[go: up one dir, main page]

CN111339486A - A big data evaluation method for deep foundation pit blasting vibration velocity risk level - Google Patents

A big data evaluation method for deep foundation pit blasting vibration velocity risk level Download PDF

Info

Publication number
CN111339486A
CN111339486A CN202010126471.2A CN202010126471A CN111339486A CN 111339486 A CN111339486 A CN 111339486A CN 202010126471 A CN202010126471 A CN 202010126471A CN 111339486 A CN111339486 A CN 111339486A
Authority
CN
China
Prior art keywords
vibration velocity
blasting vibration
foundation pit
factors
risk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010126471.2A
Other languages
Chinese (zh)
Inventor
袁长丰
陈秋汝
于广明
李亮
凌贤长
贺可强
路世豹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao University of Technology
Original Assignee
Qingdao University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao University of Technology filed Critical Qingdao University of Technology
Priority to CN202010126471.2A priority Critical patent/CN111339486A/en
Priority to PCT/CN2020/089026 priority patent/WO2021169038A1/en
Publication of CN111339486A publication Critical patent/CN111339486A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • G06F17/15Correlation function computation including computation of convolution operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • G06F17/16Matrix or vector computation, e.g. matrix-matrix or matrix-vector multiplication, matrix factorization
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Mathematical Physics (AREA)
  • Theoretical Computer Science (AREA)
  • Pure & Applied Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Databases & Information Systems (AREA)
  • Algebra (AREA)
  • General Engineering & Computer Science (AREA)
  • Software Systems (AREA)
  • Business, Economics & Management (AREA)
  • Computing Systems (AREA)
  • Economics (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明属于深基坑施工对周围环境影响分析领域,具体涉及一种深基坑爆破振速风险等级大数据评价方法。是在对周围环境信息进行量化的基础上,考虑多种数据下的爆破振速风险评价,最终确定工程所需的爆破振速。该方法避免了只根据爆破规范来进行的、不考虑周围环境情况的爆破振速确定方法,确定的爆破振速更具科学合理性。

Figure 202010126471

The invention belongs to the field of analysis of the impact of deep foundation pit construction on the surrounding environment, and particularly relates to a big data evaluation method for a deep foundation pit blasting vibration velocity risk level. On the basis of quantifying the surrounding environmental information, considering the blasting vibration velocity risk assessment under various data, the blasting vibration velocity required for the project is finally determined. This method avoids the method of determining the blasting vibration velocity, which is carried out only according to the blasting specification and does not consider the surrounding environment, and the determined blasting vibration velocity is more scientific and reasonable.

Figure 202010126471

Description

一种深基坑爆破振速风险等级大数据评价方法A big data evaluation method for deep foundation pit blasting vibration velocity risk level

技术领域:Technical field:

本发明属于深基坑施工对周围环境影响分析领域,具体涉及一种深基坑爆破振速风险等级大数据评价方法。The invention belongs to the field of analysis of the impact of deep foundation pit construction on the surrounding environment, and particularly relates to a big data evaluation method for a deep foundation pit blasting vibration velocity risk level.

背景技术:Background technique:

随着国家基础设施建设的快速发展,深大基坑不断出现。在基坑施工过程中经常需要岩石爆破,爆破振动会对周围环境产生影响,特别是在人群拥挤的城市中,周围都是建筑物和居民,对爆破要求更高。合理评估爆破振速对周围环境影响是关系民生的工程实际问题,具有重要意义。目前,爆破振速的实施主要通过对照爆破规范要求来确定,这样按照规范确定的振速在实际工程爆破时,经常出现附近居民上访和建筑物损伤的案例,究其原因,主要是爆破波这种能量在不同地层组合的介质中的传播能耗不同,同时,爆破所处的不同周围环境要求也不同。因此,需要综合考虑各种影响因素,对规范要求的爆破振速进行周围环境风险等级评价后在最终爆破振速,这样才能够更科学开展施工。With the rapid development of national infrastructure construction, deep and large foundation pits continue to appear. Rock blasting is often required in the process of foundation pit construction, and blasting vibration will affect the surrounding environment, especially in crowded cities, surrounded by buildings and residents, and higher requirements for blasting. Reasonable assessment of the impact of blasting vibration speed on the surrounding environment is a practical engineering problem related to people's livelihood, and is of great significance. At present, the implementation of blasting vibration velocity is mainly determined by comparing with the requirements of blasting regulations. In this way, when the vibration velocity determined according to the specifications is used in actual engineering blasting, there are often cases of petitions by nearby residents and damage to buildings. The reason is mainly the blasting wave. The propagation energy consumption of various kinds of energy in the medium of different formation combinations is different, and at the same time, the requirements of different surrounding environments where the blasting is located are also different. Therefore, it is necessary to comprehensively consider various influencing factors, and evaluate the surrounding environmental risk level for the blasting vibration velocity required by the specification, and then determine the final blasting vibration velocity, so that the construction can be carried out more scientifically.

发明内容:Invention content:

本发明要解决的技术问题是爆破所处的周围环境要求不同,不能仅对照爆破规范要求来确定。The technical problem to be solved by the present invention is that the requirements of the surrounding environment where the blasting is located are different, which cannot be determined only by reference to the requirements of the blasting specification.

为解决上述问题,本发明提出基坑爆破振速风险等级大数据评价方法,在对周围环境信息进行量化的基础上,考虑多种数据下的爆破振速风险评价,最终确定工程所需的爆破振速。该方法避免了只根据爆破规范来进行的、不考虑周围环境情况的爆破振速确定方法,确定的爆破振速更具科学合理性。In order to solve the above problems, the present invention proposes a big data evaluation method for the vibration velocity risk level of foundation pit blasting. On the basis of quantifying the surrounding environmental information, considering the blasting vibration velocity risk assessment under various data, the blasting required for the project is finally determined. Vibration speed. This method avoids the method of determining the blasting vibration velocity, which is carried out only according to the blasting specification and does not consider the surrounding environment, and the determined blasting vibration velocity is more scientific and reasonable.

为达到上述目的,本发明具体通过以下技术方案实现,一种深基坑爆破振速风险等级大数据评价方法,如图1所示,以地铁车站深基坑爆破为例,包括以下步骤:In order to achieve the above object, the present invention is specifically realized by the following technical solutions. A method for evaluating the risk level of vibration velocity in deep foundation pit blasting with big data, as shown in Figure 1, takes the deep foundation pit blasting of a subway station as an example, including the following steps:

(1)确定爆破工程周围环境影响因素,划分因素的风险等级,采用集合方法公约量化因素;(1) Determine the environmental impact factors around the blasting project, divide the risk levels of the factors, and use the collective method to quantify the factors;

(2)确定风险评价集合,把对爆破振速对周围环境影响风险评价划分等级,为后期评价确定标准;(2) Determine the risk assessment set, classify the risk assessment of the impact of blasting vibration speed on the surrounding environment, and determine the standard for the later assessment;

(3)根据公约量化因素确定隶属度函数以及隶属度;(3) Determine the membership function and membership degree according to the quantification factors of the convention;

(4)计算各影响因素信息熵,确定考虑信息熵的各影响因素权重,得到影响因素权重矩阵,然后建立周围环境风险评价初级矩阵,即隶属度矩阵,进一步得到爆破振速对周围环境影响风险评价终极矩阵;(4) Calculate the information entropy of each influencing factor, determine the weight of each influencing factor considering the information entropy, obtain the weight matrix of the influencing factors, and then establish the primary matrix of surrounding environmental risk assessment, that is, the degree of membership matrix, and further obtain the impact of blasting vibration velocity on the surrounding environment. Evaluate the final matrix;

(5)搜索风险评价终极矩阵隶属度,根据步骤(2)的标准确定因素所在评价集中的等级,得出风险评价结果。(5) Search the membership degree of the ultimate risk evaluation matrix, determine the level of the evaluation set where the factor is located according to the standard of step (2), and obtain the risk evaluation result.

进一步的,步骤(1)分为以下步骤:Further, step (1) is divided into the following steps:

(1-1)选取爆破振速影响因素:(1-1) Select the influencing factors of blasting vibration velocity:

爆破振速能量传输的范围主要和8类因素相关,分别是:基坑壁岩体级别、岩体风化程度、土体等级、岩土体含水性、地质勘察、单段最大药量、爆破效果、爆破中心至测点距离。把这8类因素用符号表示,如表1所示。建立因素集C。The range of blasting vibration velocity energy transmission is mainly related to 8 types of factors, namely: rock mass grade of foundation pit wall, rock mass weathering degree, soil mass grade, water content of rock and soil mass, geological survey, maximum charge of a single section, blasting effect , The distance from the blasting center to the measuring point. The eight types of factors are represented by symbols, as shown in Table 1. Create a factor set C.

影响爆破振速的因素很多,不同的因素或者相同的因素中不同的等级都会对爆破振速产生不同的影响。这八个因素是从工程地质因素,水文地质因素和设计施工因素三个方面考虑的。其中基坑壁岩体级别、岩体风化程度、土体等级是从工程地质因素考虑;岩土体含水性是从水文地质因素考虑;地质勘察、单段最大药量、爆破效果、爆破中心至测点距离是从设计施工因素方面考虑。这八个因素是影响爆破振速的主要因素,研究他们对研究爆破振速来说更全面,更有意义。There are many factors that affect the blasting vibration velocity, and different factors or different levels of the same factor will have different effects on the blasting vibration velocity. These eight factors are considered from three aspects: engineering geological factors, hydrogeological factors and design and construction factors. Among them, the rock mass grade of the foundation pit wall, the weathering degree of the rock mass, and the soil mass grade are considered from the engineering geological factors; the water content of the rock and soil mass is considered from the hydrogeological factors; The distance between the measuring points is considered from the design and construction factors. These eight factors are the main factors affecting the blasting vibration velocity, and researching them is more comprehensive and meaningful for the study of blasting vibration velocity.

表1爆破振速影响因素对应符号Table 1 Corresponding symbols of the influencing factors of blasting vibration velocity

Figure BDA0002394514210000021
Figure BDA0002394514210000021

Ci表示因素集C中周围环境影响属性。C i represents the influence attribute of the surrounding environment in the factor set C.

(1-2)对这8类因素进行等级划分。由于因素的等级划分按照因素特点,有的是定性划分,有的是定量划分,划分结果如表2所示。其中,基坑壁岩体级别是根据岩体的坚硬程度和完整性将稳定性相似的一些岩体划分为一类。(1-2) Classify these 8 types of factors. Because the classification of factors is based on the characteristics of factors, some are qualitatively divided, some are quantitatively divided, and the classification results are shown in Table 2. Among them, the rock mass grade of the foundation pit wall is to classify some rock masses with similar stability into one class according to the hardness and integrity of the rock mass.

表2 8类因素等级划分Table 2 Classification of 8 types of factors

Figure BDA0002394514210000022
Figure BDA0002394514210000022

Figure BDA0002394514210000031
Figure BDA0002394514210000031

进一步的,步骤(2)中爆破振速风险评价集合确定具体为:根据表3按照爆破振速对周围环境影响给出了风险评价等级划分。D表示评价集合。Further, the determination of the blasting vibration velocity risk assessment set in step (2) is as follows: according to Table 3, the risk assessment grade is given according to the impact of blasting vibration velocity on the surrounding environment. D represents the evaluation set.

表3爆破振速评价集合D等级划分Table 3 D-level division of blasting vibration velocity evaluation set

Figure BDA0002394514210000032
Figure BDA0002394514210000032

进一步的,步骤(3)隶属度函数以及隶属度时根据不可量化因素和可量化因素分别确定。对于不可量化因素,采用Karwowski隶属函数,Karwowski隶属函数是工程上常用的经验隶属函数,具有准确性。对于可量化因素,采用中间形二次抛物形隶属度函数,其形式简单,计算量小,能最大程度的反映数据的变化过程;隶属函数的形状越陡,分辨率越高,计算结果区分度越高。Further, in step (3), the membership function and the membership are respectively determined according to non-quantifiable factors and quantifiable factors. For unquantifiable factors, the Karwowski membership function is used, which is an empirical membership function commonly used in engineering and has accuracy. For quantifiable factors, an intermediate quadratic parabolic membership function is used, which has a simple form and a small amount of calculation, and can reflect the changing process of the data to the greatest extent; higher.

进一步的,步骤(4)中具体为:Further, in step (4), be specifically:

(4-1)信息熵的确定:针对基坑爆破,进行6次集合方法公约量化因素,得到公约量化集c={c1,c2,c4,c5,c6,c8},H(D|{ci})表示影响因素集中的因素ci相对于风险评价集合中的D的信息熵,用信息熵表示为:(4-1) Determination of information entropy: For the foundation pit blasting, perform 6 times the set method to quantify the factors, and obtain the quantified set c={c 1 ,c 2 ,c 4 ,c 5 ,c 6 ,c 8 }, H(D|{c i }) represents the information entropy of the factor c i in the influencing factor set relative to D in the risk assessment set, which is expressed as:

Figure BDA0002394514210000033
Figure BDA0002394514210000033

(4-2)权重计算:(4-2) Weight calculation:

Wi反映在整个评价系统中某一个属性相对于总体属性的重要程度。相应的影响因素子集ci权重为:Wi reflects the importance of a certain attribute relative to the overall attribute in the whole evaluation system. The corresponding influence factor subset c i weight is:

Figure BDA0002394514210000041
Figure BDA0002394514210000041

其中,σCD(ci)=p(Di|ci)。where σ CD (ci )=p(D i | ci ) .

(4-3)得到终极矩阵:(4-3) Get the final matrix:

将上述权重整理成矩阵形式,得到归一化权重后的矩阵,用A表示。Arrange the above weights into a matrix form to obtain a matrix after normalized weights, denoted by A.

采用二次抛物形分布,求得隶属度矩阵为R。Using the quadratic parabolic distribution, the membership matrix is obtained as R.

则得到终极矩阵为B,B=A×R。Then the final matrix is B, B=A×R.

进一步的,步骤(5)具体为根据最大隶属度原则,得出隶属度最大值。根据最大隶属度判断其在评价集中的范围,确定其风险等级。Further, step (5) is specifically to obtain the maximum membership degree according to the principle of maximum membership degree. According to the maximum membership degree, the scope of the evaluation set is judged, and the risk level is determined.

本发明的有益效果为:The beneficial effects of the present invention are:

本发明在对周围环境信息进行量化的基础上,考虑多种数据下的爆破振速风险评价,最终确定工程所需的爆破振速;避免了只根据爆破规范来进行的、不考虑周围环境情况的爆破振速确定方法,确定的爆破振速更具科学合理性。On the basis of quantifying the surrounding environment information, the invention takes into account the blasting vibration velocity risk assessment under various data, and finally determines the blasting vibration velocity required by the project; it avoids carrying out only according to the blasting specification without considering the surrounding environment. The blasting vibration velocity determination method is more scientific and reasonable.

附图说明Description of drawings

图1是本发明实施的技术流程图。FIG. 1 is a technical flow chart of the implementation of the present invention.

具体实施方式:Detailed ways:

为使本发明实施例的目的、技术方案和优点更加清楚,下面对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of them. Example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

实施例1:Example 1:

某地铁车站深基坑全长202米,为地下两层岛式车站,标准段宽度18.7m,高度为14.605m。周围有政府服务中心,建筑公司,民房等重要建筑物,地质较为简单,拱顶埋深17.8-38.9m,覆岩14-36m,深基坑大部分位于微风化岩中,车站主体主要通过的地层为第182层微风化细粒花岗岩(厚度25-64m,肉红色,节理裂隙稍发育-不发育,属较完整的较硬-坚硬岩,岩体基本质量等级Ⅲ级,岩石饱和)。工程地质特征:车站属于剥蚀残丘-剥蚀斜坡地貌,采用暗挖法施工,隧道穿越地层主要为细粒花岗岩微风化和细粒花岗岩微风化节理发育带和细粒花岗岩(块状破碎岩),场区地下水主要为基岩裂隙水,水量较小。选取影响因素集和风险评价集,如表1和表2所示。计算信息熵,相应的重要度和归一化权重矩阵。The deep foundation pit of a subway station has a total length of 202 meters and is an underground two-story island station with a standard section width of 18.7m and a height of 14.605m. There are government service centers, construction companies, private houses and other important buildings around. The geology is relatively simple. The depth of the vault is 17.8-38.9m, the overlying rock is 14-36m, and most of the deep foundation pits are located in the slightly weathered rock. The stratum is the 182nd layer of micro-weathered fine-grained granite (thickness 25-64m, red flesh, slightly developed-undeveloped joints and fissures, relatively complete hard-hard rock, basic rock mass grade III, saturated rock). Engineering geological features: The station belongs to the denudation residual hill-denudation slope landform, and the construction is carried out by the underground excavation method. The stratum that the tunnel passes through is mainly fine-grained granite micro-weathering and fine-grained granite micro-weathering joint development zone and fine-grained granite (massive broken rock). The groundwater in the site is mainly bedrock fissure water with a small amount of water. Select the influencing factor set and risk assessment set, as shown in Table 1 and Table 2. Calculate the information entropy, the corresponding importance and the normalized weight matrix.

表4归一化权重分配表Table 4 Normalized weight distribution table

Figure BDA0002394514210000051
Figure BDA0002394514210000051

H(D|C)=0.1174。H(D|C)=0.1174.

将表格中归一化权重整理成矩阵形式。Arrange the normalized weights in the table into a matrix form.

A=[0.1735,0.1643,0.1476,0.1348,0.1938,0.1860]。A=[0.1735, 0.1643, 0.1476, 0.1348, 0.1938, 0.1860].

采用的是二次抛物形分布。隶属度矩阵为R,A quadratic parabolic distribution is used. The membership matrix is R,

Figure BDA0002394514210000052
Figure BDA0002394514210000052

终极矩阵为B,则The final matrix is B, then

Figure BDA0002394514210000053
Figure BDA0002394514210000053

but

B=[0.2128,0.5770,0.6136,0.3994,0.0995]B=[0.2128, 0.5770, 0.6136, 0.3994, 0.0995]

表5爆破振速等级评价隶属度取值范围Table 5 Value range of membership degree for blasting vibration velocity grade evaluation

评价等级Evaluation level 安全Safety 较安全Safer 预警early warning 较危险more dangerous 危险Danger 区域划分Regional division [1,0.8][1,0.8] [0.6,0.8)[0.6,0.8) [0.4,0.6)[0.4,0.6) [0.2,0.4)[0.2,0.4) [0,0.2)[0,0.2)

该深基坑施工爆破振动数据进行监测时,监测点距爆破中心距离为50米。根据最大隶属度原则,得出最大值为0.6136,根据表5,对应等级为较安全。爆破振动速度在规范规定的范围内,不会对周围环境造成大规模的破坏,是较安全的状态。永年路站监测所得最大爆破振速为0.95cm/s,根据监测报告,爆破没有对周围建筑物造成大规模的破坏,与评估结果吻合。When monitoring the blasting vibration data of the deep foundation pit construction, the distance between the monitoring point and the blasting center is 50 meters. According to the principle of maximum membership degree, the maximum value is 0.6136. According to Table 5, the corresponding level is relatively safe. The blasting vibration speed is within the range specified in the specification, and it will not cause large-scale damage to the surrounding environment, which is a relatively safe state. The maximum blasting vibration velocity obtained from the monitoring of Yongnian Road Station is 0.95cm/s. According to the monitoring report, the blasting did not cause large-scale damage to the surrounding buildings, which is consistent with the assessment results.

Claims (9)

1.一种深基坑爆破振速风险等级大数据评价方法,其特征在于包括以下步骤:1. a deep foundation pit blasting vibration velocity risk level big data evaluation method is characterized in that comprising the following steps: (1)确定爆破工程周围环境影响因素,划分因素的风险等级,采用集合方法公约量化因素;(1) Determine the environmental impact factors around the blasting project, divide the risk levels of the factors, and use the collective method to quantify the factors; (2)确定风险评价集合,把爆破振速对周围环境影响风险评价划分等级,为后期评价确定标准;(2) Determine the risk assessment set, classify the risk assessment of the impact of blasting vibration speed on the surrounding environment, and determine the standard for later assessment; (3)根据公约量化因素确定隶属度函数以及隶属度;(3) Determine the membership function and membership degree according to the quantification factors of the convention; (4)计算各影响因素信息熵,确定考虑信息熵的各影响因素权重,得到影响因素权重矩阵,然后建立周围环境风险评价初级矩阵,即隶属度矩阵,进一步得到爆破振速对周围环境影响风险评价终极矩阵;(4) Calculate the information entropy of each influencing factor, determine the weight of each influencing factor considering the information entropy, obtain the weight matrix of the influencing factors, and then establish the primary matrix of surrounding environmental risk assessment, that is, the degree of membership matrix, and further obtain the impact of blasting vibration velocity on the surrounding environment. Evaluate the final matrix; (5)搜索风险评价终极矩阵隶属度,根据步骤(2)的标准确定因素所在评价集中的等级,得出风险评价结果。(5) Search the membership degree of the ultimate risk evaluation matrix, determine the level of the evaluation set where the factor is located according to the standard of step (2), and obtain the risk evaluation result. 2.如权利要求1所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(1)中选取爆破振速影响因素具体为建立因素集C,包括基坑壁岩体级别C1、岩体风化程度C2、土体等级C3、岩土体含水性C4、地质勘察C5、单段最大药量C6、爆破效果C7、爆破中心至测点距离C82. a kind of deep foundation pit blasting vibration velocity risk level big data evaluation method as claimed in claim 1, is characterized in that: in step (1), choose blasting vibration velocity influence factor to be specifically set up factor set C, comprise foundation pit wall Rock mass grade C 1 , rock mass weathering degree C 2 , soil mass grade C 3 , water content of rock and soil mass C 4 , geological survey C 5 , single-stage maximum charge C 6 , blasting effect C 7 , blasting center to measuring point distance C 8 . 3.如权利要求2所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(1)中风险等级的划分,按照下表进行:3. a kind of deep foundation pit blasting vibration velocity risk grade big data evaluation method as claimed in claim 2 is characterized in that: in step (1), the division of risk grade is carried out according to the following table:
Figure RE-FDA0002444548450000011
Figure RE-FDA0002444548450000011
4.如权利要求1所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(2)中爆破振速风险评价集合确定,按照下表进行:4. a kind of deep foundation pit blasting vibration velocity risk level big data evaluation method as claimed in claim 1, is characterized in that: in step (2), blasting vibration velocity risk assessment set is determined, and carry out according to the following table:
Figure RE-FDA0002444548450000021
Figure RE-FDA0002444548450000021
5.如权利要求1所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(3)隶属度函数以及隶属度时根据不可量化因素和可量化因素分别确定;对于不可量化因素,采用Karwowski隶属函数;对于可量化因素,采用中间形二次抛物形隶属度函数。5. a kind of deep foundation pit blasting vibration velocity risk grade big data evaluation method as claimed in claim 1, is characterized in that: during step (3) membership degree function and membership degree, determine respectively according to non-quantifiable factor and quantifiable factor; For unquantifiable factors, the Karwowski membership function is used; for quantifiable factors, the intermediate quadratic parabolic membership function is used. 6.如权利要求1所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(4)中信息熵的确定具体为:针对基坑爆破,进行6次集合方法公约量化因素,得到公约量化集c={c1,c2,c4,c5,c6,c8},H(D|{ci})表示影响因素集中的因素ci相对于风险评价集合中的D的信息熵,用信息熵表示为:6. a kind of deep foundation pit blasting vibration velocity risk level big data evaluation method as claimed in claim 1, is characterized in that: in step (4), the determination of information entropy is specifically: for foundation pit blasting, carry out 6 collection methods Covenant quantification factors, get the quantification set c={c 1 , c 2 , c 4 , c 5 , c 6 , c 8 }, H(D|{c i }) represents the factor c i in the set of influencing factors relative to the risk The information entropy of D in the evaluation set is expressed as:
Figure RE-FDA0002444548450000022
Figure RE-FDA0002444548450000022
7.如权利要求6所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(4)中中权重计算具体为:Wi反映在整个评价系统中某一个属性相对于总体属性的重要程度;相应的影响因素子集ci权重为:7. a kind of deep foundation pit blasting vibration velocity risk level big data evaluation method as claimed in claim 6, is characterized in that: in step (4), weight calculation is specifically: W i is reflected in a certain attribute in the whole evaluation system The importance relative to the overall attribute; the corresponding weight of the subset c i of the influencing factors is:
Figure RE-FDA0002444548450000023
Figure RE-FDA0002444548450000023
其中,σCD(ci)=p(Di|ci)。where σ CD (ci )=p(D i | ci ) .
8.如权利要求7所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(4)中得到终极矩阵具体为:8. a kind of deep foundation pit blasting vibration velocity risk grade big data evaluation method as claimed in claim 7, is characterized in that: in step (4), obtain the ultimate matrix specifically: 将权重整理成矩阵形式,得到归一化权重后的矩阵,用A表示;Arrange the weights into a matrix form, and get the matrix after normalized weights, which is represented by A; 采用二次抛物形分布,求得隶属度矩阵为R;Using the quadratic parabolic distribution, the membership matrix is obtained as R; 则得到终极矩阵为B,B=A×R。Then the final matrix is B, B=A×R. 9.如权利要求1所述的一种深基坑爆破振速风险等级大数据评价方法,其特征在于:步骤(5)具体为为根据最大隶属度原则,得出隶属度最大值。根据最大隶属度判断其在评价集中的范围,确定其风险等级。9 . The big data evaluation method for deep foundation pit blasting vibration velocity risk level according to claim 1 , wherein step (5) is specifically to obtain the maximum membership degree according to the principle of maximum membership degree. 10 . According to the maximum membership degree, the scope of the evaluation set is judged, and the risk level is determined.
CN202010126471.2A 2020-02-28 2020-02-28 A big data evaluation method for deep foundation pit blasting vibration velocity risk level Pending CN111339486A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202010126471.2A CN111339486A (en) 2020-02-28 2020-02-28 A big data evaluation method for deep foundation pit blasting vibration velocity risk level
PCT/CN2020/089026 WO2021169038A1 (en) 2020-02-28 2020-05-07 Deep foundation pit blasting vibration velocity risk level big data evaluation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010126471.2A CN111339486A (en) 2020-02-28 2020-02-28 A big data evaluation method for deep foundation pit blasting vibration velocity risk level

Publications (1)

Publication Number Publication Date
CN111339486A true CN111339486A (en) 2020-06-26

Family

ID=71183894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010126471.2A Pending CN111339486A (en) 2020-02-28 2020-02-28 A big data evaluation method for deep foundation pit blasting vibration velocity risk level

Country Status (2)

Country Link
CN (1) CN111339486A (en)
WO (1) WO2021169038A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111709592A (en) * 2020-08-20 2020-09-25 北京大成国测科技有限公司 Deep foundation pit deformation prediction method and system based on neural network and rough set classification

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113793038B (en) * 2021-09-16 2023-12-22 贵阳市城市轨道交通集团有限公司 Karst mountain area subway tunnel engineering disaster partitioning method under multi-factor coupling
CN114049053A (en) * 2022-01-12 2022-02-15 国网江西省电力有限公司电力科学研究院 A method and device for analyzing risk distribution of distribution network towers under flood
CN114595581A (en) * 2022-03-11 2022-06-07 重庆地质矿产研究院 A Probabilistic Model of Regional Geological Hazard Risk Based on Dynamic Weights of Influencing Factors
CN114925508B (en) * 2022-05-05 2024-10-08 中国路桥工程有限责任公司 Slope dynamic stability evaluation method based on fuzzy set theory
CN114781040B (en) * 2022-05-10 2023-07-07 青岛理工大学 Building blasting vibration safety evaluation method, device, equipment and medium
CN115879821B (en) * 2023-01-03 2023-09-19 北京工业大学 A construction quality assessment method for foundation pit projects based on multi-source heterogeneous data
CN116151933B (en) * 2023-04-18 2023-10-24 深圳市感恩网络科技有限公司 International trade information data digital supervision system and method based on big data
CN117078106B (en) * 2023-08-31 2024-02-20 兰州理工大学 Comprehensive evaluation and index weight sensitivity analysis method for blasting rock mass quality

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452836A (en) * 2014-12-10 2015-03-25 青岛理工大学 Stability detection early warning method for deep foundation pit supporting structure
CN105718668A (en) * 2016-01-22 2016-06-29 辽宁工程技术大学 Open pit mine cast blasting effect analysis method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU866099A1 (en) * 1980-01-04 1981-09-23 Тольяттинский политехнический институт Method of driving wells in earth
CN104951615A (en) * 2015-07-06 2015-09-30 福州大学 Cutting slope fuzzy hierarchy risk evaluation method
CN105701345B (en) * 2016-01-13 2018-06-26 青岛理工大学 Evaluation method and application of hole collapse risk of bored pile foundation
CN110378619A (en) * 2019-07-26 2019-10-25 中国电建集团成都勘测设计研究院有限公司 Method of tunnel drilling and blasting risk analysis method based on fuzzy overall evaluation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452836A (en) * 2014-12-10 2015-03-25 青岛理工大学 Stability detection early warning method for deep foundation pit supporting structure
CN105718668A (en) * 2016-01-22 2016-06-29 辽宁工程技术大学 Open pit mine cast blasting effect analysis method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李梅,等: "《信息论基础教程(第3版)》", 31 August 2015, 北京邮电大学出版社 *
陈礼彪: "山岭隧道施工期安全风险评价方法研究", 《中国博士学位论文全文数据库工程科技II辑(月刊)》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111709592A (en) * 2020-08-20 2020-09-25 北京大成国测科技有限公司 Deep foundation pit deformation prediction method and system based on neural network and rough set classification

Also Published As

Publication number Publication date
WO2021169038A1 (en) 2021-09-02

Similar Documents

Publication Publication Date Title
CN111339486A (en) A big data evaluation method for deep foundation pit blasting vibration velocity risk level
Li et al. Unascertained measure model of water and mud inrush risk evaluation in karst tunnels and its engineering application
CN113570226A (en) Evaluation method of probability grade of water inrush disaster in tunnel in fault fracture zone
CN110515117B (en) Underground karst cave detection method based on pile hammer shock and decision tree model
Zheng et al. Rockburst prediction model based on entropy weight integrated with grey relational BP neural network
CN105926569A (en) Method for quantitatively evaluating site stability of old goaf in coalmine based on settlement monitoring data
CN106407545A (en) Soft soil foundation ditch safety evaluation method based on fuzzy comprehensive judgment method
CN103886176A (en) Method for determining dynamic stability coefficient of creeping slope
CN112100727A (en) Early warning prevention and control method for water inrush of water-rich tunnel under influence of fault fracture zone
CN105701345B (en) Evaluation method and application of hole collapse risk of bored pile foundation
CN110378551A (en) A kind of vcehicular tunnel facility military service method of evaluating performance based on big data
CN105046080B (en) A kind of rock mass quality classification
CN105653811A (en) Rocked depth determining method for high voltage transformer substation deep back filled region rotary excavation drilling
Yu et al. Dynamic Risk Assessment of Karst Tunnel Collapse Based on Fuzzy‐AHP: A Case Study of the LianHuaShan Tunnel, China
CN111551985A (en) Underground karst cave detection method based on pile hammer shock and k nearest neighbor algorithm
CN107169637A (en) A kind of power station layer of sand soil property liquefaction evaluation method
CN115526389A (en) A geological risk prediction method for coal mine dynamic disasters based on sedimentary facies
CN118583968B (en) Method for evaluating stability of tunnel surrounding rock
Wang et al. Analysis of blasting vibration effect of railway tunnel and determination of reasonable burial depth
Yin et al. Evaluation of controlled blasting quality for rock-mass tunneling based on multiple indices
Wang et al. A new bayesian network model for the risk assessment of water inrush in karst tunnels
Jia et al. Development and Application of Model Test System for Reconstruction and Expansion of Existing Shallow Single‐Hole Tunnel into Twin‐Arch Tunnel
Zhang et al. Comprehensive evaluation of shaped charge blasting effect of rock roadway based on entropy-weighted matter-element extension model
CN114626230B (en) A simulation method of geological mineral resources reserves
Chen et al. Propagation laws of blasting seismic waves in weak rock mass: a case study of muzhailing tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Yuan Changfeng

Inventor after: Xu Sifa

Inventor after: Chen Qiuru

Inventor after: Yu Guangming

Inventor after: Li Liang

Inventor after: Ling Xianchang

Inventor after: He Keqiang

Inventor after: Lu Shibao

Inventor after: Xu Hongjian

Inventor after: Wang Chang

Inventor before: Yuan Changfeng

Inventor before: Chen Qiuru

Inventor before: Yu Guangming

Inventor before: Li Liang

Inventor before: Ling Xianchang

Inventor before: He Keqiang

Inventor before: Lu Shibao

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200626