CN110820729B - Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery - Google Patents
Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery Download PDFInfo
- Publication number
- CN110820729B CN110820729B CN201911078962.8A CN201911078962A CN110820729B CN 110820729 B CN110820729 B CN 110820729B CN 201911078962 A CN201911078962 A CN 201911078962A CN 110820729 B CN110820729 B CN 110820729B
- Authority
- CN
- China
- Prior art keywords
- pile
- rotary
- drilling
- hole
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 49
- 238000010276 construction Methods 0.000 claims abstract description 82
- 239000004567 concrete Substances 0.000 claims abstract description 16
- 230000002787 reinforcement Effects 0.000 claims abstract description 15
- 239000013049 sediment Substances 0.000 claims abstract description 7
- 238000004140 cleaning Methods 0.000 claims abstract description 4
- 238000005553 drilling Methods 0.000 claims description 52
- 238000001746 injection moulding Methods 0.000 claims description 4
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 claims description 3
- 239000000843 powder Substances 0.000 claims description 3
- 239000002689 soil Substances 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 claims 1
- 239000010959 steel Substances 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 abstract description 11
- 239000011435 rock Substances 0.000 abstract description 8
- 238000005422 blasting Methods 0.000 abstract description 6
- 230000008569 process Effects 0.000 description 18
- 238000010586 diagram Methods 0.000 description 9
- 239000003973 paint Substances 0.000 description 4
- 230000002265 prevention Effects 0.000 description 4
- 239000004593 Epoxy Substances 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- HCHKCACWOHOZIP-UHFFFAOYSA-N Zinc Chemical compound [Zn] HCHKCACWOHOZIP-UHFFFAOYSA-N 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 239000006185 dispersion Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000004880 explosion Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- 239000011490 mineral wool Substances 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 229920006389 polyphenyl polymer Polymers 0.000 description 2
- 229910052725 zinc Inorganic materials 0.000 description 2
- 239000011701 zinc Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000013016 damping Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 239000008187 granular material Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000010445 mica Substances 0.000 description 1
- 229910052618 mica group Inorganic materials 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000011376 self-consolidating concrete Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B3/00—Rotary drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/001—Drilling a non circular hole
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- Physics & Mathematics (AREA)
- Geochemistry & Mineralogy (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Earth Drilling (AREA)
Abstract
The invention discloses a rapid hole forming method of an anti-slide pile rotary excavating machine, which integrates high efficiency and safety, and comprises the following steps: A. paying off and positioning the anti-slide pile hole or lofting a field; B. the rotary pile digging machine digs holes or mechanically forms holes by rotary digging piles according to the serial numbers and positions of pile cores; C. cleaning the excessive earthwork on the side wall and removing the sediment at the bottom of the pile; D. putting down a reinforcement cage; E. and pouring concrete to form the anti-slide pile. The invention solves the problems that the efficiency of crushing and rock entering of the manual hole digging pile is low, blasting excavation is not allowed under the complex environment, and the hole forming construction difficulty is very high, and on one hand, mechanical hole forming can be carried out under the condition of not using a pile casing and a retaining wall, so that the construction cost is greatly reduced; on the other hand, the construction of the slide-resistant pile is quickly finished in a limited time from the self-stability capability support of the hole wall after the mechanical hole forming until the concrete pouring forming, so that the construction safety and quality are ensured.
Description
Technical Field
The invention relates to a hole forming construction method for an anti-slide pile, in particular to a high-efficiency and safety integrated rapid hole forming method for an anti-slide pile rotary excavating machine, and belongs to the technical field of side slope support structure construction.
Background
The non-circular anti-slide pile is generally formed by manually digging holes. The construction operation process of the manual hole digging pile is simple, the construction is convenient, and the construction quality is easy to guarantee. But the underground operation condition of the hole digging pile is poor, the environment is severe, the labor intensity is high, the construction speed of a single pile is slow, and the potential safety hazard in construction is also very prominent; constructors need to adopt underground operation, the personal safety problem is very severe, many unsafe factors and hidden dangers exist, and the construction safety management difficulty is high; and the resistance of the landslide body is weakened in the pile well excavation process, and particularly when a hard and stable stratum below a sliding bed is excavated, blasting is usually needed, the stratum is disturbed greatly, the instability and the construction risk are aggravated, and the safety of constructors and surrounding building structures is difficult to guarantee.
The mechanical pore-forming cast-in-place pile has high construction efficiency, less operators, less danger and little influence by weather, and the mechanical pore-forming is increased compared with the concrete required by the manual hole-forming pile (because of the increase of hole collapse and filling coefficient).
Therefore, the key point for solving the technical problems is to develop a rapid hole forming method of the anti-slide pile rotary excavating machinery, which has the advantages of strong practicability and high working reliability, and integrates high efficiency and safety.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention provides the pile hole forming device which has the advantages of high hole forming speed, high positioning precision, convenience in operation, low safety risk and wide applicability, can greatly improve the construction efficiency, quickens the construction progress, is accurate in positioning, solves the problems of slow construction progress and high risk of the manual hole digging pile, and has better market application prospect.
The invention also aims to solve the problems that the efficiency of crushing and entering the rock of the manual hole digging pile is low, blasting excavation is not allowed under the complex environment, and the hole forming construction difficulty is very high. Aiming at part of stratums with relatively good and stable geological conditions, the mechanical rapid hole forming construction method disclosed by the invention can be used for mechanically forming holes without using a pile casing and a retaining wall, so that the construction cost is greatly reduced; on the other hand, by means of the rapid construction characteristic of the method, the construction of the slide-resistant pile can be rapidly completed within the limited time from the self-stability capability support of the hole wall after the mechanical hole forming until the concrete pouring forming, and the construction safety and quality are ensured.
The invention further aims to provide the rectangular anti-sliding pile mechanical rapid hole forming construction method which is low in construction cost, good in hole forming quality and high in precision, solves the problems that manual hole digging piles are low in rock entering efficiency due to breakage, explosion and excavation are not allowed under the complex environment, and hole forming construction difficulty is high, only needs to adopt conventional rotary pile machine mechanical equipment, does not increase the construction cost excessively, and can reduce the labor intensity of operators to the maximum extent.
The invention also aims to ensure the parameters such as verticality, flatness and the like in the rectangular pile hole excavation process, ensure good hole forming quality and good construction safety, greatly improve the construction efficiency, provide a convenient and quick method for rock stratum construction, solve the problems of poor hole forming quality, low construction efficiency and difficult control of safety risk in the traditional manual hole digging pile process, and be suitable for popularization and application.
The invention also aims to strictly control unsafe factors caused by manual hole digging in the construction process, simultaneously promote the application range of mechanized construction, improve the working efficiency and reduce the construction cost; meanwhile, the working environment of operators is improved, the potential safety hazard of manual downhole operation is reduced, and the personal safety of the operators is ensured.
In order to solve the problems and achieve the purpose, the invention provides a rapid hole forming method of an anti-slide pile rotary excavating machine, which integrates high efficiency and safety, and is realized by adopting the following design structure and the following technical scheme:
a rapid hole forming method of an anti-slide pile rotary excavating machine integrating high efficiency and safety comprises the following steps:
A. paying off and positioning the anti-slide pile hole or lofting a field; wherein, the step when slide-resistant pile hole unwrapping wire location does:
a.1, positioning the contour line of the anti-slide pile hole, and determining a maximum rectangular line in the contour line of the anti-slide pile hole, wherein the determination of the maximum rectangular line is to place four end points of the rectangular line on the contour line of the anti-slide pile hole as much as possible by adopting a method of inscribing with the contour line of the anti-slide pile hole;
a.2, determining the diameter D of the drill bit of the rotary excavating pile machine according to the determined length D of the short side of the rectangular line1Diameter d of drill bit of rotary pile digging machine1The length D of the short side of the rectangular line is not less than, and finally, the drill bit of the rotary excavating pile machine meeting the requirements is determined by combining with the specifications of drill bits commonly used in the market;
a.3, determining the position of a first-time drilled pile core according to the short edge of one side of the rectangular wire;
a.4, determining the position of the pile core drilled for the second time according to the short edge of the other side of the rectangular line;
in A.3 and A.4, determining the position of a drill core of the rotary drilling pile machine in the direction of the long side of the rectangular line, and adopting a method of two tangent points and one radius, wherein the method of the two tangent points and the one radius is characterized in that two end points of one short side of the rectangular line are taken as the two tangent points, and a circle is made according to the radius of a drill bit of the rotary drilling pile machine, so that the center of the circle falls on the center line of the short side in the rectangular line, and the center of the circle is the position of the drill core of the rotary drilling pile machine;
a.5, determining the residual drilling-down times and the diameter of the drill bit of the rotary pile driver according to the length D of the short side of the rectangular line and the diameter D1 of the drill bit, wherein in A.5, the method for determining the residual drilling-down times of the rotary pile driver comprises the following steps:
a.5.1 the length L of the long side of the rectangular wire is not more thanThe drilling times of the rotary drilling pile machine are determined to be twice;
a.5.2 the length L of the long side of the rectangular wire is larger thanThe third time of rotary digging pile machine down drilling core position is located on the short edge central line, specifically the central point position of the short edge central line of the non-digging area;
a.5.3, stopping drilling if the distance between the pile cores drilled for the first time and the third time is not more than 0.8D; if the distance between the first time of pile core dropping and the third time of pile core dropping is larger than 0.8D, determining the center position of the distance between the first time of pile core dropping and the third time of pile core dropping as the position of the pile core dropping of the fourth time of rotary excavating pile machine until the distance between the pile cores dropping twice adjacent to each other is not larger than 0.8D;
a.5.4 referring to the step A.5.3, if the distance between the pile cores drilled in the second time and the third time is not more than 0.8D, stopping drilling; if the distance between the pile cores drilled for the second time and the third time is larger than 0.8D, determining the central position of the distance between the pile cores drilled for the second time and the third time as the position of the pile core drilled for the fifth time by the rotary drilling pile machine until the distance between the pile cores drilled for two adjacent times is not larger than 0.8D;
a.6 paying off and positioning the drilling pile core position of the residual rotary drilling pile machine according to the drilling times of the rotary drilling pile machine;
B. the rotary excavating pile machine excavates holes according to the serial number and the position of a pile core;
C. cleaning the excessive earthwork on the side wall and removing the sediment at the bottom of the pile;
D. putting down a reinforcement cage;
E. and pouring concrete to form the anti-slide pile.
As another preferable technical solution of the invention, in step a.5.3 and step a.5.4, the diameter of the drill bit of the rotary pile digging machine is determined by the shortest distance of the trenchless area along the long side direction of the rectangular line, and when the shortest distance exceeds the length D of the short side of the rectangular line, the diameter of the drill bit is required to be not less than the length of the short side of the rectangular line; when the shortest distance is less than or equal to the length D of the short side of the rectangular wire, the diameter of the drill bit is required to be equal to or slightly less than the length of the short side of the rectangular wire.
As the preferable technical scheme of the invention, in the step B, a dry hole operation mechanical hole forming construction method is adopted for hole digging of the rotary pile digging machine; in the step C, removing redundant earthwork on the side wall and pile bottom sediment by adopting soil removing equipment or rotary pile digging equipment; and D, hoisting the reinforcement cage into the pile hole by using a truck crane after one-step processing and forming.
In the step D and the step E, an injection molding layer, an anti-rust layer and a warning layer are sequentially sprayed on the outer surfaces of the reinforcement cage and the formed anti-slide pile from inside to outside, and fluorescent powder is coated on the warning layer;
the mechanical hole forming steps of the rotary excavating pile machine are as follows:
b.1 moving the rotary excavating pile driver to a first-time pile core drilling position, and drilling to a designed pile bottom elevation;
b.2 moving the rotary excavating pile driver to a second-time pile core drilling position, and drilling to a designed pile bottom elevation;
and B.3, replacing the drill bit, moving the rotary drilling pile machine to the position of the residual drilled pile core, and drilling to the designed pile bottom elevation.
Compared with the prior art, the invention has the following beneficial effects:
1. the method solves the problems that the efficiency of crushing and rock entering of the manual hole digging pile is low, blasting excavation is not allowed under the complex environment, and the hole forming construction difficulty is very high, adopts the conventional rotary digging mechanical equipment, does not increase the construction cost, and has the advantages of simple operation, safe construction, high speed and high efficiency, meanwhile, aiming at part of stratums with relatively good and stable geological conditions, the mechanical quick hole forming construction method disclosed by the invention is used, on one hand, mechanical hole forming can be carried out under the condition of not using a pile casing and a retaining wall, and the construction cost is greatly reduced; on the other hand, by means of the rapid construction characteristic of the method, the construction of the slide-resistant pile can be rapidly completed within the limited time from the self-stability capability support of the hole wall after the mechanical hole forming to the time before the concrete pouring and forming, so that the construction safety and quality are ensured;
2. the invention can reduce the reinforced concrete dado of the manual hole digging pile, the cost increase is less, basically in the state of keeping level; secondly, the mechanical hole forming of the slide-resistant pile can greatly reduce the construction risk compared with manual hole digging, such as sudden conditions of hole collapse, electric shock, gas explosion and the like in the manual hole digging process; in addition, the mechanical hole forming of the slide-resistant pile greatly improves the construction efficiency, accelerates the construction progress and solves the problems of slow construction progress and high risk of manual hole digging piles;
3. the construction method solves the problems that the efficiency of crushing and rock entering of the manual hole digging pile is low, blasting excavation is not allowed under the complex environment, and the hole forming construction difficulty is very high, only the conventional rotary pile digging machine mechanical equipment is needed, the construction cost is not excessively increased, and the construction method has the advantages of high hole forming speed, high positioning precision, convenience in operation, low safety risk, wide applicability and the like;
4. the method provided by the invention has the advantages that the construction cost is low, the hole forming quality is good, the precision is high, the problems that the efficiency of breaking and entering the rock of the manual hole digging pile is low, blasting excavation is not allowed under the complex environment, and the hole forming construction difficulty is very high are solved, and the labor intensity of operators can be reduced to the maximum extent while the construction cost is not excessively increased only by adopting conventional rotary excavating mechanical equipment;
5. the method can ensure the parameters such as verticality, flatness and the like in the rectangular pile hole excavation process, has good hole forming quality and good construction safety, also greatly improves the construction efficiency, provides a convenient and quick method for rock stratum construction, solves the problems of poor hole forming quality, low construction efficiency and difficult control of safety risk in the traditional manual hole digging pile process, and is suitable for popularization and use;
6. the invention strictly controls unsafe factors caused by manual hole digging in the construction process, simultaneously promotes the application range of mechanized construction, improves the working efficiency and reduces the construction cost; meanwhile, the working environment of operators is improved, the potential safety hazard of manual downhole operation is reduced, and the personal safety of the operators is ensured;
7. according to the invention, square hole forming can be realized through the rotary digging pile machine, the problem that the cast-in-place square pile in the civil engineering field can only be formed through manual hole forming is solved, the purposes of quickly forming holes and shortening the construction period are realized, quick construction can be realized under the working conditions of arranging anti-slide piles, building engineering pile foundation foundations, abutment pile foundations and the like on high-risk side slopes of the roadbed, the engineering construction period is greatly shortened, the cost is reduced, the labor intensity of workers is reduced, the operation risk of manually digging the square hole is avoided, the success quality is improved, and the personal safety is also ensured;
8. the invention has the characteristics of simple structure, convenient operation, construction quality and safety guarantee, labor saving, cost saving, great improvement on construction efficiency and the like, and compared with the conventional manual excavation construction method, the construction method is more convenient, more economical, safer and more quality and quantity guarantee;
9. the self-luminous fluorescent material is coated on the exterior of the anti-slide pile formed by the reinforcement cage, so that the positions of all components can be clearly marked in night or in dark rooms and underground construction environments, and the safety prompt effect can be effectively realized, thereby ensuring the construction safety in the construction process to the maximum extent.
Drawings
Embodiments of the invention are described in further detail below with reference to the attached drawing figures, wherein:
FIG. 1 is one of the schematic views of the first core position of the drilled pile of the present invention;
FIG. 2 is one of the schematic views of the second core position of the drilled pile of the present invention;
FIG. 3 is one of schematic positions of an anti-slide pile hole and a rotary-digging pile core of the hole forming process of the present invention;
FIG. 4 is one of schematic diagrams of a first hole forming of a rotary excavating pile according to the hole forming process of the present invention;
FIG. 5 is one of schematic diagrams of a second hole forming of a rotary excavating pile according to the hole forming process of the present invention;
FIG. 6 is one of schematic diagrams of third hole forming of a rotary excavating pile according to the hole forming process of the present invention;
FIG. 7 is one of the pile forming diagrams of the downward reinforcement and the poured concrete of the hole forming process of the present invention;
FIG. 8 is a second schematic view of the first drilling position of the pile core according to the construction method of the present invention;
FIG. 9 is a second schematic view of the second drilling position of the pile core according to the construction method of the present invention;
FIG. 10 is a second schematic view of the third core-setting position of the construction method of the present invention;
FIG. 11 is a second schematic diagram of a first hole forming of the rotary excavating pile according to the construction method of the present invention;
FIG. 12 is a second schematic diagram of second hole forming of the rotary excavation pile according to the construction method of the present invention;
FIG. 13 is a second schematic diagram of third hole forming of the rotary excavating pile according to the construction method of the present invention;
FIG. 14 is a second schematic diagram of the pile formation of the downward reinforcement and the poured concrete according to the construction method of the present invention;
FIG. 15 is a schematic block diagram of the overall construction process of the present invention;
wherein, the reference numbers in the figures: in the figure: 1-a rectangular line; 3-short edge end point; 4-short side center line; 5, setting the position of the pile core for the first time; 6-the position of the pile core is drilled in the second time; 7-the position of the pile core is drilled in the third time; 8-a reinforcement cage; 9-concrete, 10-excess earthwork of the side wall.
Detailed Description
In order to make the technical means, the inventive features, the achievement purposes and the effects of the present invention easy to understand, the technical solutions of the present invention are further described in detail with reference to the drawings and the detailed description below, and it is to be noted that the embodiments and the features in the embodiments in the present application can be combined with each other without conflict. The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings.
Example 1
The landslide prevention and control project is taken as an example for explanation, a side slope supporting structure part of the landslide prevention and control project is supported by a pile-plate type retaining wall, and a rectangular anti-slide pile with the pile foundation size of 1.5m multiplied by 2.4m is adopted. The pore-forming process is shown in fig. 1-7 and generally comprises the following steps:
A. paying off and positioning the anti-slide pile hole;
a.1, the contour line of the slide-resistant pile hole is rectangular, namely the contour line of the slide-resistant pile hole is the largest rectangular line, and the size of the slide-resistant pile hole rectangular line 1 is determined to be 1.5m multiplied by 2.4 m;
a.2 according to the length of the short side of the rectangular line D ═ 1.5m, the diameter of a hole formed by a medium-sized or large-sized rotary excavating pile machine in the market is 0.8-2.5 m, and the diameter of a drill bit of the rotary excavating pile machine is determined to be D1=1.8m;
A.3, determining the position of a first-time drilling pile core along the short edge of one side of a rectangular line, and as shown in FIG. 1, adopting a method of two tangent points and one radius, wherein the method of two tangent points and one radius is to use two short edge end points 3 of the short edge of the rectangular line as two tangent points and draw a circle with the radius of a drill bit of the rotary pile driver being 0.9m, so that the circle center is located on a short edge central line 4 in the rectangular line, and the circle center is the position 5 of the first-time drilling pile core;
a.4, taking two short-side end points 3 of the other short side of the rectangular line as tangent points, and determining the position 6 of the secondary drilled pile core according to a method of two tangent points and a radius as shown in FIG. 2;
a.5 the length L of the long side of the rectangular wire is 2400mm which is larger thanThe calculated length of 2343mm, therefore, the position of the pile core drilled by the rotary excavating pile machine for the third time is located on the short-edge center line 4, as shown in fig. 3, and specifically located at the center point of the short-edge center line 4 of the trenchless area; the shortest distance of the trenchless area along the long side direction of the rectangular line is smaller than the length of the short side of the rectangular line, so the diameter of the third drill bit is 1500 mm; calculating the distance between the pile cores drilled for the first time and the third time to be 702mm, and the distance between the pile cores drilled for the second time and the third time to be 702mm, wherein the distance is less than 0.8D to 1200mm, so that the drilling times are determined to be three times;
B. the rotary pile digging machine is based on the serial number of the pile core;
performing hole-drilling by multiple times according to the serial number of the pile core, the position 5 of the first drilled pile core, the position 6 of the second drilled pile core and the position 7 of the third drilled pile core, as shown in figures 4-6;
C. adopting rotary excavating pile driver equipment to clean redundant earthwork on the side wall and remove sediment at the bottom of the pile;
D. the reinforcement cage 8 is formed by one-step processing and then is hoisted into the pile hole by a truck crane;
Example 2
The invention is explained by taking landslide prevention and control engineering as an example, a side slope supporting structure part of the landslide prevention and control engineering is supported by a pile-plate type retaining wall, and a rectangular slide-resistant pile with the pile foundation size of 1.5m multiplied by 2.4m is adopted. The construction method is shown in figures 8-14 and generally comprises the following steps:
A. lofting a field;
a.1, determining the contour line 1 of the hole of the slide-resistant pile by spraying a dust line, wherein the size of the contour line is 1.5m multiplied by 2.4 m;
a.2, according to the condition that the length of the short side of the contour line of the hole of the slide-resistant pile is 1.5m, the diameter of a drill hole of a medium-sized or large-sized rotary drilling rig in the market is 0.8-2.5 m, and the diameter of a drill bit of the rotary drilling pile machine is determined to be 1.8 m;
a.3, determining a first-time drilling-down pile core position 5 according to the short edge at one side of the anti-slide pile hole contour line, and as shown in FIG. 8, adopting a method of two tangent points and one radius, taking the end points 3 of the two short edges at one side of the anti-slide pile hole contour line as the two tangent points, and taking the radius of a drill bit of the rotary pile driver as 0.9m as a circle, so that the circle center is located on a short edge central line 4 perpendicular to the short edge in the anti-slide pile hole contour line, and the circle center is the first-time drilling-down pile core position 5;
a.4, determining the position 6 of the secondary drilled pile core according to the short side at the other side of the contour line of the slide-resistant pile hole, and determining the position 6 of the secondary drilled pile core according to a method of two tangent points and one radius by taking the end points 3 of the two short sides at the other side of the contour line of the slide-resistant pile hole as the circle center as shown in FIG. 9;
a.5, determining the rotary excavating pile machine with the drill bit diameter of 1.5m along the length of the long edge of the contour line of the slide-resistant pile hole and the residual unearthed area, wherein the residual drilling times are one time;
a.6, taking the center point of the contour line of the slide-resistant pile hole as the position of the pile core drilled in the last time, and positioning and setting out as shown in figure 10;
B. mechanically forming holes by adopting a rotary digging pile dry hole operation construction method;
b.1, moving the rotary excavating pile driver with a drill bit of 1.8m to a first-time pile core drilling position 5, and drilling to the designed pile bottom elevation as shown in figure 11;
b.2, moving the rotary excavating pile driver with a drill bit of 1.8m to a second-time pile core drilling position 6, and drilling to the designed pile bottom elevation as shown in figure 12;
b.3, replacing a drill bit with 1.5m, moving the rotary pile-digging machine to the position of the last lower drill pile core, and drilling to the designed pile bottom elevation as shown in figure 13;
C. cleaning the redundant earthwork 10 on the side wall by using rotary excavating pile machine equipment with a drill bit of 1.5m or 1.2m, and removing the sediment at the bottom of the pile;
D. after the reinforcement cage 8 is formed by one-step processing, the reinforcement cage 8 is hoisted into the pile hole by using a truck crane;
E. the concrete 9 is poured to form a non-circular anti-skid pile as shown in fig. 14.
In summary, in the working process of the above embodiments 1 and 2, in the steps D and E, the injection molding layer, the rust-proof layer, and the warning layer are sequentially sprayed on the outer surfaces of the reinforcement cage and the formed anti-slide pile from inside to outside, and the fluorescent powder is coated on the warning layer.
Specifically, a high-molecular wear-resistant material is injected on the injection molding layer; the anti-rust layer comprises epoxy zinc-rich primer, chlorinated rubber finish paint and epoxy mica iron intermediate paint positioned between the epoxy zinc-rich primer and the chlorinated rubber finish paint; the warning layer is a yellow or black reflective warning tape or a reflective color film or reflective paint.
The concrete is self-dense concrete or high-strength light polyphenyl granule concrete; the self-compacting concrete or the high-strength light polyphenyl particle concrete is internally provided with a cement-based heat-insulating and noise-eliminating layer, a metal plate layer, a rock wool plate layer, a damping layer, a waterproof layer and a stress dispersion layer, wherein the cement-based heat-insulating and noise-eliminating layer, the metal plate layer, the rock wool plate layer, the waterproof layer and the stress dispersion layer are sequentially stacked or mixed together.
Finally, it should be noted that the above-mentioned embodiments are only preferred embodiments of the present invention, and are not intended to limit the present invention in other forms, and any person skilled in the art may change or modify the technical content disclosed above into equivalent embodiments with equivalent changes. However, any simple modification, equivalent change and modification of the above embodiments according to the technical essence of the present invention are within the protection scope of the technical solution of the present invention.
Claims (4)
1. The utility model provides a collection high efficiency and safe in quick pore-forming method of friction pile rotary excavating machinery in an organic whole which characterized in that includes following step:
A. paying off and positioning the anti-slide pile hole or lofting a field; wherein, the step when slide-resistant pile hole unwrapping wire location does:
a.1, positioning the contour line of the anti-slide pile hole, and determining a maximum rectangular line in the contour line of the anti-slide pile hole, wherein the determination of the maximum rectangular line is to place four end points of the rectangular line on the contour line of the anti-slide pile hole as much as possible by adopting a method of inscribing with the contour line of the anti-slide pile hole;
a.2, determining the diameter D of the drill bit of the rotary excavating pile machine according to the determined length D of the short side of the rectangular line1Diameter d of drill bit of rotary pile digging machine1The length D of the short side of the rectangular line is not less than, and finally, the drill bit of the rotary excavating pile machine meeting the requirements is determined by combining with the specifications of drill bits commonly used in the market;
a.3, determining the position of a first-time drilled pile core according to the short edge of one side of the rectangular wire;
a.4, determining the position of the pile core drilled for the second time according to the short edge of the other side of the rectangular line;
in A.3 and A.4, determining the position of a drill core of the rotary drilling pile machine by adopting a method of two points of tangency and one radius, wherein the method of the two points of tangency and the one radius is characterized by taking two end points of one short side of a rectangular line as the two points of tangency, and making a circle according to the radius of a drill bit of the rotary drilling pile machine, so that the center of the circle falls on the center line of the short side in the rectangular line, and the center of the circle is the position of the drill core of the rotary drilling pile machine;
a.5, determining the residual drilling-down times and the diameter of the drill bit of the rotary pile driver according to the length D of the short side of the rectangular line and the diameter D1 of the drill bit, wherein in A.5, the method for determining the residual drilling-down times of the rotary pile driver comprises the following steps:
a.5.1 the length L of the long side of the rectangular wire is not more thanThe drilling times of the rotary drilling pile machine are determined to be twice;
a.5.2 the length L of the long side of the rectangular wire is larger thanThe third time of rotary digging pile machine down drilling core position is located on the short edge central line, specifically the central point position of the short edge central line of the non-digging area;
a.5.3, stopping drilling if the distance between the pile cores drilled for the first time and the third time is not more than 0.8D; if the distance between the first time of pile core dropping and the third time of pile core dropping is larger than 0.8D, determining the center position of the distance between the first time of pile core dropping and the third time of pile core dropping as the position of the pile core dropping of the fourth time of rotary excavating pile machine until the distance between the pile cores dropping twice adjacent to each other is not larger than 0.8D;
a.5.4 referring to the step A.5.3, if the distance between the pile cores drilled in the second time and the third time is not more than 0.8D, stopping drilling; if the distance between the pile cores drilled for the second time and the third time is larger than 0.8D, determining the central position of the distance between the pile cores drilled for the second time and the third time as the position of the pile core drilled for the fifth time by the rotary drilling pile machine until the distance between the pile cores drilled for two adjacent times is not larger than 0.8D;
a.6 paying off and positioning the drilling pile core position of the residual rotary drilling pile machine according to the drilling times of the rotary drilling pile machine;
B. the rotary excavating pile machine excavates holes according to the serial number and the position of a pile core;
C. cleaning the excessive earthwork on the side wall and removing the sediment at the bottom of the pile;
D. putting down a reinforcement cage;
E. and pouring concrete to form the anti-slide pile.
2. The anti-slide pile rotary excavating mechanical rapid hole forming method integrating high efficiency and safety into a whole according to claim 1, characterized in that in the step A.5.3 and the step A.5.4, the diameter of a drill bit of the rotary excavating pile machine is determined by the shortest distance of an unearthed area along the long side direction of a rectangular line, and when the shortest distance exceeds the length D of the short side of the rectangular line, the diameter of the drill bit is required to be not less than the length of the short side of the rectangular line; when the shortest distance is less than or equal to the length D of the short side of the rectangular wire, the diameter of the drill bit is required to be equal to or slightly less than the length of the short side of the rectangular wire.
3. The anti-slide pile rotary excavating mechanical rapid hole forming method integrating high efficiency and safety as claimed in claim 1, wherein in step B, a dry hole operation mechanical hole forming construction method is adopted for hole digging of the rotary excavating pile machine; in the step C, removing redundant earthwork on the side wall and pile bottom sediment by adopting soil removing equipment or rotary pile digging equipment; and D, hoisting the reinforcement cage into the pile hole by using a truck crane after one-step processing and forming.
4. The anti-slide pile rotary excavating mechanical rapid hole forming method integrating high efficiency and safety into a whole according to claim 1, characterized in that in the step D and the step E, an injection molding layer, an anti-rust layer and a warning layer are sequentially sprayed on the outer surfaces of the steel reinforcement cage and the formed anti-slide pile from inside to outside, and fluorescent powder is coated on the warning layer;
the mechanical hole forming steps of the rotary excavating pile machine are as follows:
b.1 moving the rotary excavating pile driver to a first-time pile core drilling position, and drilling to a designed pile bottom elevation;
b.2 moving the rotary excavating pile driver to a second-time pile core drilling position, and drilling to a designed pile bottom elevation;
and B.3, replacing the drill bit, moving the rotary drilling pile machine to the position of the residual drilled pile core, and drilling to the designed pile bottom elevation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911078962.8A CN110820729B (en) | 2019-11-07 | 2019-11-07 | Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911078962.8A CN110820729B (en) | 2019-11-07 | 2019-11-07 | Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110820729A CN110820729A (en) | 2020-02-21 |
CN110820729B true CN110820729B (en) | 2021-04-16 |
Family
ID=69553047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911078962.8A Active CN110820729B (en) | 2019-11-07 | 2019-11-07 | Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110820729B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112796307A (en) * | 2021-01-04 | 2021-05-14 | 成都欣皓地基基础工程有限责任公司 | Square pile construction method of rotary drilling rig |
WO2022095548A1 (en) | 2020-11-04 | 2022-05-12 | 成都欣皓地基基础工程有限责任公司 | Square pile construction method and device for rotary drilling rig |
CN114555888B (en) * | 2021-01-04 | 2023-01-31 | 成都欣皓地基基础工程有限责任公司 | Square pile construction method and equipment for rotary drilling rig |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587840A (en) * | 2017-09-26 | 2018-01-16 | 中铁大桥局集团第五工程有限公司 | A kind of rectangle pile foundation drilling construction method |
CN107905236A (en) * | 2017-11-10 | 2018-04-13 | 中铁隧道集团处有限公司 | The construction method of friction pile churning driven fast pore-creating and concrete placings |
CN108678661A (en) * | 2018-03-22 | 2018-10-19 | 中交路桥北方工程有限公司 | Rectangular friction pile forming hole method and the rectangular drill bit of pore-forming |
CN109630015A (en) * | 2018-11-26 | 2019-04-16 | 中铁二十局集团第二工程有限公司 | A kind of friction pile mechanical hole building method |
CN109681116A (en) * | 2019-01-31 | 2019-04-26 | 四川省交通运输厅交通勘察设计研究院 | A kind of square pile rotary drilling device and its rotary digging method for realizing rectangular pore-forming |
CN110374091A (en) * | 2019-07-09 | 2019-10-25 | 云南建投基础工程有限责任公司 | A kind of rectangle friction pile mechanical hole building construction method |
-
2019
- 2019-11-07 CN CN201911078962.8A patent/CN110820729B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587840A (en) * | 2017-09-26 | 2018-01-16 | 中铁大桥局集团第五工程有限公司 | A kind of rectangle pile foundation drilling construction method |
CN107905236A (en) * | 2017-11-10 | 2018-04-13 | 中铁隧道集团处有限公司 | The construction method of friction pile churning driven fast pore-creating and concrete placings |
CN108678661A (en) * | 2018-03-22 | 2018-10-19 | 中交路桥北方工程有限公司 | Rectangular friction pile forming hole method and the rectangular drill bit of pore-forming |
CN109630015A (en) * | 2018-11-26 | 2019-04-16 | 中铁二十局集团第二工程有限公司 | A kind of friction pile mechanical hole building method |
CN109681116A (en) * | 2019-01-31 | 2019-04-26 | 四川省交通运输厅交通勘察设计研究院 | A kind of square pile rotary drilling device and its rotary digging method for realizing rectangular pore-forming |
CN110374091A (en) * | 2019-07-09 | 2019-10-25 | 云南建投基础工程有限责任公司 | A kind of rectangle friction pile mechanical hole building construction method |
Also Published As
Publication number | Publication date |
---|---|
CN110820729A (en) | 2020-02-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110820729B (en) | Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery | |
CN112554177A (en) | Construction method of ultra-long small-diameter cast-in-situ bored pile | |
CN103835661B (en) | A kind of local excavation pre support mine shaft rising boring technique | |
CN103835723B (en) | Pit shaft passes through the comprehensive pre-administering method on stratum, goaf | |
CN104631438B (en) | Long auger guncreting uplift pile construction method | |
CN203924085U (en) | A kind of caisson structure that is applied to collecting well | |
CN106988302A (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
CN106149684A (en) | A kind of full-sleeve long screw auger drilling deposited pile construction method | |
CN110374091B (en) | Mechanical pore-forming construction method for rectangular slide-resistant pile | |
CN103015429A (en) | Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method | |
CN107035376A (en) | One kind common law in huge thick bedrock aquifer digs shaft construction method | |
CN106437796A (en) | Rock stratum shield tunnel end reinforcing structure and reinforcing method | |
CN104863183B (en) | Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction | |
CN106677166A (en) | Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode | |
CN116446385A (en) | A karst non-filled cast-in-situ pile structure and its construction method | |
CN104947664A (en) | Thick stone sea-filling layer prestressing force high-strength concrete square pile construction method | |
CN112502615B (en) | Construction method of deep large-diameter gas extraction well | |
CN107605488A (en) | A kind of bored shaft and its filling reinforcement means that suspends | |
CN214832582U (en) | Underground continuous wall is at punching lamination construction pre-reinforcement structure | |
CN103527202A (en) | Method for constructing tunnel under complicated geological conditions | |
Mangushev et al. | Modern technologies of foundation building in the conditions of weak soils of St. Petersburg | |
CN110820733B (en) | Improved mechanical rapid hole forming construction method for simple rectangular slide-resistant pile | |
CN110512594A (en) | The simple and easy method of churning driven opportunity cavity pore-forming | |
CN114251098B (en) | A shaft construction method | |
CN116756940A (en) | Push pipe engineering design and construction method based on stress performances of different geological environments |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |