CN110878607A - A composite curtain wall structure - Google Patents
A composite curtain wall structure Download PDFInfo
- Publication number
- CN110878607A CN110878607A CN201911155739.9A CN201911155739A CN110878607A CN 110878607 A CN110878607 A CN 110878607A CN 201911155739 A CN201911155739 A CN 201911155739A CN 110878607 A CN110878607 A CN 110878607A
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- aluminum
- aluminum alloy
- glass
- assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
本发明公开了一种复合幕墙结构,包括幕墙立柱、铝单板、幕墙玻璃、连接石材、铝合金横梁组件以及角钢横梁组件,连接石材的一侧面通过角钢横梁组件和幕墙立柱相连接,连接石材的一端通过铝合金横梁组件和幕墙玻璃相连接,连接石材的另一端通过铝合金横梁组件和铝单板的一端相连接,铝单板的另一端和幕墙玻璃相连接,铝合金横梁组件和幕墙立柱相连接;幕墙玻璃、连接石材以及铝单板均和幕墙立柱互相平行;本发明的复合幕墙采用幕墙玻璃、连接石材以及铝单板,将玻璃、石材和铝板三者巧妙的组合到一起,具有连接方便简单、连接紧密的优点。
The invention discloses a composite curtain wall structure, comprising a curtain wall column, an aluminum veneer, a curtain wall glass, a connecting stone, an aluminum alloy beam assembly and an angle steel beam assembly. One end is connected with the curtain wall glass through the aluminum alloy beam assembly, the other end of the connecting stone is connected with one end of the aluminum veneer through the aluminum alloy beam assembly, the other end of the aluminum veneer is connected with the curtain wall glass, the aluminum alloy beam assembly and the curtain wall The columns are connected; the curtain wall glass, the connecting stone and the aluminum veneer are all parallel to the curtain wall columns; the composite curtain wall of the present invention adopts the curtain wall glass, the connecting stone and the aluminum veneer, and the glass, the stone and the aluminum plate are skillfully combined together, It has the advantages of convenient and simple connection and tight connection.
Description
技术领域technical field
本发明涉及建筑装饰技术领域,具体涉及一种复合幕墙结构。The invention relates to the technical field of architectural decoration, in particular to a composite curtain wall structure.
背景技术Background technique
幕墙是建筑的外墙围护,不承重,像幕布一样挂上去,故又称为“帷幕墙”,是现代大型和高层建筑常用的带有装饰效果的轻质墙体。由面板和支承结构体系组成的,可相对主体结构有一定位移能力或自身有一定变形能力、不承担主体结构所作用的建筑外围护结构或装饰性结构;幕墙是利用各种强劲、轻盈、美观的建筑材料取代传统的砖石或窗墙结合的外墙工法,是包围在主结构的外围而使整栋建筑达到美观,使用功能健全而又安全的外墙工法。简言之,是将建筑穿上一件漂亮的外衣。The curtain wall is the outer wall of the building. It is not load-bearing and hangs like a curtain, so it is also called "curtain wall". It is a lightweight wall with decorative effects commonly used in modern large and high-rise buildings. It is composed of panels and supporting structure systems, which can have a certain displacement ability relative to the main structure or have a certain deformation ability itself, and do not assume the role of the main structure. The outer protective structure or decorative structure of the building; The beautiful building material replaces the traditional exterior wall construction method of masonry or window wall. It surrounds the periphery of the main structure to make the whole building look beautiful, and uses a sound and safe exterior wall construction method. In short, it is about putting architecture on a beautiful coat.
近些年来随着建筑材料的不断发展,幕墙面板的品种也在不断增加,各种轻质面板材料都能作为幕墙的面板,为人们提供了丰富多彩的幕墙形式,而随着幕墙的不断发展,不同材料集中在一起的复合幕墙更是得到业主和设计师的青睐,幕墙的形式丰富多彩,变化无穷,丰富立面效果,然而,复合幕墙并不是简单的将不同的单一幕墙强行加在一起,要合理的运用单一幕墙的体系,进行优化,但现实情况中大多数设计施工要么做成非常复杂的结构,增加很多不必要的构件或者将构件做成很大、很复杂的断面,要么将单一幕墙强行叠加各自成体系,中间打胶,这样造成的后果就是连接不合理,受力不明确,结构不节能,防水效果差,操作空间小,无法实现设计要求,材料的浪费,加工难度大、甚于造成延误工期和影响工程质量严重后果。In recent years, with the continuous development of building materials, the variety of curtain wall panels is also increasing. Various lightweight panel materials can be used as curtain wall panels, providing people with a variety of curtain wall forms. With the continuous development of curtain walls , The composite curtain wall with different materials is favored by the owners and designers. The form of the curtain wall is rich and colorful, with endless changes and rich façade effects. However, the composite curtain wall is not a simple combination of different single curtain walls. , It is necessary to rationally use a single curtain wall system for optimization, but in reality, most designs and constructions are either made into very complex structures, adding many unnecessary components or making components into large and complex sections, or A single curtain wall is forcibly superimposed to form a system, and glue is applied in the middle. The consequences of this are unreasonable connection, unclear force, inefficient structure, poor waterproof effect, small operating space, unable to meet design requirements, waste of materials, and difficult processing. , even more serious consequences of delaying the construction period and affecting the quality of the project.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提供一种复合幕墙结构,以解决现有技术中导致的上述多项缺陷或缺陷之一。The purpose of the present invention is to provide a composite curtain wall structure to solve the above-mentioned defects or one of the defects caused in the prior art.
为达到上述目的,本发明是采用下述技术方案实现的:To achieve the above object, the present invention adopts the following technical solutions to realize:
一种复合幕墙结构,包括幕墙立柱、铝单板、幕墙玻璃、连接石材、铝合金横梁组件以及角钢横梁组件,所述连接石材的一侧面通过角钢横梁组件和所述幕墙立柱相连接,所述连接石材的一端通过铝合金横梁组件和所述幕墙玻璃相连接,所述连接石材的另一端通过铝合金横梁组件和所述铝单板的一端相连接,所述铝单板的另一端和所述幕墙玻璃相连接,所述铝合金横梁组件和所述幕墙立柱相连接;所述幕墙玻璃、连接石材以及铝单板均和所述幕墙立柱互相平行。A composite curtain wall structure includes a curtain wall column, an aluminum veneer, a curtain wall glass, a connecting stone, an aluminum alloy beam assembly, and an angle steel beam assembly. One side of the connecting stone is connected to the curtain wall column through an angle steel beam assembly, and the One end of the connecting stone is connected to the curtain wall glass through an aluminum alloy beam assembly, the other end of the connecting stone is connected to one end of the aluminum veneer through an aluminum alloy beam assembly, and the other end of the aluminum veneer is connected to the other end of the aluminum veneer. The curtain wall glass is connected, the aluminum alloy beam assembly is connected with the curtain wall column; the curtain wall glass, the connecting stone and the aluminum veneer are all parallel to the curtain wall column.
进一步地,所述连接石材和所述铝合金横梁组件之间设有连接缝隙,所述连接缝隙内填充有泡沫条。泡沫条的设置使的两者之间没有直接接触,一方面防止损坏铝合金横梁组件,另一方面保证密封效果。Further, a connecting gap is provided between the connecting stone and the aluminum alloy beam assembly, and the connecting gap is filled with foam strips. The foam strips are arranged so that there is no direct contact between the two, on the one hand to prevent damage to the aluminum alloy beam assembly, and on the other hand to ensure the sealing effect.
进一步地,所述泡沫条外周设有密封胶。密封胶的设置进一步保证了两者的密封效果,使连接处紧密,起到了一定的防水效果。Further, the outer periphery of the foam strip is provided with a sealant. The setting of the sealant further ensures the sealing effect of the two, so that the connection is tight and has a certain waterproof effect.
进一步地,所述铝单板和所述幕墙立柱之间通过连接角铝相连接,所述连接角铝和所述幕墙立柱之间设有防腐垫片。通过防腐垫片和幕墙立柱相接触增加了连接角铝的使用寿命。Further, the aluminum veneer and the curtain wall column are connected by connecting angle aluminum, and an anti-corrosion gasket is arranged between the connecting angle aluminum and the curtain wall column. The service life of the connecting angle aluminum is increased by the contact between the anti-corrosion gasket and the curtain wall column.
进一步地,所述铝合金横梁组件包括横梁和盖板组件,所述盖板组件通过螺栓连接在所述横梁的一侧,所述横梁通过第一螺栓连接在所述幕墙立柱上;Further, the aluminum alloy beam assembly includes a beam and a cover plate assembly, the cover plate assembly is connected to one side of the beam through bolts, and the beam is connected to the curtain wall column through a first bolt;
所述幕墙玻璃的一端通过玻璃垫块连接在所述横梁和盖板组件之间。One end of the curtain wall glass is connected between the beam and the cover plate assembly through a glass spacer.
进一步地,所述横梁和所述盖板组件连接有两块幕墙玻璃,其中一块所述幕墙玻璃和所述横梁之间设有第一支撑块,另一块所述幕墙玻璃和所述盖板组件之间设有第一支撑块,两块所述幕墙玻璃之间设有中间支撑块。Further, the beam and the cover plate assembly are connected with two pieces of curtain wall glass, one of which is provided with a first support block between the curtain wall glass and the beam, and the other piece of the curtain wall glass and the cover plate assembly. A first support block is arranged therebetween, and an intermediate support block is arranged between the two pieces of the curtain wall glass.
进一步地,还包括L型板,所述L型板的竖板通过背挂件和所述连接石材相连接,所述L型板的横板和所述角钢横梁相连接。Further, it also includes an L-shaped plate, the vertical plate of the L-shaped plate is connected with the connecting stone through the back hanger, and the horizontal plate of the L-shaped plate is connected with the angle steel beam.
进一步地,所述角钢横梁组件包括角钢横梁和铝合金角铝,所述铝合金角铝通过螺栓和所述幕墙立柱相连接,所述角钢横梁和所述铝合金角铝通过第二螺栓相连接;所述L型板的横板连接在所述铝合金角铝和所述角钢横梁之间。Further, the angle steel beam assembly includes an angle steel beam and an aluminum alloy angle aluminum, the aluminum alloy angle aluminum is connected with the curtain wall column by bolts, and the angle steel beam and the aluminum alloy angle aluminum are connected by a second bolt. ; The transverse plate of the L-shaped plate is connected between the aluminum alloy angle aluminum and the angle steel beam.
进一步地,所述连接石材为花岗石。花岗石具有较强的硬度和稳定性,保证了使用寿命的长久。Further, the connecting stone is granite. Granite has strong hardness and stability, which ensures a long service life.
根据上述技术方案,本发明的实施例至少具有以下效果:According to the above technical solutions, the embodiments of the present invention have at least the following effects:
1、本发明的复合幕墙采用幕墙玻璃、连接石材以及铝单板,将玻璃、石材和铝板三者巧妙的组合到一起;三者之间并通过铝合金横梁组件连接并连接至幕墙立柱上,铝合金横梁组件保证了三者的连接效果以及三者和幕墙立柱的连接效果,具有连接方便简单、连接紧密的优点;1. The composite curtain wall of the present invention adopts curtain wall glass, connecting stone and aluminum veneer, and combines glass, stone and aluminum plate ingeniously; the three are connected by aluminum alloy beam components and connected to the curtain wall column, The aluminum alloy beam assembly ensures the connection effect of the three and the connection effect of the three and the curtain wall column, and has the advantages of convenient and simple connection and tight connection;
2、本发明采用铝合金横梁组件将幕墙玻璃、连接石材以及铝单板连接组成复合幕墙,安装拆卸方便,且拆解后的幕墙组件便于加工制造。2. The present invention adopts aluminum alloy beam components to connect the curtain wall glass, connecting stone and aluminum veneer to form a composite curtain wall, which is convenient to install and disassemble, and the disassembled curtain wall components are easy to manufacture.
附图说明Description of drawings
图1为本发明具体实施方式的整体结构示意图;Fig. 1 is the overall structure schematic diagram of the specific embodiment of the present invention;
图2为图1中的部分结构示意图;Fig. 2 is the partial structure schematic diagram in Fig. 1;
图3为图1中的部分结构示意图;Fig. 3 is the partial structure schematic diagram in Fig. 1;
图4为图1中A部分的放大图;Fig. 4 is an enlarged view of part A in Fig. 1;
图5为图1中B部分的放大图;Fig. 5 is an enlarged view of part B in Fig. 1;
图6为图1中C部分的放大图。FIG. 6 is an enlarged view of part C in FIG. 1 .
其中:1、幕墙立柱;2、铝单板;3、幕墙玻璃;31、第一支撑块;32、中间支撑块;4、花岗石;5、铝合金横梁组件;6、角钢横梁组件;7、背挂件;21、连接角铝;22、防腐垫片;23、固定螺丝;51、横梁;52、横梁盖板;53、第一螺栓;54、外盖板;55、内盖板;56、玻璃垫块;57、密封胶;58、泡沫条;59、铝合金槽铝;61、角钢横梁;62、铝合金角铝;63、第二螺栓。Among them: 1. Curtain wall column; 2. Aluminum veneer; 3. Curtain wall glass; 31. First support block; 32. Intermediate support block; 4. Granite; 5. Aluminum alloy beam assembly; 6. Angle steel beam assembly; 7, back pendant; 21, connecting angle aluminum; 22, anti-corrosion gasket; 23, fixing screw; 51, beam; 52, beam cover; 53, first bolt; 54, outer cover; 55, inner cover; 56, glass spacer; 57, sealant; 58, foam strip; 59, aluminum alloy groove; 61, angle steel beam; 62, aluminum alloy angle aluminum; 63, second bolt.
具体实施方式Detailed ways
为使本发明实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体实施方式,进一步阐述本发明。In order to make the technical means, creative features, achievement goals and effects realized by the present invention easy to understand, the present invention will be further described below with reference to the specific embodiments.
需要说明的是,在本发明的描述中,术语“前”、“后”、“左”、“右”、“上”、“下”、“内”、“外”等指示的方位或位置关系为基于附图中所示的方位或位置关系,仅是为了便于描述本发明而不是要求本发明必须以特定的方位构造和操作,因此不能理解为对本发明的限制。本发明描述中使用的术语“前”、“后”、“左”、“右”、“上”、“下”指的是附图中的方向,术语“内”、“外”分别指的是朝向或远离特定部件几何中心的方向。It should be noted that, in the description of the present invention, the terms "front", "rear", "left", "right", "upper", "lower", "inner", "outer" and the like indicate the orientation or position The relationship is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the present invention rather than requiring the present invention to be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention. The terms "front", "rear", "left", "right", "upper" and "lower" used in the description of the present invention refer to the directions in the drawings, and the terms "inner" and "outer" respectively refer to is the direction toward or away from the geometric center of a particular part.
如图1至图3所示,一种复合幕墙结构,包括一幕墙立柱1,幕墙立柱1用于连接幕墙组件,幕墙组件包括一块铝单板2、四块幕墙玻璃3以及一块花岗石4。花岗石4、幕墙玻璃3和铝单板2的右侧面和幕墙立柱1的侧面平行,保证复合幕墙的使用效果。本发明的连接件包括铝合金横梁组件5和角钢横梁组件6,铝合金横梁组件5和角钢横梁组件6有多个。As shown in Figures 1 to 3, a composite curtain wall structure includes a
铝合金横梁组件5包括横梁51和盖板组件,盖板组件通过螺栓连接在横梁51的一侧,横梁通过第一螺栓53连接在幕墙立柱1上。横梁51包括横梁框架和连接角铝,横梁框架和连接角铝通过螺栓连接,连接角铝通过第一螺栓固定在幕墙立柱1的前后侧面,横梁框架的开口端卡合连接有横梁盖板52,横梁盖板52保证了横梁51的密封效果。盖板组件包括外盖板54和内盖板55,内盖板55通过螺栓和横梁51相连接,内盖板55和横梁51的连接处设有隔热垫块,内盖板55和外盖板54卡合连接。内盖板55和横梁框架底部的开口上连接有铝合金槽铝59,保证了铝合金横梁组件5的密封效果。外盖板54的右侧面和花岗石4、铝单板2以及其中两块幕墙玻璃3的右侧面在同一平面上,组成复合幕墙的外表面。在同一平面上,保证复合幕墙的外侧面平齐,具有美观效果,且外侧面平齐能够起到防水作用。The aluminum
具体的,铝合金横梁组件5用于连接铝单板2、花岗石4以及幕墙玻璃3。铝合金横梁组件5中的外盖板54和花岗石4之间存在连接缝隙,花岗石4和铝单板2之间存在连接缝隙。连接缝隙处放置有泡沫条58,泡沫条58通过密封胶57和外盖板54以及铝单板2连接,泡沫条58通过密封胶57和外盖板54以及花岗石4相连接,密封胶为硅酮密封胶57,密封胶57的设置保证了连接处的密封效果,并保证防水作用。Specifically, the aluminum
如图4所示,两块幕墙玻璃3连接在横梁51和内盖板55之间,如图4所示,横梁51和内盖板55的上放置有玻璃垫块56,玻璃垫块56保证幕墙玻璃3的使用寿命。横梁51的横梁框架的左侧卡接有第一支撑块31,第一支撑块31用于支撑幕墙玻璃3,内盖板55的右侧卡接有第一支撑块31,第一支撑块31用于支撑幕墙玻璃3。两块幕墙玻璃3中间设有中间支撑块32。中间支撑块32和第一支撑块31起到支撑幕墙玻璃3的作用。As shown in FIG. 4 , two pieces of
如图5所示,角钢横梁组件6包括角钢横梁61和铝合金角铝62,铝合金角铝62通过螺栓连接在幕墙立柱1的前后侧面,角钢横梁61通过第二螺栓63和铝合金角铝62相连接,角钢横梁61的形状为L型,铝合金角铝62的形状为方形。角钢横梁61连接在铝合金角铝62的顶部。角钢横梁组件6通过L型板和背挂件7相连接,背挂件7和花岗石4相连接。背挂件7为U型,背挂件7的U型底端部通过地脚螺栓连接至花岗石4的左侧面,背挂件7的U型开口端通过连接螺栓及垫片和L型板的竖板相连接。L型板的横板通过螺栓连接在角钢横梁61的顶面。角钢横梁组件6的设置提高了花岗石4的连接的稳定,由于花岗石4的重量较大,所以为了保证连接结构的强度足够,所以设置角钢横梁组件6。As shown in FIG. 5 , the angle
本发明通过角钢横梁组件6将花岗石4固定在幕墙立柱1上,通过铝合金横梁组件5将铝单板2、花岗石4以及幕墙玻璃3连接,并将其连接至幕墙立柱1上,保证了复合幕墙的结构稳定,并保证了连接件的强度。复合幕墙结构受力合理,角钢横梁组件6的设置保证了花岗石4的稳定。In the present invention, the
如图6所示,铝单板2和幕墙立柱1之间通过连接角铝21相连接,连接角铝21和幕墙立柱1之间设有防腐垫片22。连接角铝21和防腐垫片22通过固定螺丝23连接在幕墙立柱1上,防腐垫片22的设置能够保证连接角铝21的使用寿命。As shown in FIG. 6 , the
由技术常识可知,本发明可以通过其它的不脱离其精神实质或必要特征的实施方案来实现。因此,上述公开的实施方案,就各方面而言,都只是举例说明,并不是仅有的。所有在本发明范围内或在等同于本发明的范围内的改变均被本发明包含。It is known from the technical common sense that the present invention can be realized by other embodiments without departing from its spirit or essential characteristics. Accordingly, the above-disclosed embodiments are, in all respects, illustrative and not exclusive. All changes within the scope of the present invention or within the scope equivalent to the present invention are encompassed by the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911155739.9A CN110878607B (en) | 2019-11-22 | 2019-11-22 | Composite curtain wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911155739.9A CN110878607B (en) | 2019-11-22 | 2019-11-22 | Composite curtain wall structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110878607A true CN110878607A (en) | 2020-03-13 |
CN110878607B CN110878607B (en) | 2025-02-14 |
Family
ID=69729040
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911155739.9A Active CN110878607B (en) | 2019-11-22 | 2019-11-22 | Composite curtain wall structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110878607B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114776034A (en) * | 2022-05-30 | 2022-07-22 | 北京城建集团有限责任公司 | Glass curtain wall mounting construction process |
CN116378267A (en) * | 2023-03-28 | 2023-07-04 | 中煤江南市政建设(广东)有限公司 | Construction method for junction of stone curtain wall and glass curtain wall |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4899508A (en) * | 1988-04-28 | 1990-02-13 | Butler Manufacturing Company | Panel and glass curtain wall system |
CN2481783Y (en) * | 2001-04-25 | 2002-03-13 | 哈尔滨市东方墙业装饰有限责任公司 | Energy-saving concealed frame curtain wall |
EP2216474A1 (en) * | 2009-02-06 | 2010-08-11 | Cuhadaroglu Metal Sanayi Ve Pazarlama A.S. | A curtain wall system in which the joining distance between the load bearing profile and the plate is reduced |
CN103850373A (en) * | 2014-03-05 | 2014-06-11 | 北京中瑞宏宇幕墙装饰工程有限公司 | Novel combined curtain wall system |
CN205077681U (en) * | 2015-09-23 | 2016-03-09 | 常州通越铝板幕墙制造有限公司 | Aluminum plate curtain wall |
CN207017497U (en) * | 2017-06-15 | 2018-02-16 | 苏州苏明装饰股份有限公司 | A kind of open stone curtain wall system |
CN109930724A (en) * | 2019-02-28 | 2019-06-25 | 上海市建筑装饰工程集团有限公司 | A kind of connection structure of upright posts of glass curtain wall and crossbeam |
CN211690968U (en) * | 2019-11-22 | 2020-10-16 | 苏州广林建设有限责任公司 | Composite curtain wall structure |
-
2019
- 2019-11-22 CN CN201911155739.9A patent/CN110878607B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4899508A (en) * | 1988-04-28 | 1990-02-13 | Butler Manufacturing Company | Panel and glass curtain wall system |
CN2481783Y (en) * | 2001-04-25 | 2002-03-13 | 哈尔滨市东方墙业装饰有限责任公司 | Energy-saving concealed frame curtain wall |
EP2216474A1 (en) * | 2009-02-06 | 2010-08-11 | Cuhadaroglu Metal Sanayi Ve Pazarlama A.S. | A curtain wall system in which the joining distance between the load bearing profile and the plate is reduced |
CN103850373A (en) * | 2014-03-05 | 2014-06-11 | 北京中瑞宏宇幕墙装饰工程有限公司 | Novel combined curtain wall system |
CN205077681U (en) * | 2015-09-23 | 2016-03-09 | 常州通越铝板幕墙制造有限公司 | Aluminum plate curtain wall |
CN207017497U (en) * | 2017-06-15 | 2018-02-16 | 苏州苏明装饰股份有限公司 | A kind of open stone curtain wall system |
CN109930724A (en) * | 2019-02-28 | 2019-06-25 | 上海市建筑装饰工程集团有限公司 | A kind of connection structure of upright posts of glass curtain wall and crossbeam |
CN211690968U (en) * | 2019-11-22 | 2020-10-16 | 苏州广林建设有限责任公司 | Composite curtain wall structure |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114776034A (en) * | 2022-05-30 | 2022-07-22 | 北京城建集团有限责任公司 | Glass curtain wall mounting construction process |
CN116378267A (en) * | 2023-03-28 | 2023-07-04 | 中煤江南市政建设(广东)有限公司 | Construction method for junction of stone curtain wall and glass curtain wall |
CN116378267B (en) * | 2023-03-28 | 2024-08-23 | 中煤江南市政建设(广东)有限公司 | Construction method for junction of stone curtain wall and glass curtain wall |
Also Published As
Publication number | Publication date |
---|---|
CN110878607B (en) | 2025-02-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102045134B1 (en) | Architectural decorative panel dry-row structure with free mounting and disassembly and flexible size combination | |
CN107044179B (en) | Decorative panel and template integrated heat-preservation decorative composite wall and construction method thereof | |
CN201598759U (en) | Honeycomb aluminum plate stone composite panel curtain wall | |
CN105102092A (en) | Wall and construction method for same | |
CN212582974U (en) | Double wall for quick disassembly | |
CN110878607A (en) | A composite curtain wall structure | |
CN103290963B (en) | Modularized combination type heat insulating curtain wall panel | |
CN211690968U (en) | Composite curtain wall structure | |
CN112127511A (en) | Wall enclosure system for quick assembly and disassembly | |
CN202658773U (en) | Bamboo-board curtain wall system | |
CN104769195A (en) | Combined wall body and construction method thereof | |
CN201738473U (en) | Glass curtain wall structure with large-sized trim strips | |
CN203795652U (en) | Combination wall | |
CN209621046U (en) | A kind of slit stone thermal insulation side-hung hidden door | |
CN214658167U (en) | An inverted unit design structure of an elliptical multi-curved GRG ceiling | |
CN205502460U (en) | Glass fiber reinforced gypsum board's seamless connection structure | |
CN211774992U (en) | Wall body wood finish coat and furred ceiling connected node structure | |
CN204456543U (en) | Carry keel assembling curtain wall circuit board | |
KR102574090B1 (en) | Insulation structure of exterior panels for building with enhanced seismic performance | |
CN218437630U (en) | Wallboard connecting structure | |
CN219386791U (en) | Supporting structure of curtain wall | |
WO2020180276A1 (en) | Facade cladding system | |
CN110541510A (en) | Thin calcium silicate board dry-hanging system | |
CN103046672B (en) | Curtain wall without keels | |
CN215254130U (en) | Seamless mosaic structure of arc wood decorations post integrated design |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |