[go: up one dir, main page]

CN110043029A - The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing - Google Patents

The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing Download PDF

Info

Publication number
CN110043029A
CN110043029A CN201910416166.4A CN201910416166A CN110043029A CN 110043029 A CN110043029 A CN 110043029A CN 201910416166 A CN201910416166 A CN 201910416166A CN 110043029 A CN110043029 A CN 110043029A
Authority
CN
China
Prior art keywords
water tank
monitoring
bracket
steel pipe
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910416166.4A
Other languages
Chinese (zh)
Inventor
张宏明
马德志
杨正成
刘扬辉
卢熙文
王雪岚
张弘
胡传贵
杨鸿祥
粟瑶
刘旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Original Assignee
Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Construction Engineering Group Second Construction Engineering Co Ltd filed Critical Guizhou Construction Engineering Group Second Construction Engineering Co Ltd
Priority to CN201910416166.4A priority Critical patent/CN110043029A/en
Publication of CN110043029A publication Critical patent/CN110043029A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/02Details
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/08Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
    • G01N3/10Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces generated by pneumatic or hydraulic pressure
    • G01N3/12Pressure testing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及建筑施工技术领域,且公开了巨型空腹梁钢管满堂支架的水箱预压工艺,包括以下操作工艺:满堂支架搭设→选择预压区域→确定预压荷载→水箱搭设→监测点布置→监测仪器设置→蓄水分级加载→预压监测→沉降稳定→排水卸载→调整支架模板→下道工序。通过使用工地常备简单设备,自行配置水箱,灵活简便,工效高,比传统的堆载预压法工期可缩短1/3以上;加工费用低,操作简便,节省费用,比采用预制钢筋混凝土块预压法可节省投资70~80%,比堆放沙袋预压节省投资30~40%,与现场钢筋材料预压相比可节省投资20%~30%,本预压法具有施工设备少,施工效率高,就地取材,制作简单,环保施工,模拟浇筑过程中的实际受力状态合理等优点。

The invention relates to the technical field of building construction, and discloses a water tank preloading process for a giant hollow beam steel tube full-floor support, including the following operation processes: erecting a full-floor support → selecting a preloading area → determining a preloading load → setting up a water tank → monitoring point layout → monitoring Instrument setting→water storage grading loading→preload monitoring→settlement stabilization→drainage unloading→adjustment of support template→next process. By using the simple equipment standing on site and configuring the water tank by yourself, it is flexible and simple, with high work efficiency, and the construction period can be shortened by more than 1/3 compared with the traditional piling preloading method; the processing cost is low, the operation is simple, and the cost is saved, which is more efficient than using prefabricated reinforced concrete blocks. The pressing method can save 70~80% of investment, 30~40% investment compared with stacking sandbag pre-pressing, and 20%~30% investment compared with on-site reinforced material pre-pressing. This pre-pressing method has the advantages of less construction equipment and higher construction efficiency. It has the advantages of high height, local materials, simple production, environmental protection construction, and reasonable simulation of the actual stress state during the pouring process.

Description

巨型空腹梁钢管满堂支架的预压水箱及预压工艺Pre-pressing water tank and pre-pressing technology of giant hollow beam steel tube full support

技术领域technical field

本发明涉及建筑施工技术领域,具体为巨型空腹梁钢管满堂支架的预压水箱。The invention relates to the technical field of building construction, in particular to a pre-pressed water tank of a giant hollow beam steel tube full of supports.

背景技术Background technique

在大跨度现浇巨型空腹梁混凝土浇筑过程中,支架的稳定性和变形量直接影响空腹梁混凝土浇筑的安全及质量。In the process of large-span cast-in-place giant hollow beam concrete pouring, the stability and deformation of the support directly affect the safety and quality of the hollow beam concrete pouring.

支架预压的目的是为了检验支架的安全性和收集施工沉降数据,经过预压,可检验支架的强度、刚度及安全性,确保施工安全;可消除支架非弹性变形的影响,掌握弹性变形数据,使预拱度设置合理,有利于空腹梁杆件线形控制,现有支架预压荷载常见选择预制钢筋混凝土块预压、水袋预压、堆放沙袋预压、或现场的钢筋材料预压等方法,采用预制钢筋混凝土块预压需要用起吊机分批将预制钢筋混凝土块预压放置在支架,在放置过程中预制钢筋混凝土块预压由于重量和面积不同,造成预制钢筋混凝土块预压不适均匀排列在支架上,导致支架的预压受力不均匀,出现局部预压过载的现象,水袋预压同样需要搬运设备将其堆在支架上,采用水袋预压的方式,容易造成支架预压时偏载,影响测试后的精准度,采用现场的钢筋材料预压,需要耗费大量的物资与人力,综上所述这些方法需要大量的人工、起重吊装设备,材料浪费严重,施工时间较长,不仅费工费时而且对预压场地有一定限制。The purpose of bracket preloading is to test the safety of the bracket and collect construction settlement data. After preloading, the strength, stiffness and safety of the bracket can be tested to ensure construction safety; the influence of the inelastic deformation of the bracket can be eliminated, and the elastic deformation data can be mastered , the pre-camber setting is reasonable, which is beneficial to the linear control of the hollow beam members. The pre-compression load of the existing brackets is commonly selected from the pre-compression of prefabricated reinforced concrete blocks, water bag pre-compression, stacking sand bag pre-compression, or on-site steel material pre-compression, etc. Method, the use of prefabricated reinforced concrete blocks preloading needs to use a crane to place the prefabricated reinforced concrete blocks on the support in batches. During the placement process, the prefabricated reinforced concrete blocks are preloaded due to different weights and areas. The preloading of the reinforced concrete blocks is uncomfortable Evenly arranged on the bracket, the preloading force of the bracket is uneven, and the phenomenon of partial preloading overload occurs. The preloading of the water bag also requires handling equipment to stack it on the bracket. The preloading method of the water bag is easy to cause the bracket. The eccentric load during preloading will affect the accuracy after the test. The use of on-site steel bar material for preloading requires a lot of materials and manpower. In summary, these methods require a lot of labor and hoisting equipment, resulting in serious waste of materials and construction. The time is long, which is not only labor-intensive and time-consuming, but also has certain restrictions on the pre-pressing site.

发明内容SUMMARY OF THE INVENTION

针对上述背景技术的不足,本发明提供了巨型空腹梁钢管满堂支架的预压水箱,具备节省资源、缩短施工工期、操作简便的优点,解决了背景技术提出的问题。In view of the deficiencies of the above background technology, the present invention provides a pre-pressed water tank with a giant hollow beam steel tube full support, which has the advantages of saving resources, shortening the construction period, and being easy to operate, and solves the problems raised by the background technology.

本发明提供如下技术方案:巨型空腹梁钢管满堂支架的水箱预压工艺,包括以下操作工艺:满堂支架搭设→选择预压区域→确定预压荷载→水箱搭设→监测点布置→监测仪器设置→蓄水分级加载→预压监测→沉降稳定→排水卸载→调整支架模板→下道工序;The present invention provides the following technical solutions: a water tank pre-pressing process for a giant hollow beam steel tube full support, including the following operation processes: erecting a full support → selecting a pre-pressing area → determining a pre-loading load → setting up a water tank → monitoring point arrangement → monitoring instrument setting → storage Water stage loading→preload monitoring→settlement stabilization→drainage unloading→adjustment of support template→next process;

首先已搭设完成的钢管满堂支架上设计制作水箱,搭设时直接利用现场脚手架进行,水箱主体采用木方搭建,制作好水箱底模,在进行两侧模板的制作;水箱两侧模板外侧用竖向木方作次楞,主楞为双钢管横向加固,箱体内铺防水布,螺杆采用新型防水对拉螺杆(自带防水封堵);螺杆两端穿孔处另增设胶垫、防水胶等封堵严密,箱体使用木面板材质,箱体制作完成后按要求布置监测点及安置监测仪器,用水泵直接向箱体灌水施压,每级荷载施加完成时,监测各监测点标高并计算沉降量,全部预压荷载施加完毕后,每间隔24小时监测一次并记录各监测点标高,当支架预压符合预压合格时,进行支架卸载,卸载6小时后,监测各监测点标高,并计算支架各监测点的弹性变形量,加载过程中,支架预压监测36h不能满足本规定,应重新对支架进行验算与安全检验,可根据实际情况延长预压时间或采取其他处理方法。First of all, the water tank is designed and manufactured on the completed steel pipe full-house support. When erecting, the on-site scaffolding is directly used. The main body of the water tank is built with wooden squares. The wooden square is used as the secondary corrugation, the main corrugation is transversely reinforced by double steel pipes, the box is covered with waterproof cloth, and the screw rod adopts a new type of waterproof double-pull screw (with waterproof plugging); The box body is made of wood panel material. After the box body is made, the monitoring points and monitoring instruments are arranged according to the requirements. The water pump is directly applied to the box body to apply pressure. When the application of each level of load is completed, the elevation of each monitoring point is monitored and the settlement amount is calculated. , After all preload loads are applied, monitor and record the elevation of each monitoring point every 24 hours. When the preload of the support meets the preload qualification, unload the support. After unloading for 6 hours, monitor the elevation of each monitoring point and calculate the support. The elastic deformation of each monitoring point, during the loading process, the support preload monitoring for 36 hours cannot meet this requirement, the support should be checked again and safety inspection should be carried out, and the preload time can be extended or other treatment methods can be taken according to the actual situation.

巨型空腹梁钢管满堂支架的预压水箱,包括钢管满堂支架、木方、木面板、防水布、新型防水对拉螺杆,所述木方、木面板、防水布、新型防水对拉螺杆构成水箱,所述木方设在水箱的最外侧,所述木面板设在水箱的中部,所述防水布设在水箱的最内侧,所述木方、木面板、防水布通过新型防水对拉螺杆连接,所述新型防水对拉螺杆上安装有位于水箱内侧的橡胶圈,所述水箱的两侧设有抛杆,所述钢管满堂支架上安装有位于水箱下方的监测装置。The pre-pressed water tank of the giant hollow-beam steel tube full bracket, including the steel tube full bracket, the wooden square, the wooden panel, the tarpaulin, and the new waterproof pull screw, the wooden frame, the wooden panel, the waterproof cloth, and the new waterproof pull screw constitute the water tank. The wooden square is arranged on the outermost side of the water tank, the wooden panel is arranged in the middle of the water tank, and the waterproof cloth is arranged on the innermost side of the water tank. A rubber ring located on the inner side of the water tank is installed on the new waterproof pair of pull screws, throwing bars are arranged on both sides of the water tank, and a monitoring device located below the water tank is installed on the steel pipe full bracket.

优选的,所述水箱预压采用分级加载,按预压荷载0%→60%→80%→100%分别施压,每级加载完成后,先停止下一级加载,并每间隔12小时对支架沉降量进行一次监测,当支架顶部监测点12小时的沉降量平均值小于2mm时,可进行下一级加载,每级加载预压作好监测数据记录,在预压检测数据达到设计和有关规范的要求后即可一次性排水卸载。Preferably, the preloading of the water tank adopts graded loading, and the pressure is applied according to the preloading load of 0%→60%→80%→100%. After each stage of loading is completed, the next stage of loading is stopped first, and every 12 hours. The settlement of the support is monitored once. When the average settlement of the monitoring point at the top of the support for 12 hours is less than 2mm, the next level of loading can be performed. The preloading of each stage of loading is recorded. After the requirements of the specification, it can be drained and unloaded at one time.

优选的,所述水箱底面积不小于拟现浇结构梁实际投影面,水头高度由预压荷载换算得出,支架预压加载范围不应小于现浇混凝土结构物的实际投影面。Preferably, the bottom area of the water tank is not less than the actual projection surface of the to-be-cast-in-situ structural beam, the water head height is calculated from the preloading load, and the preloading range of the support should not be smaller than the actual projection surface of the cast-in-place concrete structure.

优选的,所述支架预压荷载取值不应小于支架承受的混凝土结构恒载与模板重量之和的1.1倍,预压单元内荷载强度可以按照其预压单元内预压荷载重量除以预压单元面积得到。Preferably, the value of the preloading load of the support should not be less than 1.1 times the sum of the dead load of the concrete structure and the weight of the formwork that the support bears. The load strength in the preloading unit can be divided by the weight of the preloading load in the preloading unit The pressure cell area is obtained.

优选的,所述支架的沉降监测点布置应沿混凝土结构纵向每隔1/4跨径布置一个监测断面,每个监测断面上的监测点不宜少于5个,并应对称布置,支架沉降监测点应在支架顶部和底部对应位置上分别布置。Preferably, the settlement monitoring points of the support should be arranged with a monitoring section every 1/4 of the span along the longitudinal direction of the concrete structure, and the monitoring points on each monitoring section should not be less than 5, and should be arranged symmetrically, and the support settlement monitoring Points should be placed at corresponding positions on the top and bottom of the bracket.

本发明具备以下有益效果:The present invention has the following beneficial effects:

1、该巨型空腹梁钢管满堂支架的预压水箱,通过使用工地常备简单设备,自行配置水箱,灵活简便,工效高,比传统的堆载预压法工期可缩短1/3以上;加工费用低,操作简便,节省费用,比采用预制钢筋混凝土块预压法可节省投资70~80%,比堆放沙袋预压节省投资30~40%,与现场钢筋材料预压相比可节省投资20%~30%,本预压法具有施工设备少,施工效率高,就地取材,制作简单,环保施工,模拟浇筑过程中的实际受力状态合理等优点,较好的解决了支架高度高、预压面狭长的问题,满足了支架承载力及变形量的检测要求,缩短了建设工期,节省了费用。1. The pre-pressing water tank of the giant hollow beam steel pipe full-house bracket is equipped with the water tank by using the simple equipment standing on the construction site, which is flexible and simple, and has high work efficiency. Compared with the traditional stacking pre-pressing method, the construction period can be shortened by more than 1/3; the processing cost is low , Easy to operate, cost saving, 70~80% investment compared with prefabricated reinforced concrete block preloading method, 30~40% investment saving compared with stacking sandbag preloading, 20% investment saving compared with on-site reinforced material preloading~ 30%, this preloading method has the advantages of less construction equipment, high construction efficiency, local materials, simple production, environmental protection construction, and reasonable actual stress state during the simulation of the pouring process. The problem of long and narrow surface meets the testing requirements of the bearing capacity and deformation of the support, shortens the construction period and saves costs.

2、该巨型空腹梁钢管满堂支架的预压水箱,通过预压,检验了支架的稳定性,消除了支架的非弹性变形,并根据预压报告中弹性变形数据,调整支架预拱度值,确保了支架在混凝土浇筑过程中的变形量在容许范围内,本发明在具体的操作过程中,对施工材料和工艺没有特殊的要求,现场搭设,制作简便,操作容易,适用性较好。2. The pre-pressing water tank of the giant hollow-beam steel tube full-house bracket has been pre-pressed to check the stability of the bracket, eliminate the inelastic deformation of the bracket, and adjust the pre-camber value of the bracket according to the elastic deformation data in the pre-load report. It is ensured that the deformation of the bracket during the concrete pouring process is within the allowable range. In the specific operation process, the present invention has no special requirements for construction materials and processes.

附图说明Description of drawings

图1为本发明结构示意图;Fig. 1 is the structural representation of the present invention;

图2为本发明使用流程示意图。Figure 2 is a schematic diagram of the use flow of the present invention.

图中:1、钢管满堂支架;2、木方;3、木面板;4、防水布;5、新型防水对拉螺杆;6、抛杆;7、监测装置;8、橡胶圈。In the picture: 1. Steel pipe full house bracket; 2. Wooden square; 3. Wooden panel; 4. Waterproof cloth;

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

请参阅图1-2,巨型空腹梁钢管满堂支架的水箱预压工艺,包括以下操作工艺:满堂支架搭设→选择预压区域→确定预压荷载→水箱搭设→监测点布置→监测仪器设置→蓄水分级加载→预压监测→沉降稳定→排水卸载→调整支架模板→下道工序,采用在原支架上现场制作预压水箱,较好的解决了梁宽有限情况下高支架压载物的堆集和稳定性问题,整个支架系统的受力模拟性好,预压过程与实际受力状态接近,施工环保,无污染,不会对周边环境造成大的影响;Please refer to Figure 1-2, the water tank preloading process of the giant hollow beam steel tube full support, including the following operation processes: erecting the full support → selecting the preloading area → determining the preloading load → setting up the water tank → monitoring point layout → monitoring instrument setting → storage Water stage loading→preload monitoring→settlement stabilization→drainage unloading→adjustment of support formwork→next process, the pre-pressed water tank is made on the original support on site, which can better solve the problem of high support ballast accumulation and failure in the case of limited beam width. Stability problem, the force simulation of the entire support system is good, the preloading process is close to the actual force state, the construction is environmentally friendly, pollution-free, and will not have a great impact on the surrounding environment;

首先已搭设完成的钢管满堂支架上设计制作水箱,可根据大跨度结构梁实际投影面积及上部工程结构形式、荷载大小等布设水箱,具有灵活性和适应性,搭设时直接利用现场脚手架进行,水箱主体采用木方搭建,制作好水箱底模,在进行两侧模板的制作;水箱两侧模板外侧用竖向木方作次楞,主楞为双钢管横向加固,箱体内铺防水布,螺杆采用新型防水对拉螺杆(自带防水封堵);螺杆两端穿孔处另增设胶垫、防水胶等封堵严密,箱体使用木面板材质,箱体制作完成后按要求布置监测点及安置监测仪器,用水泵直接向箱体灌水施压,水泵扬程选择约为提水高度的1.15~1.20倍,水源可直接取自施工现场集水池也可取自自来水,在最高水头位置设置直径75泄水管,水位超过限定高度时自动泄水,水箱两端分别设置,管道可与箱底端排水管连接,每级荷载施加完成时,监测各监测点标高并计算沉降量,全部预压荷载施加完毕后,每间隔24小时监测一次并记录各监测点标高,当支架预压符合预压合格时,进行支架卸载,预压中加卸载对称、均衡,能避免偏载对支架造成不利影响,卸载6小时后,监测各监测点标高,并计算支架各监测点的弹性变形量,加载过程中,支架预压监测36h不能满足本规定,应重新对支架进行验算与安全检验,可根据实际情况延长预压时间或采取其他处理方法。First of all, the water tank is designed and manufactured on the completed steel pipe full-house support. The water tank can be arranged according to the actual projected area of the large-span structural beam, the upper engineering structure form, and the load size, etc., with flexibility and adaptability. The main body is built with wooden squares, the bottom form of the water tank is made, and the formwork on both sides is made; the outer sides of the formwork on both sides of the water tank are made of vertical wooden squares as secondary corrugations, the main corrugation is transversely reinforced by double steel pipes, the inside of the box is covered with waterproof cloth, and the screws are made of New waterproof paired screw (with waterproof plug); additional rubber pads and waterproof glue are added at the perforations at both ends of the screw to seal tightly. The box is made of wood panel material. After the box is made, the monitoring points and placement monitoring are arranged as required. For the instrument, use the water pump to directly irrigate the box with pressure. The pump lift is selected to be about 1.15 to 1.20 times the water lifting height. The water source can be directly taken from the construction site sump or tap water. A drain pipe with a diameter of 75 is set at the highest head position. , when the water level exceeds the limit height, the water is automatically discharged. The two ends of the water tank are set up separately, and the pipeline can be connected with the drainage pipe at the bottom of the tank. When the application of each level of load is completed, the elevation of each monitoring point is monitored and the settlement amount is calculated. Monitor once every 24 hours and record the elevation of each monitoring point. When the preloading of the support meets the preloading requirements, the support is unloaded. The loading and unloading in the preloading is symmetrical and balanced, which can avoid the adverse effect of partial load on the support. After unloading for 6 hours , monitor the elevation of each monitoring point, and calculate the elastic deformation of each monitoring point of the support. During the loading process, the support preload monitoring for 36 hours cannot meet this requirement, and the support should be checked again and the safety inspection should be carried out. The preload time can be extended according to the actual situation. or take other treatment methods.

巨型空腹梁钢管满堂支架的预压水箱,包括钢管满堂支架1,为防止支架基础遇水后降低承载能力,支架基础应做好防水、排水工作;不同类型的支架应根据工程结构形式、荷载大小、支架高度、支架基础情况等选择具有代表性区域进行预压,确定预压范围、木方2、木面板3、防水布4、新型防水对拉螺杆5,水箱底模、侧模,新型防水对拉螺杆5等结构构件应由计算确定,应能满足承载力、刚度和稳定性要求,木方2、木面板3、防水布4、新型防水对拉螺杆5构成水箱,木方2设在水箱的最外侧,木面板3设在水箱的中部,防水布4设在水箱的最内侧,木方2、木面板3、防水布4通过新型防水对拉螺杆5连接,新型防水对拉螺杆5上安装有位于水箱内侧的橡胶圈8,水箱的两侧设有抛杆6,钢管满堂支架1上安装有位于水箱下方的监测装置7,监测装置7可采用位移计和水准仪同步进行监测,监测装置7监测的内容为加载之前监测点标高、每级加载后监测点标高、加载至100%后每间隔24小时监测点标高、卸载6小时后监测点标高,通过对预压荷载的换算,确定水头高度(水重量取10KN/立方米),水箱高度宜比水头高度高10CM~30CM,水箱底面积按不小于现浇混凝土结构物的实际投影面来确定。The pre-pressurized water tank of the giant hollow beam steel tube full support, including the steel tube full support 1, in order to prevent the support foundation from reducing the bearing capacity when it encounters water, the support foundation should be waterproof and drainage work; different types of supports should be based on the project structure. Select a representative area for pre-compression, determine the pre-compression range, wood square 2, wood panel 3, waterproof cloth 4, new waterproof pull screw 5, water tank bottom mold, side mold, new waterproof Structural components such as the pull screw 5 should be determined by calculation, and should meet the requirements of bearing capacity, stiffness and stability. The wooden square 2, the wooden panel 3, the waterproof cloth 4, and the new waterproof pair of the pull screw 5 constitute a water tank, and the wooden square 2 is located in the water tank. On the outermost side of the water tank, the wooden panel 3 is located in the middle of the water tank, and the waterproof cloth 4 is located at the innermost side of the water tank. A rubber ring 8 is installed on the inner side of the water tank, and there are throwing rods 6 on both sides of the water tank. A monitoring device 7 located under the water tank is installed on the steel pipe full bracket 1. The content monitored by device 7 is the elevation of the monitoring point before loading, the elevation of the monitoring point after each level of loading, the elevation of the monitoring point every 24 hours after loading to 100%, and the elevation of the monitoring point after 6 hours of unloading. The height of the water head (the weight of water is 10KN/m3), the height of the water tank should be 10CM~30CM higher than the height of the water head, and the bottom area of the water tank should be determined not less than the actual projection surface of the cast-in-place concrete structure.

其中,水箱预压采用分级加载,按预压荷载0%→60%→80%→100%分别施压,每级加载完成后,先停止下一级加载,并每间隔12小时对支架沉降量进行一次监测,当支架顶部监测点12小时的沉降量平均值小于2mm时,可进行下一级加载,每级加载预压作好监测数据记录,在预压检测数据达到设计和有关规范的要求后即可一次性排水卸载,支架预压应在支架基础预压合格后进行。Among them, the preloading of the water tank adopts staged loading, and the preloading load is 0%→60%→80%→100% respectively. After each stage of loading is completed, the next stage of loading is stopped first, and the settlement of the support is measured every 12 hours. Carry out one monitoring, when the 12-hour average settlement of the monitoring point at the top of the support is less than 2mm, the next level of loading can be performed, and the monitoring data records are made for the preloading of each level of loading. After that, it can be drained and unloaded at one time, and the preloading of the support should be carried out after the preloading of the support foundation is qualified.

其中,水箱底面积不小于拟现浇结构梁实际投影面,水头高度由预压荷载换算得出,支架预压加载范围不应小于现浇混凝土结构物的实际投影面。Among them, the bottom area of the water tank is not less than the actual projection surface of the to-be-cast-in-situ structural beam, the water head height is calculated from the preloading load, and the preloading range of the support should not be smaller than the actual projection surface of the cast-in-place concrete structure.

其中,支架预压荷载取值不应小于支架承受的混凝土结构恒载与模板重量之和的1.1倍,预压单元内荷载强度可以按照其预压单元内预压荷载重量除以预压单元面积得到,同一预压单元内荷载采用均布形式,方便施工加载。Among them, the value of the preloading load of the support should not be less than 1.1 times the sum of the dead load of the concrete structure and the weight of the formwork that the support bears. It is obtained that the load in the same preloading unit is uniformly distributed, which is convenient for construction loading.

其中,支架的沉降监测点布置应沿混凝土结构纵向每隔1/4跨径布置一个监测断面,每个监测断面上的监测点不宜少于5个,并应对称布置,支架沉降监测点应在支架顶部和底部对应位置上分别布置,监测预压合格为各监测点最初24小时的沉降量平均值小于1mm,各监测点最初72小时的沉降量平均值小于5mm。Among them, the arrangement of the settlement monitoring points of the support should be arranged along the longitudinal direction of the concrete structure with a monitoring section every 1/4 of the span. The monitoring points on each monitoring section should not be less than 5, and should be arranged symmetrically. The support settlement monitoring points should be at The top and bottom of the support are arranged at the corresponding positions, and the monitoring preload is qualified when the average settlement of each monitoring point in the first 24 hours is less than 1mm, and the average settlement of each monitoring point in the first 72 hours is less than 5mm.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that, in this document, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or device that includes a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus.

尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, and substitutions can be made in these embodiments without departing from the principle and spirit of the invention and modifications, the scope of the present invention is defined by the appended claims and their equivalents.

Claims (6)

1. the water tank pre-pressing process of huge laced beam steel pipe full framing, it is characterised in that: including following operating procedure: Man Tangzhi Frame, which is set up, → selecting precompressed region → determines that prefabricating load → water tank sets up → monitoring point arrangement → monitoring instrument setting → water storage Hierarchical loading → precompressed monitoring → settlement stability → draining unloads → adjusts rack template → next procedure;
It has set up first and has designed and produced water tank on the steel pipe full framing of completion, directly carried out using live scaffold when setting up, Water tank main body is built using flitch, makes water tank bed die, in the production for carrying out two side templates;With perpendicular on the outside of two side template of water tank Secondary stupefied to flitch work, stupefied master is double steel pipe transversely strengthening, and paving waterproof cloth in cabinet, screw rod uses new waterproof Screw arbor with nut at both-ends (certainly Band waterproof blocks);It is tight that the closure such as rubber mat, marine glue are separately added at the perforation of screw rod both ends, cabinet uses wooden boards material, cabinet Monitoring point and placement monitoring instrument are arranged after completing as required, is directly poured water pressure to cabinet with water pump, every grade of load is applied It when adding into, monitors each monitoring point absolute altitude and calculates settling amount, after whole prefabricating loads apply, monitored at interval of 24 hours Once and each monitoring point absolute altitude is recorded, when pre-pressing bracket meets precompressed qualification, carries out bracket unloading, after unloading 6 hours, monitoring Each monitoring point absolute altitude, and the elastic deformation amount of each monitoring point of bracket is calculated, in loading procedure, pre-pressing bracket monitoring 36h cannot expire This regulation of foot should carry out checking computations and safety verification to bracket again, can extend according to the actual situation squeeze time or take other Processing method.
2. the precompressed water tank of huge laced beam steel pipe full framing, it is characterised in that: including steel pipe full framing (1), flitch (2), wooden boards (3), waterproof cloth (4), new waterproof Screw arbor with nut at both-ends (5), the flitch (2), wooden boards (3), waterproof cloth (4), New waterproof Screw arbor with nut at both-ends (5) constitutes water tank, and the flitch (2) is located at the outermost of water tank, and the wooden boards (3) are located at water tank Middle part, the waterproof cloth (4) is located at the most inner side of water tank, and the flitch (2), wooden boards (3), waterproof cloth (4) pass through novel Water-proof double-unit screw (5) connects, the rubber ring (8) being equipped on the inside of water tank on the new waterproof Screw arbor with nut at both-ends (5), institute The two sides for stating water tank, which are equipped with, throws bar (6), the monitoring device (7) being equipped with below water tank on the steel pipe full framing (1).
3. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Water tank precompressed uses hierarchical loading, presses respectively by prefabricating load 0% → 60% → 80% → 100%, after the completion of every grade of load, first stops Only next stage loads, and is once monitored at interval of 12 hours to bracket settling amount, when cradle top monitoring point 12 is small When settling amount average value is less than 2mm, next stage load can be carried out, every grade of load precompressed performs monitoring data record, examines in precompressed Measured data can disposably drain unloading after reaching design and the requirement in relation to standardizing.
4. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Water tank floor space is not less than the quasi- practical perspective plane of cast-in-place structural beam, and head height show that pre-pressing bracket adds by prefabricating load conversion Carry the practical perspective plane that range is no less than cast-in-place concrete structure object.
5. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described Pre-pressing bracket Load value is no less than 1.1 times of the concrete structure dead load that bracket is born and the sum of template weight, precompressed list First internal loading intensity can be obtained according to prefabricating load weight in its prepressing units divided by prepressing units area.
6. the water tank pre-pressing process of huge laced beam steel pipe full framing according to claim 1, it is characterised in that: described The settlement monitoring point arrangement of bracket should be longitudinal every 1/4 span setting, one monitoring section along concrete structure, and each monitoring is disconnected Monitoring point on face should not be less than 5, and should be arranged symmetrically, and bracket settlement monitoring point should be in cradle top and bottom corresponding position On be respectively arranged.
CN201910416166.4A 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing Pending CN110043029A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910416166.4A CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910416166.4A CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Publications (1)

Publication Number Publication Date
CN110043029A true CN110043029A (en) 2019-07-23

Family

ID=67282581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910416166.4A Pending CN110043029A (en) 2019-05-20 2019-05-20 The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing

Country Status (1)

Country Link
CN (1) CN110043029A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364759A (en) * 2020-03-18 2020-07-03 重庆交通建设(集团)有限责任公司 Prepressing device of full-scale support of giant open-web girder steel pipe and construction method thereof
CN111693366A (en) * 2020-05-27 2020-09-22 中冶建筑研究总院有限公司 Construction method for pre-loading structure in limited space
CN112030710A (en) * 2020-09-14 2020-12-04 武汉一冶建筑安装工程有限责任公司 Prepressing method and prepressing device for arch springing of arch ring bottom template
CN113931075A (en) * 2021-11-04 2022-01-14 中铁四局集团有限公司 Upper-pressing-down-hanging combined hydraulic-method prepressing and construction method for movable formwork
CN114427220A (en) * 2022-03-04 2022-05-03 中电建十一局工程有限公司 Porous arch bridge water bag prepressing construction method
CN114441307A (en) * 2021-12-29 2022-05-06 中铁二十局集团有限公司 Stent preloading method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3153291C2 (en) * 1980-10-10 1987-10-22 Peri-Werk Artur Schwoerer Gmbh & Co Kg, 7912 Weissenhorn, De Shuttering for concrete floor (ceiling) with joist
CN103225300A (en) * 2013-04-18 2013-07-31 贵州建工集团第二建筑工程有限责任公司 Process and equipment for reinforcing and strengthening concrete filling pile
WO2013166658A1 (en) * 2012-05-08 2013-11-14 Liu Chun Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork
CN103437549A (en) * 2013-09-16 2013-12-11 中铁四局集团建筑工程有限公司 Preloading structural part for high and large formwork support system
CN105155425A (en) * 2015-09-22 2015-12-16 深圳市市政工程总公司 Fluid analogue simulation preloading construction method of full framing
CN209976021U (en) * 2019-05-20 2020-01-21 贵州建工集团第二建筑工程有限责任公司 Prepressing water tank of giant open-web girder steel pipe full-scale support

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3153291C2 (en) * 1980-10-10 1987-10-22 Peri-Werk Artur Schwoerer Gmbh & Co Kg, 7912 Weissenhorn, De Shuttering for concrete floor (ceiling) with joist
WO2013166658A1 (en) * 2012-05-08 2013-11-14 Liu Chun Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork
CN103225300A (en) * 2013-04-18 2013-07-31 贵州建工集团第二建筑工程有限责任公司 Process and equipment for reinforcing and strengthening concrete filling pile
CN103437549A (en) * 2013-09-16 2013-12-11 中铁四局集团建筑工程有限公司 Preloading structural part for high and large formwork support system
CN105155425A (en) * 2015-09-22 2015-12-16 深圳市市政工程总公司 Fluid analogue simulation preloading construction method of full framing
CN209976021U (en) * 2019-05-20 2020-01-21 贵州建工集团第二建筑工程有限责任公司 Prepressing water tank of giant open-web girder steel pipe full-scale support

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364759A (en) * 2020-03-18 2020-07-03 重庆交通建设(集团)有限责任公司 Prepressing device of full-scale support of giant open-web girder steel pipe and construction method thereof
CN111693366A (en) * 2020-05-27 2020-09-22 中冶建筑研究总院有限公司 Construction method for pre-loading structure in limited space
CN112030710A (en) * 2020-09-14 2020-12-04 武汉一冶建筑安装工程有限责任公司 Prepressing method and prepressing device for arch springing of arch ring bottom template
CN113931075A (en) * 2021-11-04 2022-01-14 中铁四局集团有限公司 Upper-pressing-down-hanging combined hydraulic-method prepressing and construction method for movable formwork
CN114441307A (en) * 2021-12-29 2022-05-06 中铁二十局集团有限公司 Stent preloading method
CN114427220A (en) * 2022-03-04 2022-05-03 中电建十一局工程有限公司 Porous arch bridge water bag prepressing construction method

Similar Documents

Publication Publication Date Title
CN110043029A (en) The precompressed water tank and pre-pressing process of huge laced beam steel pipe full framing
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN101603372B (en) Method for reinforcing integral replacement concrete for high-rise building steel bar concrete column
CN108827669A (en) It is a kind of for simulating the pilot system of tunnel deformation destruction characteristic
CN105155425A (en) Fluid analogue simulation preloading construction method of full framing
CN102061742A (en) Shockproof reinforced concrete pseudo-classic building structural system
CN209976021U (en) Prepressing water tank of giant open-web girder steel pipe full-scale support
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN203241408U (en) Indoor vacuum combined-supercharge preloading model test device
CN206928642U (en) A kind of safety and environmental protection movable formwork support
CN109098314A (en) One kind being easily installed compact assembled lining
CN212294351U (en) Water bag pre-pressing construction equipment for viaduct cast-in-place beam support system
CN108374350B (en) A composite frame and installation method of steel anchor beam and steel corbel unit
CN111636360A (en) A device for making a shaking table model of a roller compacted concrete arch dam
CN216340861U (en) Diagonal bracing structure for aluminum alloy template
CN111236632A (en) Construction method of heavy bracket and profile steel combined supporting system for super-thick top plate
CN111257136A (en) Pseudo-static force horizontal shear test method and device for masonry
CN110847257A (en) A pile foundation static load experimental device and method suitable for narrow space
CN207017653U (en) A kind of box unloads special buttress and its unloading structure
CN211596858U (en) An experimental device for static load of pile foundation suitable for narrow space
CN111364759A (en) Prepressing device of full-scale support of giant open-web girder steel pipe and construction method thereof
CN210975868U (en) Root-opening adjustable narrow base tower steel structure foundation
CN211235297U (en) A face rockfill dam face rotating extrusion test device
CN207689265U (en) A kind of device for indoor simulation Stratified Rock Slope Unloading Deformation
CN221895937U (en) A prefabricated steel structure for civil engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190723