CN110632448B CN201910870249.0A CN201910870249A CN110632448B CN 110632448 B CN110632448 B CN 110632448B CN 201910870249 A CN201910870249 A CN 201910870249A CN 110632448 B CN110632448 B CN 110632448B
Authority
CN
China
Prior art keywords
result
loop
terminal
impedance value
phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910870249.0A
Other languages
Chinese (zh)
Other versions
CN110632448A (en
Inventor
张志闻
余梅梅
侯玉
刘旸
黄令忠
李涛
戴斌
刘启彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Bureau Co Ltd
Original Assignee
Shenzhen Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Bureau Co Ltd filed Critical Shenzhen Power Supply Bureau Co Ltd
Priority to CN201910870249.0A priority Critical patent/CN110632448B/en
Publication of CN110632448A publication Critical patent/CN110632448A/en
Application granted granted Critical
Publication of CN110632448B publication Critical patent/CN110632448B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Measurement Of Resistance Or Impedance (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The invention discloses a wiring detection method of a three-phase three-wire metering device with a mutual inductor, which comprises the following steps: step S1, measuring a target metering device by using a bridge device with an impedance measuring loop, detecting the impedance value of a current loop of the target metering device, and judging the wiring condition of the current loop according to the detection result; and step S2, measuring the target metering device by using the bridge device with the impedance measuring loop, detecting the impedance value of the voltage loop, and judging the wiring condition of the voltage loop according to the detection result. By implementing the method, the metering device is effectively detected by checking the impedance values of the current loop and the voltage loop in the metering loop only through the bridge device without disconnecting the wires, the risk of wiring errors or polarity reversal is reduced, wiring error points are accurately locked, the working efficiency is improved, and unnecessary power supply and utilization disputes are reduced.

Description

一种带互感器的三相三线计量装置接线检测方法A three-phase three-wire metering device wiring detection method with transformer

技术领域technical field

本发明属于电子测量领域,涉及带互感器的三相三线计量装置接线检测方法。The invention belongs to the field of electronic measurement, and relates to a wiring detection method of a three-phase three-wire metering device with a transformer.

背景技术Background technique

随着社会用电的发展和电能计量技术的更新换代,以及供电部门对智能电表的深化应用,电表更换频率与工作量也大幅度提升,出现电表接线错误导致计量异常的情况也随之增多,特别是带互感器的计量装置接错线机率更大,漏计电量也就更大,造成电费回收的困难增加。With the development of social electricity consumption and the upgrading of electric energy measurement technology, as well as the deepening of the application of smart meters by the power supply department, the frequency and workload of electric meter replacement have also been greatly increased, and the occurrence of meter wiring errors resulting in abnormal measurement has also increased. In particular, the metering device with the transformer has a higher probability of being connected to the wrong line, and the leakage of electricity is also larger, which increases the difficulty of electricity bill recovery.

出现计量装置接线错误主要有两方面原因:一是安装完毕后未按工序检查接线;二是常规的接线检查方式需要拆解导线测量,容易造成后续恢复接线时错接或漏接。为了确保电能计量的准确性,供电部门也采取了不少管理措施,包括制定电表的安装规范与流程。根据案例分析,多数的接错线发生在安装完毕后拆线进行对线时,特别是表计新装或封表时现场一般未送电,无法用校验仪对计量装置接线进行检查,通常采用万用表上“蜂鸣器”来判断现场接线的正误,但是存在以下几个问题:1、由于万用表配置的表笔和测量线路长度有限,现场检查存在一定难度;2、CT和PT一般装在计量柜的后面,校验时需要两个人一个在计量柜前面一个在后面,同时操作,在沟通不到位的情况下,很容易判断错误;3、由于“蜂鸣器”采用直流电源的方式判断线路的通断,所以在检验接线的时候,需要把CT和PT对应的接线端先断开,才能准确判断线路接线,如此会增加线路检查的复杂程度,并且在复原回去时也存在接错线的可能性。There are two main reasons for the wrong wiring of the metering device: one is that the wiring is not checked according to the procedure after installation; the other is that the conventional wiring inspection method requires dismantling the wire for measurement, which is likely to cause misconnection or missed connection during subsequent wiring restoration. In order to ensure the accuracy of electric energy measurement, the power supply department has also taken many management measures, including formulating the installation specifications and procedures of electric meters. According to the case analysis, most of the wrong wiring occurs when the wiring is disconnected after installation, especially when the meter is newly installed or sealed, the site is generally not powered, and the calibrator cannot be used to check the wiring of the metering device. The "buzzer" on the multimeter is used to judge the correctness of the on-site wiring, but there are the following problems: 1. Due to the limited length of test leads and measurement lines configured by the multimeter, on-site inspection is difficult; 2. CT and PT are generally installed in the measuring cabinet In the back of the meter, two people are needed, one in front of the metering cabinet and the other in the back, and operate at the same time. If the communication is not in place, it is easy to judge the error; 3. Because the "buzzer" uses DC power to judge the circuit On and off, so when checking the wiring, it is necessary to disconnect the corresponding terminals of CT and PT to accurately judge the wiring of the line, which will increase the complexity of the line inspection, and there is also the possibility of wrong wiring when it is restored. sex.

发明内容SUMMARY OF THE INVENTION

本发明实施例所要解决的技术问题在于,对计量回路进行检测校验的时候需要进行拆接线操作,增加了接线错误或极性反接的风险,对错误点的确定操作复杂,效率低。The technical problem to be solved by the embodiments of the present invention is that when the metering loop is tested and verified, the wiring operation needs to be disconnected, which increases the risk of wiring errors or reverse polarity, and the operation for determining the error point is complicated and inefficient.

本发明的一方面,提供带互感器的三相三线计量装置接线检测方法,其包括如下步骤:One aspect of the present invention provides a method for detecting the wiring of a three-phase three-wire metering device with a transformer, which includes the following steps:

步骤S1,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况;Step S1, utilizes the bridge device with the impedance measurement loop to measure the target metering device, detects the impedance value of its current loop, and judges the current loop wiring condition according to the detected result;

步骤S2,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况。In step S2, a bridge device with an impedance measurement loop is used to measure the target metering device, to detect the impedance value of the voltage loop thereof, and to determine the connection condition of the voltage loop according to the detection result.

优选地,所述步骤S1中检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况包括,Preferably, the impedance value of its current loop is detected in the step S1, and the current loop wiring condition is determined according to the detection result, including,

测量A相电流回路,断开计量装置的接线盒连片LA1,使用电桥装置的测量夹子分别连接端子KA1和端子A4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;Measure the A-phase current loop, disconnect the junction box connecting piece LA1 of the metering device, use the measuring clip of the bridge device to connect the terminal KA1 and the terminal A4 respectively, start the bridge device, and check the result of its impedance value. If the result of the resistance value is zero, then the connection between the CT and the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, there is a disconnection point in the current loop;

将计量装置的接线盒连片LA1闭合,再次启动电桥装置,检测A相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点。Close the junction box connecting piece LA1 of the metering device, start the bridge device again, and detect the result of the impedance value of the A-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the result of the reactance value If not zero, there is a disconnection point in the wiring circuit from the junction box to the meter.

更具体的,所述步骤S1中检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况包括,More specifically, the impedance value of its current loop is detected in the step S1, and the current loop wiring condition is judged according to the detection result, including,

测量C相电流回路,断开计量装置的接线盒连片LC1,使用电桥装置的测量夹子分别连接端子KC1和端子C4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;Measure the C-phase current loop, disconnect the junction box connection piece LC1 of the metering device, use the measuring clip of the bridge device to connect the terminals KC1 and C4 respectively, start the bridge device, and check the result of its impedance value. If the result of the resistance value is zero, then the connection between the CT and the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, there is a disconnection point in the current loop;

将计量装置的接线盒连片LC1闭合,再次启动电桥装置,检测C相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点。Close the junction box connection piece LC1 of the metering device, start the bridge device again, and detect the result of the impedance value of the C-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the result of the reactance value If not zero, there is a disconnection point in the wiring circuit from the junction box to the meter.

进一步,所述检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到阻抗值为零时,进行步骤S2。Further, after the impedance value of the current loop is detected, after judging the wiring condition of the current loop according to the detection result, the connection point of the connection loop is adjusted according to the detection result of the impedance value, and the impedance value of the loop is repeatedly measured until the impedance value is zero. , and go to step S2.

优选的,所述步骤S2中检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况包括,Preferably, in the step S2, the impedance value of the voltage loop is detected, and the voltage loop wiring condition is determined according to the detection result, including:

测量A相电压回路,将电桥装置的测量夹子分别连接端子PA1和端子PA2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则A相电压回路中存在断点。Measure the A-phase voltage loop, connect the measuring clips of the bridge device to terminal PA1 and terminal PA2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. If it is not zero, there is a breakpoint in the A-phase voltage loop.

具体的,所述步骤S2中检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况包括,Specifically, in the step S2, the impedance value of the voltage loop is detected, and the wiring condition of the voltage loop is determined according to the detection result, including:

测量B相电压回路,将电桥装置的测量夹子分别连接端子PB1和端子PB2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则B相电压回路中存在断点。Measure the B-phase voltage loop, connect the measuring clips of the bridge device to terminal PB1 and terminal PB2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. If it is not zero, there is a breakpoint in the B-phase voltage loop.

具体的,所述步骤S2中检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况包括,Specifically, in the step S2, the impedance value of the voltage loop is detected, and the wiring condition of the voltage loop is determined according to the detection result, including:

测量C相电压回路,将电桥装置的测量夹子分别连接端子PC1和端子PC2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则C相电压回路中存在断点。Measure the C-phase voltage loop, connect the measuring clips of the bridge device to terminal PC1 and terminal PC2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. If it is not zero, there is a breakpoint in the C-phase voltage loop.

进一步,所述检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到阻抗值为零结束。Further, the impedance value of the voltage loop is detected, and after judging the connection of the voltage loop according to the detection result, the connection point of the connection loop is adjusted according to the detection result of the impedance value, and the impedance value of the loop is repeatedly measured until the impedance value is zero. .

实施例本发明实施例,具有如下有益效果:Embodiment The embodiment of the present invention has the following beneficial effects:

本发明实施例提供的带互感器的三相三线计量装置接线检测方法,仅通过电桥装置在不带电不拆接线的情况下,通过对计量回路中电流回路和电压回路进行校验阻抗值的方法实现对计量装置的有效检测,降低接线错误或极性反接风险,准确锁定接线错误点,提高工作效率,减少不必要的供用电纠纷。The method for detecting the wiring of a three-phase three-wire metering device with a transformer provided by the embodiment of the present invention only uses the bridge device to verify the impedance value of the current circuit and the voltage circuit in the metering circuit under the condition that the bridge device is not charged and does not disconnect the wiring. The method realizes the effective detection of the metering device, reduces the risk of wrong wiring or reversed polarity, accurately locks the wrong point of the wiring, improves the work efficiency, and reduces unnecessary power supply and consumption disputes.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,根据这些附图获得其他的附图仍属于本发明的范畴。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention, and for those of ordinary skill in the art, obtaining other drawings according to these drawings still belongs to the scope of the present invention without any creative effort.

图1为本发明提供的带互感器的三相三线计量装置接线检测方法的一个实施例的主流程示意图。FIG. 1 is a schematic diagram of the main flow of an embodiment of the wiring detection method for a three-phase three-wire metering device with a transformer provided by the present invention.

图2为本发明提供的带互感器的三相三线计量装置接线检测方法的计量装置的电路连接图Fig. 2 is the circuit connection diagram of the metering device of the three-phase three-wire metering device wiring detection method with transformer provided by the present invention

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明作进一步地详细描述。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings.

如图1所示为本发明提供的带互感器的三相三线计量装置接线检测方法的一个实施例的主流程示意图,在本实施例中,所述方法包括如下步骤:1 is a schematic diagram of the main flow of an embodiment of a method for detecting the connection of a three-phase three-wire metering device with a transformer provided by the present invention. In this embodiment, the method includes the following steps:

步骤S1,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况;Step S1, utilizes the bridge device with the impedance measurement loop to measure the target metering device, detects the impedance value of its current loop, and judges the current loop wiring condition according to the detected result;

如图2所示,在本发明的一个实施例中,测量A相电流回路,断开计量装置的接线盒连片LA1,使用电桥装置的测量夹子分别连接端子KA1和端子A4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;As shown in Figure 2, in one embodiment of the present invention, the A-phase current loop is measured, the junction box connecting piece LA1 of the metering device is disconnected, the measuring clip of the bridge device is used to connect the terminal KA1 and the terminal A4 respectively, and the bridge is started. The device detects the result of its impedance value. If the result of the reactance value is not zero, the connection between the CT and the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, Then there is a disconnection point in the current loop;

将计量装置的接线盒连片LA1闭合,再次启动电桥装置,检测A相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点。Close the junction box connecting piece LA1 of the metering device, start the bridge device again, and detect the result of the impedance value of the A-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the result of the reactance value If not zero, there is a disconnection point in the wiring circuit from the junction box to the meter.

更具体的,测量C相电流回路,断开计量装置的接线盒连片LC1,使用电桥装置的测量夹子分别连接端子KC1和端子C4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;More specifically, measure the C-phase current loop, disconnect the junction box connecting piece LC1 of the metering device, use the measuring clip of the bridge device to connect the terminal KC1 and the terminal C4 respectively, start the bridge device, and detect the result of its impedance value, if the reactance If the result of the resistance value is not zero, the connection between the CT and the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, there is a disconnection point in the current loop;

将计量装置的接线盒连片LC1闭合,再次启动电桥装置,检测C相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点。Close the junction box connection piece LC1 of the metering device, start the bridge device again, and detect the result of the impedance value of the C-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the result of the reactance value If not zero, there is a disconnection point in the wiring circuit from the junction box to the meter.

进一步,所述检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到阻抗值为零时,进行步骤S2。Further, after the impedance value of the current loop is detected, after judging the wiring condition of the current loop according to the detection result, the connection point of the connection loop is adjusted according to the detection result of the impedance value, and the impedance value of the loop is repeatedly measured until the impedance value is zero. , and go to step S2.

在本实施例中,步骤S2,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况。In this embodiment, in step S2, a bridge device with an impedance measurement loop is used to measure the target metering device, to detect the impedance value of its voltage loop, and to determine the connection of the voltage loop according to the detection result.

如图2所示,具体的,测量A相电压回路,将电桥装置的测量夹子分别连接端子PA1和端子PA2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则A相电压回路中存在断点。As shown in Figure 2, specifically, measure the A-phase voltage loop, connect the measuring clips of the bridge device to terminal PA1 and terminal PA2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, Then the wiring is correct. If the result of the impedance value is not zero, there is a breakpoint in the A-phase voltage loop.

更具体的,测量B相电压回路,将电桥装置的测量夹子分别连接端子PB1和端子B2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则B相电压回路中存在断点。More specifically, measure the B-phase voltage loop, connect the measuring clips of the bridge device to terminal PB1 and terminal B2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. If the result of the impedance value is not zero, there is a break in the B-phase voltage loop.

更具体,测量C相电压回路,将电桥装置的测量夹子分别连接端子PC1和端子PC2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则C相电压回路中存在断点。More specifically, measure the C-phase voltage loop, connect the measuring clips of the bridge device to terminal PC1 and terminal PC2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. The result of the value is not zero, then there is a breakpoint in the C-phase voltage loop.

进一步,所述检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到阻抗值为零结束。Further, the impedance value of the voltage loop is detected, and after judging the connection of the voltage loop according to the detection result, the connection point of the connection loop is adjusted according to the detection result of the impedance value, and the impedance value of the loop is repeatedly measured until the impedance value is zero. .

在本发明的实施例中,利用电流互感器、电压互感器线圈的电感特性,结合电能计量装置典型接线方式,通过电桥检测计量回路的电感值,从而判断接线正确与否。In the embodiment of the present invention, the inductance characteristics of the coils of the current transformer and the voltage transformer are used, combined with the typical wiring mode of the electric energy metering device, the inductance value of the metering loop is detected by the bridge, so as to determine whether the wiring is correct or not.

更多的细节,可以参照并结合前述对附图的描述,在此不进行详述。For more details, reference may be made to and combined with the foregoing description of the accompanying drawings, which will not be described in detail here.

实施本发明实施例,具有如下有益效果:Implementing the embodiment of the present invention has the following beneficial effects:

本发明实施例提供带互感器的三相三线计量装置接线检测方法;仅通过电桥装置在不带电不拆接线的情况下,通过对计量回路中电流回路和电压回路进行校验阻抗值的方法实现对计量装置的有效检测,降低接线错误或极性反接风险,准确锁定接线错误点,提高工作效率,减少不必要的供用电纠纷。The embodiment of the present invention provides a method for detecting the wiring of a three-phase three-wire metering device with a transformer; a method for verifying the impedance value of the current circuit and the voltage circuit in the metering circuit only through the bridge device without the wiring being disconnected. It can effectively detect the metering device, reduce the risk of wiring errors or reverse polarity, accurately lock the wiring errors, improve work efficiency, and reduce unnecessary power supply disputes.

以上所揭露的仅为本发明一种较佳实施例而已,当然不能以此来限定本发明之权利范围,因此依本发明权利要求所作的等同变化,仍属本发明所涵盖的范围。The above disclosure is only a preferred embodiment of the present invention, and of course, it cannot limit the scope of the rights of the present invention. Therefore, the equivalent changes made according to the claims of the present invention are still within the scope of the present invention.

Claims (4)

1.一种带互感器的三相三线计量装置接线检测方法,其特征在于,包括如下步骤:1. a three-phase three-wire metering device wiring detection method with transformer, is characterized in that, comprises the steps: 步骤S1,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况;Step S1, using a bridge device with an impedance measurement loop to measure the target metering device, detect the impedance value of its current loop, and determine the current loop wiring condition according to the detection result; 其中,测量A相电流回路,断开计量装置的接线盒连片LA1,使用电桥装置的测量夹子分别连接端子KA1和端子A4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;Among them, measure the A-phase current loop, disconnect the junction box connection piece LA1 of the metering device, use the measuring clip of the bridge device to connect the terminal KA1 and the terminal A4 respectively, start the bridge device, and detect the result of its impedance value. If the result is not zero, the connection from CT to the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, there is a disconnection point in the current loop; 其中,将计量装置的接线盒连片LA1闭合,再次启动电桥装置,检测A相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点;Among them, close the junction box connection piece LA1 of the metering device, start the bridge device again, and detect the result of the impedance value of the A-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the reactance value If the result is not zero, there is a disconnection point in the wiring circuit from the junction box to the meter; 其中,测量C相电流回路,断开计量装置的接线盒连片LC1,使用电桥装置的测量夹子分别连接端子KC1和端子C4,启动电桥装置,检测其阻抗值的结果,若电抗值的结果不为零,则CT至接线盒接线正确,若电阻值的结果为零,则接线两端的极性相反,若电阻值的结果为无穷大,则电流回路中存在断开点;Among them, measure the C-phase current loop, disconnect the junction box connection piece LC1 of the metering device, use the measuring clip of the bridge device to connect the terminals KC1 and C4 respectively, start the bridge device, and detect the result of its impedance value. If the result is not zero, the connection from CT to the junction box is correct. If the result of the resistance value is zero, the polarities of both ends of the connection are opposite. If the result of the resistance value is infinite, there is a disconnection point in the current loop; 其中,将计量装置的接线盒连片LC1闭合,再次启动电桥装置,检测C相电流回路的阻抗值的结果,若电阻值的结果为零,则整个计量装置的回路接线正确;若电抗值的结果不为零,则接线盒至电表接线回路中存在断开点;Among them, close the junction box connection piece LC1 of the metering device, start the bridge device again, and detect the result of the impedance value of the C-phase current loop. If the result of the resistance value is zero, the circuit wiring of the entire metering device is correct; if the reactance value If the result is not zero, there is a disconnection point in the wiring circuit from the junction box to the meter; 步骤S2,利用带阻抗测量回路的电桥装置测量目标计量装置,检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况;Step S2, utilize the bridge device with impedance measurement loop to measure the target metering device, detect the impedance value of its voltage loop, and judge the voltage loop wiring condition according to the detection result; 其中,测量A相电压回路,将电桥装置的测量夹子分别连接端子PA1和端子PA2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则A相电压回路中存在断点;Among them, measure the A-phase voltage loop, connect the measuring clips of the bridge device to the terminal PA1 and the terminal PA2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. The result is not zero, then there is a breakpoint in the A-phase voltage loop; 其中,测量C相电压回路,将电桥装置的测量夹子分别连接端子PC1和端子PC2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则C相电压回路中存在断点;Among them, measure the C-phase voltage loop, connect the measuring clips of the bridge device to the terminal PC1 and the terminal PC2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. The result is not zero, then there is a breakpoint in the C-phase voltage loop; 其中:in: 端子PA1、PC1分别为电压互感器二次侧的A相接线端子、C相接线端子;Terminals PA1 and PC1 are the A-phase connection terminals and C-phase connection terminals of the secondary side of the voltage transformer respectively; 端子PA2、PC2分别为电表的A相电压接线端子、C相电压接线端子;Terminals PA2 and PC2 are the A-phase voltage connection terminals and C-phase voltage connection terminals of the meter respectively; 端子KA1为电流互感器的A相k1接线端子,端子KA2为电流互感器的A相k2接线端子;The terminal KA1 is the A-phase k1 terminal of the current transformer, and the terminal KA2 is the A-phase k2 terminal of the current transformer; 端子KC1为电流互感器的C相k1接线端子,端子KC2为电流互感器的C相k2接线端子;The terminal KC1 is the C-phase k1 connection terminal of the current transformer, and the terminal KC2 is the C-phase k2 connection terminal of the current transformer; 连片LA1为接线盒A相电流回路的短接连片;The connecting piece LA1 is the short connecting piece of the A-phase current loop of the junction box; 连片LC1为接线盒C相电流回路的短接连片;The connecting piece LC1 is the short connecting piece of the C-phase current loop of the junction box; 端子A4为接线盒A相电流接线端子;Terminal A4 is the terminal box A-phase current terminal; 端子C4为接线盒C相电流接线端子。Terminal C4 is the C-phase current connection terminal of the junction box. 2.如权利要求1所述的方法,其特征在于,所述步骤S2中检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况包括,2. The method according to claim 1, wherein the impedance value of the voltage loop is detected in the step S2, and judging the connection condition of the voltage loop according to the detection result includes: 测量B相电压回路,将电桥装置的测量夹子分别连接端子PB1和端子PB2,启动电桥装置,检测其阻抗值的结果,若阻抗值的结果为零,则接线正确,若阻抗值的结果不为零,则B相电压回路中存在断点;Measure the B-phase voltage loop, connect the measuring clips of the bridge device to terminal PB1 and terminal PB2 respectively, start the bridge device, and detect the result of its impedance value. If the result of the impedance value is zero, the wiring is correct. If it is not zero, there is a breakpoint in the B-phase voltage loop; 其中:in: 端子PB1为电压互感器二次侧的B相接线端子;Terminal PB1 is the B-phase connection terminal of the secondary side of the voltage transformer; 端子PB2为电表的B相电压接线端子。Terminal PB2 is the B-phase voltage connection terminal of the meter. 3.如权利要求1所述的方法,其特征在于,所述检测其电流回路的阻抗值,根据检测的结果判断电流回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到整个计量装置的回路接线正确时,进行步骤S2。3. The method according to claim 1, wherein the impedance value of the current loop is detected, and after judging the current loop wiring condition according to the detected result, the connection loop connection point adjustment is performed according to the detection result of the impedance value, Repeat the measurement of the impedance value of the loop until the loop wiring of the entire metering device is correct, then go to step S2. 4.如权利要求2所述的方法,其特征在于,所述检测其电压回路的阻抗值,根据检测的结果判断电压回路接线情况之后,根据阻抗值的检测结果,进行连接回路连接点调整,重复测量回路的阻抗值,直到阻抗值为零结束。4. The method according to claim 2, wherein, the impedance value of the voltage loop is detected, and after judging the voltage loop wiring condition according to the detection result, the connection loop connection point adjustment is performed according to the detection result of the impedance value, Repeatedly measure the impedance value of the loop until the impedance value is zero.
CN201910870249.0A 2019-09-16 2019-09-16 A three-phase three-wire metering device wiring detection method with transformer Active CN110632448B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910870249.0A CN110632448B (en) 2019-09-16 2019-09-16 A three-phase three-wire metering device wiring detection method with transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910870249.0A CN110632448B (en) 2019-09-16 2019-09-16 A three-phase three-wire metering device wiring detection method with transformer

Publications (2)

Publication Number Publication Date
CN110632448A CN110632448A (en) 2019-12-31
CN110632448B true CN110632448B (en) 2022-07-15

Family

ID=68972508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910870249.0A Active CN110632448B (en) 2019-09-16 2019-09-16 A three-phase three-wire metering device wiring detection method with transformer

Country Status (1)

Country Link
CN (1) CN110632448B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111650535B (en) * 2020-05-29 2022-07-15 深圳供电局有限公司 Electric energy meter wiring detection method
CN111650538B (en) * 2020-05-29 2022-07-26 深圳供电局有限公司 A kind of electric energy meter wiring detection device and method
CN113820632A (en) * 2020-06-18 2021-12-21 杭州普安科技有限公司 Passive power secondary circuit wiring checking system and method
CN112345980B (en) * 2020-12-11 2025-03-11 国家电网有限公司 A current secondary connection missing warning device
CN112986856A (en) * 2021-03-26 2021-06-18 西安热工研究院有限公司 Method for checking integrity of three-phase current secondary circuit of power plant
CN116482581B (en) * 2023-06-20 2023-11-14 广东电网有限责任公司佛山供电局 Transformer substation voltage transformer opening triangle voltage secondary circuit tester

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2199540Y (en) * 1994-07-25 1995-05-31 宋伟新 Fast measuring bridge for DC resistance of power transformer
CN101713809A (en) * 2009-12-10 2010-05-26 贵州电力试验研究院 Checking method of CT secondary wire in switch cabinet
CN205210166U (en) * 2015-10-29 2016-05-04 国网山东省电力公司电力科学研究院 Electric detection means is stolen in reposition of redundant personnel
CN106569085A (en) * 2016-10-27 2017-04-19 国网内蒙古东部电力有限公司电力科学研究院 Current transformer secondary circuit cable checking method
CN106645931A (en) * 2016-11-29 2017-05-10 国网四川省电力公司电力科学研究院 Current transformer secondary circuit monitoring module and method, and specific transformer acquiring terminal
CN106707026A (en) * 2017-01-05 2017-05-24 中国电力科学研究院 Device for measuring electric reactance of electric energy metering secondary circuit
CN107037303A (en) * 2016-11-07 2017-08-11 北京博纳电气股份有限公司 Detection means and detection method for tested CT secondary side circuit states outside ammeter
CN107656104A (en) * 2017-10-31 2018-02-02 广东电网有限责任公司电力科学研究院 A kind of intelligent wiring box and critical point electric energy metering secondary state monitoring method
CN107817463A (en) * 2017-11-20 2018-03-20 国网福建省电力有限公司 A kind of electricity anti-theft method for detecting short circuit electric energy meter
CN107976648A (en) * 2017-10-15 2018-05-01 四川罡正电子科技有限公司 A kind of Electric control measuring instrument automatic connection test method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2199540Y (en) * 1994-07-25 1995-05-31 宋伟新 Fast measuring bridge for DC resistance of power transformer
CN101713809A (en) * 2009-12-10 2010-05-26 贵州电力试验研究院 Checking method of CT secondary wire in switch cabinet
CN205210166U (en) * 2015-10-29 2016-05-04 国网山东省电力公司电力科学研究院 Electric detection means is stolen in reposition of redundant personnel
CN106569085A (en) * 2016-10-27 2017-04-19 国网内蒙古东部电力有限公司电力科学研究院 Current transformer secondary circuit cable checking method
CN107037303A (en) * 2016-11-07 2017-08-11 北京博纳电气股份有限公司 Detection means and detection method for tested CT secondary side circuit states outside ammeter
CN106645931A (en) * 2016-11-29 2017-05-10 国网四川省电力公司电力科学研究院 Current transformer secondary circuit monitoring module and method, and specific transformer acquiring terminal
CN106707026A (en) * 2017-01-05 2017-05-24 中国电力科学研究院 Device for measuring electric reactance of electric energy metering secondary circuit
CN107976648A (en) * 2017-10-15 2018-05-01 四川罡正电子科技有限公司 A kind of Electric control measuring instrument automatic connection test method
CN107656104A (en) * 2017-10-31 2018-02-02 广东电网有限责任公司电力科学研究院 A kind of intelligent wiring box and critical point electric energy metering secondary state monitoring method
CN107817463A (en) * 2017-11-20 2018-03-20 国网福建省电力有限公司 A kind of electricity anti-theft method for detecting short circuit electric energy meter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
电能计量装置接线正误判定方法探讨;青志明等;《电工技术》;20190531(第9期);第96-97,114页 *

Also Published As

Publication number Publication date
CN110632448A (en) 2019-12-31

Similar Documents

Publication Publication Date Title
CN110632448B (en) A three-phase three-wire metering device wiring detection method with transformer
CN104267368B (en) A kind of current transformer for metering secondary circuit failure monitoring method
CN111983521A (en) An electric energy meter with functions of automatic identification of wrong wiring and correct measurement and method thereof
CN104237738A (en) Distribution feeder single-phase grounding location system and location method
CN102087351B (en) Watt-hour meter inspection quality real-time monitoring device and method
CN109613386A (en) The detection method and device of three phase mains inlet wire zero curve misconnection, automatic change-over
CN114518549B (en) A method and system for real-time monitoring of incorrect wiring modes of three-phase smart meters
CN103675749A (en) Performance detector of electric energy meter under direct current and even harmonic conditions
CN109031154A (en) High accuracy battery AC internal Resistance detection device
CN103645415A (en) Practical method of inspecting electric energy metering device wiring in charged mode
CN117554880A (en) Method and device for detecting faults of secondary circuit of high-voltage transformer for metering
CN117517869A (en) Fault diagnosis system of high-voltage direct-current circuit
CN212658814U (en) Passive power secondary circuit wiring inspection system
CN107884737B (en) Wireless high-precision synchronous on-site capacitive equipment on-line monitoring and checking system and method
CN108107313A (en) The method that unloaded situation judges connection box of electric energy meter correctness
CN106526527A (en) Method for searching minimal inclination angle to determine low-voltage three-phase four-wire wiring
CN108845225A (en) Correctness Analysis Method of Power Capacitor and Reactor Secondary Current Loop Wiring Based on Fault Component Detection
CN102621519A (en) Tester for electric energy metering device
CN113820632A (en) Passive power secondary circuit wiring checking system and method
CN107037307A (en) A kind of secondary through-flow method of power plant main system c-type
CN207882428U (en) Portable electric energy measurement wiring calibration equipment
CN110006325A (en) A kind of deformation of transformer winding intelligent detecting method based on frequency sweep impedance
CN203101571U (en) Secondary common loop multipoint earth fault testing device
CN108152782A (en) A kind of test method of massive quantity power supply and measurement electric energy meter more positive coefficient
CN219016553U (en) Three-phase misconnection prevention detection circuit and air conditioner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant