[go: up one dir, main page]

CN110106789A - Titanium/aluminum/titanium light high-strength emergency bridge and erection method - Google Patents

Titanium/aluminum/titanium light high-strength emergency bridge and erection method Download PDF

Info

Publication number
CN110106789A
CN110106789A CN201910349100.8A CN201910349100A CN110106789A CN 110106789 A CN110106789 A CN 110106789A CN 201910349100 A CN201910349100 A CN 201910349100A CN 110106789 A CN110106789 A CN 110106789A
Authority
CN
China
Prior art keywords
titanium
bridge
floorings
aluminium
emergency
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910349100.8A
Other languages
Chinese (zh)
Inventor
史长根
冯柯
张晶晶
房中行
邵飞
柯文轩
孙泽瑞
李峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PLA University of Science and Technology
Original Assignee
PLA University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PLA University of Science and Technology filed Critical PLA University of Science and Technology
Priority to CN201910349100.8A priority Critical patent/CN110106789A/en
Publication of CN110106789A publication Critical patent/CN110106789A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

为了使车辆和机械克服浅滩、河流、坑洼、泥泞及松软地面等路面障碍,发明了一种6米宽,厚度为2mm+6mm+2mm钛/铝/钛轻质高强度金属复合材料应急桥。应急桥主要由桥面板、横系材、辅助器材等组成。8块桥面板组成两个等宽车辙,两车辙之间通过横系材联接为整体;桥面板本体为工字梁结构,上、下翼板和腹板采用钛/铝/钛叠层材料,钛/铝/钛为“三明治”式叠层结构。应急桥其整桥(长×宽×高)尺寸为:6000mm×3400mm×240mm;桥面板(长×宽×高)尺寸为:600mm×260mm×240mm;其总重量为1600kg;桥面板单块重量约为190kg。由于桥面板单块重量低于200kg,且长度超过600mm,可由4‑6人进行徒手架设,架设时间小于30分钟。此应急桥可通过组合架设使用,保证履带式荷载40吨、轮式轴压13吨的机械装备顺利通过,也可单独架设使用保证人员通过较深的山谷等路面障碍。In order to enable vehicles and machinery to overcome road obstacles such as shoals, rivers, potholes, mud and soft ground, a 6-meter-wide emergency bridge with a thickness of 2mm+6mm+2mm titanium/aluminum/titanium light-weight high-strength metal composite material was invented . The emergency bridge is mainly composed of bridge deck, transverse ties, auxiliary equipment and so on. Eight bridge decks form two equal-width ruts, and the two ruts are connected as a whole by transverse ties; the main body of the bridge deck is an I-beam structure, and the upper and lower wing plates and webs are made of titanium/aluminum/titanium laminated materials. Titanium/aluminum/titanium is a "sandwich" laminated structure. The size of the whole bridge (length × width × height) of the emergency bridge is: 6000mm × 3400mm × 240mm; the size of the bridge deck (length × width × height) is: 600mm × 260mm × 240mm; its total weight is 1600kg; the weight of a single bridge deck About 190kg. Since the weight of a single bridge deck is less than 200kg and the length exceeds 600mm, it can be erected by 4-6 people by hand, and the erection time is less than 30 minutes. This emergency bridge can be erected in combination to ensure the smooth passage of mechanical equipment with a crawler load of 40 tons and a wheeled axial pressure of 13 tons. It can also be erected and used alone to ensure that personnel can pass through deep valleys and other road obstacles.

Description

一种钛/铝/钛轻质高强度应急桥梁及架设方法A titanium/aluminum/titanium light-weight high-strength emergency bridge and its erection method

技术领域technical field

本发明涉及的是一种钛/铝/钛轻质高强度应急桥梁及架设方法,属于金属复合材料制造及桥梁结构设计等综合技术领域。The invention relates to a titanium/aluminum/titanium light-weight high-strength emergency bridge and its erection method, belonging to the comprehensive technical fields of metal composite material manufacturing and bridge structure design.

背景技术Background technique

在抢险救灾、野外作业或军事行动过程中,一些浅滩、河流、坑洼、泥泞及松软地面严重阻碍了救援车辆和机械的正常通行。应急桥梁是克服上述复杂路面障碍的重要器材工具,在民用运输交通以及战时支援保障方面具有无可替代的作用。基于此,应急桥不仅要重量轻便于架设,又要有足够的强度刚度便于机械车辆通过。During rescue and disaster relief, field operations or military operations, some shoals, rivers, potholes, muddy and soft ground seriously hinder the normal passage of rescue vehicles and machinery. Emergency bridges are important equipment and tools to overcome the above-mentioned complex road obstacles, and play an irreplaceable role in civil transportation and wartime support. Based on this, the emergency bridge should not only be light in weight and easy to erect, but also have sufficient strength and rigidity to facilitate the passage of mechanical vehicles.

目前非金属材料或铝合金等应急桥梁普遍存在强度不够,而钢制结构应急桥梁又由于重量大不易架设,阻碍了应急桥梁的应急抢险的快速抢修保障性能。如模块化小跨径铝合金桥梁(CN 201459589 U)具有模块化安装、结构简单、使用方便的特点,但由于铝合金的本身强度较低,无法很好满足大型重载车辆的通过要求;钢制桥梁网格多点受力桥板(CN204266119 U)利用网格多点受力利用原理,提高了钢制桥梁的使用寿命与安全性,但其便携性、可拆卸性由于其安装过程的繁琐而有所不足;移动应急轻质桥梁结构(CN 204644855U)采用车辆折叠搭载,具有搭载快、负荷强度大、可扩展并调整斜度等优点,但其架设需要车辆以及平台的相对固定,便捷性有待提高;如何找到一种用于桥梁结构的新型材料,使其具有较高的强度以及较轻的重量,同时兼具较好的可安装性、可操作性,成为新型应急桥梁发展的关键。At present, emergency bridges made of non-metallic materials or aluminum alloys generally have insufficient strength, and emergency bridges with steel structures are difficult to erect due to their heavy weight, which hinders the rapid repair support performance of emergency bridges. For example, the modular small-span aluminum alloy bridge (CN 201459589 U) has the characteristics of modular installation, simple structure, and convenient use, but due to the low strength of the aluminum alloy itself, it cannot well meet the passing requirements of large and heavy-duty vehicles; Bridge grid multi-point force bridge plate (CN204266119 U) uses the principle of grid multi-point force utilization to improve the service life and safety of steel bridges, but its portability and detachability are due to the cumbersome installation process. But there are some deficiencies; the mobile emergency light bridge structure (CN 204644855U) adopts vehicle folding to carry, has the advantages of fast carrying, high load strength, expandability and slope adjustment, but its erection requires relatively fixed vehicles and platforms, and is convenient It needs to be improved; how to find a new type of material for bridge structure, so that it has higher strength and lighter weight, and at the same time has better installability and operability, has become the key to the development of new emergency bridges.

发明内容Contents of the invention

此发明包括轻质高强度钛/铝/钛复合材料及其制造方法、6米应急桥的结构组成及架设撤收方法三部分。The invention includes three parts: lightweight high-strength titanium/aluminum/titanium composite material and its manufacturing method, the structural composition of the 6-meter emergency bridge, and its erection and withdrawal method.

1、应急桥轻质高强度钛/铝/钛复合材料及其制造方法1. Lightweight and high-strength titanium/aluminum/titanium composite material for emergency bridge and its manufacturing method

在爆炸焊接过程中,复板首先必须产生弯曲,其次复板不能产生破坏,即爆炸载荷必须满足以下两个条件才能实现成功焊接。爆炸载荷所产生的最大弯矩首先必须超过材料的动态屈服极限弯矩,使复板产生弯折变形,才能满足爆炸焊接复板和基板斜碰撞的条件,因而才有可能获得有效的焊接界面。In the explosive welding process, the doubler plate must first be bent, and secondly, the doubler plate cannot be damaged, that is, the explosive load must meet the following two conditions to achieve successful welding. The maximum bending moment generated by the explosive load must first exceed the dynamic yield limit bending moment of the material to cause the double plate to bend and deform, so as to meet the oblique collision conditions between the double plate and the base plate for explosive welding, and thus it is possible to obtain an effective welding interface.

基复板碰撞速度随着装药厚度的增加而迅速上升,过高的碰撞速度将产生最小界面结合能以外多余的能量,使结合界面发生过度熔化,复合板整体塑性变形、开裂、灼伤等,严重影响界面结合质量和复合板外观。当装药厚度超过上限时,界面熔化现象极为严重,强度极大的拉伸波从地基反射回到结合界面,将处于熔融状态的金属彻底拉开,导致焊接失效。因此装药量上限的控制能够减小界面熔化的程度。另外,钛和铝在爆炸焊接过程中由于界面高温,会生成脆性的TiC、TiO、Al2O3等金属间化合物,因此钛/铝/钛焊接参数的确定应遵循下限法则,即在焊接窗口下限附近获得最佳的参数,使得钛/铝/钛复合材料的界面结合强度最高。The collision velocity of the base-composite plate increases rapidly with the increase of the charge thickness. Excessively high collision velocity will generate excess energy beyond the minimum interface binding energy, which will cause excessive melting of the bonding interface, and the overall plastic deformation, cracking, and burns of the composite plate will cause severe damage. Affects the quality of interface bonding and the appearance of composite panels. When the charge thickness exceeds the upper limit, the phenomenon of interface melting is extremely serious, and the extremely strong tensile wave is reflected from the foundation back to the joint interface, completely pulling apart the metal in the molten state, resulting in welding failure. Therefore, the control of the upper limit of charge amount can reduce the degree of interface melting. In addition, due to the high temperature at the interface between titanium and aluminum, brittle intermetallic compounds such as TiC, TiO, and Al 2 O 3 will be formed during the explosive welding process. Therefore, the determination of titanium/aluminum/titanium welding parameters should follow the lower limit rule, that is, in the welding window The optimal parameters are obtained near the lower limit, which makes the interfacial bonding strength of titanium/aluminum/titanium composites the highest.

装药厚度δ、基复板间距s、炸药爆速D是直接决定爆炸焊接质量的三个静态工艺参数。根据建立的钛-铝动态参数窗口的边界条件,以界面结合能最小原理、窗口法则、极限法则为理论原则,根据焊接动态参数窗口,碰撞速度下限,碰撞速度上限,结合下限质量比Rmin、上限质量比Rmax这两个边界条件,可构建并计算钛-铝合金爆炸焊接装药质量比与复板厚度初始参数窗口。Charge thickness δ, spacing s between base and cladding plates, and explosive detonation velocity D are three static process parameters that directly determine the quality of explosive welding. According to the established boundary conditions of the titanium-aluminum dynamic parameter window, based on the principle of minimum interface binding energy, window law and limit law, according to the welding dynamic parameter window, the lower limit of the collision velocity, the upper limit of the collision velocity, the combined lower limit mass ratio R min , The two boundary conditions of the upper limit mass ratio R max can be used to construct and calculate the initial parameter window of the charge mass ratio of titanium-aluminum alloy explosive welding and the doubler plate thickness.

长期的爆炸焊接生产表明,异种金属复合板的装药厚度在装药质量比下限Rmin附近取值时,结合质量最佳,符合装药厚度下限法则。爆炸焊接时,配置60#粉状乳化炸药,即在粉状乳化炸药中添加60%石英砂,其密度控制炸药爆速D≈1200m/s,有效多方指数γ=1.8,针对2mm厚度的钛和6mm厚度的铝,计算可得下限装药厚度δ0=20-25mm;两板间距s=3-4mm。为消除稀疏波边界效应,复板尺寸和装药面积在起爆端增加约30mm、在两侧和尾端均分别增加20mm;复合板钛/铝一次爆炸焊接后进行消除爆炸应力退火处理,退火温度为350℃,随炉冷却后进行校平和表面处理,再进行二次爆炸,二次爆炸焊接参数60#粉状乳化炸药,焊接参数取上述一次爆炸参数的最下限值,消除钛/铝/钛双面复合板爆炸应力退火工艺参数参考单面复合板退火参数。经过两次爆炸焊接及退火校平处理后得到了100%厚度为2mm+6mm+2mm钛/铝/钛高强度双面复合材料。其抗拉强度大于425MPa;规定非比例延伸强度大于305MPa;断后伸长率大于20%;界面剪切强度大于108MPa。The long-term explosive welding production shows that when the charge thickness of the dissimilar metal clad plate is near the lower limit R min of the charge mass ratio, the bonding quality is the best, which conforms to the law of the lower limit of the charge thickness. During explosive welding, configure 60 # powdery emulsion explosive, that is, add 60% quartz sand to the powdery emulsion explosive, and its density Control explosive detonation velocity D≈1200m/s, effective polytropic index γ=1.8, for 2mm thick titanium and 6mm thick aluminum, calculate the lower limit charge thickness δ 0 =20-25mm; the distance between two plates s=3-4mm. In order to eliminate the sparse wave boundary effect, the doubler plate size and charge area were increased by about 30mm at the initiation end, and 20mm at both sides and the tail end respectively; The temperature is 350°C. After cooling with the furnace, leveling and surface treatment are carried out, and then the secondary explosion is carried out. The welding parameters of the secondary explosion are 60 # powdery emulsion explosives. The welding parameters take the lower limit of the above primary explosion parameters to eliminate titanium/aluminum/ The technical parameters of explosive stress annealing of titanium double-sided clad plate refer to the annealing parameters of single-sided clad plate. After two times of explosive welding and annealing and leveling treatment, a 100% titanium/aluminum/titanium high-strength double-sided composite material with a thickness of 2mm+6mm+2mm was obtained. Its tensile strength is greater than 425MPa; the specified non-proportional elongation strength is greater than 305MPa; the elongation after breaking is greater than 20%; the interface shear strength is greater than 108MPa.

2、6米长应急桥的结构组成2. Structural composition of the 6-meter-long emergency bridge

此应急桥采用上述厚度为2mm+6mm+2mm钛/铝/钛轻质高强度金属复合层板制造,为了克服浅滩、河流、坑洼、泥泞及松软地面或类似障碍,此发明设计6米长应急桥的技术方案,可保证履带式荷载40吨、轮式轴压13吨的机械装备顺利通过桥梁。This emergency bridge is made of titanium/aluminum/titanium lightweight high-strength metal composite laminates with a thickness of 2mm+6mm+2mm. In order to overcome shoals, rivers, potholes, muddy and soft ground or similar obstacles, this invention is designed to be 6 meters long The technical scheme of the emergency bridge can ensure that the mechanical equipment with a crawler load of 40 tons and a wheeled axial load of 13 tons can pass through the bridge smoothly.

发明的6米应急桥由8块桥面板组成两个等宽车辙,两车辙之间通过横系材联接为整体;桥面板本体为工字梁结构,上、下翼板和腹板采用钛/铝/钛叠层材料,钛/铝/钛为三明治式叠层结构。应急桥其整桥(长×宽×高)尺寸为:6000mm×3400mm×240mm;桥面板(长×宽×高)尺寸为:600mm×260mm×240mm;其总重量为1600kg;桥面板单块重量约为190kg。由于桥面板单块重量低于200kg,且长度超过600mm,可由4-6人进行徒手架设,架设时间小于30分钟。The invented 6-meter emergency bridge consists of 8 bridge decks consisting of two equal-width ruts, and the two ruts are connected as a whole by transverse ties; the bridge deck body is an I-beam structure, and the upper and lower flanges and webs are made of titanium/ Aluminum/titanium laminated material, titanium/aluminum/titanium is a sandwich laminated structure. The size of the whole bridge (length × width × height) of the emergency bridge is: 6000mm × 3400mm × 240mm; the size of the bridge deck (length × width × height) is: 600mm × 260mm × 240mm; its total weight is 1600kg; the weight of a single bridge deck About 190kg. Since the weight of a single bridge deck is less than 200kg and the length exceeds 600mm, it can be erected by 4-6 people by hand, and the erection time is less than 30 minutes.

发明的6米长应急桥主要由桥面板、横系材、辅助器材组成如图1所示,整桥由8块桥面板组成两个等宽车辙,两车辙之间通过横系材联接为整体。The 6-meter-long emergency bridge invented is mainly composed of bridge decks, transverse ties, and auxiliary equipment. As shown in Figure 1, the whole bridge consists of 8 bridge decks to form two equal-width ruts, and the two ruts are connected by transverse ties to form a whole. .

桥面板本体为工字梁结构,在桥面板本体上设置有单耳、双耳、外顶块、内顶块、长插销及提环。单双耳用于横向之间联结;插销用于单双耳之间及横系材与桥面板联结;提环用于人工抬运或机械吊运,如图2所示。The bridge deck body is an I-beam structure, and there are single ears, double ears, outer top blocks, inner top blocks, long pins and lifting rings on the bridge deck body. The single and double lugs are used for horizontal connection; the pins are used for the connection between the single and double lugs and the connection between the horizontal tie and the bridge deck; the lifting ring is used for manual or mechanical lifting, as shown in Figure 2.

桥面板主体上、下翼板和腹板为钛/铝/钛复合材料,上、下翼板厚度为8mm,腹板厚度为6mm。由于钛/铝/钛复合材料两种组分物理性能相差巨大,无法焊接,因此本方案采用铆接的连接方式,上下翼板通过折边角钢铆接在一起,如图3所示。The upper and lower flanges and webs of the bridge deck are made of titanium/aluminum/titanium composite materials, the thickness of the upper and lower flanges is 8mm, and the thickness of the web is 6mm. Due to the huge difference in physical properties of the two components of titanium/aluminum/titanium composite materials, they cannot be welded. Therefore, this scheme adopts the riveting connection method, and the upper and lower wings are riveted together by hemming angle steel, as shown in Figure 3.

横系材用于桥面板间横向联结固定,可根据装备的类型调整宽度。联接时,通过顺时针旋转或逆时针旋转调节手柄可以使横系材伸长或缩短如图4所示。应急桥的调整宽度为2800mm~3300mm。Transverse ties are used for horizontal connection and fixation between bridge decks, and the width can be adjusted according to the type of equipment. When connecting, the horizontal tie can be lengthened or shortened by rotating the adjusting handle clockwise or counterclockwise, as shown in Figure 4. The adjustment width of the emergency bridge is 2800mm~3300mm.

辅助器材包括撬杠、锚钎、锤。撬杠主要用于拼装时桥面板挪动和锚钎撤收以及插销撤收。锚钎主要用于系留。锤用于将锚钎固定在地面和插销的撤收,如图4、图5、图6所示。Auxiliary equipment includes crowbar, anchor drill, hammer. The crowbar is mainly used for the movement of the bridge deck, the withdrawal of the anchor and the withdrawal of the bolt during assembly. Anchor drills are mainly used for mooring. The hammer is used to fix the anchor drill on the ground and withdraw the bolt, as shown in Fig. 4, Fig. 5 and Fig. 6.

3、6米长应急桥的架设与撤收方法3. Erection and withdrawal methods of 6-meter-long emergency bridge

发明的6米长应急桥的架设方法如下:The erection method of the 6 meter long emergency bridge of invention is as follows:

(1)架设第一块桥面板(1) Erection of the first bridge deck

6名人员同时握住桥面板的提环,将第一块桥面板抬到架设位置(靠近靠近浅滩、坑洼、弹坑等类似障碍附近,中间的两人撤出,分别抬在桥面板的两端头,只到到达指定位置,如图8所示)。6 personnel hold the lifting ring of the bridge deck at the same time, lift the first bridge deck to the erection position (near the shallows, potholes, bomb craters and other similar obstacles, the two people in the middle withdraw, and lift them on the two sides of the bridge deck respectively. terminal until it reaches the specified position, as shown in Figure 8).

(2)架设第二块桥面板(2) Erection of the second bridge deck

按第一步方法将第二块桥面板抬到第一块桥面板旁边,与第一块桥面板横向联接,如图9所示。联结时,将双耳上的插销拔出,用手抬或者撬杠移动桥面板,将两桥面板上对应的单、双耳插入,同时两桥面板上的内外顶块随之对应插入。然后,将单双耳用插销固定。Lift the second bridge deck to the side of the first bridge deck according to the first step, and connect it horizontally with the first bridge deck, as shown in Figure 9. When connecting, pull out the pins on the two ears, move the bridge deck by hand or a crowbar, insert the corresponding single and double ears on the two bridge decks, and at the same time insert the inner and outer top blocks on the two bridge decks accordingly. Then, fix the single and double ears with pins.

(3)架设第三、四块桥面板(3) Erection of the third and fourth bridge decks

按以上方法架设第三、四块桥面板,组成一个车辙,如图10所示。According to the above method, the third and fourth bridge decks are erected to form a rut, as shown in Figure 10.

(4)架设第五~八块桥面板(4) Erection of the fifth to eighth bridge decks

按以上方法架设第五~八块桥面板,组成另一个车辙,如图11所示。According to the above method, the fifth to eighth bridge decks are erected to form another rut, as shown in Figure 11.

(5)联接横系材(5) Connecting horizontal ties

将横系材分别联接在辆车辙内侧腹板两端的单、双耳上,联接时,将装有叉头一端与单耳相连,将装有环头的一端与双耳相连,如图12所示。Connect the transverse ties to the single and double lugs at both ends of the inner web of the rut respectively. When connecting, connect the end with the fork head to the single ear, and the end with the ring head to the double lugs, as shown in Figure 12 Show.

(6)固定桥跨(6) Fixed bridge span

将锚钎插入桥跨辆车辙外侧桥面板两端的单双耳孔中,用大锤将锚钎固定在弹坑两边路基上,将桥跨固定,如图13所示。Insert the anchors into the single and double lugs on both ends of the bridge deck outside the rut of the bridge span, fix the anchors on the subgrades on both sides of the crater with a sledgehammer, and fix the bridge span, as shown in Figure 13.

6米应急桥的撤收流程与架设流程基本相反。此应急桥可通过组合架设使用,保证履带式荷载40吨、轮式轴压13吨的机械装备顺利通过,也可单独架设使用保证人员通过较深的山谷等路面障碍。The withdrawal process of the 6-meter emergency bridge is basically the opposite of the erection process. This emergency bridge can be erected in combination to ensure the smooth passage of mechanical equipment with a crawler load of 40 tons and a wheeled axial pressure of 13 tons. It can also be erected and used alone to ensure that personnel can pass through deep valleys and other road obstacles.

附图说明Description of drawings

图1为6米应急桥示意图,1-桥面板、2-横系材、3、辅助器材;图2为桥面板示意图,1-提环、2-单耳接头、3、桥面板本体、4-外顶块、5-内顶块、6-双耳接头、7-插销;图3为桥面板主体截面示意图,1-翼板(Ti/Al/Ti复合材料)、2-腹板(Ti/Al/Ti复合材料)、3-折边角钢、4-铆钉;图4为横系材示意图,1-叉头螺杆、2-套管、3、调节手柄、4-环头螺杆;图5为锚钎;图6为锤;图7为撬杠;图8为架设第一块桥面板示意图;图9为架设第二块桥面板示意图;图10为架设第三、四块桥面板示意图;图11为架设第五~八块桥面板示意图;图12为联接横系材示意图;图13为固定桥跨示意图。Figure 1 is a schematic diagram of a 6-meter emergency bridge, 1-bridge deck, 2-horizontal ties, 3, auxiliary equipment; Figure 2 is a schematic diagram of the bridge deck, 1-lift ring, 2-single ear joint, 3, bridge deck body, 4 -outer top block, 5-inner top block, 6-ear joint, 7-bolt; Figure 3 is a schematic cross-sectional view of the main body of the bridge deck, 1-flange (Ti/Al/Ti composite material), 2-web (Ti /Al/Ti composite material), 3-flange angle steel, 4-rivet; Figure 4 is a schematic diagram of the horizontal tie material, 1-fork head screw, 2-sleeve, 3, adjusting handle, 4-ring head screw; Figure 5 Figure 6 is a hammer; Figure 7 is a crowbar; Figure 8 is a schematic diagram of erecting the first bridge deck; Figure 9 is a schematic diagram of erecting the second bridge deck; Figure 10 is a schematic diagram of erecting the third and fourth bridge decks; Figure 11 is a schematic diagram of erecting the fifth to eighth bridge decks; Figure 12 is a schematic diagram of connecting transverse ties; Figure 13 is a schematic diagram of fixed bridge spans.

Claims (4)

1. a kind of titanium/aluminium/titanium light-high-strength emergency bridge and erection method, it is characterized in that light-high-strength titanium/aluminium/titanium is compound Material and its manufacturing method;6 meters long titanium/aluminium/titanium emergency bridge structure composition;It is 6 meters long emergency bridge erection and remove receiving method.
2. a kind of titanium/aluminium/titanium light-high-strength emergency bridge according to claim 1 and erection method, it is characterized in that gently Matter high strength titanium/aluminium/titanium composite material and its manufacturing method, titanium/aluminium/titanium composite material charge depth is in charge to mass ratio lower limit Near Rmin when value, bond quality is best, meets charge depth lower limit rule, configuration 60#Powdery emulsifying explosive, i.e., in powdery 60% quartz sand, density are added in emulsionExplosion velocity of explosive D ≈ 1200m/s is controlled, it is effectively multi-party Exponent gamma=1.8, the aluminium of titanium and 6mm thickness for 2mm thickness, can be calculated lower limit charge depth δ0=20-25mm, two plates Distance s=3-4mm;It carries out eliminating detonation stresses annealing, annealing temperature 350 after composite plate titanium/explosive welding of aluminium one time DEG C, it is smoothed and is surface-treated after furnace cooling, then carry out subsequent explosion, subsequent explosion welding parameter 60#It is powder emulsified fried Medicine, welding parameter take the most lower limit value of an above-mentioned explosive parameters, eliminate titanium/aluminium/titanium double-sided composite plate detonation stresses lehr attendant Skill parameter reference single side composite plate annealing parameter;100% thickness has been obtained after explosive welding twice and annealing smoothing process For 2mm+6mm+2mm titanium/aluminium/titanium high-strength double-face composite material, it is strong that tensile strength is greater than 425MPa, regulation Non-proportional extension Degree is greater than 305MPa, elongation after fracture is greater than 20%;Interface shear strength is greater than 108MPa.
3. a kind of titanium/aluminium/titanium light-high-strength emergency bridge according to claim 1 and erection method, it is characterized in that this Bridge of meeting an urgent need is manufactured using above-mentioned with a thickness of 2mm+6mm+2mm titanium/aluminium/titanium light-high-strength metal composite laminate, 6 meters long emergency bridge It is mainly made of floorings, horizontal system's material, auxiliary appliance, whole bridge forms two wide tracks by 8 pieces of floorings, leads between two tracks It is whole for crossing horizontal system's material connection;Floorings ontology is structural I-beam, and upper and lower wing plate and web use titanium/aluminium/titanium laminated material Material, it is ensured that 40 tons of crawler type load, wheeled axis press 13 tons of mechanized equipment to pass through bridge;Meet an urgent need bridge its whole bridge (it is long × It is wide × high) size are as follows: 6000mm × 3400mm × 240mm, floorings (length × width × height) size are as follows: 600mm × 260mm × 240mm, its total weight are 1600kg, floorings monolithic weight is about 190kg;Since floorings monolithic weighs less than 200kg, and Length is more than 600mm, can manually be set up by 4-6 people, sets up the time less than 30 minutes;Floorings ontology is I-beam knot Structure is provided with monaural, ears, outer jacking block, interior jacking block, cremorne bolt and drop handle on floorings ontology;Single ears are for transverse direction Between be coupled, bolt is used between single ears and horizontal system's material is coupled with floorings, and drop handle is transported or machinery handling for manually lifting;Bridge floor The upper and lower wing plate of plate main body and web are titanium/aluminium/titanium composite material, and upper and lower wing plate is with a thickness of 8mm, web thickness 6mm;Horizontal system Transverse splicing is fixed between material is used for floorings, can adjust width according to the type of equipment.When connection, by rotating clockwise or inverse Hour hands rotation regulation handle can be such that horizontal system's material elongates or shortens;The adjustment width of emergency bridge is 2800mm~3300mm;Auxiliary Equipment includes crowbar, anchor pricker, hammer;Floorings, which are moved, when crowbar is mainly used for assembly removes receipts with anchor pricker and bolt removes receipts;Anchor pricker It is mainly used for being tethered at;It hammers into shape and removes receipts for what anchor pricker was fixed on ground and bolt.
4. a kind of titanium/aluminium/titanium light-high-strength emergency bridge according to claim 1 and erection method, it is characterized in that 6 meters The erection of long emergency bridge and remove receiving method are as follows: set up first piece of floorings, 6 personnel hold the drop handle of floorings simultaneously, by the One piece of floorings lifts to decorating position, and when near the similar obstacles such as shoal, hollow, crater, two intermediate people are withdrawn from, respectively The two ends in floorings are lifted, only to arrival designated position;Second piece of floorings is set up, by the first one step process by second piece of bridge floor Plate is lifted to beside first piece of floorings, laterally couple with first piece of floorings, when connection, by the bolt extraction on ears, uses hand Single, double ear corresponding on two floorings is inserted by lift or the mobile floorings of crowbar, at the same the inside and outside jacking block on two floorings with Correspondence insertion, then, single ears are fixed with bolt;Third and fourth block floorings is set up, sets up third and fourth by the above process Block floorings form a track;The five~eight piece of floorings are set up, set up the five~eight piece of floorings, group by the above process At another track;Couple horizontal system's material, horizontal system's material is connected in respectively in track on the single, double ear at coxostermum both ends, couples When, it will be connected equipped with plug one end with monaural, one end equipped with ring head will be connected with ears;Fixed bridge is across by anchor pricker insertion bridge In single Double-ear-hole across bridge floor board ends on the outside of track, anchor pricker is fixed on the roadbed of crater both sides with sledgehammer, spanning is consolidated It is fixed;The removing of 6 meters of emergency bridges receives process and erection process is substantially opposite;This emergency bridge can be set up by combination to be used, and guarantees crawler belt 40 tons of formula load, wheeled axis press 13 tons of mechanized equipment to pass through, can also individually set up passed through using guarantee personnel it is deeper The road barriers such as mountain valley.
CN201910349100.8A 2019-04-30 2019-04-30 Titanium/aluminum/titanium light high-strength emergency bridge and erection method Pending CN110106789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910349100.8A CN110106789A (en) 2019-04-30 2019-04-30 Titanium/aluminum/titanium light high-strength emergency bridge and erection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910349100.8A CN110106789A (en) 2019-04-30 2019-04-30 Titanium/aluminum/titanium light high-strength emergency bridge and erection method

Publications (1)

Publication Number Publication Date
CN110106789A true CN110106789A (en) 2019-08-09

Family

ID=67487229

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910349100.8A Pending CN110106789A (en) 2019-04-30 2019-04-30 Titanium/aluminum/titanium light high-strength emergency bridge and erection method

Country Status (1)

Country Link
CN (1) CN110106789A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0340409A1 (en) * 1988-04-29 1989-11-08 Dornier Gmbh Bridge
US5331700A (en) * 1991-08-08 1994-07-26 Man Gutehoffnungshutte Ag Bridging system consisting of track supports
CN102561171A (en) * 2011-12-28 2012-07-11 中国人民解放军总后勤部建筑工程研究所 Detachable type emergency bridge made of composite material
CN106944736A (en) * 2017-05-22 2017-07-14 史少杰 The double vertical explosive welding 3-layer composite materials of the high corrosion resistant titanium/aluminium/titanium of light-high-strength
CN108857035A (en) * 2018-07-12 2018-11-23 中国人民解放军陆军工程大学 TA (1-18)/5 series aluminum alloy/TA (1-18) composite plate and welding method
CN208309362U (en) * 2018-05-03 2019-01-01 赵启林 A kind of large span modular composite emergency bridge suitable for artificial assembly

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0340409A1 (en) * 1988-04-29 1989-11-08 Dornier Gmbh Bridge
US5331700A (en) * 1991-08-08 1994-07-26 Man Gutehoffnungshutte Ag Bridging system consisting of track supports
CN102561171A (en) * 2011-12-28 2012-07-11 中国人民解放军总后勤部建筑工程研究所 Detachable type emergency bridge made of composite material
CN106944736A (en) * 2017-05-22 2017-07-14 史少杰 The double vertical explosive welding 3-layer composite materials of the high corrosion resistant titanium/aluminium/titanium of light-high-strength
CN208309362U (en) * 2018-05-03 2019-01-01 赵启林 A kind of large span modular composite emergency bridge suitable for artificial assembly
CN108857035A (en) * 2018-07-12 2018-11-23 中国人民解放军陆军工程大学 TA (1-18)/5 series aluminum alloy/TA (1-18) composite plate and welding method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑远谋: "《爆炸焊接和爆炸复合材料》", 30 April 2017 *

Similar Documents

Publication Publication Date Title
CN104847123B (en) Connect the building method of steel corridor
CN109162356A (en) A kind of assembling type steel structure exempts from casting concrete building structure
CN102409618A (en) Inverted type triangular and obliquely-creeping cradle
CN110553560A (en) Blasting demolition method for building
Liew et al. Structural performance of steel-concrete-steel sandwich composite structures
CN105484147B (en) Steel case purlin composite continuous bridge and its construction method
CN110106789A (en) Titanium/aluminum/titanium light high-strength emergency bridge and erection method
CN205347957U (en) Steel case purlin combination continuous bridge
CN205741871U (en) There is the prestressed reinforced concrete box beam of double limb corrugated steel web
CN100354485C (en) Fixing device and building method for outer decorative stone curtain wall of steel pipe truss tower
CN206607724U (en) A kind of assembling type steel structure Side fascia subiculum upper hanging type attachment structure
CN108005268A (en) Oblique slotted steel plate shear wall
CN202280022U (en) Inversely-hung triangular aslant-climbing hanging basket
CN208379414U (en) A kind of X-type light steel truss structure bridge effectively improving vertical rigidity
CN204715561U (en) The replaceable steel coupling beam of span centre clean cut system
CN107675711A (en) A kind of steel pipe support structure for exempting to tear support open
CN207776150U (en) Oblique slotted steel plate shear wall
CN206616788U (en) A kind of Prefabricated slab type steel reinforced concrete combined staircase
CN213710178U (en) An energy-absorbing protective structure for an air defense wall
CN207314527U (en) H profile steel, the connection structure of H profile steel and H profile steel concrete structure
CN206667082U (en) A kind of steel box-girder splice plate more changing device
CN208184070U (en) A kind of wine cup shape Section of Steel-concrete Composite Beam
CN209011455U (en) A kind of light-duty stair
CN203808353U (en) C-shaped steel reinforced concrete composite interlayer bearing plate
CN111549901A (en) High-ductility concrete slip filler wall frame structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190809