CN110245863B - An electric combined system and online regulation method based on electric conversion energy storage - Google Patents
An electric combined system and online regulation method based on electric conversion energy storage Download PDFInfo
- Publication number
- CN110245863B CN110245863B CN201910513732.3A CN201910513732A CN110245863B CN 110245863 B CN110245863 B CN 110245863B CN 201910513732 A CN201910513732 A CN 201910513732A CN 110245863 B CN110245863 B CN 110245863B
- Authority
- CN
- China
- Prior art keywords
- gas
- power
- electric
- load
- energy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06312—Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
技术领域technical field
本发明涉及电气联合系统技术领域,尤其涉及一种基于电气转换储能的电气联合系统及在线调控方法。The invention relates to the technical field of electrical combined systems, in particular to an electrical combined system based on electrical conversion and energy storage and an online regulation method.
背景技术Background technique
我国现在是世界上最大的风力发电市场,截止到2016年,我国风力发电容量占全球风力发电容量的35%。尽管风电的渗透性日益增强,我国仍然面临着严重的风力削减问题,特别是在北方省份。风电消纳的主要障碍是电力系统的灵活性不够。然而,在我国北方地区,60%以上的发电机组是热电联产(CHP)机组,为了保证供暖需求,热电联产机组采用“以热定电”的运行模式。热电联产机组“以热定电”的运行模式压缩了风电上网空间,加剧了弃风现象。my country is now the world's largest wind power market. As of 2016, my country's wind power generation capacity accounted for 35% of the global wind power generation capacity. Despite the increasing penetration of wind power, my country still faces serious wind curtailment problems, especially in the northern provinces. The main obstacle to wind power accommodation is the lack of flexibility of the power system. However, in northern China, more than 60% of generating units are combined heat and power (CHP) units. In order to ensure the heating demand, CHP units adopt the operation mode of "power determined by heat". The operation mode of cogeneration units that "constantly determines power by heat" reduces the space for wind power to be connected to the grid and intensifies the phenomenon of wind curtailment.
随着新能源的使用受到了人们的广泛重视,风电等新能源发电系统装机容量在不断并增加,预计到2020年风机装机容量将达到2亿千瓦。但是由于风电场和电网建设不同步、风电特性和电网调峰能力不匹配等原因,在一些地区出现了弃风现象,造成了能源浪费和经济损失。综合能源系统架构集成可再生能源是提高可再生能源利用率的重要手段之一。基于天然气和电力供能的微网系统是典型用户侧综合能源系统形态,通过对微网中天然气和电力环节进行协调优化,可以提高可再生能源利用率;此外,也可以在耦合系统中发展储气、储电和储势等技术,提高可再生能源的利用率,最终形成多元消纳技术和多元储能技术减少弃风现象。由于电力大量存储会存在高成本等问题,而储气成本相对较低,因此,可以在微网中大力发展储气技术。例如,通过电转气技术将多余的风电转化为天然气进行存储,减小弃风、弃光等现象。As the use of new energy has attracted widespread attention, the installed capacity of wind power and other new energy power generation systems has continued to increase. It is estimated that the installed capacity of wind turbines will reach 200 million kilowatts by 2020. However, due to the asynchronous construction of wind farms and power grids, and the mismatch between wind power characteristics and peak-shaving capabilities of the power grid, wind curtailment has occurred in some areas, resulting in energy waste and economic losses. Integrated energy system architecture Integrating renewable energy is one of the important means to improve the utilization rate of renewable energy. The microgrid system based on natural gas and electric power supply is a typical user-side comprehensive energy system form. By coordinating and optimizing the natural gas and electric power links in the microgrid, the utilization rate of renewable energy can be improved; in addition, the storage system can also be developed in the coupling system. Gas, electricity storage, and potential storage technologies will improve the utilization rate of renewable energy, and finally form multiple consumption technologies and multiple energy storage technologies to reduce wind curtailment. Due to the high cost of large-scale storage of electricity, and the relatively low cost of gas storage, gas storage technology can be vigorously developed in microgrids. For example, through the power-to-gas technology, excess wind power is converted into natural gas for storage, reducing the phenomenon of abandoning wind and light.
电转气技术是在负荷低谷、可再生能源出力高峰时段,将富裕的电能转化为天然气或氢气,存储在天然气管网或天然气存储设备中;在电力短缺时段,将存储的气体转化为电能或者热能提供给用户,从而提高了微网在负荷低谷时段消纳可再生能源的能力。电转气技术也增加了电–气联合环节的耦合作用,增强电力网络与天然气网络系统之间的功能稳定性。The power-to-gas technology is to convert the rich electric energy into natural gas or hydrogen during the low load and peak hours of renewable energy output, and store it in the natural gas pipeline network or natural gas storage equipment; during the power shortage period, the stored gas is converted into electric energy or heat energy Provided to users, thereby improving the ability of the microgrid to absorb renewable energy during low load periods. The power-to-gas technology also increases the coupling effect of the electricity-gas joint link, and enhances the functional stability between the power network and the natural gas network system.
电转气将电能转化为化学能,通过氢气或天然气存储起来。根据电转气的最终产物不同,可以将电转气技术分为电解氢和甲烷化二个阶段。首先,将多余的电能通过电解水产生氢气,其能量将多余的电能电解水生产氢气,直接用于工业生产或者在安全约束下进行燃气发电,化学方程式为:Power-to-gas converts electrical energy into chemical energy, which is stored in hydrogen or natural gas. According to the different final products of power-to-gas, power-to-gas technology can be divided into two stages: electrolysis of hydrogen and methanation. First of all, excess electric energy is used to electrolyze water to produce hydrogen, and its energy is used to produce hydrogen by electrolyzing water, which can be directly used in industrial production or gas-fired power generation under safety constraints. The chemical equation is:
2H2O→2H2+O2 (1)2H 2 O→2H 2 +O 2 (1)
电解产生的氢气可以直接利用,但是由于氢气存储和传输困难,一般采用电解天然气的形式,即甲烷化。天然气较氢气有更高的单位能量密度,并且可以直接注入现有天然气网络进行大规模存储和远距离传输。电转天然气是在电解氢气的基础上,利用二氧化碳和氢气在高温高压环境下反应生成甲烷,化学方程式为:The hydrogen produced by electrolysis can be used directly, but due to the difficulty of hydrogen storage and transportation, it is generally in the form of electrolysis of natural gas, that is, methanation. Natural gas has a higher unit energy density than hydrogen, and can be directly injected into existing natural gas networks for large-scale storage and long-distance transmission. Electric-to-natural gas is based on the electrolysis of hydrogen, using carbon dioxide and hydrogen to react under high temperature and high pressure to generate methane. The chemical equation is:
CO2+4H2→CH4+2H2O (2)CO 2 +4H 2 →CH 4 +2H 2 O (2)
甲烷化过程是一个放热催化反应,反应所需的二氧化碳可来源于工业生产过程中产生的废气、化石燃料燃烧发电、生物质和空气等。甲烷化后的天然气后可注入天然气网络存储,天然气一般存储在废弃油气田、含水层或盐穴中。天然气存储容量巨大,可达几百兆立方米,相当于存储电能达到TW·h级别。电负荷高峰时段通过燃料电池或燃气轮机将天然气转化为电能,以此形成电–气–电的循环储能系统,传统的储能设备电转气存储容量小、放电时间短,无法有效消纳大规模的风电,且无法实现能量的长时间、大范围时空平移;传统的储能设备都为单时间的断面优化,导致调控缺少灵活性;The methanation process is an exothermic catalytic reaction, and the carbon dioxide required for the reaction can come from the waste gas generated in the industrial production process, fossil fuel combustion power generation, biomass and air, etc. Methanated natural gas can be injected into the natural gas network for storage, and natural gas is generally stored in abandoned oil and gas fields, aquifers or salt caverns. The storage capacity of natural gas is huge, up to hundreds of trillion cubic meters, which is equivalent to storing electric energy reaching the level of TW·h. During the peak hours of electric load, natural gas is converted into electric energy through fuel cells or gas turbines to form an electric-gas-electric cycle energy storage system. The traditional energy storage equipment power-to-gas storage capacity is small and the discharge time is short, which cannot effectively consume large-scale wind power, and it is impossible to achieve long-term and large-scale time-space translation of energy; traditional energy storage equipment is optimized for a single-time section, resulting in a lack of flexibility in regulation;
发明内容Contents of the invention
本发明要解决的技术问题是针对上述现有技术的不足,提供一种基于电气转换储能的电气联合系统及在线调控方法,通过电转气设备、燃气轮机、燃气热电联产机组、燃气锅炉和储气罐间的有序配合,增强了电气联合系统运行的灵活性。The technical problem to be solved by the present invention is to provide an electrical combined system based on electrical conversion and energy storage and an online control method for the deficiencies of the above-mentioned prior art. The orderly cooperation between the gas tanks enhances the flexibility of the electrical combined system operation.
为解决上述技术问题,本发明所采取的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
一方面,本发明提供一种基于电气转换储能的电气联合系统,包括能量源信息采集单元、能量转换单元和负荷单元;On the one hand, the present invention provides an electrical combination system based on electrical conversion and energy storage, including an energy source information acquisition unit, an energy conversion unit and a load unit;
所述负荷单元包括电负荷单元和热负荷单元,所述电负荷单元用于为负载的用电设备提供电负荷,所述热负荷单元用于负载的用户提供热能;The load unit includes an electric load unit and a heat load unit, the electric load unit is used to provide electric load for the electric equipment of the load, and the heat load unit is used to provide heat energy for the user of the load;
所述能量源信息采集单元包括能量信息采集器和天然气母线;能量信息采集器分别与风电机组、电网以及能量转换单元相连接,所述天然气母线与天然气网络相连接;The energy source information acquisition unit includes an energy information collector and a natural gas busbar; the energy information collector is connected to the wind turbine, the power grid, and the energy conversion unit respectively, and the natural gas busbar is connected to the natural gas network;
所述能量转换单元包括:电转气设备、燃气轮机、燃气热电联产机组、燃气锅炉和储气罐;所述电转气设备的输入端与电母线相连接,电母线与电负荷单元相连接;所述电转气设备的输出端与储气罐的输入端相连接;所述储气罐的输出端与燃气轮机的输入端相连接;所述燃气轮机的输出端与电母线相连接;能量信息采集器分别与燃气热电联产机组和燃气锅炉相连接;所述燃气锅炉的输入端与天然气母线相连接;所述燃气锅炉的输出端与热负荷单元相连;所述燃气热电联产机组的输入端与天然气母线相连接;所述燃气热电联产机组的输出端分别与热负荷单元的输入端和电母线相连;The energy conversion unit includes: power-to-gas equipment, a gas turbine, a gas-fired cogeneration unit, a gas boiler, and a gas storage tank; the input end of the power-to-gas equipment is connected to an electric bus, and the electric bus is connected to an electric load unit; The output end of the power-to-gas equipment is connected to the input end of the gas storage tank; the output end of the gas storage tank is connected to the input end of the gas turbine; the output end of the gas turbine is connected to the electric bus; the energy information collector is respectively It is connected with the gas cogeneration unit and the gas boiler; the input end of the gas boiler is connected with the natural gas bus; the output end of the gas boiler is connected with the heat load unit; the input end of the gas cogeneration unit is connected with the natural gas The busbar is connected; the output end of the gas cogeneration unit is respectively connected with the input end of the heat load unit and the electric busbar;
另一方面,本发明提供一种基于电气转换储能的在线调控方法,通过所述的一种基于电气转换储能的电气联合系统实现,包括以下步骤:On the other hand, the present invention provides an online regulation method based on electrical conversion energy storage, which is realized by the electrical combination system based on electrical conversion energy storage, including the following steps:
步骤1:以1小时作为一个调度时段,以24个调度时段作为一个调度周期T,获取电气联合系统能量信息采集器获取的当前时段t的能量源信息、能量转换单元中储气罐气压PS和负荷单元中当前时段t的负荷信息;所述能量源信息包括燃气热电联产机组的耗气功率Pgas,CHP和燃气锅炉的耗气功率Pgas,GB,风电机组出力PF,向电网购电量Pgrid;所述负荷信息包括电负荷PE和热负荷PH;Step 1: Take 1 hour as a scheduling period and 24 scheduling periods as a scheduling period T to obtain the energy source information of the current period t obtained by the energy information collector of the electrical joint system, and the air pressure P S of the gas storage tank in the energy conversion unit and the load information of the current period t in the load unit; the energy source information includes the gas consumption power P gas,CHP of the gas-fired cogeneration unit and the gas consumption power P gas,GB of the gas-fired boiler, the wind turbine output P F , Online shopping power P grid ; the load information includes electric load P E and thermal load P H ;
步骤2:对电气联合系统中能量源信息采集器中当前时段t的风电机组出力PF和负荷单元中当前时段t的电负荷PE和热负荷PH的变化量进行监测,判断电气联合系统是否发生能量更新,若是,则执行步骤3,若否则维持原来运行状态并执行步骤1;Step 2: Monitor the wind turbine output P F of the current period t in the energy source information collector in the electrical combined system and the changes in the electric load PE and thermal load P H of the load unit in the current period t, and judge the electric combined system Whether energy update occurs, if yes, go to step 3, if not, keep the original running state and go to
其中,触发能量更新的情况包括:Among them, the situations that trigger energy update include:
1)风电机组出力的变化量超过阈值εPF(t-1):|PF-PF(t-1)|>εPF(t-1);1) The variation of wind turbine output exceeds the threshold εP F(t-1) : |P F -P F(t-1) |>εP F(t-1) ;
2)负荷单元能量需求的变化量超过阈值τL(t-1):|L-L(t-1)|>τL(t-1);2) The change in energy demand of the load unit exceeds the threshold τL (t-1) : |LL (t-1) |>τL (t-1) ;
式中,L=PE+PH,ε、τ为参数,其取值是根据实际的负荷情况产生的上下调控范围;t-1表示上一时段,t表示当前时段;In the formula, L=P E + PH , ε, τ are parameters, and their values are the upper and lower control ranges generated according to the actual load situation; t-1 represents the previous period, and t represents the current period;
步骤3:当电气联合系统发生能量更新时,采用电气转换储能的在线调控策略,所述调控策略为当燃气热电联产机组供应能够满足系统需求时则维持现状,燃气热电联产机组供应不能满足系统需求时优先采用燃气热电联产机组满足热负荷的需求,燃气锅炉作为备用热源,电量根据用户优先级原则进行再分配;然后判断电负荷是否满足系统需求;若满足且电能过剩,则系统采用电转气装置,将多余的风电出力转化为天然气,并将天然气存储在储气罐中;若不满足,则电转气装置储气罐放气,采用燃气轮机将天然气转化为电能供给系统电负荷或向电网购电Pgrid;Step 3: When the energy update occurs in the electric combined system, adopt the online control strategy of electric conversion energy storage. The control strategy is to maintain the status quo when the supply of gas-fired cogeneration units can meet the system demand, and the supply of gas-fired cogeneration units cannot When the system demand is met, the gas-fired cogeneration unit is preferred to meet the demand of the heat load. The gas boiler is used as a backup heat source, and the power is redistributed according to the principle of user priority; then judge whether the electric load meets the system demand; The power-to-gas device is used to convert excess wind power output into natural gas, and the natural gas is stored in the gas storage tank; if it is not satisfied, the gas storage tank of the power-to-gas device is released, and the gas turbine is used to convert natural gas into electric energy to supply the system's electric load or Purchase electricity P grid from the grid ;
步骤4:判断电气联合系统当前时段t是否小于调度周期T,如果t<T,则本调度时段结束,令t=t+1后,执行步骤1;如果t=T,则结束本周期的调度。Step 4: Judging whether the current period t of the electrical combined system is less than the scheduling period T, if t<T, then the scheduling period ends, and after setting t=t+1, execute
所述步骤3包括如下步骤:Described step 3 comprises the steps:
步骤3.1:优先采用燃气热电联产机组满足热负荷的需求,燃气锅炉作为备用热源;Step 3.1: Prioritize the use of gas-fired cogeneration units to meet the demand for heat load, and gas-fired boilers as backup heat sources;
判断电气联合系统中热负荷PH由燃气热电联产机组供应是否满足系统需求,其中确定满足热负荷需求的标志为:Judging whether the heat load P H in the electric combined system is supplied by the gas-fired cogeneration unit meets the system demand, and the sign to determine whether the heat load demand is met is:
式中,WL=1时表示满足热负荷需求,WL=0时表示不满足热负荷需求;PCHP,h为燃气热电联产机组的产热功率;其中,燃气热电联产机组的产热功率为:In the formula, when W L =1, it means that the heat load demand is met, and when W L =0, it means that the heat load demand is not met; P CHP,h is the heat production power of the gas-fired cogeneration unit; where, the output of the gas-fired cogeneration unit The thermal power is:
PCHP,h=ηCHP,hPgas,CHP P CHP,h =η CHP,h P gas,CHP
式中,ηCHP,h表示燃气热电联产机组的热转换效率;Pgas,CHP表示燃气热电联产机组的耗气功率;In the formula, ηCHP,h represents the heat conversion efficiency of the gas-fired cogeneration unit; Pgas,CHP represents the gas consumption power of the gas-fired cogeneration unit;
若WL=1时,即燃气热电联产机组供应能够满足系统需求,锅炉不启动工作,维持现有工作状态;If W L = 1, that is, the supply of the gas-fired cogeneration unit can meet the system demand, the boiler will not start to work, and the current working state will be maintained;
若WL=0时,即燃气热电联产机组供应不能满足系统需求,燃气锅炉作为燃气热电联产机组的热备用启动,与燃气热电联产机组联合工作满足热负荷需求:If W L = 0, that is, the supply of the gas cogeneration unit cannot meet the system demand, the gas boiler is started as the hot standby of the gas cogeneration unit, and works jointly with the gas cogeneration unit to meet the heat load demand:
PCHP,h+PGB,h≥PH;P CHP,h +P GB,h ≥ P H ;
其中,燃气锅炉的产热功率:Among them, the heat production power of the gas boiler:
PGB,h=ηGBPgas,GB P GB,h =η GB P gas,GB
式中,PGB,h为燃气锅炉的产热功率;ηGB表示燃气锅炉效率;Pgas,GB表示燃气锅炉的耗气功率;In the formula, P GB,h is the heat production power of the gas boiler; η GB represents the efficiency of the gas boiler; P gas, GB represents the gas consumption power of the gas boiler;
步骤3.2:根据当前时段风电机组出力PF,燃气热电联产机组电出力PCHP和电负荷PE,判断t时段电负荷是否满足系统需求;系统满足电负荷需求的标志:Step 3.2: According to the output P F of the wind turbine unit, the electrical output P CHP of the gas cogeneration unit and the electrical load P E in the current period, determine whether the electrical load meets the system demand in the period t; the sign that the system meets the electrical load demand:
式中,Ut=1时表示电能过剩,Ut=0时表示电能不足;In the formula, when U t =1, it means excess electric energy, and when U t =0, it means insufficient electric energy;
其中,燃气热电联产机组的发电功率为:Among them, the generating power of the gas cogeneration unit is:
PCHP=ηCHPPgas,CHP P CHP =η CHP P gas,CHP
式中,ηCHP表示燃气热电联产机组的电转换效率。In the formula, ηCHP represents the electrical conversion efficiency of the gas-fired cogeneration unit.
如果Ut=1时,即t时段电负荷能够满足系统需求,且电能过剩,则进行步骤3.3,如果Ut=0时,即t时段电负荷不能满足系统需求,则跳转至步骤3.4;If U t = 1, that is, the electric load can meet the system demand during the t period, and the electric energy is surplus, proceed to step 3.3; if U t = 0, that is, the electric load cannot meet the system demand during the t period, then jump to step 3.4;
步骤3.3:若发电量过大,满足基础电负荷后仍有余量,系统采用电转气装置,将多余的风电出力转化为天然气,并将天然气存储在储气罐中,判断电转气设备储气罐存储容量是否满足储气条件:Step 3.3: If the power generation is too large and there is still a surplus after meeting the basic electric load, the system uses a power-to-gas device to convert the excess wind power output into natural gas, and stores the natural gas in a gas storage tank to judge the gas storage of the power-to-gas equipment Whether the tank storage capacity meets the gas storage conditions:
式中,Vt=1时表示可以储气,Vt=0时表示为不可以储气;Ss为电转气储气罐当前调度时段的存储容量,Ss,min为电转气储气罐内最小存储容量,Ss,max为电转气储气罐内最大存储容量。In the formula, when V t = 1, it means that gas storage is possible, and when V t = 0, it means that gas storage is not possible; S s is the storage capacity of the power-to-gas gas storage tank in the current scheduling period, and S s,min is the power-to-gas gas storage tank The minimum storage capacity inside, S s,max is the maximum storage capacity inside the power-to-gas storage tank.
电转气设备储气罐的存储容量为:The storage capacity of the gas storage tank of the power-to-gas equipment is:
△P=PS-P0 △P=P S -P 0
式中,K为储气罐内压缩机单位时间耗气量;Pa为电转气储气罐安装所在地的海拔高度的大气压;△P为当前调度时段电转气储气罐气压PS与最低送出气压P0的变化量;KL为当前调度时段内电转气储气罐内压力综合参数;Q为当前调度时段内电转气储气罐输出气流量;In the formula, K is the gas consumption per unit time of the compressor in the gas storage tank; P a is the atmospheric pressure at the altitude where the power-to-gas gas storage tank is installed; The variation of P 0 ; K L is the comprehensive parameter of the internal pressure of the power-to-air gas storage tank during the current scheduling period; Q is the output gas flow rate of the power-to-gas gas storage tank during the current scheduling period;
当Vt=0时,即电转气设备储气罐存储容量不满足储气条件,则跳转至步骤4;如果Vt=1时,表示电转气储气罐容量满足储气条件,则将多余的风电转化的天然气存储在储气罐中,然后跳转至步骤3.5;When V t = 0, that is, the storage capacity of the gas storage tank of the power-to-gas equipment does not meet the gas storage conditions, then jump to step 4; if V t = 1, it means that the capacity of the gas storage tank of the power-to-gas equipment meets the gas storage conditions, then set The excess natural gas converted from wind power is stored in the gas storage tank, and then skip to step 3.5;
其中,电转气设备消耗的电能为:Among them, the electric energy consumed by the power-to-gas equipment is:
式中,PP2G表示电转气设备的耗电功率;Hg表示天然气的热值;ηP2G表示电转气设备的转换效率;In the formula, P P2G represents the power consumption of the power-to-gas equipment; H g represents the calorific value of natural gas; η P2G represents the conversion efficiency of the power-to-gas equipment;
步骤3.4::若t时段电负荷无法满足系统基础电负荷需求时,判断电转气装置储气罐存储容量是否满足放气条件;若是,则电转气装置储气罐放气,采用燃气轮机将天然气转化为电能供给系统电负荷,然后跳转至步骤3.5;若否,则向电网购电Pgrid;Step 3.4: If the electric load cannot meet the basic electric load demand of the system during the period t, judge whether the storage capacity of the gas storage tank of the power-to-gas device meets the gas release condition; Supply system electric load for electric energy, and then jump to step 3.5; if not, purchase electricity P grid from the grid ;
所述放气条件为:Described deflation condition is:
式中,Xt=1时表示可以放气,Xt=0时表示为不可以放气;In the formula, when X t = 1, it means deflation is possible, and when X t = 0, it means that deflation is not possible;
其中,储气罐不可以放气时向电网购电量:Among them, when the gas storage tank cannot release gas, it purchases electricity from the grid:
Pgrid=PE-PCHP-PF P grid =P E -P CHP -P F
式中,Pgrid表示储气罐不可以放气时向电网的购电量;In the formula, P grid represents the electricity purchased from the grid when the gas storage tank cannot be released;
燃气轮机的发电功率:Gas turbine power generation:
PGT=ηGTQHg P GT =η GT QH g
式中,PGT表示燃气轮机的发电功率;ηGT表示燃气轮机的转换效率;In the formula, PGT represents the generating power of the gas turbine; ηGT represents the conversion efficiency of the gas turbine;
步骤3.5:判断当前时段t是否达到电能平衡状态:Step 3.5: Judging whether the current time period t has reached the power balance state:
式中,如果Yt=1时,即达到电能平衡状态,则跳转至步骤4;如果Yt=0时,即无法达到电能平衡状态,则向电网购电Pgrid,直到电能平衡后返回步骤4;In the formula, if Y t = 1, the state of electric energy balance is reached, then jump to step 4; if Y t = 0, that is, the state of electric energy balance cannot be reached, then purchase power P grid from the grid until the state of electric energy balance is returned Step 4;
其中,电能处于平衡状态时向电网购电量:Among them, when the electric energy is in a balanced state, the electricity purchased from the grid:
Pgrid=PE-PCHP-PF-PGT P grid =P E -P CHP -P F -P GT
式中,Pgrid表示为达到电能平衡时向电网购电量。In the formula, P grid represents the power purchased from the grid when the power balance is reached.
采用上述技术方案所产生的有益效果在于:本发明提供的一种基于电气转换储能的电气联合系统及在线调控方法,本系统对电–气联合系统进行单元化处理,使其便于控制和执行在线调控策略,为了平抑风电出力、负荷需求的波动性,本发明提出了在线调控策略,该策略利用电转气设备提高了电–气互联综合能源系统风电消纳能力,同时在电负荷低谷和风电出力高峰时段能够有效减缓了负荷的波动;通过电转气设备和燃气轮机实现了电力网络与天然气网络间双向能量流动,增强电–气网络的耦合,提高了能源利用效率从而提高了系统的稳定性。通过电-气转换储能的在线调控策略对能量进行分配,使系统具有良好的灵活的调控作用。本方法较传统的储能设备,电转气存储容量大、放电时间长,可有效消纳大规模风电并实现能量的长时间、大范围时空平移;燃气轮机组与电转气技术实现了电力网络与天然气网络间双向能量流动,增强电–气网络的耦合,提高了能源利用效率从而提高了系统稳定性;The beneficial effects produced by adopting the above technical solution are: the present invention provides an electric combined system based on electrical conversion energy storage and an online regulation method. This system performs unitized processing on the electric-pneumatic combined system, making it easy to control and execute On-line regulation strategy, in order to stabilize the fluctuation of wind power output and load demand, the present invention proposes an on-line regulation strategy. This strategy uses power-to-gas equipment to improve the wind power consumption capacity of the electricity-gas interconnected integrated energy system, and at the same time, in the low power load and wind power The load fluctuation can be effectively slowed down during the peak output period; the two-way energy flow between the power network and the natural gas network is realized through the power-to-gas equipment and the gas turbine, the coupling of the power-gas network is enhanced, the energy utilization efficiency is improved, and the stability of the system is improved. The energy is distributed through the online regulation strategy of electricity-gas conversion energy storage, so that the system has a good and flexible regulation function. Compared with traditional energy storage equipment, this method has larger power-to-gas storage capacity and longer discharge time, which can effectively accommodate large-scale wind power and realize long-term and large-scale time-space translation of energy; the gas turbine unit and power-to-gas technology have realized power network and natural gas Two-way energy flow between networks enhances the coupling of electric-gas networks, improves energy utilization efficiency and improves system stability;
附图说明Description of drawings
图1为本发明实施例提供的电气转换储能的电气联合系统结构图;Fig. 1 is the structural diagram of the electrical combination system of electrical conversion energy storage provided by the embodiment of the present invention;
图2为本发明实施例提供的电气转换储能的在线调控方法流程图;Fig. 2 is a flowchart of an online regulation method for electrical conversion energy storage provided by an embodiment of the present invention;
具体实施方式detailed description
下面结合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific implementation manners of the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
本实施例的方法如下所述。The method of this example is as follows.
一方面,本发明提供一种基于电气转换储能的电气联合系统,如图1所示,包括能量源信息采集单元、能量转换单元和负荷单元;On the one hand, the present invention provides an electrical combined system based on electrical conversion and energy storage, as shown in Figure 1, including an energy source information collection unit, an energy conversion unit and a load unit;
所述负荷单元包括电负荷单元和热负荷单元,所述电负荷单元用于为负载的用电设备提供电负荷,所述热负荷单元用于为负载的用户提供热能;The load unit includes an electric load unit and a heat load unit, the electric load unit is used to provide electric load for the electric equipment of the load, and the heat load unit is used to provide heat energy for the user of the load;
所述能量源信息采集单元用于采集风电机组输出端信息、电网和天然气母线上的信息;包括能量信息采集器和天然气母线;能量信息采集器分别与风电机组、电网以及能量转换单元相连接,所述天然气母线与天然气网络相连接;The energy source information collection unit is used to collect the output information of the wind turbine, the information on the power grid and the natural gas bus; it includes an energy information collector and a natural gas bus; the energy information collector is connected to the wind turbine, the power grid and the energy conversion unit respectively, The natural gas bus is connected to the natural gas network;
所述能量转换单元包括:电转气设备(P2G)、燃气轮机、燃气热电联产机组(CHP)、燃气锅炉和储气罐;所述电转气设备的输入端与电母线相连接,电母线与电负荷单元相连接;所述电转气设备的输出端与储气罐的输入端相连接;所述储气罐的输出端与燃气轮机的输入端相连接;所述燃气轮机的输出端与电母线相连接;能量信息采集器分别与燃气热电联产机组和燃气锅炉相连接;所述燃气锅炉的输入端与天然气母线相连接;所述燃气锅炉的输出端与热负荷单元相连;所述燃气热电联产机组的输入端与天然气母线相连接;所述燃气热电联产机组的输出端分别与热负荷单元的输入端和电母线相连;The energy conversion unit includes: power-to-gas equipment (P2G), gas turbine, gas-fired combined heat and power unit (CHP), gas boiler and gas storage tank; the input end of the power-to-gas equipment is connected to the electric bus, and the electric bus is connected to the electric bus. The load unit is connected; the output end of the power-to-gas equipment is connected to the input end of the gas storage tank; the output end of the gas storage tank is connected to the input end of the gas turbine; the output end of the gas turbine is connected to the electric bus The energy information collector is connected to the gas cogeneration unit and the gas boiler respectively; the input end of the gas boiler is connected to the natural gas busbar; the output end of the gas boiler is connected to the heat load unit; the gas cogeneration The input end of the unit is connected to the natural gas busbar; the output end of the gas cogeneration unit is respectively connected to the input end of the heat load unit and the electric busbar;
所述能量转换单元,作为电气联合系统的能量枢纽,计及了电转气设备和燃气轮机两种耦合形式。通过监测当前时段储气罐气压PS,来决定储气罐的运行状态。电转气将多余的风电转化为天然气,注入储气罐中储存。相反,燃气轮机通过消耗储气罐中天然气,将获得的电能汇集到电母线上,实现了电力网络与天然气网络间双向能量流动。The energy conversion unit, as the energy hub of the electric combined system, takes into account two coupling forms of power-to-gas equipment and gas turbines. The operating state of the gas storage tank is determined by monitoring the air pressure P S of the gas storage tank in the current period. Power-to-gas converts excess wind power into natural gas and injects it into gas storage tanks for storage. On the contrary, the gas turbine consumes the natural gas in the gas storage tank and gathers the obtained electric energy to the electric bus, realizing the two-way energy flow between the electric power network and the natural gas network.
另一方面,本发明提供一种基于电–气转换储能的在线调控方法,通过所述的一种基于电气转换储能的电气联合系统实现,如图2所示,包括以下步骤:On the other hand, the present invention provides an on-line control method based on electricity-gas conversion energy storage, which is realized through the electrical combined system based on electrical conversion energy storage, as shown in Figure 2, including the following steps:
步骤1:以1小时作为一个调度时段,以24个调度时段作为一个调度周期T,获取电–气联合系统能量源信息采集器中当前时段t的能量源信息、能量转换单元中储气罐气压PS和负荷单元中当前时段t的负荷信息;所述能量源信息包括燃气热电联产机组的耗气功率Pgas,CHP和燃气锅炉的耗气功率Pgas,GB,风电机组出力PF,向电网购电量Pgrid;所述负荷信息包括电负荷PE和热负荷PH;Step 1: Taking 1 hour as a scheduling period and 24 scheduling periods as a scheduling period T, obtain the energy source information of the current period t in the energy source information collector of the electric-gas combined system, and the air pressure of the gas storage tank in the energy conversion unit P S and the load information of the current period t in the load unit; the energy source information includes the gas consumption power P gas,CHP of the gas-fired cogeneration unit and the gas consumption power P gas,GB of the gas boiler, the output power P F of the wind turbine, Purchase electricity from the grid P grid ; the load information includes electric load P E and thermal load P H ;
步骤2:对电–气联合系统中能量源信息采集器中当前时段t的风电机组出力PF和负荷单元中当前时段t的电负荷PE和热负荷PH的变化量进行监测,判断电–气联合系统是否发生能量更新,若是,则执行步骤3,若否则维持原来运行状态并执行步骤1;Step 2: Monitor the output PF of the wind turbine in the current period t in the energy source information collector of the electricity-gas combined system and the changes in the electric load PE and thermal load P H in the load unit in the current period t, and judge the power –Whether energy update occurs in the combined gas system, if yes, go to step 3, if not, keep the original running state and go to
其中,触发能量更新的情况包括:Among them, the situations that trigger energy update include:
1)风电机组出力的变化量超过一定阈值:|PF-PF(t-1)|>εPF(t-1);1) The variation of wind turbine output exceeds a certain threshold: |P F -P F(t-1) |>εP F(t-1) ;
2)负荷单元能量需求的变化量超过一定阈值:|L-L(t-1)|>τL(t-1);2) The change in energy demand of the load unit exceeds a certain threshold: |LL (t-1) |>τL (t-1) ;
式中,L=PE+PH,ε,τ为参数,ε,τ的取值是根据实际的负荷情况产生的上下调控范围;t-1表示上一时段,t表示当前时段;L(t-1)=PE(t-1)+PH(t-1);In the formula, L=P E +P H , ε, τ are parameters, and the values of ε, τ are the upper and lower control ranges generated according to the actual load situation; t-1 represents the previous period, t represents the current period; L ( t-1) = P E (t-1) + P H (t-1);
步骤3:当电–气联合系统发生能量更新时,采用一种基于电–气转换储能的在线调控策略,所述调控策略为当燃气热电联产机组供应能够满足系统需求时则维持现状,燃气热电联产机组供应不能满足系统需求时优先采用燃气热电联产机组满足热负荷的需求,燃气锅炉作为备用热源,电量根据用户优先级原则进行再分配;然后判断电负荷是否满足系统需求;若满足且电能过剩,则系统采用电转气装置,将多余的风电出力转化为天然气,并将天然气存储在储气罐中;若不满足,则电转气装置储气罐放气,采用燃气轮机将天然气转化为电能供给系统电负荷或向电网购电Pgrid;具体步骤如下:Step 3: When the energy update occurs in the electricity-gas combined system, an online regulation strategy based on electricity-gas conversion energy storage is adopted. The regulation strategy is to maintain the status quo when the supply of gas cogeneration units can meet the system demand, When the supply of gas-fired cogeneration units cannot meet the system demand, the gas-fired cogeneration unit is preferred to meet the demand of heat load, and the gas boiler is used as a backup heat source, and the power is redistributed according to the principle of user priority; then judge whether the electric load meets the system demand; if If it is satisfied and the electric energy is surplus, the system adopts the power-to-gas device to convert the excess wind power output into natural gas, and stores the natural gas in the gas storage tank; To supply the electric load of the system with electric energy or to purchase electricity P grid from the grid; the specific steps are as follows:
步骤3.1:由于热负荷和电负荷中固定部分都具有不可调控性,优先采用燃气热电联产机组满足热负荷的需求,燃气锅炉作为备用热源;Step 3.1: Since the fixed part of the thermal load and electrical load is not adjustable, the gas-fired cogeneration unit is preferred to meet the demand of the thermal load, and the gas-fired boiler is used as a backup heat source;
判断电–气联合系统中热负荷PH由燃气热电联产机组供应是否满足系统需求,其中确定满足热负荷需求的标志为:Judging whether the heat load P H in the electricity-gas combined system is supplied by the gas-fired cogeneration unit meets the system demand, and the sign to determine whether the heat load demand is met is:
式中,WL=1时表示满足热负荷需求,WL=0时表示不满足热负荷需求;PCHP,h为燃气热电联产机组的产热功率;其中,燃气热电联产机组的产热功率为:In the formula, when W L =1, it means that the heat load demand is met, and when W L =0, it means that the heat load demand is not met; P CHP,h is the heat production power of the gas-fired cogeneration unit; where, the output of the gas-fired cogeneration unit The thermal power is:
PCHP,h=ηCHP,hPgas,CHP P CHP,h =η CHP,h P gas,CHP
式中,ηCHP,h表示燃气热电联产机组的热转换效率;Pgas,CHP表示燃气热电联产机组的耗气功率;In the formula, ηCHP,h represents the heat conversion efficiency of the gas-fired cogeneration unit; Pgas,CHP represents the gas consumption power of the gas-fired cogeneration unit;
若WL=1时,即燃气热电联产机组供应能够满足系统需求,锅炉不启动工作,维持现有工作状态;If W L = 1, that is, the supply of the gas-fired cogeneration unit can meet the system demand, the boiler will not start to work, and the current working state will be maintained;
若WL=0时,即燃气热电联产机组供应不能满足系统需求,燃气锅炉作为燃气热电联产机组的热备用启动,与燃气热电联产机组联合工作满足热负荷需求:If W L = 0, that is, the supply of the gas cogeneration unit cannot meet the system demand, the gas boiler is started as the hot standby of the gas cogeneration unit, and works jointly with the gas cogeneration unit to meet the heat load demand:
PCHP,h+PGB,h≥PH;P CHP,h +P GB,h ≥ P H ;
其中,燃气锅炉的产热功率:Among them, the heat production power of the gas boiler:
PGB,h=ηGBPgas,GB P GB,h =η GB P gas,GB
式中,PGB,h为燃气锅炉的产热功率;ηGB表示燃气锅炉效率;Pgas,GB表示燃气锅炉的耗气功率;In the formula, P GB,h is the heat production power of the gas boiler; η GB represents the efficiency of the gas boiler; P gas, GB represents the gas consumption power of the gas boiler;
步骤3.2:根据当前时段风电机组出力PF,燃气热电联产机组电出力PCHP和电负荷PE,判断t时段电负荷是否满足系统需求;系统满足电负荷需求的标志:Step 3.2: According to the output P F of the wind turbine unit, the electrical output P CHP of the gas cogeneration unit and the electrical load P E in the current period, determine whether the electrical load meets the system demand in the period t; the sign that the system meets the electrical load demand:
式中,Ut=1时表示电能过剩,Ut=0时表示电能不足;In the formula, when U t =1, it means excess electric energy, and when U t =0, it means insufficient electric energy;
其中,燃气热电联产机组的发电功率为:Among them, the generating power of the gas cogeneration unit is:
PCHP=ηCHPPgas,CHP P CHP =η CHP P gas,CHP
式中,ηCHP表示燃气热电联产机组的电转换效率。In the formula, ηCHP represents the electrical conversion efficiency of the gas-fired cogeneration unit.
如果Ut=1时,即t时段电负荷能够满足系统需求,且电能过剩,则进行步骤3.3,如果Ut=0时,即t时段电负荷不能满足系统需求,则跳转至步骤3.4;If U t = 1, that is, the electric load can meet the system demand during the t period, and the electric energy is surplus, proceed to step 3.3; if U t = 0, that is, the electric load cannot meet the system demand during the t period, then jump to step 3.4;
步骤3.3:若发电量过大,满足基础电负荷后仍有余量,系统采用电转气装置,将多余的风电出力转化为天然气,并将天然气存储在储气罐中,判断电转气设备储气罐存储容量是否满足储气条件:Step 3.3: If the power generation is too large and there is still a surplus after meeting the basic electric load, the system uses a power-to-gas device to convert the excess wind power output into natural gas, and stores the natural gas in a gas storage tank to judge the gas storage of the power-to-gas equipment Whether the tank storage capacity meets the gas storage conditions:
式中,Vt=1时表示可以储气,Vt=0时表示为不可以储气;Ss为电转气储气罐当前调度时段的存储容量,Ss,min为电转气储气罐内最小存储容量,Ss,max为电转气储气罐内最大存储容量。In the formula, when V t = 1, it means that gas storage is possible, and when V t = 0, it means that gas storage is not possible; S s is the storage capacity of the power-to-gas gas storage tank in the current scheduling period, and S s,min is the power-to-gas gas storage tank The minimum storage capacity inside, S s,max is the maximum storage capacity inside the power-to-gas storage tank.
电转气设备储气罐的存储容量为:The storage capacity of the gas storage tank of the power-to-gas equipment is:
△P=PS-P0 △P=P S -P 0
式中,K为储气罐内压缩机单位时间耗气量;Pa为电转气储气罐安装所在地的海拔高度的大气压;△P为当前调度时段电转气储气罐气压PS与最低送出气压P0的变化量;KL为当前调度时段内电转气储气罐内压力综合参数;Q为当前调度时段内电转气储气罐输出气流量;In the formula, K is the gas consumption per unit time of the compressor in the gas storage tank; P a is the atmospheric pressure at the altitude where the power-to-gas gas storage tank is installed; The variation of P 0 ; K L is the comprehensive parameter of the internal pressure of the power-to-air gas storage tank during the current scheduling period; Q is the output gas flow rate of the power-to-gas gas storage tank during the current scheduling period;
当Vt=0时,即电转气设备储气罐存储容量不满足储气条件,则跳转至步骤4;如果Vt=1时,表示电转气储气罐容量满足储气条件,则将多余的风电转化的天然气存储在储气罐中,然后跳转至步骤3.5;When V t = 0, that is, the storage capacity of the gas storage tank of the power-to-gas equipment does not meet the gas storage conditions, then jump to step 4; if V t = 1, it means that the capacity of the gas storage tank of the power-to-gas equipment meets the gas storage conditions, then set The excess natural gas converted from wind power is stored in the gas storage tank, and then skip to step 3.5;
其中,电转气设备消耗的电能为:Among them, the electric energy consumed by the power-to-gas equipment is:
式中,PP2G表示电转气设备的耗电功率;Hg表示天然气的热值;ηP2G表示电转气设备的转换效率;In the formula, P P2G represents the power consumption of the power-to-gas equipment; H g represents the calorific value of natural gas; η P2G represents the conversion efficiency of the power-to-gas equipment;
步骤3.4::若t时段电负荷无法满足系统基础电负荷需求时,判断电转气装置储气罐存储容量是否满足放气条件;若是,则电转气装置储气罐放气,采用燃气轮机将天然气转化为电能供给系统电负荷,然后跳转至步骤3.5;若否,则向电网购电Pgrid;Step 3.4: If the electric load cannot meet the basic electric load demand of the system during the period t, judge whether the storage capacity of the gas storage tank of the power-to-gas device meets the gas release condition; Supply system electric load for electric energy, and then jump to step 3.5; if not, purchase electricity P grid from the grid ;
所述放气条件为:Described deflation condition is:
式中,Xt=1时表示可以放气,Xt=0时表示为不可以放气;In the formula, when X t = 1, it means deflation is possible, and when X t = 0, it means that deflation is not possible;
其中,储气罐不可以放气时向电网购电量:Among them, when the gas storage tank cannot release gas, it purchases electricity from the grid:
Pgrid=PE-PCHP-PF P grid =P E -P CHP -P F
式中,Pgrid表示储气罐不可以放气时向电网的购电量;In the formula, P grid represents the electricity purchased from the grid when the gas storage tank cannot be released;
燃气轮机的发电功率:Gas turbine power generation:
PGT=ηGTQHg P GT =η GT QH g
式中,PGT表示燃气轮机的发电功率;ηGT表示燃气轮机的转换效率;In the formula, PGT represents the generating power of the gas turbine; ηGT represents the conversion efficiency of the gas turbine;
步骤3.5:判断当前时段t是否达到电能平衡状态:Step 3.5: Judging whether the current time period t has reached the power balance state:
式中,如果Yt=1时,即达到电能平衡状态,则跳转至步骤4;如果Yt=0时,即无法达到电能平衡状态,则向电网购电Pgrid,直到电能平衡后返回步骤4;In the formula, if Y t = 1, the state of electric energy balance is reached, then jump to step 4; if Y t = 0, that is, the state of electric energy balance cannot be reached, then purchase power P grid from the grid until the state of electric energy balance is returned Step 4;
其中,电能处于平衡状态时向电网购电量:Among them, when the electric energy is in a balanced state, the electricity purchased from the grid:
Pgrid=PE-PCHP-PF-PGT P grid =P E -P CHP -P F -P GT
式中,Pgrid表示为达到电能平衡时向电网购电量。In the formula, P grid represents the power purchased from the grid when the power balance is reached.
步骤4:判断电–气联合系统当前时段t是否小于调度周期T,如果t<T,则本调度时段结束,令t=t+1后,执行步骤1;如果t=T,则结束本周期的调度。Step 4: Judging whether the current period t of the electricity-gas combined system is less than the scheduling period T, if t<T, then the scheduling period ends, after setting t=t+1, execute
最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明权利要求所限定的范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still be Modifications are made to the technical solutions described in the foregoing embodiments, or equivalent replacements are made to some or all of the technical features; these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope defined by the claims of the present invention.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910513732.3A CN110245863B (en) | 2019-06-14 | 2019-06-14 | An electric combined system and online regulation method based on electric conversion energy storage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910513732.3A CN110245863B (en) | 2019-06-14 | 2019-06-14 | An electric combined system and online regulation method based on electric conversion energy storage |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110245863A CN110245863A (en) | 2019-09-17 |
CN110245863B true CN110245863B (en) | 2023-01-17 |
Family
ID=67887026
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910513732.3A Active CN110245863B (en) | 2019-06-14 | 2019-06-14 | An electric combined system and online regulation method based on electric conversion energy storage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110245863B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110707712B (en) * | 2019-10-15 | 2022-10-28 | 东北大学 | A Reliability Analysis Method of Microgrid Power Supply Considering Demand Response |
CN111899121B (en) * | 2020-06-23 | 2023-07-04 | 深圳职业技术学院 | Regional energy system source-load coordinated operation simple method based on electric gas conversion equipment |
CN112039750A (en) * | 2020-09-01 | 2020-12-04 | 四川大学 | Electrical combined system network state estimation method based on comprehensive energy system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2015157208A (en) * | 2015-12-29 | 2017-07-05 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Саратовский государственный технический университет имени Гагарина Ю.А." (СГТУ имени Гагарина Ю.А.) | The method of operation of the compressor station of gas pipelines |
WO2018059096A1 (en) * | 2016-09-30 | 2018-04-05 | 国电南瑞科技股份有限公司 | Combined decision method for power generation plans of multiple power sources, and storage medium |
CN109193815A (en) * | 2018-10-17 | 2019-01-11 | 燕山大学 | A kind of combined heat and power dispatching method improving wind electricity digestion |
CN109461097A (en) * | 2018-11-15 | 2019-03-12 | 东北大学 | A kind of electric heating association system dispatching method based on additional heating source consumption abandonment |
-
2019
- 2019-06-14 CN CN201910513732.3A patent/CN110245863B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2015157208A (en) * | 2015-12-29 | 2017-07-05 | Федеральное государственное бюджетное образовательное учреждение высшего образования "Саратовский государственный технический университет имени Гагарина Ю.А." (СГТУ имени Гагарина Ю.А.) | The method of operation of the compressor station of gas pipelines |
WO2018059096A1 (en) * | 2016-09-30 | 2018-04-05 | 国电南瑞科技股份有限公司 | Combined decision method for power generation plans of multiple power sources, and storage medium |
CN109193815A (en) * | 2018-10-17 | 2019-01-11 | 燕山大学 | A kind of combined heat and power dispatching method improving wind electricity digestion |
CN109461097A (en) * | 2018-11-15 | 2019-03-12 | 东北大学 | A kind of electric heating association system dispatching method based on additional heating source consumption abandonment |
Also Published As
Publication number | Publication date |
---|---|
CN110245863A (en) | 2019-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112736939B (en) | Optimized capacity configuration method for hydrogen production and storage device of hydrogen-doped natural gas comprehensive energy system | |
CN110932317B (en) | A Design Method for Distributed Energy System with Essentially Renewable Energy Complementary | |
CN108832656B (en) | Multi-target planning method for utilizing micro energy network based on electricity-gas conversion and renewable energy | |
CN106444562B (en) | Coordination system and method of multiple energy storage devices based on wind-solar-electric-heat-gas conversion module | |
CN109742800B (en) | Energy internet system based on natural gas, hydrogen and electric power and working method | |
CN112800619B (en) | Modeling and planning method of multi-source heterogeneous all-renewable energy thermal-electricity-storage coupled system | |
CN110991000B (en) | Modeling method for energy hub considering solid oxide fuel cell and electric conversion gas | |
CN109474025B (en) | Optimized dispatching model of park level comprehensive energy system | |
CN112329259A (en) | A multi-energy complementary cooling, heating and power cogeneration microgrid framework and its modeling method | |
CN110245863B (en) | An electric combined system and online regulation method based on electric conversion energy storage | |
CN212063513U (en) | Renewable energy power generation methane production device and power generation device with peak regulation capacity | |
Huang et al. | Assessment of an integrated energy system embedded with power-to-gas plant | |
CN110244568B (en) | Energy hub model of industrial enterprise microgrid and multi-energy complementary optimization control method thereof | |
CN106712033A (en) | A method for absorbing abandoned wind in a thermal power plant | |
CN114676897A (en) | Optimal scheduling method for comprehensive energy system of park containing CHP-P2G-hydrogen energy | |
CN116231694A (en) | Comprehensive energy system with wind-solar complementary hydrogen production and cold-hot electric multifunctional complementation | |
CN116402214A (en) | A low-carbon optimal operation method for hydrogen-containing integrated energy systems considering generalized integrated demand response | |
Chi et al. | Optimization of configuration for home micro-grid cogeneration system based on Wind-PV/T-PEMFC | |
CN116742692A (en) | An optimized dispatching method for hydrogen-containing integrated energy systems taking into account comprehensive demand response | |
US12316126B2 (en) | Energy storage and modulating system for renewable energy off-grid power generation, and method for modulating the same | |
CN110380447B (en) | A risk reduction scheduling method for electric-gas interconnected energy system under wind turbine failure | |
CN117649089A (en) | Robust low-carbon optimal scheduling method for integrated energy system integrating hydrogen energy | |
CN117787636A (en) | Multi-target planning method, system and equipment for comprehensive energy system | |
CN217656429U (en) | Micro-grid multi-energy complementary system based on offshore wind power | |
Jin et al. | Modeling and Simulation of Energy Hub Considering Solid Oxide Fuel Cell and Power to Gas |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |