[go: up one dir, main page]

CN110528501A - High rich water faces sea area diaphragm wall and connects sealing device - Google Patents

High rich water faces sea area diaphragm wall and connects sealing device Download PDF

Info

Publication number
CN110528501A
CN110528501A CN201910669495.XA CN201910669495A CN110528501A CN 110528501 A CN110528501 A CN 110528501A CN 201910669495 A CN201910669495 A CN 201910669495A CN 110528501 A CN110528501 A CN 110528501A
Authority
CN
China
Prior art keywords
wall
steel
width
shaped steel
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910669495.XA
Other languages
Chinese (zh)
Inventor
白晓宇
张明义
王永洪
王海刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao University of Technology
Original Assignee
Qingdao University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao University of Technology filed Critical Qingdao University of Technology
Priority to CN201910669495.XA priority Critical patent/CN110528501A/en
Publication of CN110528501A publication Critical patent/CN110528501A/en
Priority to PCT/CN2020/103604 priority patent/WO2021013201A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明属于基坑支护技术领域,涉及一种高富水临海地区地连续墙接头止水装置,连续墙水平筋和连续墙竖向主筋机械连接,钢花管绑扎搭接在第一墙幅钢筋笼上;镀锌铁皮安装在工字型钢板的外侧,镀锌铁皮和压条钢筋点焊焊接,工字钢与第一墙幅钢筋笼焊接连接,u形箍筋和连续墙水平筋单面焊接连接,注浆管和第二墙幅钢筋笼绑扎搭接,第二墙幅钢筋笼在吊装嵌固于工字型钢板翼板内;沙袋堆在工字型钢板接头腹板外侧,下填高度为地下连续墙高度;其防水效果理想,能够有效防止混凝土绕流,钢花管的设置确保了接缝处止水效果。

The invention belongs to the technical field of foundation pit support, and relates to a water-stopping device for a diaphragm wall joint in a high-water-rich area near the sea. The horizontal ribs of the diaphragm wall are mechanically connected with the vertical main ribs of the diaphragm wall. Above; the galvanized iron sheet is installed on the outside of the I-shaped steel plate, the galvanized iron sheet is spot-welded with the layered reinforcement, the I-shaped steel is welded to the first wall reinforcement cage, and the U-shaped stirrup is welded to the horizontal reinforcement of the continuous wall on one side. Note The grout pipe and the reinforcement cage of the second wall are bound and lapped, and the reinforcement cage of the second wall is embedded in the I-shaped steel plate wing during hoisting; the sandbags are piled on the outside of the web of the I-shaped steel plate joint, and the height of the underfill is continuous underground The height of the wall; its waterproof effect is ideal, which can effectively prevent the concrete from flowing around, and the setting of the steel flower tube ensures the waterproof effect of the joints.

Description

一种高富水临海地区地连续墙接头止水装置A water-stop device for diaphragm wall joints in high-water-rich coastal areas

技术领域:Technical field:

本发明属于基坑支护技术领域,涉及一种高富水临海地区地连续墙接头止水装置,特别是一种以工字形钢为接头的止水装置。The invention belongs to the technical field of foundation pit support, and relates to a water-stopping device for joints of continuous walls in high-water-rich coastal areas, in particular to a water-stopping device with I-shaped steel as the joint.

背景技术:Background technique:

地下连续墙是一种重要的深基坑支护结构形式,其基本的工艺流程包括:导墙施工、泥浆制备、成槽施工、钢筋笼制作、钢筋笼吊装、接头处理、水下混凝土灌注等,其中地下连续墙接头处(特别是在一种高富水临海地区)的施工)是影响地下连续墙防渗止水的技术难题。Diaphragm wall is an important form of deep foundation pit support structure. Its basic process includes: guide wall construction, mud preparation, trench construction, steel cage production, steel cage hoisting, joint treatment, underwater concrete pouring, etc. , wherein the construction of the joints of the underground diaphragm wall (especially in a high-rich water-facing area) is a technical problem affecting the anti-seepage and water-proofing of the underground diaphragm wall.

目前,常用的地下连续墙接头处施工方法包括以下几种:一是圆形接头管技术:是清底换浆后置入槽段的一端或两端,混凝土初凝后,用拔管器拔起,其特点是造价低廉,方法成熟,适用广泛,但拔管时间难掌握,防水效果不理想;二是“一”或“十”型钢板接头:成槽后,随钢筋笼置入槽段,做为一次性防水装置,钢板两侧嵌入前后施工两幅连续墙内,其特点使用广泛,造价便宜,但接缝处混凝土接触不良,易夹砂;三是“工”或“王”型钢接头:成槽后,置入相应槽段做为一次性防水装置,钢筋笼嵌入型钢板翼板内,其特点是适应于富水地层,整体性好,防水效果突出,不足是造价昂贵;四是旋喷桩防水接头:连续墙浇筑完成后,在接缝处外侧,打入旋喷桩防水,特点是适用于软弱底层,防水效果一般,缺点是施工周期长,造价昂贵;五是橡胶止水带接头:由特质的接头管带入既定位置,下个槽段开槽后拔出接头管,其适用于较浅连续墙,防绕流,但其施工复杂,整体刚度差,如CN200910193231.8公开了一种地下连续墙接头柔性止水带安装装置及方法,所述安装装置为由钢板或型钢制作成的宽度和厚度之比接近1的接头管结构,其与混凝土相接触的一侧设有至少一个可安装橡胶止水带的安装槽,且所述安装槽的开口处的宽度比槽腔的宽度略小。由于接头管的宽厚比接近1。近年来出现了注浆式接头,如201810132066.4公开了一种可注浆式地下连续墙接头及其施工方法,其特点是地墙接头在迎土面一侧设有两注浆管组成可注浆的地下连续墙接头,所述地墙接头采用刚性接头连接时,两注浆管由圆环将其固定在刚性接头迎土面的一侧,采用柔性接头连接时,两注浆管分别固定在钢筋笼迎土面的两端,具体施工包括:导墙、单元槽段和地下连续墙的施工;但是由于工程地质条件差,地下连续墙成槽质量是重难点,而且该止水方法施工成本高。At present, the commonly used construction methods at the joints of underground diaphragm walls include the following: One is the circular joint pipe technology: after cleaning the bottom and changing the grout, it is inserted into one or both ends of the groove section. First, it is characterized by low cost, mature method, and wide application, but it is difficult to control the time of extubation, and the waterproof effect is not ideal; the second is "one" or "ten" steel plate joint: after the groove is formed, it is placed into the groove section with the steel cage , as a one-time waterproof device, the two sides of the steel plate are embedded in the two continuous walls of the front and back construction. Its characteristics are widely used and the cost is cheap, but the concrete at the joints is poorly contacted and sand is easy to be included; the third is "gong" or "king" steel Joint: After the groove is formed, put it into the corresponding groove section as a one-time waterproof device. The steel cage is embedded in the steel plate wing plate. It is characterized by being suitable for water-rich strata, with good integrity and outstanding waterproof effect. The disadvantage is that it is expensive; four. It is the waterproof joint of the rotary grouting pile: After the continuous wall is poured, the rotary grouting pile is driven into the outer side of the joint for waterproofing. It is characterized by being suitable for the weak bottom layer and has a general waterproof effect. Hose joint: brought into the predetermined position by a special joint pipe, and the joint pipe is pulled out after the next slot section is slotted. It is suitable for shallow continuous walls and prevents circumvention, but its construction is complicated and the overall rigidity is poor, such as CN200910193231. 8 discloses an installation device and method for an underground diaphragm wall joint flexible waterstop. The installation device is a joint pipe structure made of steel plates or section steel with a ratio of width to thickness close to 1. A part of the joint that is in contact with concrete At least one installation groove for installing a rubber water stop belt is provided on the side, and the width of the opening of the installation groove is slightly smaller than the width of the groove cavity. Since the aspect ratio of the joint pipe is close to 1. In recent years, grouting joints have appeared. For example, 201810132066.4 discloses a groutable underground diaphragm wall joint and its construction method. The underground diaphragm wall joint, when the ground wall joint is connected by a rigid joint, the two grouting pipes are fixed on the side of the rigid joint facing the soil by a ring, and when the flexible joint is used, the two grouting pipes are respectively fixed on The two ends of the steel cage facing the soil surface, the specific construction includes: the construction of the guide wall, the unit groove section and the underground diaphragm wall; however, due to the poor engineering geological conditions, the quality of the groove formed by the underground diaphragm wall is a major and difficult point, and the construction cost of this water-stopping method is high.

因此,基于各种地下连续墙接头处施工方法以及工程地质情况的不同,合理选择地下连续墙接头处的结构形式变得尤为重要。Therefore, based on the different construction methods and engineering geological conditions of various underground diaphragm wall joints, it is particularly important to reasonably select the structural form of underground diaphragm wall joints.

发明内容:Invention content:

本发明的目的在于克服现有技术存在的缺点,设计提供一种在高富水临海地区地连续墙接头止水装置,实现在地下连续墙接头处在施工以及支护过程中时防渗止水。The purpose of the present invention is to overcome the shortcomings of the prior art, and to design and provide a water-stopping device for diaphragm wall joints in high-water-rich coastal areas, so as to prevent seepage and water at the joints of underground diaphragm walls during construction and support.

为了实现上述目的,本发明所述高富水临海地区地下连续墙接头止水装置的主体结构包括工字型钢板、连续墙水平筋、连续墙竖向主筋、u形箍筋、镀锌铁皮、压条钢筋、钢花管、注浆管、第一墙幅钢筋笼、第二墙幅钢筋笼和沙袋;连续墙水平筋和连续墙竖向主筋机械连接,钢花管绑扎搭接在第一墙幅钢筋笼上;镀锌铁皮安装在工字型钢板的外侧,镀锌铁皮和压条钢筋点焊焊接,工字钢与第一墙幅钢筋笼焊接连接,焊缝长度为100mm;u形箍筋和连续墙水平筋单面焊接连接,注浆管和第二墙幅钢筋笼绑扎搭接,第二墙幅钢筋笼在吊装嵌固于工字型钢板翼板内;沙袋堆在工字型钢板接头腹板外侧,下填高度为地下连续墙高度。In order to achieve the above object, the main structure of the underground diaphragm wall joint water stop device in the high-rich water near the sea area of the present invention includes I-shaped steel plates, diaphragm wall horizontal ribs, diaphragm wall vertical main ribs, U-shaped stirrups, galvanized iron sheets, layered steel bars , steel flower pipe, grouting pipe, reinforcement cage for the first wall width, reinforcement cage for the second wall width and sandbags; the horizontal reinforcement of the continuous wall and the vertical main reinforcement of the continuous wall are mechanically connected, and the steel flower pipe is bound and lapped on the reinforcement cage for the first wall width ; The galvanized iron sheet is installed on the outside of the I-shaped steel plate, and the galvanized iron sheet and the layered steel bar are spot welded, and the I-shaped steel is welded to the first wall reinforcement cage, and the weld length is 100mm; The grouting pipe and the second wall reinforcement cage are bound and overlapped, and the second wall reinforcement cage is hoisted and embedded in the I-shaped steel plate wing; sandbags are piled on the outside of the I-shaped steel plate joint web, and the lower The fill height is the height of the underground diaphragm wall.

本发明所述工字型钢板由H型钢板焊接而成,其翼缘的宽度为400mm,翼缘的厚度为10mm,腹板的高度为160mm,腹板的厚度为10mm。The I-shaped steel plate of the present invention is welded by H-shaped steel plate, the width of the flange is 400mm, the thickness of the flange is 10mm, the height of the web is 160mm, and the thickness of the web is 10mm.

本发明所述连续墙水平筋和连续墙竖向主筋根据工程需要选择型号和大小。The type and size of the horizontal reinforcement of the diaphragm wall and the vertical main reinforcement of the diaphragm wall are selected according to the needs of the project.

本发明所述u形箍筋的型号及间距与连续墙水平筋相同,u形箍筋的弯起角度为45°,使第二墙幅钢筋笼在吊装时更好的嵌固于工字钢翼板内,便于施工。The type and spacing of the U-shaped stirrups in the present invention are the same as those of the horizontal bars of the continuous wall, and the bending angle of the U-shaped stirrups is 45°, so that the second wall reinforcement cage can be better embedded in the I-beam during hoisting Inside the wing plate, it is convenient for construction.

本发明所述镀锌铁皮的厚为0.3mm,宽为500mm,当在槽段混凝土浇筑时向外撑开,镀锌铁皮防止混凝土流入相邻未成槽的槽段。The galvanized iron sheet of the present invention has a thickness of 0.3 mm and a width of 500 mm. When concrete is poured in the trough section, it is stretched outwards, and the galvanized iron sheet prevents concrete from flowing into the adjacent ungrooved trough section.

本发明所述压条钢筋的型号和大小采用C20,在距离工字型钢板边缘100mm处与镀锌铁皮点焊焊接。The type and size of the layered steel bars in the present invention are C20, and they are spot-welded with galvanized iron sheets at a distance of 100 mm from the edge of the I-shaped steel plate.

本发明所述钢花管的直径为A50,其壁厚为3mm,高度与地下连续墙的高度相当,两根钢花管在距离工字型钢板1水平100mm处与第一墙幅钢筋笼绑扎连接,钢花管的作用是在止水结构成形后基坑开挖前进行注浆补强,确保接缝处止水效果,注浆管的大小与钢花管相同。The diameter of the steel flower pipes described in the present invention is A50, its wall thickness is 3mm, and its height is equivalent to the height of the underground diaphragm wall. The role of the steel flower pipe is to carry out grouting reinforcement after the water-stop structure is formed and before the excavation of the foundation pit to ensure the water-stop effect at the joints. The size of the grout pipe is the same as that of the steel flower pipe.

本发明实现高富水临海地区地下连续墙接头止水的具体过程为:The specific process of the present invention to realize the waterproofing of the joints of the underground diaphragm wall in the area of high-rich water near the sea is as follows:

(1)浇筑导墙:采用现有施工工艺依次进行场地平整→测量放样→开挖导墙沟及处理废土→绑扎导墙钢筋、安装立墙外侧模板→浇筑墙体混凝土→拆除模板加横向支撑→槽内分层回填土方;(1) Pouring guide wall: use the existing construction technology to level the site → measure and stake out → excavate the guide wall trench and dispose of waste soil → tie the guide wall reinforcement, install the outer formwork of the vertical wall → pour the wall concrete → remove the formwork and add horizontal Support→layered earthwork backfilling in the trench;

(2)泥浆制备:在成槽过程中,泥浆起到护壁、携渣、冷却机具、切土润滑的作用,性能良好的泥浆能确保成槽时槽壁的稳定,防止塌槽,同时在砼浇灌时对保证砼的浇灌质量起着极其重要的作用;根据所在地质、地下水性质及施工经验进行泥浆配合比设计,使配置的泥浆指标符合施工要求,泥浆配置的过程为:先将水加至搅拌筒1/3后,启动制浆机,再在定量水箱不断加水的同时,加入膨润土粉,搅拌10min后,加入CMC液和碱粉等外加剂继续搅拌10min即可停止搅拌放入新浆池中,待静置膨化24h后使用;(2) Mud preparation: In the process of trough formation, the mud plays the role of wall protection, slag carrying, cooling equipment, and cutting soil lubrication. The mud with good performance can ensure the stability of the trough wall during trough formation and prevent the trough from collapsing. When pouring, it plays an extremely important role in ensuring the quality of concrete pouring; the mud mix ratio is designed according to the geology, groundwater properties and construction experience, so that the configured mud index meets the construction requirements. The process of mud configuration is: first add water to After 1/3 of the mixing drum, start the pulping machine, and then add bentonite powder while continuously adding water to the quantitative water tank. After stirring for 10 minutes, add CMC liquid and alkali powder and other admixtures and continue stirring for 10 minutes, then stop stirring and put it into the new pulp tank In the middle, use it after standing for 24 hours of puffing;

(3)Ⅰ期槽段开挖:将首开槽作为试验槽段,收集成槽施工的各类参数和数据等,试成槽后地连墙常规成槽,根据设计图纸及导墙确定Ⅰ期槽段开挖位置,成槽机进行开挖作业;成槽时采用泥浆护壁,成槽后根据相关规范对槽孔进行验收,槽段完成后用刷壁器斜铲铲除未脱落的硬物,进行槽壁清理;该过程为控制正式成槽施工过程的垂直度、泥浆参数,保证工程实施的连续性,达到指导施工的目的;(3) Excavation of the trench section in phase I: the first trench is used as the test trench section, and various parameters and data of the trench construction are collected. After the trench is tested, the ground connection wall is routinely trenched, and the phase I is determined according to the design drawings and the guide wall The excavation position of the slot section is excavated by the slotting machine; the mud wall is used when the slot is formed, and the slot hole is checked and accepted according to the relevant specifications after the slot is completed. Carry out tank wall cleaning; this process is to control the verticality and mud parameters of the formal trench construction process, ensure the continuity of project implementation, and achieve the purpose of guiding construction;

(4)钢筋笼制作:将第一墙幅钢筋笼采用现有技术按施工要求制作好后与工字型钢板焊接,同时安装好镀锌铁皮和压条钢筋;(4) Reinforcement cage production: The first wall width reinforcement cage is manufactured according to the construction requirements by the existing technology and then welded with the I-shaped steel plate, and the galvanized iron sheet and layered steel bars are installed at the same time;

(5)步骤(3)清槽结束后经检验成槽质量和泥浆指标,合格后吊放接头箱,将第一幅钢筋笼下放到既定位置,在工字型钢板接头外侧填筑沙袋,防止混凝土外流;为减少地下连续墙墙竖向沉降和相应的地表沉降,在工字型钢板接头处用预设的钢花管进行注浆加固,然后通过预埋的注浆管水下浇筑首幅地下连续墙,浇筑完成后起拔接头箱;(5) Step (3) After the cleaning of the tank, the quality of the tank and the mud index are inspected. After passing the test, the joint box is lifted, the first steel cage is lowered to the predetermined position, and sandbags are filled outside the I-shaped steel plate joint to prevent Outflow of concrete; in order to reduce the vertical settlement of the underground diaphragm wall and the corresponding surface settlement, grouting reinforcement is carried out at the joints of the I-shaped steel plates with preset steel flower pipes, and then the first underground wall is poured underwater through the pre-buried grouting pipes. Diaphragm wall, pull out the joint box after pouring is completed;

(6)相邻槽段Ⅱ期完成后,先用刷壁器斜铲铲除未脱落的硬物,再用刷壁器钢丝刷自上而下分段刷洗Ⅰ期槽端头工字钢板,上下刷数遍,直至刷子上不带泥屑,孔底淤积不再增加,刷壁后使新老混凝土接合处干净密实;(6) After the completion of Phase II of the adjacent tank section, first use the wall brusher to remove the hard objects that have not fallen off, and then use the wall brusher wire brush to scrub the I-shaped steel plate at the end of the Phase I tank from top to bottom, up and down Brush several times until there is no mud debris on the brush, the accumulation at the bottom of the hole will no longer increase, and the joint between the new and old concrete will be clean and dense after brushing the wall;

(7)吊放接头箱,将第二墙幅钢筋笼吊装嵌固于工字型钢板翼板内,通过注浆管水下浇筑混凝土,浇筑完成后起拔接头箱;(7) Hanging the joint box, hoisting and embedding the second wall reinforcement cage in the I-shaped steel plate wing plate, pouring concrete underwater through the grouting pipe, and pulling out the joint box after the pouring is completed;

(8)其余墙幅按照上述步骤,依次浇筑,直至最后一幅连续墙浇筑完成。(8) The rest of the walls are poured sequentially according to the above steps until the last continuous wall is poured.

本发明与现有技术相比,在高富水临海地区,以工字钢为地下连续墙接头的施工方法比较适用,防水效果较理想;用镀锌铁皮及工字钢外侧填筑沙袋能够有效防止混凝土绕流;而且采用市场销售专门的钢丝刷刷壁,有着良好的刷壁效果,有利于加强混凝土的整体性,增强防水效果;钢花管的设置进一步确保了接缝处止水效果。Compared with the prior art, the present invention is more suitable for the construction method using I-beam as the joint of the underground diaphragm wall in high-rich water and coastal areas, and the waterproof effect is ideal; filling sandbags on the outside of the galvanized iron sheet and I-beam can effectively prevent concrete Circumvention; and the use of special steel wire brushes sold in the market has a good wall brushing effect, which is conducive to strengthening the integrity of the concrete and enhancing the waterproof effect; the setting of the steel flower tube further ensures the water-stopping effect at the joints.

附图说明:Description of the drawings:

图1为本发明所述高富水临海地区地下连续墙接头止水装置的主体结构原理示意图。Fig. 1 is a schematic diagram of the principle structure of the main structure of the underground diaphragm wall joint water-stop device in the high-rich water near the sea area of the present invention.

图2为本发明所述高富水临海地区地下连续墙接头止水装置的主体结构的三维立体图.Fig. 2 is a three-dimensional perspective view of the main structure of the underground diaphragm wall joint water-stopping device in the high-rich water near the sea area of the present invention.

图3为本发明所述工字型钢板结构示意图。Fig. 3 is a schematic diagram of the structure of the I-shaped steel plate of the present invention.

图4为本发明所述钢花管结构示意图。Fig. 4 is a schematic diagram of the structure of the steel flower tube of the present invention.

具体实施方式:Detailed ways:

下面通过实施例并结合附图对本发明作进一步说明。The present invention will be further described below by way of embodiments and in conjunction with the accompanying drawings.

实施例1:Example 1:

本实施例所述高富水临海地区地下连续墙接头止水装置的主体结构包括工字型钢板1、连续墙水平筋2、连续墙竖向主筋3、u形箍筋4、镀锌铁皮5、压条钢筋6、钢花管7、注浆管8、第一墙幅钢筋笼9、第二墙幅钢筋笼10和沙袋11;连续墙水平筋2和连续墙竖向主筋3机械连接,钢花管7绑扎搭接在第一墙幅钢筋笼9上;镀锌铁皮5安装在工字型钢板1的外侧,镀锌铁皮5和压条钢筋6点焊焊接,工字钢1与第一墙幅钢筋笼9焊接连接,焊缝长度为100mm;u形箍筋4和连续墙水平筋2单面焊接连接,注浆管8和第二墙幅钢筋笼10绑扎搭接,第二墙幅钢筋笼10在吊装嵌固于工字型钢板1翼板内;沙袋11堆在工字型钢板1接头腹板外侧,下填高度为地下连续墙高度。The main structure of the underground diaphragm wall joint water-stop device in the high-rich water near the sea area of this embodiment includes I-shaped steel plate 1, diaphragm wall horizontal rib 2, diaphragm wall vertical main rib 3, U-shaped stirrup 4, galvanized iron sheet 5, layering strip Steel bar 6, steel flower pipe 7, grouting pipe 8, first wall reinforcement cage 9, second wall reinforcement cage 10 and sandbag 11; diaphragm wall horizontal reinforcement 2 and diaphragm wall vertical main reinforcement 3 are mechanically connected, and steel flower pipe 7 is bound Lap on the first wall reinforcement cage 9; the galvanized iron sheet 5 is installed on the outside of the I-shaped steel plate 1, the galvanized iron sheet 5 and the bead reinforcement 6 are spot welded, and the I-shaped steel 1 is welded to the first wall reinforcement cage 9 , the weld length is 100mm; the U-shaped stirrup 4 and the horizontal bar 2 of the continuous wall are welded on one side, the grouting pipe 8 and the second wall reinforcement cage 10 are tied and overlapped, and the second wall reinforcement cage 10 is embedded in the hoisting In the I-shaped steel plate 1 wing plate; 11 sandbags are stacked outside the web of the I-shaped steel plate 1 joint, and the height of the underfill is the height of the underground diaphragm wall.

本实施例所述工字型钢板1由H型钢板焊接而成,其翼缘的宽度为400mm,翼缘的厚度为10mm,腹板的高度为160mm,腹板的厚度为10mm。The I-shaped steel plate 1 described in this embodiment is welded by H-shaped steel plates. The width of the flange is 400 mm, the thickness of the flange is 10 mm, the height of the web is 160 mm, and the thickness of the web is 10 mm.

本实施例所述连续墙水平筋2和连续墙竖向主筋3根据工程需要选择型号和大小。The type and size of the horizontal ribs 2 of the diaphragm wall and the vertical main ribs 3 of the diaphragm wall described in this embodiment are selected according to the needs of the project.

本实施例所述u形箍筋4的型号及间距与连续墙水平筋2相同,U形箍筋4的弯起角度为45°,使第二墙幅钢筋笼10在吊装时更好的嵌固于工字钢1翼板内,便于施工。The type and spacing of the U-shaped stirrups 4 described in this embodiment are the same as those of the horizontal ribs 2 of the continuous wall, and the bending angle of the U-shaped stirrups 4 is 45°, so that the second wall width reinforcement cage 10 can be better embedded during hoisting. It is fixed in the I-beam 1 wing plate, which is convenient for construction.

本实施例所述镀锌铁皮5的厚为0.3mm,宽为500mm,当在槽段混凝土浇筑时向外撑开,镀锌铁皮5防止混凝土流入相邻未成槽的槽段。The galvanized iron sheet 5 described in this embodiment has a thickness of 0.3mm and a width of 500mm. When concrete is poured in the groove section, it is stretched outwards, and the galvanized iron sheet 5 prevents the concrete from flowing into the adjacent ungrooved groove section.

本实施例所述压条钢筋6的型号和大小采用C20,在距离工字型钢板1边缘100mm处与镀锌铁皮5点焊焊接。The type and size of the layered steel bars 6 in this embodiment are C20, and they are spot welded with the galvanized iron sheet 5 at a distance of 100 mm from the edge of the I-shaped steel plate 1 .

本实施例所述钢花管7的直径为A50,其壁厚为3mm,高度与地下连续墙的高度相当,两根钢花管7在距离工字型钢板1水平100mm处与第一墙幅钢筋笼9绑扎连接,钢花管7的作用是在止水结构成形后基坑开挖前进行注浆补强,确保接缝处止水效果,注浆管8的大小与钢花管7相同。The diameter of the steel flower pipe 7 described in this embodiment is A50, its wall thickness is 3mm, and its height is equivalent to the height of the underground diaphragm wall. 9 binding connections, the effect of the steel flower pipe 7 is to carry out grouting reinforcement before the excavation of the foundation pit after the water-stop structure is formed, to ensure the water-stop effect at the joint, and the size of the grouting pipe 8 is the same as that of the steel flower pipe 7.

实施例2:Example 2:

本实施例将实施例1所述接头止水装置应用于某地铁站地下连续墙的施工,具体施工过程为:In this embodiment, the joint water-stop device described in Embodiment 1 is applied to the construction of an underground diaphragm wall of a certain subway station. The specific construction process is as follows:

(1)浇筑导墙:测量放线完成后,开始施工导墙,导墙的施工质量直接关系到地下连续墙的施工质量,导墙施工必须严格按照规范标准要求进行,必须严格控制施工质量,导墙断面采用倒“L”型现浇钢筋混凝土,均布HRB400C12@200钢筋骨架,导墙使用C30混凝土,导墙开挖前必须先人工开挖探槽,挖掘机作业时必须有专人旁站监督施工,然后绑扎导墙钢筋和立模板,浇筑C30混凝土,拆除模板加横向支撑,最后槽内分层回填土方;(1) Pouring guide wall: After the measurement and setting-out is completed, the construction of the guide wall begins. The construction quality of the guide wall is directly related to the construction quality of the underground diaphragm wall. The cross-section of the guide wall is made of inverted "L" cast-in-place reinforced concrete, with HRB400C12@200 steel skeleton evenly distributed, and the guide wall is made of C30 concrete. Before excavation of the guide wall, the excavation trench must be manually excavated. When the excavator is operating, a special person must stand by Supervise the construction, then bind the guide wall reinforcement and vertical formwork, pour C30 concrete, remove the formwork and add lateral support, and finally backfill the earthwork in layers in the groove;

(2)泥浆制备:在成槽过程中,泥浆起到护壁、携渣、冷却机具、切土润滑的作用,性能良好的泥浆能确保成槽时槽壁的稳定,防止塌槽,同时在砼浇灌时对保证砼的浇灌质量起着极其重要的作用;根据所在地质、地下水性质及青岛市地区施工经验进行泥浆配合比设计,使配置的泥浆指标符合施工要求(泥浆比重控制在1.1g/cm3~1.25g/cm3左右、粘度25~30s之间),泥浆配置方法为:先将水加至搅拌筒1/3后,启动制浆机,再在定量水箱不断加水的同时,加入膨润土粉,搅拌10min后,加入CMC液和碱粉等外加剂继续搅拌10min即可停止搅拌放入新浆池中,待静置膨化24h后使用;(2) Mud preparation: During the trough forming process, the mud plays the role of wall protection, slag carrying, cooling equipment, and cutting soil lubrication. The mud with good performance can ensure the stability of the trough wall during trough forming and prevent the trough from collapsing. When pouring, it plays an extremely important role in ensuring the quality of concrete pouring; the mud mix ratio is designed according to the geology, groundwater properties and construction experience in Qingdao City, so that the configured mud index meets the construction requirements (the mud proportion is controlled at 1.1g/cm 3 ~ 1.25g/ cm3 , viscosity between 25 ~ 30s), the slurry configuration method is: first add water to 1/3 of the mixing drum, start the pulping machine, and then add bentonite while continuously adding water to the quantitative water tank powder, after stirring for 10 minutes, add additives such as CMC liquid and alkali powder and continue stirring for 10 minutes, then stop stirring and put it into the new pulp tank, and use it after standing for 24 hours of puffing;

(3)Ⅰ期槽段开挖:为控制正式成槽施工过程的垂直度、泥浆参数,保证工程实施的连续性,达到指导施工的目的,将首开槽作为试验槽段,收集成槽施工的各类参数和数据等,试成槽后地连墙常规成槽,根据设计图纸及导墙确定Ⅰ期槽段开挖位置,本实施例中用徐工480型液压抓斗成槽机成槽,成槽时采用泥浆护壁,成槽后根据相关规范对槽孔进行验收,槽段完成后用刷壁器斜铲铲除未脱落的硬物,刷壁器使用特制刷壁器,刷壁器高3米,重4吨,一侧为斜钢铲,用来铲除钢板上粘附较牢固的砂带、混凝土等物;另一侧为钢丝刷,用来刷除钢板上粘附的泥土,最后挖槽机进行槽壁清底;(3) Phase I trench section excavation: In order to control the verticality and mud parameters of the formal trenching construction process, ensure the continuity of the project implementation, and achieve the purpose of guiding the construction, the first trenching is used as the test trench section, and the excavation of the trenching construction is collected. Various parameters and data, etc. After the trench is tested, the ground connection wall is conventionally formed, and the excavation position of the first phase of the trench is determined according to the design drawings and the guide wall. When the groove is formed, mud is used to protect the wall. After the groove is formed, the groove hole is checked and accepted according to the relevant specifications. After the groove section is completed, the hard objects that have not fallen off are removed with an oblique shovel. The wall brush uses a special wall brush, and the height of the wall brush is 3 meters, weighing 4 tons, one side is a slanted steel shovel, which is used to remove abrasive belts, concrete, etc. that are firmly adhered to the steel plate; The tank machine cleans the bottom of the tank wall;

(4)钢筋笼制作:制作前先钢筋除锈,采用胎具法成型工艺制作钢筋笼,焊接时严格控制焊接质量,将第一墙幅钢筋笼9采用现有技术按施工要求制作好后与工字型钢板1焊接,同时在工字钢接头在工字钢外侧安装0.3mm厚、500mm宽的防绕镀锌铁皮5,镀锌铁皮5与工字钢1搭接宽度不小于100mm,采用一条压条钢筋6固定焊接;(4) steel cage making: steel bar is derusted earlier before making, adopts mold method forming process to make steel cage, strictly controls welding quality during welding, adopts existing technology to make after the first wall reinforcement cage 9 is done by construction requirements and I-shaped steel plate 1 is welded, and an anti-winding galvanized iron sheet 5 with a thickness of 0.3mm and a width of 500mm is installed on the outside of the I-shaped steel at the I-shaped steel joint. The overlapping width of the galvanized iron sheet 5 and the I-shaped steel 1 is not less than 100mm, and a bead is used Steel bar 6 is fixedly welded;

(5)步骤(3)清槽结束后经检验成槽质量和泥浆指标,合格后吊放接头箱,将第一幅钢筋笼9采用双机抬吊进行整体吊装,采用一台130t履带吊作主吊,一台55t履带吊作副吊,钢筋笼吊点设置为主吊4点、副吊6点下放到既定位置,在工字型钢板1接头外侧填筑沙袋11,防止混凝土外流;为减少地下连续墙墙竖向沉降和相应的地表沉降,在工字型钢板1接头处用预设的钢花管7进行注浆加固,然后通过预埋的注浆管8水下浇筑首幅地下连续墙,浇筑完成后起拔接头箱;(5) Step (3) After the cleaning of the tank, the quality of the finished tank and the mud index are inspected. After passing the inspection, the joint box is hoisted, and the first steel cage 9 is hoisted as a whole by double-machine hoisting, and a 130t crawler crane is used for the overall hoisting. For the main hoist, a 55t crawler crane is used as the auxiliary hoist. The hoisting points of the steel cage are set at 4 points for the main hoist and 6 points for the auxiliary hoist, and lowered to a predetermined position. Sandbags 11 are filled outside the I-shaped steel plate 1 joint to prevent the concrete from flowing out; for To reduce the vertical settlement of the underground diaphragm wall and the corresponding surface settlement, use the preset steel flower pipe 7 to carry out grouting reinforcement at the joint of the I-shaped steel plate 1, and then pour the first underground continuous wall through the pre-buried grouting pipe 8 underwater. For the wall, pull out the joint box after the pouring is completed;

(6)相邻槽段Ⅱ期完成后,先用刷壁器斜铲铲除未脱落的砂带等硬物,再用刷壁器钢丝刷自上而下分段刷洗Ⅰ期槽端头工字钢板,上下刷数遍,直至刷子上不带泥屑,孔底淤积不再增加,刷壁后使新老混凝土接合处干净密实;(6) After the completion of the second phase of the adjacent tank section, first use the wall brusher to shovel to remove hard objects such as abrasive belts that have not fallen off, and then use the wall brusher wire brush to scrub the I-shaped end of the first phase of the tank from top to bottom Brush the steel plate up and down several times until there is no mud debris on the brush, and the accumulation at the bottom of the hole will no longer increase. After brushing the wall, the joint between the new and old concrete will be clean and dense;

(7)吊放接头箱,将第二墙幅钢筋笼10吊装嵌固于工字型钢板1翼板内,通过注浆管8水下浇筑混凝土,浇筑完成后起拔接头箱;(7) Hanging the joint box, hoisting and embedding the second wall reinforcement cage 10 in the wing plate of the I-shaped steel plate 1, pouring concrete underwater through the grouting pipe 8, and pulling out the joint box after the pouring is completed;

(8)其余墙幅按照上述步骤,依次浇筑,直至最后一幅连续墙浇筑完成。(8) The rest of the walls are poured sequentially according to the above steps until the last continuous wall is poured.

Claims (8)

  1. The regional ground continuous wall connector antipriming 1. a kind of high rich water borders on the sea, it is characterised in that main structure includes i shaped steel Plate, diaphragm wall horizontal bar, the vertical main reinforcement of diaphragm wall, u u stirrup, galvanized iron sheet, press strip reinforcing bar, steel floral tube, Grouting Pipe, the first wall Width steel reinforcement cage, the second wall width steel reinforcement cage and sandbag;Diaphragm wall horizontal bar and the vertical main reinforcement mechanical connection of diaphragm wall, steel floral tube binding It is overlapped on the first wall width steel reinforcement cage;Galvanized iron sheet is mounted on the outside of I-shaped steel plate, galvanized iron sheet and press strip reinforcing bar spot welding Welding, I-steel and the first wall width steel reinforcement cage are welded to connect, fusion length 100mm;U u stirrup and diaphragm wall horizontal bar single side It is welded to connect, Grouting Pipe and the second wall width steel reinforcement cage binding overlap joint, the second wall width steel reinforcement cage is in lifting build-in in I-shaped steel plate In wing plate;Sandbag piles up I-shaped plate joint web outside, and lower raising degree is diaphram wall height.
  2. 2. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that the I-shaped Shape steel plate is welded by H profile steel plate, and the width on the edge of a wing is 400mm, the edge of a wing with a thickness of 10mm, the height of web is 160mm, web with a thickness of 10mm.
  3. 3. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that described continuous Wall horizontal bar and the vertical main reinforcement of diaphragm wall are according to requirement of engineering selection model and size.
  4. 4. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that the u shape hoop The model and spacing of muscle are identical as diaphragm wall horizontal bar, and the transfer angle of u u stirrup is 45 °, are hanging the second wall width steel reinforcement cage Better build-in is convenient for construction in I-steel wing plate when dress.
  5. 5. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that described zinc-plated The thickness of iron sheet is 0.3mm, width 500mm, and when strutting outward when slot section concrete pours, galvanized iron sheet prevents concrete from flowing into The slot section of adjacent non-grooving.
  6. 6. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that the press strip The model and size of reinforcing bar use C20, apart from i shaped steel edges of boards edge 100mm at and galvanized iron sheet spot-welded.
  7. 7. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that the spray of molten steel The diameter of pipe is A50, wall thickness 3mm, and highly suitable with the height of diaphram wall, two steel floral tubes are apart from i shaped steel It is connected at the horizontal 100mm of plate 1 with the binding of the first wall width steel reinforcement cage, the effect of steel floral tube is the excavation of foundation pit after water sealing structure forming Preceding carry out grouting reinforcing, it is ensured that the size of seam crossing water-stagnating effect, Grouting Pipe is identical as steel floral tube.
  8. 8. high rich water borders on the sea regional ground continuous wall connector antipriming according to claim 1, it is characterised in that use the dress It sets and realizes that high rich water borders on the sea the detailed process of regional ground continuous wall connector sealing are as follows:
    (1) it pours and leads wall: levelling of the land → surveying and locating → excavation successively being carried out using existing construction technology and leads wall ditch and processing Roach → wall reinforcing bar, installation wall outboard template are led in binding → pours walls concrete → form removal and adds in cross-brace → slot The back-filling in layers earthwork;
    (2) slurrying: mud mix-design is carried out according to place geology, Groundwater Property and construction experience, makes configuration Mud index meets construction requirement, the process of mud configuration are as follows: after water is first added to mixing drum 1/3, starts pulper, then fixed While water-masuring box constantly adds water, bentonite in powder is added, after stirring 10min, CMC liquid is added and ground caustic continues to stir 10min i.e. Can stop stirring being put into new stock tank, wait stand extruding for 24 hours afterwards use;
    (3) I phase slot sections are excavated: will be first opened slot as test flume section, collected all kinds of parameters and data of trenching construction etc., try grooving Ground-connecting-wall routine grooving afterwards according to design drawing and leads wall and determines that I phase slot section excavates position, and chute forming machine carries out excavation operation;At Mud off is used when slot, is carried out an acceptance inspection according to related specifications to slot after grooving, is tiltedly rooted out after the completion of slot section with brush wall device The hard object not fallen off carries out cell wall cleaning;
    (4) the first wall width steel reinforcement cage fabrication of reinforcing cage: is made into rear and I-shaped steel plate by construction requirement using the prior art Welding, while installing galvanized iron sheet and press strip reinforcing bar;
    (5) grooving quality and mud index are examined after the clear trough end of step (3), connector case is hung after qualified, by the first width steel Muscle cage transfers to commitment positions, fills sandbag on the outside of I-shaped plate joint, prevents concrete from outflowing;It is continuous to reduce underground Wall wall Vertical Settlement and corresponding ground settlement carry out grouting and reinforcing with preset steel floral tube in i shaped steel plate connector, so Afterwards by the pre-buried first width diaphram wall of Grouting Pipe underwater casting, is risen after the completion of pouring and pull out connector case;
    (6) after the completion of II phase of adjacent slot section, the hard object not fallen off first tiltedly is rooted out with brush wall device, then with brush wall device wire brush from upper And I phase groove end I-shaped steel plate is scrubbed in lower segmentation, brush several times, is not further added by up to, without spare, bottom hole is deposited on brush up and down, Make New-old concrete joint completely closely knit after brush wall;
    (7) connector case is hung, by the second wall width reinforcing bar cage hoisting build-in in I-shaped steel plate wing plate, is poured under water by Grouting Pipe Concrete is built, is risen after the completion of pouring and pulls out connector case;
    (8) remaining wall width is successively poured according to above-mentioned steps, until last width diaphragm wall pours completion.
CN201910669495.XA 2019-07-24 2019-07-24 High rich water faces sea area diaphragm wall and connects sealing device Pending CN110528501A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201910669495.XA CN110528501A (en) 2019-07-24 2019-07-24 High rich water faces sea area diaphragm wall and connects sealing device
PCT/CN2020/103604 WO2021013201A1 (en) 2019-07-24 2020-07-22 Water stopping device and method for ground continuous wall joint in high-water-rich coastal area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910669495.XA CN110528501A (en) 2019-07-24 2019-07-24 High rich water faces sea area diaphragm wall and connects sealing device

Publications (1)

Publication Number Publication Date
CN110528501A true CN110528501A (en) 2019-12-03

Family

ID=68660780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910669495.XA Pending CN110528501A (en) 2019-07-24 2019-07-24 High rich water faces sea area diaphragm wall and connects sealing device

Country Status (1)

Country Link
CN (1) CN110528501A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111270653A (en) * 2020-03-06 2020-06-12 中电建十一局工程有限公司 One-time pouring construction method for hydraulic dam side water-stop steel plate
CN111535298A (en) * 2020-05-12 2020-08-14 中建六局水利水电建设集团有限公司 Seepage-proofing construction method for underground diaphragm wall
WO2021013201A1 (en) * 2019-07-24 2021-01-28 青岛理工大学 Water stopping device and method for ground continuous wall joint in high-water-rich coastal area
CN112854196A (en) * 2021-01-08 2021-05-28 中国建筑第八工程局有限公司 Construction method and structure of bending-pulling-resistant underground continuous wall
CN113026722A (en) * 2021-02-22 2021-06-25 南通四建集团有限公司 Combined water stop structure with multilateral ribbed plates for underground continuous wall and construction method
CN113338947A (en) * 2021-04-14 2021-09-03 浙江交工集团股份有限公司 Sand-flowing-preventing water-gushing working well for water-rich sand layer and construction method thereof
CN113897945A (en) * 2021-11-04 2022-01-07 湖北省交通规划设计院股份有限公司 Ground-connecting wall combined connecting structure and construction method
CN115324117A (en) * 2022-08-16 2022-11-11 中铁二十局集团南方工程有限公司 Construction method of water stop for ground connection wall joint
CN115369924A (en) * 2022-08-02 2022-11-22 中国建筑第八工程局有限公司 Construction method of underground continuous wall joint
CN115977163A (en) * 2023-01-13 2023-04-18 中交路桥建设有限公司 Slurry leakage prevention device for underground diaphragm wall construction and implementation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138943A (en) * 1993-11-18 1995-05-30 Kajima Corp Joint structure of underground wall
CN200981996Y (en) * 2006-12-18 2007-11-28 上海华瀛建筑科技有限公司 Super deep underground continuous wall adapter
CN203834524U (en) * 2014-03-31 2014-09-17 广西建工集团第五建筑工程有限责任公司 Concrete streaming preventing device for H-type steel connector grout stop plate at underground continuous wall chase section
CN206554070U (en) * 2017-02-28 2017-10-13 中交二公局第二工程有限公司 A kind of anti-by-pass means of ground-connecting-wall H profile steel joint
CN107687166A (en) * 2017-10-18 2018-02-13 太原理工大学 Diaphram wall is anti-to stream, water-impervious I-shaped steel joint structure and construction method
CN207934021U (en) * 2018-02-02 2018-10-02 中铁十四局集团大盾构工程有限公司 A kind of lock catch device for preventing streaming for diaphram wall H profile steel connector
CN211312489U (en) * 2019-07-24 2020-08-21 青岛理工大学 High rich water faces sea area diaphragm wall and connects sealing device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138943A (en) * 1993-11-18 1995-05-30 Kajima Corp Joint structure of underground wall
CN200981996Y (en) * 2006-12-18 2007-11-28 上海华瀛建筑科技有限公司 Super deep underground continuous wall adapter
CN203834524U (en) * 2014-03-31 2014-09-17 广西建工集团第五建筑工程有限责任公司 Concrete streaming preventing device for H-type steel connector grout stop plate at underground continuous wall chase section
CN206554070U (en) * 2017-02-28 2017-10-13 中交二公局第二工程有限公司 A kind of anti-by-pass means of ground-connecting-wall H profile steel joint
CN107687166A (en) * 2017-10-18 2018-02-13 太原理工大学 Diaphram wall is anti-to stream, water-impervious I-shaped steel joint structure and construction method
CN207934021U (en) * 2018-02-02 2018-10-02 中铁十四局集团大盾构工程有限公司 A kind of lock catch device for preventing streaming for diaphram wall H profile steel connector
CN211312489U (en) * 2019-07-24 2020-08-21 青岛理工大学 High rich water faces sea area diaphragm wall and connects sealing device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
倪鹏: "地下连续墙施工技术的应用", 《太原城市职业技术学院学报》, no. 3, pages 182 - 183 *
李希宏: "复杂地质条件下地连墙接缝质量控制要点", 《中国水运》, vol. 16, no. 6, pages 184 - 185 *
杨跃: "《现代高层建筑施工》", 华中科技大学出版社, pages: 35 - 46 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021013201A1 (en) * 2019-07-24 2021-01-28 青岛理工大学 Water stopping device and method for ground continuous wall joint in high-water-rich coastal area
CN111270653A (en) * 2020-03-06 2020-06-12 中电建十一局工程有限公司 One-time pouring construction method for hydraulic dam side water-stop steel plate
CN111270653B (en) * 2020-03-06 2021-08-24 中电建十一局工程有限公司 One-time pouring construction method for hydraulic dam side water-stop steel plate
CN111535298A (en) * 2020-05-12 2020-08-14 中建六局水利水电建设集团有限公司 Seepage-proofing construction method for underground diaphragm wall
CN112854196A (en) * 2021-01-08 2021-05-28 中国建筑第八工程局有限公司 Construction method and structure of bending-pulling-resistant underground continuous wall
CN113026722A (en) * 2021-02-22 2021-06-25 南通四建集团有限公司 Combined water stop structure with multilateral ribbed plates for underground continuous wall and construction method
CN113338947A (en) * 2021-04-14 2021-09-03 浙江交工集团股份有限公司 Sand-flowing-preventing water-gushing working well for water-rich sand layer and construction method thereof
CN113338947B (en) * 2021-04-14 2024-04-09 浙江交工集团股份有限公司 Water-rich sand layer anti-flowing sand water-surge working well and construction method thereof
CN113897945A (en) * 2021-11-04 2022-01-07 湖北省交通规划设计院股份有限公司 Ground-connecting wall combined connecting structure and construction method
CN115369924A (en) * 2022-08-02 2022-11-22 中国建筑第八工程局有限公司 Construction method of underground continuous wall joint
CN115369924B (en) * 2022-08-02 2023-11-21 中国建筑第八工程局有限公司 Construction method of underground diaphragm wall joint
CN115324117A (en) * 2022-08-16 2022-11-11 中铁二十局集团南方工程有限公司 Construction method of water stop for ground connection wall joint
CN115977163A (en) * 2023-01-13 2023-04-18 中交路桥建设有限公司 Slurry leakage prevention device for underground diaphragm wall construction and implementation method

Similar Documents

Publication Publication Date Title
CN110528501A (en) High rich water faces sea area diaphragm wall and connects sealing device
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN102322064A (en) Construction method for underground diaphragm wall of deep foundation pit for subway station in collapsible loess areas
CN104929143B (en) A kind of bottom of foundation ditch dewatering well shut-in well method
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN109339065A (en) Method for deep water exposed bedrock close-packed pile supporting construction bearing platform
CN109537574A (en) The construction technology of diaphram wall in a kind of extremely hard rock
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN114753348A (en) Construction method of complex stratum ultra-deep ultra-thick underground diaphragm wall
CN211312489U (en) High rich water faces sea area diaphragm wall and connects sealing device
CN108532587A (en) A kind of rainy season railway website construction method of underground continuous wall
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN110528500A (en) Water stopping method for continuous wall joint in high-water-rich coastal area
CN110409511A (en) A water-stopping method for joints between occlusal piles and ground-connected walls
CN112878332A (en) Basement elevator shaft sump construction structure and method thereof
CN117513363A (en) Fluid solidified soil backfill system and construction method for narrow fertilizer trough in pit
CN112695763A (en) Deep sludge stratum foundation pit excavation method
WO2021013201A1 (en) Water stopping device and method for ground continuous wall joint in high-water-rich coastal area
CN210507415U (en) Ground is wall joint sealing device even
CN210315908U (en) Immersed tube type inspection well
CN106192880A (en) The box harbour of L-type and method of construction thereof
CN108894206A (en) Shoal sewage pipe, well anti-floating system and construction method
CN113818482A (en) New and old pipe gallery connecting method for reducing uneven settlement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination