[go: up one dir, main page]

CN109930624A - A kind of embedding petrographic province blower foundation of offshore wind farm and construction method - Google Patents

A kind of embedding petrographic province blower foundation of offshore wind farm and construction method Download PDF

Info

Publication number
CN109930624A
CN109930624A CN201910274592.9A CN201910274592A CN109930624A CN 109930624 A CN109930624 A CN 109930624A CN 201910274592 A CN201910274592 A CN 201910274592A CN 109930624 A CN109930624 A CN 109930624A
Authority
CN
China
Prior art keywords
jacket
embedding
piling bar
offshore wind
blower foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910274592.9A
Other languages
Chinese (zh)
Inventor
刘金全
周全智
李红有
迟洪明
吴永祥
全建军
沈石水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longyuan Beijing Wind Power Engineering Design and Consultation Co Ltd
Original Assignee
Longyuan Beijing Wind Power Engineering Design and Consultation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longyuan Beijing Wind Power Engineering Design and Consultation Co Ltd filed Critical Longyuan Beijing Wind Power Engineering Design and Consultation Co Ltd
Priority to CN201910274592.9A priority Critical patent/CN109930624A/en
Publication of CN109930624A publication Critical patent/CN109930624A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a kind of embedding petrographic province blower foundation of offshore wind farm and construction method, blower foundation includes piling bar, jacket, transformational structure;Jacket is more, and more jackets are fixedly connected by horizontal brace or diagonal brace;Piling bar is inserted in jacket;The lower end of piling bar is provided with overlap joint stem, embedding along stem;Transformational structure is set to the top of jacket and piling bar.The construction method of above-mentioned blower foundation, including Prefabricated steel construction product, decentralization jacket, piling, installation temporary construction platform and equipment, embedding rock, remove temporary construction platform and transformational structure is installed etc..The present invention drives piles mode after may be implemented by installing jacket in advance, has the advantages that construction is simple, easy to operate, duty cycle is short, can avoid underwater operation;The factory floor machine-shaping by land of all steel constructions significantly avoids on-site assembly construction, has significantly saved construction period;Temporary construction platform installation is simple and convenient and reuses after can dismantling.

Description

一种海上风电嵌岩区风机基础及施工方法Fan foundation and construction method for offshore wind power rock-socketed area

技术领域technical field

本发明涉及一种风机基础及施工方法,尤其涉及一种海上风电嵌岩区风机基础及施工方法。The invention relates to a fan foundation and a construction method, in particular to a fan foundation and a construction method in an offshore wind power rock-socketed area.

背景技术Background technique

随着海上风能的开发逐渐扩大,在岩石地质中进行嵌岩施工已逐步成为海上风能开发中的核心问题,嵌岩区的风机基础造价严重制约着海上风电场的成本,因此海上风电嵌岩区的风机基础比选就显得尤为关键。With the gradual expansion of offshore wind energy development, rock-socketed construction in rock geology has gradually become a core issue in offshore wind energy development. The selection of the fan base is particularly critical.

目前海上风电嵌岩风机基础形式主要有高桩承台基础和单桩基础。其中,高桩承台基础一般包含6-8根斜桩,斜桩固定后,在桩底进行芯柱嵌岩施工,上部进行混凝土承台浇筑。该风机基础所使用的嵌岩桩的数量多,导致海上清孔、钻孔、底部芯柱嵌岩施工工作量大,再加上上部还需进行钢套箱安装和混凝土承台浇筑,工序多,施工效率低,另外由于桩是倾斜的,不仅钻孔效率低,一般还需搭设稳桩平台,施工周期相当长,对海上天气窗口期要求高。At present, the foundation forms of rock-socketed wind turbines for offshore wind power mainly include high pile cap foundation and single pile foundation. Among them, the high pile cap foundation generally contains 6-8 inclined piles. After the inclined piles are fixed, the core column rock-socketing construction is carried out at the bottom of the pile, and the upper part is poured with concrete cap. The number of rock-socketed piles used in the foundation of the fan is large, which leads to a large workload of offshore hole cleaning, drilling, and rock-socketed construction of the bottom core column. In addition, the upper part needs to be installed with steel casing and concrete capping, which requires many procedures. , the construction efficiency is low, and because the piles are inclined, not only the drilling efficiency is low, but also a stable pile platform is generally required. The construction period is quite long, and the requirements for the offshore weather window period are high.

而单桩基础桩径一般较大,随着水深和风机的增大,最大桩径可达8m。由于单桩直径大,且埋深较深,对钻机钻孔的直径要求大,导致工程造价高,而且单桩基础嵌岩一般需二次成孔,即一次钻孔,二次扩孔,施工效率很低,施工工期长,天气窗口期要求高。此外,单桩基础也需搭设专门的海上施工平台并固定钻机进行钻孔,存在施工周期长,造价高,应用海域水深较浅的缺点。The diameter of the single pile foundation is generally larger. With the increase of water depth and fan, the maximum pile diameter can reach 8m. Due to the large diameter of the single pile and the deep burial depth, the diameter of the drilling rig is required to be large, resulting in high engineering cost, and the single pile foundation generally needs to be drilled twice for rock sockets, that is, one drilling, secondary reaming, and construction. The efficiency is very low, the construction period is long, and the weather window period is demanding. In addition, the monopile foundation also needs to set up a special offshore construction platform and fix the drilling rig for drilling, which has the disadvantages of long construction period, high cost and shallow water depth in the application sea area.

为了降低海上风机基础的成本,缩短施工周期,提高海上施工的安全性,并适应较深海域风电场在岩石地基条件下的开发要求,亟需提出一种新型的海上风电嵌岩区风机基础及施工方法。In order to reduce the cost of offshore wind turbine foundations, shorten the construction period, improve the safety of offshore construction, and adapt to the development requirements of wind farms in deep seas under rocky foundation conditions, it is urgent to propose a new type of wind turbine foundation for offshore wind power in rock-socketed areas. Construction method.

发明内容SUMMARY OF THE INVENTION

为了解决上述技术所存在的不足之处,本发明提供了一种海上风电嵌岩区风机基础及施工方法。In order to solve the shortcomings of the above-mentioned technologies, the present invention provides a fan foundation and a construction method in an offshore wind power rock-socketed area.

为了解决以上技术问题,本发明采用的技术方案是:一种海上风电嵌岩区风机基础,包括钢桩,还包括导管架、转换结构、搭接芯柱、嵌沿芯柱;导管架为多根,多根导管架通过水平撑或斜撑固定连接;In order to solve the above technical problems, the technical scheme adopted in the present invention is: a fan foundation for offshore wind power rock-socketed area, including steel piles, and also includes jackets, conversion structures, overlapping core columns, and embedded core columns; Roots, multiple jackets are fixedly connected by horizontal braces or diagonal braces;

钢桩插置于导管架内,其上端通过连接板与导管架的上端相焊接;钢桩的长度大于导管架的长度;The steel pile is inserted into the jacket, and its upper end is welded with the upper end of the jacket through the connecting plate; the length of the steel pile is greater than that of the jacket;

钢桩的下端设置有搭接芯柱;搭接芯柱的下端设置有嵌沿芯柱;转换结构设置于导管架与钢桩的顶端。The lower end of the steel pile is provided with a lapped core column; the lower end of the lapped core column is provided with an embedded core column; the conversion structure is arranged on the top of the jacket and the steel pile.

进一步地,转换结构包括主立柱、支撑腿、过渡锥管;支撑腿为多根,多根支撑腿沿主立柱的外壁呈辐射状排列;支撑腿的下端均固定设置有过渡锥管;过渡锥管的下端设置有锥尖结构,过渡锥管通过锥尖结构插置于钢桩的顶端。Further, the conversion structure includes a main column, a supporting leg, and a transition cone; there are multiple supporting legs, and the plurality of supporting legs are arranged radially along the outer wall of the main column; the lower ends of the supporting legs are all fixed with transition cones; The lower end of the pipe is provided with a cone tip structure, and the transition cone tube is inserted into the top end of the steel pile through the cone tip structure.

进一步地,钢桩通过转换结构与风机塔筒相连接。Further, the steel piles are connected with the wind turbine tower through the conversion structure.

进一步地,搭接芯柱、嵌沿芯柱均以钢筋笼为骨架,内外浇筑混凝土而成型;搭接芯柱设置于钢桩的内部下端。Further, both the lapped core column and the embedded core column are formed by using a steel cage as a skeleton, and are formed by pouring concrete inside and outside; the lapped core column is arranged at the inner lower end of the steel pile.

进一步地,导管架的下端设置有防沉板,用于防止安装过程中导管架因自重作用下沉降过大。Further, the lower end of the jacket is provided with an anti-sinking plate, which is used to prevent the jacket from sinking too much due to its own weight during the installation process.

进一步地,导管架的内壁上焊接设置有锲块,用于对钢桩进行水平限位。Further, a wedge block is welded on the inner wall of the jacket to limit the horizontal position of the steel pile.

进一步地,导管架与钢桩的上端架设有临时施工平台。Further, a temporary construction platform is erected on the upper end of the jacket and the steel pile.

进一步地,导管架为直立式。或者,导管架为斜式,其斜度为7:1~12:1。Further, the jacket is vertical. Alternatively, the jacket is inclined, and its inclination is 7:1 to 12:1.

一种海上风电嵌岩区风机基础的施工方法,包括以下步骤:A construction method for a wind turbine foundation in an offshore wind power rock-socketed area, comprising the following steps:

a、在陆上工厂车间对导管架、钢桩、转换结构、临时施工平台、搭接芯柱和嵌沿芯柱用钢筋笼预制成型;a. Prefabricate steel cages for jackets, steel piles, transition structures, temporary construction platforms, lapped core columns and embedded core columns in the onshore factory workshop;

b、将导管架下放至工作海域海床上,因有防沉板的作用,导管架的沉降得到有效控制;b. Lower the jacket to the seabed of the working sea area, and the settlement of the jacket can be effectively controlled due to the function of the anti-sinking plate;

c、进行打桩作业,将钢桩穿过导管架并打入至土层的底端;c. Carry out piling operation, drive the steel piles through the jacket and drive them to the bottom of the soil layer;

d、打桩完毕后,焊接连接板,使得钢桩与导管架连接为一体;d. After the piling is completed, the connecting plate is welded so that the steel pile and the jacket are connected as a whole;

e、将钢桩的顶端切割至平齐,然后安装钻孔嵌岩用临时施工平台,并在临时施工平台上安装嵌岩设备;e. Cut the top of the steel pile to be flush, then install a temporary construction platform for drilling rock sockets, and install rock socketing equipment on the temporary construction platform;

f、沿着钢桩向土层下方的基岩层打孔,可多台钻机同时操作;打孔至预定深度后,沿钢桩向基岩层及土层的孔内下放钢筋笼并浇铸混凝土,完成嵌岩作用;f. Drill holes into the bedrock layer below the soil layer along the steel pile, and multiple drilling rigs can operate at the same time; after drilling to a predetermined depth, lower the reinforcement cage along the steel pile into the hole of the bedrock layer and the soil layer and pour concrete, complete rock socketing;

g、嵌岩施工完毕后,移除嵌岩设备及临时施工平台;g. After the rock-socketing construction is completed, remove the rock-socketing equipment and temporary construction platform;

h、安装转换结构,完成风机基础施工。h. Install the conversion structure and complete the fan foundation construction.

本发明通过预先安装导管架可以实现后打桩方式,具有施工简单、操作方便、作业周期短、可避免水下作业的优点;所有的钢结构均在陆上工厂车间加工成型,大幅度避免了现场组装施工,显著节约了施工周期;临时施工平台安装简单方便并且可以拆卸后重复利用。The invention can realize the post-piling method by pre-installing the jacket, and has the advantages of simple construction, convenient operation, short operation period, and avoidance of underwater operation; Assembly and construction significantly saves the construction period; the temporary construction platform is simple and convenient to install and can be disassembled and reused.

附图说明Description of drawings

图1为本发明的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of the present invention.

图2为钢桩和导管架通过连接板相连接的结构示意图。Figure 2 is a schematic structural diagram of the connection between the steel pile and the jacket through the connecting plate.

图3为转换结构的放大结构示意图。FIG. 3 is an enlarged schematic view of the conversion structure.

图4为钢桩和导管架通过锲块相连接的结构示意图。FIG. 4 is a schematic structural diagram of the connection between the steel pile and the jacket through a wedge block.

图5为导管架在工作海域海床上的安装状态示意图。FIG. 5 is a schematic diagram of the installation state of the jacket on the seabed of the working sea area.

图6为打桩状态示意图。FIG. 6 is a schematic diagram of a pile driving state.

图7为临时施工平台的安装状态示意图。FIG. 7 is a schematic diagram of the installation state of the temporary construction platform.

图8为嵌岩作业的状态示意图。FIG. 8 is a schematic diagram of the state of the rock-socketing operation.

图9为嵌岩作业完成后拆除临时施工平台的状态示意图。FIG. 9 is a schematic diagram showing the state of dismantling the temporary construction platform after the rock-socketing operation is completed.

图10为转换结构的安装过程示意图。FIG. 10 is a schematic diagram of the installation process of the conversion structure.

图11为转换结构安装好之后的风机基础的整体结构图。FIG. 11 is an overall structural diagram of the fan foundation after the conversion structure is installed.

图中:1、转换结构;2、导管架;3、连接板;4、斜撑;5、防沉板;6、钢桩;7、搭接芯柱;8、嵌沿芯柱;9、锲块;10、过渡锥管;11、临时施工平台;12、主立柱;13、支撑腿;14、土层;15、基岩层。In the figure: 1. Conversion structure; 2. Jacket; 3. Connecting plate; 4. Diagonal brace; 5. Anti-sinking plate; 6. Steel pile; 7. Lap core column; 8. Embedded core column; 9. Wedge block; 10. Transition cone pipe; 11. Temporary construction platform; 12. Main column; 13. Support leg; 14. Soil layer; 15. Bedrock layer.

具体实施方式Detailed ways

下面结合附图和具体实施方式对本发明作进一步详细的说明。The present invention will be described in further detail below with reference to the accompanying drawings and specific embodiments.

图1-2所示的一种海上风电嵌岩区风机基础,包括钢桩6,还包括导管架2、转换结构1、搭接芯柱7、嵌沿芯柱8;导管架2为多根,多根导管架通过水平撑或斜撑4固定连接;A fan foundation in an offshore wind power rock-socketed area shown in Figure 1-2 includes steel piles 6, jackets 2, transition structures 1, lapped core columns 7, and embedded core columns 8; the jackets 2 are multiple , a plurality of jackets are fixedly connected by horizontal braces or diagonal braces 4;

钢桩6插置于导管架2内,其上端通过连接板3与导管架2的上端相焊接;钢桩6的长度大于导管架2的长度,便于插置于嵌岩区内进行嵌岩作用;The steel pile 6 is inserted into the jacket 2, and its upper end is welded with the upper end of the jacket 2 through the connecting plate 3; the length of the steel pile 6 is greater than that of the jacket 2, which is convenient for being inserted into the rock-socketing area for rock-socketing effect ;

钢桩6的下端设置有搭接芯柱7;搭接芯柱7的下端设置有嵌沿芯柱8;转换结构1设置于导管架与钢桩的顶端,用于将导管架与风机塔筒相搭接。The lower end of the steel pile 6 is provided with a lapped core column 7; the lower end of the lapped core column 7 is provided with an embedded core column 8; overlap.

如图3所示,转换结构1包括主立柱12、支撑腿13、过渡锥管10;风机塔筒可设置于主立柱12的上端;钢桩6通过转换结构1与风机塔筒相连接。支撑腿13为多根,多根支撑腿沿主立柱12的外壁呈辐射状排列;支撑腿13的下端均固定设置有过渡锥管10;过渡锥管10的下端设置有锥尖结构,过渡锥管10通过锥尖结构插置于钢桩6的顶端。As shown in FIG. 3 , the conversion structure 1 includes a main column 12 , a support leg 13 , and a transition cone 10 ; the fan tower can be arranged on the upper end of the main column 12 ; the steel pile 6 is connected to the fan tower through the conversion structure 1 . There are multiple support legs 13, and the multiple support legs are arranged radially along the outer wall of the main column 12; the lower ends of the support legs 13 are fixedly provided with a transition cone tube 10; the lower end of the transition cone tube 10 is provided with a cone tip structure, and the transition cone The tube 10 is inserted into the top end of the steel pile 6 through the cone-tip structure.

搭接芯柱7、嵌沿芯柱8均以钢筋笼为骨架,内外浇筑混凝土而成型;搭接芯柱7设置于钢桩6的内部下端。Both the lapped core column 7 and the embedded core column 8 are formed by using a steel cage as a skeleton, and are formed by pouring concrete inside and outside;

导管架2的下端设置有防沉板5,用于防止安装过程中导管架因自重作用下沉降过大。The lower end of the jacket 2 is provided with an anti-sinking plate 5, which is used to prevent the jacket from sinking too much under the action of its own weight during the installation process.

如图4所示,导管架2的内壁上焊接设置有锲块9,只用于对钢桩6进行水平限位,而不传递竖向力和弯矩。As shown in FIG. 4 , a wedge block 9 is welded on the inner wall of the jacket 2 , which is only used to limit the horizontal position of the steel pile 6 without transmitting vertical force and bending moment.

导管架2与钢桩6的上端架设有临时施工平台11。A temporary construction platform 11 is erected on the upper ends of the jacket 2 and the steel pile 6 .

导管架2为直立式或斜式,为斜式时其斜度为7:1~12:1。The jacket 2 is of a vertical type or an oblique type, and when it is an oblique type, its inclination is 7:1 to 12:1.

一种海上风电嵌岩区风机基础的施工方法,包括以下步骤:A construction method for a wind turbine foundation in an offshore wind power rock-socketed area, comprising the following steps:

a、在陆上工厂车间对导管架2、钢桩6、转换结构1、临时施工平台11、搭接芯柱7和嵌沿芯柱8用钢筋笼预制成型;a. The jacket 2, the steel pile 6, the transition structure 1, the temporary construction platform 11, the lapped core column 7 and the embedded core column 8 are prefabricated with steel cages in the onshore factory workshop;

b、将导管架2下放至工作海域海床上,因有防沉板5的作用,导管架2的沉降得到有效控制,如图5所示;b. Lower the jacket 2 to the seabed of the working sea area. Due to the function of the anti-sinking plate 5, the settlement of the jacket 2 is effectively controlled, as shown in Figure 5;

c、进行打桩作业,将钢桩6穿过导管架2并打入至土层的底端,如图6所示;c. Carry out the piling operation, pass the steel pile 6 through the jacket 2 and drive it to the bottom end of the soil layer, as shown in Figure 6;

d、打桩完毕后,焊接连接板3,使得钢桩6与导管架2连接为一体;d. After the piling is completed, the connecting plate 3 is welded, so that the steel pile 6 is connected with the jacket 2 as a whole;

e、将钢桩6的顶端切割至平齐,然后安装钻孔嵌岩用临时施工平台11(图7所示),并在临时施工平台11上安装嵌岩设备;e, cut the top end of the steel pile 6 to be flush, then install the temporary construction platform 11 (shown in Figure 7) for drilling rock-socketed, and install the rock-socketing equipment on the temporary construction platform 11;

f、沿着钢桩6向土层下方的基岩层打孔,可多台钻机同时操作;打孔至预定深度后,沿钢桩6向基岩层及土层的孔内下放钢筋笼并浇铸混凝土,完成嵌岩作用(图8所示);f. Drill holes into the bedrock layer below the soil layer along the steel pile 6, and multiple drilling rigs can operate at the same time; after drilling to a predetermined depth, lower the reinforcement cage along the steel pile 6 to the hole in the bedrock layer and the soil layer and cast concrete , to complete the rock-socketing effect (as shown in Figure 8);

g、嵌岩施工完毕后,移除嵌岩设备及临时施工平台11(图9所示);g. After the rock-socketing construction is completed, remove the rock-socketing equipment and the temporary construction platform 11 (as shown in Figure 9);

h、安装转换结构1,完成风机基础施工(图10、图11所示)。h. Install the conversion structure 1 and complete the fan foundation construction (as shown in Figure 10 and Figure 11).

本发明与现有技术相比,具有以下优势:Compared with the prior art, the present invention has the following advantages:

1)相较于目前普遍的先打桩方式,本发明可以实现后打桩,也就是先安装导管架再打桩以及嵌岩,具有施工简单方便、周期短,避免水下作业的优点;1) Compared with the current common first piling method, the present invention can realize piling after, that is, install the jacket before piling and rock socketing, and has the advantages of simple and convenient construction, short cycle, and avoiding underwater operation;

2)所有的钢结构均在陆上工厂车间加工成型,大幅度避免了现场组装施工,显著节约了施工周期;2) All steel structures are processed and formed in the onshore factory workshop, which greatly avoids on-site assembly and construction, and significantly saves the construction period;

3)通过上部的转换结构实现导管架与风机塔筒之间的对接,且转换结构的下端具有锥尖结构,可在连接时起导向作用,焊接方便、操作简单;3) The connection between the jacket and the fan tower is realized through the upper conversion structure, and the lower end of the conversion structure has a cone-tip structure, which can play a guiding role during connection, and is convenient for welding and simple operation;

4)导管架与钢桩之间通过连接板焊接在一起,且导管架与钢桩之间设置有锲块,可实现对钢桩的水平限位,避免了传统的灌浆操作;4) The jacket and the steel pile are welded together by connecting plates, and a wedge block is arranged between the jacket and the steel pile, which can realize the horizontal limit of the steel pile and avoid the traditional grouting operation;

5)导管架的下端设置有防沉板,可在安装过程中,防止导管架因自重作用而下沉降过大的问题;5) The lower end of the jacket is provided with an anti-sinking plate, which can prevent the jacket from sinking too much due to its own weight during the installation process;

6)可在导管架的顶端设置临时施工平台进行嵌岩作用,减少了传统方法在海上搭设嵌岩平台的工作量;此外,嵌岩完成后,临时施工平台可拆除并转接转换结构,可重复利用。6) A temporary construction platform can be set at the top of the jacket for rock-socketing, which reduces the workload of setting up a rock-socketed platform at sea by traditional methods; in addition, after the rock-socketing is completed, the temporary construction platform can be removed and transferred reuse.

上述实施方式并非是对本发明的限制,本发明也并不仅限于上述举例,本技术领域的技术人员在本发明的技术方案范围内所做出的变化、改型、添加或替换,也均属于本发明的保护范围。The above-mentioned embodiments are not intended to limit the present invention, and the present invention is not limited to the above-mentioned examples. Changes, modifications, additions or replacements made by those skilled in the art within the scope of the technical solutions of the present invention also belong to the present invention. the scope of protection of the invention.

Claims (10)

1. a kind of embedding petrographic province blower foundation of offshore wind farm, including piling bar (6), it is characterised in that: further include jacket (2), conversion Structure (1) overlaps stem (7), is embedding along stem (8);The jacket (2) is more, and more jackets are by horizontal brace or tiltedly Support (4) is fixedly connected;
The piling bar (6) is inserted in jacket (2), and the upper end is mutually welded by connecting plate (3) and the upper end of jacket (2); The length of the piling bar (6) is greater than the length of jacket (2);
The lower end of the piling bar (6) is provided with overlap joint stem (7);The lower end of overlap joint stem (7) is provided with embedding along stem (8);The transformational structure (1) is set to the top of jacket and piling bar.
2. the embedding petrographic province blower foundation of offshore wind farm according to claim 1, it is characterised in that: transformational structure (1) packet Include head tree (12), supporting leg (13), transition Taper Pipe (10);The supporting leg (13) is more, and more supporting legs are along head tree (12) outer wall radially arranges;The lower end of the supporting leg (13) is fixedly installed transition Taper Pipe (10);The transition The lower end of Taper Pipe (10) is provided with cone structure, and transition Taper Pipe (10) is inserted in the top of piling bar (6) by cone structure.
3. the embedding petrographic province blower foundation of offshore wind farm according to claim 2, it is characterised in that: the piling bar (6) is by turning Structure (1) is changed to be connected with blower fan tower barrel.
4. the embedding petrographic province blower foundation of offshore wind farm according to claim 1 or 2, it is characterised in that: the overlap joint stem (7), it is embedding along stem (8) using steel reinforcement cage as skeleton, inside and outside casting concrete and form;The overlap joint stem (7) is set to steel The interior lower end of stake (6).
5. the embedding petrographic province blower foundation of offshore wind farm according to claim 4, it is characterised in that: under the jacket (2) End is provided with mud mat (5), for preventing jacket in installation process excessive because settling under Gravitative Loads.
6. the embedding petrographic province blower foundation of offshore wind farm according to claim 5, it is characterised in that: the jacket (2) it is interior Welding is provided with wedge (9) on wall, for carrying out Horizontal limiting to piling bar (6).
7. the embedding petrographic province blower foundation of offshore wind farm according to claim 6, it is characterised in that: the jacket (2) and steel The upper end frame of stake (6) is equipped with temporary construction platform (11).
8. the embedding petrographic province blower foundation of offshore wind farm according to claim 7, it is characterised in that: the jacket (2) is straight It is vertical.
9. the embedding petrographic province blower foundation of offshore wind farm according to claim 7, it is characterised in that: the jacket (2) is oblique Formula, gradient are 7:1~12:1.
10. a kind of construction method of the embedding petrographic province blower foundation of offshore wind farm as claimed in claim 7, it is characterised in that: described Method the following steps are included:
A, by land factory floor to jacket (2), piling bar (6), transformational structure (1), temporary construction platform (11), overlap joint stem (7) and it is embedding pre-formed with steel reinforcement cage along stem (8);
B, jacket (2) are transferred to working sea area sea bed, because playing the role of mud mat (5), the sedimentation of jacket (2) is obtained Effectively control;
C, piling work is carried out, piling bar (6) are passed through into jacket (2) and is squeezed into the bottom end of soil layer;
D, after piling, welded connecting plate (3), so that piling bar (6) is connected as one with jacket (2);
E, the top of piling bar (6) is cut to concordantly, then installation drills embedding rock with temporary construction platform (11), and applies temporarily Embedding rock equipment is installed on work platform (11);
F, along piling bar (6) to below soil layer horizon d punch, can more bench drill machines operate simultaneously;After punching to predetermined depth, Steel reinforcement cage and casting concrete are transferred into the hole of horizon d and soil layer along piling bar (6), completes embedding rock effect;
G, after embedding rock construction, embedding rock equipment and temporary construction platform (11) are removed;
H, transformational structure (1) is installed, completes blower foundation construction.
CN201910274592.9A 2019-04-08 2019-04-08 A kind of embedding petrographic province blower foundation of offshore wind farm and construction method Pending CN109930624A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910274592.9A CN109930624A (en) 2019-04-08 2019-04-08 A kind of embedding petrographic province blower foundation of offshore wind farm and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910274592.9A CN109930624A (en) 2019-04-08 2019-04-08 A kind of embedding petrographic province blower foundation of offshore wind farm and construction method

Publications (1)

Publication Number Publication Date
CN109930624A true CN109930624A (en) 2019-06-25

Family

ID=66989453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910274592.9A Pending CN109930624A (en) 2019-04-08 2019-04-08 A kind of embedding petrographic province blower foundation of offshore wind farm and construction method

Country Status (1)

Country Link
CN (1) CN109930624A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364496A (en) * 2020-03-25 2020-07-03 上海勘测设计研究院有限公司 Jacket rotary pile foundation structure and construction method thereof
CN112112182A (en) * 2020-08-14 2020-12-22 海洋石油工程股份有限公司 Jacket platform
CN117868074A (en) * 2024-03-12 2024-04-12 海南利策新能科技有限公司 Split jacket

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1676758A (en) * 2004-04-02 2005-10-05 上海市基础工程公司 Tremie frame for marine bridge construction and platform construction process of tremie frame method
CN103277262A (en) * 2013-04-27 2013-09-04 广东明阳风电产业集团有限公司 An offshore wind turbine foundation structure
CN104099917A (en) * 2014-08-07 2014-10-15 熊翱 Multilayer multi-foot frame structure and construction method thereof
CN206503157U (en) * 2017-02-28 2017-09-19 中国电力工程顾问集团华北电力设计院有限公司 The embedding rock mixing pile foundation of offshore wind farm
CN209779672U (en) * 2019-04-08 2019-12-13 龙源(北京)风电工程设计咨询有限公司 Offshore wind power rock-socketed area fan foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1676758A (en) * 2004-04-02 2005-10-05 上海市基础工程公司 Tremie frame for marine bridge construction and platform construction process of tremie frame method
CN103277262A (en) * 2013-04-27 2013-09-04 广东明阳风电产业集团有限公司 An offshore wind turbine foundation structure
CN104099917A (en) * 2014-08-07 2014-10-15 熊翱 Multilayer multi-foot frame structure and construction method thereof
CN206503157U (en) * 2017-02-28 2017-09-19 中国电力工程顾问集团华北电力设计院有限公司 The embedding rock mixing pile foundation of offshore wind farm
CN209779672U (en) * 2019-04-08 2019-12-13 龙源(北京)风电工程设计咨询有限公司 Offshore wind power rock-socketed area fan foundation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李亚军等: "海上风电嵌岩区风机基础比选原则及依据", 南方能源建设, vol. 5, no. 4, 25 December 2018 (2018-12-25), pages 1 - 2 *
李春等: "现代大型风力机设计原理", 31 January 2013, 上海科学技术出版社, pages: 2 - 3 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364496A (en) * 2020-03-25 2020-07-03 上海勘测设计研究院有限公司 Jacket rotary pile foundation structure and construction method thereof
CN112112182A (en) * 2020-08-14 2020-12-22 海洋石油工程股份有限公司 Jacket platform
CN117868074A (en) * 2024-03-12 2024-04-12 海南利策新能科技有限公司 Split jacket
CN117868074B (en) * 2024-03-12 2024-09-24 海南利策新能科技有限公司 Split jacket

Similar Documents

Publication Publication Date Title
CN102906339B (en) Auxiliary equipment stake is arranged in sea bed, offshore foundation structure and set up the method for offshore foundation
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
JP5278828B2 (en) How to install the jacket
CN109469089B (en) An internally inserted offshore wind power conductor frame foundation with self-contained pile stabilizing casing and construction method
CN110331936B (en) Combined drilling bottom-expanding pile-planting construction method
CN109930624A (en) A kind of embedding petrographic province blower foundation of offshore wind farm and construction method
DK2700750T3 (en) Pile FOR OFFSHORE STRUCTURES AND METHOD FOR CONSTRUCTION OF A pile FOR OFFSHORE STRUCTURES
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN105421445A (en) Construction method for non-prestressed centrifugal high-strength concrete pile planted pile
CN110359476A (en) A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN110273413A (en) A kind of efficient construction method of prefabricated pile
CN102286982A (en) Deep foundation pit precast building enclosure for constructing in low environment
CN115262614A (en) Embedded rock-socketed pile foundation and construction method
CN112878363B (en) Construction method for post-pile-filling of existing basement structure
CN210395407U (en) Anchor rod gravity type offshore wind power foundation
CN205116168U (en) End grout static pressure tubular pile construction equipment is expanded in drilling
CN209779672U (en) Offshore wind power rock-socketed area fan foundation
CN216428321U (en) A cartridge type fan foundation structure and wind generating set for collapsible loess area
CN107237342A (en) New low pile cap foundation structure and its construction method
CN219411005U (en) Reinforcing apparatus of single pile basis
CN116537248A (en) Transmission line straight-inclined combined tree root-shaped spiral anchor foundation
CN207193962U (en) A kind of overhead transmission line concrete precast pipe pile is implanted into pile-driving system
CN105239575A (en) Construction device and construction method of bored cast-in-place static pressure pipe pile with enlarged bottom
CN105926582B (en) Prefabricated hollow component underground tunneling construction assembly, diaphragm wall and construction method
CN214423184U (en) Be applied to hasp steel-pipe pile cofferdam under water level variation condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190625

RJ01 Rejection of invention patent application after publication