[go: up one dir, main page]

CN109930747A - A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces - Google Patents

A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces Download PDF

Info

Publication number
CN109930747A
CN109930747A CN201910316451.9A CN201910316451A CN109930747A CN 109930747 A CN109930747 A CN 109930747A CN 201910316451 A CN201910316451 A CN 201910316451A CN 109930747 A CN109930747 A CN 109930747A
Authority
CN
China
Prior art keywords
web
steel
cast
longitudinal reinforcement
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910316451.9A
Other languages
Chinese (zh)
Inventor
刘学春
陈关泼
朱涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201910316451.9A priority Critical patent/CN109930747A/en
Publication of CN109930747A publication Critical patent/CN109930747A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of cast-in-place package Honeycomb Beams of welded type holes in soffit that misplaces comprising the steel skeleton being made of girder and secondary beam;Wherein, girder and secondary beam are made of I-beam, which includes web and the top flange and lower flange for being separately positioned on its web or more two sides;Default broken line cutting of the I-beam on its web is divided into two a sides along toothed girder steel, and the toothed side dislocation welding of two girder steels forms the girder or secondary beam of web strips hole;After the completion of steel prefabricated skeleton, longitudinal reinforcement and pipeline are arranged wherein;Wherein, lower part longitudinal reinforcement and pipeline both pass through the hole on web, and top longitudinal reinforcement passes through from the top of top flange, are arranging longitudinal reinforcement and pipeline after-pouring concrete, steel skeleton is wrapped up with concrete, so that steel skeleton and reinforced concrete floor form integral module.Honeycomb Beam cross sectional moment of inertia of the invention and anti-bending bearing capacity are big, and have good energy dissipation capacity under seismic loading.

Description

一种错位焊接式腹板开洞的现浇包裹蜂窝梁A cast-in-place wrapped honeycomb beam with dislocation welded web openings

技术领域technical field

本发明涉及建筑构件技术领域,尤其涉及一种错位焊接式腹板开洞的现浇包裹蜂窝梁。The invention relates to the technical field of building components, in particular to a cast-in-place wrapped honeycomb beam with a dislocation welded web opening.

背景技术Background technique

我国每年城乡新建房屋面积20亿立方米,其中80%以上为高能耗建筑,我国单位建筑面积能耗是发达国家的2倍以上。据中国钢协统计,2016年我国钢产量达到8亿吨,自2000年起稳居世界第一,相对应的当前国内建筑工业化程度不到10%,而发达国家钢结构建筑面积占总建筑面积50%以上,日本占到80%。中国作为世界上建筑规模、钢材产量最大的国家,房屋钢结构的发展严重滞后。The area of newly built houses in urban and rural areas in my country is 2 billion cubic meters every year, of which more than 80% are buildings with high energy consumption. The energy consumption per unit building area in my country is more than twice that of developed countries. According to the statistics of China Iron and Steel Association, my country's steel output reached 800 million tons in 2016, ranking first in the world since 2000. Correspondingly, the current domestic construction industrialization degree is less than 10%, while the steel structure construction area of developed countries accounts for the total construction area. More than 50%, Japan accounted for 80%. As the country with the largest construction scale and the largest steel output in the world, China's development of building steel structures is seriously lagging behind.

现今我国建筑使用组合梁楼板多采用传统现浇施工方式,位于楼板下方的钢梁为实腹式,用钢量大,导致梁高有限,若将翼缘削弱或腹板开洞,则需进一步考虑其失稳问题,且钢梁易锈蚀,不耐高温,防腐、防火等问题尤为重要;钢梁与楼板需要栓钉相互连接,耗费人力、物力;采用混凝土包裹的组合梁,由于钢梁上翼缘距离模板较近,导致输送混凝土入口极小,施工不便;建筑所用管线多在梁板的下方,导致建筑净空降低,占用室内使用空间;在受地震等荷载情况下,支座处楼板即为控制截面,承受负弯矩,钢筋混凝土处于受拉状态,易发生破坏;此外,梁板截面为T形,梁高为钢梁高度h0与楼板厚度L之和,钢梁净高度h0不能作为梁高表示,表述极易混淆。Nowadays, the composite beam floor slabs used in buildings in China mostly adopt the traditional cast-in-place construction method. The steel beams located under the floor slabs are of solid web type, and the amount of steel used is large, resulting in limited beam height. The problem of instability, and the steel beam is easy to rust, not resistant to high temperature, anti-corrosion, fire prevention and other issues are particularly important; the steel beam and the floor need to be connected to each other with studs, which consumes manpower and material resources; the composite beam wrapped in concrete, due to the distance between the upper flange of the steel beam and the formwork It is relatively close, resulting in a very small entrance for conveying concrete and inconvenient construction; the pipelines used in the building are mostly below the beams and slabs, which reduces the building headroom and occupies indoor use space; in the case of earthquakes and other loads, the floor at the support is the control section. Under the negative bending moment, the reinforced concrete is in tension and is prone to damage; in addition, the beam-slab section is T-shaped, the beam height is the sum of the steel beam height h0 and the floor thickness L, and the steel beam net height h0 cannot be expressed as the beam height, Expressions are very confusing.

发明内容SUMMARY OF THE INVENTION

针对上述现有技术中存在的问题,本发明提供一种错位焊接式腹板开洞的现浇包裹蜂窝梁,该错位焊接式腹板开洞的现浇包裹蜂窝梁包括四根主梁和一根次梁;所述四根主梁组合成矩形框架,所述次梁固定在所述矩形框架内,与所述矩形框架短边一侧的主梁平行设置,形成钢制骨架;In view of the problems existing in the above-mentioned prior art, the present invention provides a cast-in-place wrapped honeycomb beam with a dislocation welded web opening. Root secondary beams; the four main beams are combined into a rectangular frame, the secondary beams are fixed in the rectangular frame, and are arranged in parallel with the main beams on the short side of the rectangular frame to form a steel frame;

其中,所述主梁和所述次梁均由工字梁制成,所述工字梁包括腹板和分别设置在其腹板上下两侧的上翼缘及下翼缘;所述工字梁沿其腹板上的预设折线切割分成两个一侧边沿带齿的钢梁,两个钢梁带齿的一侧错位焊接形成腹板带有孔洞的所述主梁或所述次梁;Wherein, the main beam and the secondary beam are both made of I-beam, and the I-beam includes a web and upper and lower flanges respectively arranged on the upper and lower sides of the web; the I-beam is along the The preset broken line on the web is cut into two steel beams with teeth on one side, and the two steel beams with teeth on one side are dislocated and welded to form the main beam or the secondary beam with holes in the web;

所述钢制骨架预制完成后,在其中布置纵向钢筋和管线,所述纵向钢筋包括上部纵向钢筋和下部纵向钢筋;其中,所述下部纵向钢筋和所述管线均穿过所述主梁和次梁上的孔洞,所述上部纵向钢筋从所述主梁和次梁的上翼缘上部通过,在布置好所述纵向钢筋和所述管线后浇筑混凝土,用混凝土将所述钢制骨架包裹,从而使得所述钢制骨架与钢筋混凝土楼板形成整体模块。After the steel frame is prefabricated, longitudinal reinforcement bars and pipelines are arranged therein, and the longitudinal reinforcement bars include upper longitudinal reinforcement bars and lower longitudinal reinforcement bars; wherein, the lower longitudinal reinforcement bars and the pipelines pass through the main beam and the secondary longitudinal reinforcement. The hole on the beam, the upper longitudinal steel bar passes through the upper part of the upper flange of the main beam and the secondary beam, pours concrete after arranging the longitudinal steel bar and the pipeline, and wraps the steel frame with concrete, Thus, the steel frame and the reinforced concrete floor slab form an integral module.

进一步地,所述主梁和所述次梁的上部分位于所述钢筋混凝土楼板内部。Further, the upper parts of the main beam and the secondary beam are located inside the reinforced concrete floor slab.

进一步地,所述工字梁的上翼缘包括两个梯形板;其中,所述两个梯形板分别设置在所述工字梁上侧的两端。Further, the upper flange of the I-beam includes two trapezoidal plates; wherein, the two trapezoidal plates are respectively arranged at both ends of the upper side of the I-beam.

进一步地,所述工字梁的上翼缘的宽度小于所述工字梁的下翼缘的宽度。Further, the width of the upper flange of the I-beam is smaller than the width of the lower flange of the I-beam.

可选地,所述主梁和所述次梁上的孔洞呈六边形。Optionally, the holes on the main beam and the secondary beam are hexagonal.

可选地,所述主梁和所述次梁上的孔洞呈矩形。Optionally, the holes on the main beam and the secondary beam are rectangular.

可选地,所述主梁和所述主梁之间,以及所述主梁和所述次梁之间,均以焊接的方式连接固定。Optionally, the main beam and the main beam, and between the main beam and the secondary beam, are connected and fixed by welding.

本发明提供的错位焊接式腹板开洞的现浇包裹蜂窝梁具有如下有益效果:The cast-in-place wrapped honeycomb beam with dislocation welding type web opening provided by the present invention has the following beneficial effects:

本发明提供的错位焊接式腹板开洞的现浇包裹蜂窝梁,将钢梁腹板沿折线切割,然后错位焊接形成腹板开洞的钢梁,从而充分利用了材料,在不增加钢材的前提下使梁高增大,使截面惯性矩增大,抗弯承载力也增大;The dislocation welding type cast-in-place wrapped honeycomb beam with web opening provided by the present invention cuts the steel beam web along the broken line, and then dislocation welding forms the steel beam with the web opening, so that the material is fully utilized, and the steel beam is not increased. Under the premise, the beam height is increased, the moment of inertia of the section is increased, and the flexural bearing capacity is also increased;

同时钢梁腹板处形成多个六边形或矩形孔洞,从而使得建筑所用管线(水、暖、电管等)可从钢梁腹板的孔洞中穿过,舍弃了吊顶内走管线的传统方式,做到了管线不外露,达到了室内规整美观的效果,并且使房间内部净高增加,从而增大了使用空间;At the same time, a plurality of hexagonal or rectangular holes are formed in the web of the steel beam, so that the pipelines (water, heating, electric pipes, etc.) used in the building can pass through the holes of the web of the steel beam, abandoning the tradition of routing pipelines in the ceiling In this way, the pipelines are not exposed, the interior is neat and beautiful, and the interior height of the room is increased, thereby increasing the usable space;

根据靠近支座位置钢梁承受的负弯矩大小,将钢梁的上翼缘形状变为梯形,同时钢梁中部不设上翼缘,或将钢梁上翼缘变窄,从而节省钢材,在受地震作用等反复荷载较大的情况下,上翼缘屈服,但因其处于钢筋混凝土楼板内,故不会发生失稳现象,具有良好的耗能能力,下翼缘较宽,也不发生塑性失稳现象,不会使包裹混凝土脱落;According to the negative bending moment of the steel beam near the support position, the shape of the upper flange of the steel beam is changed to a trapezoid, and there is no upper flange in the middle of the steel beam, or the upper flange of the steel beam is narrowed, so as to save steel and reduce the cost of the steel beam. In the case of large repeated loads such as earthquake action, the upper flange yields, but because it is located in the reinforced concrete floor, it will not cause instability and has good energy dissipation capacity. The lower flange is wider and does not have plasticity. Instability phenomenon, will not make the wrapped concrete fall off;

施工完成后,钢梁被混凝土完全包裹于内部,提高了构件的局部稳定,且具有良好的防腐、防火效果;After the construction is completed, the steel beam is completely wrapped in concrete, which improves the local stability of the components and has good anti-corrosion and fire-proof effects;

传统组合梁楼板梁截面按T形计算,梁高为钢梁高度h0与楼板厚度L之和,与之不同的是,而本发明的现浇包裹蜂窝梁为梁板整体模块,梁高即为钢梁净高h0,表述较为明确;此外,传统组合梁楼板中楼板处于T形截面上部,钢梁位于楼板下方,在承受荷载的情况下,支座处楼板承受负弯矩,处于受拉状态,而本发明的现浇包裹蜂窝梁的钢梁上部分位于楼板内部,一方面不仅省去梁板栓钉连接,混凝土浇灌,提高了施工效率,另一方面使得钢梁承受弯矩的中性轴上移,楼板受拉截面面积减小,结构安全性能得到提升。The traditional composite beam floor beam section is calculated according to the T shape, and the beam height is the sum of the steel beam height h0 and the floor thickness L. The difference is that the cast-in-place wrapped honeycomb beam of the present invention is a beam-slab integral module, and the beam height is The net height h0 of steel beams is relatively clear; in addition, in the traditional composite beam floor slab, the floor slab is located at the upper part of the T-shaped section, and the steel beam is located under the floor slab. The upper part of the steel beam of the cast-in-place wrapped honeycomb beam of the present invention is located inside the floor slab. On the one hand, the beam-slab bolt connection and concrete pouring are omitted, and the construction efficiency is improved; on the other hand, the neutral axis of the steel beam bearing the bending moment is moved upward, The tensile section area of the floor slab is reduced, and the structural safety performance is improved.

附图说明Description of drawings

图1和图2是本发明的开六边形孔洞的钢梁腹板制作流程图;Fig. 1 and Fig. 2 are the steel beam web manufacturing flow chart of the present invention that opens hexagonal hole;

图3是本发明开矩形孔洞的钢梁腹板制作流程图Fig. 3 is a flow chart of the present invention for making a steel beam web with a rectangular hole

图4是本发明腹板开六边形孔洞的钢梁示意图;4 is a schematic diagram of a steel beam with a hexagonal hole in the web of the present invention;

图5是本发明腹板开矩形孔洞的钢梁示意图;5 is a schematic diagram of a steel beam with rectangular holes in the web of the present invention;

图6是本发明的现浇包裹蜂窝梁的钢制骨架示意图;Fig. 6 is the steel frame schematic diagram of the cast-in-place wrapped honeycomb beam of the present invention;

图7是本发明的现浇包裹蜂窝梁的断面分解图;Fig. 7 is the sectional exploded view of the cast-in-place wrapped honeycomb beam of the present invention;

图8是本发明的现浇包裹蜂窝梁浇筑完成后的截面图;Fig. 8 is the sectional view after the pouring of the cast-in-place wrapped honeycomb beam of the present invention is completed;

图9是本发明上翼缘较窄、腹板开六边形孔洞的钢梁示意图;9 is a schematic diagram of a steel beam with a narrow upper flange and a hexagonal hole in the web of the present invention;

图10是本发明上翼缘较窄、腹板开矩形孔洞的钢梁示意图;10 is a schematic diagram of a steel beam with a narrow upper flange and a rectangular hole in the web of the present invention;

图11是本发明上翼缘为梯形、腹板开六边形孔洞的钢梁示意图;11 is a schematic diagram of a steel beam with a trapezoidal upper flange and a hexagonal hole in the web of the present invention;

图12是本发明上翼缘为梯形、腹板开矩形孔洞的钢梁示意图;12 is a schematic diagram of a steel beam with a trapezoidal upper flange and a rectangular hole in the web of the present invention;

图13是本发明的上翼缘削弱型的现浇包裹蜂窝梁的钢制骨架示意图;13 is a schematic view of the steel skeleton of the cast-in-place wrapped honeycomb beam of the weakened upper flange of the present invention;

图14是本发明的上翼缘削弱型的现浇包裹蜂窝梁的断面分解图;14 is an exploded sectional view of the cast-in-place wrapped honeycomb beam of the weakened upper flange of the present invention;

图15是本发明的上翼缘削弱型的现浇包裹蜂窝梁的浇筑完成截面图。Fig. 15 is a sectional view of the cast-in-place wrapped honeycomb beam of the weakened upper flange of the present invention after pouring.

附图标记说明:Description of reference numbers:

1:腹板,2:上翼缘,3:下翼缘,4:孔洞,5:主梁,6:次梁,1: Web, 2: Top Flange, 3: Bottom Flange, 4: Hole, 5: Primary Beam, 6: Secondary Beam,

7:钢制骨架,8:混凝土。7: Steel frame, 8: Concrete.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

请参阅图1至图15,本实施例提供一种错位焊接式腹板开洞的现浇包裹蜂窝梁,该错位焊接式腹板开洞的现浇包裹蜂窝梁包括四根主梁5和一根次梁6;四根主梁5组合成矩形框架,次梁6固定在该矩形框架内,与矩形框架短边一侧的主梁5平行设置,形成钢制骨架7,如图6和图13所示。其中,各主梁5之间,以及主梁5和次梁6之间,均以焊接的方式连接固定。Please refer to FIG. 1 to FIG. 15 , the present embodiment provides a cast-in-place wrapped honeycomb beam with a dislocation welded web opening. The dislocation welded cast-in-place wrapped honeycomb beam with a web opening includes four main beams 5 and The root beam 6; the four main beams 5 are combined into a rectangular frame, and the secondary beam 6 is fixed in the rectangular frame and is arranged in parallel with the main beam 5 on the short side of the rectangular frame to form a steel frame 7, as shown in Figures 6 and 6 13 shown. Among them, the main beams 5 and between the main beam 5 and the secondary beam 6 are all connected and fixed by welding.

其中,主梁5和次梁6均由工字梁制成,该工字梁包括腹板1和分别设置在其腹板1上下两侧的上翼缘2及下翼缘3;工字梁沿其腹板1上的预设折线切割分成两个一侧边沿带齿的钢梁,两个钢梁带齿的一侧错位焊接形成腹板带有孔洞4的主梁5或次梁6,从而充分利用材料,在不增加钢材的情况下,使得腹板1增高,同时在其上形成多个孔洞4,从而使得梁高增大,进而使得截面惯性矩增大,抗弯承载力也增大。Among them, the main beam 5 and the secondary beam 6 are both made of I-beams, and the I-beam includes a web 1 and an upper flange 2 and a lower flange 3 respectively arranged on the upper and lower sides of the web 1; The preset broken line on the web 1 is cut into two steel beams with teeth on one side, and the two steel beams with teeth are dislocated and welded to form the main beam 5 or the secondary beam 6 with holes 4 in the web, so as to fully Using materials, without adding steel, the height of the web 1 is increased, and a plurality of holes 4 are formed on it, thereby increasing the beam height, thereby increasing the moment of inertia of the section, and increasing the flexural bearing capacity.

钢制骨架7预制完成后,在其中布置纵向钢筋和管线(水、暖、电管等),该纵向钢筋包括上部纵向钢筋和下部纵向钢筋;其中,下部纵向钢筋和管线均穿过主梁5和次梁6上的孔洞4,从而隐藏于楼板内部,增加房间内部净高,且达到室内规整美观的效果。上部纵向钢筋从主梁5和次梁6的上翼缘的上部通过,在布置好纵向钢筋和管线后浇筑混凝土8,用混凝土8将钢制骨架7包裹,从而使得钢制骨架7与钢筋混凝土楼板形成整体模块;After the steel frame 7 is prefabricated, longitudinal reinforcement bars and pipelines (water, heating, electric pipes, etc.) are arranged in it, and the longitudinal reinforcement bars include upper longitudinal reinforcement bars and lower longitudinal reinforcement bars; wherein, the lower longitudinal reinforcement bars and pipelines pass through the main beam 5. And the hole 4 on the secondary beam 6, so as to hide inside the floor slab, increase the clear height inside the room, and achieve the effect of neat and beautiful interior. The upper longitudinal steel bars pass through the upper parts of the upper flanges of the main beam 5 and the secondary beam 6. After the longitudinal steel bars and pipelines are arranged, concrete 8 is poured, and the steel frame 7 is wrapped with the concrete 8, so that the steel frame 7 is connected with the reinforced concrete. The floor slab forms an integral module;

上述主梁5和次梁6的上部分位于钢筋混凝土楼板内部,如图7、图8、图14以及图15所示;如此一来,不仅可以省去梁板栓钉连接,便于混凝土浇灌,提高施工效率,又可以在楼板受荷情况下,钢梁承受弯矩的中性轴上移,支座处楼板负弯矩减小,受拉截面面积减小,结构安全性能得到提升。并且由于钢制骨架7被混凝土8完全包裹于内部,从而提高了构件的局部稳定,且具有良好的防腐、防火效果。此外,由于钢梁的上翼缘2位于楼板的上表面,因此梁高即为钢梁净高h0,表述明确。The upper part of the above-mentioned main beam 5 and secondary beam 6 is located inside the reinforced concrete floor, as shown in Figure 7, Figure 8, Figure 14 and Figure 15; in this way, not only can the beam-plate stud connection be omitted, it is convenient for concrete pouring, and the construction is improved. In addition, when the floor is under load, the neutral axis of the steel beam bearing the bending moment is moved upward, the negative bending moment of the floor at the support is reduced, the tensile section area is reduced, and the structural safety performance is improved. In addition, since the steel frame 7 is completely enclosed by the concrete 8, the local stability of the component is improved, and it has good anti-corrosion and fire-proof effects. In addition, since the upper flange 2 of the steel beam is located on the upper surface of the floor slab, the beam height is the net height h0 of the steel beam, and the expression is clear.

进一步地,根据靠近支座位置钢梁承受的负弯矩大小,本实施例中将上述工字梁的上翼缘2设置成两个梯形板;该两个梯形板分别设置在工字梁上侧的两端,中间部分则不设翼缘,如图11和图12所示;或将上翼缘2缩窄,使得工字梁的上翼缘2的宽度小于其下翼缘3的宽度;如图9和图10所示。从而节省钢材,在受地震作用等反复荷载较大的情况下,上翼缘2屈服,但因其处于钢筋混凝土楼板内,故不会发生失稳现象,具有良好的耗能能力,下翼缘3较宽,也不发生塑性失稳现象,不会使包裹混凝土脱落。Further, according to the size of the negative bending moment that the steel beam near the support position bears, in the present embodiment, the upper flange 2 of the above-mentioned I-beam is set to two trapezoidal plates; the two trapezoidal plates are respectively arranged on the I-beam. The two ends of the side and the middle part are not provided with flanges, as shown in Figure 11 and Figure 12; or the upper flange 2 is narrowed, so that the width of the upper flange 2 of the I-beam is smaller than the width of the lower flange 3 ; as shown in Figure 9 and Figure 10. In this way, steel is saved. In the case of repeated loads such as earthquakes, the upper flange 2 yields. However, because it is in the reinforced concrete floor, it will not cause instability and has good energy dissipation capacity. 3 It is wider, and plastic instability does not occur, and the wrapped concrete will not fall off.

可选地,上述主梁5和次梁6上的孔洞4可以呈六边形,如图4、图9和图11所示;或呈矩形,如图5、图10和图12所示。由于六边形或矩形的孔洞4其孔径较大,因此较圆形孔洞的优势在于更方便管线与钢筋从中穿过。Optionally, the holes 4 on the main beam 5 and the secondary beam 6 may be hexagonal, as shown in FIGS. 4 , 9 and 11 ; or rectangular, as shown in FIGS. 5 , 10 and 12 . Since the hexagonal or rectangular hole 4 has a larger hole diameter, the advantage of the round hole is that it is more convenient for pipelines and steel bars to pass therethrough.

本实施例的错位焊接式腹板开洞的现浇包裹蜂窝梁的装配方式如下:The assembly method of the cast-in-place wrapped honeycomb beam with the dislocation welded web opening of the present embodiment is as follows:

在工厂将腹板1沿折线切割,然后错位焊接,使得腹板1增高,并形成多个六边形或矩形的孔洞4;主梁5作为边框置于四周,中部的次梁6平行于短边主梁放置,各钢梁之间的连接处以焊接方式固定;将在工厂预制的钢制骨架7运送至施工现场,采用吊装的方式放置在支好的模板内,然后布置楼板内部管线与钢筋,最后浇筑混凝土8。In the factory, the web 1 is cut along the fold line, and then welded at a dislocation, so that the web 1 is increased, and a plurality of hexagonal or rectangular holes 4 are formed; the main beam 5 is placed around as a frame, and the secondary beam 6 in the middle is parallel to the short The side main beams are placed, and the joints between the steel beams are fixed by welding; the steel frame 7 prefabricated in the factory is transported to the construction site, placed in the supported formwork by hoisting, and then the pipelines and steel bars inside the floor are arranged , and finally pour concrete 8.

此外,需要说明的是,本实施例中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者终端设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者终端设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者终端设备中还存在另外的相同要素。In addition, it should be noted that, in this embodiment, the terms "comprising", "comprising" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal device including a series of elements not only Include those elements, but also include other elements not expressly listed or inherent to such process, method, article or terminal equipment. Without further limitation, an element defined by the phrase "comprises a..." does not preclude the presence of additional identical elements in the process, method, article or terminal device comprising said element.

以上仅为本发明优选实施例而已,并不用于限制本发明,对于本领域技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (7)

1.一种错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,包括四根主梁和一根次梁;所述四根主梁组合成矩形框架,所述次梁固定在所述矩形框架内,与所述矩形框架短边一侧的主梁平行设置,形成钢制骨架;1. a cast-in-place wrapped honeycomb beam with dislocation welding type web opening, is characterized in that, comprises four main beams and a secondary beam; Described four main beams are combined into rectangular frame, and described secondary beam is fixed on In the rectangular frame, the main beam on the short side of the rectangular frame is arranged in parallel to form a steel frame; 其中,所述主梁和所述次梁均由工字梁制成,所述工字梁包括腹板和分别设置在其腹板上下两侧的上翼缘及下翼缘;所述工字梁沿其腹板上的预设折线切割分成两个一侧边沿带齿的钢梁,两个钢梁带齿的一侧错位焊接形成腹板带有孔洞的所述主梁或所述次梁;Wherein, the main beam and the secondary beam are both made of I-beam, and the I-beam includes a web and upper and lower flanges respectively arranged on the upper and lower sides of the web; the I-beam is along the The preset broken line on the web is cut into two steel beams with teeth on one side, and the two steel beams with teeth on one side are dislocated and welded to form the main beam or the secondary beam with holes in the web; 所述钢制骨架预制完成后,在其中布置纵向钢筋和管线,所述纵向钢筋包括上部纵向钢筋和下部纵向钢筋;其中,所述下部纵向钢筋和所述管线均穿过所述主梁和次梁上的孔洞,所述上部纵向钢筋从所述主梁和次梁的上翼缘上部通过,在布置好所述纵向钢筋和所述管线后浇筑混凝土,用混凝土将所述钢制骨架包裹,从而使得所述钢制骨架与钢筋混凝土楼板形成整体模块。After the steel frame is prefabricated, longitudinal reinforcement bars and pipelines are arranged therein, and the longitudinal reinforcement bars include upper longitudinal reinforcement bars and lower longitudinal reinforcement bars; wherein, the lower longitudinal reinforcement bars and the pipelines pass through the main beam and the secondary longitudinal reinforcement. The hole on the beam, the upper longitudinal steel bar passes through the upper part of the upper flange of the main beam and the secondary beam, pours concrete after arranging the longitudinal steel bar and the pipeline, and wraps the steel frame with concrete, Thus, the steel frame and the reinforced concrete floor slab form an integral module. 2.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述主梁和所述次梁的上部分位于所述钢筋混凝土楼板内部。2 . The cast-in-place wrapped honeycomb beam with web openings by dislocation welding according to claim 1 , wherein the upper parts of the main beam and the secondary beam are located inside the reinforced concrete floor slab. 3 . 3.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述工字梁的上翼缘包括两个梯形板;其中,所述两个梯形板分别设置在所述工字梁上侧的两端。3 . The cast-in-place wrapped honeycomb beam with a dislocation welded web opening according to claim 1 , wherein the upper flange of the I-beam comprises two trapezoidal plates; wherein, the two trapezoidal plates They are respectively arranged at both ends of the upper side of the I-beam. 4.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述工字梁的上翼缘的宽度小于所述工字梁的下翼缘的宽度。4. The cast-in-place wrapped honeycomb beam with dislocation welded web openings according to claim 1, wherein the width of the upper flange of the I-beam is smaller than the width of the lower flange of the I-beam . 5.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述主梁和所述次梁上的孔洞呈六边形。5 . The cast-in-place wrapped honeycomb beam with a dislocation welded web opening according to claim 1 , wherein the holes on the main beam and the secondary beam are hexagonal. 6 . 6.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述主梁和所述次梁上的孔洞呈矩形。6 . The cast-in-place wrapped honeycomb beam with dislocation welded web openings according to claim 1 , wherein the holes on the main beam and the secondary beam are rectangular. 7 . 7.如权利要求1所述的错位焊接式腹板开洞的现浇包裹蜂窝梁,其特征在于,所述主梁和所述主梁之间,以及所述主梁和所述次梁之间,均以焊接的方式连接固定。7. The cast-in-place wrapped honeycomb beam with dislocation welded web openings according to claim 1, characterized in that, between the main beam and the main beam, and between the main beam and the secondary beam are connected and fixed by welding.
CN201910316451.9A 2019-04-19 2019-04-19 A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces Pending CN109930747A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910316451.9A CN109930747A (en) 2019-04-19 2019-04-19 A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910316451.9A CN109930747A (en) 2019-04-19 2019-04-19 A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces

Publications (1)

Publication Number Publication Date
CN109930747A true CN109930747A (en) 2019-06-25

Family

ID=66990363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910316451.9A Pending CN109930747A (en) 2019-04-19 2019-04-19 A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces

Country Status (1)

Country Link
CN (1) CN109930747A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982729A (en) * 2021-03-16 2021-06-18 北京工业大学 Modularized concrete-filled steel tube multidimensional energy dissipation wall with uniformly distributed stress under earthquake
US11236500B2 (en) 2020-04-29 2022-02-01 Folding Holdings, LLC Built-up beams and building structures

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2632188Y (en) * 2003-06-03 2004-08-11 张英保 Assembled building top
CN103132649A (en) * 2013-03-13 2013-06-05 广西大学 Steel box girder matched with cellular steel web plate
CN203429885U (en) * 2013-06-28 2014-02-12 湖北弘毅建筑装饰工程有限公司 Circular-hole web box-shaped steel reinforced concrete composite flat beam
CN104563391A (en) * 2014-10-31 2015-04-29 华南理工大学 Recycled hybrid beam with built-in discontinuous I-shaped steel and construction technology thereof
JP2017150189A (en) * 2016-02-23 2017-08-31 新日鐵住金株式会社 Buckling stiffening structure of h-shaped cross-sectional member and steel-frame structure
CN108385885A (en) * 2018-02-12 2018-08-10 北京工业大学 A kind of assembled stealth beam floor
CN108978856A (en) * 2018-09-25 2018-12-11 沈阳建筑大学 A kind of assembled Honeycomb Beam panel structure system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2632188Y (en) * 2003-06-03 2004-08-11 张英保 Assembled building top
CN103132649A (en) * 2013-03-13 2013-06-05 广西大学 Steel box girder matched with cellular steel web plate
CN203429885U (en) * 2013-06-28 2014-02-12 湖北弘毅建筑装饰工程有限公司 Circular-hole web box-shaped steel reinforced concrete composite flat beam
CN104563391A (en) * 2014-10-31 2015-04-29 华南理工大学 Recycled hybrid beam with built-in discontinuous I-shaped steel and construction technology thereof
JP2017150189A (en) * 2016-02-23 2017-08-31 新日鐵住金株式会社 Buckling stiffening structure of h-shaped cross-sectional member and steel-frame structure
CN108385885A (en) * 2018-02-12 2018-08-10 北京工业大学 A kind of assembled stealth beam floor
CN108978856A (en) * 2018-09-25 2018-12-11 沈阳建筑大学 A kind of assembled Honeycomb Beam panel structure system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11236500B2 (en) 2020-04-29 2022-02-01 Folding Holdings, LLC Built-up beams and building structures
US20220396946A1 (en) * 2020-04-29 2022-12-15 Folding Holdings, LLC Built-up beams and building structures
US11718982B2 (en) * 2020-04-29 2023-08-08 Folding Holdings, LLC Built-up beams and building structures
CN112982729A (en) * 2021-03-16 2021-06-18 北京工业大学 Modularized concrete-filled steel tube multidimensional energy dissipation wall with uniformly distributed stress under earthquake
CN112982729B (en) * 2021-03-16 2022-03-29 北京工业大学 Modularized concrete-filled steel tube multidimensional energy dissipation wall with uniformly distributed stress under earthquake

Similar Documents

Publication Publication Date Title
JP5830195B2 (en) How to assemble a truss, suspend a formwork, and manufacture a ferrocement slab on site
CN107288218B (en) An assembled reinforced concrete frame structure beam-column joint and its manufacturing method
CN103184762B (en) Multi-story/high-rise fabricated steel structural prestressed supporting system capable of realizing rigid connection of joints
CN110306724A (en) A prefabricated wrapped honeycomb beam with misaligned welded web opening
CN204098313U (en) Two-way mixing cross wise reinforcement truss self-supporting hollowcore slab
CN108457422A (en) Precast prestressed beam, assembled composite frame structure and its installation method
CN109930747A (en) A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces
CN109577492B (en) Connecting structure for section steel part wrapped concrete column and reinforced concrete beam node
CN101881060B (en) Prestressed concrete mansard rigid-frame beam
CN204081090U (en) The node component of a kind of U-shaped steel-concrete combination beam and special-shaped steel pipe concrete post
CN110607877A (en) A kind of L-shaped steel pipe recycled concrete special-shaped column with open T-shaped ribs and its method
CN217557313U (en) Prefabricated combined shear wall
CN207003719U (en) A kind of prefabricated steel faced wall with steel bar girder
CN110528734A (en) A kind of steel-concrete combination shear wall with short piers
CN110258920A (en) A kind of prefabricated package Honeycomb Beam of holes in soffit
CN110306725A (en) A cast-in-place wrapped honeycomb beam with web openings
CN215254994U (en) Assembled reinforced concrete one-way close rib superimposed sheet superstructure
CN116265671A (en) Thermal insulation prefabricated wallboard and construction method for constructing wall by adopting thermal insulation prefabricated wallboard
CN105971176B (en) Thin-wall steel tube rib hollow concrete superimposed sheet, floor, building and manufacture method
CN111962731B (en) Grid beam and bidirectional stressed steel bar truss floor structure and construction method thereof
CN107190885A (en) A kind of prefabricated steel faced wall with steel bar girder
CN103541478B (en) Lattice superposed beam and plate and construction method thereof
CN209723346U (en) A kind of firm energy-saving building laminated floor slab
CN108978860B (en) Steel pipe concrete column-steel pipe concrete beam node connection structure
CN110042985A (en) A kind of cast-in-place package Honeycomb Beam of splitting type holes in soffit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190625

RJ01 Rejection of invention patent application after publication