CN109723414A - A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs - Google Patents

A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs Download PDF

Info

Publication number
CN109723414A
CN109723414A CN201910084349.0A CN201910084349A CN109723414A CN 109723414 A CN109723414 A CN 109723414A CN 201910084349 A CN201910084349 A CN 201910084349A CN 109723414 A CN109723414 A CN 109723414A
Authority
CN
China
Prior art keywords
water injection
fracture
injection pressure
anticline
critical water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910084349.0A
Other languages
Chinese (zh)
Inventor
冯阵东
史淑珍
魏国营
贾天让
闫江伟
刘擎
李宝林
孙绍栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201910084349.0A priority Critical patent/CN109723414A/en
Publication of CN109723414A publication Critical patent/CN109723414A/en
Pending legal-status Critical Current

Links

Landscapes

  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

本发明公开了一种背斜油气藏裂缝型储层临界注水压力计算方法。在考虑井点裂缝走向、充填程度统计的基础上,建立了裂缝重新破裂与注水压力的模型;通过分构造部位统计井点地应力,确定了背斜高点和两翼油水边界之间注水压力的范围;对于局部裂缝相对密集地区,比较压裂井点最小破裂压力与背斜高点临界注水压力的关系,提出不同条件下计算裂缝密集带临界注水压力的方法;对于背斜构造局部,多期构造应力叠加、裂缝走向杂乱的地区,提出确定裂缝端点应力偏差方法,计算任意走向裂缝突破压力基础上确定该地区临界注水压力。The invention discloses a method for calculating the critical water injection pressure of a fractured reservoir of an anticline oil and gas reservoir. Based on the statistics of fracture trend and filling degree at the well point, a model of fracture re-fracture and water injection pressure is established. By calculating the in-situ stress of the well point according to the structural position, the water injection pressure between the high point of the anticline and the oil-water boundary of the two flanks is determined. For areas with relatively dense local fractures, compare the relationship between the minimum fracture pressure at the fracturing well point and the critical water injection pressure at the high point of the anticline, and propose a method for calculating the critical water injection pressure in the fracture-intensive zone under different conditions; For areas where tectonic stress is superimposed and fracture strikes are disordered, a method for determining the stress deviation of fracture endpoints is proposed, and the critical water injection pressure in this area is determined based on the calculation of the breakthrough pressure of fractures of any strike.

Description

A kind of critical water injection pressure calculation method of oil-gas anticlinal deposits crack elimination
Technical field
The present invention relates to a kind of oil-gas field development field, specifically a kind of critical water filling pressure of oil-gas anticlinal deposits crack elimination Power calculation method.
Background technique
During oil extraction in oil field, by disposing between water injection well and producing well according to certain rule, stratum can be kept The recovery ratio in oil field is improved while pressure, biggish water injection pressure can improve the efficiency of oil recovery in a short time.However, part oil Slit band is extremely developed in the reservoir of field, and after water injection pressure reach a certain height, crack may as the natural plane of weakness of rock It opens, causes injection water along slit band quickly through reducing sweep efficiency, cause producing well High water cut in a short time.Therefore, It determines reasonable water injection pressure, recovery ratio can be improved to greatest extent.The present invention proposes a kind of oil-gas anticlinal deposits crack elimination Critical water injection pressure calculation method.
Summary of the invention
The purpose of the present invention is to provide a kind of critical water injection pressure calculation methods of oil-gas anticlinal deposits crack elimination, with solution Certainly the problems mentioned above in the background art.
To achieve the above object, the invention provides the following technical scheme:
A kind of critical water injection pressure calculation method of oil-gas anticlinal deposits crack elimination comprising the steps of:
A, it on the basis of considering well point fracture strike, filling operation statistics, establishes crack and ruptures again and water injection pressure Model;
B, by dividing tectonic position to count well point crustal stress, it is determined that fill the water pressure between anticlinal high and both wings oils water boundary The range of power;
C, for local cracks with respect to dense region, comparison pressure break well point minimum burst pressure and the critical water filling of anticlinal high The relationship of pressure;
D, the method for proposing to calculate dense band critical water injection pressure in crack under different condition;
E, for anticline, locally more phase tectonic stresses are superimposed, and fracture strike is regional in a jumble, propose to determine crack endpoint stress Deviation approach and any method for moving towards crack breakthrough pressure of calculating, and determine the critical water injection pressures in these areas.
As further technical solution of the present invention: the step B is specifically: divide tectonic position statistics well point now most Minor principal stress, maximum principal stress, and the critical water injection pressure near anticlinal high and alar part oils water boundary is calculated, determine anticlinal belt The distribution of critical water injection pressure.
As further technical solution of the present invention: in the step C: the critical water injection pressure of comparison anticlinal high and well point Pressure minimum burst pressure relationship, the method for determining the critical water injection pressure in crack compact district under different condition, and safe guarantor is set Protect threshold value.
As further technical solution of the present invention: the safeguard protection threshold value is 5MPa.
As further technical solution of the present invention: the step D is specifically: the crustal stress for calculating crack compact district is inclined Difference determines the calculation method of the mixed and disorderly critical water injection pressure in area of more phase Stress superpositions, fracture strike.
As further technical solution of the present invention: the model in step A includes: crack elimination water filling critical pressure meter It is infused when calculation, anticlinal oil pool fracture reservoir water injection pressure calculate, dense band critical water injection pressure in crack calculates and fracture strike is mixed and disorderly Water pressure calculation.
As further technical solution of the present invention: the critical condition of gash fracture are as follows: Δ Ρ=σf, σfIt is broken for slit band Resistance to spalling, it is related with the Filling Characteristics in crack;Δ Ρ is that fracture surface eliminates the tensile residual stresses after skeleton pressure.
Compared with prior art, the beneficial effects of the present invention are: the present invention is considering well point fracture strike, filling operation system On the basis of meter, establishes crack and rupture again and the model of water injection pressure;By dividing tectonic position to count well point crustal stress, really The range of water injection pressure between anticlinal high and both wings oils water boundary is determined;For local cracks with respect to dense region, compare pressure The relationship of well point minimum burst pressure Yu the critical water injection pressure of anticlinal high is split, proposes that calculating crack dense band under different condition faces The method of boundary's water injection pressure;For arch structure part, the mixed and disorderly area of more phase tectonic stress superpositions, fracture strike is proposed true Determine crack endpoint stress-deviation method, calculates any determining critical water injection pressure in this area on the basis of moving towards crack breakthrough pressure.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
Embodiment 1: a kind of critical water injection pressure calculation method of oil-gas anticlinal deposits crack elimination, this method are considering well point On the basis of fracture strike, filling operation statistics, establishes crack and rupture again and the model of water injection pressure;By dividing formations Position statistics well point crustal stress, it is determined that the range of water injection pressure between anticlinal high and both wings oils water boundary;For local cracks Opposite dense region, compares the relationship of pressure break well point minimum burst pressure and the critical water injection pressure of anticlinal high, proposes different items The method of the critical water injection pressure of crack dense band is calculated under part;For anticline, locally more phase tectonic stress superpositions, fracture strike are miscellaneous Disorderly area proposes to determine crack endpoint stress-deviation method and calculates any method for moving towards crack breakthrough pressure, and determined The critical water injection pressure in these areas.
Specific as follows: 1. crack eliminations fill the water critical pressure computation model:
In the injecting process, because pressure is excessive, after balancing the frame stress in stratum, such as still above rupture strength, then may be used Rupture can be generated, the tonguing of injection water body is caused.In the injecting process, shaft bottom is not much different along well ambient pressure, when crack is deposited When, be the position that stratum is easiest to rupture, when pit shaft internal pressure power overcomes to fall perpendicular to fracture surface as the plane of weakness on stratum After compression, slit band rupture strength is such as still greater than, crack further extends, and the critical condition of gash fracture is then are as follows:
Δ Ρ=σf (1)
In formula (1): σfIt is related with the Filling Characteristics in crack for slit band rupture strength;Δ Ρ is that fracture surface eliminates skeleton Tensile residual stresses after pressure meet respectively:
σf=C* σT (2)
Δ Ρ=Ρ-Ρf (3)
In formula (2): σTFor the tensile strength of reservoir rock, can be obtained according to laboratory test results;C is frac-pack Coefficient, less than 1, value is influenced the numerical value by the filling operation, charges type, filling method of slit band, when charges with enclose Lithofacies like when, which is infinitely close to 1, the tensile strength of gash fracture intensity infinite approach reservoir rock, which can be with Empirical value is provided after observing by rock core.
In formula (3): P bottom pressure;ΡfThe stress in vertical fracture face meets:
σ1: horizontal maximum principal stress;σ2: horizontal minimum principal stress;σ1、σ2It can test to obtain by well point, θ: crack normal Transmeridional angle is deviated, can be calculated after well point counts fracture strike with formula (5):
(5)
Formula (1), (2), (4) are substituted into (3), shaft bottom critical pressure P should are as follows:
2. anticlinal oil pool fracture reservoir water injection pressure calculates:
The stress distribution now of oil-gas anticlinal deposits is uneven, shallower close to anticline axle portion buried depth, and close to both wings with depth Degree increases, and corresponding triaxial stress increases in various degree.In the stress statistic processes of well point, it should tectonic position be divided to unite Meter, nearby well point is one group to high point, seeks corresponding maximum and minimum principal stress, water filling critical pressure corresponds to formula (7), and carries on the back Oblique both wings are another group close to oils water boundary position well point, read corresponding stress, and water filling critical pressure corresponds to formula (8).
It will be in formula (7), (8): PHigh point、σ1 high point、σ2 high pointsRespectively correspond the critical water injection pressure near anticlinal high, maximum is led Stress, minimum principal stress;PIt is black、σ1 wing、σ2 wingsThen correspond to critical water injection pressure of the flank of anticline near oils water boundary, maximum main Stress, minimum principal stress.Under normal conditions, high point nearby fills the water critical pressure and corresponds to minimum value Pmin, and it is right near oils water boundary Answer Pmax
By taking Ao Nan anticlinal oil pool as an example, fracture strike α assembly average in well point is NE65 °;Crack fills crack with half Based on, volumetric efficiency C value is 0.5;Reservoir siltstone, laboratory test tensile strength σTFor 3.89MPa;Read anticlinal high Principal stress greatest around is 30Mpa, minimum principal stress 18Mpa, and near alar part oils water boundary, corresponding maximum, most Minor principal stress is respectively 37MPa, 23MPa.According to formula (5), (7), (8), critical note near the anticlinal high can be calculated Water pressure is 22.06MPa, and the critical water injection pressure of alar part is 27.42Mpa, therefore the best water injection pressure of the oil reservoir should collect In between 22.06~27.42MPa.
3. dense band critical water injection pressure in crack calculates:
The fracture development of reservoir is extremely uneven in oil-gas anticlinal deposits, the part region relatively intensive there may be crack, In the injecting process crack dense band is likely to form stress concentration, so that many cracks be caused to be connected to, injection water is along newly penetrating through Slit band quickly propels.In addition, oil field in seismic data interpretation, is influenced by seismic data resolution, it is difficult to identify that turn-off is small In the tomography of 5m, therefore the safeguard protection section of 5MPa is set, the critical water injection pressure in crack compact district takes:
ΡIt is closeHigh point-5 (9)
Reference should be made to pressure break situations while if wellblock there are pressure break data, considers tectonic position, when fracture pressure is small When anticlinal high critical pressure, close quarters critical water injection pressure in crack is taken:
ΡIt is closeIt is broken-5 (10)
In formula (10): ΡIt is brokenFor the well point fracture pressure minimum value read in pressing crack construction process.High point critical pressure and pressure Caused by deviation when splitting between minimum burst pressure is crack or craven fault endpoint stress concentration.That is:
Ρf0=PHigh point-PIt is broken (11)
In formula (11): Ρf0Refer to pressure divergence caused by crack or craven fault both ends stress concentration.
By taking Ao Nan oil-gas anticlinal deposits as an example, critical water injection pressure is 22.06Mpa near the high point that is calculated, and well point Pressure break data shows that fracture pressure is distributed between 19~43MPa, minimum burst pressure 19MPa, which is less than high point critical Pressure, therefore determine that crack dense band water injection pressure nearby, the numerical value are 14MPa using formula (10), corresponding crack is concentrated Stress-deviation Ρ caused by bandf0For 3.06Mpa.
Embodiment 2, on the basis of embodiment 1, since oil and gas reservoir experienced more phase tectonic movements after deposition, The most area fracture strike of anticline has predominant direction, however very mixed and disorderly in fracture strike, needs to calculate any trend The cracking pressure in crack.Water injection pressure calculates as follows when fracture strike is mixed and disorderly:
Any fracture strike α, normal direction θ is α+90, after considering slit band problem of stress concentration, corresponding critical pressure Power ΡαMeet:
Still by taking Ao Nan oil-gas anticlinal deposits as an example, biggest principal stress direction is approximately EW, minimum principal stress now for this area Direction is nearly north-south.Parameters in formula (11) it is known that any fracture strike critical pressure only with crack with answer now Power angle is related.It can be calculated that the crack of south-north direction (α=0) is vertical with maximum principal stress, cracking pressure is up to 28.89MPa;East-west crack is parallel with maximum principal stress (α=90), has the smallest cracking pressure 16.89MPa.? On the basis of this, according to formula (9) can calculate fracture strike it is mixed and disorderly when, corresponding water filling critical pressure be 11.89MPa.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (7)

1.一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,包含以下步骤:1. an anticline oil and gas reservoir fracture type reservoir critical water injection pressure calculation method, is characterized in that, comprises the following steps: A、在考虑井点裂缝走向、充填程度统计的基础上,建立裂缝重新破裂与注水压力的模型;A. On the basis of taking into account the fracture trend and filling degree statistics at the well point, a model of fracture re-fracture and water injection pressure is established; B、通过分构造部位统计井点地应力,确定了背斜高点和两翼油水边界之间注水压力的范围;B. The range of water injection pressure between the high point of the anticline and the oil-water boundary of the two flanks is determined by calculating the in-situ stress of the well points according to the structural parts; C、对于局部裂缝相对密集地区,对比压裂井点最小破裂压力与背斜高点临界注水压力的关系;C. For areas with relatively dense local fractures, compare the relationship between the minimum fracture pressure at the fracturing well point and the critical water injection pressure at the high point of the anticline; D、提出不同条件下计算裂缝密集带临界注水压力的方法;D. Propose a method for calculating the critical water injection pressure in the fracture-intensive zone under different conditions; E、对于背斜局部多期构造应力叠加,裂缝走向杂乱地区,提出确定裂缝端点应力偏差方法及计算任意走向裂缝突破压力的方法,并确定这些地区的临界注水压力。E. For the local multi-stage tectonic stress superposition of the anticline and the chaotic fracture trend, the method of determining the stress deviation of the fracture end point and the method of calculating the breakthrough pressure of the fracture in any trend are proposed, and the critical water injection pressure in these areas is determined. 2.根据权利要求1所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,所述步骤B具体是:分构造部位统计井点的现今最小主应力、最大主应力,并计算背斜高点及翼部油水边界附近的临界注水压力,确定背斜带临界注水压力的分布范围。2. a kind of anticline oil and gas reservoir fracture-type reservoir critical water injection pressure calculation method according to claim 1, is characterized in that, described step B is specifically: the present minimum principal stress, maximum principal stress of statistical well points by structural position stress, and calculate the critical water injection pressure near the high point of the anticline and the oil-water boundary of the wing to determine the distribution range of the critical water injection pressure in the anticline zone. 3.根据权利要求1所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,所述步骤C中:对比背斜高点临界注水压力与压裂井点最小破裂压力关系,确定不同条件下裂缝密集区临界注水压力的方法,并设置安全保护阈值。3. a kind of anticline oil and gas reservoir fractured reservoir critical water injection pressure calculation method according to claim 1, is characterized in that, in described step C: contrast anticline high point critical water injection pressure and fracturing well point minimum fracture pressure relationship, the method to determine the critical water injection pressure in the fracture-intensive area under different conditions, and set the safety protection threshold. 4.根据权利要求3所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,所述安全保护阈值为5MPa。4 . The method for calculating the critical water injection pressure of a fractured reservoir in an anticline oil and gas reservoir according to claim 3 , wherein the safety protection threshold is 5MPa. 5 . 5.根据权利要求1所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,所述步骤D具体是:计算裂缝密集区的地应力偏差,确定多期应力叠加、裂缝走向杂乱地区临界注水压力的计算方法。5. a kind of anticline oil and gas reservoir fracture-type reservoir critical water injection pressure calculation method according to claim 1, is characterized in that, described step D is specifically: calculate the in-situ stress deviation of the fracture-intensive area, determine multi-phase stress superposition , Calculation method of critical water injection pressure in areas with chaotic fracture trend. 6.根据权利要求1所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,步骤A中的模型包括:裂缝型储层注水临界压力计算、背斜油藏裂缝储层注水压力计算、裂缝密集带临界注水压力计算和裂缝走向杂乱时注水压力计算。6. a kind of anticline oil and gas reservoir fractured reservoir critical water injection pressure calculation method according to claim 1, is characterized in that, the model in step A comprises: fractured reservoir water injection critical pressure calculation, anticline reservoir fracture Reservoir water injection pressure calculation, critical water injection pressure calculation in the fracture dense zone and water injection pressure calculation when the fracture trend is disordered. 7.根据权利要求1-6任一所述的一种背斜油气藏裂缝型储层临界注水压力计算方法,其特征在于,裂缝破裂的临界条件为:ΔΡ=σf,σf为裂缝带破裂强度,与裂缝的充填特征有关;ΔΡ为裂缝面消除骨架压力后的残余张应力。7. a kind of anticline oil and gas reservoir fracture type reservoir critical water injection pressure calculation method according to any one of claims 1-6, is characterized in that, the critical condition of fracture rupture is: ΔP=σ f , σ f is fracture zone The rupture strength is related to the filling characteristics of the crack; ΔP is the residual tensile stress after the skeleton pressure is eliminated on the crack surface.
CN201910084349.0A 2019-01-29 2019-01-29 A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs Pending CN109723414A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910084349.0A CN109723414A (en) 2019-01-29 2019-01-29 A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910084349.0A CN109723414A (en) 2019-01-29 2019-01-29 A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs

Publications (1)

Publication Number Publication Date
CN109723414A true CN109723414A (en) 2019-05-07

Family

ID=66301062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910084349.0A Pending CN109723414A (en) 2019-01-29 2019-01-29 A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs

Country Status (1)

Country Link
CN (1) CN109723414A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116877034A (en) * 2023-08-14 2023-10-13 德州学院 Micro-pressure driving implementation method, system and storage medium for low/ultra-low permeability reservoir development

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6904366B2 (en) * 2001-04-03 2005-06-07 The Regents Of The University Of California Waterflood control system for maximizing total oil recovery
WO2007144562A1 (en) * 2006-06-15 2007-12-21 Aberdeen Petroleum Engineering Consultants Limited Controlled location of the precipitation of scale in reservoirs
CN101403314A (en) * 2008-11-18 2009-04-08 河南理工大学 Coal mine down-hole drilling hydraulic fracturing anti-reflection mash gas extraction technique
CN205977170U (en) * 2016-07-08 2017-02-22 河南理工大学 Automatic sealing device that fills in coal seam developments crack
CN104989341B (en) * 2015-06-24 2017-10-17 中国石油天然气股份有限公司 Method for determining effective displacement injection-production well spacing of low-permeability oil reservoir
CN105672971B (en) * 2016-01-05 2017-12-19 中国石油大学(华东) A kind of Reservoir Fracture Opening pressure, open order and water injection pressure Forecasting Methodology
CN107762475A (en) * 2017-11-16 2018-03-06 中国石油集团川庆钻探工程有限公司 Hydration induction pretreatment and evaluation method before shale reservoir fracturing
US20180208480A1 (en) * 2015-07-18 2018-07-26 Vetco Gray Scandinavia As Seawater injection control methods and systems

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6904366B2 (en) * 2001-04-03 2005-06-07 The Regents Of The University Of California Waterflood control system for maximizing total oil recovery
WO2007144562A1 (en) * 2006-06-15 2007-12-21 Aberdeen Petroleum Engineering Consultants Limited Controlled location of the precipitation of scale in reservoirs
CN101403314A (en) * 2008-11-18 2009-04-08 河南理工大学 Coal mine down-hole drilling hydraulic fracturing anti-reflection mash gas extraction technique
CN104989341B (en) * 2015-06-24 2017-10-17 中国石油天然气股份有限公司 Method for determining effective displacement injection-production well spacing of low-permeability oil reservoir
US20180208480A1 (en) * 2015-07-18 2018-07-26 Vetco Gray Scandinavia As Seawater injection control methods and systems
CN105672971B (en) * 2016-01-05 2017-12-19 中国石油大学(华东) A kind of Reservoir Fracture Opening pressure, open order and water injection pressure Forecasting Methodology
CN205977170U (en) * 2016-07-08 2017-02-22 河南理工大学 Automatic sealing device that fills in coal seam developments crack
CN107762475A (en) * 2017-11-16 2018-03-06 中国石油集团川庆钻探工程有限公司 Hydration induction pretreatment and evaluation method before shale reservoir fracturing

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
余文彬: "准东低渗透油藏临界压力注水评价与应用", 《中国优秀硕士学位论文全文数据库 工程科技Ⅰ辑》 *
李聪,冯阵东 等: "高密度井网区动静结合储层精细描述——以南堡凹陷高76断块Es31Ⅱ(1)小层为例", 《沉积与特提斯地质》 *
柳家奎 等: "王场背斜构造裂缝性油藏注水开发特征研究", 《石油天然气学报》 *
陈永生: "合理注水压力讨论", 《石油勘探与开发》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116877034A (en) * 2023-08-14 2023-10-13 德州学院 Micro-pressure driving implementation method, system and storage medium for low/ultra-low permeability reservoir development
CN116877034B (en) * 2023-08-14 2024-01-23 德州学院 Micro-pressure flooding implementation methods, systems and storage media for low/ultra-low permeability reservoir development

Similar Documents

Publication Publication Date Title
CN103953323B (en) A kind of horizontal well produces the hydraulic fracturing process of seam net
CN108319756B (en) A method for simulation and characterization of volumetric fracture network expansion in tight reservoirs
Li et al. A new technique for preventing and controlling coal and gas outburst hazard with pulse hydraulic fracturing: a case study in Yuwu coal mine, China
US8967262B2 (en) Method for determining fracture spacing and well fracturing using the method
Jiqiang et al. New water drive characteristic curves at ultra-high water cut stage
CN103939099B (en) The prevention and controls of the dangerous coal seam group bump of a kind of thump
RU2012111318A (en) METHOD FOR DEVELOPMENT OF OIL AND GAS DEPOSIT WITH APPLICATION OF HYDRAULIC GROWTH
CN105239984A (en) Method for controlling coal mine underground fracturing crack propagation
Peng et al. Fracture propagation, proppant transport and parameter optimization of multi-well pad fracturing treatment
CN109723414A (en) A method for calculating critical water injection pressure in fractured reservoirs of anticline oil and gas reservoirs
Wang et al. Coupling Technology of Deep‐Hole Presplitting Blasting and Hydraulic Fracturing Enhance Permeability Technology in Low‐Permeability and Gas Outburst Coal Seam: A Case Study in the No. 8 Mine of Pingdingshan, China
CN107288576A (en) Reservoir temporarily blocks up the low frequency hydraulic pulse generating means and its method of turnaround fracture
Peng et al. Study of the borehole hydraulic fracturing and the principle of gas seepage in the coal seam
Wang et al. Dynamic subsidence prediction of ground surface above salt cavern gas storage considering the creep of rock salt
McKenna Where did the proppant go?
CN104989362A (en) Secondary Permeability Enhancement Method of Coal Seam Gas Injection Expansion After Liquid CO2 Explosion to Promote Gas Drainage
CN104632173B (en) Fracture network fracturing layer selection method for non-natural fracture compact reservoir
CN102477852A (en) Perforating method for improving fracturing effect of casing inclined shaft
Wang et al. Impact analysis of pigging in shield segment of gas pipe
CN207080199U (en) Reservoir temporarily blocks up the low frequency hydraulic pulse generating means of turnaround fracture
CN112727401A (en) Reservoir transformation yield increasing method suitable for volatile oil reservoir
CN205605206U (en) Three -dimensional visual model of bottom water oil reservoir horizontal well development
CN110671089A (en) Fracturing filling process parameter optimization design method
Zhang et al. Investigation of a self-excited pulsed water jet slotting for coal roadway driving
Zhaowei et al. Case study: Analysis of the correlation between casing deformation and fracture zone in Changning Block, Sichuan

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190507