CN111395350A - 一种软土深基坑挖土施工工法 - Google Patents
一种软土深基坑挖土施工工法 Download PDFInfo
- Publication number
- CN111395350A CN111395350A CN202010294890.7A CN202010294890A CN111395350A CN 111395350 A CN111395350 A CN 111395350A CN 202010294890 A CN202010294890 A CN 202010294890A CN 111395350 A CN111395350 A CN 111395350A
- Authority
- CN
- China
- Prior art keywords
- excavation
- foundation pit
- soft soil
- construction method
- deep foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明提出一种软土深基坑挖土施工工法,包括如下步骤:a,划分跳仓开挖分区;b,确定开挖顺序及流向;c,布置临时施工道路;d,开挖作业。本发明的优点:基坑开挖一次到底,无需分层开挖,可提高工作效率,节约成本;跳仓挖土,分块释放基坑侧压力,基坑开挖更安全,在一定程度上还可以减少锚索等基坑侧壁支护措施,优化设计,加快施工进度;采取跳仓挖土,地下室结构也是跳仓浇筑,可省去后浇带一侧的止水钢板及凿毛费用;合理设计临时施工道路和施工顺序,减少施工道路的换填。
Description
技术领域
本发明涉及基坑施工,特别是指一种软土深基坑挖土施工工法。本发明主要应用在开挖深度6-10m的软土深基坑开挖施工,尤其适用于基坑开挖深度10m以下的基坑设计安全储备小、大型基坑开挖。
背景技术
基坑是在基础设计位置按基底标高和基础平面尺寸所开挖的土坑,一般来说,深基坑是指开挖深度大于等于5m的基坑。深基坑的施工质量在建筑工程中是基石的作用,而分层分段的开挖方式是深基坑常用的一种施工工法。
对于软土深基坑,采用传统的分层分段开挖方式,需多次换填施工道路,增加土方开挖成本,土方开挖工效低,并且难以满足基坑变形控制要求,基坑开挖安全隐患大,这是软土深基坑开挖面临的普遍技术难题。
发明内容
本发明提出一种软土深基坑挖土施工工法,解决了软土深基坑土方开挖难度大、工效低、安全风险大等难题,具有明显的经济效益和社会效益。
本发明的技术方案是这样实现的:一种软土深基坑挖土施工工法,包括如下步骤:
a,划分跳仓开挖分区;b,确定开挖顺序及流向;c,布置临时施工道路;d,开挖作业。
所述的步骤a中,根据结构底板控制收缩裂缝的尺寸要求、临时放坡的空间需求、挖土作业面需要,以及兼顾挖土效率来划分跳仓开挖分区的大小,并对跳仓开挖分区进行编号。
所述的步骤b中,开挖分区之间采取跳仓挖土,将基坑侧壁土应力分块释放。
所述的步骤d中,通过在地下室底板和中楼板设置传力带,利用开挖分区的开挖时间差,将基坑侧壁的土压力先后作用在地下室结构上,大大减小基坑开挖的安全风险。
所述的步骤b中,开挖流向采取从基坑侧壁向基坑内部开挖,及时浇筑紧靠基坑侧壁的配筋垫层。
所述的步骤c中,根据开挖顺序,将临时施工道路布置在开挖时间较晚的区域,尽量避免临时施工道路移位。
所述的步骤c中,先将临时施工道路下方的虚土挖除,然后采用砖渣回填、压实。
所述的步骤c中,临时施工道路厚度0.5~0.7m,宽度8~10m。
所述的步骤d中,在每个开挖分区的开挖点形成临时二级放坡,在一个开挖断面上的坡顶、坡中平台、坡底各布置一台挖机,接力挖土,采取退挖、一次到底的开挖方式。
所述的步骤d中,采取跳仓挖土,可以减少锚索等基坑侧壁支护措施,优化设计,加快施工进度。
所述的步骤d中,采取跳仓挖土,地下室结构也是跳仓浇筑,可省去后浇带一侧的止水钢板及凿毛费用。
所述的步骤d中,临时两级放坡的坡度为1:1.5,在退挖过程中,始终以形成两级放坡为根本,来挖除土方。
所述的步骤d中,根据基坑变形监测结果,可灵活调整开挖分区的大小。
所述的步骤d中,土方开挖至设计标高后,应在8小时内将垫层浇筑完毕,及时施工地下室底板,防止软土基坑的基底隆起,尽快将基坑侧压力传递给地下室结构。
本发明的优点:基坑开挖一次到底,无需分层开挖,可提高工作效率,节约成本;跳仓挖土,分块释放基坑侧压力,基坑开挖更安全,在一定程度上还可以减少锚索等基坑侧壁支护措施,优化设计,加快施工进度;采取跳仓挖土,地下室结构也是跳仓浇筑,可省去后浇带一侧的止水钢板及凿毛费用;合理设计临时施工道路和施工顺序,减少施工道路的换填。
附图说明
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1为实施例1开挖分区示意图。
图2为实施例1临时施工道路示意图。
图3为实施例1两级放坡示意图。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
一种软土深基坑挖土施工工法,包括如下步骤。
a,划分跳仓开挖分区。根据结构底板控制收缩裂缝的尺寸要求、临时放坡的空间需求、挖土作业面需要,以及兼顾挖土效率来划分开挖分区的大小,并对开挖分区进行编号。
b,确定开挖顺序及流向。开挖分区之间采取跳仓挖土,将基坑侧壁土应力分块释放。开挖流向采取从基坑侧壁向基坑内部开挖,及时浇筑紧靠基坑侧壁的配筋垫层。
c,布置临时施工道路。根据开挖顺序,将临时施工道路布置在开挖时间较晚的区域,尽量避免临时施工道路移位。临时施工道路呈环状布置,施工机械车辆 “一进一出”通行。先将临时施工道路下方的虚土挖除,然后采用砖渣回填、压实,临时施工道路厚度0.5~0.7m,宽度8~10m。
d,开挖作业。开挖分区之间采取跳仓挖土,将基坑侧壁土应力分块释放。通过在地下室底板和中楼板设置传力带,利用开挖分区的开挖时间差,将基坑侧壁的土压力先后作用在地下室结构上,大大减小基坑开挖的安全风险。
在每个开挖分区的每个开挖点形成临时二级放坡,在一个开挖断面上的坡顶、坡中平台、坡底各布置一台挖机,接力挖土,采取退挖、一次到底的开挖方式。临时两级放坡的坡度为1:1.5,在退挖过程中,始终以形成两级放坡为根本,来挖除土方。
根据基坑变形监测结果,可灵活调整开挖分区的大小。
土方开挖至设计标高后,应在8小时内将垫层浇筑完毕,及时施工地下室底板,防止软土基坑的基底隆起,尽快将基坑侧压力传递给地下室结构。
实施例1
如图1至3所示,一种软土深基坑挖土施工工法,包括如下步骤。
a,划分跳仓开挖分区。根据结构底板控制收缩裂缝的尺寸要求、临时放坡的空间需求、挖土作业面需要,以及兼顾挖土效率来划分开挖分区的大小,将本工程土方开挖划分为14个区进行跳仓开挖,并对开挖分区进行编号。
b,确定开挖顺序及流向。开挖分区之间采取跳仓挖土,将基坑侧壁土应力分块释放。开挖流向采取从基坑侧壁向基坑内部开挖,及时浇筑紧靠基坑侧壁的配筋垫层。同时根据业主预售、地下室顶板行车等施工部署要求,以及栈桥影响,本工程跳仓开挖顺序为3区→1区→4区→2区→5区→7区→9区→6区→8区→13区→10区→12区→14区→11区,在视图右侧预留出入口。其中,3区为业主预售楼栋,优先施工,1区~9区地下室顶板为整个工程的场内交通枢纽,也应提前组织施工。
c,布置临时施工道路。将临时施工道路布置在开挖时间较晚的区域,尽量避免临时施工道路移位。本工程基坑面积较大,日均出土量约4000立方,且土方开挖与基坑支护交叉施工,为了避免场内交通拥堵,临时施工道路呈环状布置,施工机械车辆考虑“一进一出”通行。先将临时施工道路下方的虚土挖除,然后采用砖渣回填、压实;临时施工道路厚度0.6m,宽度8~10m。
d,开挖作业。跳仓挖土的相邻分区,后开挖的分区开挖前,其相邻分区应已开展地下室底板钢筋绑扎,后开挖的分区开挖完成后,其相邻分区的地下室底板(传力带与底板同步浇筑)应浇筑完成。相邻分区的地下室底板施工节奏与土方开挖节奏应相互协调,将基坑侧壁土应力分块释放,基坑侧壁土压力分块、先后传递给地下室结构,确保基坑开挖安全。
采取跳仓挖土,可以减少锚索等基坑侧壁支护措施,优化基坑设计,加快施工进度。采取跳仓挖土,地下室结构也是跳仓浇筑,可省去后浇带一侧的止水钢板及凿毛费用。
各开挖分区内采取“一个断面三台挖机”接力开挖方式,从基坑侧壁开始退挖,开挖时形成临时两级放坡,三台挖机分别布置在坡顶、坡中平台、坡底接力挖土、一次到底(即不分层),与分层开挖相比,不需要多次换填出土施工道路,加快了土方开挖进度。
临时两级放坡的坡度为1:1.5,在退挖过程中,始终以形成两级放坡为根本,来挖除土方。土方开挖至设计标高后,应在8小时内将垫层浇筑完毕,及时施工地下室底板,防止软土基坑的基底隆起,尽快将基坑侧压力传递给地下室结构。
在休班停机前,应确保形成两级放坡,挖机驶离作业面,防止临时边坡坍塌。土方即挖即运,严禁坑边堆载。
开挖作业时,根据基坑变形监测结果,可灵活调整开挖分区的大小。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (10)
1.一种软土深基坑挖土施工工法,其特征在于,包括如下步骤:
a,划分跳仓开挖分区;
b,确定开挖顺序及流向;
c,布置临时施工道路;
d,开挖作业。
2.根据权利要求1或2所述的软土深基坑挖土施工工法,其特征在于:所述的步骤b中,开挖流向采取从基坑侧壁向基坑内部开挖,及时浇筑紧靠基坑侧壁的配筋垫层。
3.根据权利要求1所述的软土深基坑挖土施工工法,其特征在于:所述的步骤c中,根据开挖顺序,将临时施工道路布置在开挖时间较晚的区域,尽量避免临时施工道路移位。
4.根据权利要求3所述的软土深基坑挖土施工工法,其特征在于:所述的步骤c中,先将临时施工道路下方的虚土挖除,然后采用砖渣回填、压实。
5.根据权利要求1所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,通过在地下室底板和中楼板设置传力带,利用开挖分区的开挖时间差,将基坑侧壁的土压力先后作用在地下室结构上,大大减小基坑开挖的安全风险。
6.根据权利要求1所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,采取跳仓挖土,可以减少锚索等基坑侧壁支护措施,优化基坑设计,加快施工进度。
7.根据权利要求1或6所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,采取跳仓挖土,地下室结构也是跳仓浇筑,可省去后浇带一侧的止水钢板及凿毛费用。
8.根据权利要求1所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,在每个开挖分区的开挖点形成临时二级放坡,在一个开挖断面上的坡顶、坡中平台、坡底各布置一台挖机,接力挖土,采取退挖、一次到底的开挖方式。
9.根据权利要求1或8所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,根据基坑变形监测结果,可灵活调整开挖分区的大小。
10.根据权利要求1或8所述的软土深基坑挖土施工工法,其特征在于:所述的步骤d中,土方开挖至设计标高后,应在8小时内将垫层浇筑完毕,及时施工地下室底板,防止软土基坑的基底隆起,尽快将基坑侧压力传递给地下室结构。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010294890.7A CN111395350A (zh) | 2020-04-15 | 2020-04-15 | 一种软土深基坑挖土施工工法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010294890.7A CN111395350A (zh) | 2020-04-15 | 2020-04-15 | 一种软土深基坑挖土施工工法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111395350A true CN111395350A (zh) | 2020-07-10 |
Family
ID=71435159
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010294890.7A Pending CN111395350A (zh) | 2020-04-15 | 2020-04-15 | 一种软土深基坑挖土施工工法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111395350A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114117585A (zh) * | 2021-10-28 | 2022-03-01 | 中建三局集团(深圳)有限公司 | 基坑跳仓法施工中目标开挖方案的确定方法 |
CN114164814A (zh) * | 2021-11-03 | 2022-03-11 | 广州航海学院 | 适用于临海机场改扩建工程的泡沫轻质土换填软基工法 |
CN114232397A (zh) * | 2021-11-29 | 2022-03-25 | 国网北京市电力公司 | 地基换填方法 |
CN114922191A (zh) * | 2022-05-18 | 2022-08-19 | 中国建筑第八工程局有限公司 | 多基坑中的狭小基坑施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000297590A (ja) * | 1999-04-16 | 2000-10-24 | Chem Grouting Co Ltd | 掘削壁築造工法 |
CN102535474A (zh) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | 一种深基坑挖土的施工方法 |
CN103321230A (zh) * | 2013-07-12 | 2013-09-25 | 上海隧道工程股份有限公司 | 在运行浅埋地铁长距离穿越场地中的深大基坑开挖方法 |
CN103590406A (zh) * | 2013-11-29 | 2014-02-19 | 中船第九设计研究院工程有限公司 | 一种超大型深基坑分区同步开挖的施工方法 |
CN105926630A (zh) * | 2016-04-27 | 2016-09-07 | 中天建设集团有限公司 | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 |
-
2020
- 2020-04-15 CN CN202010294890.7A patent/CN111395350A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000297590A (ja) * | 1999-04-16 | 2000-10-24 | Chem Grouting Co Ltd | 掘削壁築造工法 |
CN102535474A (zh) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | 一种深基坑挖土的施工方法 |
CN103321230A (zh) * | 2013-07-12 | 2013-09-25 | 上海隧道工程股份有限公司 | 在运行浅埋地铁长距离穿越场地中的深大基坑开挖方法 |
CN103590406A (zh) * | 2013-11-29 | 2014-02-19 | 中船第九设计研究院工程有限公司 | 一种超大型深基坑分区同步开挖的施工方法 |
CN105926630A (zh) * | 2016-04-27 | 2016-09-07 | 中天建设集团有限公司 | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 |
Non-Patent Citations (1)
Title |
---|
余杰等: "《 建筑基坑跳仓开挖的施工组织》", 《建筑施工》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114117585A (zh) * | 2021-10-28 | 2022-03-01 | 中建三局集团(深圳)有限公司 | 基坑跳仓法施工中目标开挖方案的确定方法 |
CN114164814A (zh) * | 2021-11-03 | 2022-03-11 | 广州航海学院 | 适用于临海机场改扩建工程的泡沫轻质土换填软基工法 |
CN114164814B (zh) * | 2021-11-03 | 2023-10-13 | 广州航海学院 | 适用于临海机场改扩建工程的泡沫轻质土换填软基工法 |
CN114232397A (zh) * | 2021-11-29 | 2022-03-25 | 国网北京市电力公司 | 地基换填方法 |
CN114922191A (zh) * | 2022-05-18 | 2022-08-19 | 中国建筑第八工程局有限公司 | 多基坑中的狭小基坑施工方法 |
CN114922191B (zh) * | 2022-05-18 | 2024-03-12 | 中国建筑第八工程局有限公司 | 多基坑中的狭小基坑施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111395350A (zh) | 一种软土深基坑挖土施工工法 | |
CN107313431B (zh) | 临近不等高基坑同步施工方法 | |
CN101691751B (zh) | 超长人工挖孔桩穿越溶洞施工方法及穿越溶洞的超长桩 | |
CN102995659A (zh) | 超大型地下工程的先中心区结合周边的施工方法 | |
CN110159294A (zh) | 一种高陡地形桥隧相接段接长明洞施工方法 | |
CN107190752A (zh) | 一种柔性复合防渗装配式可回收矩形截面排桩支护结构的设计施工方法 | |
CN105839946A (zh) | 砖混结构建筑物提升增层方法 | |
CN106498951B (zh) | 一种竖井开挖施工方法 | |
CN113006113B (zh) | 一种地下连续墙加大直径钢管桩的复合锚碇基础及其施工方法 | |
WO2004033843A2 (en) | Subterranean structures and methods for constructing subterranean structures | |
CN106988337B (zh) | 一种用于减小条形浅基础房屋不均匀沉降的加固方法 | |
CN117536478B (zh) | 地连墙拆除块吊具、地连墙拆除方法、围堰拆除方法 | |
CN104480945B (zh) | 一种基坑逆作施工方法 | |
CN104499489B (zh) | 一种基坑施工方法 | |
JP6194388B1 (ja) | オープンシールド工法 | |
CN111218938A (zh) | 既有隧道上方的基坑开挖施工方法 | |
CN111764417A (zh) | 河岸围堰结构拆除施工方法 | |
CN109797717A (zh) | 一种河道上穿即有地铁隧道的施工方法 | |
CN115262567A (zh) | 一种超窄全硬岩深基坑开挖方法 | |
CN110735434B (zh) | 一种狭长深基坑内地下传力带代替传统内支撑施工的方法 | |
CN111851510B (zh) | 土岩基坑爆破开挖体系及应用其的施工方法 | |
CN115094912A (zh) | 一种超大型软土基坑上部建筑跨分区顺逆结合施工方法 | |
KR0179326B1 (ko) | 강재 지지박스에 의한 지하연속벽의 시공방법 | |
JPH06341154A (ja) | 地下躯体構築工法 | |
CN113266362A (zh) | 一种穿越既有密集锚索区域的顶管盖挖施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450003 Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd. Address before: 450003 No. 108 Chengdong Road, Jinshui District, Henan, Zhengzhou Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200710 |