[go: up one dir, main page]

CN109616953B - A kind of instrument cable laying method - Google Patents

A kind of instrument cable laying method Download PDF

Info

Publication number
CN109616953B
CN109616953B CN201811554916.6A CN201811554916A CN109616953B CN 109616953 B CN109616953 B CN 109616953B CN 201811554916 A CN201811554916 A CN 201811554916A CN 109616953 B CN109616953 B CN 109616953B
Authority
CN
China
Prior art keywords
cable
laying machine
cables
cable laying
instrument
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811554916.6A
Other languages
Chinese (zh)
Other versions
CN109616953A (en
Inventor
李庆国
王新献
张连国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonghua Luxi Engineering Co.,Ltd.
Original Assignee
LUXI INDUSTRY EQUIPMENT CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LUXI INDUSTRY EQUIPMENT CO LTD filed Critical LUXI INDUSTRY EQUIPMENT CO LTD
Priority to CN201811554916.6A priority Critical patent/CN109616953B/en
Publication of CN109616953A publication Critical patent/CN109616953A/en
Application granted granted Critical
Publication of CN109616953B publication Critical patent/CN109616953B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Electric Cable Installation (AREA)

Abstract

本发明公开了一种仪表电缆敷设方法,其特征在于:步骤为:(1)将仪表电缆逐一粘贴电缆线号标识;(2)按照一个穿线孔穿入一根仪表电缆的原则,根据线号标识,逐一将仪表电缆穿入穿线管;(3)将来自穿线管初步定位的电缆,根据线号标识按照顺序依次放入滑轮组凹槽内;根据安装现场情况,每10‑20m固定一个滑轮组;(4)电缆敷设机输送:根据现场情况每50‑100m固定一个电缆敷设机、每个电缆敷设机固定一名操作人员,根据安装现场的电缆滑架和敷设机配置情况,按照电缆滑架和电缆敷设机的配置顺序,敷设人员通过利用对讲机通知电缆敷设机操作人员同时操作电缆敷设机开启或停运的方式,逐步将电缆传输至电缆桥架上。本发明利用机械方式敷设仪表电缆,将仪表电缆作业人员降低2/3;利用电缆穿线管初步定位工装和电缆滑架实现电缆精确定位,解决了因仪表电缆较细、利用设备传输过程中造成的电缆相互缠绕问题,实现了仪表电缆快速传送,敷设效率提高70%以上。

Figure 201811554916

The invention discloses a method for laying instrument cables, which is characterized in that the steps are: (1) pasting the cable wire number identifications on the instrument cables one by one; Thread the instrument cables into the threading pipe one by one; (3) Put the cables from the preliminary positioning of the threading pipe into the groove of the pulley block in sequence according to the wire number identification; According to the installation site conditions, fix a pulley block every 10-20m; (4) Cable laying machine transportation: According to the site conditions, one cable laying machine is fixed every 50-100m, and one operator is fixed for each cable laying machine. The configuration sequence of the cable laying machine, the laying personnel gradually transmit the cable to the cable tray by using the walkie-talkie to notify the cable laying machine operator to simultaneously operate the cable laying machine to start or stop the operation. The invention lays the instrument cable mechanically, reducing the operator of the instrument cable by 2/3; using the cable threading pipe preliminary positioning tool and the cable carriage to realize the precise positioning of the cable, and solves the problems caused by the thin instrument cable and the transmission process of the equipment. The problem of mutual entanglement of cables realizes the rapid transmission of instrument cables, and the laying efficiency is increased by more than 70%.

Figure 201811554916

Description

Instrument cable laying method
Technical Field
The invention belongs to the field of cable laying, and particularly relates to an instrument cable laying method.
Background
At present, in the instrument cable installation field, the most extensive high-risk operation is high-altitude operation in the cabling process, and the data display is carried out: since 2003, a high-altitude falling accident occurs in about 450 years, the high-altitude falling accident accounts for 52% and 48% of the total number of construction accidents and the number of deaths respectively, the instrument cable is thin (usually 1cm), the weight is small, the laying mode is mainly to stretch and lay at different positions of a bridge frame together by depending on manpower, if the cable laying equipment is used for laying, due to the lack of a positioning device, the problem that continuous transmission is influenced due to mutual winding caused by the thin instrument cable is easy to occur, in order to change the current situation, an instrument cable laying method needs to be developed urgently, and the technical progress of the industry is promoted.
Disclosure of Invention
The invention mainly solves the problems in the prior art and provides a method for laying an instrument cable. According to the method, the instrument cable is laid by adopting machinery instead of manpower, so that the cable laying efficiency and the safety coefficient are improved.
In order to realize the purpose, the invention adopts the following technical scheme:
an instrument cable laying method comprises the following steps:
(1) line number marking: and pasting cable line number marks on the instrument cables on the instrument cable reel on the laying site one by one.
(2) Preliminary positioning of the cable threading pipe: providing a threading pipe primary positioning device, and threading instrument cables into the threading pipe one by one according to the principle that one threading hole penetrates one instrument cable and the line number identification; the positioning functions to prevent adjacent cables from intertwining during transmission.
(3) Cable carriage repositioning: providing a pulley block with a plurality of grooves, and sequentially placing cables from the initial positioning of the threading pipe into the grooves of the pulley block according to the line number marks in sequence; and according to the situation of an installation site, fixing one pulley block every 10-20 m.
(4) Conveying by a cable laying machine: fixing one cable laying machine every 50-100m according to the field condition, and fixing one operator for each cable laying machine; sequentially putting cables from the initial positioning of the cable threading pipes into a 1 st cable laying machine according to line number marks, after the cables of the 1 st cable laying machine are laid, informing a 1 st cable laying machine operator to start the 1 st cable laying machine by a laying person, under the transmission of the 1 st cable laying machine, drawing the cables onto a cable sliding frame adjacent to the 1 st cable laying machine by the laying person, informing the 1 st cable laying machine operator to stop the cable laying machine by the laying person through an interphone, sequentially putting the cables into a cable sliding frame groove adjacent to the 1 st cable laying machine by the laying person according to the line number marks, and then informing the 1 st cable laying machine operator to start the 1 st cable laying machine to continue to transmit instrument cables through the interphone; according to the configuration conditions of the cable sliding frame and the cable laying machine on the installation site, according to the configuration sequence of the cable sliding frame and the cable laying machine, a laying person gradually transmits the cable to the cable bridge frame in a mode of informing an operator of the cable laying machine of simultaneously operating the cable laying machine to start or stop by using the interphone.
The invention also aims to provide a device for realizing the method, which comprises a cable threading pipe primary positioning tool and a cable sliding frame.
The cable threading pipe primary positioning tool is composed of 3-10 threading pipes with the diameter of 2cm and the length of 5cm, which are welded on a support plate with the length of 10cm and the width of 5cm, and the support plate is welded on a threading pipe support; and polishing the two ends of the threading pipe by polishing equipment to be smooth and prevent the surface layer of the cable from being scratched.
The cable balladeur train comprises balladeur train support, connecting rod, bearing, recess pulley, fixation nut, support, and wherein the balladeur train support passes through the welding mode with the balladeur train support to be connected, and the bearing is installed on recess pulley mounting hole, each symmetry installation of both sides one, and the connecting rod is installed on the bearing mounting hole, and connecting thread is processed at the connecting rod both ends, fixes the connecting rod on the balladeur train support through fixation nut.
Further, the depth of the groove is 3-5 cm.
The invention has the beneficial effects that:
the invention provides an instrument cable laying method, which has the following advantages:
1. the instrument cable is laid by a mechanical mode, and 2/3 is reduced for instrument cable operators, so that the risk of high-altitude operation is greatly reduced.
2. Utilize cable threading pipe preliminary location frock and cable balladeur train to realize cable accurate positioning, solved because of instrument cable thin, utilize the cable intertwine problem that causes in the equipment transmission process, realized the quick conveying of instrument cable, lay efficiency and improve more than 70%.
Drawings
FIG. 1 is a schematic flow chart of the present invention
FIG. 2 is a front view of the cable carriage of the present invention
FIG. 2-1 is a top plan view of a cable carriage of the present invention
Fig. 2-2 are side views of the cable carriage of the present invention
FIG. 3 shows a positioning tool for a threading pipe according to the present invention
Wherein 0001, instrument cable drum, 0002, cable threading pipe positioning device, 0003, 1 st cable laying machine, 0004, 1 st cable carriage, 0005, 2 nd cable carriage, 0006, 3 rd cable carriage, 0007, 2 nd cable laying machine, 0008, 4 th cable carriage, 0009, 5 th cable carriage, 0010, 6 th cable carriage, 0011, 7 th cable carriage, 0012, 8 th cable carriage, 0013, 9 th cable carriage, 0014, 10 th cable carriage, 0015, 3 rd cable laying machine, 0016, 11 th cable carriage, 0017, 12 th cable carriage, 0018, 13 th cable carriage, 0019, 14 th cable carriage, 0020, 15 th cable carriage, 0021, 4 th cable laying machine, 0022, 16 th cable carriage, 0023, 17 th cable carriage, 0024, 18 th cable carriage, 0025, 19 th cable carriage, 0026, 20 th cable carriage, 0027 th cable carriage, 00221 st cable laying machine, 0028 th cable carriage, 00222 th cable carriage, 0029. the 5 th cable laying machine, 0030, 23 rd cable carriage, 0031, 24 th cable carriage, 0032, 25 th cable carriage, 0033, 26 th cable carriage, 0034, 27 th cable carriage, 0035, the 6 th cable laying machine, 0036, carriage support, 0037, connecting rod, 0038, bearing, 0039, groove pulley, 0040, fixing nut, 0041, carriage support, 0042, threading pipe, 0043, threading pipe support plate, 0044, threading pipe support.
Detailed Description
It should be noted that the following detailed description is exemplary and is intended to provide further explanation of the disclosure. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.
Example 1:
the number of instrument cables to be laid is 6, and six cable laying machines (FDS-6 type or the same type of function) and 27 cable carriages are configured according to the installation site condition. The number of operators is seven, wherein 6 operators of the cable laying machine and 1 operator of the cable laying machine are provided; firstly, a laying worker pastes cable line number marks, namely 1#, 2#, 3#, 4#, 5# and 6# to instrument cables 0001 on an instrument cable tray on a laying site one by one; then, according to the principle that one instrument cable is inserted into one instrument cable through one threading hole, the instrument cables are inserted into the threading pipes one by one according to the line number identification; and then the cables positioned by the cable threading pipe positioning tool 0002 are sequentially placed into a cable laying machine 0003 according to the line number identification and the positioning sequence.
After the cables of the cable laying machine 0003 are laid, a laying person informs the 1 st cable laying machine operator to start the 1 st cable laying machine, the laying person pulls the cables to the 1 st cable carriage 0004 under the transmission of the 1 st cable laying machine 0003, at the moment, the laying person informs the 1 st cable laying machine operator to stop the 1 st cable laying machine 0003 through an interphone, the laying person puts the cables into the 1 st cable carriage 0004 groove according to the line number marks in sequence, at the moment, the laying person informs the 1 st cable laying machine operator to start the 1 st cable laying machine 0003 through the interphone, the cables are pulled to the 2 nd cable carriage 0005, at the moment, the laying person informs the 1 st cable laying machine operator to stop the 1 st cable laying machine 0003 through the interphone, the laying person puts the cables into the 2 nd cable carriage 0003 groove according to the line number marks in sequence, at the moment, the laying person informs the 1 st cable laying machine operator to start the 1 st cable laying machine 0003 through the interphone And the cable is pulled to a 3 rd cable carriage 0006, at the moment, a laying personnel informs a 1 st cable laying machine operator to stop the 1 st cable laying machine 0003 through an interphone, the laying personnel sequentially puts the cable into a 2 nd cable carriage 0006 groove according to line number marks, at the moment, the laying personnel informs the 1 st cable laying machine operator to start the 1 st cable laying machine 0003 through the interphone, and the cable is pulled to a 2 nd cable conveyor 0007.
According to the operation method, a laying worker transmits instrument cables step by step under the transmission of a laying machine, before the laying worker reaches a cable laying machine or a cable sliding frame, the laying machine is informed to the operator of the cable laying machine by using the interphone, the cable laying machine which is transmitting the cables is stopped at the same time, the cables are placed on the cable laying machine or in a cable sliding frame groove according to line number marks in sequence, the operator of the cable laying machine is informed to start the cable laying machine which is to transmit the cables at the same time by using the interphone, the operation is carried out in sequence, after the cables are conveyed to a set place, all the cable laying machines are stopped, and finally the cables are taken out from the laying machines and the cable sliding frame groove and are placed into a cable bridge frame to finish the laying of the cables. During the cable laying process, the corresponding shutdown or startup conditions of the cable carriage and the cable laying machine are as follows:
Figure BDA0001911600590000041
example 2:
the utility model provides a cable threading pipe preliminary location frock, is constituteed on the backup pad 0043 that length is 10cm, width are 5cm by 3 diameter are 2cm, length are 5 cm's threading pipe 0042 welding, and backup pad 0043 welds on threading pipe support 0044. Meanwhile, the two ends of the threading pipe are polished smoothly by a polishing machine, so that the surface layer of the cable is prevented from being scratched.
Example 3:
the utility model provides a cable threading pipe preliminary location frock, is formed on the backup pad 0043 that length is 10cm, width are 5cm by 10 diameter threading pipes 0042 welding that length is 2cm, length are 5cm, and backup pad 0043 welds on threading pipe support 0044. Meanwhile, the two ends of the threading pipe are polished smoothly by a polishing machine, so that the surface layer of the cable is prevented from being scratched.
Example 4:
the utility model provides a cable threading pipe preliminary location frock, is formed on the backup pad 0043 that length is 10cm, width are 5cm by 6 diameter for 2cm, length are welded to the threading pipe 0042 of 5cm, backup pad 0043 welds on threading pipe support 0044. Meanwhile, the two ends of the threading pipe are polished smoothly by a polishing machine, so that the surface layer of the cable is prevented from being scratched.
Example 5:
a cable carriage is composed of a carriage support 0036, a connecting rod 0037, a bearing 0038, a groove pulley 0039, a fixing nut 0040 and a carriage support 0041, wherein the carriage support 0036 is connected with the carriage support 0041 in a welding mode, the bearing 0038 is installed on an installation hole of the groove pulley 0039, two sides of the bearing 0038 are respectively and symmetrically installed one, the connecting rod 0037 is installed on an installation hole of the bearing 0038, connecting threads are processed at two ends of the connecting rod 0037, and the connecting rod 0037 is fixed on the carriage support 0036 through the fixing nut 0040; the groove pulley 0039 had a groove depth of 3 cm.
Example 6:
a cable carriage is composed of a carriage support 0036, a connecting rod 0037, a bearing 0038, a groove pulley 0039, a fixing nut 0040 and a carriage support 0041, wherein the carriage support 0036 is connected with the carriage support 0041 in a welding mode, the bearing 0038 is installed on an installation hole of the groove pulley 0039, two sides of the bearing 0038 are respectively and symmetrically installed one, the connecting rod 0037 is installed on an installation hole of the bearing 0038, connecting threads are processed at two ends of the connecting rod 0037, and the connecting rod 0037 is fixed on the carriage support 0036 through the fixing nut 0040; the groove pulley 0039 had a groove depth of 5 cm.
Example 7:
a cable carriage is composed of a carriage support 0036, a connecting rod 0037, a bearing 0038, a groove pulley 0039, a fixing nut 0040 and a carriage support 0041, wherein the carriage support 0036 is connected with the carriage support 0041 in a welding mode, the bearing 0038 is installed on an installation hole of the groove pulley 0039, two sides of the bearing 0038 are respectively and symmetrically installed one, the connecting rod 0037 is installed on an installation hole of the bearing 0038, connecting threads are processed at two ends of the connecting rod 0037, and the connecting rod 0037 is fixed on the carriage support 0036 through the fixing nut 0040; the groove pulley 0039 had a groove depth of 4 cm.
The above embodiments are only exemplary embodiments of the present invention, and are not intended to limit the present invention, and the scope of the present invention is defined by the claims. Various modifications and equivalents may be made by those skilled in the art within the spirit and scope of the present invention, and such modifications and equivalents should also be considered as falling within the scope of the present invention.

Claims (1)

1. An instrument cable laying method is characterized in that: the method comprises the following steps:
(1) line number marking: pasting cable line number marks on instrument cables on an instrument cable reel on a laying site one by one;
(2) preliminary positioning of the cable threading pipe: providing a threading pipe primary positioning device, and threading instrument cables into the threading pipe one by one according to the principle that one threading hole penetrates one instrument cable and the line number identification; the positioning function is to prevent adjacent cables from winding each other in the transmission process; the cable threading pipe primary positioning tool is composed of 3-10 threading pipes with the diameter of 2cm and the length of 5cm, which are welded on a support plate with the length of 10cm and the width of 5cm, and the support plate is welded on a threading pipe support;
(3) cable carriage repositioning: providing a pulley block with a plurality of grooves, and sequentially placing cables from the initial positioning of the threading pipe into the grooves of the pulley block according to the line number marks in sequence; according to the situation of an installation site, fixing a pulley block every 10-20 m; the cable sliding frame comprises a sliding frame support, a connecting rod, a bearing, a groove pulley, a fixing nut and a support, wherein the sliding frame support is connected with the support in a welding mode; the depth of the groove is 3-5 cm;
(4) conveying by a cable laying machine: fixing one cable laying machine every 50-100m according to the field condition, and fixing one operator for each cable laying machine; sequentially putting cables positioned by a threading pipe into a 1 st cable laying machine according to line number marks, after the cables of the 1 st cable laying machine are laid, informing a 1 st cable laying machine operator to start the 1 st cable laying machine by a laying person, pulling the cables onto a cable sliding frame adjacent to the 1 st cable laying machine by the laying person under the conveying of the 1 st cable laying machine, informing the 1 st cable laying machine operator to stop the cable laying machine by the laying person through an interphone, sequentially putting the cables into a cable sliding frame groove adjacent to the 1 st cable laying machine by the laying person according to the line number marks, and then informing the 1 st cable laying machine operator to start the 1 st cable laying machine to continuously transmit instrument cables through the interphone; according to the configuration conditions of the cable sliding frame and the cable laying machine on the installation site, according to the configuration sequence of the cable sliding frame and the cable laying machine, a laying person gradually transmits the cable to the cable bridge frame in a mode of informing an operator of the cable laying machine of simultaneously operating the cable laying machine to start or stop by using the interphone.
CN201811554916.6A 2018-12-19 2018-12-19 A kind of instrument cable laying method Active CN109616953B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811554916.6A CN109616953B (en) 2018-12-19 2018-12-19 A kind of instrument cable laying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811554916.6A CN109616953B (en) 2018-12-19 2018-12-19 A kind of instrument cable laying method

Publications (2)

Publication Number Publication Date
CN109616953A CN109616953A (en) 2019-04-12
CN109616953B true CN109616953B (en) 2021-04-02

Family

ID=66009535

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811554916.6A Active CN109616953B (en) 2018-12-19 2018-12-19 A kind of instrument cable laying method

Country Status (1)

Country Link
CN (1) CN109616953B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112490945A (en) * 2020-11-10 2021-03-12 上海宝冶集团有限公司 Quality control method for improving one-time success rate of withstand voltage of cable sheath

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204216501U (en) * 2014-11-28 2015-03-18 国家电网公司 Cable laying tool
CN105226574A (en) * 2015-11-05 2016-01-06 山西省工业设备安装有限公司 Cable laying method and lay part
CN108242780A (en) * 2017-12-15 2018-07-03 中色十二冶金建设有限公司 A kind of device and its laying method for being suitble to different occasion cable layings

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201891041U (en) * 2010-12-03 2011-07-06 宁波凯特机械有限公司 Wire-separating and winding-resistant device of cascade unit
CN203283965U (en) * 2013-05-24 2013-11-13 江阴市江凌科技有限公司 Instrument monitoring control box with cable reeling and unreeling function
US10295106B2 (en) * 2015-06-19 2019-05-21 Ulc Robotics, Inc. Launch system for a pressurized pipeline
CN205081400U (en) * 2015-11-05 2016-03-09 山西省工业设备安装有限公司 Cable laying spare
CN105932633A (en) * 2016-06-03 2016-09-07 成都格瑞思文化传播有限公司 Pay-off pulley

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204216501U (en) * 2014-11-28 2015-03-18 国家电网公司 Cable laying tool
CN105226574A (en) * 2015-11-05 2016-01-06 山西省工业设备安装有限公司 Cable laying method and lay part
CN108242780A (en) * 2017-12-15 2018-07-03 中色十二冶金建设有限公司 A kind of device and its laying method for being suitble to different occasion cable layings

Also Published As

Publication number Publication date
CN109616953A (en) 2019-04-12

Similar Documents

Publication Publication Date Title
CN103241586B (en) Under shed telpher and cable installatition construction method
KR101462842B1 (en) Apparatus and method for installing underground cable using vehicle
IT201900001841A1 (en) CABLE RECOVERY MACHINE
CN105448395B (en) The extra large cable joint and its online Transition Technology of a kind of different sheathed structures
CN102620057B (en) Pipe arrangement method and pipe arrangement device for pipe gallery
CN107785122B (en) A kind of preparation process of seamless Through ground wire
CN109616953B (en) A kind of instrument cable laying method
CN112051282B (en) Electrified X-ray flaw detection device and method for splicing sleeve of overhead transmission line
IT201900001845A1 (en) CABLE RECOVERY MACHINE
CN210393136U (en) Mop mechanism for cloth laying cutting bed
KR101454625B1 (en) Apparatus for laying of cable
CN109004579A (en) A kind of network engineering threading apparatus
CN216272381U (en) Apparatus and system for threading cable into tubules attached to electrically heated conduit
CN205051256U (en) A pay -off for power distribution network
CN104209350A (en) Band steel traction connection structure and band penetration method for continuous band steel unit
KR100981711B1 (en) Guide harness for 3-phase cable pulling
CN107302195A (en) Cable laying method
CN211056399U (en) Be used for interval cable unwrapping wire auxiliary device
CN209352373U (en) A pay-off device for insulated wire production
CN102390754B (en) Semiautomatic paying-off device
CN204847571U (en) Aluminium pole pay -off
CN203205778U (en) Bottom-opened cable feeder
CN106772861B (en) Special accommodating tool for optical fibers of transformer substation
KR101361065B1 (en) New railway roadbed laying method for simultaneously three thermal power cable
CN218289890U (en) Quick pay-off suitable for corner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 252000 Lu Xi Group's residence, Chemical Industry Park, High-tech Industrial Development Zone, Liaocheng City, Shandong Province

Patentee after: Zhonghua Luxi Engineering Co.,Ltd.

Country or region after: China

Address before: 252000 new chemical materials Industrial Park, Liaocheng high tech Industrial Development Zone, Shandong Province

Patentee before: LUXI INDUSTRY EQUIPMENT Co.,Ltd.

Country or region before: China