[go: up one dir, main page]

CN109838087A - Reusable assembled architecture support device - Google Patents

Reusable assembled architecture support device Download PDF

Info

Publication number
CN109838087A
CN109838087A CN201910261714.0A CN201910261714A CN109838087A CN 109838087 A CN109838087 A CN 109838087A CN 201910261714 A CN201910261714 A CN 201910261714A CN 109838087 A CN109838087 A CN 109838087A
Authority
CN
China
Prior art keywords
precast beam
bracing members
steel
fixed
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910261714.0A
Other languages
Chinese (zh)
Other versions
CN109838087B (en
Inventor
丁怡
马跃红
翟晨阳
沈洪权
岳晨曦
从卫民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huaiyin Construction Engineering Group Co Ltd
Original Assignee
Jiangsu Huaiyin Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huaiyin Construction Engineering Group Co Ltd filed Critical Jiangsu Huaiyin Construction Engineering Group Co Ltd
Priority to CN201910261714.0A priority Critical patent/CN109838087B/en
Publication of CN109838087A publication Critical patent/CN109838087A/en
Application granted granted Critical
Publication of CN109838087B publication Critical patent/CN109838087B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to building fields, disclose a kind of reusable assembled architecture support device, and including precast beam (1) and two groups of supporting mechanisms in the precast beam (1) front and rear sides are arranged;It include a steel strand cable (2), two retaining mechanisms (3) and at least one bracing members (4) in supporting mechanism described in every group, each bracing members (4) are each attached to a middle side part of the precast beam (1), the both ends of the steel strand cable (2) pass through two retaining mechanisms (3) respectively and are locked in the side both ends middle and upper part of the precast beam (1), and the middle part of the steel strand cable (2) is effectively contacted with the bottom of each bracing members (4).The present invention forms overall structure using the connection of component, few to reduce the usage amount of scaffold, effective lifting construction speed, and reuse with or without vertical support, reduces building cost.

