[go: up one dir, main page]

CN110745714B - Self-lifting installation method of hoisting tower system - Google Patents

Self-lifting installation method of hoisting tower system Download PDF

Info

Publication number
CN110745714B
CN110745714B CN201910964825.8A CN201910964825A CN110745714B CN 110745714 B CN110745714 B CN 110745714B CN 201910964825 A CN201910964825 A CN 201910964825A CN 110745714 B CN110745714 B CN 110745714B
Authority
CN
China
Prior art keywords
lifting
self
hoisting
frame
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910964825.8A
Other languages
Chinese (zh)
Other versions
CN110745714A (en
Inventor
黄书海
赵伟
龚兴生
张胜林
欧阳斌
刘贤
孙全武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Original Assignee
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd filed Critical GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority to CN201910964825.8A priority Critical patent/CN110745714B/en
Publication of CN110745714A publication Critical patent/CN110745714A/en
Application granted granted Critical
Publication of CN110745714B publication Critical patent/CN110745714B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/34Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a self-lifting installation method of a hoisting tower system, wherein the hoisting tower system is composed of 4 hoisting towers with the same structure, each hoisting tower is formed by overlapping and accumulating a plurality of segments, the tops of 2 hoisting towers which are longitudinally arranged are connected through an electric hoist track beam, and the tops of 2 hoisting towers which are transversely arranged are connected through a hoisting beam. The method can solve the problems of narrow field and high hoisting height, reduces the problem of labor consumption and construction risk, and can realize a series of operation work such as installation, removal, hoisting and the like of the tower frame only by a small amount of manual cooperation when the hoisting tower frame is built by the installation method, thereby greatly improving the working efficiency of the hoisting work on the one hand; on the other hand, the construction risk of constructors is greatly reduced, and meanwhile, the tower system can be used in a turnover mode, so that the construction marginal cost is greatly reduced.

Description

Self-lifting installation method of hoisting tower system
Technical Field
The invention relates to a self-lifting installation method of a hoisting tower system, and belongs to the technical field of hoisting tower installation.
Background
In engineering construction, fixed point hoisting of a main engineering component is often involved, and a mode of erecting a support and matching with a large-tonnage hoisting crane is often adopted in the past construction of the process, but the mode has two defects: on one hand, the erection and the disassembly of the bracket need to consume more labor, the occupied construction working area is larger, and the construction period is longer; on the other hand, when the height of the support to be erected is very high (exceeding 30 m), the crane is often greatly limited in lifting, and even if a tower crane system is adopted, if a tower crane cannot be used as an attachment facility, the maximum lifting height can be controlled within 40 m; moreover, when the support is erected and dismantled in a mode of manually matching mechanical equipment, not only can longer time be consumed, but also construction safety risks can be increased, and even the situation that the support erection, dismantling and construction hoisting cannot be solved by the traditional process occurs.
Disclosure of Invention
The invention aims to provide a self-lifting installation method of a lifting tower system. The method can solve the problems of narrow field and high hoisting height, reduces the problem of labor consumption and construction risk, and can realize a series of operation work such as installation, removal, hoisting and the like of the tower frame only by a small amount of manual cooperation when the hoisting tower frame is built by the installation method, thereby greatly improving the working efficiency of the hoisting work on the one hand; on the other hand, the construction risk of constructors is greatly reduced, and meanwhile, the tower system can be used in a turnover mode, so that the construction marginal cost is greatly reduced.
The technical scheme of the invention is as follows: a self-lifting installation method of a lifting tower system comprises the steps that part frame bodies of 4 lifting towers are firstly built on the ground, a self-lifting outer sleeve frame is sleeved on the outer side of each part of frame body, the tops of 2 longitudinally arranged self-lifting outer sleeve frames are connected through an electric hoist track beam, and the tops of 2 transversely arranged self-lifting outer sleeve frames are connected through a lifting cross beam; the electric hoist on the electric hoist track beam lifts the segment upwards and then moves transversely and fixes the segment at the top of the hoisting tower frame, then the self-lifting outer sleeve frame climbs upwards along the hoisting tower frame, and the segment is lifted and fixed repeatedly again until the hoisting tower frame is built and is completed to the required height.
In the self-lifting installation method of the hoisting tower system, the installation method comprises the following steps:
A. fixing the bottom segment of the segments on the ground, and fixedly stacking a standard middle segment of the plurality of segments on the bottom segment in an overlapping manner;
B. installing a lifting jack on the self-lifting outer sleeve frame, lifting and sleeving the self-lifting outer sleeve frame outside the installed standard middle section, and fixedly connecting the self-lifting outer sleeve frame with the standard middle section through a temporary fixedly connecting device;
C. an electric hoist track beam is arranged between 2 self-lifting outer sleeves which are longitudinally arranged, an electric hoist is arranged on the electric hoist track beam, and a lifting cross beam and lifting equipment are arranged at the top of the 2 self-lifting outer sleeves which are transversely arranged;
D. lifting the standard middle section to be installed upwards through the electric hoist, moving the standard middle section to be installed along the electric hoist track beam to enable the standard middle section to be installed to be located above the standard middle section which is fixedly installed at the topmost end, and then fixedly connecting the standard middle section to be installed with the standard middle section below the standard middle section;
E. repeating the step D, and installing another standard middle section to be installed above the standard middle section which is fixedly installed at the topmost end of the other end of the same electric hoist track beam;
F. fixing a lifting jack above the standard middle section at the topmost end, loosening a temporary fixedly connecting device between the self-lifting outer sleeve frame and the standard middle section, starting the lifting jack, and lifting the self-lifting outer sleeve frame upwards;
G. fixedly connecting the lifted self-lifting outer sleeve frame with the topmost standard middle section through a temporary fixedly connecting device, and separating and lifting the lifting jack from the topmost standard middle section and then lifting upwards;
H. and D-G is repeated until all the standard middle sections are completely installed, and then the D-G is repeated, and the top section of the sections is fixed on the topmost standard middle section, so that the whole hoisting tower system is completely installed.
In the self-lifting installation method of the hoisting tower system, after the hoisting tower system finishes the hoisting operation, the hoisting tower system is reversely operated in the above mode to finish the descending and dismantling work of the hoisting tower system.
In the self-lifting installation method of the hoisting tower system, in the process of the step F, the self-lifting outer sleeve frames of 4 hoisting towers are synchronously lifted upwards.
In the self-lifting installation method of the hoisting tower system, the temporary fixedly connecting device comprises a segment connecting lug plate arranged on the outer side wall of the segment and a sleeve frame positioning lug plate arranged on the inner side wall of the self-lifting outer sleeve frame, and when the self-lifting outer sleeve frame is fixed on the segment, the connecting lug plate and the sleeve frame positioning lug plate are connected together through a limiting bolt.
In the self-lifting installation method of the hoisting tower system, the top and the bottom of each segment are respectively provided with a segment flange connecting plate, when two adjacent segments are connected, the two segment flange connecting plates are fixedly connected by using bolts, and when the lifting jack is connected with the segment, the bottom of the lifting jack is fixed on the segment flange connecting plate at the top of the segment.
In the self-lifting installation method of the hoisting tower system, the sections and the self-lifting outer jacket frame are frame structures formed by connecting rod pieces which are arranged longitudinally, transversely, vertically and/or obliquely, wherein the middle upper parts of two corresponding side surfaces of the 2 self-lifting outer jacket frames which are connected with each other through the electric hoist track beams are hollow, and the top sections are of square cone structures.
In the self-lifting installation method of the lifting tower system, in the process of installing the top section, firstly, a sand box cushion block is fixedly installed at the top of the top section, after the top section is installed, the self-lifting outer jacket frame is lowered by using the lifting jack, so that the self-lifting outer jacket frame falls on the sand box cushion block, and then the self-lifting outer jacket frame is fixedly connected with the standard middle section.
In the self-lifting installation method of the lifting tower system, after the self-lifting outer jacket frame falls on the sand box cushion block, the self-lifting outer jacket frame is fixedly connected with the standard middle section through the hoop member.
In the self-lifting installation method of the lifting tower system, 2 cross rods are arranged at the top of the self-lifting outer sleeve frame, and each cross rod is provided with 2 fixing penetrating holes of lifting jacks.
In the self-lifting installation method of the hoisting tower system, the electric hoist and the lifting jack are controlled by the lifting control system.
The invention has the beneficial effects that: compared with the prior art, in the self-lifting installation method of the lifting tower system, the connecting pieces are directly arranged on the sections of the lifting tower, the connecting pieces are also arranged on the self-lifting sleeve frame, the sections and the self-lifting sleeve frame can be temporarily fixed by the connecting pieces, and the force bearing points are alternated by the aid of the electric hoist and the lifting jack which are arranged on the self-lifting sleeve frame, so that the self-lifting and self-descending functions of the lifting tower are achieved, and the using purpose is achieved. The whole hoisting tower system can realize hoisting operation of components within 60m in a non-adhesion state by a small amount of manual matching after the installation of the basic segments is finished on the ground, thereby greatly shortening the hoisting operation time and greatly reducing the safety risk of the hoisting operation. Moreover, due to the tower system in the air, a good working surface can be provided for subsequent component positioning installation and accessory facility construction, and the problem of a working site for subsequent construction is solved. Because the section that the tower designed is less, when using in practice, can make up according to on-the-spot actual conditions is nimble, under the circumstances that construction site is limited, other mechanical equipment can't use, if hoist and mount height surpass 30m and can't be under the construction all around and adhere to the facility, can solve the hoist and mount problem of engineering component. The independent height of this scheme design at present is 60m, if need increase the height can through the mode of basis increase height to solve.
Drawings
FIG. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a schematic structural view of the segment to be hoisted according to the present invention;
FIG. 3 is a schematic side view of FIG. 1;
FIG. 4 is a schematic view of a top-view structure of the self-lifting jacket bracket, an electric hoist track beam and a lifting cross beam which are connected with each other;
FIG. 5 is a schematic view of a connection structure between a self-elevating jacket frame and an elevating jack;
FIG. 6 is a schematic diagram of a standard middle segment structure;
FIG. 7 is a schematic top segment construction;
FIG. 8 is a schematic structural view of a self-elevating jacket frame;
fig. 9 is a schematic view of the structure of the bottom segment, the standard middle segment and the top segment after they are connected with each other.
Reference numerals: 1-bottom section, 2-self-lifting outer sleeve frame, 3-electric hoist, 4-electric hoist track beam, 5-lifting jack, 6-sand box cushion block, 7-lifting beam, 8-connecting lug plate, 9-sleeve frame positioning lug plate, 10-section flange connecting plate, 11-limiting bolt, 12-lifting control system, 13-top section, 14-hoop component, 15-standard middle section, 16-cross bar and 17-fixing penetrating hole.
Detailed Description
The invention is further illustrated by the following figures and examples, which are not to be construed as limiting the invention.
The embodiment of the invention comprises the following steps: a self-lifting installation method of a lifting tower system is disclosed, as shown in attached figures 1-9, a part of frame bodies of 4 lifting towers are installed on the ground in a square structure, the outer side of the part of frame body of each lifting tower is sleeved with a self-lifting outer jacket frame 2, 2 groups of 2 self-lifting outer jacket frames 2 which are longitudinally arranged are connected through an electric hoist track beam 4, 2 groups of 2 self-lifting outer jacket frames 2 which are transversely arranged are connected through a lifting cross beam 7, and lifting equipment is installed on the lifting cross beam 7. Because the height of partial frame body of the hoisting tower frame installed in the earlier stage is only about 9m and is far lower than the design height, the height of the hoisting tower frame needs to be increased. The heightening mode is that the electric hoist 3 on the electric hoist track beam 4 upwards lifts the segment and then places the segment on the top of the installed hoisting tower along the transverse movement of the electric hoist track beam 4, then fixes the segment on the top of the hoisting tower, then the self-lifting outer sleeve frame 2 upwards climbs along the hoisting tower, and the segment is repeatedly lifted and fixed again until the hoisting tower is built to the required height.
In the whole process, the hoisting tower frame is heightened through the self-lifting outer sleeve frame 2, then the self-lifting outer sleeve frame 2 ascends along the heightened hoisting tower frame, and the lifting beam 7 and the lifting equipment can be lifted upwards to the required height in the climbing process.
The specific installation method of the system comprises the following steps:
A. when erecting the tower system, firstly, the number of standard middle sections 15 except the bottom section 1 and the top section 13 is determined according to the height required by hoisting. And then all the components are transported to a construction site, firstly, the bottom section 1 of the sections is fixed on the ground, then, a crane is used for hoisting the standard middle section 15, the standard middle sections 15 of the plurality of sections are fixedly stacked on the bottom section 1 in a one-to-one overlapping mode, the bottom section 1 and the standard middle sections 15 are stacked to the height of about 9m, and then the step B can be carried out after the self-lifting outer jacket frame 2 can be correctly installed.
B. Firstly, 4 lifting jacks 5 are arranged on each self-lifting outer jacket frame 2, 1 self-lifting outer jacket frame 2 is correspondingly arranged on 1 lifting tower frame, and 4 self-lifting outer jacket frames 2 are required to be prepared due to the arrangement of 4 lifting tower frames. The self-elevating jacket frame 2 is a hollow frame structure having a size larger than that of each segment so as to be sleeved outside the segment at a later installation. And then hoisting the installed self-lifting outer jacket frame 2 by using a crane, hoisting and sleeving the self-lifting outer jacket frame 2 outside the installed standard middle segment 15, and fixedly connecting the self-lifting outer jacket frame 2 with the standard middle segment 15 through a temporary fixedly connecting device. After the self-lifting outer sleeve frame 2 of the 4 hoisting towers is completely installed, the next step can be carried out.
C. Install 1 electric block track roof beam 4 between 2 vertical self-lifting outer cover racks 2 that set up, install electric block 3 on the electric block track roof beam 4, 2 horizontal self-lifting outer cover racks 2 tops that set up install 1 and lift by crane crossbeam 7 and equipment. And hoisting the electric hoist track beam 4, the hoisting cross beam 7 and the hoisting equipment by using a crane in the installation process. After all the parts are installed, the tower is hoisted to enter a self-lifting installation stage. The self-lifting installation stage comprises the following steps:
D. the method comprises the steps that 1 section of a standard middle section 15 to be installed is lifted upwards through vertical movement of an electric hoist 3, the lifting height is stopped after being higher than the standard middle section 15 at the topmost end of an installed hoisting tower, then the electric hoist 3 is controlled to move horizontally along an electric hoist track beam 4, so that the standard middle section 15 to be installed is lifted to be located above the standard middle section 15 which is fixedly installed at the topmost end, and then the lifted standard middle section 15 to be installed is fixedly connected with the standard middle section 15 below;
E. repeating the step D, and installing another section of standard middle section 15 to be installed above the standard middle section 15 which is fixedly installed at the topmost end of the other end of the same electric hoist track beam 4;
F. the bottom of a lifting jack 5 fixedly connected with the self-lifting outer jacket frame 2 is fixed above a topmost standard middle section 15 at the moment, a temporary fixedly connecting device between the self-lifting outer jacket frame 2 and the standard middle section 15 is loosened, and the self-lifting outer jacket frame 2 is fixedly connected with the lifting tower frame because the lifting jack 5 is fixedly connected with the lifting tower frame at the moment, so that the self-lifting outer jacket frame 2 cannot slide downwards even if the temporary fixedly connecting device between the self-lifting outer jacket frame 2 and the standard middle section 15 is loosened. Then starting the lifting jack 5, lifting the self-lifting outer jacket frame 2 upwards by the lifting jack 5 to reach a standard lifting height, and stopping;
G. fixedly connecting the lifted self-lifting outer sleeve frame 2 with the top standard middle section 15 at the top at the moment through a temporary fixedly connecting device, separating the lifting jack 5 from the top standard middle section 15, and lifting and retracting the lifting jack upwards;
H. and D-G is repeated until all the standard middle sections 15 are completely installed, and then the D-G is repeated, the top section 13 of the sections is fixed on the topmost standard middle section 15, and the whole hoisting tower system is completely installed. And then, hoisting the tower into a hoisting stage.
And after the hoisting tower system finishes the hoisting operation, the descending and dismantling work of the hoisting tower system is finished according to the inverse operation of the mode. When the hoisting tower is dismantled to a position close to the ground, the hoisting crossbeam 7, the hoisting equipment, the electric hoist track beam 4, the self-lifting outer jacket frame 2 and the rest standard middle segment 15 can be dismantled by using a crane.
And in the process of the step F, in the process of moving the self-lifting outer jacket frame 2 upwards, the synchronous upwards lifting of the self-lifting outer jacket frame 2 of the 4 hoisting towers is ensured. Just so can keep electric block track roof beam 4 and lift by crane the balance of crossbeam 7, avoid promoting desynchronously, lead to electric block track roof beam 4 and lift by crane the crossbeam 7 slope for the hoist and mount pylon receives oblique pressure, takes place to collapse easily.
The temporary fixed connection device comprises a section connecting lug plate 8 arranged at the top end and the bottom end of the outer side wall of the section and a sleeve frame positioning lug plate 9 arranged on the inner side wall of the self-lifting outer sleeve frame 2, and the connecting lug plate 8 and the sleeve frame positioning lug plate 9 are connected together through a limiting bolt 11 when the self-lifting outer sleeve frame 2 is fixed on the section. And in the lifting or descending process of the self-lifting outer sleeve frame 2, the limiting bolt 11 is taken out. The height of the self-elevating jacket frame 2 lifted upward each time can be 1 standard middle segment 15, because the other segments except the top segment 13 installed last in the installed segments are the standard middle segments 15, so that the new standard middle segments 15 can be conveniently installed.
The top and the bottom of the segment are respectively provided with a segment flange connecting plate 10, when two adjacent segments are connected, the two segment flange connecting plates 10 are fixedly connected by using bolts, and when the lifting jack 5 is connected with the segment, the bottom of the lifting jack is fixed on the segment flange connecting plate 10 at the top of the segment. The quick connection between the segments, and the segments to the lifting jack 5, is achieved by the flange connection plates 10.
The sections and the self-lifting outer sleeve frame 2 are frame structures formed by connecting rods arranged longitudinally, transversely, vertically and/or obliquely, and the bottom section 1 and the standard middle section 15 are square frame structures formed by connecting rods arranged longitudinally, transversely, vertically and obliquely. In the whole hoisting tower structure, except for the bottom section 1 and the top section 13, the rest parts are standard middle sections 15, and the standard middle sections 15 are mainly used for transmitting vertical loads and bearing a part of wind loads. The top section 13 is a square cone structure formed by connecting rods arranged longitudinally, transversely and obliquely, and can well transmit hoisting load to the standard middle section 15 part of the hoisting tower frame. The bottom section 1 is mainly responsible for foundation bearing of the whole hoisting tower, and if the bottom section 1 needs to be buried and cannot be recycled, the bottom section 1 is not recycled as a permanent structure. Wherein the middle upper parts of two corresponding side surfaces of 2 self-lifting outer sleeves 2 which are connected with each other through the electric hoist track beam 4 are hollowed out. The hollow part at the middle upper part of the self-lifting outer sleeve frame 2 is a moving space for the electric hoist 3 and the hoisted section to move horizontally.
In the process of installing the jacking segment 13, 1 sand box cushion block 6 is fixedly installed at the top of the jacking segment 13, after the jacking segment 13 is installed, the lifting jack 5 is fixedly connected with the jacking segment 13, a temporary fixedly connecting device between the self-lifting outer jacket frame 2 and the standard middle segment 15 is loosened, then the lifting jack 5 is started, the self-lifting outer jacket frame 2 is lowered under the action of the lifting jack 5, the top bottom surface of the self-lifting outer jacket frame 2 falls on the sand box cushion block 6, and then the self-lifting outer jacket frame 2 is fixedly connected with the standard middle segment 15 through the hoop member 14. The self-lifting outer sleeve frame 2 is stably dropped on the hoisting tower frame.
The top of the self-lifting outer sleeve frame 2 is provided with 2 cross rods 16, and each cross rod 16 is provided with 2 fixing penetrating holes 17 of the lifting jacks 5. The lifting jack 5 is fixed to the top of the self-lifting jacket frame 2 after passing through the fixing insertion hole 17.
The electric hoist 3 and the lifting jack 5 are controlled by a lifting control system 12.
The self-elevating jacket frame 2 in the whole system is responsible for providing a section of transportation, installation and removal platform.

Claims (5)

1. The self-lifting installation method of the hoisting tower system is characterized by comprising the following steps: firstly, building partial frame bodies of 4 hoisting towers on the ground, sleeving a self-lifting outer sleeve frame (2) at the outer side of each partial frame body, connecting the tops of 2 self-lifting outer sleeve frames (2) which are longitudinally arranged through an electric hoist track beam (4), and connecting the tops of 2 self-lifting outer sleeve frames (2) which are transversely arranged through a hoisting cross beam (7); the electric hoist (3) on the electric hoist track beam (4) lifts the segments upwards and then moves transversely and fixes the segments on the top of the hoisting tower frame, then the self-lifting outer sleeve frame (2) climbs upwards along the hoisting tower frame, and the segments are lifted and fixed repeatedly again until the hoisting tower frame is built to the required height;
the installation method comprises the following steps:
A. fixing a bottom segment (1) of the segments on the ground, and fixedly stacking a standard middle segment (15) of the plurality of segments on the bottom segment (1) in an overlapping manner;
B. a lifting jack (5) is arranged on the self-lifting outer sleeve frame (2), the self-lifting outer sleeve frame (2) is lifted and sleeved outside the installed standard middle section (15), and the self-lifting outer sleeve frame (2) is fixedly connected with the standard middle section (15) through a temporary fixedly connecting device;
C. an electric hoist track beam (4) is arranged between 2 self-lifting outer sleeves (2) which are longitudinally arranged, an electric hoist (3) is arranged on the electric hoist track beam (4), and a lifting cross beam (7) and lifting equipment are arranged at the top of the 2 self-lifting outer sleeves (2) which are transversely arranged;
D. lifting the standard middle section (15) to be installed upwards through the electric hoist (3), moving the electric hoist along the electric hoist track beam (4) to enable the standard middle section (15) to be installed to be located above the standard middle section (15) which is fixedly installed at the topmost end, and then fixedly connecting the standard middle section (15) to be installed with the standard middle section (15) below;
E. d, repeating the step D, and installing another standard middle section (15) to be installed above the standard middle section (15) which is fixedly installed at the topmost end of the other end of the same electric hoist track beam (4);
F. fixing a lifting jack (5) above the standard middle section (15) at the topmost end, loosening a temporary fixedly connecting device between the self-lifting outer jacket frame (2) and the standard middle section (15), starting the lifting jack (5), and lifting the self-lifting outer jacket frame (2) upwards;
G. fixedly connecting the lifted self-lifting outer sleeve frame (2) with the top standard middle section (15) through a temporary fixedly connecting device, and separating the lifting jack (5) from the top standard middle section (15) and then lifting upwards;
H. D-G is repeated until all the standard middle sections (15) are completely installed, and then D-G is repeated, the top section (13) of the sections is fixed on the standard middle section (15) at the topmost part, and the whole hoisting tower system is completely installed;
the sections and the self-lifting outer sleeve frame (2) are of frame structures formed by connecting rod pieces which are arranged longitudinally, transversely, vertically and/or obliquely, wherein the middle upper parts of two corresponding side surfaces of the 2 self-lifting outer sleeve frames (2) which are connected with each other through an electric hoist track beam (4) are hollowed out, and the top sections are of square cone structures;
in the process of installing the jacking segment (13), firstly, a sand box cushion block (6) is fixedly installed at the top of the jacking segment (13), after the jacking segment (13) is installed, the self-lifting outer jacket frame (2) is lowered by using a lifting jack (5), so that the self-lifting outer jacket frame (2) falls on the sand box cushion block (6), then the self-lifting outer jacket frame (2) is fixedly connected with a standard middle segment (15), and after the self-lifting outer jacket frame (2) falls on the sand box cushion block (6), the self-lifting outer jacket frame (2) is fixedly connected with the standard middle segment (15) through a hoop member (14);
the top of the self-lifting outer sleeve frame (2) is provided with 2 cross rods (16), and each cross rod (16) is provided with a fixed penetrating hole (17) of 2 lifting jacks (5).
2. The self-lifting installation method of the hoisting tower system according to claim 1, wherein: after the hoisting tower system finishes the hoisting operation, the descending and dismantling work of the hoisting tower system is finished according to the inverse operation of the mode; and in the process of the step F, the self-lifting outer sleeve frame (2) of the 4 hoisting towers is synchronously lifted upwards.
3. The self-lifting installation method of the hoisting tower system according to claim 1, wherein: the temporary fixedly connecting device comprises a segment connecting lug plate (8) arranged on the outer side wall of the segment and a sleeve frame positioning lug plate (9) arranged on the inner side wall of the self-lifting outer sleeve frame (2), and when the self-lifting outer sleeve frame (2) is fixed on the segment, the connecting lug plate (8) and the sleeve frame positioning lug plate (9) are connected together through a limiting bolt (11).
4. The self-lifting installation method of the hoisting tower system according to claim 1, wherein: the top and the bottom of the segment are respectively provided with a segment flange connecting plate (10), when two adjacent segments are connected, the two segment flange connecting plates (10) are fixedly connected by using bolts, and when the lifting jack (5) is connected with the segment, the bottom of the lifting jack is fixed on the segment flange connecting plate (10) at the top of the segment.
5. The self-lifting installation method of the hoisting tower system according to claim 1, wherein: the electric hoist (3) and the lifting jack (5) are controlled by a lifting control system (12).
CN201910964825.8A 2019-10-11 2019-10-11 Self-lifting installation method of hoisting tower system Active CN110745714B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910964825.8A CN110745714B (en) 2019-10-11 2019-10-11 Self-lifting installation method of hoisting tower system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910964825.8A CN110745714B (en) 2019-10-11 2019-10-11 Self-lifting installation method of hoisting tower system

Publications (2)

Publication Number Publication Date
CN110745714A CN110745714A (en) 2020-02-04
CN110745714B true CN110745714B (en) 2021-02-02

Family

ID=69278043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910964825.8A Active CN110745714B (en) 2019-10-11 2019-10-11 Self-lifting installation method of hoisting tower system

Country Status (1)

Country Link
CN (1) CN110745714B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113846573B (en) * 2020-06-25 2025-02-28 中交路桥建设有限公司 Self-lifting arch rib vertical rotation lifting frame installation system and method
CN112160243B (en) * 2020-09-04 2022-02-11 中交路桥华南工程有限公司 Steel tower lifting installation method
CN113148893A (en) * 2021-04-17 2021-07-23 中交路桥建设有限公司 Hydraulic jacking load-bearing support and mounting method thereof
CN115402945A (en) * 2022-09-08 2022-11-29 中交路桥华南工程有限公司 Lifting and jacking integrated self-climbing crane
CN116181077B (en) * 2023-03-31 2024-10-01 浙江中南绿建科技集团有限公司 Construction method of high-rise steel column

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030213647A1 (en) * 2002-05-20 2003-11-20 Andre St-Germain Removable tower sleeve
CN101537976B (en) * 2009-03-20 2010-07-28 史胜海 Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN107724691B (en) * 2017-09-22 2022-08-16 河北卓达建材研究院有限公司 Mobile building loading machine
CN110259152A (en) * 2019-05-31 2019-09-20 深圳市协鹏建筑与工程设计有限公司福田分公司 A kind of construction material movement system and method
CN110182694A (en) * 2019-06-04 2019-08-30 深圳市协鹏建筑与工程设计有限公司福田分公司 One kind being applied to console mode and self-crawling type integral construction job platform
CN110259079A (en) * 2019-06-13 2019-09-20 深圳市协鹏建筑与工程设计有限公司福田分公司 One kind being used for building machinery and construction synchronization lifting structure

Also Published As

Publication number Publication date
CN110745714A (en) 2020-02-04

Similar Documents

Publication Publication Date Title
CN110745714B (en) Self-lifting installation method of hoisting tower system
AU2009244469B2 (en) Erection method for solar receiver and support tower
US11274432B2 (en) Method of constructing a building, and a building construction system therefor
KR19990072014A (en) Lift-up method for building buildings from above to the ground
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
CN206110656U (en) Scalable foldable integrally lift up tube formwork of elevartor shaft
CN114775806B (en) Wall body and upper concrete structure construction platform utilizing jacking net rack and method thereof
CN110589690A (en) Climbing method of internal climbing tower crane in narrow space
CN108005373B (en) Integrated lifting platform system and assembling method thereof
CN203684113U (en) Automatic beam placement platform device
JP5039304B2 (en) Construction method of boiler frame
CN218912242U (en) Tripod extension jacking formwork platform for elevator shaft construction
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN110735399B (en) Installation method of cast-in-place support beam system capable of automatically rising or falling
CN109372242B (en) Elevator shaft construction safety lifting platform device and using method
CN112983088A (en) Construction device and construction method for silo
CN112627543A (en) Shaft inner lifting frame for mounting steel beams of core tube elevator shaft and steel beam construction method
CN215710948U (en) Lift goes out roofing buttress device
CN218623600U (en) 5G roof television microwave signal tower lifting installation structure
US20250003390A1 (en) Wind turbine lifting rig
CN204752102U (en) Door derrick crane pylon standard festival equipment relay formula is vertical from jacking device
CN223018135U (en) A construction platform suitable for various occasions
CN111945890B (en) Jack-up multi-story steel structure and its construction method
KR200200364Y1 (en) High building construction apparatus
CN115898010A (en) Ultrahigh rectangular column slip form and operation platform construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant