[go: up one dir, main page]

CN111335177B - Underwater dry operation construction system and method by bottomless air bag method - Google Patents

Underwater dry operation construction system and method by bottomless air bag method Download PDF

Info

Publication number
CN111335177B
CN111335177B CN202010224600.1A CN202010224600A CN111335177B CN 111335177 B CN111335177 B CN 111335177B CN 202010224600 A CN202010224600 A CN 202010224600A CN 111335177 B CN111335177 B CN 111335177B
Authority
CN
China
Prior art keywords
air bag
airbag
air
construction
seabed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010224600.1A
Other languages
Chinese (zh)
Other versions
CN111335177A (en
Inventor
赵学敏
胡吉庆
桑登峰
刘梅梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co ltd
CCCC Fourth Harbor Engineering Co Ltd
CCCC Fourth Harbor Engineering Institute Co Ltd
Original Assignee
Sixth Engineering Co ltd
CCCC Fourth Harbor Engineering Co Ltd
CCCC Fourth Harbor Engineering Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co ltd, CCCC Fourth Harbor Engineering Co Ltd, CCCC Fourth Harbor Engineering Institute Co Ltd filed Critical Sixth Engineering Co ltd
Priority to CN202010224600.1A priority Critical patent/CN111335177B/en
Publication of CN111335177A publication Critical patent/CN111335177A/en
Application granted granted Critical
Publication of CN111335177B publication Critical patent/CN111335177B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Revetment (AREA)

Abstract

本发明提供了一种无底气囊法水下干作业施工系统及方法,该系统包括由柔性材料制造的下部敞口的气囊、由钢性材料制造的环形气囊底口、压设于气囊底口上的配重、用于运送施工人员及施工材料的潜水艇、设置于环形气囊底口下方且连通气囊内外的潜水艇通道、设置于水面之上的空压机、发电机及砼泵,气囊位于水面之下,气囊底口着陆于找平施工后的海床,气囊具有用于施工作业的充气内腔,充气内腔内设有送气管、电缆及砼泵送管分别贯穿气囊与水面之上的空压机、电机机及砼泵连接,充气内腔维持有与海底压力相适配的空气充气气压。本发明可在水下任意位置形成一个无水的作业环境,能显著提高施工质量,与围堰法施工相比,其施工成本低,安全可控。

The present invention provides a bottomless airbag method underwater dry operation construction system and method, the system includes an airbag with an open bottom made of flexible material, an annular airbag bottom made of rigid material, a counterweight pressed on the airbag bottom, a submarine for transporting construction personnel and construction materials, a submarine channel arranged below the annular airbag bottom and connecting the inside and outside of the airbag, an air compressor, a generator and a concrete pump arranged above the water surface, the airbag is located below the water surface, the bottom of the airbag lands on the seabed after leveling construction, the airbag has an inflatable inner cavity for construction operations, an air delivery pipe, a cable and a concrete pump delivery pipe are arranged in the inflatable inner cavity, respectively passing through the airbag and connecting with the air compressor, the electric motor and the concrete pump above the water surface, and the inflatable inner cavity maintains an air inflation pressure that matches the seabed pressure. The present invention can form a waterless working environment at any position underwater, can significantly improve the construction quality, and compared with the cofferdam method construction, its construction cost is low, safe and controllable.

Description

无底气囊法水下干作业施工系统及方法Bottomless airbag method underwater dry operation construction system and method

技术领域Technical Field

本发明涉及水下施工技术领域,尤其涉及水下干作业施工技术。The invention relates to the technical field of underwater construction, in particular to underwater dry operation construction technology.

背景技术Background Art

随着社会经济的发展,大量的建筑工程需要在水下进行施工,例如跨海大桥的下部结构、海上风力发电机站的基础等,目前,水下施工技术比较成熟的主要有导管法水下灌注砼、围堰施工、预制构件水下安装施工等,但是这些施工技术都有各自的局限性,最难克服的难题是随着水深度的增加,施工技术难度及施工成本也随之增大,安全风险也会增加。With the development of social economy, a large number of construction projects need to be constructed underwater, such as the substructure of cross-sea bridges and the foundation of offshore wind turbine stations. At present, the relatively mature underwater construction technologies mainly include underwater concrete pouring by duct method, cofferdam construction, underwater installation and construction of prefabricated components, etc. However, these construction technologies have their own limitations. The most difficult problem to overcome is that with the increase of water depth, the difficulty of construction technology and construction cost will also increase, and the safety risk will also increase.

为了解决深水施工的技术难题,本发明拟在水底建造一个无水的施工作业环境,从而可以在该无水作业环境内完成各项施工任务。In order to solve the technical difficulties of deep-water construction, the present invention intends to build a waterless construction working environment under water, so that various construction tasks can be completed in the waterless working environment.

发明内容Summary of the invention

本发明的目的在于提供一种建造于水底的、用于提供无水施工作业环境的系统。The object of the present invention is to provide a system constructed under water for providing a waterless construction working environment.

为了实现上述目的,本发明采用了以下技术方案:一种无底气囊法水下干作业施工系统,其包括由柔性材料制造的下部敞口的气囊、由钢性材料制造的环形气囊底口、压设于气囊底口上的配重、用于运送施工人员及施工材料的潜水艇、设置于环形气囊底口下方且连通气囊内外的潜水艇通道、设置于水面之上的空压机、发电机及砼泵,气囊位于水面之下,气囊底口着陆于找平施工后的海床,气囊具有用于施工作业的充气内腔,充气内腔内设有送气管、电缆及砼泵送管分别贯穿气囊与水面之上的空压机、电机机及砼泵连接,充气内腔维持有与海底压力相适配的空气充气气压,充气气压根据气囊的高度计算确定:In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a bottomless airbag method underwater dry construction system, which includes an airbag with an open bottom made of flexible material, an annular airbag bottom made of rigid material, a counterweight pressed on the bottom of the airbag, a submarine for transporting construction personnel and construction materials, a submarine passage arranged below the bottom of the annular airbag and connecting the inside and outside of the airbag, an air compressor, a generator and a concrete pump arranged above the water surface, the airbag is located below the water surface, the bottom of the airbag lands on the seabed after leveling construction, the airbag has an inflatable inner cavity for construction operations, an air supply pipe, a cable and a concrete pumping pipe are arranged in the inflatable inner cavity, which respectively penetrate the airbag and are connected to the air compressor, the electric motor and the concrete pump above the water surface, the inflatable inner cavity maintains an air inflation pressure that matches the seabed pressure, and the inflation pressure is calculated and determined according to the height of the airbag:

ps=K(ρgh+P0) ps =K(ρgh+ P0 )

ps——测试压强 ps ——test pressure

P0——大气压强P 0 —— atmospheric pressure

ρ——水的密度ρ——density of water

g——重力加速度g——acceleration due to gravity

h——气囊的高度h——Height of the airbag

K——安全系数,K值不小于1.4。K——Safety factor, K value shall not be less than 1.4.

优选地,气囊底口具有一水平的环形钢板,环形钢板上设有垂直筒状护壁,气囊贴于筒状护壁内侧,筒状护壁外侧压有配重。Preferably, the bottom opening of the airbag has a horizontal annular steel plate, a vertical cylindrical protective wall is arranged on the annular steel plate, the airbag is attached to the inner side of the cylindrical protective wall, and a counterweight is pressed on the outer side of the cylindrical protective wall.

优选地,筒状护壁与环形钢板之间设有多块支撑肋板。Preferably, a plurality of supporting ribs are provided between the cylindrical protective wall and the annular steel plate.

在海床不平整的凹陷位置,气囊袋口从环形钢板下方下垂至与海床接触。At the concave position where the seabed is uneven, the airbag bag opening hangs down from under the annular steel plate until it contacts the seabed.

本发明的另一目的在于提供一种水下干作业施工方法。Another object of the present invention is to provide an underwater dry operation construction method.

一种无底气囊法水下干作业施工方法,其使用了如上任一所述的无底气囊法水下干作业施工系统,并采用以下步骤施工:A bottomless airbag method for underwater dry work construction, which uses any of the bottomless airbag method underwater dry work construction systems described above, and adopts the following steps for construction:

(s1)制作气囊及气囊底口;(s1) manufacturing the airbag and the bottom of the airbag;

(s2)海床找平,开挖潜水艇通道;(s2) Leveling the seabed and excavating submarine passages;

(s3)气囊检测合格后,将电线、送气管、砼泵管与气囊的贯穿口密封连接好,按照预定位置将气囊沉入海床,气囊入水后要排干气囊内部的空气;(s3) After the airbag passes the inspection, the wires, air supply pipes, concrete pump pipes and the through-holes of the airbag are sealed and connected, and the airbag is sunk into the seabed according to the predetermined position. After the airbag enters the water, the air inside the airbag must be drained;

(s4)气囊沉入海床后,检查气囊底口是否落在平整的海床平面,气囊底口着陆于海床凹陷位置时将气囊袋口下放至与海床底部接触,然后在气囊底口上方进行配重安装;(s4) After the airbag sinks to the seabed, check whether the bottom of the airbag falls on the flat seabed plane. When the bottom of the airbag lands in a concave position on the seabed, lower the airbag bag mouth until it contacts the bottom of the seabed, and then install the counterweight above the bottom of the airbag;

(s5)对气囊内腔进行充气;(s5) inflating the inner cavity of the airbag;

(s6)施工人员及材料通过潜水艇经潜水艇通道进入气囊内部进行施工,无法装入潜水艇的大块材料通过绳索沉入潜水艇通道通道口,再通过绳索牵引到气囊内腔,在施工过程中,要连续不断的往气囊内部送气,确保气囊内部空气清新;(s6) Construction personnel and materials enter the airbag through the submarine channel for construction. Large materials that cannot be loaded into the submarine are sunk into the submarine channel through ropes and then pulled into the airbag cavity through ropes. During the construction process, air must be continuously supplied to the airbag to ensure that the air inside the airbag is fresh;

(s7)施工人员在气囊内部进行基础施工;(s7) Construction workers are carrying out basic construction inside the airbag;

(s8)基础施工完成后,上浮气囊到墩身施工的预定高度,先在气囊底口设置工作平台以封闭气囊底部开口,搭设工作平台脚手架,脚手架上预留施工人员及施工材料的出入口;(s8) After the foundation construction is completed, the airbag is floated up to the predetermined height for the pier body construction. A working platform is first set up at the bottom of the airbag to close the bottom opening of the airbag, and a scaffolding for the working platform is set up. The entrance and exit for construction personnel and construction materials are reserved on the scaffolding;

(s9)根据气囊的有效空间,每浇筑一段墩身混凝土就调整气囊一段上浮高度,直到墩身施工至水面以上,拆除气囊。(s9) According to the effective space of the airbag, the floating height of the airbag is adjusted every time a section of pier body concrete is poured, until the pier body is constructed above the water surface and the airbag is removed.

步骤(s5)的充气气压根据气囊的高度计算确定:The inflation pressure of step (s5) is calculated and determined based on the height of the airbag:

ps=K(ρgh+P0) ps =K(ρgh+ P0 )

ps——测试压强 ps ——test pressure

P0——大气压强P 0 —— atmospheric pressure

ρ——水的密度ρ——density of water

g——重力加速度g——acceleration due to gravity

h——气囊的高度h——Height of the airbag

K——安全系数,K值不小于1.4,K——Safety factor, K value is not less than 1.4,

充气完成后需要记录好充气量,作为气囊在水下的控制充气量v。After inflation is completed, the inflation volume needs to be recorded as the control inflation volume v of the airbag underwater.

步骤(s5)的充气应分步进行,根据气密性实验得出的控制充气量v,按照0.3v-0.6v-0.9v-1.0v的步骤进行,每步充气完成后,检查气囊的状态,看气囊有没有存在扭结、漏气情况。The inflation in step (s5) should be carried out in steps, according to the controlled inflation volume v obtained from the airtightness experiment, and in the steps of 0.3v-0.6v-0.9v-1.0v. After each inflation step, check the state of the airbag to see if there is any kink or leakage in the airbag.

步骤(s8)上浮气囊之前,先安装好海底地锚,将地锚和气囊进行有效连接,在承台基础上提前预留锚固钢筋,将气囊锚固在承台基础上,锚固连接好后,拆除部分配重,让气囊缓慢上浮到预定高度。Before the floating airbag in step (s8), install the seabed anchor first, effectively connect the anchor and the airbag, reserve anchor steel bars on the foundation in advance, anchor the airbag on the foundation, and after the anchor connection is completed, remove part of the counterweight to allow the airbag to slowly float to a predetermined height.

配重根据气囊的体积计算确定:The weight is calculated based on the volume of the airbag:

G——配重G——Counterweight

m——气囊及底口钢板的整体质量m——the overall mass of the airbag and bottom steel plate

v——气囊充满空气后的体积v - the volume of the airbag when it is filled with air

ρ——水的密度ρ——density of water

ρ′——配重的密度ρ′——density of the counterweight

K——安全系数,其中K值不小于1.4。K——Safety factor, where the K value is not less than 1.4.

当水深超过20m时,内囊内部施工人员佩戴减压呼吸器。When the water depth exceeds 20m, construction workers inside the inner capsule wear decompression respirators.

本发明优势在于在水下任意位置形成一个无水的作业环境,能显著提高工程质量,与围堰法施工相比,其施工成本低,安全可控。The advantage of the present invention is that a waterless working environment can be formed at any position underwater, which can significantly improve the quality of the project. Compared with the cofferdam construction method, the construction cost is low and the safety is controllable.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1是气囊在找平的海床上安装的立面示意图。FIG. 1 is a schematic elevation view of the installation of the airbag on the leveled seabed.

图2是气囊在不完全平整的海床上安装的立面示意图。FIG. 2 is a schematic elevation view of the installation of the airbag on a seabed that is not completely flat.

图3是气囊上浮后用于墩柱施工的立面示意图。FIG. 3 is a schematic elevation view of the pier construction after the airbag floats up.

图4是气囊底口结构示意图。FIG. 4 is a schematic diagram of the airbag bottom structure.

图5是图4的A-A剖示图。FIG. 5 is a cross-sectional view taken along line A-A in FIG. 4 .

图6是物理原理图。Figure 6 is a physical principle diagram.

其中,气囊101,工作平台102,配重103,锚104,砼泵送管105,电线106,送气管107,灯108,材料牵引绳109,空压机110,发电机111,砼泵112,气囊底口113,环形钢板114,筒状护壁115,支撑肋板116,潜水艇通道117,材料200Among them, airbag 101, working platform 102, counterweight 103, anchor 104, concrete pumping pipe 105, wire 106, air pipe 107, light 108, material hauling rope 109, air compressor 110, generator 111, concrete pump 112, airbag bottom 113, annular steel plate 114, cylindrical wall 115, supporting rib 116, submarine channel 117, material 200

具体实施方式DETAILED DESCRIPTION

本发明的设计及实施涉及到的物理原理如图6所示。The physical principles involved in the design and implementation of the present invention are shown in FIG6 .

将杯子倒扣入水中(底部杯口不需要封闭),在水压作用下杯子内的空气无法溢出,便在杯子中形成了一个无水的环境。Put the cup upside down in water (the bottom of the cup does not need to be sealed). Under the action of water pressure, the air in the cup cannot escape, thus forming a waterless environment in the cup.

根据液体压强计算公式,p=ρgh,杯子内部的气体压强为p=ρgH+P0(P0为大气压强)。杯子内部的气体压强处处相等,由此可知杯子外壁任意一点的压强都小于杯子内壁的压强。因此考虑采用柔性材料沉入水中,并在内部充入空气,使形成一个无水的施工作业环境。According to the liquid pressure calculation formula, p = ρgh, the gas pressure inside the cup is p = ρgH + P 0 (P 0 is the atmospheric pressure). The gas pressure inside the cup is equal everywhere, so it can be seen that the pressure at any point on the outer wall of the cup is less than the pressure on the inner wall of the cup. Therefore, it is considered to use flexible materials to sink into the water and fill the inside with air to form a waterless construction working environment.

杯子所受的浮力等于杯子所排开水的重力,在施工中,所形成的气囊的体积越大,则受到的浮力也就越大,所以需要解决好气囊在水中的锚固措施。The buoyancy of the cup is equal to the gravity of the water displaced by the cup. During construction, the larger the volume of the air bag formed, the greater the buoyancy it will experience, so it is necessary to solve the anchoring measures of the air bag in the water.

如图1~5所示可见本发明的一种无底气囊法水下干作业施工系统,其包括由柔性材料橡胶制造的下部敞口的气囊101、由钢板制造的环形气囊底口113、压设于气囊底口上的配重103、用于运送施工人员及施工材料的潜水艇、设置于环形气囊底口下方且连通气囊内外的潜水艇通道117、设置于水面之上的空压机110、发电机111及砼泵112。As shown in Figures 1 to 5, a bottomless airbag method underwater dry construction system of the present invention includes an airbag 101 with an open bottom made of flexible rubber material, an annular airbag bottom 113 made of steel plate, a counterweight 103 pressed on the airbag bottom, a submarine for transporting construction personnel and construction materials, a submarine channel 117 arranged below the annular airbag bottom and connecting the inside and outside of the airbag, an air compressor 110, a generator 111 and a concrete pump 112 arranged above the water surface.

气囊101位于水面之下,气囊具有用于施工作业的充气内腔,充气内腔内设有送气管107、电缆106及砼泵送管105分别贯穿气囊与水面之上的空压机110、电机机111及砼泵112连接,充气内腔维持有与海底压力相适配的空气充气气压,充气气压根据气囊的高度计算确定:The airbag 101 is located under the water surface. The airbag has an inflatable inner cavity for construction operations. An air delivery pipe 107, a cable 106 and a concrete pumping pipe 105 are respectively inserted through the airbag and connected to an air compressor 110, an electric motor 111 and a concrete pump 112 above the water surface. The inflatable inner cavity maintains an air inflation pressure that matches the seabed pressure. The inflation pressure is calculated and determined according to the height of the airbag:

ps=K(ρgh+P0) ps =K(ρgh+ P0 )

ps——测试压强 ps ——test pressure

P0——大气压强P 0 —— atmospheric pressure

ρ——水的密度ρ——density of water

g——重力加速度g——acceleration due to gravity

h——气囊的高度h——Height of the airbag

K——安全系数,K值不小于1.4。K——Safety factor, K value shall not be less than 1.4.

气囊底口113着陆于找平施工后的海床,如图4所示,气囊底口具有一水平的环形钢板114,环形钢板114上设有垂直筒状护壁115,气囊贴于筒状护壁内侧,筒状护壁外侧压有配重。筒状护壁与环形钢板之间设有多块支撑肋板116。The bottom opening 113 of the airbag lands on the seabed after leveling. As shown in FIG4 , the bottom opening of the airbag has a horizontal annular steel plate 114, on which a vertical cylindrical protective wall 115 is arranged. The airbag is attached to the inner side of the cylindrical protective wall, and a counterweight is pressed on the outer side of the cylindrical protective wall. A plurality of supporting ribs 116 are arranged between the cylindrical protective wall and the annular steel plate.

本发明的水下干作业施工方法按以下步骤实施:The underwater dry operation construction method of the present invention is implemented according to the following steps:

(s1)制作气囊及气囊底口。为了保证气囊底口有固定的形状,并方便气囊在海底就位,气囊底口采用钢材制作,气囊选用气密性好的橡胶制作。(s1) Making the airbag and the bottom of the airbag. In order to ensure that the bottom of the airbag has a fixed shape and facilitate the positioning of the airbag on the seabed, the bottom of the airbag is made of steel and the airbag is made of rubber with good airtightness.

(s2)在海床上进行承台基础施工时,需要先对海床进行找平,确保气囊底口落在水平面上,并提前挖好潜水艇通道,便于人员及材料进出。(s2) When constructing the pedestal foundation on the seabed, it is necessary to first level the seabed to ensure that the bottom of the airbag falls on a horizontal plane, and to dig a submarine passage in advance to facilitate the entry and exit of personnel and materials.

(s3)气囊下水前检查气囊的气密性和承压能力,并验算气囊的抗拉强度。气囊的气密性检查方法是将气囊的底口封闭,然后充气做气密性试验。由于气囊在水中的时候,气囊外壁受到水的压强,气囊内壁受到空气的压强,压力会相互抵消,只有气囊顶面所受到的压强差最大,所以充气气压根据气囊的高度计算确定:(s3) Before launching the airbag, check the air tightness and pressure bearing capacity of the airbag, and verify the tensile strength of the airbag. The air tightness inspection method of the airbag is to seal the bottom of the airbag, and then inflate it for air tightness test. When the airbag is in water, the outer wall of the airbag is subjected to water pressure, and the inner wall of the airbag is subjected to air pressure. The pressures will offset each other, and only the top surface of the airbag is subjected to the largest pressure difference. Therefore, the inflation pressure is calculated and determined according to the height of the airbag:

ps=K(ρgh+P0) ps =K(ρgh+ P0 )

ps——测试压强 ps ——test pressure

P0——大气压强P 0 —— atmospheric pressure

ρ——水的密度ρ——density of water

g——重力加速度g——acceleration due to gravity

h——气囊的高度h——Height of the airbag

K——安全系数,K值不小于1.4,K——Safety factor, K value is not less than 1.4,

充气完成后需要记录好充气量,作为气囊在水下的控制充气量v。充气完成后每30min检测一次气囊内部的气压,观测时间不小于3小时,每小时气压变化值不大于0.1ps为合格。After inflation is completed, the inflation volume needs to be recorded as the airbag's underwater control inflation volume v. After inflation is completed, the air pressure inside the airbag should be tested every 30 minutes. The observation time should not be less than 3 hours. The pressure change value per hour should not be greater than 0.1ps to be qualified.

由于气囊在水中受到水向上的浮力,气囊外壁承受拉力,气囊的抗拉强度验算为:Since the airbag is subject to the upward buoyancy of water in the water, the outer wall of the airbag is subjected to tension. The tensile strength of the airbag is calculated as:

2πRdσs≥K(ρVg-mg)2πRdσ s ≥K(ρVg-mg)

R——气囊底口的中心半径R——Center radius of the airbag bottom

d——气囊壁厚d——airbag wall thickness

σs——气囊材料的控制拉应力σ s ——Controlled tensile stress of airbag material

ρ——水的密度ρ——density of water

V——气囊充满空气后的体积V - the volume of the airbag when it is filled with air

g——重力加速度g——acceleration due to gravity

K——安全系数,不小于1.4K——Safety factor, not less than 1.4

m——气囊的质量m——the mass of the airbag

气囊检测合格后,将电线、送气管、砼泵管等设施与的贯穿口密封连接好,并做好管线的保护工作。检查无误后按照预定位置沉入海床,为保证气囊顺利下沉,气囊入水后要排干气囊内部的空气,并保证气囊不被底口钢板刮伤或压住。After the airbag is tested and qualified, the wires, air pipes, concrete pump pipes and other facilities are sealed and connected to the penetration ports, and the pipelines are protected. After the inspection is correct, it is sunk into the seabed according to the predetermined position. To ensure the smooth sinking of the airbag, the air inside the airbag must be drained after entering the water, and the airbag must not be scratched or pressed by the bottom steel plate.

(s4)气囊沉入海床后,检查气囊有没有被底口钢板压住,检查气囊底口是否落在平整的海床平面,如图1所示。(s4) After the airbag sinks to the seabed, check whether the airbag is pressed by the bottom steel plate and whether the bottom of the airbag falls on the flat seabed plane, as shown in Figure 1.

在海床不平整的凹陷位置,气囊袋口从环形钢板下方下垂至与海床接触,如图2所示。然后在气囊底口上方进行配重安装;At the concave position where the seabed is uneven, the airbag opening is lowered from the bottom of the annular steel plate until it contacts the seabed, as shown in Figure 2. Then, a counterweight is installed above the bottom opening of the airbag;

配重根据气囊的体积计算确定:The weight is calculated based on the volume of the airbag:

G——配重G——Counterweight

m——气囊及底口钢板的整体质量m——the overall mass of the airbag and bottom steel plate

v——气囊充满空气后的体积v - the volume of the airbag when it is filled with air

ρ——水的密度ρ——density of water

ρ′——配重的密度ρ′——density of the counterweight

K——安全系数,其中K值不小于1.4。K——Safety factor, where the K value is not less than 1.4.

配重必须和气囊进行有效连接固定,防止水流或波浪力造成气囊失稳。The counterweight must be effectively connected and fixed to the airbag to prevent the airbag from becoming unstable due to water flow or wave force.

(s5)配重安装好后,检查配重安装过程中有没有压住或刮伤气囊,检测无误后对气囊进行充气。充气应分步进行,根据气密性实验得出的控制充气量v,按照0.3v-0.6v-0.9v-1.0v的步骤进行,每步充气完成后,检查气囊的状态,看气囊有没有扭结、气囊有没有漏气、气囊是否稳定等。(s5) After the counterweight is installed, check whether the airbag is pressed or scratched during the installation process. After the inspection is correct, inflate the airbag. Inflation should be carried out step by step. According to the controlled inflation volume v obtained from the air tightness test, follow the steps of 0.3v-0.6v-0.9v-1.0v. After each inflation step, check the status of the airbag to see if there is any kink in the airbag, whether the airbag is leaking, and whether the airbag is stable.

