CN111733827A - Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology - Google Patents
Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology Download PDFInfo
- Publication number
- CN111733827A CN111733827A CN202010608501.3A CN202010608501A CN111733827A CN 111733827 A CN111733827 A CN 111733827A CN 202010608501 A CN202010608501 A CN 202010608501A CN 111733827 A CN111733827 A CN 111733827A
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- concrete
- steel
- construction method
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
一种邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法。其包括施工准备、围护桩施工、基坑顶部支撑及初步开挖、既有混凝土结构凿除、人工继续开挖及混凝土封底等步骤。本发明效果:将传统基坑的混凝土钻孔桩加旋喷桩的防护施工方法改变成混凝土钻孔桩加钢沉箱的防护施工方法,其中混凝土钻孔桩主要起抗剪力作用,钢沉箱起防水防砂作用,从而形成整个深基坑的防护体系。开挖过程中,混凝土钻孔桩加钢沉箱的防护体系,既保证了基坑稳定安全,又能防止地下水压过大时,地下涌水、涌砂,造成既有线路沉降,保证了营业线的安全。
A construction method for deep foundation pit protection in a station yard under a complex environment of silt geology adjacent to a high-speed railway. It includes steps such as construction preparation, construction of enclosure piles, support at the top of the foundation pit and preliminary excavation, chiseling of existing concrete structures, manual continued excavation, and concrete back sealing. Effect of the invention: the protection construction method of concrete bored piles and rotary spray piles in traditional foundation pits is changed into a protection construction method of concrete bored piles and steel caissons, wherein the concrete bored piles mainly play the role of shear resistance, and the steel caisson plays the role of shear resistance. Waterproof and sand control effect, thus forming a protection system for the entire deep foundation pit. During the excavation process, the protection system of concrete bored piles and steel caisson not only ensures the stability and safety of the foundation pit, but also prevents the underground water and sand gushing when the groundwater pressure is too high, causing the settlement of the existing line and ensuring the safety of the business line. Safety.
Description
技术领域technical field
本发明属于技术领域,特别是涉及一种邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法。The invention belongs to the technical field, and in particular relates to a protection construction method for a deep foundation pit in a station yard under a complex environment of silt geology adjacent to a high-speed railway.
背景技术Background technique
对于邻近既有高铁复杂环境淤泥地质下站场深基坑的施工,基坑防护一般采用混凝土钻孔桩加旋喷桩的防护施工方法,在高铁站场中,通常存在地质条件十分复杂且地下混凝土结构多的情况,由于土质软,地下水丰富,因此高压旋喷桩有时达不到预计的桩底高程,从而难以起到止水帷幕效果。另外,有可能在开挖过程中出现涌水涌砂现象,结果造成既有线沉降,因此上述防护施工方法在这样条件的施工过程中已难以满足既有高铁的运营安全要求。此外,如果在基坑内还需要设置诸如电梯井等小基坑的话,继续开挖小基坑就极有可能出现塌方、流沙、地下水倒灌等情况,从而影响施工的进度及安全。For the construction of deep foundation pits near the existing high-speed rail complex environment and silt geology, the foundation pit protection generally adopts the protection construction method of concrete bored piles and rotary spray piles. In high-speed rail stations, there are usually complex geological conditions and underground In the case of many concrete structures, due to the soft soil and abundant groundwater, the high-pressure jetted piles sometimes cannot reach the expected pile bottom elevation, making it difficult to achieve the effect of a water-stop curtain. In addition, it is possible that water gushing and sand gushing may occur during the excavation process, resulting in settlement of the existing line. Therefore, the above-mentioned protective construction method can hardly meet the operational safety requirements of the existing high-speed railway during the construction process under such conditions. In addition, if a small foundation pit such as an elevator shaft needs to be set up in the foundation pit, if the small foundation pit continues to be excavated, it is very likely that there will be landslides, quicksand, groundwater backflow, etc., thus affecting the progress and safety of the construction.
发明内容SUMMARY OF THE INVENTION
为了解决上述问题,本发明的目的在于提供了一种邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法。In order to solve the above problems, the purpose of the present invention is to provide a construction method for the protection of deep foundation pits in stations adjacent to high-speed rail complex environments with silt geology.
为了达到上述目的,本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法包括按顺序进行的下列步骤:In order to achieve the above-mentioned purpose, the construction method for the protection of deep foundation pits in the adjacent high-speed rail complex environment silt geology provided by the present invention comprises the following steps in order:
1)施工前,根据地质情况并考虑高铁营业线安全,预制钻孔桩用钢护筒和钢沉箱,并在待施工的深基坑一侧设置泥浆箱;1) Before construction, according to the geological conditions and considering the safety of the high-speed railway business line, steel casings and steel caissons for bored piles shall be prefabricated, and a mud tank shall be set up on the side of the deep foundation pit to be constructed;
2)按照设计要求,在待施工的深基坑边缘处采用冲击钻机成孔,泥浆护壁的方式间隔距离形成多个钻孔,每下钻一段距离,对钻孔进行检查并清孔,之后将一节钢护筒设置在该钻孔的侧壁上,如此反复,直至达到混凝土钻孔桩的设计深度,然后在设有钢护筒的每个钻孔内放入一个钢筋笼,之后在钻孔内灌注混凝土,待混凝土凝固并达到设计强度后而制成多根混凝土钻孔桩,作为基坑围护桩;2) According to the design requirements, a percussion drill is used to form holes at the edge of the deep foundation pit to be constructed, and multiple drilling holes are formed at intervals by means of mud wall protection. A section of steel casing is set on the side wall of the borehole, and so on until the design depth of the concrete bored pile is reached, and then a steel cage is placed in each borehole provided with a steel casing, and then the Concrete is poured into the hole, and after the concrete is solidified and reaches the design strength, a plurality of concrete bored piles are made as foundation pit enclosure piles;
3)人工凿除上述混凝土钻孔桩的桩头,然后在凿除桩头的混凝土钻孔桩的上端进行冠梁施工,在冠梁施工的同时将多块钢板间隔距离预埋在冠梁的内侧面上;3) Manually chisel off the pile head of the above-mentioned concrete bored pile, then carry out crown beam construction at the upper end of the concrete bored pile of the chiseled pile head, and at the same time of crown beam construction, multiple steel plates are pre-buried in the crown beam at intervals. inner side;
4)在混凝土钻孔桩的内侧开挖土体,当下挖至距离混凝土钻孔桩的顶部1m处时,将多道横向支撑的两端分别焊接在冠梁上相对应的一对钢板上;继续开挖土体至既有混凝土结构位置;4) When excavating the soil body inside the concrete bored pile, when digging down to 1m from the top of the concrete bored pile, the two ends of the multiple horizontal supports are respectively welded to the corresponding pair of steel plates on the crown beam; Continue to excavate the soil to the position of the existing concrete structure;
5)利用破碎锤将既有混凝土结构凿除至主基坑的基底高程,由此形成主基坑;5) Use a breaker to chisel the existing concrete structure to the base elevation of the main foundation pit, thereby forming the main foundation pit;
6)将钢沉箱下放到主基坑的底面上,并精确定位在小基坑的位置,然后人工在钢沉箱的内部继续开挖土体,开挖土体的同时钢沉箱将逐渐下沉,直至钢沉箱的下端达到小基坑的基底高程,由此形成小基坑,钢沉箱作为小基坑的防护结构;6) Lower the steel caisson to the bottom surface of the main foundation pit, and position it precisely at the position of the small foundation pit, and then manually continue to excavate the soil inside the steel caisson. The steel caisson will gradually sink while excavating the soil. Until the lower end of the steel caisson reaches the base elevation of the small foundation pit, a small foundation pit is formed, and the steel caisson serves as a protective structure for the small foundation pit;
7)利用天泵车浇筑混凝土对主基坑和小基坑进行封底,确保地下无涌水涌砂现象,然后浇筑其他位置垫层,由此完成整个深基坑的防护体系施工过程。7) Use the sky pump truck to pour concrete to seal the bottom of the main foundation pit and the small foundation pit to ensure that there is no water and sand gushing underground, and then pour the cushion in other positions, thus completing the construction process of the protection system for the entire deep foundation pit.
在步骤1)中,所述钢护筒的厚度为6mm、高度为250cm,内径为100cm;泥浆箱采用长6m、宽2m,厚15mm的钢板焊接而成;钢沉箱采用废弃桥墩模板焊制而成。In step 1), the thickness of the steel casing is 6mm, the height is 250cm, and the inner diameter is 100cm; the mud box is welded by steel plates with a length of 6m, a width of 2m, and a thickness of 15mm; to make.
在步骤2)中,所述混凝土钻孔桩的桩径为0.8m,桩间距为1.0m,桩长为6-18m。In step 2), the diameter of the concrete bored pile is 0.8m, the distance between the piles is 1.0m, and the length of the pile is 6-18m.
在步骤3)中,凿除的桩头高度为1米;冠梁的高度为1米,宽度为0.8米,采用钢筋混凝土结构,保护层厚度为40mm,混凝土采用C30混凝土,主筋采用HRB400Φ22钢筋。In step 3), the height of the chiseled pile head is 1 meter; the height of the crown beam is 1 meter, the width is 0.8 meters, the reinforced concrete structure is adopted, the thickness of the protective layer is 40mm, the concrete adopts C30 concrete, and the main reinforcement adopts HRB400Φ22 steel bar.
在步骤4)中,所述横向支撑采用直径50cm的钢管;土体采用分段、分层、对称、平衡、限时的开挖方式,分层厚度为3.5米,长度为6米。In step 4), a steel pipe with a diameter of 50 cm is used for the lateral support; the soil is excavated in a segmented, layered, symmetrical, balanced, and time-limited manner, with a layered thickness of 3.5 meters and a length of 6 meters.
本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法具有如下有益效果:The construction method for the protection of deep foundation pits in stations under silt geology in a complex environment adjacent to a high-speed railway provided by the present invention has the following beneficial effects:
1、将传统基坑的混凝土钻孔桩加旋喷桩的防护施工方法改变成混凝土钻孔桩加钢沉箱的防护施工方法,其中混凝土钻孔桩主要起抗剪力作用,钢沉箱起防水防砂作用,从而形成整个深基坑的防护体系。1. Change the protection construction method of concrete bored piles and rotary spray piles in the traditional foundation pit to the protection construction method of concrete bored piles and steel caissons, in which the concrete bored piles mainly play the role of shear resistance, and the steel caisson plays the role of waterproof and sand prevention. function, thus forming a protection system for the entire deep foundation pit.
2、开挖过程中,混凝土钻孔桩加钢沉箱的防护体系,既保证了基坑稳定安全,又能防止地下水压过大时,地下涌水、涌砂,造成既有线路沉降,保证了营业线的安全。2. During the excavation process, the protection system of concrete bored piles and steel caisson not only ensures the stability and safety of the foundation pit, but also prevents the underground water and sand gushing out when the groundwater pressure is too large, causing the settlement of the existing lines and ensuring the business operation. line safety.
附图说明Description of drawings
图1为本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法流程图。FIG. 1 is a flowchart of a construction method for deep foundation pit protection in a station yard under a complex environment of silt geology near a high-speed rail provided by the present invention.
图2为采用本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法时深基坑平面图。2 is a plan view of a deep foundation pit when the construction method for protecting a deep foundation pit in a station yard under a complex environment of silt geology provided by the present invention is adopted.
图3为采用本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法时深基坑侧面图。3 is a side view of the deep foundation pit when the construction method for the protection of the deep foundation pit in the station yard under the complex environment of the silt geology provided by the present invention is adopted.
具体实施方式Detailed ways
在某铁路工程站场改建工程中,该站场所在位置的地质环境复杂且地下混凝土结构多,土质软,地下水丰富。为了保证施工安全及既有营业线运营安全,本申请人利用本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法进行了深基坑的施工,有效地防止了塌方,流沙,地下水倒灌等情况对工程的影响,确保了施工的进度及安全。In the reconstruction project of a railway engineering station, the site is located in a complex geological environment with many underground concrete structures, soft soil and abundant groundwater. In order to ensure the construction safety and the operation safety of the existing business line, the applicant has carried out the construction of the deep foundation pit by using the deep foundation pit protection construction method of the nearby high-speed railway complex environment silt geology provided by the present invention, effectively preventing landslides, quicksand , the impact of groundwater inversion and other conditions on the project, to ensure the progress and safety of the construction.
下面结合附图和具体实施例对本发明进行详细说明。The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
如图1-图3所示,本发明提供的邻近高铁复杂环境淤泥地质下站场深基坑防护施工方法包括按顺序进行的下列步骤:As shown in Figures 1 to 3, the construction method for the protection of deep foundation pits in stations under silt geological conditions adjacent to high-speed rail complex environments provided by the present invention includes the following steps in order:
1)施工前,根据地质情况并考虑高铁营业线安全,预制钻孔桩用钢护筒和钢沉箱4,并在待施工的深基坑1一侧设置泥浆箱;在本发明中,钢护筒的厚度为6mm、高度为250cm,内径为100cm;泥浆箱采用长6m、宽2m,厚15mm的钢板焊接而成;钢沉箱4采用废弃桥墩模板焊制而成。1) Before construction, according to the geological conditions and considering the safety of the high-speed rail line, prefabricated steel casings and steel caisson 4 for bored piles, and set up a mud tank on one side of the deep foundation pit 1 to be constructed; The thickness of the cylinder is 6mm, the height is 250cm, and the inner diameter is 100cm; the mud tank is welded by steel plates with a length of 6m, a width of 2m and a thickness of 15mm; the steel caisson 4 is welded by the template of the abandoned bridge pier.
2)按照设计要求,在待施工的深基坑1边缘处采用冲击钻机成孔,泥浆护壁的方式间隔距离形成多个钻孔,每下钻一段距离,对钻孔进行检查并清孔,之后将一节钢护筒设置在该钻孔的侧壁上,如此反复,直至达到混凝土钻孔桩2的设计深度,然后在设有钢护筒的每个钻孔内放入一个钢筋笼,之后在钻孔内灌注混凝土,待混凝土凝固并达到设计强度后而制成多根混凝土钻孔桩2,作为基坑围护桩;在本发明中,混凝土钻孔桩2的桩径为0.8m,桩间距为1.0m,桩长为6-18m;钻进时,采用小冲程开孔,进入正常钻进状态后,采用4~5m中大冲程,最大冲程不超过6m,钻进过程中应及时排碴。注意地层变化,在地层变化处抽取碴样,以判断地质类别,并与设计提供的地质剖面图相对照,作好相关记录,及时根据地质条件调整钻进工艺。钢筋笼主筋接头采用双面搭接焊,每一截面上接头数量不超过50%,加强箍筋与主筋连接全部焊接。清孔采用抽浆法,利用冲击钻机的泥浆泵持续吸渣5min~15min左右,将孔底钻渣清除干净。当下完钢筋笼和导管后利用导管进行二次清孔,使清孔后钻孔内的泥浆指标及孔底沉渣厚度符合设计及规范要求。在清孔排渣时注意保持钻孔内水头,防止坍塌。二次清孔完成后,立即浇筑混凝土。2) According to the design requirements, a percussion drill is used to form holes at the edge of the deep foundation pit 1 to be constructed, and multiple holes are formed at intervals by means of mud wall protection. A section of steel casing is set on the side wall of the borehole, and so on, until the design depth of the concrete
3)人工凿除上述混凝土钻孔桩2的桩头,然后在凿除桩头的混凝土钻孔桩2的上端进行冠梁施工,在冠梁施工的同时将多块钢板间隔距离预埋在冠梁的内侧面上。在本发明中,凿除的桩头高度为1米;冠梁的高度为1米,宽度为0.8米,采用钢筋混凝土结构,保护层厚度为40mm,混凝土采用C30混凝土,主筋采用HRB400Φ22钢筋。3) Manually chisel off the pile head of the above-mentioned concrete
4)在混凝土钻孔桩2的内侧开挖土体,当下挖至距离混凝土钻孔桩2的顶部1m处时,将多道横向支撑3的两端分别焊接在冠梁上相对应的一对钢板上;继续开挖土体至既有混凝土结构位置,比如既有挡墙基础或管桩桩帽;在本发明中,横向支撑3采用直径50cm的钢管。土体采用分段、分层、对称、平衡、限时的开挖方式,分层厚度为3.5米,长度为6米,开挖完成需在9小时内;4) Excavate the soil inside the concrete
5)利用破碎锤将既有混凝土结构凿除至主基坑的基底高程,由此形成主基坑;5) Use a breaker to chisel the existing concrete structure to the base elevation of the main foundation pit, thereby forming the main foundation pit;
6)将钢沉箱4下放到主基坑的底面上,并精确定位在小基坑的位置,然后人工在钢沉箱4的内部继续开挖土体,开挖土体的同时钢沉箱4将逐渐下沉,直至钢沉箱4的下端达到小基坑的基底高程,由此形成小基坑,钢沉箱4作为小基坑的防护结构;6) Lower the steel caisson 4 to the bottom surface of the main foundation pit, and accurately position it at the position of the small foundation pit, and then manually continue to excavate the soil inside the steel caisson 4. While excavating the soil, the steel caisson 4 will gradually Sinking until the lower end of the steel caisson 4 reaches the base elevation of the small foundation pit, thereby forming a small foundation pit, and the steel caisson 4 serves as a protective structure for the small foundation pit;
7)利用天泵车浇筑混凝土对主基坑和小基坑进行封底,确保地下无涌水涌砂现象,然后浇筑其他位置垫层,由此完成整个深基坑1的防护体系施工过程。7) Use the sky pump truck to pour concrete to seal the bottom of the main foundation pit and the small foundation pit to ensure that there is no water and sand gushing underground, and then pour the cushion at other positions, thus completing the construction process of the protection system of the entire deep foundation pit 1.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010608501.3A CN111733827A (en) | 2020-06-29 | 2020-06-29 | Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010608501.3A CN111733827A (en) | 2020-06-29 | 2020-06-29 | Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111733827A true CN111733827A (en) | 2020-10-02 |
Family
ID=72653564
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010608501.3A Pending CN111733827A (en) | 2020-06-29 | 2020-06-29 | Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111733827A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113585273A (en) * | 2021-08-06 | 2021-11-02 | 中交隧道工程局有限公司 | Earth-rock geological foundation pit forming construction method |
CN114215066A (en) * | 2021-11-24 | 2022-03-22 | 中国水利水电第九工程局有限公司 | Open cut foundation pit side wall collapse prevention excavation construction method |
CN115030207A (en) * | 2022-07-06 | 2022-09-09 | 河南三建建设集团有限公司 | Construction method of steel caisson at bottom pit part of elevator shaft |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106592601A (en) * | 2016-12-05 | 2017-04-26 | 中建六局土木工程有限公司 | Metro-adjacent complex geological environment supporting system construction method |
CN110093971A (en) * | 2019-04-26 | 2019-08-06 | 中铁第四勘察设计院集团有限公司 | The Combined water pump house and its construction method of subterranean tunnel |
CN110847159A (en) * | 2019-11-28 | 2020-02-28 | 中铁十六局集团有限公司 | Construction process of in-hole mechanical pile for subway construction |
CN111305225A (en) * | 2020-03-09 | 2020-06-19 | 中铁科建工程有限公司 | Engineering construction method of underground protective structure |
-
2020
- 2020-06-29 CN CN202010608501.3A patent/CN111733827A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106592601A (en) * | 2016-12-05 | 2017-04-26 | 中建六局土木工程有限公司 | Metro-adjacent complex geological environment supporting system construction method |
CN110093971A (en) * | 2019-04-26 | 2019-08-06 | 中铁第四勘察设计院集团有限公司 | The Combined water pump house and its construction method of subterranean tunnel |
CN110847159A (en) * | 2019-11-28 | 2020-02-28 | 中铁十六局集团有限公司 | Construction process of in-hole mechanical pile for subway construction |
CN111305225A (en) * | 2020-03-09 | 2020-06-19 | 中铁科建工程有限公司 | Engineering construction method of underground protective structure |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113585273A (en) * | 2021-08-06 | 2021-11-02 | 中交隧道工程局有限公司 | Earth-rock geological foundation pit forming construction method |
CN114215066A (en) * | 2021-11-24 | 2022-03-22 | 中国水利水电第九工程局有限公司 | Open cut foundation pit side wall collapse prevention excavation construction method |
CN114215066B (en) * | 2021-11-24 | 2023-09-22 | 中国水利水电第九工程局有限公司 | Collapse-prevention excavation construction method for side wall of open cut foundation pit |
CN115030207A (en) * | 2022-07-06 | 2022-09-09 | 河南三建建设集团有限公司 | Construction method of steel caisson at bottom pit part of elevator shaft |
CN115030207B (en) * | 2022-07-06 | 2024-05-03 | 河南三建建设集团有限公司 | Construction method of steel caisson at pit part of elevator |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101139838B (en) | Construction method for high artesian area ultra-deep foundation pit | |
CN108914931B (en) | An assembled vertical shield ring foundation pile and construction method | |
CN102392458B (en) | Piling beam cofferdam construction method used for bare rock foundation construction in water | |
CN101215834A (en) | Construction Method of Outrigger Type Diaphragm Wall | |
CN105672348A (en) | Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region | |
CN103422510B (en) | Steel pipe frame type cofferdam structure and construction method | |
CN104295239A (en) | Method for using rotary drilling rig to drill into hard rock stratum | |
Godavarthi et al. | Contiguous pile wall as a deep excavation supporting system | |
CN111733827A (en) | Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology | |
CN111236241B (en) | Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method | |
CN111705786A (en) | Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile | |
CN106758759B (en) | A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed | |
CN104790410A (en) | Foundation pit excavation supporting method suitable for watercourse with shallow water and sludge | |
CN117661615A (en) | A method for sealing water inrush at the bottom of foundation pits | |
CN110055973A (en) | Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time | |
CN112942399A (en) | Open caisson mechanical construction device and method for penetrating rock stratum | |
CN113216215A (en) | Deep groove support reverse construction method in complex environment | |
CN209260739U (en) | A kind of foundation pit water-stopping system close to river permeable stratum | |
CN112709252B (en) | Bearing platform construction method in semi-water flooding steep rock slope | |
CN214423184U (en) | Be applied to hasp steel-pipe pile cofferdam under water level variation condition | |
CN114658050A (en) | Construction method for grooving diaphragm wall containing medium-stroke petrochemical rock stratum | |
Igba et al. | Strengthening and underpinning of a sinking two storey building in Lagos State Nigeria | |
CN114232602A (en) | Underground continuous pile construction process | |
CN220487583U (en) | High-water-head water-rich stratum freezing method shield receiving well | |
CN111395066B (en) | Reconstruction structure and construction method of existing railway subgrade underground drainage system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201002 |