Description

Reusable assembled architecture support device
Technical field
The present invention relates to building field, in particular to a kind of reusable assembled architecture support device.
Background technique
Country greatly develops assembled architecture at present, and prefabricated components needed for engineering produce completion in factory floor in advance, Prefabricated components are transported to building site installation again until needing, the operation that disturbs residents of a large amount of strong noise, high pollution has been moved to factory Workshop is hung oneself from a beam by mechanical work lifting, hanging column, is mounted to overall structure.
Currently, prefabricated member is generally prefabricated post, precast beam, superimposed sheet, precast stair plate etc., precast beam 1 is fixed on 5 top of prefabricated post, 11 level of superimposed sheet are layered on precast beam 1, are supported below superimposed sheet 11 by a large amount of scaffold 13, then The cast-in-place concrete 12 on superimposed sheet 11 again makes superimposed sheet 11 and cast-in-place concrete 12 form entirety, as shown in Figure 1.
On the one hand this mounting means is needed using a large amount of scaffold 13, building for scaffold 13 is more time-consuming, Both uneconomical, do not achieve the purpose that succinctly to construct, speed of application is fast unlike cast-in-place yet.
Summary of the invention
Goal of the invention: aiming at the problems existing in the prior art, the present invention provides a kind of reusable assembled and builds Support device is built, forms overall structure using the connection of component, it is few to reduce the usage amount of scaffold with or without vertical support, Effective lifting construction speed, and can reuse, reduce building cost.
Technical solution: the present invention provides a kind of reusable assembled architecture support device, including precast beam and Two groups of supporting mechanisms of the precast beam front and rear sides are set;It include steel strand cable, two in supporting mechanism described in every group A retaining mechanism and at least one bracing members, each bracing members are each attached to a middle side part of the precast beam, the steel The both ends of strand cable pass through two retaining mechanisms respectively and are locked in the side both ends middle and upper part of the precast beam, the steel The middle part of strand cable is effectively contacted with the bottom of each bracing members.
It preferably, include pedestal, steel plate and anchor clamp in the retaining mechanism, the pedestal is fixed on the precast beam One side end, the steel plate are fixed on the base vertically, and the anchor clamp is close to the steel plate close to the prefabricated beam-ends The side in portion is fixed on the base, and offers the locking passed through for steel strand cable on the steel plate and the anchor clamp Through-hole.The both ends of steel strand cable are each passed through the steel plate at precast beam both ends and the locking through-hole of anchor clamp, clamp anchor by anchor clamp Gu if desired adjust the stretching force on steel strand cable, then opening on the steel strand cable of precast beam two sides is adjusted in synchronism by anchoring piece Pulling force keeps the stretching force on the steel strand cable of two sides equal, the present apparatus is made to reach best support effect.
Further, the side in the steel plate far from the prefabricated beam end, the locking through-hole two sides are also solid respectively Surely there is limited block.The setting of limited block can guarantee that the angular range between the both ends and precast beam of steel strand cable is certain, angle mistake It is big or it is too small it cannot be guaranteed that steel strand cable to bracing members have enough towing force vertically upward, the invention mesh of the present apparatus is not achieved 's.
Preferably, the top of each bracing members is vertically fixed on the side middle and upper part of the precast beam, and bottom is Arc groove structure.The arc groove structure of bracing members bottom can limit steel strand cable in the circular arc groove, effectively prevent steel Strand cable falls off with bracing members bottom, has the function of towing force vertically upward to guarantee steel strand cable to bracing members.
Preferably, each bracing members are steel bolt, and each bracing members are horizontally fixed in the precast beam Portion, and each bracing members are vertical with the precast beam.
Preferably, each bracing members are made of fixed block and pulley, and the fixed block is fixed on the precast beam Side middle and upper part, the pulley rotation are connected to the fixed block bottom, and the steel strand cable is effectively contacted with the pulley.Pulley Setting convenient for by anchoring piece adjusting steel strand cable on stretching force.
Further, the reusable assembled architecture support device further includes prefabricated post, and the two of precast beam End is fixed at the top of the prefabricated post of landing by the first steel square.Prefabricated post is for being made precast beam.
Preferably, the quantity of the bracing members is odd number, and the spacing between each bracing members is equal, is located at interposition The bottom position for the bracing members set is minimum, and each bracing members are symmetrical.Since the middle part of precast beam is most easily by top Pressure damages deformation by pressure, so arranging each bracing members in the manner described above in the present apparatus, enables to the steel branch in most middle position Born pressure maximum is supportted, the bending resistance in precast beam middle position section is increased, is then extended from most intermediate to two sides, two Each bracing members in side are symmetrical to two sides as basic point using intermediate bracing members, and the pressure being more advantageous on dispersion precast beam extends The service life of the present apparatus.
The utility model has the advantages that in the present invention, after applying stretching force to steel strand cable from the both ends of precast beam by retaining mechanism, steel Strand cable has towing force vertically upward to the bottom of bracing members, can substitute the scaffold being located at below precast beam originally completely Vertical support power improves the bearing capacity of precast beam, and whole load on precast beam can pass through the interim of precast beam and prefabricated post Tie point is all transmitted to ground from prefabricated post;
As it can be seen that the present apparatus compared with prior art, has the advantage that
(1) present apparatus can form overall structure using the connection of component, few with or without vertical support, reduce making for scaffold Dosage, effective lifting construction speed;
(2) present apparatus can be convenient and efficient with standardized production, modularization installation;
(3) after the present apparatus is installed in building site, on beam superimposed sheet and precast beam and prefabricated Column border node pour smash completion maintenance after, shape The overall structure of Cheng Xin, steel strand cable can unload at this time, and bracing members are removed, and steel strand cable and bracing members can be transferred to one layer again Construction, it is seen that the present apparatus can be reused, and building cost is effectively reduced.
Detailed description of the invention
Fig. 1 is the schematic diagram of building-supporting device in the prior art;
Fig. 2 is the schematic diagram of reusable assembled architecture support device in embodiment of the present invention 1;
Fig. 3 is the top view of Fig. 2;
Fig. 4 is the structural schematic diagram of retaining mechanism;
Fig. 5 is the sectional view of bracing members;
Fig. 6 is the top view after superimposed sheet is placed in the present apparatus;
Fig. 7 is the schematic diagram of reusable assembled architecture support device in embodiment of the present invention 2;
Fig. 8 is the schematic diagram of reusable assembled architecture support device in embodiment of the present invention 3;
Fig. 9 is the top view of Fig. 8.
Specific embodiment
The present invention is described in detail with reference to the accompanying drawing.
Embodiment 1:
Present embodiments provide for a kind of reusable assembled architecture support devices, as shown in Figures 2 and 3, mainly by pre- Column 5, precast beam 1 and two groups of supporting mechanism compositions processed, the bottom of prefabricated post 5 is fixed on base for post 7, and prefabricated post 5 is relatively interior two-by-two Upper lateral part is fixed with the first steel square 6, and precast beam 1 is placed on the first steel square 6 between prefabricated post 5 two-by-two, two groups of supports Mechanism is separately positioned on the front and rear sides of precast beam 1;Every group of supporting mechanism by 2, two retaining mechanisms 3 of a steel strand cable and Three bottoms are that the bracing members 4 of arc groove structure form, and the top of each bracing members 4 is vertically fixed on the side of precast beam 1 Middle and upper part, bottom is hanging, and the spacing between each bracing members 4 is equal, and the bottom position of centrally located bracing members 4 is most It is low, and each bracing members 4 are that basic point is symmetrical to two sides with intermediate bracing members 4.
Two retaining mechanisms 3 are separately fixed at the side both ends middle and upper part of precast beam 1;Such as Fig. 4, retaining mechanism 3 mainly by Pedestal 301, steel plate 302 and anchor clamp 303 form, and pedestal 301 is fixed on a side end of precast beam 1, and steel plate 302 is fixed vertically On pedestal 301, and steel plate 302 is arranged diagonally downward with respect to precast beam 1, and anchor clamp 303 is close to steel plate 302 close to precast beam 1 The side of end is fixed on pedestal 301, and offers the locking passed through for steel strand cable 2 on steel plate 302 and anchor clamp 303 Through-hole 304 is also respectively fixed with limited block 305 in side, locking through-hole 304 two sides of the steel plate 302 far from 1 end of precast beam;
The both ends of steel strand cable 2 are respectively by passing through the locking through-hole 304 on two sides retaining mechanism light plate 302 and anchor clamp 303 Afterwards, the side both ends middle and upper part of precast beam 1 is fixed on by anchor clamp 303, middle part each section of steel strand cable 2 is located at each bracing members 4 bottom arc groove 401(such as Fig. 5) in and effectively contact with it.
Above-mentioned apparatus is installed in the following manner:
After the completion of base for post 7, prefabricated post 5 is lifted in place, slip casting hole location is adjusted, prefabricated post 5 and 7 junction slip casting of base for post are supported Shield makes base for post 7 and prefabricated post 5 form overall structure, when prefabricated post 5 is prefabricated, at the top of prefabricated post 5 by prefabricated post 5 with it is prefabricated 1 junction prepared screw-bolt hole 8 of beam, for wearing bolt 9 for the side for being fixed on prefabricated post 5 on one side of the first steel square 6, with can The support precast beam 1 on the another side of the first steel square 6.
When precast beam 1 is prefabricated, lateral duct is reserved in two side ends position thereon, for wearing bolt with fixing and locking mechanism 3 Pedestal 301;1 middle part lower edge of precast beam is reserved to be equally spaced symmetrically arranged three reserved lateral ducts, for passing through spiral shell Tether the top for connecing bracing members 4;Lateral duct is also equidistantly reserved in the front and rear sides middle and upper part of precast beam 1, for passing through spiral shell The one side for connecing the second steel square 10 is tethered, with the support superimposed sheet 11 on the other end of the second steel square 10, pays attention to the second right angle The upper surface of steel 10 is flushed with the upper surface of precast beam 1.
After the completion of precast beam 1 is prefabricated, the second steel square 10 is fixed on to the cross of 1 front and back side middle and upper part of precast beam using bolt To duct position, two pairs of four retaining mechanisms 3 are separately fixed at the reserved cross in its front and rear sides end middle and upper part using bolt To duct position, at this point, being in an acute angle theta diagonally downward between the steel plate 302 in retaining mechanism 3 and precast beam 1, then by two The both ends of root steel strand cable 2 are each passed through the locking through-hole 304 in two pairs of retaining mechanisms 3, and adjustment 2 medium position of steel strand cable makes its position It is effectively contacted in the bottom arc groove of each bracing members 4 and with it, then the tensioning force request needed on steel strand cable 2, The stretching force being adjusted in synchronism by anchor clamp 303 on the steel strand cable 2 of 1 two sides of precast beam, when adjusting stretching force, the two of steel strand cable 2 Angle theta between end and precast beam 1 will receive the limitation of two pieces of limited blocks 305 on steel plate 302, to guarantee that stretching force is enough;It adjusts The both ends of steel strand cable 2 are fixedly clamped by anchor clamp 303 after section end.
Then above-mentioned assembled precast beam 1 is placed on the first steel square 6 between prefabricated post 5 two-by-two, will be overlapped Plate 11 is placed into 10 upper surface of the second steel square between precast beam 1 two-by-two, at this time the lower surface of superimposed sheet 11 and precast beam 1 Upper surface flushes, such as Fig. 6, finally between 11 top of superimposed sheet, superimposed sheet 11 and precast beam 1 node and prefabricated post 5 with Node disturbing concrete 12 between precast beam 1 is completed maintenance, after forming new overall structure, steel strand cable 2 is unloaded, steel branch Support 4 and the second steel square 10 for being used to support superimposed sheet 11 are removed, 4 He of bracing members after steel strand cable 2 and dismounting after unloading Superimposed sheet 11 can be transferred to one layer of construction again, with recycling.
Embodiment 2:
Present embodiment is roughly the same with embodiment 1, and the main distinction is, in the present embodiment, such as Fig. 7, each bracing members 4 It is made of fixed block 401 and pulley 402, fixed block 401 is fixed on the side of precast beam 1 vertically, and pulley 402 is rotatably connected on solid Determine 401 bottom of block, each fulcrum in the middle part of steel strand cable 2 effectively contacts respectively with each pulley 402.The setting of pulley 402 easily facilitates The stretching force on steel strand cable 2 is adjusted by anchoring piece 303.In addition to this, present embodiment is identical with embodiment 1, this Place does not repeat them here.
Embodiment 3:
Present embodiment is roughly the same with embodiment 1, and the main distinction is, in the present embodiment, such as Fig. 8 and 9, each steel branch Support 4 is steel bolt, and each bracing members 4 are horizontally fixed on the middle part of precast beam 1, and each bracing members 4 are vertical with precast beam 1.
In addition to this, present embodiment is identical with embodiment 1, is not repeated herein.
The technical concepts and features of above embodiment only to illustrate the invention, its object is to allow be familiar with technique People cans understand the content of the present invention and implement it accordingly, and it is not intended to limit the scope of the present invention.It is all according to the present invention The equivalent transformation or modification that Spirit Essence is done, should be covered by the protection scope of the present invention.

Claims (8)

1. a kind of reusable assembled architecture support device, which is characterized in that including precast beam (1) and be arranged described Two groups of supporting mechanisms of precast beam (1) front and rear sides;It include a steel strand cable (2), two locks in supporting mechanism described in every group Tight mechanism (3) and at least one bracing members (4), each bracing members (4) are each attached in the side of the precast beam (1) Portion, the both ends of the steel strand cable (2) pass through two retaining mechanisms (3) respectively and are locked the one of the precast beam (1) Side both ends middle and upper part, the middle part of the steel strand cable (2) are effectively contacted with the bottom of each bracing members (4).
2. reusable assembled architecture support device according to claim 1, which is characterized in that the locking machine It include that pedestal (301), steel plate (302) and anchor clamp (303), the pedestal (301) are fixed on the precast beam (1) in structure (3) A side end, the steel plate (302) is fixed on vertically on the pedestal (301), and the anchor clamp (303) is close to the steel plate (302) side close to the precast beam (1) end is fixed on the pedestal (301), and the steel plate (302) and the anchor The locking through-hole (304) passed through for steel strand cable (2) is offered on fixture (303).
3. reusable assembled architecture support device according to claim 2, which is characterized in that in the steel plate (302) side, locking through-hole (304) two sides far from the precast beam (1) end are also respectively fixed with limited block (305).
4. reusable assembled architecture support device according to claim 1, which is characterized in that each steel branch The top of support (4) is vertically fixed on the side middle and upper part of the precast beam (1), and bottom is arc groove structure.
5. reusable assembled architecture support device according to claim 1, which is characterized in that each steel branch Supportting (4) is equal steel bolt, and each bracing members (4) are horizontally fixed on the middle part of the precast beam (1), and each bracing members (4) vertical with the precast beam (1).
6. reusable assembled architecture support device according to claim 1, which is characterized in that each steel branch Support (4) is made of fixed block (401) and pulley (402), and the fixed block (401) is fixed on the side of the precast beam (1) Middle and upper part, the pulley (402) are rotatably connected on the fixed block (401) bottom, the steel strand cable (2) and the pulley (402) effectively contact.
7. reusable assembled architecture support device according to any one of claim 1 to 6, feature exist In further including prefabricated post (5), the both ends of the precast beam (1) are fixed on the prefabricated post of landing by the first steel square (6) (5) top.
8. reusable assembled architecture support device according to any one of claim 1 to 6, feature exist In the quantity of the bracing members (4) is odd number, equal, the centrally located steel of the spacing between each bracing members (4) Support the bottom position of (4) minimum, and each bracing members (4) are symmetrical.
CN201910261714.0A 2019-04-02 2019-04-02 Reusable assembled building supporting device Active CN109838087B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910261714.0A CN109838087B (en) 2019-04-02 2019-04-02 Reusable assembled building supporting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910261714.0A CN109838087B (en) 2019-04-02 2019-04-02 Reusable assembled building supporting device

Publications (2)

Publication Number Publication Date
CN109838087A true CN109838087A (en) 2019-06-04
CN109838087B CN109838087B (en) 2024-04-19

Family

ID=66886741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910261714.0A Active CN109838087B (en) 2019-04-02 2019-04-02 Reusable assembled building supporting device

Country Status (1)

Country Link
CN (1) CN109838087B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851869A (en) * 2020-08-14 2020-10-30 北京京诚华宇建筑设计研究院有限公司 Prestressed prefabricated roof panel
CN112227705A (en) * 2020-09-29 2021-01-15 浙江绿筑集成科技有限公司 Floor slab supporting method using tensioning strings

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050061435A (en) * 2005-06-01 2005-06-22 김기태 The cross-lined steel wire rope support and the reinforcement method of construction using of the cross-lined steel wire rope support
KR20060003972A (en) * 2004-07-05 2006-01-12 강신량 Beam and girder reinforcement method using external post tension method and apparatus used in it
CN102677909A (en) * 2012-05-15 2012-09-19 东南大学 Tool type support for mounting composite slabs
CN104452775A (en) * 2014-11-26 2015-03-25 江苏鸿基科技有限公司 Prestress support used for foundation pit and construction method
CN105781012A (en) * 2016-05-12 2016-07-20 中建八局第建设有限公司 Steel box girder external prestressed construction technology of civil building
CN105839914A (en) * 2016-06-01 2016-08-10 成都建筑工程集团总公司 Adjustable steel beam supporting device and adjustable steel beam supporting system
CN205777531U (en) * 2016-05-31 2016-12-07 上海宝冶集团有限公司 Floor slab construction beam string shuttering supporting equipment
CN106499175A (en) * 2017-01-04 2017-03-15 中冶建工集团有限公司 A kind of self-locking steel twisted wire pours bracing frame and its installation and application
CN108708498A (en) * 2018-07-09 2018-10-26 上海建工集团股份有限公司 A kind of external prestressing strengthening concrete frame beam structure and its construction method
CN209837671U (en) * 2019-04-02 2019-12-24 丁怡 Repeatedly-usable assembled building supporting device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060003972A (en) * 2004-07-05 2006-01-12 강신량 Beam and girder reinforcement method using external post tension method and apparatus used in it
KR20050061435A (en) * 2005-06-01 2005-06-22 김기태 The cross-lined steel wire rope support and the reinforcement method of construction using of the cross-lined steel wire rope support
CN102677909A (en) * 2012-05-15 2012-09-19 东南大学 Tool type support for mounting composite slabs
CN104452775A (en) * 2014-11-26 2015-03-25 江苏鸿基科技有限公司 Prestress support used for foundation pit and construction method
CN105781012A (en) * 2016-05-12 2016-07-20 中建八局第建设有限公司 Steel box girder external prestressed construction technology of civil building
CN205777531U (en) * 2016-05-31 2016-12-07 上海宝冶集团有限公司 Floor slab construction beam string shuttering supporting equipment
CN105839914A (en) * 2016-06-01 2016-08-10 成都建筑工程集团总公司 Adjustable steel beam supporting device and adjustable steel beam supporting system
CN106499175A (en) * 2017-01-04 2017-03-15 中冶建工集团有限公司 A kind of self-locking steel twisted wire pours bracing frame and its installation and application
CN108708498A (en) * 2018-07-09 2018-10-26 上海建工集团股份有限公司 A kind of external prestressing strengthening concrete frame beam structure and its construction method
CN209837671U (en) * 2019-04-02 2019-12-24 丁怡 Repeatedly-usable assembled building supporting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851869A (en) * 2020-08-14 2020-10-30 北京京诚华宇建筑设计研究院有限公司 Prestressed prefabricated roof panel
CN112227705A (en) * 2020-09-29 2021-01-15 浙江绿筑集成科技有限公司 Floor slab supporting method using tensioning strings
CN112227705B (en) * 2020-09-29 2022-04-01 浙江绿筑集成科技有限公司 Floor slab supporting method using tensioning strings

Also Published As

Publication number Publication date
CN109838087B (en) 2024-04-19

Similar Documents

Publication Publication Date Title
CN106120559A (en) A kind of bridge limited bracket construction method and bridge
CN107355037A (en) Assembling type steel structure builds self-bearing type steel truss form bracing system and construction method
CN105569242A (en) Assembling method for composite floor slabs
CN105544762A (en) Method for installing seismic isolation layer
CN109838087A (en) Reusable assembled architecture support device
CN202658590U (en) Integral assembled drilling platform
CN208830444U (en) Inspection shaft steel combined template
KR100529517B1 (en) Method for pulling up equally the upper structure of a bridge using a raising bracket supporting load dispersedly, having a displacement measuring instrument
CN110670734A (en) Fixing device for pre-buried steel plate under shock insulation support and construction method thereof
CN213328682U (en) Mounting structure suitable for heavy scattered cable saddle
CN105480842B (en) Equipment support beam and its construction method are poured after one kind
CN109989590B (en) Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam
CN113737661B (en) Construction method for steel-concrete combined section of tower base of cable-stayed bridge
CN112412152B (en) Construction method of underslung derrick-free variable-section rectangular chimney support system
CN117661852A (en) Group holding pole type electric lifting device and installation method of storage tank barrel plate
CN211647357U (en) Tool type chute
CN108385710B (en) Reusable tower foundation and installation method thereof
CN110644510B (en) Construction method of pier steel cofferdam
CN202273243U (en) Adjustable height type pole and tower foundation
KR100452495B1 (en) The support and pulling up method using support and pulling up bracket for bridge up structure repair and reinforcement pulling up apparatus, and this
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN111751069A (en) Mounting device and mounting method for embedded panel of vertical actuator of vibrating table
CN205257759U (en) After water equipment support roof beam
CN216971846U (en) Deep foundation pit circulating water pipeline installing support frame
CN219430545U (en) Operation platform for utilizing stiffness framework for tower column head section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ding Yi

Inventor after: Ma Yuehong

Inventor after: Zhai Chenyang

Inventor after: Shen Hongquan

Inventor after: Yue Chenxi

Inventor after: Cong Weimin

Inventor before: Ding Yi

Inventor before: Ma Yuehong

Inventor before: Zhai Chenyang

Inventor before: Shen Hongquan

Inventor before: Yue Chenxi

Inventor before: Cong Weimin

GR01 Patent grant
GR01 Patent grant