Summary of the invention
It cannot achieve effluent cycle utilization, the serious problem of water resource waste to solve current service rack, the present invention provides
This kind of sewage circulating treating system suitable for ground carwash platform, it is improved in that the effluent cycle system packet
Include diversion trench, silt pond, multifeed clarifier, flocculant water tank and circulation clear water reserviors, wherein
The diversion trench is connect with the silt pond, generated sewage when for by Construction traffic rinsing table cleaning vehicle
It imports in the silt pond;
The silt pond is set to below ground, and for precipitating the silt in the sewage, the sewage is through the silt pond
The multifeed clarifier is flowed into after precipitating;
The multifeed clarifier is used to precipitate the sewage after the precipitating of the silt pond, in the multifeed clarifier respectively
It is connected in series between grade sedimentation basin;
Flocculant is contained in the flocculant water tank, and is separately connected with the sedimentation basins at different levels, and the flocculant is used for
Accelerate the settlement of sewage;
The circulation clear water reserviors are connect with the multifeed clarifier, clear after multifeed clarifier precipitating for storing
Water.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, silt bottom of pond end is equipped with silt
Pump, the silt after the sediment pump is used to precipitate are extracted out.
Further, the institute in above-mentioned Construction traffic rinsing table effluent cycle system, after the precipitating of the silt pond
It states sewage and flows into the sedimentation basin by filter screen.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, the multifeed clarifier includes level-one
Sedimentation basin and second-level settling pond.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, the first stage precipitation tank and the mud
It is connected between sand basin by the first transverse tube, is connect between the second-level settling pond by the second transverse tube.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, first transverse tube is in vertical direction
Higher than second transverse tube.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, the circulation clear water reserviors and described the
Two sedimentation basins are connected by vertical tube.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, second transverse tube is in vertical direction
Higher than the vertical tube.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, the flocculant water tank is set to described
Above sedimentation basin.
Further, in above-mentioned Construction traffic rinsing table effluent cycle system, the circulation clear water reserviors are applied with described
The high-pressure spray gun of work vehicle rinsing table is connected, and realizes recycling for waste water.
Analysis is it is found that compared with prior art, the present invention have the following beneficial effects:
It is used with being matched with most of ground type service rack equipped with collecting gutter, suitability is good;Using strainer coarse filtration and wadding
Solidifying sedimentation combines, high compared to traditional three-level physical sedimentation pond deposition efficiency, and reduces the quantity of sedimentation basin, and
The waste water circulatory system that high-end carwash platforms some at present are equipped with is compared, and cost is lower.
Specific embodiment
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.The explanation of each example through the invention
Mode, which provides, to be not intended to limit the present invention.In fact, those skilled in the art will be clear that, the scope of the present invention or essence are not being departed from
In the case where mind, it can modify in the present invention and modification.For example, being illustrated or described as the spy of a part of one embodiment
Sign can be used for another embodiment, to generate another embodiment.Thus, it may be desirable to which the present invention includes to be included into appended power
Such modifications and variations in the range of benefit requirement and its equivalent.
In the description of the present invention, term " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear", "left", "right", " perpendicular
Directly ", the orientation or positional relationship of the instructions such as "horizontal", "top", "bottom" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the present invention rather than require the present invention that must be constructed and operated in a specific orientation, therefore should not be understood as pair
Limitation of the invention.Term used in the present invention " connected ", " connection ", " setting " shall be understood in a broad sense, for example, it may be solid
Fixed connection, may be a detachable connection;It can be directly connected, can also be indirectly connected by intermediate member, for ability
For the those of ordinary skill in domain, the concrete meaning of above-mentioned term can be understood as the case may be.
As shown in Figure 1, being the structural schematic diagram of Construction traffic rinsing table effluent cycle system provided by the invention, the sewage
The circulatory system includes diversion trench 1, silt pond 4, multifeed clarifier, flocculant water tank 9 and circulation clear water reserviors 11.Wherein, diversion trench 1
Ground or more can be set to hereinafter, it connect with the top in silt pond 4, the sewage that Construction traffic generates after rinsing table cleaning can
It is imported in silt pond 4 through ground diversion trench 1.Because being mixed with silt in the sewage that flows in diversion trench 1, therefore it is preferred that diversion trench 1 is on ground
It is higher than silt pond 4 on face to be arranged, and will be arranged to the connecting pin in silt pond 4 with corner structure, then the top with silt pond 4
End connection, such setting can preferably ensure smoothly to import sewage in silt pond 4.In some alternative embodiments,
Diversion trench 1 can also be obliquely installed, i.e., towards and the connecting pin in silt pond 4 gradually decrease setting, and by the company with silt pond 4
The top that end is set to silt pond 4 is connect, so as to preferably ensure smoothly to import sewage in silt pond 4.
Specifically, above-mentioned silt pond 4 is set to below ground, is in cuboid-type or cylinder type.Through derived from diversion trench 1
It after sewage with silt imports silt pond 4, is stood in silt pond 4 first, the silt during standing in sewage will be
Automatic sedimentation is in the bottom in silt pond 4 under gravity, when the sewage imported in silt pond 4 is enough, after precipitating silt
Upper layer sewage can flow into multifeed clarifier through the first transverse tube 2 to be continued to settle.
Further, the first transverse tube 2 for connecting silt pond 4 and multifeed clarifier is set to silt pond 4 and multifeed clarifier
First stage precipitation tank 6 upper end, and which is provided with filter screen, which is set to the connecting pin in silt pond 4, and the application is preferred
Filter device is close mesh filter screen 3, i.e., the upper layer sewage after precipitating silt in silt pond 4 also needs to filter through overstocked mesh filter screen 3
After can flow into multi stage precipitation mud and continue to precipitate, close mesh filter screen 3, which is arranged, may insure when due in Construction traffic cleaning process
The sewage of generation is more, full silt pond 4 is stored when sewage fails to precipitate well in silt pond 4, close mesh filter screen 3 can have at this time
The barrier silt of effect flows into multifeed clarifier.Preferably, above-mentioned close mesh filter screen 3 is 100 mesh filter screens.Wherein, mesh (mesh)
Refer to the empty eye number on 1inch (2.54cm) sieve.1 mesh just refers to that the eyelet on every square of English inch is 1.In addition to indicating to sieve
Outside the eyelet of net, it is used to indicate simultaneously can be by the partial size of the particle of sieve, and mesh number is higher, and partial size is smaller.According to silt
The diameter of particle is generally 0.05mm-2.0mm, and the preferably close mesh filter screen 3 of the present embodiment is that 100 mesh are that most preferably, about may filter that
Particulate matter diameter is 0.15mm.
It is first stage precipitation tank 6 respectively preferably two in the present embodiment as shown in Figure 1, the multifeed clarifier in the application
With second-level settling pond 8.First stage precipitation tank 6 and second-level settling pond 8 are connected in series by the second transverse tube 7.First stage precipitation tank 6 and second level
Sedimentation basin 8 is set to below ground, can be and is in same level with above-mentioned silt pond 4, is also possible to lower than silt
The position in pond 4 is arranged.First stage precipitation tank 6 and second-level settling pond 8 can be cuboid-type or cylinder type, and the present invention does not do this
It is specific to limit.
Above-mentioned sewage after filtering imports first stage precipitation tank 6 first, and continues to settle in first stage precipitation tank 6, until
To be stored in first stage precipitation tank 6 it is full after, after liquid level reaches the position of the second transverse tube 7 in first stage precipitation tank 6, then through level-one sedimentation
Sewage flow to progress second level sedimentation in second-level settling pond 8 through the second transverse tube 7.Sewage precipitated in above-mentioned two-stage sedimentation basin with
Staticly settling in silt pond 4 the difference is that, first stage precipitation tank 6 and second-level settling pond 8 respectively with above-mentioned flocculant water
Case 9 is connected by tubule, and flocculant water tank 9 is set to the top of first stage precipitation tank 6 and second-level settling pond 8, when first stage precipitation tank 6
After importing sewage in second-level settling pond 8, the flocculant in flocculant water tank 9 can pass through tubule under control of the control system
It flows into first stage precipitation tank 6 and second-level settling pond 8, under the action of flocculant, the impurity in sedimentation basin in sewage can be with wadding
Solidifying agent, which combines, generates flocculent deposit and rapid subsidence.Sedimentation basin is used in combination the application with flocculant water tank 9, compared to tradition
Simple physical subsidence style, can high degree improve sewage treating efficiency, while the setting of sedimentation basin can also be reduced, because passing
The sedimentation basin that the physics subsidence style of system needs to be arranged more stages could be up to standard by sewage treatment.Above-mentioned flocculant is preferably nothing
Machine high polymer coagulant.Inorganic polymer flocculant be grow up on the basis of tradition aluminium salt, molysite one kind it is novel
Water treatment agent, price is less expensive, and purifying water effect is good.It up to standard can continue cycling through and use through above-mentioned two-stage oettIed sewage
The clear water flowed out in clear water degree, i.e. second-level settling pond 8 is flow in circulation clear water reserviors 11 by vertical tube 10 and is utilized for circulating in.
Above-mentioned each sedimentation basin will be lower than in the vertical direction by recycling clear water reserviors 11, being capable of maximum journey to ensure to demonstrate,prove processed clear water
The remittance of degree.The other end of circulation clear water reserviors 11 is connected with high-pressure spray gun, and high-pressure spray gun can will store in circulation clear water reserviors 11
Clear water extraction after be directly used in Construction traffic cleaning, realize recycling for waste water.
Further, with the increase of use time, the silt of 4 bottom deposit of silt pond can be more and more, therefore, this Shen
It please is equipped with sediment pump 5 in the bottom in above-mentioned silt pond 4, sediment pump 5 can periodically automatically extract the silt of bottom deposit out.By
Impurity content is seldom in through silt pond 4 and the filtered sewage of close mesh filter screen 3, therefore the application is not in first stage precipitation tank
6 and the bottom of second-level settling pond 8 sediment pump 5 is set, but periodic detection is if it find that when more sediment long-term accumulation, then makes
Sediment is extracted out with sediment pump.
Further, due to can be fewer and fewer by impurity in the sewage of precipitation process layer by layer, i.e., from the left end in Fig. 1 to
Right end, from silt pond 4 to second-level settling pond 8, impurity can be fewer and fewer in sewage therein, and lower sediment thing is fewer and fewer, on
The clear water of layer is more and more, to guarantee that filtered clear water can utmostly flow to next stage, guarantees sewage treating efficiency, this
Application the second transverse tube 7 of setting will be lower than the height of the first transverse tube 2 in the height of vertical direction.Similarly, 8 right end of second-level settling pond connects
The connection open height of the vertical tube 10 connect will be lower than the height of the second transverse tube 7 in vertical direction.
Combined with specific embodiments below, to the course of work of the Construction traffic rinsing table effluent cycle system of the application do into
One step illustrates:
When carwash, the waste water with silt flows into the diversion trench 1 below service rack by the rain perforaled strainer around service rack,
Waste water enters silt pond 4 by diversion trench 1, filters out coarse grained silt and impurity through overstocked mesh filter screen 3 after precipitating.Silt pond 4
The sediment pump 5 of bottom automatically turns on exclusion silt at regular intervals prevents close mesh filter screen 3 from blocking.After close mesh filter screen 3
Water flows into first stage precipitation tank 6 by the first transverse tube 2, and flocculant water tank 9 opens the tubule connecting with first stage precipitation tank 6 at this time, and
Flocculant is added in first stage precipitation tank 6, the sewage in first stage precipitation tank 6 forms flocculent deposit, Zhi Houxu in conjunction with flocculant
Shape precipitating sink, the limpider sewage in upper layer by the second transverse tube 7 continue indwelling second-level settling pond 8, flow into second-level settling pond 8 with
Same principle carries out secondary precipitation.Clear water by secondary precipitation flows into circulation clear water reserviors 11 into vertical tube 10 is crossed, and recycles clear water reserviors
11 are connected with the high-pressure spray gun of rinse-system again, recycle to realize to flushing waste water.
Construction traffic rinsing table effluent cycle system provided by the invention can be matched with ground type service rack, work
When, collecting gutter need to be only connected with system entry diversion trench 1 more than bottom surface, by system circulation clear water reserviors 11 and service rack
High-pressure spray gun is connected, and assembly is simple, and suitability is strong.
It is combined using strainer coarse filtration and flocculation sedimentation technology, it is high compared to traditional three-level physical sedimentation pond deposition efficiency,
Reduce the quantity of sedimentation basin.It can be greatly reduced using the flocculate that sewage after strainer coarse filtration is formed in I and II sedimentation basin,
Therefore also do not need the installation in sedimentation basin is using sediment pump extraction if sediment long-term accumulation is more except silt system
Can, it is lower that cost is compared with the service rack sedimentation basin that can reach identical sedimentation effect at present.
The above description is only a preferred embodiment of the present invention, is not intended to restrict the invention, for those skilled in the art
For member, the invention may be variously modified and varied.All within the spirits and principles of the present invention, it is made it is any modification,
Equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.