[go: up one dir, main page]

CN110725700B - Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method - Google Patents

Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method Download PDF

Info

Publication number
CN110725700B
CN110725700B CN201910924103.XA CN201910924103A CN110725700B CN 110725700 B CN110725700 B CN 110725700B CN 201910924103 A CN201910924103 A CN 201910924103A CN 110725700 B CN110725700 B CN 110725700B
Authority
CN
China
Prior art keywords
glue injection
hole
coal seam
plug
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910924103.XA
Other languages
Chinese (zh)
Other versions
CN110725700A (en
Inventor
刘厅
赵洋
林柏泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201910924103.XA priority Critical patent/CN110725700B/en
Publication of CN110725700A publication Critical patent/CN110725700A/en
Application granted granted Critical
Publication of CN110725700B publication Critical patent/CN110725700B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/12Packers; Plugs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开的一种煤层喷涂加固与分级注胶协同封孔方法,涉及煤层协同封孔方法技术领域。该封孔方法首先对巷道壁面进行喷涂加固,然后施工顺层瓦斯抽采钻孔并进行注胶封孔,最后通过注胶管向瓦斯抽采钻孔两侧的注胶钻孔内带压注入胶体封堵裂隙带;随着抽采的进行,瓦斯浓度逐渐降低到一定值时,再次通过注胶管向注胶钻孔内注入胶体封堵次生裂隙。本发明公开的一种煤层喷涂加固与分级注胶协同封孔方法,通过巷道壁喷涂加固与钻孔注胶相结合的方式实现钻孔封堵,操作简单、成本低、安全性高、效果好,同时采用两级注胶方式,对于由于煤层瓦斯的解吸流动导致煤基质收缩产生的次生裂隙,进行较好的封堵,进一步提高了煤层钻孔瓦斯抽采的效果和抽采浓度。

Figure 201910924103

The invention discloses a coal seam spraying reinforcement and graded glue injection synergistic sealing method, which relates to the technical field of coal seam synergistic sealing methods. The sealing method firstly sprays and reinforces the wall of the roadway, then constructs a gas drainage hole along the layer and injects glue to seal the hole, and finally injects colloid under pressure into the glue injection hole on both sides of the gas drainage hole through the glue injection pipe. Seal the fracture zone; with the progress of the extraction, when the gas concentration gradually decreases to a certain value, inject colloid into the injection hole again through the injection pipe to plug the secondary fractures. The invention discloses a coal seam spraying reinforcement and grading glue injection synergistic sealing method, which realizes the drilling hole plugging through the combination of roadway wall spraying reinforcement and drilling glue injection, and has the advantages of simple operation, low cost, high safety and good effect. At the same time, the two-stage glue injection method is used to better seal the secondary cracks caused by the shrinkage of the coal matrix due to the desorption flow of the coal seam gas, which further improves the effect and concentration of the gas drainage in the coal seam drilling holes.

Figure 201910924103

Description

一种煤层喷涂加固与分级注胶协同封孔方法Coal seam spray reinforcement and graded glue injection synergistic sealing method

技术领域technical field

本发明涉及煤层协同封孔方法技术领域,具体涉及一种煤层喷涂加固与分级注胶协同封孔方法。The invention relates to the technical field of a coal seam cooperative sealing method, in particular to a coal seam spraying reinforcement and graded glue injection cooperative sealing method.

背景技术Background technique

随着浅部煤炭资源的逐渐枯竭,未来深部煤炭资源开采将成为常态。但是进入深部以后,煤层含气量高、压力大,严重威胁矿井的安全生产。而煤层气是一种清洁高效能源和强温室气体,据统计,我国埋深在2000m以上的煤层气资源量约为36.81万亿m3,居世界第三位。其中,埋深在1000~2000m之间的煤层气资源量占全国煤层气资源总量的61.2%,具有极高的开采价值。因此,实现煤层气的高效开发对于保障采矿安全,实现资源利用以及环境保护具有重要意义。With the gradual exhaustion of shallow coal resources, the mining of deep coal resources will become the norm in the future. However, after entering the deep, the coal seam has high gas content and high pressure, which seriously threatens the safe production of the mine. CBM is a clean and efficient energy source and a strong greenhouse gas. According to statistics, the amount of CBM resources buried deeper than 2000m in China is about 36.81 trillion m 3 , ranking third in the world. Among them, the coalbed methane resources buried between 1000 and 2000m account for 61.2% of the total coalbed methane resources in the country, and have extremely high mining value. Therefore, realizing the efficient development of CBM is of great significance for ensuring mining safety, realizing resource utilization and environmental protection.

煤层巷道采掘后,煤体的应力平衡状态被打破,进一步导致巷道周围的煤体在应力的作用下发生破碎,形成裂隙带。而且在瓦斯抽采钻孔和注浆钻孔施工完成后,由于打钻过程的扰动以及卸压作用,导致钻孔周围在原有裂隙带的基础上形成更多的裂隙,影响瓦斯抽采效果。基于这一问题,人们提出通过注浆封孔的方式来提高煤层钻孔瓦斯抽采的效果和抽采浓度。但是传统的注浆封孔方式多为一次性注浆,封孔效果差,对于提高瓦斯抽采的效果不明显。After the coal seam roadway is excavated, the stress balance state of the coal body is broken, which further leads to the fragmentation of the coal body around the roadway under the action of stress, forming a fissure zone. Moreover, after the gas drainage drilling and grouting drilling are completed, due to the disturbance of the drilling process and the pressure relief effect, more cracks are formed around the drilling hole on the basis of the original crack zone, which affects the gas drainage effect. Based on this problem, it is proposed to improve the effect and concentration of gas drainage in coal seam boreholes by grouting and sealing. However, the traditional grouting and sealing methods are mostly one-time grouting, and the sealing effect is poor, and the effect of improving gas drainage is not obvious.

因此,为了提高煤层钻孔瓦斯抽采的效果和抽采浓度,急需寻求全新的瓦斯抽采钻孔封孔方法,以满足煤矿井下钻孔封孔的要求。Therefore, in order to improve the effect and concentration of gas drainage in coal seam drilling, it is urgent to find a new method of drilling and sealing for gas drainage, so as to meet the requirements of drilling and sealing of underground coal mines.

发明内容SUMMARY OF THE INVENTION

根据本发明的目的提出的一种煤层喷涂加固与分级注胶协同封孔方法,包括以下步骤:According to the purpose of the present invention, a coal seam spraying reinforcement and graded glue injection synergistic sealing method, comprising the following steps:

S1.煤层巷道采掘后巷道壁面及周围形成裂隙带,在巷道壁喷涂浆液,对巷道壁进行加固,并形成隔离屏障初步封堵巷道壁采动裂隙。S1. After the coal seam roadway is excavated, a fissure zone is formed on the wall of the roadway and its surroundings. The slurry is sprayed on the wall of the roadway to reinforce the wall of the roadway, and an isolation barrier is formed to initially block the mining fissures of the roadway wall.

S2.根据作业要求,使用钻孔装置在巷道壁向煤层方向中施工瓦斯抽采钻孔和注胶钻孔。S2. According to the operation requirements, use the drilling device to construct the gas drainage hole and the glue injection hole in the direction of the roadway wall to the coal seam.

S3.在瓦斯抽采钻孔内放入抽采管并用封孔装置封堵孔口。S3. Put a gas drainage pipe in the gas drainage hole and seal the hole with a hole sealing device.

S4.在注胶钻孔孔口放入第三堵头,注胶管穿过第三堵头放入注胶钻孔内,通过注胶管向钻孔内带压注入胶体,封堵采动裂隙。S4. Put a third plug in the hole of the glue injection hole, put the glue injection pipe into the glue injection hole through the third plug, and inject colloid into the hole under pressure through the glue injection pipe to seal the mining fracture.

S5.将瓦斯抽采管连入抽采系统进行瓦斯抽采。S5. Connect the gas extraction pipe to the extraction system for gas extraction.

S6.待抽采一定时间后,由于煤层瓦斯的解吸流动导致煤基质收缩,裂隙增加,通过注胶管再次向煤层内注入胶体封堵次生裂隙。S6. After a certain period of time, the coal matrix shrinks due to the desorption flow of coal seam gas, and the cracks increase, and the colloid is injected into the coal seam again through the rubber injection pipe to seal the secondary cracks.

S7.继续进行瓦斯抽采,直至抽采工作完成。S7. Continue gas extraction until the extraction work is completed.

优选的,S2中所述瓦斯抽采钻孔深度为100-150m,直径为113mm,相邻两瓦斯抽采钻孔之间的间距2-4m;注胶钻孔深度为10-15m,直径为75mm;瓦斯抽采钻孔和注胶钻孔交替设置,相邻两瓦斯抽采钻孔与注胶钻孔之间的间距为 1-2m。Preferably, the depth of the gas drainage hole in S2 is 100-150m, the diameter is 113mm, and the distance between two adjacent gas drainage holes is 2-4m; the depth of the glue injection hole is 10-15m, and the diameter is 2-4m. 75mm; gas drainage holes and glue injection holes are alternately arranged, and the distance between two adjacent gas drainage holes and glue injection holes is 1-2m.

优选的,S3中所述封孔装置包括封孔胶囊、注水管以及前后设置的第一堵头和第二堵头;首先将第一堵头固定安装在抽采管上伸入瓦斯抽采钻孔内,然后放置封孔胶囊与注水管,最后将第二堵头穿过注水管和抽采管放入瓦斯抽采钻孔孔口;注水管连接水泵进行注水,封孔胶囊、第一堵头与第二堵头遇水膨胀,封堵孔口,形成封孔段。Preferably, the hole sealing device in S3 includes a hole sealing capsule, a water injection pipe, and a first plug and a second plug arranged at the front and rear; first, the first plug is fixedly installed on the drainage pipe and inserted into the gas drainage drill In the hole, then place the sealing capsule and the water injection pipe, and finally put the second plug through the water injection pipe and the extraction pipe into the gas drainage hole; the water injection pipe is connected to the water pump for water injection, the sealing capsule and the first plug The head and the second plug swell in contact with water to block the orifice to form a plugging section.

优选的,S3中瓦斯抽采钻孔中封孔段长度与注胶钻孔长度相等。Preferably, the length of the sealing section in the gas drainage borehole in S3 is equal to the length of the glue injection borehole.

优选的,S3中注胶压力为1-3MPa。Preferably, the glue injection pressure in S3 is 1-3MPa.

与现有技术相比,本发明公开的一种煤层喷涂加固与分级注胶协同封孔方法的优点是:Compared with the prior art, the advantages of the coal seam spraying reinforcement and grading glue injection synergistic sealing method disclosed in the present invention are:

(1)通过巷道壁喷涂加固与钻孔注胶相结合的方式实现钻孔封堵能够有效的封堵巷道壁面和钻孔周围裂隙,同时喷涂加固有效防止了壁面漏风和钻孔变形,操作简单、成本低、安全性高、效果好。(1) The combination of roadway wall spraying reinforcement and drilling glue injection to achieve drilling plugging can effectively seal the roadway wall and the cracks around the drilled hole, and at the same time, spraying reinforcement can effectively prevent wall air leakage and drilling deformation, and the operation is simple. , Low cost, high safety and good effect.

(2)两级注胶方式,对于由于煤层瓦斯的解吸流动导致煤基质收缩产生的次生裂隙,进行较好的封堵,显著提高了煤层钻孔瓦斯抽采的效果和抽采浓度,节约了煤层瓦斯抽采,进一步提高煤层开采效率。(2) The two-stage glue injection method can better seal the secondary cracks caused by the shrinkage of the coal matrix due to the desorption flow of the coal seam gas, which can significantly improve the gas drainage effect and the drainage concentration of the coal seam drilling holes, and save energy. The coal seam gas drainage is further improved, and the coal seam mining efficiency is further improved.

附图说明Description of drawings

为了更清楚的说明本发明实施例或现有技术的技术方案,下面将对实施例或现有技术描述中所需要使用的附图做简单的介绍,显而易见的,下面描述中的附图仅仅是本发明的一些实施例,对于本领域中的普通技术人员来说,在不付出创造性劳动的前提下,还可根据这些附图获得其他附图。In order to illustrate the technical solutions of the embodiments of the present invention or the prior art more clearly, the following briefly introduces the accompanying drawings used in the description of the embodiments or the prior art. Obviously, the drawings in the following description are only For some embodiments of the present invention, for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative efforts.

图1为本发明实施结构图。FIG. 1 is a structural diagram of the implementation of the present invention.

图中的数字或字母所代表的零部件名称为:The names of the parts represented by the numbers or letters in the figure are:

1-抽采管;2-注胶管;3-瓦斯抽采钻孔;4-注胶钻孔;5-第二堵头;6-第三堵头;7-第一堵头;8-隔离屏障;9-胶体;10-封孔胶囊;11-注水管。1-Drainage pipe; 2-Gas injection pipe; 3-Gas drainage hole; 4-Glue injection hole; 5-Second plug; 6-Third plug; 7-First plug; 8-Isolation Barrier; 9-colloid; 10-sealing capsule; 11-water injection pipe.

具体实施方式Detailed ways

下面结合附图对本发明的具体实施方式做简要说明。显然,所描述的实施例仅仅是本发明的一部分实施例,而不是全部实施例,基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,均属于本发明保护的范围。The specific embodiments of the present invention will be briefly described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, those of ordinary skill in the art can obtain all other implementations without creative work. For example, all belong to the protection scope of the present invention.

图1示出了本发明较佳的实施例,对其进行了详细的剖析。FIG. 1 shows a preferred embodiment of the present invention, which is dissected in detail.

如图1所示的一种煤层喷涂加固与分级注胶协同封孔方法,包括以下步骤:As shown in Figure 1, a coal seam spraying reinforcement and graded glue injection synergistic sealing method includes the following steps:

步骤一、煤层巷道采掘后巷道壁面及周围形成裂隙带,在巷道壁喷涂浆液,对巷道壁进行加固,并形成隔离屏障8初步封堵巷道壁采动裂隙,隔绝空气。Step 1: After the coal seam roadway is excavated, a fissure zone is formed on and around the roadway wall, spraying slurry on the roadway wall to reinforce the roadway wall, and forming an isolation barrier 8 to initially block the roadway wall mining fissures and isolate the air.

步骤二、根据作业要求,使用钻孔装置在巷道壁向煤层方向中施工瓦斯抽采钻孔3和注胶钻孔4。其中,瓦斯抽采钻孔3深度为100-150m,直径为113mm,相邻两瓦斯抽采钻孔3之间的间距2-4m;注胶钻孔4深度为10-15m,直径为75mm;瓦斯抽采钻孔3和注胶钻孔4交替设置,相邻两瓦斯抽采钻孔3与注胶钻孔4 之间的间距为1-2m。Step 2: According to the operation requirements, use the drilling device to construct the gas drainage hole 3 and the glue injection hole 4 in the direction of the roadway wall toward the coal seam. Among them, the gas drainage hole 3 has a depth of 100-150m and a diameter of 113mm, and the distance between two adjacent gas drainage holes 3 is 2-4m; the glue injection hole 4 has a depth of 10-15m and a diameter of 75mm; Gas drainage holes 3 and glue injection holes 4 are alternately arranged, and the distance between two adjacent gas drainage holes 3 and glue injection holes 4 is 1-2m.

步骤三、在瓦斯抽采钻孔3内放入抽采管1并用封孔装置封堵孔口。具体的,封孔装置包括封孔胶囊10、注水管11以及前后设置的第一堵头7和第二堵头5;首先将第一堵头7固定安装在抽采管1上伸入瓦斯抽采钻孔3内,然后放置封孔胶囊10与注水管11,最后将第二堵头5穿过注水管11和抽采管1放入瓦斯抽采钻孔3孔口;注水管11连接水泵进行注水,封孔胶囊10、第一堵头7 与第二堵头5遇水膨胀,封堵孔口,形成封孔段。瓦斯抽采钻孔3中封孔段长度与注胶钻孔4长度相等。Step 3: Put the gas drainage pipe 1 in the gas drainage hole 3 and seal the hole with a hole sealing device. Specifically, the hole sealing device includes a hole sealing capsule 10, a water injection pipe 11, and a first plug 7 and a second plug 5 arranged in the front and rear; first, the first plug 7 is fixedly installed on the extraction pipe 1 and extended into the gas extraction pipe. In the mining hole 3, then place the sealing capsule 10 and the water injection pipe 11, and finally put the second plug 5 through the water injection pipe 11 and the extraction pipe 1 into the orifice of the gas extraction hole 3; the water injection pipe 11 is connected to the water pump After water injection, the sealing capsule 10 , the first plug 7 and the second plug 5 swell in contact with water to block the orifice to form a sealing section. The length of the sealing section in the gas drainage hole 3 is equal to the length of the glue injection hole 4 .

步骤四、在注胶钻孔4孔口放入第三堵头6,注胶管2穿过第三堵头6放入注胶钻孔4内,通过注胶管2向注胶钻孔4内带压注入胶体9,封堵采动裂隙。其中,注胶压力为1-3MPa。注胶时长根据实际注胶钻孔4深度、注胶速率以及裂隙带宽度等综合确定。Step 4. Put the third plug 6 in the hole of the glue injection hole 4, put the glue injection pipe 2 into the glue injection hole 4 through the third plug 6, and pass the glue injection pipe 2 to the glue injection hole 4. The colloid 9 is injected by pressure to seal the mining fractures. Among them, the glue injection pressure is 1-3MPa. The glue injection time is comprehensively determined according to the actual glue injection hole 4 depth, glue injection rate and crack band width.

步骤五、将瓦斯抽采管1连入抽采系统进行瓦斯抽采。Step 5. Connect the gas extraction pipe 1 into the extraction system to perform gas extraction.

步骤六、待抽采五小时后,由于抽采瓦斯的浓度降低的同时煤层瓦斯的解吸流动导致煤基质收缩,裂隙增加,通过注胶管2再次向煤层内注入胶体9封堵次生裂隙。其中,抽采时长可根据所抽采的瓦斯浓度确定。Step 6. After five hours of extraction, the coal matrix shrinks due to the desorption and flow of coal seam gas while the concentration of the extracted gas decreases, and the cracks increase, and the colloid 9 is injected into the coal seam again through the glue injection pipe 2 to seal the secondary cracks. Wherein, the extraction time can be determined according to the concentration of the extracted gas.

步骤七、继续进行瓦斯抽采,直至抽采工作完成。Step 7. Continue gas extraction until the extraction work is completed.

综上所述,本发明公开的一种煤层喷涂加固与分级注胶协同封孔方法,通过巷道壁喷涂加固与钻孔注胶相结合的方式实现钻孔封堵,操作简单、成本低、安全性高、效果好。同时采用两级注胶方式,对于由于煤层瓦斯的解吸流动导致煤基质收缩产生的次生裂隙,进行较好的封堵,进一步提高了煤层钻孔瓦斯抽采的效果和抽采浓度。To sum up, the present invention discloses a method for coordinating hole sealing by spraying reinforcement of coal seams and grading glue injection, which realizes hole sealing through the combination of roadway wall spray reinforcement and drilling glue injection, which is simple in operation, low in cost and safe. High sex and good effect. At the same time, the two-stage glue injection method is adopted to better seal the secondary cracks caused by the shrinkage of the coal matrix due to the desorption flow of the coal seam gas, which further improves the effect and concentration of the gas drainage in the coal seam borehole.

对所公开的实施例的上述说明,使本领域专业技术人员能够实现和使用本发明。对这些实施例的多种修改方式对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神和范围的情况下,在其他实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合本文所公开的原理和新颖特点相一致的最宽的范围。The foregoing description of the disclosed embodiments enables those skilled in the art to make and use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be implemented in other embodiments without departing from the spirit and scope of the present invention. Thus, the present invention is not intended to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (4)

1. A coal seam spraying reinforcement and grading glue injection cooperative hole sealing method is characterized by comprising the following steps:
s1, forming a fracture zone on the wall surface and the periphery of a roadway after the coal seam roadway is excavated, spraying slurry on the wall of the roadway, reinforcing the wall of the roadway, and forming an isolation barrier (8) to primarily block the roadway wall mining-induced fracture;
s2, constructing a gas extraction borehole (3) and an injection borehole (4) in the direction from the wall of the roadway to the coal seam by using a drilling device according to the operation requirement;
s3, placing an extraction pipe (1) in the gas extraction drill hole (3) and plugging an orifice by using a hole sealing device; the hole sealing device comprises a hole sealing capsule (10), a water injection pipe (11), a first plug (7) and a second plug (5) which are arranged in front and back; firstly, a first plug (7) is fixedly arranged on an extraction pipe (1) and extends into a gas extraction drill hole (3), then a hole sealing capsule (10) and a water injection pipe (11) are placed, and finally a second plug (5) penetrates through the water injection pipe (11) and the extraction pipe (1) and is placed into an orifice of the gas extraction drill hole (3); the water injection pipe (11) is connected with a water pump for injecting water, the hole sealing capsule (10), the first plug (7) and the second plug (5) expand when meeting water, and the hole opening is sealed to form a hole sealing section;
s4, placing a third plug (6) into an orifice of the glue injection drill hole (4), placing the glue injection pipe (2) into the glue injection drill hole (4) through the third plug (6), and injecting a colloid (9) into the glue injection drill hole (4) through the glue injection pipe (2) in a pressing mode to plug the mining crack;
s5, connecting the gas extraction pipe (1) into an extraction system for gas extraction;
s6, after a certain period of time for extraction, because the coal matrix shrinks and cracks increase due to desorption flow of coal seam gas, injecting colloid (9) into the coal seam again through the glue injection pipe (2) to block secondary cracks;
and S7, continuing gas extraction until the extraction work is finished.
2. The method for the cooperative hole sealing of the coal seam by spraying, reinforcing and grading glue injection according to claim 1, characterized in that the depth of the gas extraction drill hole (3) in S2 is 100-150m, the diameter is 113mm, and the distance between two adjacent gas extraction drill holes (3) is 2-4 m; the depth of the glue injection drill hole (4) is 10-15m, and the diameter is 75 mm; the gas extraction drill holes (3) and the glue injection drill holes (4) are alternately arranged, and the distance between every two adjacent gas extraction drill holes (3) and every two adjacent glue injection drill holes (4) is 1-2 m.
3. The method for spraying, reinforcing and grading glue injection cooperative hole sealing of the coal seam according to claim 1, characterized in that the length of the hole sealing section in the gas extraction drill hole (3) in S3 is equal to the length of the glue injection drill hole (4).
4. The method for cooperatively sealing the hole of the coal seam by spraying, reinforcing and grading glue injection according to claim 1, wherein the glue injection pressure in S3 is 1-3 MPa.
CN201910924103.XA 2019-09-27 2019-09-27 Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method Active CN110725700B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910924103.XA CN110725700B (en) 2019-09-27 2019-09-27 Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910924103.XA CN110725700B (en) 2019-09-27 2019-09-27 Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method

Publications (2)

Publication Number Publication Date
CN110725700A CN110725700A (en) 2020-01-24
CN110725700B true CN110725700B (en) 2020-11-10

Family

ID=69218474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910924103.XA Active CN110725700B (en) 2019-09-27 2019-09-27 Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method

Country Status (1)

Country Link
CN (1) CN110725700B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794711B (en) * 2020-08-03 2023-08-08 河南理工大学 High-pressure circulating grouting hole sealing device for gas extraction drilling and use method thereof
CN112360502B (en) * 2020-09-28 2022-12-20 中煤科工开采研究院有限公司 Coal roadway rapid tunneling method and equipment based on spray layer and atmospheric pressure
CN113605960B (en) * 2021-08-04 2023-03-10 煤炭科学研究总院有限公司 Method and device for preventing coal spontaneous combustion induced by coal bed gas extraction

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8371384B2 (en) * 2010-03-31 2013-02-12 Halliburton Energy Services, Inc. Methods for strengthening fractures in subterranean formations
CN102251797A (en) * 2011-06-21 2011-11-23 高珍会 Device and method for gas drilling, cementing and hole sealing for coal mines
CN102900396B (en) * 2012-11-01 2014-12-10 中国矿业大学 Method for integrally sealing and separating gas extraction drilled hole in coal seam
CN103899268A (en) * 2014-04-08 2014-07-02 中煤科工集团重庆研究院有限公司 Method for improving gas extraction hole sealing tightness
CN108060903B (en) * 2017-11-24 2019-01-08 山东科技大学 Coal-bed gas pressure measures dynamic self-balance pressurization hole sealing device and method

Also Published As

Publication number Publication date
CN110725700A (en) 2020-01-24

Similar Documents

Publication Publication Date Title
CN105332684B (en) A kind of water under high pressure is quick-fried and CO2The coal bed gas displacement extraction technique that pressure break is combined
CN102383828B (en) Refection reducing and outburst eliminating method for deep-hole hydraulic fracture driving gas shallow hole extraction
CN103195390B (en) The nearly horizontal mash gas pumping drilling encapsulating method in this coal seam a kind of
CN110725700B (en) Coal seam spraying reinforcement and graded glue injection cooperative hole sealing method
CN104832149A (en) Electric pulse assisted hydrofracture unconventional gas reservoir permeability increasing method
CN106930746B (en) Alternate Coal Seam Permeability Enhancement Method Combined with Drilling Acetone Invasion and Hydraulic Fracturing
CN104314607B (en) A kind of multistage improves the method for coal bed drilling gas extraction concentration
CN207073410U (en) The anti-reflection system of injection hot water and liquid nitrogen is circulated to coal seam
CN105804786B (en) A kind of weak seam bottom plate layer-through drilling pressure rushes anti-reflection method
CN104763462A (en) Method for extracting high-pressure hydraulic cave-manufacturing gas from rock roadway crossing hole
CN112727535A (en) Liquid CO2Coal body cracking and permeability increasing method with cooperative drilling and water filling
CN105370256A (en) Method for increasing wetting radius of high-pressure water injection of low-air-permeability coal seams through sectioned pre-splitting
CN105221129B (en) A kind of hydraulic pressure demolition, which is opened, splits CO2Take the reservoir anti-reflection method of proppant pressure break
CN104775787A (en) Hydraulic fracturing crossing hole pitchup hole sealing method of broken surrounding rock
CN102678166B (en) Method for increasing gas extraction rate by permeability increasing of single thick coal seam
CN104481462A (en) Coal-bed gas aging well production capacity increasing method
WO2020151207A1 (en) Coordinative extraction and pressure relief method for high confined water high gas coal seam group
CN107620581B (en) Construction method of one-well dual-purpose coal mine shaft inspection hole
CN116146160A (en) Liquid CO 2 Alkaline water fracturing permeability-increasing gas extraction and coal seam water injection method
CN104695895A (en) Plugging method integrating channel blocking and leakage plugging
CN114542164A (en) An integrated method for co-production of deep coal seam fluidized coal and coalbed methane and CO2 storage
CN210798914U (en) Drilling multi-section plugging, fracturing, grouting and water injection integrated equipment
CN110886594A (en) Methods of mining coalbed methane
CN105649625B (en) A kind of high-low pressure subregion fracturing anatonosis formula coal-bed flooding method
CN103541679B (en) Combined hole sealing method for hydraulic fracturing drilling in coal mine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant