CN110880709B - Method for determining ice-watching dispatching time of power transmission line - Google Patents
Method for determining ice-watching dispatching time of power transmission line Download PDFInfo
- Publication number
- CN110880709B CN110880709B CN201911009598.XA CN201911009598A CN110880709B CN 110880709 B CN110880709 B CN 110880709B CN 201911009598 A CN201911009598 A CN 201911009598A CN 110880709 B CN110880709 B CN 110880709B
- Authority
- CN
- China
- Prior art keywords
- time
- ice
- line
- data
- time length
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 13
- 230000005540 biological transmission Effects 0.000 title claims abstract description 11
- 238000002844 melting Methods 0.000 claims abstract description 28
- 238000012216 screening Methods 0.000 claims abstract description 9
- 230000000630 rising effect Effects 0.000 claims abstract 2
- 238000012423 maintenance Methods 0.000 claims description 20
- 230000008018 melting Effects 0.000 claims description 18
- 238000009434 installation Methods 0.000 claims description 6
- 238000004364 calculation method Methods 0.000 claims description 4
- 230000008859 change Effects 0.000 claims description 2
- 238000001816 cooling Methods 0.000 claims description 2
- 230000008569 process Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000010309 melting process Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005315 distribution function Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000010257 thawing Methods 0.000 description 1
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/16—Devices for removing snow or ice from lines or cables
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a method for determining ice observation and dispatching time of a power transmission line, which comprises the following steps of: A. acquiring time node data of operation items in a plurality of historical operation tickets; B. calculating the duration of each operation item according to the time node data; C. screening out inferior data in the time length data calculated in the step B; D. calculating the average value of the remaining time length data after screening, summing the average time lengths of all the operation items to calculate the total time length from the start of ice-melting work to the start of the current line flow, wherein the total time length is combined with the start time of the current ice-melting work to calculate the start time of the current line flow: e: the ice observation dispatching time is determined according to the current line rising moment and the travel time of the ice observation personnel, so that the ice observation personnel can spread the ice observation work after arriving at an ice observation place, and the invalid waiting of the ice observation personnel in the environment with severe climate is avoided.
Description
Technical Field
The invention relates to the field of power grid operation and maintenance, in particular to a method for determining ice observation and dispatching time of a power transmission line.
Background
In severe winter, the phenomenon of icing on the transmission line can occur, which endangers the safety of the transmission line, a power supply bureau can take deicing measures, and the main means for eliminating the icing of the transmission line include direct-current deicing, ice thawing in a mode and the like.
Disclosure of Invention
In order to solve the problems, the method for determining the ice-watching dispatching time of the power transmission line comprises the following steps:
A. acquiring time node data of operation items in a plurality of historical operation tickets;
B. calculating the duration of each operation item according to the time node data;
C. screening out inferior data in the time length data calculated in the step B;
D. calculating the average value of the remaining time length data after screening, summing the average time lengths of all the operation items to calculate the total time length from the start of ice-melting work to the start of the current line flow, wherein the total time length is combined with the start time of the current ice-melting work to calculate the start time of the current line flow:
e: and determining the ice observing and dispatching time according to the current line starting upwelling moment and the travel time of ice observing personnel.
The method has the advantages that the time node of each operation item is obtained from a historical operation ticket, the operation duration of each item is calculated, normal duration data is screened out, and the time for dispatching is calculated according to the ice melting process, so that ice observation work can be performed after an ice observer arrives at an ice observation place, and invalid waiting of the ice observer in a severe climate environment is avoided.
Drawings
The invention is further illustrated by the attached drawings, the examples of which are not to be construed as limiting the invention in any way.
FIG. 1 is a flow chart of dispatch time determination in one embodiment of the present invention;
FIG. 2 is a schematic diagram of a distribution of a non-discrete random variable model in accordance with an embodiment of the present invention;
FIG. 3 is a schematic diagram showing the comparison of the ice-melting and ice-viewing processes according to an embodiment of the present invention.
Detailed Description
The following is a detailed illustration of the inventive concept in connection with the examples, and should not be taken to limit the scope of the invention, but rather as an aid to understanding the principles.
Example (b): as shown in fig. 1-3
A method for determining ice observation and dispatching time of a power transmission line comprises the following steps:
A. acquiring time node data of operation items in a plurality of historical operation tickets;
B. calculating the duration of each operation item according to the time node data;
C. screening out inferior data in the time length data calculated in the step B;
D. calculating the average value of the remaining time length data after screening, summing the average time lengths of all the operation items to calculate the total time length from the start of ice-melting work to the start of the current line upwelling, and calculating the time of the current line upwelling by combining the total time length with the current ice-melting work start time:
e: and determining the ice observing and dispatching time according to the current line starting upwelling moment and the travel time of ice observing personnel.
Preferably, in step a, the time node data includes a time t when the operation line route operation is started to be changed to maintenancer0And the time t when the line is changed from running to overhauling operationr1And the time t for starting the maintenance of the operation line to change to cold standbyr2Time t when the line is switched from maintenance to cooling standby operationrs。
Preferably, in step B, the calculated operation item duration includes:
time length T for line operation to maintenance operationr1Characterized by Tr1=tr1-tr0(1)
Ice melting equipment installation operation duration Tr2Characterized by Tr2=tr2-tr1(2)
RoutingTime length T for standby operation of overhaul-to-coldr3Characterized by Tr3=trs-tr2(3)。
Preferably, the poor quality data includes a length of time that the item was operated in the presence of a faulty repair.
The operation ticket is a proof of power grid operation, information of each operation project is recorded, time node data of each project is included in the information, the time node data are extracted, the consumed time of each project is calculated, and some special conditions may occur in the process of carrying out direct current ice melting work on the power transmission line, so that some time node data obviously deviate from a normal range. For example, if equipment such as a switch, a disconnecting link, a grounding switch, an ice melting device and the like fails, temporary shortage needs to be eliminated, and the time consumption of corresponding link operation is very long; if the line is in a cold standby or overhaul state before the ice melting operation is started, the time consumption of the corresponding link is very short (relevant time nodes cannot be extracted from an operation ticket, and the time consumption of some links for solving is zero or infinite). Therefore, when the expected value of time consumption of each link is calculated, the data of the special situation needs to be eliminated, so that more reasonable data is obtained, the inferior data is relative to a normal operation project, for the operation duration of a certain project, the time consumption is relatively stable under the normal condition according to the operation rule of a power grid, the dispatching time is calculated by combining the current ice melting process, and invalid waiting of ice watching personnel is avoided.
Preferably, the inferior data is screened out by establishing a non-discrete random variable model.
Aiming at any link, the same line or the line with the same type of ice melting devices is unfolded for multiple ice melting work to obtain solved time length, the time length is integrated in a data set to form a non-discrete immediate variable T, the probability density curve of the immediate variable is shown as the figure, wherein P is the distribution function of T, T is any non-negative real number, the minimum and maximum time length data are regarded as inferior data, and the inferior data are screened out in the calculation, namely the white bottom part (T is more than or equal to T) in the figure1And T is less than or equal to T2) For bad data, shaded parts (t)1<T<t2) For normal data, the data is calculated by the following equationSolving for t1、t2:
P{T≤t1}=0.2
P{T≤t2}=0.8
Preferably, in the step D, a time length data average value is calculated through weighted average, the weighted values are distributed from long to short correspondingly from small to large according to the time interval between the historical operation ticket where the time length data is located and the current ice-melting operation, and the sum of the weighted values is equal to 1.
For the screened duration data, an average value is obtained to be used as a basis for summing the operation durations of all projects, for the whole power grid unit, a general operation specification exists, each unit operates on the premise of not violating the specification according to the characteristics of the unit, for a certain unit, the operation duration of a certain link is mainly determined by the equipment quality and the technical level of operators when ice melting work is carried out, for example, the ice melting equipment of a certain power supply office is early in purchasing age, the equipment is aged to a certain degree, the time spent in installation operation is longer than that of the current advanced equipment, when the same equipment is operated, the experienced operators are faster than the new employees, or the equipment is updated, due to the technical development, the connection structure of the new equipment and the response mechanism are accelerated, which all affect the project operation durations, or the operator in charge of the ice melting operation changes the person, so that for a certain power supply unit, the data information in the recent ice melting operation ticket is more reliable, and the weight of the time length data close to the current ice melting operation time interval is larger during weighted average.
Preferably, in step D, the calculation of the current line upwelling starting time is characterized by:
in the formula, tdkFor the time of starting up-flow of the current line, tg0The current line is changed from operation to maintenance, and respectively carrying out weighted average values of the time length of the operation of the line from running to maintenance, the time length of the installation operation of the ice melting equipment and the time length of the operation of the line from maintenance to cold standby.
The line is changed from operation to maintenance, namely, the power supply of a normal line is stopped, a maintenance state is carried out, a key node needs to be disconnected, and the reliable short circuit of the line stroke is ensured; the ice melting equipment installation mainly relates to the operations that an ice melting device is arranged at the head end of a line, and the three phases at the tail end are in short circuit, grounded and the like; the line is changed from maintenance to cold standby, namely, a series of debugging and inspection work is carried out after the ice melting device is installed, and the cold standby mainly refers to the resting state of the line.
Preferably, in step E, the ice-watching dispatching time is characterized as:
tgp=tdk-Tp(5)
in the formula, tgpDispatching time for ice observation, TpWhen the ice-watching person travels.
Through the calculation process, the accurate line upwelling time is obtained, and the dispatching time can be calculated by combining the travel time of the ice observing person, wherein the travel time of the ice observing person mainly comprises the preparation working time T after receiving the ice observing noticeg1And a time period T for traveling to an ice siteg2,Tg2Can be determined by specialized navigation equipment.
For the ice observing personnel, the early-stage operation of the ice observing work further comprises a waiting time length delta Tg, and the expected value of delta Tg is set to be 0, namely the waiting value is eliminated as a target.
In the description of the embodiments of the invention, the particular features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples.
In the description of the embodiments of the present invention, it should be understood that "-" and "-" indicate the same range of two numerical values, and the range includes the endpoints. For example: "A-B" means a range of greater than or equal to A and less than or equal to B. "A to B" means a range of not less than A and not more than B.
In the description of the embodiments of the present invention, the term "and/or" herein is only one kind of association relationship describing an associated object, and means that there may be three kinds of relationships, for example, a and/or B, and may mean: a exists alone, A and B exist simultaneously, and B exists alone. In addition, the character "/" herein generally indicates that the former and latter related objects are in an "or" relationship.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (3)
1. A method for determining ice observation and dispatching time of a power transmission line is characterized by comprising the following steps:
A. acquiring time node data of operation items in a plurality of historical operation tickets;
B. calculating the duration of each operation item according to the time node data;
C. screening out inferior data in the time length data calculated in the step B;
D. calculating the average value of the remaining time length data after screening, summing the average time lengths of all the operation items to calculate the total time length from the start of ice-melting work to the start of the current line flow, wherein the total time length is combined with the start time of the current ice-melting work to calculate the start time of the current line flow:
e: determining ice observation dispatching time according to the current line rising moment and the travel time of ice observation personnel;
in the step A, the time node data comprises the time t when the operation line route operation is switched to maintenancer0And the time t when the line is changed from running to overhauling operationr1And the time t for starting the maintenance of the operation line to change to cold standbyr2Time t when the line is switched from maintenance to cooling standby operationrs;
In the step B, the calculated operation item duration includes:
time length T for line operation to maintenance operationr1Characterized by Tr1=tr1-tr0(1)
Ice melting equipment installation operation duration Tr2Characterized by Tr2=tr2-tr1(2)
Line route maintenance cold-transfer standby operation duration Tr3Characterized by Tr3=trs-tr2(3);
The inferior data comprises the operation duration of the project with fault maintenance;
screening the inferior data by establishing a non-discrete random variable model;
in the step D, calculating a time length data average value through weighted average, wherein the weighted values are correspondingly distributed from small to large according to the time interval between the historical operation ticket where the time length data is located and the current ice melting operation time, and the sum of the weighted values is equal to 1.
2. The method according to claim 1, wherein in step D, the calculation of the current line upwelling start time is characterized by:
in the formula, tdkFor the time of starting up-flow of the current line, tg0The current line is changed from operation to maintenance, and respectively carrying out weighted average values of the time length of the operation of the line from running to maintenance, the time length of the installation operation of the ice melting equipment and the time length of the operation of the line from maintenance to cold standby.
3. The method according to claim 1, wherein in step E, the ice observation dispatching time is characterized as:
tgp=tdk-Tp(5)
in the formula, tgpDispatching time for ice observation, TpWhen the ice-watching person travels.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911009598.XA CN110880709B (en) | 2019-10-23 | 2019-10-23 | Method for determining ice-watching dispatching time of power transmission line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911009598.XA CN110880709B (en) | 2019-10-23 | 2019-10-23 | Method for determining ice-watching dispatching time of power transmission line |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110880709A CN110880709A (en) | 2020-03-13 |
CN110880709B true CN110880709B (en) | 2020-10-16 |
Family
ID=69727892
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911009598.XA Active CN110880709B (en) | 2019-10-23 | 2019-10-23 | Method for determining ice-watching dispatching time of power transmission line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110880709B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111769478B (en) * | 2020-07-13 | 2021-07-13 | 贵州电网有限责任公司 | Direct-current ice melting control method for power transmission line |
CN114493194A (en) * | 2022-01-08 | 2022-05-13 | 江苏秉信科技有限公司 | Equipment operation duration analysis method based on multi-factor comprehensive balance |
CN114819217A (en) * | 2022-04-27 | 2022-07-29 | 西安西热电站信息技术有限公司 | Method for calculating the power loss of wind farm scheduled maintenance or planned shutdown based on work tickets |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2418473A1 (en) * | 2003-02-04 | 2004-08-04 | Hydro-Quebec | Robot vehicle that runs on conductors and has the ability to negotiate obstacles using temporary support rotors |
JP4467417B2 (en) * | 2004-12-09 | 2010-05-26 | 株式会社フジクラ | Snow melting wire, drum winding snow melting wire, and overhead snow melting wire construction method |
CN202485714U (en) * | 2011-12-05 | 2012-10-10 | 西安工程大学 | Power transmission line icing on-line monitoring system |
CN104697588A (en) * | 2015-04-07 | 2015-06-10 | 国家电网公司 | Icing observational method for electric transmission line under meteorological condition of natural icing |
CN106469892A (en) * | 2015-08-18 | 2017-03-01 | 国家电网公司 | A kind of ice-melt cable hanging device |
CN107607807B (en) * | 2017-08-18 | 2019-04-02 | 国网湖南省电力公司 | A kind of the current time characteristic test method and device of transmission pressure ice-melt |
CN108845226A (en) * | 2018-04-25 | 2018-11-20 | 国网甘肃省电力公司 | A kind of Distribution Network Failure intelligent locating method based on angle analysis weighting algorithm |
CN109342908B (en) * | 2018-12-14 | 2021-02-19 | 国家电网有限公司 | An early warning method for icing based on observation of insulators |
CN110135601A (en) * | 2019-05-17 | 2019-08-16 | 广东电网有限责任公司 | A kind of system and method that distribution scheduling interruption maintenance is permitted indirectly |
CN110598877A (en) * | 2019-08-30 | 2019-12-20 | 国家电网有限公司 | Transformer substation accessory facility maintenance method and system and terminal equipment |
-
2019
- 2019-10-23 CN CN201911009598.XA patent/CN110880709B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN110880709A (en) | 2020-03-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110880709B (en) | Method for determining ice-watching dispatching time of power transmission line | |
CN108631306B (en) | Method for evaluating recovery capability of power system after disaster | |
CN116187593B (en) | A distribution network fault prediction processing method, device, equipment, and storage medium | |
CN103986227B (en) | A kind of monitoring method for running of the power matching network based on GIS platform and system | |
CN107705032A (en) | A Line Melting Method Based on Offline Risk Assessment Model of Power Grid Icing Disaster | |
CN106017551A (en) | Intelligent transmission line integrated monitoring analysis and early warning method | |
CN101968864A (en) | Electric power system operation reliability-centered equipment importance evaluation method | |
CN106447107B (en) | Maintenance method based on aircraft structure health monitoring | |
CN111348535B (en) | Health state monitoring system and method for escalator used in rail transit station | |
CN107390087A (en) | Platform is supported in a kind of power network repairing operation | |
CN108446820A (en) | A kind of guidance station device network vulnerability assessment method considering neighbor node contribution function | |
CN108454879A (en) | Airplane fault processing system and method and computer equipment | |
CN103308314B (en) | Automobile engine fault maintenance method based on Bayesian network models and multi-criteria decision analysis | |
CN107748956A (en) | A kind of appraisal procedure of power distribution network typical wiring non-integer segmentation reliability | |
CN102799746B (en) | Power grid information checking method and system, and power grid planning auxiliary system | |
CN109472388B (en) | A loss-based fault warning method and system for power protection equipment | |
CN103324795A (en) | Direct current system reliability assessment method considering station power utilization influence | |
CN108460202A (en) | Marine system testability index optimization method | |
CN108133321A (en) | Specially become O&M trustship work management method, system, medium and computer equipment | |
CN103198369A (en) | Method and device of automatic schedule information processing of bullet train daily maintenance schedule | |
CN117810967A (en) | Multi-stage toughness improvement method of electric power system for coping with ice disaster influence | |
CN109033569B (en) | Method for optimizing strength and times of preventive maintenance threshold of shipboard aircraft sensor system | |
CN109462176B (en) | GIS-based intelligent patrol command method and system | |
CN112036650A (en) | Battery replacement management method and management system of parking space management device | |
CN106570245B (en) | Petri network-based airport terminal reliability identification method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |