CN110004927A - Construction method of prestressed micro piles - Google Patents
Construction method of prestressed micro piles Download PDFInfo
- Publication number
- CN110004927A CN110004927A CN201910237029.4A CN201910237029A CN110004927A CN 110004927 A CN110004927 A CN 110004927A CN 201910237029 A CN201910237029 A CN 201910237029A CN 110004927 A CN110004927 A CN 110004927A
- Authority
- CN
- China
- Prior art keywords
- pile
- anchor cable
- grouting
- micro
- prestressed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 28
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 59
- 239000010959 steel Substances 0.000 claims abstract description 59
- 239000000463 material Substances 0.000 claims abstract description 24
- 238000005553 drilling Methods 0.000 claims abstract description 13
- 238000004873 anchoring Methods 0.000 claims description 14
- 238000000034 method Methods 0.000 claims description 12
- 230000001681 protective effect Effects 0.000 claims description 9
- 125000006850 spacer group Chemical group 0.000 claims description 9
- 239000011083 cement mortar Substances 0.000 claims description 3
- 238000005260 corrosion Methods 0.000 claims description 3
- 238000005238 degreasing Methods 0.000 claims description 3
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 claims description 3
- 235000014121 butter Nutrition 0.000 claims description 2
- 239000011435 rock Substances 0.000 abstract description 13
- 239000002689 soil Substances 0.000 abstract description 11
- 239000002002 slurry Substances 0.000 description 8
- 201000010099 disease Diseases 0.000 description 5
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 239000004568 cement Substances 0.000 description 4
- 230000015572 biosynthetic process Effects 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 2
- 239000000654 additive Substances 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 239000000356 contaminant Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 239000004519 grease Substances 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004745 nonwoven fabric Substances 0.000 description 1
- 238000007586 pull-out test Methods 0.000 description 1
- 238000003900 soil pollution Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0046—Production methods using prestressing techniques
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/0021—Mortar
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明公开了一种预应力微型桩施工方法,包括以下步骤:在边坡上钻设桩孔;将钢管桩插入到桩孔内;将锚索捆扎在注浆管上,将注浆管插入到钢管桩的底部;通过注浆管向钢管桩内注入注浆材料,待注浆材料凝固后,将锚索通过设置于坡面上的固定台进行张拉,以对锚索施加预应力,从而可以形成对微型桩和周围岩土体的预应力,提高微型桩及周围岩土体受力性能,提高抗滑段岩土体抗滑力,且同时可有效提高微型桩的抗压、抗剪强度。
The invention discloses a prestressed micro-pile construction method, comprising the following steps: drilling a pile hole on a side slope; inserting a steel pipe pile into the pile hole; bundling an anchor cable on a grouting pipe, and inserting the grouting pipe It is inserted into the bottom of the steel pipe pile; the grouting material is injected into the steel pipe pile through the grouting pipe, and after the grouting material is solidified, the anchor cable is stretched through the fixed platform set on the slope surface to apply Prestressing, which can form the prestressing of the micro pile and the surrounding rock and soil, improve the mechanical performance of the micro pile and the surrounding rock and soil, improve the anti-slip force of the rock and soil in the anti-sliding section, and at the same time can effectively improve the resistance of the micro pile. Compressive and shear strength.
Description
技术领域technical field
本发明涉及边坡防护技术领域,具体涉及一种预应力微型桩施工方法。The invention relates to the technical field of slope protection, in particular to a construction method for prestressed micro-pile.
背景技术Background technique
微型桩一般是指桩径小于400mm,长细比大于30,采用钻孔、强配筋和压力注浆施工工艺的灌注桩,因其孔径小,施工方便,使用设备极易获取,被越来越多的人所青睐。近年来,微型桩及注浆技术在边坡防护滑坡治理、路基病害处治方面的使用也越发普及,为边坡防护、滑坡及路基病害抢险应急治理提供了很多便利。Micro piles generally refer to cast-in-place piles with a diameter of less than 400mm and a slenderness ratio of more than 30, which are constructed by drilling, strong reinforcement and pressure grouting. Because of their small aperture, convenient construction, and easy access to equipment, they are increasingly Favored by more people. In recent years, the use of micro piles and grouting technology in slope protection and landslide treatment and roadbed disease treatment has become more and more popular, providing a lot of convenience for slope protection, landslide and roadbed disease emergency treatment.
但是,这种小巧的微型桩,其强度较大型桩也有很大程度的下降,在一些地质结构复杂、防护强度要求较高的边坡、滑坡治理、路基病害处治上无法达到目标强度要求,导致在这些边坡、滑坡治理、路基病害处治上还是只能使用大型支挡等结构。因此,提高现有微型桩及周围岩土体的强度,以适应更多边坡防护、滑坡治理、路基病害处治的要求,对提高边坡防护施工的便捷性和迅速实现滑坡和路基灾害控制具有非常积极的意义。However, the strength of this kind of small micro-pile is also greatly reduced, and it cannot meet the target strength requirements in the treatment of slopes, landslides and roadbed diseases with complex geological structures and high protection strength requirements, resulting in In the treatment of these slopes, landslides, and roadbed diseases, only large-scale supports and other structures can be used. Therefore, improving the strength of the existing micro piles and the surrounding rock and soil mass to meet the requirements of more slope protection, landslide treatment, and treatment of roadbed diseases is of great significance for improving the convenience of slope protection construction and quickly realizing landslide and roadbed disaster control. very positive meaning.
发明内容SUMMARY OF THE INVENTION
基于此,有必要针对上述传统微型桩强度较低,不能满足需求的问题,提供一种预应力微型桩施工方法。Based on this, it is necessary to provide a prestressed micro-pile construction method for the problem that the strength of the traditional micro-pile is low and cannot meet the demand.
一种预应力微型桩施工方法,包括以下步骤:A prestressed micro-pile construction method, comprising the following steps:
(1)在边坡上钻设桩孔;(1) Drilling pile holes on the slope;
(2)将钢管桩插入到所述桩孔内;(2) inserting the steel pipe pile into the pile hole;
(3)将锚索捆扎在注浆管上,将注浆管插入到钢管桩的底部;(3) Bundle the anchor cable on the grouting pipe, and insert the grouting pipe into the bottom of the steel pipe pile;
(4)通过所述注浆管向所述钢管桩内注入注浆材料;(4) inject grouting material into the steel pipe pile through the grouting pipe;
(5)待所述注浆材料凝固后,将锚索通过设置于坡面上的固定台进行张拉,以对所述锚索施加预应力。(5) After the grouting material is solidified, the anchor cable is stretched through the fixed platform arranged on the slope surface to apply prestress to the anchor cable.
在其中一个实施例中,将所述钢管桩插入到所述桩孔内的步骤之前还包括:In one embodiment, before the step of inserting the steel pipe pile into the pile hole, it further comprises:
对所述桩孔进行清洁。The pile holes are cleaned.
在其中一个实施例中,所述锚索包括锚固段和自由段,所述将锚索捆扎在注浆管上的步骤具体为:In one embodiment, the anchor cable includes an anchor section and a free section, and the step of bundling the anchor cable on the grouting pipe is as follows:
通过紧固件将所述锚索捆扎在所述注浆管上,在所述注浆管的下端间隔套设扩张件,所述扩张件支撑所述锚固段形成凸起。The anchor cable is bundled on the grouting pipe by a fastener, and an expansion piece is sleeved at the lower end of the grouting pipe, and the expansion piece supports the anchoring section to form a protrusion.
在其中一个实施例中,通过紧固件将所述锚索捆扎在所述注浆管上的步骤之后还包括:In one of the embodiments, after the step of bundling the anchor cable on the grouting pipe with fasteners, the method further includes:
将定中件捆扎在所述自由段上,将定中圈插入到钢管桩内,所述定中件位于所述自由段和所述定中圈之间支撑所述注浆管,以使所述注浆管和所述钢管桩同轴。The centering piece is bundled on the free section, the centering ring is inserted into the steel pipe pile, and the centering piece is located between the free section and the centering ring to support the grouting pipe, so that the grouting pipe is supported. The grouting pipe and the steel pipe pile are coaxial.
在其中一个实施例中,所述锚索捆扎在所述注浆管上之前还包括:In one embodiment, before the anchor cable is bundled on the grouting pipe, it further comprises:
在保护套内注入黄油,然后将所述保护套套设在所述锚索上。Inject butter into the protective cover, and then set the protective cover on the anchor cable.
在其中一个实施例中,所述锚索捆扎在所述注浆管上之前还包括:In one embodiment, before the anchor cable is bundled on the grouting pipe, it further comprises:
对所述锚索的锚固段进行除油除锈,对所述锚索的自由段进行防腐处理。Degreasing and rust removal are performed on the anchoring section of the anchor cable, and anti-corrosion treatment is performed on the free section of the anchor cable.
在其中一个实施例中,所述固定台包括地梁和设置于地梁上的楔形垫块,所述将锚索通过设置于坡面上的固定台进行张拉的步骤具体为:In one of the embodiments, the fixing platform includes a ground beam and a wedge-shaped spacer set on the ground beam, and the step of tensioning the anchor cable through the fixing platform arranged on the slope is as follows:
在边坡上浇筑所述地梁和楔形垫块,浇筑过程中,将锚具放入到混凝土中,且使所述锚索穿出所述锚具,待混凝土凝固后,通过锚板将所述锚索张紧。The ground beams and the wedge-shaped spacers are poured on the side slope. During the pouring process, the anchors are put into the concrete, and the anchor cables are made to pass through the anchors. The anchor cable is tensioned.
在其中一个实施例中,所述通过锚板将所述锚索张紧的步骤之后还包括:In one embodiment, after the step of tensioning the anchor cable through the anchor plate, the step further includes:
使用混凝土封块将所述锚板和所述锚索密封。The anchor plate and the anchor cable are sealed with concrete blocks.
在其中一个实施例中,所述在边坡上钻设桩孔的步骤具体为:In one of the embodiments, the step of drilling a pile hole on the side slope is as follows:
采用风动干钻施工法在边坡上钻设所述桩孔。The pile holes are drilled on the side slope by a pneumatic dry drilling construction method.
在其中一个实施例中,通过所述注浆管向所述钢管桩内注入注浆材料的过程中,采用多次注浆完成,注浆采用强度不低于M30的水泥砂浆在1-2MPa的压力下进行。In one embodiment, the process of injecting grouting material into the steel pipe pile through the grouting pipe is completed by multiple grouting, and the grouting adopts cement mortar with a strength not lower than M30 at 1-2MPa under pressure.
上述预应力微型桩施工方法,锚索随着注浆管插入到钢管桩的底部,通过注浆管向钢管桩内从下至上注入注浆材料,待注浆材料凝固后,可以将锚索的下端锚固在稳定地层。锚索的另一端伸出钢管桩外与设置于坡面上的固定台连接,以对锚索施加预应力,形成对微型桩和周围岩土体的预应力,提高微型桩及周围岩土体受力性能,提高抗滑段岩土体抗滑力,且同时可有效提高微型桩的抗压、抗剪强度。In the above prestressed micro pile construction method, the anchor cable is inserted into the bottom of the steel pipe pile along with the grouting pipe, and the grouting material is injected into the steel pipe pile from bottom to top through the grouting pipe. The lower end of the cable is anchored in the stable formation. The other end of the anchor cable extends out of the steel pipe pile and is connected to the fixed platform set on the slope to apply prestress to the anchor cable, form the prestress of the micro pile and the surrounding rock and soil, and improve the micro pile and the surrounding rock and soil. It can improve the anti-sliding force of rock and soil in the anti-sliding section, and at the same time can effectively improve the compressive and shear strength of micro piles.
附图说明Description of drawings
图1为一实施方式中预应力微型桩施工方法的流程图;Fig. 1 is the flow chart of the construction method of prestressed micro-pile in one embodiment;
图2为一实施方式中预应力微型桩的结构示意图;FIG. 2 is a schematic structural diagram of a prestressed micropile in one embodiment;
图3为图2中钢管桩的结构示意图;Fig. 3 is the structural representation of the steel pipe pile in Fig. 2;
图4为图2中A-A线的剖视图;Fig. 4 is the sectional view of line A-A in Fig. 2;
图5为图2中B-B线的剖视图。FIG. 5 is a cross-sectional view taken along line B-B in FIG. 2 .
具体实施方式Detailed ways
为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图对本发明的具体实施方式做详细的说明。在下面的描述中阐述了很多具体细节以便于充分理解本发明。但是本发明能够以很多不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本发明内涵的情况下做类似改进,因此发明不受下面公开的具体实施的限制。In order to make the above objects, features and advantages of the present invention more clearly understood, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without departing from the connotation of the present invention, so the invention is not limited by the specific implementation disclosed below.
需要说明的是,当元件被称为“固定于”另一个元件,它可以直接在另一个元件上或者也可以存在居中的元件。当一个元件被认为是“连接”另一个元件,它可以是直接连接到另一个元件或者可能同时存在居中元件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的,并不表示是唯一的实施方式。It should be noted that when an element is referred to as being "fixed to" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for the purpose of illustration only and do not represent the only embodiment.
除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention.
请参阅图1,一实施方式中的预应力微型桩施工方法,为实现该预应力微型桩施工方法,其采用如图2所示的预应力微型桩支挡结构。该预应力微型桩施工方法具体包括如下步骤:Please refer to FIG. 1 , a prestressed micro-pile construction method in an embodiment, in order to realize the pre-stressed micro-pile construction method, the prestressed micro-pile support structure shown in FIG. 2 is adopted. The prestressed micro-pile construction method specifically includes the following steps:
步骤S110:在边坡上钻设桩孔。Step S110: Drilling pile holes on the side slope.
具体地,在边坡上钻设桩孔时,应当从边坡的上部往下开挖。当上一级边坡开挖成型后,先施工预应力微型桩再进行边坡防护,避免边坡长期暴露。待上一级边坡的预应力微型桩制作完成后,再开挖下一级边坡。桩孔的直径和深度应满足设计要求。对边坡钻设桩孔时,采用风动干钻施工法在边坡上钻设桩孔,不能采用采用水钻,避免桩孔土体污染垮塌。桩孔应进行清洁,保证桩孔的孔壁无污染物,以确保保持注浆材料体与岩体的粘接强度。如遇地层松散、破碎时,应采取跟套管的钻进技术,以使桩孔完整不坍塌。Specifically, when drilling a pile hole on a side slope, it should be excavated from the upper part of the side slope. When the upper-level slope is excavated and formed, prestressed micro-pile is constructed first and then slope protection is carried out to avoid long-term exposure of the slope. After the prestressed micro piles of the upper-level slope are completed, the next-level slope is excavated. The diameter and depth of the pile hole should meet the design requirements. When drilling the pile holes on the side slope, use the pneumatic dry drilling construction method to drill the pile holes on the side slope, and water drills cannot be used to avoid soil pollution and collapse of the pile holes. The pile hole should be cleaned to ensure that the hole wall of the pile hole is free of contaminants, so as to ensure that the bonding strength between the grouting material body and the rock mass is maintained. If the stratum is loose and broken, the drilling technique with casing should be adopted to keep the pile hole intact and not collapse.
步骤S120:将钢管桩100插入到桩孔内Step S120: Insert the steel pipe pile 100 into the pile hole
请一并参阅图3,钢管桩100的外径小于或者等于桩孔的孔径,钢管桩100 的长度与桩孔的深度相适应。钢管桩100的侧壁上开设有出浆孔102,出浆孔 102的数量为多个,多个出浆孔102沿钢管桩100的轴向方向间隔设置。注入到钢管桩100内的注浆材料可以通过出浆孔102流入到钢管桩100的外壁与桩孔的侧壁之间,待注浆材料凝固后,可以钢管桩100与岩体连接。Please refer to FIG. 3 together, the outer diameter of the steel pipe pile 100 is smaller than or equal to the diameter of the pile hole, and the length of the steel pipe pile 100 is adapted to the depth of the pile hole. The side wall of the steel pipe pile 100 is provided with a slurry outlet hole 102, the number of the slurry outlet hole 102 is multiple, and the plurality of slurry outlet holes 102 are arranged at intervals along the axial direction of the steel pipe pile 100. The grouting material injected into the steel pipe pile 100 can flow into between the outer wall of the steel pipe pile 100 and the side wall of the pile hole through the grouting hole 102. After the grouting material solidifies, the steel pipe pile 100 can be connected to the rock mass. .
步骤S130:将锚索200捆扎在注浆管110上,将注浆管110插入到钢管桩 100的底部。Step S130: The anchor cable 200 is bundled on the grouting pipe 110, and the grouting pipe 110 is inserted into the bottom of the steel pipe pile 100.
请一并参阅图4,在下钢筋笼时,同时将锚索200通过注浆管110下放到钢管桩100内。一实施方式中,锚索200通过紧固件210捆扎在注浆管110上,为了保证锚索200固定的稳固,多个紧固件210等间距将锚固捆绑固定。具体地,紧固件210为铁丝,锚索200为钢绞线。钢绞线应为高强度低松弛钢绞线,钢绞线标准强度不小于1860MPa。锚索200施工前必须进行现场抗拔试验,锚索200施工时用设计预应力至的1.1倍进行预张拉,最后按设计值锁紧。Please also refer to FIG. 4 , when lowering the reinforcement cage, the anchor cable 200 is lowered into the steel pipe pile 100 through the grouting pipe 110 at the same time. In one embodiment, the anchor cable 200 is bundled on the grouting pipe 110 by the fasteners 210. In order to ensure the stability of the anchor cable 200, a plurality of fasteners 210 are equally spaced to bind and fix the anchorage. Specifically, the fastener 210 is an iron wire, and the anchor cable 200 is a steel strand. The steel strand shall be high-strength and low-relaxation steel strand, and the standard strength of the steel strand shall not be less than 1860MPa. An on-site pull-out test must be carried out before the construction of the anchor cable 200. During the construction of the anchor cable 200, the pre-tension is carried out with 1.1 times the design prestress, and finally it is locked according to the design value.
锚索200包括锚固段202和自由段204,其中锚固段202捆扎在注浆管110 的下端,自由段204捆绑在注浆管110的上端。同时,锚索200在捆扎在注浆管110之前,需对锚索200的锚固段202进行除油除锈,在锚索200的自由段 204进行防腐处理,并在运输及下锚过程中不得损伤。锚索200外套设有保护套230,保护套230可以保护整个锚索200。具体地,保护套230可以为PVC 软管,保护套230与钢绞线间注有黄油。The anchor cable 200 includes an anchoring section 202 and a free section 204 , wherein the anchoring section 202 is tied to the lower end of the grouting pipe 110 , and the free section 204 is tied to the upper end of the grouting pipe 110 . At the same time, before the anchor cable 200 is bundled in the grouting pipe 110, the anchoring section 202 of the anchor cable 200 needs to be degreasing and rust removed, and the free section 204 of the anchor cable 200 is subjected to anti-corrosion treatment. damage. The outer jacket of the anchor cable 200 is provided with a protective cover 230 , and the protective cover 230 can protect the entire anchor cable 200 . Specifically, the protective cover 230 may be a PVC hose, and grease is injected between the protective cover 230 and the steel strand.
请一并参阅图5,进一步地,注浆管110的下端间隔套设有多个扩张件220,紧固件210和扩张件220沿注浆管110的轴向相互间隔设置,扩张件220可以支撑锚索200的锚固段202形成凸起,凸起可以保证锚固段202与稳定地层连接的稳固。扩张件220可以为圆形的厚钢板或者橡胶板制成,扩张件220设有容纳锚索200的容纳槽222。Please also refer to FIG. 5 , further, a plurality of expansion pieces 220 are sleeved at the lower end of the grouting pipe 110 at intervals, and the fasteners 210 and the expansion pieces 220 are arranged at intervals along the axial direction of the grouting pipe 110 , and the expansion pieces 220 may be The anchoring section 202 supporting the anchor cable 200 forms a protrusion, and the protrusion can ensure the stable connection between the anchoring section 202 and the stable formation. The expansion piece 220 may be made of a circular thick steel plate or a rubber plate, and the expansion piece 220 is provided with an accommodating groove 222 for accommodating the anchor cable 200 .
为了保证注浆管110插入到钢管桩100内后,注浆管110与钢管桩100同轴,锚索200的自由段204捆扎有定中件244,钢管桩100内插设有定中圈,定中圈的位置与锚索200的自由段204相对应,定中件244支撑在锚索200和定中圈之间。定中件244可以支撑起注浆管110,保证注浆管110与钢管桩100 同轴,同时避免注浆管110和锚索200在钢管桩100内晃动。具体地,定中件244为钢片弯折形成,定中件244的两端通过铁丝绑扎在保护套230上,定中圈可以为钢管。注浆管110周向方向上设有三个定中件244,相邻两个定中件 244之间的夹角为120°,保证注浆管110支撑的稳固。In order to ensure that after the grouting pipe 110 is inserted into the steel pipe pile 100, the grouting pipe 110 is coaxial with the steel pipe pile 100, the free section 204 of the anchor cable 200 is bundled with a centering piece 244, and the steel pipe pile 100 is inserted with a centering piece 244. The centering ring, the position of the centering ring corresponds to the free section 204 of the anchor cable 200, and the centering piece 244 is supported between the anchor cable 200 and the centering ring. The centering piece 244 can support the grouting pipe 110 , ensure that the grouting pipe 110 is coaxial with the steel pipe pile 100 , and prevent the grouting pipe 110 and the anchor cable 200 from shaking in the steel pipe pile 100 . Specifically, the centering member 244 is formed by bending a steel sheet, both ends of the centering member 244 are bound on the protective sleeve 230 by iron wires, and the centering ring can be a steel pipe. The grouting pipe 110 is provided with three centering pieces 244 in the circumferential direction, and the included angle between two adjacent centering pieces 244 is 120°, so as to ensure the stable support of the grouting pipe 110.
请参阅图2,注浆管110需插入到钢管桩100的底部,并且注浆管110与钢管桩100的底部具有一定距离,保证注浆材料可以顺畅的流出。需要在钢管桩100的开口处安装注浆塞250,注浆塞250密封钢管桩100的开口,避免外部的杂物落入到钢管桩100内,影响注浆材料。注浆管110的长度大于钢管桩 100的长度,注浆管110穿过注浆塞250伸出到钢管桩100外,方便注浆材料的注入。Please refer to FIG. 2 , the grouting pipe 110 needs to be inserted into the bottom of the steel pipe pile 100 , and there is a certain distance between the grouting pipe 110 and the bottom of the steel pipe pile 100 to ensure that the grouting material can flow out smoothly. The grouting plug 250 needs to be installed at the opening of the steel pipe pile 100, and the grouting plug 250 seals the opening of the steel pipe pile 100 to prevent external debris from falling into the steel pipe pile 100 and affecting the grouting material. The length of the grouting pipe 110 is greater than the length of the steel pipe pile 100, and the grouting pipe 110 extends out of the steel pipe pile 100 through the grouting plug 250 to facilitate the injection of the grouting material.
注浆塞250可以采用无纺布制成,外形为一套在热缩管上的环带,注浆前先用0.2-0.4MPa压力将注浆塞250注满,在其达到20MPa强度后进行高压注浆。注浆塞250上设有连通钢管桩100内部和外界的排气管252,注浆材料内的气体和杂质可以通过排气管252排出。The grouting plug 250 can be made of non-woven fabric, and the shape is a set of annular belts on the heat shrinkable tube. Before grouting, the grouting plug 250 is filled with a pressure of 0.2-0.4MPa, and the grouting plug 250 is filled after it reaches the strength of 20MPa. High pressure grouting. The grouting plug 250 is provided with an exhaust pipe 252 connecting the inside and the outside of the steel pipe pile 100 , and the gas and impurities in the grouting material can be discharged through the exhaust pipe 252 .
步骤S140:通过注浆管110向钢管桩100内注入注浆材料。Step S140 : inject grouting material into the steel pipe pile 100 through the grouting pipe 110 .
请再次参阅图2,具体地,注浆材料为高压浆液,采用多次注浆完成。注浆材料可以为水泥砂浆、水泥浆,也可为其他化学成分的浆液。本实施方式中,注浆材料为水泥浆,注浆采用强度不低于M30的水泥浆在1-2MPa的压力下进行,建议水灰比0.45,具体的配比和各种添加剂的掺入量须由现场试验确定。Please refer to FIG. 2 again. Specifically, the grouting material is high-pressure slurry, which is completed by multiple grouting. The grouting material can be cement mortar, cement slurry, or slurry with other chemical components. In this embodiment, the grouting material is cement slurry, and the grouting is carried out with a cement slurry with a strength not lower than M30 under a pressure of 1-2 MPa. It is recommended that the water-cement ratio be 0.45, the specific ratio and the amount of various additives to be added. Must be determined by field test.
步骤S150:待注浆材料凝固后,将锚索200通过设置于坡面10上的固定台300进行张拉,以对锚索200施加预应力。Step S150 : after the grouting material is solidified, the anchor cable 200 is stretched through the fixing platform 300 arranged on the slope surface 10 to apply prestress to the anchor cable 200 .
待注浆材料凝固后,从而将锚索200的锚固段202固定在稳定地层。锚索 200的锚固端采用OVM15锚具330锚固在边坡上的固定台300上形成,以对锚索200施加预应力。具体地,固定台300包括地梁310和设置于地梁310上的楔形垫块320。地梁310和楔形垫块320同时浇筑形成,地梁310内设有钢筋,保证地梁310具有足够的强度。地梁310和楔形垫块320中设有钢套管260,以供注浆管110和锚索200通过。After the grouting material is solidified, the anchoring section 202 of the anchor cable 200 is fixed to the stable ground. The anchoring end of the anchor cable 200 is formed by using OVM15 anchors 330 to be anchored on the fixed platform 300 on the slope, so as to apply prestress to the anchor cable 200. Specifically, the fixing platform 300 includes a ground beam 310 and a wedge-shaped spacer 320 disposed on the ground beam 310 . The ground beam 310 and the wedge-shaped spacer 320 are formed by casting at the same time, and the ground beam 310 is provided with steel bars to ensure that the ground beam 310 has sufficient strength. The ground beam 310 and the wedge-shaped spacer 320 are provided with a steel sleeve 260 for the grouting pipe 110 and the anchor cable 200 to pass through.
地梁310和楔形垫块320在浇筑的过程中,将锚具330放入到混凝土中,钢套管260穿出锚具330外,以使锚索200穿出到锚具330外。待混凝土凝固强度大于22MPa后,将锚板340设置于楔形垫块320上,且将锚索200固定于锚板340上,以对锚索200施加预应力。锚索200张拉完成后,可以使用混凝土封块350将锚板340和锚索200密封,避免锚板340和锚索200被雨水腐蚀。During the pouring process of the ground beam 310 and the wedge-shaped spacer 320 , the anchor 330 is put into the concrete, and the steel sleeve 260 is passed out of the anchor 330 , so that the anchor cable 200 is passed out of the anchor 330 . After the solidified strength of the concrete is greater than 22 MPa, the anchor plate 340 is set on the wedge-shaped spacer 320 , and the anchor cable 200 is fixed on the anchor plate 340 to apply prestress to the anchor cable 200 . After the tension of the anchor cable 200 is completed, the anchor plate 340 and the anchor cable 200 can be sealed by using the concrete block 350 to prevent the anchor plate 340 and the anchor cable 200 from being corroded by rainwater.
上述预应力微型桩施工方法,在下钢筋笼时,同时锚索200随着注浆管110 插入到钢管桩100的底部,通过注浆管110向钢管桩100内从下至上注入注浆材料,待注浆材料凝固后,可以将锚索200的锚固段202锚固在稳定地层。锚索200的锚固端伸出钢管桩100外与设置于坡面10上的固定台300连接,以对锚索200施加预应力,形成对微型桩和周围岩土体的预应力,提高微型桩及周围岩土体受力性能,提高抗滑段岩土体抗滑力,且同时可有效提高微型桩的抗压、抗剪强度。In the above prestressed micro-pile construction method, when the reinforcement cage is lowered, the anchor cable 200 is inserted into the bottom of the steel pipe pile 100 along with the grouting pipe 110, and the grouting material is injected into the steel pipe pile 100 from bottom to top through the grouting pipe 110. , after the grouting material is solidified, the anchoring section 202 of the anchor cable 200 can be anchored in the stable formation. The anchoring end of the anchor cable 200 extends out of the steel pipe pile 100 and is connected to the fixing platform 300 arranged on the slope surface 10 to apply prestress to the anchor cable 200 to form a prestress on the micro pile and the surrounding rock and soil, so as to improve the micro-pile and the surrounding rock and soil. The mechanical performance of the pile and the surrounding rock and soil mass can improve the anti-sliding force of the rock and soil mass in the anti-sliding section, and at the same time, it can effectively improve the compressive and shear strength of the micro pile.
以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The technical features of the above-described embodiments can be combined arbitrarily. For the sake of brevity, all possible combinations of the technical features in the above-described embodiments are not described. However, as long as there is no contradiction between the combinations of these technical features, All should be regarded as the scope described in this specification.
以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only represent several embodiments of the present invention, and the descriptions thereof are specific and detailed, but should not be construed as a limitation on the scope of the invention patent. It should be pointed out that for those of ordinary skill in the art, without departing from the concept of the present invention, several modifications and improvements can also be made, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention should be subject to the appended claims.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910237029.4A CN110004927A (en) | 2019-03-27 | 2019-03-27 | Construction method of prestressed micro piles |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910237029.4A CN110004927A (en) | 2019-03-27 | 2019-03-27 | Construction method of prestressed micro piles |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110004927A true CN110004927A (en) | 2019-07-12 |
Family
ID=67168358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910237029.4A Pending CN110004927A (en) | 2019-03-27 | 2019-03-27 | Construction method of prestressed micro piles |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110004927A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111042161A (en) * | 2020-01-07 | 2020-04-21 | 中国电建集团华东勘测设计研究院有限公司 | A kind of flexible treatment structure and construction method of high slope with collapsed slope |
CN111456064A (en) * | 2020-04-03 | 2020-07-28 | 中交一公局集团有限公司 | A kind of bridge steel pipe support foundation on layered rock surface and its treatment method |
CN115404886A (en) * | 2022-09-05 | 2022-11-29 | 大连理工大学 | Construction method of a prefabricated micro-pile-anchor composite support structure |
CN117345309A (en) * | 2023-12-05 | 2024-01-05 | 矿冶科技集团有限公司 | Shear-resistant prestress anchor cable |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2675742Y (en) * | 2003-07-30 | 2005-02-02 | 柳州欧维姆机械股份有限公司 | Distributed prestress finished anchor cable |
CN101298780A (en) * | 2008-06-23 | 2008-11-05 | 云南省公路规划勘察设计院 | High and light anchorage cable pile panel wall and construction method thereof |
CN103147440A (en) * | 2013-03-14 | 2013-06-12 | 黄河勘测规划设计有限公司 | Construction method of prestressed anchor cable |
CN106522243A (en) * | 2016-10-18 | 2017-03-22 | 中铁局集团有限公司 | Fissure-contained rock soil stratum prestressed anchor cable grouting and anchoring construction method |
CN106917411A (en) * | 2017-03-16 | 2017-07-04 | 广州市建誉科技有限责任公司 | Locking anchor cable structure and its construction method are anchored outside tension and compression complementary type |
CN108149679A (en) * | 2018-01-18 | 2018-06-12 | 中国建筑西北设计研究院有限公司 | A kind of construction for inserting special reinforcing bar rear in the plain concrete of CFG |
CN108677943A (en) * | 2018-06-15 | 2018-10-19 | 张玉芳 | Repeatedly control slip casting pre-stressed steel anchor pipe anchor cable composite structure and its construction method |
CN108797600A (en) * | 2018-05-21 | 2018-11-13 | 青岛建集团有限公司 | Miniature steel pipe pile prestressed anchor rope combination supporting construction method |
CN109056748A (en) * | 2018-10-17 | 2018-12-21 | 石磊 | A kind of prestressing force miniature steel pipe pile constructing structure, method |
-
2019
- 2019-03-27 CN CN201910237029.4A patent/CN110004927A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2675742Y (en) * | 2003-07-30 | 2005-02-02 | 柳州欧维姆机械股份有限公司 | Distributed prestress finished anchor cable |
CN101298780A (en) * | 2008-06-23 | 2008-11-05 | 云南省公路规划勘察设计院 | High and light anchorage cable pile panel wall and construction method thereof |
CN103147440A (en) * | 2013-03-14 | 2013-06-12 | 黄河勘测规划设计有限公司 | Construction method of prestressed anchor cable |
CN106522243A (en) * | 2016-10-18 | 2017-03-22 | 中铁局集团有限公司 | Fissure-contained rock soil stratum prestressed anchor cable grouting and anchoring construction method |
CN106917411A (en) * | 2017-03-16 | 2017-07-04 | 广州市建誉科技有限责任公司 | Locking anchor cable structure and its construction method are anchored outside tension and compression complementary type |
CN108149679A (en) * | 2018-01-18 | 2018-06-12 | 中国建筑西北设计研究院有限公司 | A kind of construction for inserting special reinforcing bar rear in the plain concrete of CFG |
CN108797600A (en) * | 2018-05-21 | 2018-11-13 | 青岛建集团有限公司 | Miniature steel pipe pile prestressed anchor rope combination supporting construction method |
CN108677943A (en) * | 2018-06-15 | 2018-10-19 | 张玉芳 | Repeatedly control slip casting pre-stressed steel anchor pipe anchor cable composite structure and its construction method |
CN109056748A (en) * | 2018-10-17 | 2018-12-21 | 石磊 | A kind of prestressing force miniature steel pipe pile constructing structure, method |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111042161A (en) * | 2020-01-07 | 2020-04-21 | 中国电建集团华东勘测设计研究院有限公司 | A kind of flexible treatment structure and construction method of high slope with collapsed slope |
CN111042161B (en) * | 2020-01-07 | 2025-06-24 | 中国电建集团华东勘测设计研究院有限公司 | A flexible treatment structure for high slopes with landslide accumulation and its construction method |
CN111456064A (en) * | 2020-04-03 | 2020-07-28 | 中交一公局集团有限公司 | A kind of bridge steel pipe support foundation on layered rock surface and its treatment method |
CN115404886A (en) * | 2022-09-05 | 2022-11-29 | 大连理工大学 | Construction method of a prefabricated micro-pile-anchor composite support structure |
CN115404886B (en) * | 2022-09-05 | 2023-09-26 | 大连理工大学 | A construction method of assembled micro pile-anchor cable combined supporting structure |
CN117345309A (en) * | 2023-12-05 | 2024-01-05 | 矿冶科技集团有限公司 | Shear-resistant prestress anchor cable |
CN117345309B (en) * | 2023-12-05 | 2024-02-20 | 矿冶科技集团有限公司 | Shear-resistant prestress anchor cable |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020238501A1 (en) | Full-assembly pressure-bearing type variable-diameter steel cage expansion head anchor rod pile system | |
CN110004927A (en) | Construction method of prestressed micro piles | |
CN209837018U (en) | Prefabricated prestressed anchor rod construction structure | |
CN105604340A (en) | Old house floor adding modifying method capable of improving seismic capacity and prolonging safe life | |
CN112301887A (en) | Anchoring system and construction method of main cable of suspension bridge under the condition of deep burial of bedrock | |
CN110761292A (en) | Prestressed anchor cable structure and prestressed anchor cable construction method | |
CN111676969A (en) | Foundation pit bag type enlarged footing anchor cable supporting structure and construction method | |
CN210562163U (en) | Prefabricated prestressed anchor rod piece | |
CN111894045A (en) | Basement floor anti-floating anchorage structure and anti-floating anchorage construction method | |
CN109113749A (en) | Four line large section railway tunnel construction method of weak surrounding rock | |
CN111980038A (en) | Novel structure for preventing and treating landslide and construction method thereof | |
CN113756339A (en) | Construction method of prestressed anchor cable frame beam structure | |
CN110565657A (en) | Supporting structure for reinforcing landslide and construction method | |
WO2023020159A1 (en) | Side slope emergency rescue support apparatus and support method | |
CN108203984A (en) | A kind of Dangerous Rock Body bolting with wire mesh method | |
KR100707138B1 (en) | Ground reinforcing grouting device and construction method | |
JP6872231B2 (en) | Reinforcement structure of rock slope with long-term durability and its construction method | |
CN209907406U (en) | Prestressed micro-pile support structure | |
CN206408630U (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body | |
CN107542086B (en) | Anchor cable construction method for filling slope | |
KR100941669B1 (en) | Re-injection device and construction method by pressure for underground anchor-pile | |
CN104929101B (en) | Resistance to plucking prestress anchoraging broken stone pile and construction method that a kind of base expanding and base expanding multistage side is expanded | |
CN110004938A (en) | A kind of foundation pit side wall structure reinforcement support device | |
CN105951874A (en) | Retaining wall reinforcing structure and construction method thereof | |
US4126001A (en) | Method for constructing a soil structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190712 |
|
RJ01 | Rejection of invention patent application after publication |