Summary of the invention
It is an object of the invention to: it is directed to above-mentioned technical problem of the existing technology, is provided a kind of using electromagnet mode
The mould of plate sprays method, effectively prevents the concrete springback problem during whitewashing, and improve the environmental quality of construction site.
The technical solution of the technology of the present invention is achieved in that a kind of mould using electromagnetism template sprays method, the method
Include the following steps:
S1: mould spray booth garage enters the tunnel construction sections to be painted poured, and revolution large arm is opened in firing platform car exhibition, and revolution large arm takes support
Frame and curtain electromagnetism template excavation face wherein side close to the bottom of two adjacent steel arch-shelfs;
S2: electromagnetism template is located to one section before support frame and is close to two or more steel arch-shelfs, and and steel arch-shelf from bottom
Form die cavity to be poured;
S3: adjustment nozzle position and angle opens spray head and Open Side Down at the top of transverse mode control sprays into rapid hardening coagulation
Soil completes pouring for first section concrete;
S4: after section concrete solidification at the beginning of mold cavity bottoms, being affixed on of extending upwards of the modular unit of electromagnetism template is described
On steel arch-shelf, new die cavity is formed, when electromagnetism template extends, spray head is lasting to the modular unit and steel arch-shelf that newly release
Fast hardening concrete is sprayed into the die cavity newly formed, is poured with completing the preliminary bracing of this section unilateral excavation face.
Mould of the present invention using electromagnetism template sprays method, further includes step S5, after top concrete solidification, returns
Turn large arm gradually to move down with support frame and electromagnetism template, while roller being driven to reversely rotate, recycles curtain electromagnetism template;Revolution
Large arm is rotated horizontally with support frame and electromagnetism template, so that the other side that electromagnetism template is secondary with section towards tunnel, and repeat to walk
Rapid S1-S4, the preliminary bracing for completing this section of tunnel other side pour.
Mould of the present invention using electromagnetism template sprays method, in step S1 and S2, drives roller in drive motor
Under the action of rotate in the forward direction, discharge curtain electromagnetism template so that the free end of electromagnetism template hangs down into its bottom and shores with template
The bottom of frame flushes, and adjusts the left-right position of support frame, to guarantee that the electromagnetism template of curtain can laterally cover the steel arch-shelf;So
The electromagnetism template outer surface being located at before support frame released is tightly attached on steel arch-shelf afterwards, and guarantees the bottom edge of electromagnetism template
It is contacted with tunnel excavation bottom surface, so that electromagnetism template, steel arch-shelf and tunnel bottom surface are enclosed with open-topped transverse direction
Die cavity;
Mould of the present invention using electromagnetism template sprays method, in step s 2: successively connecting template list from the bottom up
The power circuit of first electromagnet, so that the modular unit magnetic absorption contacted with steel arch-shelf is on steel arch-shelf;Support is adjusted simultaneously
The pitch angle of frame so that the outer surface of electromagnetism template is agreed with the radian of steel arch-shelf to greatest extent, and adjusts revolution large arm
So that template shore that frame withstands electromagnetism template and steel arch-shelf be bonded section;
Mould of the present invention using electromagnetism template sprays method, in step s 4, solidifying to section concrete at the beginning of mold cavity bottoms
Gu after, revolution large arm drives support frame gradually to move up along steel arch-shelf, while being again started up driving roller and continuous positive rotation
Turn, continuously to discharge the modular unit of curtain electromagnetism template.
Mould of the present invention using electromagnetism template sprays method, in step s 4, the rate of release and branch of electromagnetism template
Support moves up that speed is equal, and when guaranteeing that the modular unit newly released and steel arch-shelf contact, institute's band electromagnet is powered immediately
It is adsorbed on steel arch-shelf.
Mould of the present invention using electromagnetism template sprays method, during support frame is moved up along steel arch-shelf, template top
Idler wheel of shoring on support rolls across at the back of electromagnetism template, while during scrolling, forming direct branch to electromagnetism template
Support.
Mould of the present invention using electromagnetism template sprays method, in the release of electromagnetism template and removal process, electromagnet mode
The central links in backboard portion are slipped over from the annular groove of upper guide roller and lower steering roll;The chain of two sides is located at centre and shores list
Member and side are shored and are slided between unit.
Mould of the present invention using electromagnetism template sprays method, mixed with the preliminary bracing poured at left and right sides of section time tunnel
Solidifying soil layer is overlapped in tunnel top, and after lap-joint tamps with template support, strike off, complete described section tunnel wheel
Wide supporting.
The invention has the benefit that by the provided mould spray apparatus for having electromagnetism template, it can be by curtain electromagnet mode
Plate is adsorbed on tunnel steel arch frame, and the die cavity poured is formd between electromagnetism template and steel arch-shelf, so that spray head is mixed in injection
When solidifying soil, it can effectively stop the rebound path of concrete, solve the technical issues of concrete springback, significantly reduce tunnel and apply
Work cost, and improve the construction quality of branch sheath.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The technology of the present invention is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain this hair
It is bright, it is not intended to limit the present invention.
As shown, having the mould spray apparatus of electromagnetism template, the mould spray apparatus includes preceding arm mechanism 1, support frame 2, mould
Plate shores frame 3, electromagnetism template 4 and spray head 5, and the preceding arm mechanism 1 is for being rotatably mounted to trolley revolution large arm, support
The front end of arm mechanism 1, template shore the top that support frame 2 is arranged in frame 3 before frame 2 is fixed on, and electromagnetism template 4 is equipped with electromagnet
43, can be adsorbed on tunnel steel arch frame by electromagnet in the energized state so that electromagnetism template 4 and steel arch-shelf and scar it
Between form die cavity, spray head 5 can be to the die cavity ejection supporting concrete formed between electromagnetism template 4 and steel arch-shelf.
Electromagnetism template 4 is the rollable structure of curtain, integrally can be similar to the state of rolling screen door.Electromagnetism template 4 is by several moulds
Plate unit composition, it is whole that two or more the chains 44 being parallel to each other that the modular unit passes through back are connected to become electromagnetism template 4
Body;Each modular unit is mounted on independent electromagnet 43, and has independent current supply circuit;When curtain electromagnetism template 4 is flat
Backrush is accommodated on driving roller 24, and after the electromagnet of each modular unit is powered, both ends can be adsorbed on adjacent two simultaneously
On steel arch-shelf more than root.
The modular unit includes template master unit 41 and the template pair unit 42 for being connected to 41 both ends of template master unit, institute
Electromagnet 43 is stated to be mounted on the template pair unit 42 at both ends.
The template master unit 41 and template pair unit 42 are rectangular parallelepiped structure, and are connected by bulb.
The template pair unit 42 includes pair unit U-board 421 and the bulb for being connected to 421 connecting pin of pair unit U-board
Pin 422, ball stud 422 include bulb plate 422a and the bulb 422b being fixed on bulb plate 422a, and the bulb plate 422a can
It is fixed in the end slot of pair unit U-board 421 by welding.
The both ends of the pair unit U-board 421 are further fixed on L-shaped fixed base plate 423, can be by being welded and fixed;It is described
Electromagnet 43 is fixed on fixed base plate 423 by dormant bolt.The absorption of the electromagnet 43 faces outwardly, and can directly adsorb in
On steel arch-shelf.
The template master unit 41 includes master unit U-board 411, and half is provided in two end slots of master unit U-board 411
Ball cup 412, and fixed bulb 422b by bulb FE Tiler 413.
The open side of master unit U-board 411, which is located between the hemisphere headstock 412 at both ends, is provided with master unit cover board 414.Institute
Stating master unit cover board 414 can be plate or be all U-board, and the opening for being flush to master unit U-board 411 is solid by welding
It is fixed.
The length of the template master unit 41 is greater than the length of the template pair unit 42.
The template master unit 41 of the curtain electromagnetism template 4 and the back of two Side Template pair units 42 are respectively arranged with chain
Fixation hole 45, the chain 44 are made of several chain units 441, and each chain unit 441 is welded with chain fixed plate 442,
And chain fixed plate 442 is fixed on corresponding chain fixation hole 45 by bolt.
Relative to modular unit be overall structure when, when two adjacent steel arch-shelfs have certain straggly, mould of monoblock type
Formation line contact between the electromagnet and steel arch-shelf at plate unit both ends, the active force of magnetic absorption reduce, and may be
Gap is formed between electromagnetism template 4 and steel arch-shelf, concrete is caused to reveal.And modular unit is arranged to three stage structure, and
On the template pair unit 42 that electromagnet 43 is installed to both ends, and pass through bulb between template pair unit 42 and template master unit 41
Connection, so that template pair unit 42 can have certain adjustment space relative to template master unit 41, accordingly even when adjacent steel arch
There is fluctuating straggly between frame, the adjustment of adaptability can also be done, so that electromagnet 43 keeps the face contact between steel bracket,
To increase adsorption capacity, and keep good leakproofness.
It includes two pieces or more the vertical top bracing plate|s 31 being parallel to each other that the template, which shores frame 3, and the front side of top bracing plate| 31 is along perpendicular
Several idler wheel 32 is shored to evenly spaced be provided with.
One or more support beam 33 is provided with after the vertical top bracing plate| 31, the support beam 33 and every piece erect
It is connected to compressed oil cylinder 331 is all passed through between top bracing plate| 31, while being also connected with counterbalance spring 332, counterbalance spring 332 is set in
On the piston rod of compressed oil cylinder 331.Two or more guiding crossbeams 34 are additionally provided with after the vertical top bracing plate| 31, every is led
The corresponding every piece of vertical top bracing plate| 31 of crossbeam 34 is provided with guide bearing 341, the guide bearing 341 is set in correspondence and is fixed on
On guiding axis 311 on vertical top bracing plate| 31.The support beam 33 is located at after guiding crossbeam 34, and the compressed oil cylinder
331 gaps being oriented between crossbeam 34 from adjacent two pass through.
More specifically, in the present embodiment, it includes 4 pieces of vertical top bracing plate|s 31 that the template shores frame 3 altogether, wherein intermediate
Two pieces of adjacent vertical top bracing plate|s 31 top and bottom between be respectively connected with connection roll shaft 312 and lower connection roll shaft 313,
Guide roller 312a is installed on the upper connection roll shaft 312, lower steering roll 313a is installed on lower connection roll shaft 313, and
The outer diameter of the lower steering roll 313a is equal to the outer diameter of the idler wheel 32, and the outer diameter of the upper guide roller 312a is greater than described shore
The outer diameter of idler wheel 32, but the guide roller 312a and the front end cambered surface for shoring idler wheel 32 on same top bracing plate| 31 keep neat
It is flat.The two pieces of adjacent vertical top bracing plate|s 31 in centre are connected to become entirety in this way, formation is intermediate to shore unit, is mainly used for shoring
The template master unit 41 of electromagnetism template 4;And the vertical top bracing plate| 31 of two sides forms the side for shoring unit independently of centre and shores list
Member is respectively used to shore the template pair unit 42 of electromagnetism template 4.Purpose is, is adapted between adjacent two steel arch-shelfs
When with certain dislocation, unit is shored in side still can withstand on phase for the template pair unit 42 at 4 both ends of electromagnetism template of curtain
On two adjacent steel arch-shelfs, to form strong support, so that the magnetic adhesive plaster between electromagnetism template 4 and steel arch-shelf is closer
With it is firm, avoid the appearance of " quick-fried mould ", concrete will not be from both ends side leakage;And unit is shored then in electromagnetism template 4 in centre
The template master unit 41 of center portion point forms powerful support, so that the die cavity stability formed is stronger.
It is respectively arranged with identical guiding big roller 321 at the top of two pieces of vertical top bracing plate|s 31 in the outside, it is described
The outer diameter for being oriented to big roller 321 is identical as the outer diameter of the upper guide roller 312a.
Preferably, the front side of the vertical top bracing plate| 31 is equipped with the arc being adapted with steel arch-shelf;Two pieces of outside are vertical
The spacing between two column support idler wheels 32 on top bracing plate| 31 is equal to the spacing between adjacent two steel arch-shelfs.
Preferably, annular groove 312b is respectively arranged in the middle part of upper guide roller 312a and lower steering roll 313a and annular is recessed
Slot 313b, for accommodating the chain 43 of centre one at 4 back of electromagnetism template, and two chains at 4 both ends of electromagnetism template are positioned at outer
In gap between the vertical top bracing plate| 31 in two pieces of side and adjacent vertical top bracing plate| 31.
Preferably, the chain 43 on the guide pulley 26 corresponding to electromagnetism template 4 is provided with annular groove and (does not show in figure
Out).
Support frame as described above 2 includes a connecting cross beam 21 in the front lower portion connection of the preceding arm mechanism 1, connecting cross beam
21 are connect by being fixed on the rotary hinged seating 211 of its top center with preceding arm mechanism 1, any side of the connecting cross beam 21
With preceding 1 front end of arm mechanism is ipsilateral is connected with lateral rotary oil cylinder 212, lateral rotary oil cylinder 212 can be used to adjust the side of support frame 2
To angle;Support frame as described above 2 further includes two longitudinal girders 22 being parallel to each other, and the rear end of two longitudinal girders 22 with it is described
Two end sides of connecting cross beam 21 are connected by shaft 213;The front top of the longitudinal girder 22 of two of support frame as described above 2 is also respectively set
It is equipped with the support vertical beam 23 being parallel to each other, the both ends of the support beam 33 are directly anchored on support vertical beam 23, described
The both ends of guiding crossbeam 34 are separately fixed on the front supported beam 231 for being welded in support 23 front end face of vertical beam;In longitudinal 22 He of girder
It is connected between support vertical beam 23 and reinforces inclined strut beam 221.
It is additionally provided with a driving roller 24 between the front end of the longitudinal girder 22 of two of support frame as described above 2, drives roller
24 can rotate forward or backwards under the action of drive motor 241.Driving roller 24 can be used for storing curtain when rotating in the forward direction
Electromagnetism template 4, when reverse rotation, can be used for discharging the electromagnetism template 4 of curtain.
Perpendicular to two longitudinal girders 22, and it is located at the support vertical beam 23 and is respectively arranged with two courts that are parallel to each other later
On secondary support vertical beam 25, be provided with a guide pulley 26, the orienting roll between the tops of two secondary support vertical beams 25
The two sides of cylinder 26 are fixed with two pieces of annular baffles 261, the orientation of the electromagnetism template 4 for correcting curtain, avoid becoming in its traveling
It obtains crooked.
Two front and back rotary oil cylinders 27 are also connected between the connecting cross beam 21 and secondary support vertical beam 25, for adjusting branch
The pitch angle of support 2, to be adapted to the laying of the electromagnetism template 4 at different height steel arch-shelf.Specifically, close to connecting cross beam
21 liang of lower end surfaces are provided with two downward under support beams 214, and the middle part of two secondary support vertical beams 25 is provided with opposite two inwardly
The collateral beam 251 of root, and the both ends of the front and back rotary oil cylinder 27 are connected under support beam 214 and collateral beam 251.
The upper end of the preceding arm mechanism 1 is equipped with head cartridge 6, and the spray head 5 is mounted on head cartridge 6, and is sprayed
First 5 can slide back and forth and horizontally slip automatically, can also adjust automatically pitch rotation angle and rotate left and right angle, specifically
, the top of the preceding arm mechanism 1 is provided with longitudinal slide rail 11, and head cartridge 6 passes through longitudinal slide 61 and is fixed on the longitudinal direction
On sliding rail 11.
The head cartridge 6 also includes horizontal slide rail 62 and longitudinally disposed nozzle arm 63, and the nozzle arm 63 passes through
Cross slide 631 is fixed in horizontal slide rail, and spray head 5 passes through the rotatable front end for being fixed on nozzle arm 63 of spray head supporting plate 51.
It is provided with spray head rotary oil cylinder 53 on the specific nozzle arm 63, is provided in the shaft of spray head rotary oil cylinder 53
Spray head supporting plate 51, the spray head 5 are hinged on spray head supporting plate 51, are also connected with spray head between the spray head supporting plate 51 and spray head 5
The cylinder body of pitching oil cylinder 52, the spray head pitching oil cylinder 52 is hinged on spray head supporting plate 51, and piston rod joins after spray head 5
Portion, to realize that the pitch angle to spray head 5 adjusts, 53 overall control spray head 5 of the spray head rotary oil cylinder rotation, to adjust spray head
5 penetrating angle/direction relative to die cavity.
Fig. 9 be mould spray booth vehicle specific structure, including trolley vehicle frame I, sliding rack II, sliding trolley III, large arm turntable IV,
Turn round large arm V, pumping mechanism VI.The preceding arm mechanism 1 is rotatably mounted to revolution large arm V by forearm attachment base 12
Front end, under the drive of revolution large arm V, by the effect of preceding arm mechanism 1, spray head 5 can be synchronous with electromagnetism template 4
It is mobile.
The tail end of the revolution large arm V is mounted on large arm turntable IV, and large arm turntable IV includes vertical rotary components, energy
Drive the front and back rotation in perpendicular of revolution large arm V;The large arm turntable IV further includes rotating horizontally component, can be driven
Large arm V is turned round to rotate horizontally.
The vertical rotary components of large arm turntable IV are gear rotary components, can drive revolution large arm V in perpendicular
Rotational angle can be more than 240 degree.Compared with the large arm of traditional engineering truck is supported by hydraulic cylinder and provides rotary power,
Traditional large arm can only achieve 60 degree or so in unilateral rotation angle, is unable to satisfy this mould spray booth vehicle at all and needs in tunnel
The mould that each section carries out full angle sprays demand.
It is longitudinally provided with sliding rack II along car body on the trolley vehicle frame I, sliding trolley III, institute are installed in sliding rack II
Large arm turntable IV is stated to be rotatably mounted on sliding trolley III;Sliding trolley III carries large arm turntable IV can be along sliding rack II
Longitudinal sliding motion.
The sliding trolley III in sliding rack II can the distance of straight skidding be greater than distance between adjacent two rows of steel arch-shelfs
III-IV times.Specifically, the length of sliding rack II can be equal to the width of three Pin steel arch-shelfs, namely be equal to adjacent four steel arches
(for engineering reality, the distance between adjacent two steel arch-shelfs are generally 1 to the distance between two steel arch-shelfs in outside of frame
Rice, then the length of sliding rack II is just 3 meters), it can guarantee moving distance of the sliding trolley III in sliding rack II so at least
It can reach the distance between two steel arch-shelfs in outside of adjacent three steel arch-shelfs.The width of this main needle electromagnetism template 4 can only be horizontal
It is wet can to meet continuous three Pin in the case where not moving vehicle in this way in conventional constructing tunnel to adjacent two steel arch-shelfs of covering
The mould of jet mould plate sprays work, avoids and frequently moves vehicle, influences the progress of construction.And it is directed to wider wet shot template, such as applicant
The three Pin wet shot templates invented can cover adjacent continuous four rows steel arch-shelf and be formed by three transverse mode controls, such to set
Meter is not just very necessary.Certainly, the length of sliding rack II does not limit the width equal to three Pin steel arch-shelfs, theoretically can be with platform
The length of vehicle carriage I is processed longer, is realized that single moves vehicle, can be sprayed the purpose for pouring broader tunnel face.The mould spray booth vehicle
It further include pumping mechanism VI, it can be from 5 delivering concrete wet shot material of trend spray head.
The workflow of above-mentioned mould spray apparatus are as follows: during construction, arm mechanism and electromagnetism template, template before adjusting
Frame etc. is shored, is adsorbed onto electromagnetism template on steel arch-shelf, forms the die cavity of height about one meter (height that template shores frame) left and right,
The angle for adjusting spray head starts to gunite concrete inside die cavity, and during injection, concrete is cumulative, forearm machine
Structure starts to move along steel arch-shelf, while preceding arm mechanism is mobile, drive motor rotation, while discharging the electromagnet mode on reel
Plate, by compressed oil cylinder, top bracing plate|, the devices such as spring-compensating are pressed to electromagnetism template on steel arch-shelf, while electromagnetism template obtains
Electricity is adsorbed on steel arch-shelf, forms new die cavity again.In the way of this movement, continuous moving support frame discharges template,
New die cavity is gradually formed, the continuous gunite concrete of spray head continuously carries out mould and sprays supporting, when reaching vault, stops
Gunite concrete, concrete to be sprayed is all after solidification, and electromagnet is by vault to lower end power loss, while drive motor one by one
It reversely rotates, cantilever crane, which synchronizes, to be moved down, and the recycling to electromagnet template is completed, and is realized without rebound, non-dusting continuous preliminary bracing.
Method is sprayed using the mould of electromagnetism template, described method includes following steps:
S1: mould spray booth garage enters the tunnel construction sections to be painted poured, and revolution large arm is opened in firing platform car exhibition, and revolution large arm takes support
Frame and curtain electromagnetism template excavation face wherein side close to the bottom of two adjacent steel arch-shelfs;
S2: electromagnetism template is located to one section before support frame and is close to two or more steel arch-shelfs, and and steel arch-shelf from bottom
Form die cavity to be poured;
S3: adjustment nozzle position and angle opens spray head and Open Side Down at the top of transverse mode control sprays into rapid hardening coagulation
Soil completes pouring for first section concrete;
S4: after section concrete solidification at the beginning of mold cavity bottoms, being affixed on of extending upwards of the modular unit of electromagnetism template is described
On steel arch-shelf, new die cavity is formed, when electromagnetism template extends, spray head is lasting to the modular unit and steel arch-shelf that newly release
Fast hardening concrete is sprayed into the die cavity newly formed, is poured with completing the preliminary bracing of this section unilateral excavation face.
It further include step S5, after top concrete solidification, revolution large arm is gradually moved down with support frame and electromagnetism template,
It drives roller to reversely rotate simultaneously, recycles curtain electromagnetism template;It turns round large arm to rotate horizontally with support frame and electromagnetism template, make
The other side of the electromagnetism template towards tunnel with section time is obtained, and repeats step S1-S4, completes the preliminary bracing of this section of tunnel other side
It pours.
In step S1 and S2, driving roller rotates in the forward direction under the action of drive motor, discharges curtain electromagnetism template, makes
The free end for obtaining electromagnetism template hangs down into its bottom and flushes with the bottom that template shores frame, adjusts the left-right position of support frame, with
Guarantee that the electromagnetism template of curtain can laterally cover the steel arch-shelf;Then the electromagnetism template being located at before support frame that will be released
Outer surface is tightly attached on steel arch-shelf, and guarantees that the bottom edge of electromagnetism template is contacted with tunnel excavation bottom surface, so that electromagnetism template, steel arch
Frame and tunnel bottom surface are enclosed with open-topped transverse mode control;
In step s 2: the power circuit of modular unit electromagnet is successively connected from the bottom up, so that contacting with steel arch-shelf
Modular unit magnetic absorption on steel arch-shelf;The pitch angle for adjusting support frame simultaneously, so that the outer surface of electromagnetism template is most
Limits are agreed with the radian of steel arch-shelf, and adjust revolution large arm template is made to shore frame and withstand electromagnetism template and steel arch-shelf
It is bonded section;
In step s 4, after section concrete solidification at the beginning of mold cavity bottoms, revolution large arm drives support frame gradually along steel arch-shelf
It moves up, while being again started up driving roller and continuously rotating in the forward direction, continuously to discharge the template list of curtain electromagnetism template
Member.
In step s 4, the rate of release with support frame of electromagnetism template move up that speed is equal, and guarantee newly to release
When modular unit and steel arch-shelf contact, institute's band electromagnet is powered immediately to be adsorbed on steel arch-shelf.
During support frame is moved up along steel arch-shelf, template is shored the idler wheel of shoring on frame and is rolled at the back of electromagnetism template
It crosses, while during scrolling, direct support is formed to electromagnetism template.
In the release of electromagnetism template and removal process, the central links in electromagnet mode backboard portion are from upper guide roller and lower steering roll
Annular groove in slip over;The chain of two sides is located at that unit is shored in centre and side is shored and slided between unit.
It is overlapped with the preliminary bracing concrete layer poured at left and right sides of section time tunnel in tunnel top, and in lap-joint
After tamping with template support, strike off, complete the supporting of described section time of tunnel contour.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.