(s6)施工人员及材料通过潜水艇经潜水艇通道进入气囊内部进行施工,无法装入潜水艇的大块材料通过绳索沉入潜水艇通道通道口,再通过绳索牵引到气囊内腔,在施工过程中,要连续不断的往气囊内部送气,确保气囊内部空气清新;发电机和空压机至少有一台备用,防止发生故障后气囊内停电停气。(s6) Construction workers and materials enter the airbag through the submarine channel for construction. Large materials that cannot be loaded into the submarine are sunk into the submarine channel through ropes and then pulled into the airbag cavity through ropes. During the construction process, air must be continuously supplied to the airbag to ensure that the air inside the airbag is fresh; at least one generator and air compressor should be kept as a spare to prevent power outages and air shortages in the airbag in the event of a malfunction.

(s7)施工人员在气囊内部进行基础施工;当水深超过20m时,气囊内部的气压超过3个大气压,工人必须佩戴减压呼吸器,且工作时长不超过2小时。当遇到突发情况,及时将工人送出进行处理。(s7) Construction workers are carrying out foundation construction inside the airbag; when the water depth exceeds 20m, the air pressure inside the airbag exceeds 3 atmospheres, and workers must wear decompression respirators and the working time shall not exceed 2 hours. When encountering emergencies, workers should be sent out in time for treatment.

(s8)基础施工完成后,上浮气囊到墩身施工的预定高度准备进行墩柱施工。上浮气囊之前,先安装好海底地锚,将地锚和气囊进行有效连接,在承台基础上提前预留锚固钢筋,将气囊锚固在承台基础上,锚固连接好后,拆除部分配重,让气囊缓慢上浮到预定高度,如图3所示。在气囊底口设置工作平台102以封闭气囊底部开口,搭设工作平台脚手架,脚手架上预留施工人员及施工材料的出入口;(s8) After the foundation construction is completed, the floating airbag is raised to the predetermined height of the pier body construction to prepare for the pier column construction. Before the floating airbag, first install the seabed anchor, effectively connect the anchor and the airbag, reserve anchor steel bars on the foundation of the pedestal in advance, anchor the airbag on the foundation of the pedestal, and after the anchor connection is completed, remove part of the counterweight to allow the airbag to slowly float to the predetermined height, as shown in Figure 3. Set a working platform 102 at the bottom of the airbag to close the bottom opening of the airbag, set up a working platform scaffolding, and reserve entrances and exits for construction personnel and construction materials on the scaffolding;

(s9)根据气囊的有效空间,每浇筑一段墩身混凝土就调整气囊一段上浮高度,直到墩身施工至水面以上,拆除气囊。(s9) According to the effective space of the airbag, the floating height of the airbag is adjusted every time a section of pier body concrete is poured, until the pier body is constructed above the water surface and the airbag is removed.

(s10)当气囊顶端露出水面后,气囊所受到的浮力逐渐减小,受到的波浪及水流的冲击力逐渐增大。为保证气囊的稳定性,需要及时拆除部分配重,配重拆除需要严格按照对称拆除的顺序进行,防止气囊失稳。每拆除一次配重,上浮一次气囊,直到全部配重拆除完成。在拆除配重及调整气囊上浮的过程中,要验算地锚的拉力,防止缆绳断裂。(s10) When the top of the airbag emerges from the water, the buoyancy of the airbag gradually decreases, while the impact of waves and currents gradually increases. To ensure the stability of the airbag, some counterweights need to be removed in a timely manner. The removal of the counterweights needs to be carried out in a strictly symmetrical order to prevent the airbag from becoming unstable. Each time a counterweight is removed, the airbag floats up until all counterweights are removed. In the process of removing the counterweights and adjusting the airbag to float up, the tension of the anchor must be verified to prevent the cable from breaking.

墩身混凝土施工至水面以上后,拆除气囊内的脚手架及管线设备,送风管最后拆除,防止气囊塌缩造成事故。松开缆绳后停止送风,采用起重机吊起气囊放到指定位置,并拆除地锚,完成气囊的拆除。After the pier body concrete is constructed above the water surface, the scaffolding and pipeline equipment in the airbag are removed, and the air supply pipe is removed last to prevent accidents caused by the collapse of the airbag. After loosening the cable, the air supply is stopped, and the airbag is lifted by a crane and placed in the designated position, and the anchor is removed to complete the removal of the airbag.

在实施中,气囊内部预备急救逃生舱,对工人进行教育培训及应急演练,预防发生突发事件时,工人可以迅速逃生。During implementation, an emergency escape capsule is prepared inside the airbag, and workers are given education and training as well as emergency drills to allow them to escape quickly in the event of an emergency.

当河水流速太大时不宜使用,应想办法在施工区下游修筑堤坝,降低施工区水的流速后方可采用气囊法施工。It should not be used when the river flow rate is too high. We should find a way to build a dam downstream of the construction area to reduce the water flow rate in the construction area before using the air bag method.

Claims (9)

1. The underwater dry operation construction method of the bottomless air bag method is characterized in that a bottomless air bag method underwater dry operation construction system is used for construction, the bottomless air bag method underwater dry operation construction system is composed of an air bag with an open lower part, an annular air bag bottom opening, a counterweight, a submarine channel, an air compressor, a generator and a concrete pump, wherein the air bag is made of flexible materials, the annular air bag bottom opening is made of rigid materials, the counterweight is pressed on the air bag bottom opening, the submarine is used for conveying constructors and construction materials, the submarine channel is arranged below the annular air bag bottom opening and is communicated with the inside and the outside of the air bag, the air compressor, the generator and the concrete pump are arranged above the water surface, the air bag bottom opening is landed on a seabed after leveling construction, an air inflation cavity is formed in the air bag, an air supply pipe, a cable and a pumping pipe are respectively penetrated through the air bag and are connected with an air compressor, a motor and a concrete pump above the water surface, the air inflation pressure matched with the submarine pressure is maintained in the air inflation cavity, and the inflation pressure is determined according to calculation of the height of the air bag:
ps=K(ρgh+P0)
p s -test pressure
P 0 atmospheric pressure
Ρ -density of water
G-gravity acceleration
H-height of air bag
K is a safety coefficient, and the K value is not less than 1.4;
The construction method comprises the following steps:
(s 1) manufacturing an air bag and an air bag bottom opening;
(s 2) leveling the seabed and excavating a submarine channel;
(s 3) after the air bag is detected to be qualified, the electric wire, the air supply pipe, the concrete pump pipe and the through opening of the air bag are connected in a sealing mode, the air bag is sunk into the seabed according to a preset position, and air in the air bag is drained after the air bag is immersed in water;
(s 4) after the air bag is sunk into the seabed, checking whether the bottom opening of the air bag falls on a flat seabed plane, lowering the air bag opening to be in contact with the bottom of the seabed when the bottom opening of the air bag is landed on the sunken position of the seabed, and then installing a counterweight above the bottom opening of the air bag;
(s 5) inflating the balloon lumen;
(s 6) constructors and materials enter the air bag through the submarine channel to construct, large materials which cannot be filled into the submarine sink into the submarine channel through the rope and then are pulled to the inner cavity of the air bag through the rope, and in the construction process, air is continuously supplied to the air bag to ensure that the air in the air bag is fresh;
(s 7) the constructor performs foundation construction inside the air bag;
(s 8) after the foundation construction is completed, floating the air bag to a preset height for pier body construction, firstly arranging a working platform at the bottom opening of the air bag, erecting a working platform scaffold, and reserving a constructor and a construction material access port on the scaffold;
(s 9) according to the effective space of the air bag, adjusting the floating height of one section of the air bag when one section of pier body concrete is poured until the pier body is constructed above the water surface, and dismantling the air bag;
And (s 10) after the top end of the air bag is exposed out of the water surface, removing part of the counter weight, removing the counter weight strictly according to the symmetrical removing sequence, removing the counter weight once, floating the air bag once until all the counter weight is removed, removing the scaffold and pipeline equipment in the air bag after pier body concrete is constructed above the water surface, finally removing the air supply pipe, stopping air supply after loosening a cable, lifting the air bag to a designated position by adopting a crane, removing the ground anchor, and completing the removal of the air bag.
2. The method according to claim 1, characterized in that: the bottom opening of the air bag is provided with a horizontal annular steel plate, the annular steel plate is provided with a vertical cylindrical protecting wall, the air bag is attached to the inner side of the cylindrical protecting wall, and the outer side of the cylindrical protecting wall is pressed with a counterweight.
3. The method according to claim 2, characterized in that: a plurality of supporting rib plates are arranged between the cylindrical protective wall and the annular steel plate.
4. The method according to claim 2, characterized in that: at the concave position of the uneven seabed, the air bag port sags from the lower part of the annular steel plate to be in contact with the seabed.
5. The method according to claim 1, characterized in that: the inflation pressure in the step (s 5) is determined according to the height calculation of the air bag:
ps=K(ρgh+P0)
p s -test pressure
P 0 atmospheric pressure
Ρ -density of water
G-gravity acceleration
H-height of air bag
K is a safety coefficient, the K value is not less than 1.4,
After the inflation is completed, the inflation quantity needs to be recorded and used as the controlled inflation quantity v of the air bag under water.
6. The method according to claim 1, characterized in that: the inflation in the step (s 5) is carried out step by step, the inflation quantity v is controlled according to the air tightness experiment, the inflation is carried out according to the steps of 0.3v-0.6v-0.9v-1.0v, and after each step of inflation is completed, the state of the air bag is checked, and whether kinking and air leakage conditions exist in the air bag are checked.
7. The method according to claim 1, characterized in that: and (s 8) before the air bag is floated, installing a submarine ground anchor, effectively connecting the ground anchor with the air bag, reserving an anchor reinforcing steel bar on a bearing platform foundation in advance, anchoring the air bag on the bearing platform foundation, and removing part of the counterweight after the air bag is anchored and connected, so that the air bag slowly floats to a preset height.
8. The method according to claim 1, characterized in that: the balance weight is determined according to the volume calculation of the air bag:
g-counterweight
M-integral mass of air bag and bottom mouth steel plate
V-volume of balloon after filling with air
Ρ -density of water
Ρ' —density of counterweight
K is a safety coefficient, wherein the K value is not less than 1.4.
9. The method according to claim 1, characterized in that: when the water depth exceeds 20m, the constructor inside the inner bag wears the decompression respirator.
CN202010224600.1A 2020-03-26 2020-03-26 Underwater dry operation construction system and method by bottomless air bag method Active CN111335177B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010224600.1A CN111335177B (en) 2020-03-26 2020-03-26 Underwater dry operation construction system and method by bottomless air bag method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010224600.1A CN111335177B (en) 2020-03-26 2020-03-26 Underwater dry operation construction system and method by bottomless air bag method

Publications (2)

Publication Number Publication Date
CN111335177A CN111335177A (en) 2020-06-26
CN111335177B true CN111335177B (en) 2024-10-29

Family

ID=71182571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010224600.1A Active CN111335177B (en) 2020-03-26 2020-03-26 Underwater dry operation construction system and method by bottomless air bag method

Country Status (1)

Country Link
CN (1) CN111335177B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112683775B (en) * 2020-11-18 2022-10-25 中交公路规划设计院有限公司 Steel shell concrete immersed tube tunnel push-out type final joint sliding track friction force testing system
CN115140668B (en) * 2022-07-22 2023-08-01 宋连杰 Deep water construction conveying equipment in hydraulic engineering dam

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212375719U (en) * 2020-03-26 2021-01-19 中交第四航务工程局有限公司 Underwater dry operation construction system adopting bottomless air bag method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4528652B2 (en) * 2005-03-08 2010-08-18 Jfeエンジニアリング株式会社 Temporary closing method for underwater structures and temporary closing structure
RU2399550C1 (en) * 2009-04-27 2010-09-20 Валерий Павлович Монахов Mobile underwater dwelling house
CN207582469U (en) * 2017-07-03 2018-07-06 广州华申建设工程管理有限公司 Telescopic underwater dry method grouting connection structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212375719U (en) * 2020-03-26 2021-01-19 中交第四航务工程局有限公司 Underwater dry operation construction system adopting bottomless air bag method

Also Published As

Publication number Publication date
CN111335177A (en) 2020-06-26

Similar Documents

Publication Publication Date Title
CN111335177B (en) Underwater dry operation construction system and method by bottomless air bag method
CN111254981A (en) Draw formula suspension tunnel structure to one side under water
CN101003974A (en) Method for constructing groundwork for large-scale sinking well in deep water
WO2006112506A1 (en) Floating body construction method for high tide floating building
CN111232145A (en) Overall layout of deepwater semi-submersible production platform
CN103253356B (en) Large-size pipe welding floating platform waterborne and dry construction condition construction method
JP2006507987A (en) Ballast system for tension leg platform
CN212375719U (en) Underwater dry operation construction system adopting bottomless air bag method
CN107653861B (en) A multifunctional hollow artificial island tower for supporting and connecting submarine vacuum pipelines
EA001045B1 (en) Jack-up offshore platform with submerged tank and methods of installing and lowering the tank-container
WO2006085592A1 (en) Building floating in flood damage and construction method therefor
CN103938638A (en) Buoy type deepwater single-wall steel cofferdam construction method
CN1099834A (en) Sum navigation lock
CN209069744U (en) A kind of bottom-sitting type wind turbine installation vessel
CN105401564B (en) Construction method for fixing tidal current energy power generation device to water bottom and tidal current energy power generation device
CN106322098A (en) Large-capacity methane storage cabinet and internal methane storage amount measuring method thereof
JP2006322301A (en) Inundation resistant building and its construction method
CN111962547B (en) Gas wharf gate dam
CN112922424B (en) A construction method of a giant spherical tank
CN212772700U (en) Repair damaged structure that blocks up of sewage pipe
CN108951560B (en) Floating box type mounting bracket convenient for recycling hoist and recycling method of hoist
CN209839469U (en) Pocket-shaped water plugging device for drainage pipeline
CN113107521A (en) Assembly type ocean tunnel structure with escape device and application method thereof
JP2006233745A (en) Floating body construction method for flood damage floating building
CN110683010B (en) Building method of fast-assembling nest bag type offshore mining platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 510000 headquarters building, Guangzhou, Haizhuqu District, Guangdong Zhenxing street, No. 18,

Applicant after: CCCC Fourth Harbor Engineering Co.,Ltd.

Applicant after: The Sixth Engineering Co.,Ltd.

Applicant after: CCCC FOURTH HARBOR ENGINEERING INSTITUTE Co.,Ltd.

Address before: 510000 headquarters building, Guangzhou, Haizhuqu District, Guangdong Zhenxing street, No. 18,

Applicant before: CCCC Fourth Harbor Engineering Co.,Ltd.

Applicant before: Zhuhai Engineering Co.,Ltd.

Applicant before: CCCC FOURTH HARBOR ENGINEERING INSTITUTE Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant