二步,利用湿喷台车车头安装的三维隧道激光扫描仪对待作业的壁面进行轮廓扫描,并将扫描得到的隧道轮廓点云数据上传至测控中心;The second step is to use the 3D tunnel laser scanner installed on the head of the wet spray trolley to scan the contour of the wall to be operated, and upload the scanned tunnel contour point cloud data to the measurement and control center;

第三步,利用三维轮廓重建自动处理软件对扫描得到的点云数据进行处理,将扫描轮廓与设计轮廓对比识别出坑,根据坑面大小和形状辨识出小坑和大坑并提取补坑所需相关信息。对于小坑,补坑的策略是定点喷射,需提取坑面中心的坐标、坑面的法向量和填坑所需要混凝土的方量等信息;对于大坑,补坑的策略是分块填补,需将大坑坑面划分成多个小坑,再提取相应小坑的坑面中心的坐标、坑面的法向量和填坑所需要混凝土的方量等信息;The third step is to use the 3D contour reconstruction automatic processing software to process the point cloud data obtained by scanning, compare the scanning contour with the design contour to identify the pits, identify the small pits and large pits according to the size and shape of the pit surface, and extract the holes for filling the pits. Relevant information is required. For small pits, the strategy for filling pits is fixed-point spraying, and it is necessary to extract information such as the coordinates of the center of the pit surface, the normal vector of the pit surface, and the square quantity of concrete required to fill the pits; for large pits, the strategy for filling the pits is to fill in blocks. It is necessary to divide the large pit surface into multiple small pits, and then extract information such as the coordinates of the pit surface center of the corresponding small pit, the normal vector of the pit surface, and the amount of concrete required for filling the pit;

第四步,湿喷台车控制系统根据得到的坑面中心坐标、坑面的法向量和填坑所需要混凝土的方量分别确定喷浆机械手的位置、喷枪姿态和喷射时间,规划湿喷机械臂的运动轨迹,并控制湿喷机械臂进行原始层的补坑作业;In the fourth step, the control system of the wet spraying trolley determines the position of the shotcrete manipulator, the attitude of the spray gun and the spraying time according to the obtained center coordinates of the pit surface, the normal vector of the pit surface and the square quantity of concrete required for filling the pit, and plans the wet spraying machine. The movement trajectory of the arm, and control the wet spraying manipulator to carry out the pit-filling operation of the original layer;

第五步,在岩面上安装多排并列设置的弧形钢拱架。钢拱架的间距由壁面的围岩等级确定,在0.8~1.5m之间;The fifth step is to install multiple rows of arc-shaped steel arches arranged side by side on the rock surface. The spacing of the steel arches is determined by the surrounding rock grade of the wall, which is between 0.8 and 1.5m;

第六步,利用湿喷台车车头安装的三维隧道激光扫描仪对安装了钢拱架的壁面进行轮廓扫描,并将扫描得到的隧道轮廓点云数据上传至测控中心;The sixth step, use the three-dimensional tunnel laser scanner installed on the head of the wet spray trolley to scan the contour of the wall with the steel arch, and upload the scanned tunnel contour point cloud data to the measurement and control center;

第七步,先将待喷壁面进行分为五个喷射区,如图2所示,Ⅰ区、Ⅱ区、Ⅲ区和Ⅳ区的高度都为2m,Ⅴ区为隧道最顶部的区域。再分别对这五个喷射区分块,如图3所示,将每个喷射区分为大小相等的长方形喷射块,喷射块的长度b和宽度a分别由喷头水平转动和垂直转动的角度范围计算。然后取单位块的中心点为喷射点,利用三维轮廓重建自动处理软件处理第六步扫描得到的点云数据得到喷射点的坐标、法向量和对应喷射块的方量。在每个喷射区内,喷枪走一个“弓”字形轨迹;The seventh step is to divide the wall surface to be sprayed into five spray areas. As shown in Figure 2, the heights of area I, area II, area III and area IV are all 2m, and area V is the top area of the tunnel. Then, for the five injection area blocks, as shown in Figure 3, each injection area is divided into rectangular injection blocks of equal size. Then take the center point of the unit block as the injection point, and use the 3D contour reconstruction automatic processing software to process the point cloud data scanned in the sixth step to obtain the coordinates of the injection point, the normal vector and the square of the corresponding injection block. In each spray area, the spray gun follows a "bow"-shaped trajectory;

第八步,湿喷台车控制系统根据得到的喷射点的坐标、法向量和对应喷射块的方量分别确定喷浆机械手的位置、喷枪姿态和喷射时间,规划湿喷机械臂的运动轨迹,并控制湿喷机械臂进行喷浆作业。喷浆作业分为三个阶段,首先是基底层支护,然后是钢拱架层支护,最后表面层支护。如图4所示,基底层支护是填充待喷壁面与钢拱架背面的间隙,对应图中①区域;钢拱架层支护是填充钢拱架中间,对应图中②区域;表面层支护是指在钢拱架表面喷射一层约2cm厚度的混凝土,对应图中③区域。每个阶段开始时都要对隧道环面轮廓进行扫描处理,为湿喷台车控制系统规划湿喷机械臂运动提供信息。在基底层支护和钢拱架层支护的喷射作业过程中采用多次薄喷的策略,单次喷射厚度不超过20cm,这样可以有效减少混凝土掉块。In the eighth step, the control system of the wet spraying trolley determines the position of the spraying manipulator, the attitude of the spraying gun and the spraying time according to the obtained coordinates of the spraying point, the normal vector and the square of the corresponding spraying block, and plans the motion trajectory of the wet spraying manipulator. And control the wet spraying mechanical arm to carry out the spraying operation. The shotcrete operation is divided into three stages, first is the base layer support, then the steel arch layer support, and finally the surface layer support. As shown in Figure 4, the base layer support is to fill the gap between the wall to be sprayed and the back of the steel arch, corresponding to the area ① in the figure; the support of the steel arch layer is to fill the middle of the steel arch, corresponding to the area ② in the figure; the surface layer Support refers to spraying a layer of concrete with a thickness of about 2cm on the surface of the steel arch, corresponding to area ③ in the figure. The tunnel toroid profile is scanned at the beginning of each stage to provide information for the wet spray trolley control system to plan the motion of the wet spray manipulator. In the spraying operation of the base layer support and the steel arch layer support, the strategy of multiple thin spraying is adopted, and the thickness of a single spraying does not exceed 20cm, which can effectively reduce the loss of concrete blocks.

Claims (7)

1. An intelligent guniting support method for a wall surface overexcavation tunnel is characterized by comprising the following steps:
the method comprises the following steps that firstly, a total station is used for positioning the wet spraying trolley, the spatial relation between the wet spraying trolley and a tunnel is obtained, and intelligent positioning work of the wet spraying trolley is completed;
step two, performing original scanning on the tunnel ring surface outline to obtain a scanning outline, comparing the scanning outline with a design outline to identify a pit generated by overexcavation, performing motion planning on the wet spraying manipulator, and performing original layer pit repairing operation;
thirdly, installing a plurality of rows of arc-shaped steel arches which are arranged in parallel on the rock surface;
scanning the profile of the wall surface provided with the steel arch, uploading the scanned tunnel profile point cloud data to a measurement and control center, dividing the injection blocks, determining the injection points, and extracting the coordinate information of the injection points and the volume information of the injection blocks;
and fifthly, performing motion planning on the wet-spraying manipulator according to the coordinate information and the volume information, and sequentially performing basal layer support, steel arch layer support and surface layer support.
2. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 1, wherein in the second step, the method specifically comprises the following steps:
secondly, performing original scanning on the tunnel ring surface profile by using a three-dimensional laser scanner;
secondly, processing the point cloud data obtained by scanning by using three-dimensional contour reconstruction automatic processing software, comparing the scanning contour with the design contour, identifying the pit generated by overexcavation, identifying the type of the pit, and extracting information required by pit filling;
and step two, performing motion planning on the wet spraying mechanical arm according to the obtained information required by pit repairing, and further controlling the wet spraying mechanical arm to perform original layer pit repairing operation.
3. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 2, wherein the information required for pit filling comprises: the center coordinates of the pit surface, the normal vector of the pit surface and the volume of concrete needed for filling the pit.
4. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 1, wherein in the third step, the distance between the arc-shaped steel arches is determined by the surrounding rock grade of the wall surface and is 0.8-1.5 m.
5. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 1, which is characterized by specifically comprising the following steps in the fourth step:
fourthly, scanning a basal layer of the tunnel ring surface profile by using a three-dimensional laser scanner;
processing the point cloud data obtained by scanning by using three-dimensional contour reconstruction automatic processing software, dividing an injection area and an injection block and determining an injection point;
and step four, extracting coordinate information of the injection point and volume information of the injection block.
6. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 1, wherein in the fifth step, the substrate layer support specifically comprises the following steps:
fifthly, dividing the wall surface to be sprayed into five spraying areas, dividing spraying blocks in each spraying area, taking the central point of each spraying block as a spraying point, and extracting the coordinate information of the spraying point and the volume information of the spraying block;
and step two, the wet-spraying trolley control system carries out motion planning on the wet-spraying mechanical arm according to the obtained coordinate information and volume information, and then controls the wet-spraying mechanical arm to carry out basal layer guniting support operation.
7. The intelligent guniting support method for the wall surface overexcavation tunnel according to claim 1, wherein in the fifth step, the base layer support operation and the steel arch layer support operation are carried out in an accumulative thin-spraying mode, and the thickness of single spraying is not more than 20 cm.
CN202010583062.5A 2020-06-23 2020-06-23 Intelligent guniting support method for wall surface overexcavation tunnel Active CN111828042B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010583062.5A CN111828042B (en) 2020-06-23 2020-06-23 Intelligent guniting support method for wall surface overexcavation tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010583062.5A CN111828042B (en) 2020-06-23 2020-06-23 Intelligent guniting support method for wall surface overexcavation tunnel

Publications (2)

Publication Number Publication Date
CN111828042A true CN111828042A (en) 2020-10-27
CN111828042B CN111828042B (en) 2023-01-31

Family

ID=72898047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010583062.5A Active CN111828042B (en) 2020-06-23 2020-06-23 Intelligent guniting support method for wall surface overexcavation tunnel

Country Status (1)

Country Link
CN (1) CN111828042B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113341422A (en) * 2021-06-23 2021-09-03 重庆工程职业技术学院 Tunneling support method based on tunneling and anchoring machine position sensing system
CN113688500A (en) * 2021-07-14 2021-11-23 中铁工程装备集团有限公司 Universal calculation method for grouting amount of tunnel tunneling equipment and storage medium
CN114247582A (en) * 2021-12-17 2022-03-29 中铁工程装备集团隧道设备制造有限公司 Spraying path planning method
CN115178400A (en) * 2022-08-01 2022-10-14 重庆大学 Intelligent guniting robot, guniting system and method
CN115199284A (en) * 2022-07-15 2022-10-18 陕西延长石油矿业有限责任公司 Surrounding rock control method for intelligent tunneling of open-type full-face tunneling machine
CN115217491A (en) * 2022-06-10 2022-10-21 大连海事大学 A fully automatic intelligent tunnel wet spraying vehicle with machine vision and spraying method
CN115307568A (en) * 2022-05-20 2022-11-08 浙江交工宏途交通建设有限公司 Device and method for controlling tunnel excavation and supporting contour line through 3D scanning
CN116441094A (en) * 2023-04-20 2023-07-18 云南途腾智能装备有限公司 Guniting mechanical arm for concrete wet spraying trolley

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108979668A (en) * 2018-07-17 2018-12-11 中铁工程装备集团有限公司 The information intelligent construction method and system of wet shot trolley
CN109635406A (en) * 2018-12-05 2019-04-16 长沙科达智能装备股份有限公司 A kind of tunnel based on point cloud slicing is automatically whitewashed method for planning track
CN110578535A (en) * 2019-10-16 2019-12-17 中铁三局集团第二工程有限公司 primary support concrete wet spraying method applied to weak surrounding rock tunnel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108979668A (en) * 2018-07-17 2018-12-11 中铁工程装备集团有限公司 The information intelligent construction method and system of wet shot trolley
CN109635406A (en) * 2018-12-05 2019-04-16 长沙科达智能装备股份有限公司 A kind of tunnel based on point cloud slicing is automatically whitewashed method for planning track
CN110578535A (en) * 2019-10-16 2019-12-17 中铁三局集团第二工程有限公司 primary support concrete wet spraying method applied to weak surrounding rock tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘在政等: "喷射机械手智能控制系统与喷射路径规划设计研究", 《隧道建设(中英文)》 *
王明光: "新型湿喷台车与喷射混凝土施工的技术探索", 《建筑机械》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113341422A (en) * 2021-06-23 2021-09-03 重庆工程职业技术学院 Tunneling support method based on tunneling and anchoring machine position sensing system
CN113341422B (en) * 2021-06-23 2024-05-24 重庆工程职业技术学院 A tunneling support method based on a position sensing system of an anchor drill
CN113688500A (en) * 2021-07-14 2021-11-23 中铁工程装备集团有限公司 Universal calculation method for grouting amount of tunnel tunneling equipment and storage medium
CN113688500B (en) * 2021-07-14 2024-04-19 中铁工程装备集团有限公司 Tunnel boring equipment guniting amount generalized calculation method and storage medium
CN114247582A (en) * 2021-12-17 2022-03-29 中铁工程装备集团隧道设备制造有限公司 Spraying path planning method
CN115307568A (en) * 2022-05-20 2022-11-08 浙江交工宏途交通建设有限公司 Device and method for controlling tunnel excavation and supporting contour line through 3D scanning
CN115217491A (en) * 2022-06-10 2022-10-21 大连海事大学 A fully automatic intelligent tunnel wet spraying vehicle with machine vision and spraying method
CN115199284A (en) * 2022-07-15 2022-10-18 陕西延长石油矿业有限责任公司 Surrounding rock control method for intelligent tunneling of open-type full-face tunneling machine
CN115178400A (en) * 2022-08-01 2022-10-14 重庆大学 Intelligent guniting robot, guniting system and method
CN116441094A (en) * 2023-04-20 2023-07-18 云南途腾智能装备有限公司 Guniting mechanical arm for concrete wet spraying trolley
CN116441094B (en) * 2023-04-20 2023-12-29 云南途腾智能装备有限公司 Guniting mechanical arm for concrete wet spraying trolley

Also Published As

Publication number Publication date
CN111828042B (en) 2023-01-31

Similar Documents

Publication Publication Date Title
CN111828042B (en) Intelligent guniting support method for wall surface overexcavation tunnel
CN111811420B (en) Method and system for monitoring the overall absolute deformation of the three-dimensional profile of the tunnel
CN104746884B (en) Method for hoisting prefabricated parts of assembled building
CN103806478A (en) Method for measuring deformation of underground diaphragm wall
CN105063615B (en) A kind of laser melting coating scanning pattern acquisition methods for free form surface surface reconditioning
CN110542388A (en) Tunnel Face Deformation Alarm Method Based on Mobile 3D Laser Scanning
CN108345318A (en) A kind of beam sections free cantilever erection pier top block installation measurement method
CN201031704Y (en) Tunnel wireless laser stakeout device
CN115035026A (en) Tunnel blasting quality evaluation method based on three-dimensional point cloud information
CN111597625A (en) Foundation pit support excavation quality control method based on BIM
CN119167471A (en) A BIM-based hoisting simulation construction method and system
CN117630002A (en) Full-process quality detection method and system for drilling and blasting tunnel
CN115952231A (en) BIM technology-based foundation pit visualization and earthwork measurement method
CN209523764U (en) A kind of anchor combined unit jumbolter automatic station-keeping system of pick branch
CN112699452A (en) Construction method for improving flatness of large-area terrace
CN107644119A (en) A kind of Half cast factor automatic calculating method based on 3-D scanning point cloud
CN117570873A (en) Deformation monitoring method and device for underground engineering tunnels based on non-airborne mobile laser scanning
CN115140266B (en) Control method for carrying precision of ship side double-bevel sectional horizontal type main assembly
CN112650095B (en) Highly automated engineering measurement method
CN116700138A (en) A method for machining flywheel pin holes
CN110307037B (en) Automatic recognition and early warning method for tunnel engineering construction appearance
CN112528217B (en) Parabolic same-layer equal-thickness arch dam measurement lofting calculation method
CN115439624A (en) Geological logging method and terminal for large-span underground cavern and storage medium
CN115908389B (en) Method for spraying concrete to primary support of TBM tunnel
CN117313206B (en) Optimization and renovation method for geometric line shape of subway business line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant