CN109611142A CN201811484832.XA CN201811484832A CN109611142A CN 109611142 A CN109611142 A CN 109611142A CN 201811484832 A CN201811484832 A CN 201811484832A CN 109611142 A CN109611142 A CN 109611142A
Authority
CN
China
Prior art keywords
pipe
wind deflector
gas
movable
air inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811484832.XA
Other languages
Chinese (zh)
Inventor
刘勇
冷光海
罗辉
杨光友
包文涛
魏宴军
张前荣
陈宇满
林华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Original Assignee
Guizhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University filed Critical Guizhou University
Priority to CN201811484832.XA priority Critical patent/CN109611142A/en
Publication of CN109611142A publication Critical patent/CN109611142A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F5/00Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires
    • E21F5/02Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires by wetting or spraying
    • E21F5/04Spraying barriers

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The invention discloses a kind of coal mine gas fire prevention fast pumping devices, including blast pipe and exhaust pipe, air inlet fan is provided on the inside of the blast pipe, and the rear end of blast pipe is provided with the first movable wind deflector, the end of the blast pipe is provided with depositing dust storehouse, and the outside of the bleeding point is arranged the second movable wind deflector, is provided with jet pipe on the inside of the depositing dust storehouse, return pipe is provided with below the depositing dust storehouse, the exhaust pipe is located at the rear end in depositing dust storehouse.Coal mine gas fire prevention fast pumping device is provided with the first movable wind deflector and the second movable wind deflector, the intake of methane gas can be included by mine at fresh air at the mobile adjusting change blast pipe to the first movable wind deflector and the second movable wind deflector and bleeding point in the use process of device, to suitably be diluted to the gas entered inside device, so that the gas density in device is maintained at safe concentration, prevents from causing gas combustion to explode in discharge process.

Description

A kind of coal mine gas fire prevention fast pumping device
Technical field
The present invention relates to coal mining correlative technology field, specially a kind of coal mine gas fire prevention fast pumping dress It sets.
Background technique
During busy exploitation, it will usually generate more methane gas, the methane gas in coal mine road is not only The health for influencing whether staff also has the danger of combustion explosion when gas density is higher, it is therefore desirable to mine Interior methane gas carries out pump drainage, and existing coal mine gas exhaust device is the common exhaust fan general watt of use mostly This is pumped, but cannot carry out certain control to the gas gas density during pump drainage, in gas density compared with Gao Shijin Row pump drainage is also easy to that accident occurs, and influences coal mine production safety.
In view of the above-mentioned problems, carrying out innovative design on the basis of original coal mine gas prevents fires fast pumping device.
Summary of the invention
The purpose of the present invention is to provide a kind of coal mine gas fire prevention fast pumping devices, to solve above-mentioned background skill It is proposed that gas exhaust device is not easy to the gas density of control pump drainage gas, is easy to happen unexpected problem in art.
To achieve the above object, the invention provides the following technical scheme: a kind of coal mine gas fire prevention fast pumping dress It sets, including blast pipe and exhaust pipe, air inlet fan is provided on the inside of the blast pipe, and the rear end of blast pipe is provided with activity Slot, and the first movable wind deflector is provided on the inside of movable slot, the end of the blast pipe is provided with depositing dust storehouse, and drops It is provided with bleeding point on the outside of dirt storehouse, loose slot is provided on the outside of the bleeding point, and be provided with second on the inside of loose slot Movable wind deflector is provided with jet pipe on the inside of the depositing dust storehouse, and is provided with spray orifice below jet pipe, and jet pipe rear end is arranged There is water pump, is provided with return pipe below the depositing dust storehouse, and be provided with water tank below return pipe, and set on the inside of water tank It is equipped with filter screen, the exhaust pipe is located at the rear end in depositing dust storehouse, and air blower is provided on the inside of exhaust pipe.
Preferably, the first movable wind deflector is provided between the blast pipe and depositing dust storehouse, and the first movable wind deflector exists Slidable structure is constituted in movable slot.
Preferably, the left and right ends in the depositing dust storehouse are connected with each other with exhaust pipe and blast pipe respectively, and blast pipe and pumping The end of comb is respectively arranged with air inlet fan and air blower.
Preferably, the structure of the described second movable wind deflector and bleeding point is coincide, and the second movable wind deflector and depositing dust storehouse Between slidable structure constituted by loose slot.
Preferably, the jet pipe is evenly distributed on the inner upper in depositing dust storehouse, and spray orifice is evenly distributed with below jet pipe, And water pump is provided between jet pipe and water tank.
Preferably, it is connected with each other between the water tank and the bottom in depositing dust storehouse by return pipe, and between water tank and water pump It is provided with filter screen.
Compared with prior art, the fast pumping device the beneficial effects of the present invention are: the coal mine gas is prevented fires,
1, the first movable wind deflector and the second movable wind deflector, cooperation activity slot and work in the use process of device are provided with Dynamic slot uses, and can change fresh sky at blast pipe by the mobile adjusting to the first movable wind deflector and the second movable wind deflector Mine includes the intake of methane gas at gas and bleeding point, to suitably be diluted to the gas entered inside device, is protecting While holding to methane gas progress pump drainage, so that the gas density in device is maintained at safe concentration, prevent from making in discharge process It explodes at gas combustion;
2, it is provided with depositing dust storehouse, cooperates jet pipe, spray orifice and water pump to use in the use process of device, it can be in order in depositing dust storehouse Interior ejection water mist carries out depositing dust processing to the dusty gas entered in device, while gas humidity can be improved, and plays certain Fireproofing function, while return pipe, water tank and filter screen being cooperated to use, it can also subtract convenient for being recycled to depositing dust with water The waste of few water resource, improves the practicability of device.
Detailed description of the invention
Fig. 1 is positive structure schematic of the present invention;
Fig. 2 is depositing dust storehouse front cross-sectional structural schematic diagram of the present invention;
Fig. 3 is jet pipe present invention looks up structural representation of the present invention;
Fig. 4 is the movable wind deflector structural schematic diagram of the present invention first;
Fig. 5 is the movable wind deflector structural schematic diagram of the present invention second.
In figure: 1, blast pipe;2, air inlet fan;3, movable slot;4, the first movable wind deflector;5, depositing dust storehouse;6, bleeding point; 7, loose slot;8, the second movable wind deflector;9, jet pipe;10, spray orifice;11, water pump;12, return pipe;13, water tank;14, filter screen; 15, exhaust pipe;16, air blower.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-5 is please referred to, the present invention provides a kind of technical solution: a kind of coal mine gas fire prevention fast pumping device, It is living including blast pipe 1, air inlet fan 2, the movable wind deflector 4 of movable slot 3, first, depositing dust storehouse 5, bleeding point 6, loose slot 7, second Dynamic wind deflector 8, jet pipe 9, spray orifice 10, water pump 11, return pipe 12, water tank 13, filter screen 14, exhaust pipe 15 and air blower 16, into The inside of air hose 1 is provided with air inlet fan 2, and the rear end of blast pipe 1 is provided with movable slot 3, and the inside of movable slot 3 is set It is equipped with the first movable wind deflector 4, the end of blast pipe 1 is provided with depositing dust storehouse 5, and the outside in depositing dust storehouse 5 is provided with bleeding point 6, The outside of bleeding point 6 is provided with loose slot 7, and the inside of loose slot 7 is provided with the second movable wind deflector 8, the inside in depositing dust storehouse 5 It is provided with jet pipe 9, and the lower section of jet pipe 9 is provided with spray orifice 10, and 9 rear end of jet pipe is provided with water pump 11, the lower section in depositing dust storehouse 5 It is provided with return pipe 12, and the lower section of return pipe 12 is provided with water tank 13, and the inside of water tank 13 is provided with filter screen 14, taken out Comb 15 is located at the rear end in depositing dust storehouse 5, and the inside of exhaust pipe 15 is provided with air blower 16.
The first movable wind deflector 4 is provided between the blast pipe 1 and depositing dust storehouse 5 of this example, and the first movable wind deflector 4 is in work Slidable structure is constituted in dynamic slot 3, convenient for adjusting by the first movable wind deflector 4 to the ventilation quantity of fresh air outside Section.
The left and right ends in depositing dust storehouse 5 are connected with each other with exhaust pipe 15 and blast pipe 1 respectively, and blast pipe 1 and exhaust pipe 15 End be respectively arranged with air inlet fan 2 and air blower 16, convenient for by device and it is external carry out air-flow exchange, positioned at it is external into Blower 2 and air blower 16 can avoid contact with the high methane concentration range in coal mine.
The structure of second movable wind deflector 8 and bleeding point 6 is coincide, and is passed through between the second movable wind deflector 8 and depositing dust storehouse 5 Loose slot 7 constitutes slidable structure, convenient for the extraction rate of gas is adjusted by the second movable wind deflector 8, convenient for matching It closes first 4 pairs of gas gas densities entered inside device of movable wind deflector and is diluted control, avoid that gas combustion occurs.
Jet pipe 9 is evenly distributed on the inner upper in depositing dust storehouse 5, and the lower section of jet pipe 9 is evenly distributed with spray orifice 10, and sprays Water pump 11 is provided between pipe 9 and water tank 13, convenient for carrying out depositing dust to the pit gas entered in device by spraying water mist, together When to a certain degree improve device in humidity, play certain flameproof effect.
It is connected with each other between water tank 13 and the bottom in depositing dust storehouse 5 by return pipe 12, and is set between water tank 13 and water pump 11 It is equipped with filter screen 14, convenient for being recycled to the depositing dust in device with water.
Working principle: when using coal mine gas fire prevention fast pumping device, first by the power supply of device and electricity Net is connected with each other, and air inlet fan 2 and air blower 16 are mounted on to external appropriate area according to Fig. 1, depositing dust storehouse 5 is mounted on The region of drawing-off gas is needed in mine, can be begun to use.
In the use process of device according to Fig. 1-3, air inlet fan 2 can drive fresh air outside to pass through blast pipe 1 enter depositing dust storehouse 5 inside, while in mine containing methane gas can under the action of rear air blower 16 by bleeding point 6 into Enter the inside of depositing dust storehouse 5 and fresh air mixing, prevent the gas density in gas is excessively high from causing certain danger, and water pump 11 can be with It drives the liquid in water tank 13 by spraying after jet pipe 9 from spray orifice 10, dusty gas in the mine in depositing dust storehouse 5 is carried out at depositing dust Reason, while gas humidity in depositing dust storehouse 5 is improved, certain flameproof effect is played, and the spray book fallen can be from return pipe 12 return to water tank 13, are reused that can provide feed pump 11 after the filtering of filter screen 14, and treated gas Body can be discharged under the action of air blower 16 from exhaust pipe 15.
It, can also be by the first movable wind deflector 4 in movable slot 3 in conjunction with shown in Fig. 4-5 in the use process of device In mobile adjusting change the air inlet rate of fresh air at blast pipe 1, while the second active catch outside adjustable bleeding point 6 Aerofoil 8, by the air inlet rate of the second movable wind deflector 8 pit gas at the mobile change bleeding point 6 in loose slot 7, from And change the gas density for entering mixed gas in depositing dust storehouse 5, so that the methane gas in device is maintained at safe concentration range Interior carry out pump drainage, the content being not described in detail in this specification belong to the prior art well known to professional and technical personnel in the field.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (6)

1.一种煤矿井下瓦斯防火快速抽排装置,包括进风管(1)和抽排管(15),其特征在于:所述进风管(1)的内侧设置有进风机(2),且进风管(1)的后端设置有活动插槽(3),并且活动插槽(3)的内侧设置有第一活动挡风板(4),所述进风管(1)的末端设置有降尘仓(5),且降尘仓(5)的外侧设置有抽气口(6),所述抽气口(6)的外侧设置有活动槽(7),且活动槽(7)的内侧设置有第二活动挡风板(8),所述降尘仓(5)的内侧设置有喷管(9),且喷管(9)的下方设置有喷孔(10),并且喷管(9)后端设置有水泵(11),所述降尘仓(5)的下方设置有回水管(12),且回水管(12)的下方设置有水箱(13),并且水箱(13)的内侧设置有过滤网(14),所述抽排管(15)位于降尘仓(5)的后端,且抽排管(15)的内侧设置有鼓风机(16)。1. An underground gas fire-resisting rapid pumping and discharging device, comprising an air inlet pipe (1) and a suction and exhaust pipe (15), characterized in that: the inner side of the air inlet pipe (1) is provided with an air inlet (2), And the rear end of the air inlet duct (1) is provided with a movable slot (3), and the inner side of the movable slot (3) is provided with a first movable wind deflector (4), and the end of the air inlet duct (1) A dust suppression bin (5) is provided, and an air extraction port (6) is provided on the outside of the dust suppression bin (5), and a movable groove (7) is provided on the outer side of the air extraction port (6), and the inner side of the movable groove (7) is provided with There is a second movable wind deflector (8), a spray pipe (9) is arranged on the inner side of the dust suppression chamber (5), and a spray hole (10) is arranged below the spray pipe (9), and the spray pipe (9) The rear end is provided with a water pump (11), a water return pipe (12) is provided below the dust suppression chamber (5), and a water tank (13) is provided below the water return pipe (12), and the inner side of the water tank (13) is provided with a water tank (13). A filter screen (14), the suction and discharge pipe (15) is located at the rear end of the dust suppression chamber (5), and a blower (16) is arranged on the inner side of the suction and discharge pipe (15). 2.根据权利要求1所述的一种煤矿井下瓦斯防火快速抽排装置,其特征在于:所述进风管(1)和降尘仓(5)之间设置有第一活动挡风板(4),且第一活动挡风板(4)在活动插槽(3)内构成可滑动结构。2 . The device for rapid fire extraction and extraction of underground gas in coal mines according to claim 1 , wherein a first movable windshield (4) is arranged between the air inlet pipe (1) and the dust suppression bin (5). 3 . ), and the first movable wind deflector (4) forms a slidable structure in the movable slot (3). 3.根据权利要求1所述的一种煤矿井下瓦斯防火快速抽排装置,其特征在于:所述降尘仓(5)的左右两端分别与抽排管(15)和进风管(1)相互连接,且进风管(1)和抽排管(15)的末端分别设置有进风机(2)和鼓风机(16)。3. A kind of underground coal mine gas fireproof quick extraction device according to claim 1, characterized in that: the left and right ends of the dust suppression bin (5) are respectively connected with the extraction and exhaust pipe (15) and the air inlet pipe (1) They are connected to each other, and the ends of the air inlet pipe (1) and the exhaust pipe (15) are respectively provided with an inlet fan (2) and a blower (16). 4.根据权利要求1所述的一种煤矿井下瓦斯防火快速抽排装置,其特征在于:所述第二活动挡风板(8)和抽气口(6)的结构吻合,且第二活动挡风板(8)和降尘仓(5)之间通过活动槽(7)构成可滑动结构。4. The device for rapid fire extraction and extraction of gas in underground coal mines according to claim 1, characterized in that: the structure of the second movable wind deflector (8) and the air extraction port (6) are consistent, and the second movable windshield A slidable structure is formed between the wind plate (8) and the dust suppression bin (5) through the movable groove (7). 5.根据权利要求1所述的一种煤矿井下瓦斯防火快速抽排装置,其特征在于:所述喷管(9)均匀分布在降尘仓(5)的内部上方,且喷管(9)的下方均匀分布有喷孔(10),并且喷管(9)和水箱(13)之间设置有水泵(11)。5. A kind of underground coal mine gas fireproof rapid extraction device according to claim 1, characterized in that: the nozzle (9) is evenly distributed above the interior of the dust suppression bin (5), and the nozzle (9) is There are spray holes (10) evenly distributed below, and a water pump (11) is arranged between the spray pipe (9) and the water tank (13). 6.根据权利要求1所述的一种煤矿井下瓦斯防火快速抽排装置,其特征在于:所述水箱(13)和降尘仓(5)的底部之间通过回水管(12)相互连接,且水箱(13)和水泵(11)之间设置有过滤网(14)。6. A kind of underground coal mine gas fireproof rapid pumping and discharging device according to claim 1, characterized in that: the water tank (13) and the bottom of the dust suppression bin (5) are connected to each other through a return pipe (12), and A filter screen (14) is arranged between the water tank (13) and the water pump (11).
CN201811484832.XA 2018-12-05 2018-12-05 A rapid gas extraction and drainage device for underground gas in coal mines Pending CN109611142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811484832.XA CN109611142A (en) 2018-12-05 2018-12-05 A rapid gas extraction and drainage device for underground gas in coal mines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811484832.XA CN109611142A (en) 2018-12-05 2018-12-05 A rapid gas extraction and drainage device for underground gas in coal mines

Publications (1)

Publication Number Publication Date
CN109611142A true CN109611142A (en) 2019-04-12

Family

ID=66007294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811484832.XA Pending CN109611142A (en) 2018-12-05 2018-12-05 A rapid gas extraction and drainage device for underground gas in coal mines

Country Status (1)

Country Link
CN (1) CN109611142A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821543A (en) * 2019-11-18 2020-02-21 侯琛 Explosion-proof ventilation unit for underground works
CN116378748A (en) * 2023-05-18 2023-07-04 云南滇东雨汪能源有限公司 Gas processing equipment and gas extraction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0842300A (en) * 1994-07-27 1996-02-13 Fujita Corp Dust removal processing method and dust removal processing device in tunnel construction
JP2006239693A (en) * 2006-06-05 2006-09-14 Sakamoto Shokai:Kk Wet dust collector
CN203035202U (en) * 2012-12-06 2013-07-03 内蒙古福城矿业有限公司 Far-pressing-near-absorption dedusting system of fully mechanized excavation face
CN203145986U (en) * 2013-03-12 2013-08-21 河南理工大学 Compressed air diverting wall-attached air ventilator capable of adjusting air volume
CN204253093U (en) * 2014-10-23 2015-04-08 董永华 A kind of cleaning type ventilation fan for colliery face
CN207892642U (en) * 2018-03-03 2018-09-21 周华梅 A kind of underground wet scrubber
CN208153050U (en) * 2018-05-10 2018-11-27 永贵能源开发有限责任公司新田煤矿 A kind of coal mine spray dust remover

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0842300A (en) * 1994-07-27 1996-02-13 Fujita Corp Dust removal processing method and dust removal processing device in tunnel construction
JP2006239693A (en) * 2006-06-05 2006-09-14 Sakamoto Shokai:Kk Wet dust collector
CN203035202U (en) * 2012-12-06 2013-07-03 内蒙古福城矿业有限公司 Far-pressing-near-absorption dedusting system of fully mechanized excavation face
CN203145986U (en) * 2013-03-12 2013-08-21 河南理工大学 Compressed air diverting wall-attached air ventilator capable of adjusting air volume
CN204253093U (en) * 2014-10-23 2015-04-08 董永华 A kind of cleaning type ventilation fan for colliery face
CN207892642U (en) * 2018-03-03 2018-09-21 周华梅 A kind of underground wet scrubber
CN208153050U (en) * 2018-05-10 2018-11-27 永贵能源开发有限责任公司新田煤矿 A kind of coal mine spray dust remover

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821543A (en) * 2019-11-18 2020-02-21 侯琛 Explosion-proof ventilation unit for underground works
CN110821543B (en) * 2019-11-18 2021-04-27 江苏坚威防护工程科技有限公司 Explosion-proof ventilation unit for underground works
CN116378748A (en) * 2023-05-18 2023-07-04 云南滇东雨汪能源有限公司 Gas processing equipment and gas extraction method

Similar Documents

Publication Publication Date Title
CN101757825A (en) Method and equipment for suppressing dust with dry mist
CN202467890U (en) Mining wet-type pneumatic deduster
CN109736802B (en) Foam-water mist-air curtain three-stage linkage dust fall system and dust fall method
CN109611142A (en) A rapid gas extraction and drainage device for underground gas in coal mines
CN104564068A (en) Comprehensive dust preventing and treating device for fully-mechanized coal mining working face with large mining height of coal mine
CN104632268A (en) Coal mine safety dust removing device
CN101575975A (en) Dust removing method and device of cantilever-type comprehensive mechanized development machine
CN204220479U (en) A kind of sand powder seperator
CN202970548U (en) Gas jet flow dust collector for mine drilling
CN204973361U (en) Pulse deduster
CN104989446B (en) Dust degrading system for underground tunnel drilling and blasting
CN102913271A (en) Dust removal system for spraying machine
CN103410555B (en) Gallery dust remover for coal mine safety production
CN203925351U (en) A kind of for firedamp taking-out discharging drilling orifice dust catcher
CN209310437U (en) Staged biomass power generation fuel particle drying unit
CN213392150U (en) Dust fall tool for coal mining tunneling machine
CN211666762U (en) Air dust removal device for coal mine underground roadway
CN102359390A (en) Combined-type fence-wet fiber grid dust remover
CN212915004U (en) Metal dust separating device
CN107185458A (en) Continuous granulation machine
CN204841293U (en) A dust suppression device for building broken hole of rubbish
CN204041093U (en) A kind of down-hole pneumatic dedusting system
CN208373407U (en) Dry spray booth
CN208106477U (en) A kind of dust guard of coal underground separation system
CN207813611U (en) Coalcutter is with machine deduster

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412