CN109702019A CN201811567812.9A CN201811567812A CN109702019A CN 109702019 A CN109702019 A CN 109702019A CN 201811567812 A CN201811567812 A CN 201811567812A CN 109702019 A CN109702019 A CN 109702019A
Authority
CN
China
Prior art keywords
tail
coil
strip
roll
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811567812.9A
Other languages
Chinese (zh)
Inventor
张明生
王晓东
夏银锋
韩宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shougang Jingtang United Iron and Steel Co Ltd
Original Assignee
Shougang Jingtang United Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shougang Jingtang United Iron and Steel Co Ltd filed Critical Shougang Jingtang United Iron and Steel Co Ltd
Priority to CN201811567812.9A priority Critical patent/CN109702019A/en
Publication of CN109702019A publication Critical patent/CN109702019A/en
Pending legal-status Critical Current

Links

Landscapes

  • Metal Rolling (AREA)

Abstract

The invention discloses a method for preventing high-strength steel from being difficult to uncoil in a cold rolling way, wherein a steel coil is processed by a hot rolling leveling unit, and when the steel coil is thrown, tail pressing control is carried out on a roll gap of an inlet straightening roll; after the tail part reaches the roller, cutting off the irregular shape of the tail part of the steel coil and monitoring the tail part state in an inspection table; when the tail part reaches the tension roller, tail pressing control is carried out on the tension roller; when the tail part reaches the tail pressing roller, tail pressing control is carried out on the tension roller; after the steel coil is coiled, the state of the tail part of the steel coil is monitored, and the like, so that the problem of upwarping or downward buckling of the tail part of the steel coil is effectively solved when the steel coil is coiled in the cold rolling process, and the unplanned shutdown or material throwing accident caused by the fact that the cold rolling process cannot be normally uncoiled for production is remarkably reduced, thereby improving the continuity of the steel rolling process, ensuring the smooth proceeding of the process and improving the production line operation rate.

Description

A method of prevent high-strength steel cold roll uncoiling difficult
Technical field
The present invention relates to technical field of steel rolling, in particular to a kind of method for preventing high-strength steel cold roll uncoiling difficulty.
Background technique
Hot rolling produces in the technique of the 780 above high-strength steel of megapascal rank, when rolling up in cold rolling process production, it may appear that hot rolling Coil of strip tail portion upwarp or the problem of lower button, cause cold rolling process can not normal uncoiling production, lead to non-programmed halt or get rid of material, Influence its normal production.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of methods for preventing high-strength steel cold roll uncoiling difficulty, to solve The certainly problem of cold rolling process uncoiling difficulty.
To solve the above-mentioned problems, the present invention provides a kind of method for preventing high-strength steel cold roll uncoiling difficulty, including following Step:
S1: using hot-rolled leveling unit treat processing coil of strip handled, and when coil of strip throw tail when to entrance straightening roll into Row pressure tail control;
S2: when the tail portion of the coil of strip to be processed reaches roll, coil of strip tail portion irregular shape cut off and examining Look into platform monitoring coil of strip tail state;
S3: when the tail portion of the coil of strip to be processed reaches jockey pulley, pressure tail control is carried out to jockey pulley;
S4: when the tail portion of the coil of strip to be processed reaches pressure tail roller, pressure tail control is carried out to pressure tail roller;
S5: the coil of strip to be processed it is coiled after, monitor coil of strip tail state.
Further, in step sl, it is described when coil of strip throw tail when to entrance straightening roll carry out pressure tail control include:
Pressure tail control is carried out to entrance straightening roll by adjusting the roll gap of entrance straightening roll.
Preferably, the roll gap of the entrance straightening roll is -3mm-0mm.
Further, in step s3, when the tail portion of the coil of strip to be processed reaches jockey pulley, pressure tail is carried out to jockey pulley Control includes:
Pressure tail control is carried out to jockey pulley by adjusting the roll gap of jockey pulley.
Preferably, the roll gap of the jockey pulley is -80mm to -100mm.
Further, in step s 4, when the tail portion of the coil of strip to be processed reaches pressure tail roller, pressure tail is carried out to pressure tail roller Control includes:
Pressure tail control is carried out to pressure tail roller by adjusting the roll gap of pressure tail roller.
Preferably, the roll gap of the pressure tail roller is -200mm to -230mm.
Further, in step s 5, if detecting, coil of strip tail portion upwarps or lower button, puts down coil of strip tail portion again It is whole.
The method provided by the invention for preventing high-strength steel cold roll uncoiling difficulty by coil of strip hot rolling skin pass mill group at Reason carries out pressure tail control to entrance aligning roller gap when coil of strip throws tail;It is irregular to coil of strip tail portion after tail portion reaches roll Shape carries out excision and monitors tail state in inspection desk;When tail portion reaches jockey pulley, pressure tail control is carried out to jockey pulley;When When tail portion reaches pressure tail roller, pressure tail control is carried out to jockey pulley;After coil of strip is coiled, the methods of monitoring coil of strip tail state, cold Roll in process production when rolling up, effectively alleviate coil of strip tail portion upwarp or the problem of lower button, significantly reduce cold rolling process because Can not normal uncoiling production, caused non-programmed halt or get rid of material accident, to improve the continuity of steel rolling process, guarantee Technique is gone on smoothly, and improves producing line operating rate.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the control method a kind of stream of specific embodiment provided by the invention for preventing high-strength steel cold roll uncoiling difficulty Journey schematic diagram.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Referring to FIG. 1, Fig. 1 is the control method a kind of specific reality provided by the invention for preventing high-strength steel cold roll uncoiling difficulty Apply the flow diagram of mode.
In a specific embodiment, the control method provided by the present invention for preventing high-strength steel cold roll uncoiling difficulty, The following steps are included:
S1: using hot-rolled leveling unit treat processing coil of strip handled, and when coil of strip throw tail when to entrance straightening roll into Row pressure tail control.
In step sl, described entrance straightening roll to be carried out when coil of strip throws tail tail control is pressed to can be used, by adjusting entering The roll gap of mouth straightening roll carries out pressure tail control to entrance straightening roll, controls the side that the roll gap of entrance straightening roll is adjusted pressure tail Formula is relatively simple, and can significantly improve the coil of strip Quality of Tail of inlet, and coil of strip tail portion is avoided from initial step and is occurred It upwarps or lower button, lays preferable quality basis for subsequent handling process.At this point, the roll gap of the entrance straightening roll can for- 3mm-0mm, roll gap is excessive or the too small processing quality that can all influence straightening roll, selects more appropriate roll gap range, Neng Gougeng Coil of strip tail portion is avoided the occurrence of well to upwarp or lower button.
Theoretically, the roll gap range of entrance straightening roll should be according to coil of strip specification, the pressure tail control accuracy requirement etc. processed Operating condition determines, it is not limited to which between -3mm-0mm, and it is apparent that adjusted value should be greater than 0mm.
S2: when the tail portion of the coil of strip to be processed reaches roll, coil of strip tail portion irregular shape cut off and examining Look into platform monitoring coil of strip tail state.Will pass through the tail state of real time monitoring coil of strip, counter-measure is taken in time, guarantees technique It goes on smoothly.
In step s 2, coil of strip tail portion is monitored, the mode that Image Acquisition can be used is monitored, for example, in work Make platform corresponding position setting image collecting device, and acquired image information is transmitted to monitoring screen, staff passes through It identifies image information, judges whether coil of strip tail state is qualified.Alternatively, can also be realized using the first-class mode of such as infrared photography Infrared probe is mounted on workbench corresponding position by the monitoring to coil of strip tail portion, if coil of strip tail portion tilts or lower button, blocks this Infrared probe, at this time then can not receiving infrared-ray, and issue alarm signal.
S3: when the tail portion of the coil of strip to be processed reaches jockey pulley, pressure tail control is carried out to jockey pulley.
Further, in step s3, pressure tail control, control can be carried out to jockey pulley by adjusting the roll gap of jockey pulley The mode that the roll gap of power roller is adjusted pressure tail is relatively simple, and can significantly improve the coil of strip tail portion matter of tension manufacturing procedure Amount processes in this key step in tension and avoids coil of strip tail portion and occur upwarping or lower button, continuing above-mentioned operation quality Meanwhile preferable quality basis is laid for subsequent handling process.At this point, the roll gap of the jockey pulley is -80mm to -100mm, roller The excessive or too small processing quality that can all influence jockey pulley is stitched, more appropriate roll gap range is selected, can preferably avoid out Existing coil of strip tail portion upwarps or lower button.
Theoretically, the roll gap range of jockey pulley should be according to operating conditions such as coil of strip specification, the pressure tail control accuracy requirements processed It determines, it is not limited between -80mm to -100mm.
S4: when the tail portion of the coil of strip to be processed reaches pressure tail roller, pressure tail control is carried out to pressure tail roller.
In step s 4, when the tail portion of the coil of strip to be processed reaches pressure tail roller, carrying out pressure tail control to pressure tail roller can be adopted Pressure tail control is carried out to pressure tail roller with the roll gap by adjusting pressure tail roller.The side that the roll gap of control pressure tail roller is adjusted pressure tail Formula is relatively simple, and can significantly improve the coil of strip Quality of Tail at pressure tail roller, avoids and occurs in pressure tail step coil of strip tail portion It upwarps or lower button.At this point, the roll gap of the pressure tail roller is -200mm to -230mm, roll gap is excessive or too small can all influence to press tail roller Processing quality, select more appropriate roll gap range, can preferably avoid the occurrence of coil of strip tail portion and upwarp or lower button.
Theoretically, press the roll gap range of tail roller should be according to operating conditions such as coil of strip specification, the pressure tail control accuracy requirements processed It determines, it is not limited between -200mm to -230mm.
S5: the coil of strip to be processed it is coiled after, monitor coil of strip tail state.At the same time it can also which warning device is arranged, when When tail state exception, capable of emitting pre-warning signal or alarm command, such as issue sound and light alarm signal or push alarm command.
In step s 5, coil of strip tail portion is monitored, the mode that Image Acquisition can be used is monitored, for example, in work Make platform corresponding position setting image collecting device, and acquired image information is transmitted to monitoring screen, staff passes through It identifies image information, judges whether coil of strip tail state is qualified.Alternatively, can also be realized using the first-class mode of such as infrared photography Infrared probe is mounted on workbench corresponding position by the monitoring to coil of strip tail portion, if coil of strip tail portion tilts or lower button, blocks this Infrared probe, at this time then can not receiving infrared-ray, and issue alarm signal.
In step s 5, if detecting, coil of strip tail portion is upwarped or lower button, coil of strip tail portion is carried out it is smooth again, so as into One step guarantees coil of strip quality.
In this way, the method provided by the invention for preventing high-strength steel cold roll uncoiling difficulty by coil of strip hot rolling skin pass mill group into Row processing carries out pressure tail control to entrance aligning roller gap when coil of strip throws tail;After tail portion reaches roll, not to coil of strip tail portion Regular shape carries out excision and monitors tail state in inspection desk;When tail portion reaches jockey pulley, pressure tail control is carried out to jockey pulley System;When tail portion reaches pressure tail roller, pressure tail control is carried out to jockey pulley;After coil of strip is coiled, the methods of monitoring coil of strip tail state, When rolling up in cold rolling process production, upwarping or the problem of lower button, significantly reducing Cold-roller for coil of strip tail portion is effectively alleviated Sequence because can not normal uncoiling production, caused non-programmed halt or get rid of material accident, to improve the continuity of steel rolling process, It ensure that technique is gone on smoothly, improve the operating rate and yield rate of production line.
It should be noted last that the above specific embodiment is only used to illustrate the technical scheme of the present invention and not to limit it, Although being described the invention in detail referring to example, those skilled in the art should understand that, it can be to the present invention Technical solution be modified or replaced equivalently, without departing from the spirit and scope of the technical solution of the present invention, should all cover In the scope of the claims of the present invention.

Claims (8)

1. a kind of method for preventing high-strength steel cold roll uncoiling difficulty, which comprises the following steps:
S1: processing coil of strip is treated using hot-rolled leveling unit and is handled, and entrance straightening roll is pressed when coil of strip throws tail Tail control;
S2: when the tail portion of the coil of strip to be processed reaches roll, excision is carried out to coil of strip tail portion irregular shape and in inspection desk Monitor coil of strip tail state;
S3: when the tail portion of the coil of strip to be processed reaches jockey pulley, pressure tail control is carried out to jockey pulley;
S4: when the tail portion of the coil of strip to be processed reaches pressure tail roller, pressure tail control is carried out to pressure tail roller;
S5: the coil of strip to be processed it is coiled after, monitor coil of strip tail state.
2. the method for preventing high-strength steel cold roll uncoiling difficulty as described in claim 1, which is characterized in that in step sl, institute State when coil of strip throw tail when to entrance straightening roll carry out pressure tail control include:
Pressure tail control is carried out to entrance straightening roll by adjusting the roll gap of entrance straightening roll.
3. the method for preventing high-strength steel cold roll uncoiling difficulty as claimed in claim 2, which is characterized in that the entrance straightening roll Roll gap be -3mm-0mm.
4. the method for preventing high-strength steel cold roll uncoiling difficulty as described in claim 1, which is characterized in that
In step s3, when the tail portion of the coil of strip to be processed reaches jockey pulley, carrying out pressure tail control to jockey pulley includes:
Pressure tail control is carried out to jockey pulley by adjusting the roll gap of jockey pulley.
5. the method for preventing high-strength steel cold roll uncoiling difficulty as claimed in claim 4, which is characterized in that
The roll gap of the jockey pulley is -80mm to -100mm.
6. the method for preventing high-strength steel cold roll uncoiling difficulty as described in claim 1, which is characterized in that
In step s 4, when the tail portion of the coil of strip to be processed reaches pressure tail roller, carrying out pressure tail control to pressure tail roller includes:
Pressure tail control is carried out to pressure tail roller by adjusting the roll gap of pressure tail roller.
7. the method for preventing high-strength steel cold roll uncoiling difficulty as claimed in claim 6, which is characterized in that
The roll gap of the pressure tail roller is -200mm to -230mm.
8. the method for preventing high-strength steel cold roll uncoiling difficulty as described in claim 1, which is characterized in that
In step s 5, if detecting, coil of strip tail portion is upwarped or lower button, is carried out to coil of strip tail portion smooth again.
CN201811567812.9A 2018-12-21 2018-12-21 Method for preventing cold rolling and uncoiling difficulty of high-strength steel Pending CN109702019A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811567812.9A CN109702019A (en) 2018-12-21 2018-12-21 Method for preventing cold rolling and uncoiling difficulty of high-strength steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811567812.9A CN109702019A (en) 2018-12-21 2018-12-21 Method for preventing cold rolling and uncoiling difficulty of high-strength steel

Publications (1)

Publication Number Publication Date
CN109702019A true CN109702019A (en) 2019-05-03

Family

ID=66257242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811567812.9A Pending CN109702019A (en) 2018-12-21 2018-12-21 Method for preventing cold rolling and uncoiling difficulty of high-strength steel

Country Status (1)

Country Link
CN (1) CN109702019A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111744958A (en) * 2020-06-06 2020-10-09 河钢乐亭钢铁有限公司 Method for adjusting tail-fixing angle of coil box

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103706637A (en) * 2013-12-31 2014-04-09 一重集团大连设计研究院有限公司 Novel cold rolling short-process technology and units of novel cold rolling short-process technology
CN105170706A (en) * 2015-09-25 2015-12-23 新民市华星机械工业有限公司 Coiled material flattening machine
CN105728498A (en) * 2016-03-23 2016-07-06 攀钢集团西昌钢钒有限公司 Smooth repairing process for hot rolling horn rolls
CN205413959U (en) * 2016-03-18 2016-08-03 无锡市顺天铁塔器材制造有限公司 Iron tower tower material alignment cutting device
CN106424157A (en) * 2016-11-18 2017-02-22 首钢京唐钢铁联合有限责任公司 Control method and device for preventing leveling machine working roll from being scratched
CN207026109U (en) * 2017-06-12 2018-02-23 武汉乾冶工程技术有限公司 A kind of white skin rolling annealing and pickling unit in new type stainless steel. corrosion resistance arrowband
CN108089466A (en) * 2017-12-15 2018-05-29 山信软件股份有限公司 A kind of steel plates straightening control method
CN108941211A (en) * 2018-08-21 2018-12-07 首钢京唐钢铁联合有限责任公司 Hot rolling leveling unit and method for processing strip steel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103706637A (en) * 2013-12-31 2014-04-09 一重集团大连设计研究院有限公司 Novel cold rolling short-process technology and units of novel cold rolling short-process technology
CN105170706A (en) * 2015-09-25 2015-12-23 新民市华星机械工业有限公司 Coiled material flattening machine
CN205413959U (en) * 2016-03-18 2016-08-03 无锡市顺天铁塔器材制造有限公司 Iron tower tower material alignment cutting device
CN105728498A (en) * 2016-03-23 2016-07-06 攀钢集团西昌钢钒有限公司 Smooth repairing process for hot rolling horn rolls
CN106424157A (en) * 2016-11-18 2017-02-22 首钢京唐钢铁联合有限责任公司 Control method and device for preventing leveling machine working roll from being scratched
CN207026109U (en) * 2017-06-12 2018-02-23 武汉乾冶工程技术有限公司 A kind of white skin rolling annealing and pickling unit in new type stainless steel. corrosion resistance arrowband
CN108089466A (en) * 2017-12-15 2018-05-29 山信软件股份有限公司 A kind of steel plates straightening control method
CN108941211A (en) * 2018-08-21 2018-12-07 首钢京唐钢铁联合有限责任公司 Hot rolling leveling unit and method for processing strip steel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋美娟: "《材料成形测试技术》", 30 April 2018, 西安电子科技大学出版社 *
许石民等: "《板带材生产工艺及设备》", 31 August 2008, 冶金工业出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111744958A (en) * 2020-06-06 2020-10-09 河钢乐亭钢铁有限公司 Method for adjusting tail-fixing angle of coil box
CN111744958B (en) * 2020-06-06 2022-03-22 河钢乐亭钢铁有限公司 Method for adjusting tail-fixing angle of coil box

Similar Documents

Publication Publication Date Title
CN110280602A (en) Intelligent steel rolling rolling assessment system and processing method extremely
CN106670241A (en) Device and method for shortening continuous tapping time interval of rolled steel production line
CN102527720B (en) Control system and control method for multi-roller straightener of cold rolling and rewinding unit
CN104307892B (en) The method of band head correction in tandem rolling crossing process
CN109396195B (en) Anti-seismic steel bar head and tail identification quick-falling control system and control method
CN103720024B (en) A kind of method of controlling security of storage cabinet material toggling roller, system and storage cabinet
CN109702019A (en) Method for preventing cold rolling and uncoiling difficulty of high-strength steel
CN111215453A (en) A remote control system for a reversible cold rolling mill and its control method
CN111346924B (en) Anti-pressing steel control method and device and strip steel finish rolling equipment
CN207325590U (en) A kind of positive waste product of coil of strip separates coiling system
CN112077150B (en) Control method for effectively reducing waste cutting of long material production line
US9937539B2 (en) Method and device for producing a metal strip in a continuous casting and rolling process
CN111445441A (en) Strip steel head defect processing method and device
JP2013205381A (en) Method and system for detecting defect of steel tape threaded into cold rolling mill
CN111570523A (en) Rolling line parameter acquisition and analysis and negative difference early warning system for steel rolling production
CN111360077B (en) Control method for preventing strip steel from throwing into acid tank
CN106670242B (en) The device of the offline Strip Shape of On-line Control
KR100264983B1 (en) Rolling crop shape detection device and method
CN104801569A (en) Method for preventing collision of pre-straightening steel plate and subsequent equipment, and steel plate head warping detection apparatus
CN110871221A (en) Method and device for preventing coiler from steel scrap
CN111346928B (en) Start control method, device and medium for preventing strip steel from being broken under secondary pressing
CN108213084B (en) The progress control method and system of Coil Box
CN108856306B (en) Head-to-tail continuous steel feeding rolling method and system
CN109848805A (en) The continuous grinding method of metal tape and the continuous grinding production line of metal tape
JP2008207257A (en) Trim waste fragmentation device and control method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190503

RJ01 Rejection of invention patent application after publication